You are on page 1of 10

Scholarly Paper

Dispute Manifestation and Relationship Quality in Practice


Mostafa Babaeian Jelodar 1; Tak Wing Yiu, M.ASCE 2; and Suzanne Wilkinson 3

Abstract: There is a need to investigate the causes and sources of conflict and dispute in association with construction working relationships.
How relationship quality may be affected by these causes and sources, and subsequently dispute is triggered, is still unexplored or at least
unclassified. The research reported in this paper uses a three-stage approach to identify the sources of dispute and then explore the variation of
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

relationship quality during a dispute event. A comprehensive literature search and then a review of litigation cases in New Zealand during the
past 5 years were performed. Finally interviews with dispute resolution and construction experts are conducted. It is observed that three
sources of (1) project uncertainties, (2) contract and processes, and (3) people and behavior are the common causes of conflict and dispute.
However dispute triggers are different from the causes which created the conflict at the beginning. It is also acknowledged that three factors of
(1) contract provision, (2) evidence, and (3) reasoning are required for successful claim handling and dispute prevention. Based on the ability
to use these factors in dispute handling, relationship quality can be preserved or deteriorated. DOI: 10.1061/(ASCE)LA.1943-4170.0000171.
© 2015 American Society of Civil Engineers.

Introduction replacement of systems, the ultimate disposition of waste, building


systems, and the building structure (Blismas et al. 2005; Jelodar
In any working arrangement a relationship is formed; in construc- et al. 2013a). However by sustainable relationships the industry
tion a working relationship is formed by signing a contract, there- tries to maintain connection between parties, allowing for better
fore the parties are officially bound to work with each other. Just awareness and efficient flow of information. The fact that a party
like any other working arrangements a certain amount of conflict is in a sustainable relationship with the other party indicates that
exists in these in construction working relationships. Accordingly there is more collaboration, trust, and commitment which could
conflict and dispute are collectively inevitable and destructive if not be extremely valuable to the outcome of the project at hand or fu-
controlled in construction working relationships (Cheung and Yiu ture projects to come. The preservation of existing relationships if
2006). Despite other existing matters disagreements, conflict and performed appropriately will produce value in terms of quality,
dispute has been regarded as major influential issues affecting time, and even cost implications of projects (Ling et al. 2014).
the professional and personal relationships within construction Conflict and dispute in construction have been investigated because
projects. The fragmented and adversarial environment plagued with of their negative effect on costs and productivity. In addition con-
conflict and dispute is a warning sign to industry. The whole cau- flict and dispute events need to be seen and examined in a relation-
sality and handling process of conflict and dispute constantly may ship management context and their effects on relationship quality
affect the relationship quality among the parties involved (Jelodar of construction working arrangements.
2012). On the other hand the industry is aware of the value offered
by functional and good-quality working relationships, and is
therefore pushing for further advancement in relational practices Engagement of Common Sources of Conflict and
(Kumaraswamy et al. 2005; Yeung et al. 2009). In simplistic terms Dispute in Construction Relations
the industry is moving towards retainable and sustainable relation-
ships. As a result understanding how conflict and dispute influen- Conflicts are differences in interests, perception method, and values
ces contractual and working relationships becomes essential. which are quite common in human activities. Conflicts are seen to
Sustainability in the built environment by and large incorporates be inevitable and a certain level of it exists in almost all relation-
practices such as extraction of materials, manufacturing of ships (Rhys 1994). However, conflict can escalate into adversarial
products, assembly of products into buildings, maintenance and events which could have disastrous consequences; ultimately if
they are not managed properly they will result into disputes.
1
Teaching and Research Fellow, Dept. of Civil and Environmental The Institution of Civil Engineers arbitration procedure defines
Engineering, Faculty of Engineering, Univ. of Auckland, Private Bag dispute as where a claim or assertion made by one party is rejected
92019, Auckland 1142, New Zealand (corresponding author). E-mail:
by the other party and that rejection is not accepted (Brown and
mjel010@aucklanduni.ac.nz
2
Senior Lecturer, Dept. of Civil and Environmental Engineering, Marriott 1993; Kumaraswamy 1998); dispute is a state which con-
Faculty of Engineering, Univ. of Auckland, Private Bag 92019, Auckland flict escalates and its resolution is often sought through a third-
1142, New Zealand. E-mail: k.yiu@auckland.ac.nz party involvement. Therefore certain events which will lead to con-
3
Professor, Dept. of Civil and Environmental Engineering, Univ. of flict escalation and dispute could be regarded as dispute triggers. In
Auckland, Private Bag 92019, Auckland 1142, New Zealand. E-mail: s any relationship problems generally evolve through a chain of
.wilkinson@auckland.ac.nz events from minor differences to conflicts and ultimately huge
Note. This manuscript was submitted on October 16, 2014; approved on
full-scale disputes. The processes of conflict management and dis-
March 4, 2015; published online on May 29, 2015. Discussion period open
until October 29, 2015; separate discussions must be submitted for indivi-
pute resolution are a combination of formal and informal ap-
dual papers. This paper is part of the Journal of Legal Affairs and Dispute proaches, some of which are anticipated and foreseen in
Resolution in Engineering and Construction, © ASCE, ISSN 1943-4162/ contractual procedures and some are not. Thus manifested conflict
C4515003(10)/$25.00. and dispute may originate from the same common sources and are

© ASCE C4515003-1 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


the outward behavior exhibited by individuals which is perceived to obstacle to sustainability of construction relationship quality.
affect the relationship quality between the parties involved. Construction relationship quality is defined by the concepts of trust,
By nature these sources can lead to functional or dysfunctional satisfaction, performance, commitment, and communication.
conflict, therefore managing conflict in both forms is of extreme Seemingly the emergence of conflict and dispute may have direct
importance and can support the development of sustainable effects on the outcome of projects for instance performance. In
long-term relationships (Toms 2004). In construction claims are addition attributes which may go beyond the project lifecycle such
not often considered to be just negative events; some of them as trust, satisfaction, and also commitment of the parties involved
are even thought to be necessary for better evolution of design may also be affected. Ultimately the attributes will define and
and construction processes. Accordingly shifting conflict to con- record the changes of relationship quality between construction
ceptual design and early phases of the construction is thought to participants (Cheung et al. 2006; Jelodar et al. 2012; Love et al.
be beneficial which can contribute to a better well-structured design 2011; Cheung and Yiu 2006).
and conceptualization of work procedures (Kumaraswamy 1997b). There are different approaches and perspectives for investigat-
This suggests that the timing associated with conflict and the ing conflict and dispute in construction; these approaches concern a
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

