Professional Documents
Culture Documents
Reason: This strategy deals with reducing the probability, not the impact.
Reason: Provides detailed information on individual WBS elements and work packages.
® Documentation of responsibility
Reason: If there are not clear lines of responsibility for action. the chances of success are reduced.
Correct Answer
Documentation of responsibility
0 0
W ith PERT, each activity duration can range from an optimistic time to a pessimistic time.
Bla nk 1 Blank 2
Correct Answer
Blank 1: optimistic
Blank 2: pessimistic
For a proj ect task, the optimistic activity time is 3 hours, the pessimistic time is 10 hours, and the most likely time is 7 hours. Calculate the weighted
average activity time.
0 7 hours
Reason: The most likely activity time Is not the same as the weighted average activity time.
0 6.7 hours
® 6.8 hours
Reason: This Is (3 + (4x7) + 10)/6 = 6.8, the weighted average using the PERT formula.
Correct Answe r
6.8 hours
Your Answer (0 correct )
Reason: The average p roj ect duration is the sum of all the average activities times along the critical path
Reason: The average project duration is the sum of all the average activities times along the critical path
® the sum of all the average activities times along the critical path
0 the sum of times on the normal path becomes the project duration
Reason: The average p roj ect duration is the sum of all the average activities times along the critical path
Correct Answer
the sum of all the average activities times along the critical path
Reason: These are funds developed as part of the risk response plan.
Reason: Strategies are developed in Step 3 of the risk management planning cycle and need to be controlled when executed.
Reason: Strategies are d eveloped in Step 3 of the risk management planning cycle and need to be controlled when executed.
Reason: This is p art of ongoing status m eetings after the start of the proje ct.
Re ason: Strategies are developed in Step 2 of the risk management planning cycle and need to be controlled when executed.
When assigning responsibility for responding to risk on a work package, which stakeholders should be Involved In the decision-making?
Reason: The person who is doing the work on the task should know who is responsible for responding should a risk occur.
Reason: The person who will own responsibility for responding when risk occurs must agree to the responsibility.
Reason: Unless those team members are working on the task for which risk response is being assigned, they may be notified, but they're
not part of the decision-making.
D Project sponsor
Reason: The sponsor Is typically involved in more strategic-level decisions than risk response at a work-package level.
Correct Answer
Project manager
0
PERT developers chose an approximation of the beta distribution to represent activ ity d urations.
B l an k 1
Correct Answer
Blank 1: beta
Which of the follow ing is the formula fo r the standard deviation of an activ ity when using PERT?
0 a+4m
6
Correct Answer
0
The average project duration follows a normal distribution.
Blank 1
Correct Answer
Blank 1: normal
What term is used to d escribe t he docu ments needed to d evelop an adequate risk response control plan7
Project Scope.
Reason: While needed to execute a proj ect, it is not part of the risk register.
Reason: Provide s detailed informat ion on individual WBS elements and w ork packages.
Risk Register. -
Reason: Summarizes the first t hree steps in risk management planning: identify, assess, response planning.
Reason: While used as part of risk identification, it is not part of the risk register.
Correct Answer
Risk Register.
Which response explains why monitoring risk during p roj ect execut ion is imp ortant?
I!'.! People may h ide p roblems until they become difficu lt to manage.
Reason: T11is is corporate culture and the proj ect manager's attitude.
D Not required because the risk management plan is only executed at the start o f the proj ect.
Reason: Should be reviewed at each status meeting for c hange, but degree of effort is guided by proj ect complexity and team member
input.
Correct Answer
People may hide pro blems until they b ecome difficult to manage.
0 0
Risks can have b ot h positive and negative consequences
Blank 1 Blank 2
Correct Answer
Blank 1: positive
Blank 2 : negative
0
A giant Popsicle melting faster than expected is an example of negative risk.
Blank 1
Correct Answer
Blank 1: negative
Over the life of a project, how does the chance of risk events behave?
Reason: The chance of a risk event occurring declines over the life of the proj ect. See Figure 7.1 for more detail.
0 Remains constant
Reason: The chance of a risk event occurring declines over the life o f the proj ect. See Figure 7.1 for more detail.
Reason: The chance of a risk event occurring d eclines over the life of the project. See Figure 7.1 for more detail.
Correct Answer
@ 1g11re . presents a graphic model of the risk management challenge. he cha nces o a risk evenr occurri ng e.g., an error in t1111e
estimates, cost estimates. or design technology) are greatest during the ea rly stages of a project. T his is when uncertainty is highest and
many questions remain unanswered. As the project progresses toward completion. risk declines as the answers to critical issues (Will
t he technology work? Is the timeline feasible?) are resolved. The cost impact of a risk event, however. increases over the life of the
project. For example, the risk event of a design flaw occurring after a prototype has been made has a g reater cost or time 11npact than 1f
t he flaw were d iscovered during the plannrng phase of the project]
H,gh High
Cost to fh<
risk event
Ch~nces of rl!i>ks
occurring
Oefinmg Planning
Pr
A ___ is the contingency budget set aside to deal with risk events.
