Coal Truck Entry Road-1
Coal Truck Entry Road-1
WMM PCC RCC THICKNESS Avg. GSB AVERAGE AVERAGE AVERAGE Remarks
THICKNESS THICKNESS Thickness WMM PCC RCC
in mm Thickness Thickness Thickness
in mm in mm in mm
REMARKS
JP AUTOCLAVERS & CO.
JOINT MEASUREMENT REPORT
PO No.: 5600002116 Date : LOCATION: BANJARI COAL TRUCK PARKING (Entry road)
Report No.: RA Bill No.:02
CHAINAGE OFFSET BS HI IS FS
1.653 101.503
0 R 1.660
C 1.663
L 1.659
15 R 1.464
C 1.460
L 1.461
UCK PARKING (Entry road)
RA Bill No.:02
RL REMARKS
99.850
99.843
99.840
99.844
100.039
100.043
100.042