manifestation of conflict triggers is also extremely important to variety of factors ranging from commencement and trigger events
the relationship outcome. Bristow and Vasilopoulos (1995) stated to outcomes, handling, management, and conceptual organization
ignoring or delaying the resolution of conflicts can have serious styles (Cheung et al. 2006; Mallen 1963; Toms 2004). Although the
implications and lead to dispute triggers. It is believed that disputes handling and management of conflict and dispute is highly
ultimately have dire consequences on the relationship quality of the important and extremely influential to the outcome of sustaining
parties involved (Cheung and Yiu 2006). This irrationality and high relationships, they should only be investigated in full cognition
emotional state between the parties may negatively influence their of conflict and dispute events, their nature and most importantly
working relationships (Harmon 2003). In line with the current per- sources. One of the early steps in this path may be the identification
ception, Cheung et al. (2004) state that if a dispute is not resolved and classifications of simple causes which can directly or indirectly
promptly, then it may escalate, and ultimately require litigation pro- provoke conflict or dispute and influence the relationship quality.
ceedings, which can be extremely costly for the parties concerned Many studies have been undertaken to identify causes of conflict
(Love et al. 2011). On the other hand good handling of conflicts and dispute; very few studies have actually tried to provide a
can change the outcomes in terms of relationship implications. dominant classifications of causes which may influence the
This conceptualization can portray simple implications of conflict relationships in construction projects.
and dispute events on construction relationships, demonstrating The conflict and dispute resolution processes as part of overall
dependency of relationship on the timing, nature, and handling problem solving strategy will also impact the relationship quality.
of conflict and dispute events. Handling and management of Methods such as litigation being the most hostile and formal
conflict and dispute events involve a wide spectrum of actions method of dispute resolution will most probably result in relation-
and measures ranging from simple direct negotiations to mediation, ship decline (Fulbright and Jaworski 2006; Mitkus and Mitkus
arbitration, litigation, and so on; all of these approaches have 2014). However litigation is always the last resort and if other
certain and distinct effects on the outcomes of the projects and methods are not effective (Ministry of Justice New Zealand
the ongoing and future relationship of the parties involved. 2014). This implies that studying litigation and court cases can
be invaluable to understanding the nature of construction relation-
ships. The court proceedings and decisions will also provide a his-
Need to Explore Relationship Quality in a Conflict tory of the problem which is useful for the purpose of the research
and Dispute Manifestation reported in this paper and perhaps provides an evaluation of how
relationships evolved during the conflict and dispute process. The
Relationship quality to some extent has been conceptualized and research reported in this paper intends to investigate the sources of
classified by Jelodar and Yiu (2012); they have argued that relation- dispute through the classification of common causes of conflict and
ship quality can be introduced as a systematic high-order construct dispute imbedded in litigation cases. The sources were extensively
to construction projects in order to provide an assessment ground studied to determine their interaction with the relationship quality
for the status of relationships in construction activities (Jelodar of the parties involved.
et al. 2015). For this purpose a framework was suggested that
defined the notion relationship quality. Based on literature, conflict
and dispute can be systematically related to relationships in Methodology
addition their causes and management style can be determinants
of relationship quality in a systematic outlook (Jelodar et al. A three-stage approach was designed to achieve the objectives of
2013b). This basically implies that conflict and dispute will cause the research reported in this paper. Data was collected as part of a
relationship deterioration and poor-quality relationships could be a larger study with the theme of construction relationship quality. The
source of further potential dispute. Therefore in a systematic frame- approach primarily was based on pinpointing the theoretical
work dispute and relationship quality could be regarded as cyclic foundations for the systematic engagement of causes and sources
events which can trigger one another (Jelodar 2012). of conflict and dispute. Second, the actual practices implemented
However the focus of the research reported in this paper is what are observed to provide an assessment of relationship quality
effects relationship quality and most of the reasons for relationship during dispute events. The three-stage approach will provide a
deterioration are seen within the causes of conflict and dispute chance for methodological triangulation since data is collected
evolving through a consequent turn of events which influence by more than one method (Eriksson et al. 2009). Each of the three
relationship quality. Based on this idea a monitoring tool was methodology stages is outlined, as follows:
suggested that entails a timeline of simple causes that trigger 1. Literature review: In Stage 1 relevant articles and research
conflict and dispute in construction (Jelodar and Yiu 2012). It is work with the theme of conflict and dispute are identified.
vital to understand the nature of these causes which can negatively Accordingly a pool of possible causes and classification
influence the quality of relationships and ultimately serve as an strategies are driven. Ultimately the general classifications

© ASCE C4515003-2 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


are compounded into one final classification. The final 2005; Tilley and McFallan 2000), and late authority approvals
classification demonstrates the causes of conflict and dispute (Waldron 2006) are the most significant contributing factors. The
based on its sources. result of these overruns and their corresponding causes are conflicts
2. Review of court cases: Publically available court proceedings and disputes which are the origin of schedule disruption, increase
and decisions are acquired. With a preliminary review a tech- in project costs, and also relationship deterioration or failure
nique to extract appropriate data is created. Accordingly infor- (Cheung and Yiu 2006).
mation such as the potential causes, number of causes, claim The factors of uncertainty, contractual problems, and opportun-
nature, entitlement, and dispute triggers are extracted based on istic behavior identified by Mitropoulos and Howell (2001) are
court decisions. The results are classified and disseminated via similar to those recognized by Diekmann and Nelson (1985) which
graphs and amalgamated with Stage 1 to determine the sources consider project, processes, and people related issues as the main
of construction dispute. Stage 2 allows for hard evidence to be sources of conflict and ultimately dispute. Additionally Yousefi
elicited and incorporated in the research reported in this paper. (2009) has classified the dispute causes into contractual causes,
3. Expert interviews: At Stage 3, two-phase interviews are organizational causes, and technical causes, but Mitropoulos and
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