0 preventive reserve
Reason: Risks often cannot be prevented, b ut the probability of a risk happening can be reduced through mitigation.
0 risk mitigation
Reason: Mitigation is the action taken to minimize or reduce t he chance of a risk happening.
® management reserve -
Reason: The term for a contingency b udget to deal with risks is management reserve.
Correct Answer
management reserve
Risk Identification.
Risk Assessment.
Correct Answer
1. Risk Identification.
2. Risk Assessment.
Reason: By definition, ris k goes both ways, although most risk management plans just address the negatives.
Reason: Risk is the inability to control chance events, so while we can plan to manage risk, we cannot "overcome" it completely.
Reason: Determining how to respond after a risk happens comes after identifying risk ev ents.
Reason: Determining what can be done to minimize risk before t he p roject begins comes after identifying risk events.
Correct Answer
0 Scope development
0 Defining
0 Planning
® Delivering -
Reason: This would infer that the proj ect is complete, but if something is w rong it would most likely generate the highest cost to correct the
mistake.
Correct Answer
Delivering
Events t hat are within the project manager's control are called "risks" but to differentiate events t hat are outside of a project team's cont rol, the term
_ _ _ _ _ _ is often used.
® threat
0 contingency
0 chance
0 probability
Correct Answer
threat
0 True
I@ False
Correct Answer
False
What is the b enefit of a risk management plan f or a proj ect?
Reason: The sco pe is fixed until and unles s it is modified by a scope ch ange control, which may be init iated by a risk occurring .
Reason: The re w ill o nly be one WBS, altho ug h it can be alt ered as a response to a risk occurring .
Correct Answer
In a generic proj ect life cycle, which phase(s) has/ have the highest probability of risk occurring?
Reason: This is w here scope and WBS uncerta inty is t he greatest, and many planning q uestio ns are yet to be answered.
Reason: It's high during p lanning, but sho uld fall off during the execution of the project.
Reason: A s the w ork completes, the chance of a negative risk event w ill d iminish.
0 Delivering
Reason: If t his were true, there would have been a co mplete lack of project control.
Correct Answer
Reason: The cost to fix a risk event rises over the left of the project. See Figure 7.1 for more detail.
Reason: The cost to fix a risk event rises over the left of the project. See Fig ure 7.1 for more detail.
Reason: The cost to fix a risk event rises over the left of the project. See Fig ure 7.1 for more detail.
Correct Answer
0 top-down
Reason: It would not be appropriate for management to make a decision that requires specialist input.
® group
Reason: Group decision making should be used w he n it wil l improve the quality of important decisions. This is ofte n the case w ith complex
problems that req uire tl1e input of a variety of d iffe re nt specialists.
0 unanimous
Reason: It is not necessary that everyone support the decision 100%, but they must at least agree it is the best decision under the
c ircumstances.
Correct Answer
g roup
Place the steps to group decision making in the correct sequence.
Identifying problems
Reaching a decision
Following up
Correct Answer
2. Generating alternatives
4. Fo llow ing up
In w hat step of g roup decision making does t he p roject manager identify the underlying issues?
Reason: In this step, b rainsto rming is used to develop mu lt iple possible solutio ns.
0 Fo llow -up
Reason: In this final ste p, th e decisio n has been mad e an d implemented, and its effectiveness should be evaluated.
0 Reaching a decision
Reaso n: In this step, alternative so lutions are evaluated and o ne solution is chosen.
Correct Answer
Problem identificatio n
0
During brainstorm ing , th e team generates a list of possible solutions on a flipchart or b lackboard.
Blank 1
Correct Answer
Correct Answer
@ conflict management -
Reason: Conflict may be avoided if a way can be found to encourage strong commitment to a decision.
problem identification
Reason: Problem identification is one of the major steps in the group decision-making process.
Reason: Group decision making should be used when strong commitment to the decision is needed and there is a low probability of
acceptance if only one person makes the decision.
Reason: Although a manager may use MBWA to improve relationships in a team, its primary purpose is not strong commitment to a decision.
Correct Answer
What title best describes the role of the project manager in t he group decision making process?
0 Ultimate authority
Reason: In group decision making, the project manager has ceded the authority to the group for that decision.
0 Tie-b reaker
Reason: If the p roj ect manager is able to guide the process, the team will agree on the best possible solut ion.