conducted to gain insight on how sources of disputes will Howell (2001) and Diekmann and Nelson (1985) suggested a broad
affect relationship quality in construction practice, as follows: classification of conflict and dispute causes which is perhaps more
(1) conflict management and dispute resolution experts are comprehensive; thus most of the significant causes and sources will
interviewed to provide a foundation of information and fall within the range of three classes according to the available
practices, and (2) actual construction experts are interviewed literature. Love et al. (2011) also stated that “ : : : scope changes that
to provide their experience on the issue. Ultimately through arise from the innate uncertainty that exists within the project
content analysis a simple framework is developed and management system (e.g., scope changes, design errors, site con-
demonstrated for practical interaction of dispute source with ditions), poor contract documentation that arise from the organiza-
relationship quality. Expert opinion is gathered and classified tional system (e.g., inadequate/incomplete design information,
to solicit the phenomenon in question and explain how ambiguities in contract documents), and behavioral adaptations
relationships are affected by dispute events. of individuals within the people system (e.g., poor communication,
poor management, skill and experience, and personality traits)
are key causal factors contributing to dispute.” The previously
Literature Review mentioned classes are elaborated as described next.
It is very important to identify and explore the nature of the Project uncertainty is the general cause of change beyond the
common causes and triggers of conflict and dispute, especial since expectation of the parties involved in construction projects [Con-
the full awareness and realization of a conflict incident may be struction Industry Institute (CII) 1995; Diekmann and Nelson
achieved in later stages of the project where a lot of recourses 1985] Williamson (1979) also has regarded uncertainty as one
and money has been spent. However the causes which correspond of the main contributing factors to contractual problems and dis-
to the incident are associated to the early stages of the project putes. Yates (1998) considered inclement weather conditions and
(Gardiner and Simmons 1998). Detection and categorizing the Waldron (2006) viewed site conditions and availability of resources
causes will also enable the identification of avoidable causes of associated with different levels of uncertainty and possible causes
claims moreover assisting the mitigation of dispute; reducing the of disputes.
damage, time, and cost needed for correction (Kumaraswamy Contract and process, which includes imperfect contracts and
1997b). The causes of conflict and dispute have been assessed unrealistic performance expectations, could also encompass design
by a number of researchers each giving different classifications; errors which can lead to complexity ambiguities and malfunctions
however a close look at their classification will bring patterns of in documentations and processes. Due to extensive, elongated, and
similarities and shared concepts to light. A lot of studies have con- complex documentation of construction contracts, disagreements
sidered disputes as the consequence of unresolved conflicts and or dispute seems highly probable regarding contracting obligations
claims, therefore these research works have suggested that the con- and expectations. In addition when a contracting party’s perception
flicts, claims, and disputes arise from common sources (Diekmann is that the other party is not meeting contractual obligations or
and Nelson 1985; Heath et al. 1994; Hewitt 1991; Kumaraswamy expectations they will claim for their losses in terms of time and
1997a; Semple et al. 1994; Watts and Scrivener 1993). cost which may also trigger disputes (Semple et al. 1994). Yates
Diekmann and Nelson (1985) believe that the cause of contract (1998) pinpointed that the main types of construction dispute arise
claims is design error or change-related. Design related issues lead from the contract documents. Totterdill (1991) perceives that
to incomplete contract documentation and changes are associated technical, legal, and managerial dispute issues must have a contrac-
with uncertainties. They also mentioned differing site conditions, tual reference. It is believed that bounded rationality or contract
weather, and strikes as other sources which are all characterized as incompleteness will assist opportunistic behavior which can
project uncertainties. In the work performed by Hewitt (1991) and develop into dispute (Williamson 1975).
Watts and Scrivener (1993), variations, change of scope, negligence People and behavior issues generally due to poor communi-
in tort, and delays (including damages, disruption, acceleration, and cation, poor interpersonal skills, opportunistic behavior, and
termination) where considered as the main causes of claims, while cognitive dissonance. Bristow and Vasilopoulos (1995) and Sykes
issues such as payment and time extensions have been also (1996) have also stressed concerned over personality issues and
regarded as claim types and dispute sources. Nevertheless these advised that disputes are due to unrealistic expectations, lack of
are thought to be secondary to the main and initial causes of claims team spirit, and misunderstandings.
which are variations and unexpected problems or design and pro- Other management literature and theories also strengthen the
cess matters (Conlin et al. 1996; Heath et al. 1994; Semple et al. same perception; a close look at Williamson (1979) framework
1994). Different individual studies into the reasons of time and cost of market failure about the combination of so-called environmental
overruns in Australian construction projects has revealed that re- and behavioral factors and their association with contractual prob-
work (Love 2002), variations (Chan and Yeong 1995; Waldron lems was elaborated and applied in construction by (Mitropoulos
2006), incorrect design and incomplete documentation (Love et al. and Howell 2001). The visualization and connection of such frame-

© ASCE C4515003-3 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


work with construction is relatively straightforward. Construction
projects are normally associated with high levels of uncertainty and
complexity which makes it almost impossible to foresee every con-
tingency (bounded rationality). Consequently problems that are not
clearly conditioned in the contract may ascend (contractual prob-
lems). After a construction project begins, the ability to change to
other contractual parties is very limited and highly unlikely (small
numbers) this limitation and inability to change the contracting
party’s may trigger opportunistic behaviors from one party taking
advantage of the other party’s limitations. Therefore it can be said
that the combination of project uncertainty, contractual problems,
and opportunistic behavior can cause problems and disputes in con-
struction projects and activities (Mitropoulos and Howell 2001).
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

Review of Court Cases


The primary source of data for this stage of the research reported in
this paper was extracted from the publically available information Fig. 2. Potential causes extracted from the court cases
and court decisions accessible at Building (2014) and also dispute
tribunal of Ministry (2014). Under the Official Information Act
1982 and based on a formal request to the Ministry of Justice, has a basis (causes and effects), contractual and legal foundation
New Zealand, information relating to the construction dispute cases for payment (entitlement), and quantified damages (Semple et
in the high court was obtained. A total of 123 construction court al. 1994).
cases were identified through the period of 2009–2014; after an Most claims had multiple causes of dispute and only 30% of the
initial investigation 22 of the court decisions were removed due total cases had only one potential cause for dispute. This indicates
to insufficient information. Consequently 101 court decisions were that conflict and dispute in construction activities are generally
acceptable for the research reported in this paper. Litigation cases complex events in nature with multiple causes which can influence
were chosen because (1) official documentation of these cases the situation through direct and systematic interactions. Fig. 2
exists which are publically available, and (2) some serious causes shows the frequency of cases with different number of potential
of dispute which can have adverse effects on relationship quality causes.
can be identified. All the decisions were based on formal claims The disputants were also extracted through the available public
with different sources and causes, thus a framework is established records. Fig. 3 demonstrates classification of the disputants based
to explore the necessary information based on the claim and the on the claimant which files the claim and takes matters to court. In
court judgment process. This data extracting framework basically light of these 33 clients were the claimants taking the contractor to
involves the following steps: court and 28 contractors were the claimant taking the client to
• Information such as claim amount, dates, and parties in dispute court. This indicates that a little over 60% of the cases were
are recorded as demographic information; between contractors and clients; the actions were directly taken
• An order of events and timeline for each case and judgment by the parties or their representatives. Construction disputes are
process is established (Fig. 1); dominated by contractor–client issues were traditionally the
• Triggering event, potential causes, and also sources of dispute perception is that one party’s gain is the other party’s loss. There
are documented; are significant numbers of disputes which either involve subcon-
• Detail on the potential causes are obtained through analysis of tractors or suppliers. A total of 13 cases were between contractors
the judges’ opinions; and and subcontractors; five cases involved contractor and supplier, one
• Information is categorized and documented according to the
timeline of the case.
Fig. 1 demonstrates the timeline order used in the research
reported in this paper. The causes and reasons which lead to the
need for a claim can be called entitlement issues (Diekmann
and Nelson 1985). Thus every claim category could be defined
an entitlement issues for resolved conflicts. A claim application

Fig. 1. Timeline of information extracted Fig. 3. Frequency of disputant parties extracted for the court cases

© ASCE C4515003-4 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


experience in completion of the processes. The claim is usually
about an incomplete or faulty process. Work delays, variations,
time limitation, scope issue, quality issues, payment delay and
problems, incomplete work, design errors, and damage can all
be process related causes, accounting for 30% of the common
causes. Cost dispute issues, contract misinterpretation, contract
documentation problem, and breach of contract are all directly
related to contract condition and account for a little over 24%
of the established causes. However processes their outcomes and
deliverables are usually cautioned and seen within the contract thus
the two sources of contract and processes are interwoven with
each other.
Site conditions, natural disaster, technical quibbles, and even
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

availability of sufficient cash flow and resource are all uncertainty


related causes. Therefore the project uncertainty source creates
around 9% of the disputes. The project-uncertainty-related causes
are the least causes of dispute in courts; this is maybe because
there are strong provisions or contingencies such as insurance
for unforeseen and uncertain events.
Some causes are due to human and peoples’ errors which can
directly influence project outcomes such as third-party involve-
ment, poor workmanship, negligence and carelessness, communi-
cation issues, and conflicting interests comprising more than 21%
of the total causes identified. Behavioral problems can also be
harmful especially to the working relationship and also indirectly
Fig. 4. Common conflict and dispute causes extracted via the data influence the project outcomes. Identified causes such opportunis-
mining framework tic behavior, poor working ethics, engineer prejudice, and culture
mount up to 15% of the total causes. Behavioral causes have also a
small share of the overall causality of dispute and this is perhaps
because these causes are not structured in the contract with
appropriate provisions. It is very difficult to legally conceptualize
case of client supplier, one case of client subcontractor, three cases behavior related issues and associate certain entitlements to
of supplier contractor, and one case of supplier client were them.
identified amounting to 24% of the total cases. The rest of the cases A combination of different causes will probably result in
involved the council, property owners, or creditors with around conflict or dispute incidents. In other words in a case of conflict
14% of the total number. Around 85% of the disputes in litigation and dispute it is hard to say just one factor has caused such a prob-
relate to major project participants such as clients, contractors, lem; it is most probable that dispute causes are interwoven and
subcontractors, and suppliers, and generally happen during project could not be isolated or controlled (Kumaraswamy 1997a).
execution and completion. This is a serious defect which influ- Mitropoulos and Howell (2001) also advocated that there was
ences working relationships and can influence the outcome of not one overriding factor as the critical cause of the dispute, but
projects. a combination of key factors. Fig. 5 shows the classification of
Fig. 4 shows all the identified potential causes in the 101 the most significant causes established based on the previous
conflict cases. Combination of these causes will provoke different literature section and confirmed by the second stage of methodol-
disputes in construction projects. After identifying the dispute case ogy which was an empirical investigation in construction dispute
the causes were extracted via the previously mentioned framework. court cases. Accordingly combination of these causes will probably
These causes are the common sources of the initial conflict and justify most conflict or dispute cases.
ultimately the dispute in process which was identified in the judge’s Although conflict and dispute may have common causes one
decision. As mentioned previously nearly 70% of the cases had has to make distinctions between triggers of a conflict and future
more than one source of conflict thus the total number of causes events which may trigger dispute. Fig. 6 classifies the triggering
identified in total was 206 causes within the possible 101 cases. The events of dispute which were extracted through the data mining
most popular causes were opportunistic behavior with the framework. These triggering events are the official legitimate jus-
frequency of 25, breach of contract with 24 and contract and tifications for why these dispute cases are pursued in litigation
documentation problem with 18 times occurrence. As discussed courts.
these causes can be the result of either the humanistic nature of Nearly half (47.5%) of the reasons that disputes were resolved in
conflicts or the fact that no contract is complete and perfect. Poor court are because no response was made to payment claim and can
workmanship, variation, work delay, communication issues, be interpreted as one party does not agree to the payment claim by
financial and cash flow issue, and payment delay and problems ac- the other. Outstanding balance was also responsible for around 23%
count for 58 causes which are a significant number. These causes of the disputes in litigation. Cost dispute and cost of repair respec-
generally relate to the process of work, people mistakes, and con- tively contribute around 10 and 7% to the total triggers of dispute.
tract condition. The identified 26 categories of causes (Fig. 4) can The rest of the triggers to these litigation cases were defective
be all simplified and classified into broader sources for conflict and construction, damage, workload more than anticipated, unclear
dispute. documents, cost revaluation, and damages due to payment delay
Some of the causes are process-related implying that these and contract termination. They could cause conflict but it cannot
causes are because of incomplete processes or the lack of be implied that the same causes will trigger disputes; claims which

© ASCE C4515003-5 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


Projject Contract and People and
Uncertaainties1 Processees
2 Behaviour3

D elays in payments Op portunistic and


E
Environmenttal issues and d Time constrraints
weather adver sarial behaviour
Delay s in work, possessions Poor co mmunication and
Siite condition
ns; limitations; a nd site equipment
and access restrictions misu nderstandings
Desi gn errors, ammbiguities Experien ce with the type of
Technical pro oblems due to o a nd change orders
o
ccomplexity oof design and d wo rk performed
C ontract docu uments Lack of team spirit
constru
uction ambiguitiies
Availability of resources Inap propriate rissk sharing
Quality prob blems
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