@ Facilitator
Reason: A project manager should facilitate the discussion within th e group so t he team reaches consensus.
Correct Answer
Facilitator
In w hat step of group decision making does the team eva luate the effectiveness of the decision?
0 Generating alternatives
Reason: In this step, b rainstorming is used to deve lop multiple possibl e so lutions.
0 Reaching a decision
Reason: In this step, altern ative solutions are evaluated and o ne so lution is chose n.
® Foll ow-up
Reason: In th is final ste p, the decisio n has been mad e and implemented, an d its effectiveness should be eva luated .
Reaso n: In this first step, the tea m ag rees on the det ails o f the pro blem to be solved.
Correct Answer
Fo llow-up
0
If d efe nsive posturing is detected during the problem-ide ntification d iscussion, then it may b e w ise to state the problem-solv ing
Blank 1
ste p if possible.
Correct Answer
In w hat step of group decision making does the team brainsto rm possible solutio ns?
0 Reaching a decision
Reason: In this step, alternative so lutions are evaluated and o ne solution is chosen.
0 Follow-up
Reason: In this final step, the d ecision has been made and implem ented , and its effectiveness should be evaluated .
0 Problem identificatio n
Reason: In this first ste p, the team ag rees on th e d etails of the proble m to be solved.
® Generating alternatives
Reason: In this step, b rainsto rming is used to develop multiple possible solutio ns.
Correct Answer
Generating alternatives
In w hat step of group decision making d o es t he team assess the merits of alternative solutions?
0 Generating alternatives
Reason: In this step, b rainstorming is used to develop mult iple possible solutions.
® Reaching a decision
Reason: In this step, alternative so lutio ns are evaluated and one solut ion is chosen.
Reason: In this first step, the team agrees o n the details o f the problem to be solved.
0 Follow-up
Reason: In this final step, the decision has been mad e and implemented, and its effective ness sho uld be evaluated.
Correct Answer
Reaching a d ecision
Onc e the decision has been made and implemented, it is important fo r the team to f ind the time to evaluate the effectiveness of t he
Blank 1
d ecision.
Correct Answer
Risk Identification
The risk management process b egins by trying to generate a list of all the possible risk that could affect the proj ect.
Blank i
Correct Answer
Blank 1: risks
Correct Answer
Blank 1: events
True or false: A risk breakdown structure sho uld focus on task-level risks during the initial risk identification stage.
0 True
Reason: The RBS should be used to focus on proj ect-level risks at the beginning.
@ False -
Reason: T he RBS sho uld be used to focus on project-level risks at the beginning.
Correct Answer
False
0 Project sponsor
0 Top management
0 Project office
0 Project vendor
@ Project manager
Correct Answer
I Project office
In addition to the core project team, who should/may participate in identifying risk?
l!lil Customers
l!lil Sponsors
Finance analysts
Correct Answer
- Customers
Sponsors
r Outside vendors/contractors
Why should groups be used in the risk identification stage, rather than individuals?
Reason: This may be an important side-effect of involving core team members and other relevant stakeholders in risk identification, but it is
not the primary reason groups sl1ould be used.
Reason: Risks will occur, whet her a group or an individual identifies the risks. The purpose of using a group is not to lay blame when a risk
occurs.
Reason: Research has shown t hat groups make more accurate j udgments about risk than do individuals.
Correct Answer
Reason: This is described as a typical mistake. Focusing on outcomes w ill not help identify causes, and t herefore not help manage risk.
Reason: This is described as a typical mistake. Focusing on outcomes w ill not help ident ify causes, and th erefore not help manage risk.
Correct Answ er
Reason: Both the RBS and Risk Profile with subsequently use the WBS to help provid e detail, but the WBS purpose is not risk management.
Reason: Both the RBS and Risk Profile may subsequently use the OBS to help provide detail, but the OBS purpose is not risk management.
Correct Answer
Risk Profile.
0
Risk pro files are updated and refined during the post-proj ect audit
Blank 1
Correct Answer
Blank 1: audit
0
One of th e keys to success in risk identification is attitude . {Enter o nly o ne word per blank.)
Blank 1
Correct Answer
A _ _ is a list of questions that address traditional areas of uncertainty on a project, drawn from previous, similar projects.
Reason: A work breakdown struct ure contains the tasks and d eliverables required to complete a p roject. It is not a list of questions.
® risk profile -
Reason: A risk profile is a list of questio ns used to help identify risks to the current p roj ect, based on similar, past p roj ects.
Reason: A risk breakdown stru cture is sim ilar to a w ork breakdown structu re in fo rmat. It is no t a list o f q uestio ns.