2
((Construction Inndustry Institute, (Che ung et al., 2006; Conlin et 3
(Br istow et al., 1995;
1995; Diekman nn et al., 1995; al., 19 96; Constructiion Industry Construc tion Industry Institute,
Kumaraswamy,, 1997a, 1997b;; Institu te, 1995; Heath et al., 1994;
Mitropoulos et al., 2001; 1995; Kill ian, 2003; Mitropoulos
Hewit t et al., 1991; Killian, 2003;
Waldron, 20066; Williamson, Kum araswamy, 199 97a, 1997b; et al., 200 1; Sykes, 1996; Cheung
1979; Yattes, 1998) Totter dill, 1991; Waldron, 2006; and Yiu 2006
Watt s et al., 1993; Williamson,
1975; Cheung and Yiu 2006)

Fig. 5. Classification of conflict causes identified by different sources

end in disputes may have different characteristics to those that are in this paper. A total of 15 people agreed to participate in the inter-
resolved (Diekmann and Nelson 1985). views; however, only 11 interviews were conducted due to some
cancelations and schedule issues. Nevertheless theoretical satura-
Expert Interviews tion was achieved via this number of interviews. The interviewees
were a mixture of arbitrators, mediators, and adjudicators which
After establishing the causes and triggers of conflict and dispute in also had experience in relationship management and negotiation
construction the next step is to identify how they affect relation- during conflict and dispute cases. A semistructured interview
ships among parties involved. Seldom has research been directed was designed to fit the purpose of the research reported in this paper
to study the implications of the classified causes from a contracting (Punch 2005). This entailed primary and fundamental questions
or working relationship perspective. The goal is to identify how and and the clarification questions. The interviews were electronically
based on what dimensions these causes will contribute to quality of recorded and transcribed, and accordingly content analysis was
contractual and working relationships. A series of qualitative inter-
performed. The main questions asked from the experts in the first
views were performed in two phases. If there is little empirical evi-
phase are as follows:
dence about a concept or phenomenon a qualitative approach
• Please provide a classification of different types of conflict or
would be the best way (Creswell 2009).
dispute which may arise in construction projects?
Primarily experienced construction dispute resolution experts
• What are the characteristics of more harmful conflicts for the
were identified thorough Arbitrators’ and Mediators’ Institute of
relationship quality of the parties involved?
New Zealand (AMINZ). Using the AMINZ database, a sample
• What is generally required for a conflict or dispute to be re-
of dispute resolution experts was drawn, who were then contacted
solved in a good spirit of respect and collaboration; ultimately
by e-mail and phone to seek their support for the research reported
preserving trust and satisfaction in the relationship?
In the next phase construction professionals were approached
and interviewed face-to-face which is considered as the most reli-
able method of data collection (Morris 2006). From the publically
available contacts and primary desk research and field investiga-
tions 20 highly experiences construction professional which were
generally senior managers, project managers, engineers, and quan-
tity surveyors were contacted and identified; 10 of them agreed to
take part in the research reported in this paper. The professional
were interviewed specifically based on their latest conflict or dis-
pute cases handled by them. Again a semistructured approach was
used. Questions asked from the construction professionals based on
their most recent conflict or dispute incident, as follows:
• Please provide a description of the conflict in process and your
handling methods or strategies.
• Are all the elements of evidence, reasoning, and contractual
provisions available for each claim or conflict situation?
• If these conditions are not satisfied how does the potential
Fig. 6. Frequency of dispute triggers
dispute affect progress and affect the relationships involved?

© ASCE C4515003-6 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


A platform of information is built in the first phase through in- Although the dispute resolution experts in the first phase of the
vestigating dispute resolution and contract management experts. interviews regarded contract provisions necessary for any claim en-
The second phase is to link construction professional’s perspective titlement, the construction professionals believe too many provi-
to the developed platforms and brings into light their perspective of sions, regulations, and formality could be problematic as well.
handling construction conflict as the actual and first hand parties In some cases due to too much complexity, high number and
involved. It is acknowledged by these professionals that conflicts ambiguity of contract clauses conflict and dispute will emerge
always exist but not all of them will manifest itself into dispute. (Semple et al. 1994). There is a belief that every provision for claim
Although the dispute cases have been investigated so far there is entitlement could be a potential trigger of dispute.
a need to perform this stage to grasp a more comprehensive picture Both groups of interviews believe that there is a good chance
of conflicts and disputes. that with sufficient evidence and appropriate reasoning the claim
could be successful and a greater dispute can be avoided. However,
contract and document ambiguities can make the interpretation
Findings of these provisions and clauses difficult; thus claims can trigger
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

future disputes. The understanding of the contract provisions by


There is a strong consensus among the dispute resolution experts the opposing parties involved may be different in lack of serious
interviewed in the first phase that when conflicts emerge to the sur- precontract audits or meetings to clear all the interpretational
face and claims are launched. It is the claim process that defines the inconsistencies of the contract.
fate of the conflict; this is also outlined by Kumaraswamy (1997b). Because the chain of conflicts, claims and disputes do not
This suggests that the existence of contract provisions were entitle- always arise from a single source; each claim must be analyzed
ments are clearly stated can be helpful in construction conflict. It is in terms of its causality and sources before any handling method
believed that “strong evidence and reasoning is required to justify or decision is applied. After generalizing the interviews it is ob-
the entitlement to that claim.” Basically all disputes must have served that in specific conflicts which the causes are not control-
some sort of contractual reference for recognition (Totterdill 1991). lable; for instance weather issues, accidents, market and financial
As discussed in the previous section conflict and dispute sources uncertainties, the responsibility, and liability factor are relative to
could be project, uncertainty, contract, processes, people, or behav- the nature of the cause. Therefore in addressing any claim or
ior-related. The practitioners believe that with respect to their sour- conflict due to these causes, normally a distinction between what
ces there are different ways of handling these conflicts. However all was controllable and what was uncontrollable is made. This means
agreed that negotiation would be the first step since there is a fear of there are elements and dimension of control which should be taken
more formal approaches. In dealing with any conflict contractual to account in conflict and dispute resolution. For instance in behav-
provisions are the essence but the general the consensus is that con- ior control is involved and is the result of conscious choices and
flicts should not be taken to a personal level because it can be actions. Parties believe that although in most of the people and
extremely harmful. Out of these sources people and behavioral- behavior-related issues liability may not be well structured in
related issues have more potential to escalate to a more personal the contract but these issues can be prevented and are controllable
level. In addition according to the conflict management experts by the people in charge. So if it occurs, conflict goes through a
conflict arising from people and behavior issues have a totally tough and personal stage, which makes the treatment of this
different repercussion and create a more controversial setting. kind of conflict difficult and the chances of further disputes are
These problems normally manifest because of opportunistic and imminent.
adversarial behavior, poor communication, misunderstandings,
lack of experience with the type of work performed, and lack of
team spirit are very difficult to be conceptualized and incorporated Relationship Quality in a Conflict and Dispute
into the contract provisions thus making the claim process Incidents: Analysis of Interviews
extremely difficult, frustrating, and adversarial. Behavioral issues
are extremely unstable, unpredictable, and also dispute-provoking, Claims if not handled appropriately may trigger adverse dispute
especially with less-reinforced contract provisions available. incidents which by all means can affect the relationship quality
Generally where conflicts arise from uncertainty such as of the parties. A step before applying certain management tactic
environmental issues, weather, site conditions, technical problems or strategy would probably be to identify the actual sources of con-
due design complexity, and availability of resources then with flict and the following claim made. This key information is required
appropriate evidence and reasoning a case can be negotiated and for analyzing the claim entitlement via reasoning and evidence, ac-
perhaps with the available contract provisions a suitable claim complished by some sort of provision in the contract. As mentioned
can be launched. However, contracts normally will not cover every
previously claims can have different causes which originate in a
contingency of uncertainty which make it difficult for the plaintiff
singular or multiple source setting; as three combinational and gen-
to launch the claim. Uncertainty-related issues if not included in the
eral sources for conflicts, claims and disputes has been identified
contract are normally dealt by the measure of mutual understanding
between the parties involved in construction. And claims are (Fig. 5). The claim maybe a mixture of these sources and it is im-
accepted through insurance and other compensation policies. portant to understand where each claim will stand in terms of its
For conflicts sourcing from contract and processes which may causes, formation, and source structure. It can be hypothesized that
include issues such as delays in payments, time constraints, delays each claim initially has proportions of all the three general source
in work, design errors, ambiguities, change orders, contract domains of (1) project uncertainties, (2) contract and processes, and
documents obscurities, inappropriate risk sharing, and quality prob- (3) people and behavior. In addition each two sources can be com-
lems normally some sort of contract provision exists, although pared successively and analyzed to provide a better understanding
every contingency may not be seen for. This is because contracts of the structure of each claim. For instance a manifested claim is
normally recognize the need for changes during the project. Hence tested to determine if it the cause of that it originates in the general
many clauses are included to acknowledge that certain changes are source groups of project uncertainties or contract and processes as
contract-related and process-related. illustrated in Fig. 7.

© ASCE C4515003-7 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


(a) (b) (a) (b)
Dominant cause: project Dominant cause: Both Dominant cause: project Dominant cause: Both
uncertainty related Contract provision availability: uncertainty related Contract provision availability:
Contract provision availability: highly likely Contract provision availability: unclear
highly likely Next step: Compare with highly likely Next step: Compare with
Next step: Compare with people and behaviour issues Next step: Compare with Contract and Processes
people and behaviour issues Contract and Processes There is chance of
opportunistic behaviour and
adverse relationship
(c) (d) implications
Dominant cause: Probably Dominant cause: Contract
people and behaviour related and Processes related (c) (d)
Contract provision availability: Contract provision availability: Dominant cause: Probably Dominant cause: people and
unclear highly likely Contract and Processes behaviour related
More likely to have adverse Next step: Compare with Contract provision availability:
related
effects on relationships people and behaviour issues Contract provision availability: unclear
highly likely Next step: Compare with
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

If a good case is built then Contract and Processes


Fig. 7. Analysis of claims based on project uncertainty against there is a chance of claim More likely to have adverse
contract-related and process-related sources acceptance and relationship effects on relationships
retention

Fig. 8. Analysis of claims based on project uncertainty against people


If the claim falls in the Fig. 7(a) section it indicates that the dom- and behavior issues
inant causes is project uncertainty = related and at the same time
contract and process-related issues have very little impact on the
formation of the claim. Subsequently a separate analysis between
a good case is built with proper evidence, reasoning and all-
project uncertainties related causes and people and behavior issues importantly sufficient contract provisions which for these sources
should be made. If a claim which has a weak root in the two sources
are most likely to be available; the claim is expected to be accepted
of project uncertainties and contract and processes [Fig. 7(c)] in good spirit. Since there is no opportunism or behavioral issues
occurs, the possible cause of claim could be people and behavior involved and all the provisions are clearly set and the contract is
issues. As mentioned previously, provisions for behavioral issues adequate then the impact on trust and performance satisfaction
are generally unlikely and ambiguous. Therefore the conflict may is minimized and the future relationship of the parties is retained
exist but conceptualizing and formulating a claim entitlement in an appropriate manner. If the sources of conflict fall within
becomes very difficult within the confined of construction Fig. 8(d), indicating the dominant cause to be people and behavior
contract. On the other hand the previously mentioned causes issues, the possibility of more adverse relationships seems to be
can be extremely problematic since they can escalate into a per- stronger. This is basically because contract provisions are unlikely
sonal realm. This may guide the conflicts into an elevated level to be sufficient for these causes and even if provisions are available
and possibly further infuriating dispute in addition when issues be- they are most probably very unclear in correspondence with behav-
come personal and provisions and guidelines are lacking interpre- ioral issues.
tations and justifications will be more biased. Self-interests will Similarly to comparing project uncertainty sources, the contract
dominate the relationships and a win–lose attitude befits the norm and processes-related sources can also be compared with the people
by all sides involved in the conflict; consequently trust and and behavior issues of conflict and dispute. Figs. 9(a and d)
satisfaction of the other party is lost commitment is weakened represent the dominant presence of contract and process relates
and normal communication and teamwork is disrupted. Under sources and people and behavior issues respectively. Fig. 9(b)
these circumstances working relationships will suffer and relation- specifies that both sources have a strong effect on the conflict and
ship quality will deteriorate, and if the conflict escalates into a more claim process. Since one of the sources is directly people and
formal dispute incident such as litigation then there is a potential for
total relationship breakage.
Project-uncertainty-related sources are also required to be as- (a) (b)
sessed against people and behavior-related issues in some stage, Dominant cause: Contract Dominant cause: Both
especially if project uncertainty has been identified as the key sour- and Processes related Contract provision availability:
Contract provision availability: unclear
ces of conflict and claim in the previous stage. Fig. 8(a) illustrates highly likely Next step: Compare with
this analysis; in this case the dominant source of conflict and claim Next step: Compare with project uncertainty
is project uncertainty. But Fig. 8(b) represents conflicts which stem project uncertainty There is chance of
from both of the project uncertainty and also people and behavior opportunistic behaviour and
adverse relationship
sources which make the situation more complex. There is a strong implications
chance that provisions exist for project uncertainty issues but on the
(c) (d)
other hand the presence of provisions for people and behavior Dominant cause: Probably Dominant cause: people and
issues seems to be unclear even if they exist in the first place. project uncertainty related behaviour related
If the contractual provisions for people and behavior issues are Contract provision availability: Contract provision availability:
weak then there is a chance of opportunism and opportunistic highly likely unclear
If a good case is built then Next step: Compare with
behavior to take advantage of the other causes of conflict and there is a chance of claim project uncertainty
dispute in this case project uncertainty, this can seriously lead to acceptance and relationship More likely to have adverse
relationship malfunction. Fig. 8(c) represents a situation where retention effects on relationships
none of the previously mentioned causes are the reason behind
Fig. 9. Analysis of claims based on contract and process against people
the conflict or claim; then there is a chance that contract and proc-
and behavior issues
esses related sources are the prime source. In these circumstances if

© ASCE C4515003-8 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


behavior-related, relationships could be fragile and at the verge of Bristow, D. J., and Vasilopoulos, R. (1995). “The new CCDC 2:
deterioration is opportunism is not curbed. Fig. 9(c) on the other hand Facilitating dispute resolution of construction projects.” Constr.
demonstrates the other source which is project uncertainty as the Law J., 11(2), 95–117.
most probable explanation for the conflict episode thus if evidence Brown, H. J., and Marriott, A. L. (1993). ADR principles and practice,
and reasoning are sufficient; in light of contract provisions there is a Sweet and Maxwell.
Building Dispute Tribunal. (2014). “Building Disputes Tribunal (NZ) Ltd
high chance of effective conflict resolution and relationship retention.
2014.” 〈http://www.buildingdisputestribunal.co.nz〉 (Apr. 7, 2015).
This is a simple methodology to perhaps predict which of the
Chan, A. P. C., and Yeong, C. M. (1995). “A comparison of strategies for
sources or situation have the most potential to stir up more conflict. reducing variations.” J. Constr. Manage. Econ., 13(6), 467–473.
Although simple root causes of conflicts, claims, and disputes are Cheung, S. O., and Yiu, T. W. (2006). “Are construction disputes inevitable?”
the primary cause of conflicts and claims they are not the ultimate Eng. Manage. IEEE Trans., 53(3), 456–470.
triggers of relationship deterioration; often what causes decline in Cheung, S.-O., Suen, H. C. H., Ng, S. T., and Leung, M. Y. (2004).
relationship quality is the mismanagement and mishandling of “Convergent views of neutrals and users about alternative dispute
conflict and claims when they emerge. resolution.” J. Manage. Eng., 10.1061/(ASCE)0742-597X(2004)20:3
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

(88), 88–96.
Cheung, S.-O., Yiu, T. W., and Yeung, S. F. (2006). “A study of styles
Conclusion and outcomes in construction dispute negotiation.” J. Constr. Eng.
Manage., 132(8), 805–814.
There are vast amounts of literature available on the causation of CII (Construction Industry Institute). (1995). “Disputes potential index
conflict and dispute; these causes have either been quoted individu- (SP23-3).” Construction Industry Institute, Austin, TX.
ally or categorized based on their logical relevance to one another. Conlin, J., Lanford, D. A., and Kennedy, P. (1996). “The sources, causes,
Although the research reported in this paper has developed three and effects of construction disputes: A research project.” Construction
Industry Board (CIB), London.
categories of (1) project uncertainty, (2) contract and process,
Creswell, J. W. (2009). Research design: Qualitative, quantitative, and
and (3) people and behavior issues for common sources of
mixed methods approaches, Sage, Thousand Oaks, CA.
conflicts, claims, and disputes, further empirical testing can be Diekmann, J. E., and Nelson, M. C. (1985). “Construction claims:
performed to identify and confirm these categories and furthermore Frequency and severity.” J. Constr. Eng. Manage., 10.1061/(ASCE)
identify the latent patterns behind these causes. 0733-9364(1985)111:1(74), 74–81.
Although these identified causes and sources may be the early Eriksson, P. E., Atkin, B., and Nilsson, T. (2009). “Overcoming barriers to
triggers to conflict and dispute, they are not the ultimate triggers partnering through cooperative procurement procedures.” Eng. Constr.
of adverse dispute resolution approaches such as litigation or arbi- Archit. Manage., 16(6), 598–611.
tration which can affect relationships in construction projects. What Fulbright, R. C., and Jaworski, L. L. P. (2006). “The third annual report of
can be regarded as the ultimate triggers of these drastic measures the litigation trends survey findings.”
are the opportunism and also the initial handling of the conflict or Gardiner, P. D., and Simmons, J. E. L. (1998). “Conflict in small- and
dispute situation that are normally conducted through alternative medium-sized projects: Case of partnering to the rescue.” J. Manage.
dispute resolution (ADR) methods. Consequently this incompe- Eng., 10.1061/(ASCE)0742-597X(1998)14:1(35), 35–40.
tency can be a trigger for dispute escalation and ultimately an Harmon, K. (2003). “Effectiveness of dispute review boards.” J. Constr. Eng.
Manage., 129(6), 674–679.
impediment to relationship retention and sustainability. On the
Heath, B., Hills, B., and Berry, M. (1994). “The origin of conflict within the
other hand contract provisions and contingencies plus evidence
construction process.” First Plenary Meeting of TG-15, International
and reasoning are all vital determinants of conflict and dispute Council for Building (CIB) Publication 171, Netherlands.
management; thus their implication, availability, or unavailability Hewitt, R. (1991). Winning contract disputes: Strategic planning for major
can either act as a mean of relationship retention or even as imped- litigation, Ernst and Young, London.
iments to sustainable relationships. Jelodar, M. B. (2012). “Systematic framework of conflict, dispute and rela-
As stressed previously the time of conflict manifestation and tionship quality in construction projects.” Proc., 37th Annual Conf. of the
identification is also the key to the outcome of conflicts. The earlier Australasian Universities Building Educators Association (AUBEA),
occurrence of conflict can make it easier for the parties to reach an Australasian Universities Building Educators Association (AUBEA),
agreement or settlement. Thus investigations and the identification Auckland, New Zealand.
of the time associated with the initial triggers to a conflict incident Jelodar, M. B., Jaafar, M. S., and Yi, T. W. (2013a). “In seek of sustain-
and also the time of conflict manifestation could ultimately be ability; constructability application and contract management in
useful in reducing the impediments to sustainable relationships Malaysian industrialized building systems.” J. Leg. Aff. Dispute Reso-
in construction projects. lut. Eng. Constr., 10.1061/(ASCE)LA.1943-4170.0000121, 196–204.
Jelodar, M. B., and Yiu, T. W. (2012). “Evaluation of relationship quality in
construction cases using a process model of conflict and disputes in
project management.” Proc., 8th Int. Project Management (IMP) Conf.,
Acknowledgments Tehran, Iran.
Jelodar, M. B., Yiu, T. W., and Wilkinson, S. (2013b). “Stirring sustainable
Ting Chang Chen and Cong Ding are thanked for their assistance procurement by conceptualizing relationship quality in construction.”
and effort in collecting the necessary legal cases for the research Proc., World Building Congress.
reported in this paper. Jelodar, M. B., Yiu, T. W., and Wilkinson, S. (2015). “Systematic repre-
sentation of relationship quality in conflict and dispute: For construction
projects.” Constr. Econ. Build., 15(1), 15.
References Kumaraswamy, M. M. (1997a). “Common categories and causes of
construction claims.” Constr. Law J., 13(1), 21–34.
Works Cited Kumaraswamy, M. M. (1997b). “Conflicts, claims and disputes in
construction.” Eng. Constr. Archit. Manage., 4(2), 95–111.
Blismas, N. G., Pendlebury, M., Gibb, A., and Pasquire, C. (2005). Kumaraswamy, M. M. (1998). “Tracing the roots of construction claims
“Constraints to the use of off-site production on construction projects.” and disputes.” Proc., Royal Institution of Chartered Surveyors (RICS)
Archit. Eng. Des. Manage., 1(3), 153–162. Construction and Building Research Conf., London.

© ASCE C4515003-9 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003


Kumaraswamy, M. M., Rahman, M. M., Ling, F. Y. Y., and Phng, S. T. Semple, C., Hartman, F. T., and Jergeas, G. (1994). “Construction claims
(2005). “Reconstructing cultures for relational contracting.” J. Constr. and disputes: Causes and cost/time overruns.” J. Constr. Eng. Manage.,
Eng. Manage., 10.1061/(ASCE)0733-9364(2005)131:10(1065), 10.1061/(ASCE)0733-9364(1994)120:4(785), 785–795.
1065–1075. Sykes, J. K. (1996). “Claims and disputes in construction: Suggestions for
Ling, F. Y. Y., Ong, S. Y., Ke, Y., Wang, S., and Zou, P. (2014). “Drivers and their timely resolution.” Constr. Law J., 12(1), 3–13.
barriers to adopting relational contracting practices in public projects: Tilley, P. A., and McFallan, S. L. (2000). “Design and documentation
Comparative study of Beijing and Sydney.” Int. J. Proj. Manage., 32(2), quality survey comparison of designers’ and contractors’ perspectives.”
275–285. BCE DOC 00/115, CSIRO Building, Melbourne, Australia.
Love, P. E. D. (2002). “Influence of project type and procurement method Toms, L. (2004). “The effect of conflict management strategies on manifest
conflict and relationship quality in a buyer/seller environment.” Ph.D.
on rework costs in building construction projects.” J. Constr. Eng.
thesis, Louisiana Tech Univ., Ruston, LA.
Manage., 10.1061/(ASCE)0733-9364(2002)128:1(18), 18–29.
Totterdill, B. W. (1991). “Does the construction industry need alternative
Love, P. E. D., Davis, P. R., On, C. S., and Irani, Z. (2011). “Causal dis-
dispute resolution? The opinion of an engineer.” Constr. Law J., 7(3),
covery and inference of project disputes.” IEEE Trans. Eng. Manage., 189–199.
58(3), 400–411. Waldron, B. D. (2006). “Scope for improvement: A survey of pressure
Downloaded from ascelibrary.org by UCLA Digital Coll Svcs on 06/24/16. Copyright ASCE. For personal use only; all rights reserved.

Love, P. E. D., Edwards, D. J., and Smith, J. (2005). “Contract documen- points in Australian construction and infrastructure projects.” Rep.
tation and the incidence of rework in projects.” Archit. Eng. Des. Prepared for Blake Dawson Waldron Associates, Sydney,
Manage., 1(4), 247–259. Australia.
Mallen, B. (1963). “A theory of retailer-supplier conflict, control and Watts, V. M., and Scrivener, J. C. (1993). “Review of Australian building
cooperation.” J. Retailing, 39, 24–32. disputes settled by litigation.” Build. Res. Inf., 21(1), 59–63.
Ministry of Justice New Zealand. (2014). “Dispute tribunal Ministry of Wiliamson, O. E. (1975). Markets and hierarchies, analysis and antitrust
Justice New Zealand 2014.” 〈http://www.justice.govt.nz/tribunals/ implications: A study in the economics of internal organization, Free
disputes-tribunal〉 (Apr. 7, 2015). Press, New York.
Mitkus, S., and Mitkus, T. (2014). “Causes of conflicts in a construction Williamson, O. E. (1979). “Transaction-cost economics: The governance of
industry: A communicational approach.” Procedia Soc. Behav. Sci., contractual relations.” J. Law Econ., 22(2), 233–261.
110, 777–786. Yates, D. J. (1998). “Conflict and dispute in the development
Mitropoulos, P., and Howell, G. (2001). “Model for understanding, process: A transaction cost economic perspective.” 〈http://www.
preventing, and resolving project disputes.” J. Constr. Eng. Manage., prres.net/proceedings/proceedings1998/Papers/Yates3Ai.pdf〉 (Apr. 7,
10.1061/(ASCE)0733-9364(2001)127:3(223), 223–231. 2015).
Morris, T. (2006). Social work research methods: Four alternative Yeung, J. F. Y., Chan, A. P. C., and Chan, D. W. M. (2009). “Developing a
performance index for relationship-based construction projects in
paradigms, Sage, Thousand Oaks, CA.
Australia: Delphi study.” J. Manage. Eng., 10.1061/(ASCE)0742-
Punch, K. F. (2005). Introduction to social research: Quantitative and
597X(2009)25:2(59), 59–68.
qualitative approaches, Sage, Thousand Oaks, CA.
Yousefi, S. (2009). “Attitude-based strategic and tactical negotiations for
Rhys, J. S. (1994). “How constructive is construction law?” Constr. Law J., conflict resolution in construction.” Ph.D. thesis, Univ. of Waterloo,
10, 28–38. Waterloo, ON, Canada.

© ASCE C4515003-10 J. Leg. Aff. Dispute Resolut. Eng. Constr.

J. Leg. Aff. Dispute Resolut. Eng. Constr., 2016, 8(1): C4515003

You might also like