Correct Answer
risk profile
Risk Assessment
Assessing identified risk is done with respect to what aspect of the project? {Check all that apply.)
Risk profiles
Reason: While assessing a risk, th e project's ti m ing is also taken into consideration.
Correct Answer
Project t iming
Project cost
Project priorities
In scenario analysis, the significance o f _ _ is assessed.
0 high-probability risks
Reason: Scenario analysis is used to determ ine the probability o f a risk occurring, and the impact or consequence, should it occur.
Reason: A ll risk events are assessed to determi ne t he like lihood of occurrence and the impact or consequences should it occur.
Correct An swer
Which statement best describes the scales used to measure/predict probability, impact, and detection?
Rea son: Nume rical rankings may not alw ays deliver true results, so common sense needs to be applied as well.
Reason: Will range from simple to complex, but sl1o uld be defi ned prior to beginning the process.
Correct An swer
L'!ll Impact
Reason: The matrix is likelihood v. impact and separated into zones for priority.
Cost
Reason: The matrix is likelihood v. impact and separated into zones for priority.
L'!ll Likelihood
Reason: The matrix is likelihood v. impact and separated into zones for priority.
D Detectability
Reason: The matrix is likelihood v. impact and separated into zones for priority.
Correct Answer
Impact
Likelihood
Why is the second ste p of risk management to assess the risks ident ified in the first step?
Reason: While more may be identified, this is not the purpose o f assessment.
Reason: Risk identification will likely produce more potent ial risks than there are resources, so the goal is to separate the important ones to
develop a response plan.
Correct Answer
Reason: Although more costly toward the end, it is not a part of the assessment.
~ Impact of an event
Reason: Scenario analysis is the easiest and most commonly used technique for analyzing risks. Team members assess the significance of
each risk event in terms of probability of the event and impact of the event.
Risk management
Reason: Scenario analysis is the easiest and most commonly used technique for analyzing risks. Team members assess the significance of
each risk event in terms of probability of the event and impact of the event.
Correct Answer
Impact of an event
Probability of an event
0
Impact scales can be a bit more problematic, since adverse risks affect proj ect object ives differently.
Blank 1
Correct Answer
Blank 1: Impact
0
Green zone risks are typically considered inconsequential and ignored unless t heir status changes.
Blank 1
Correct Answer
Blank 1: Green
0
Red zone risks receive fi rst priority.
Blank 1
Correct Answer
Blank 1: Red
0 0
Impact x Probability x Detection = Risk Value
Blank 1 Blank 2
Correct Answer
Blank 1: Risk
Blank 2: Value
0
PERT and related techniques take a more macro perspective by looking at overall cost and schedule risks.
Blank 1
Correct Answer
r···Blank 1: PERT
Often organizations find it useful to categorize t he severity of different risks into some form of risk assessment matrix. The matrix is typically structured
around the impact and likelihood of the risk event. Match the zones shown below with their meanings.
Red
f[_
1
_____ Major risks. ol _
Yellow
{l~--Mod
erate-
r ks.
is- - ~•j
Green
f
1 [ ~ - - - ~ol
~ Minor risks. _
Correct Answer
Reason: The FMEA is designed to calculate and ra nk by the p roduct of impact, p robability, and detect io n.
Reason: The FMEA is designed to calculate and ra nk by the p roduct of impact, p robability, and detect io n.
0 subjective classifications
Reason: This is more like the risk severity matrix using like lihood v. impact and separated into zones for priority.
Correct Answer
What time frames does the statisti cal methodolo gy in Prog ram Evaluation and Review Techniq ue (PERT) simulation ut ilize?
Reason: Activity optimistic and pessimist ic times are used to create a c riticality index, i.e., a re lative probability of a task becoming critica l.
Reason: Activity optimistic and pessimist ic times are used to create a c riticality index, i.e., a re lative probability of a task becoming critica l.
Correct Answer
Reason: PERT uses a weighted average including optimistic, most likely, and pessimist ic times, but this is not the outcome.
Reason: PERT takes a macro approach of total p roj ect timing using individual activity
Reason: PERT uses a weighted average including optimistic, most likely, and pessimist ic times, but this is not the outcome.
Correct Answer
Risk Response
Risk responses are developed based upon __.
Reason: These are considered during the assessment steps. Response development needs to consider appropriate act ions after
assessment is conducted.
0 project cost.
0 project timing.
Correct Answer
~ impact
Reason: Minimize the negative consequences when the risk event occurs.
D timing
Reason: While always a consideration, the two strategies are not specifically related to this.
D cost
Reason: While always a consideration, the two strategies are not specifically related to this.
~ likelihood -
Reason: Lessen the chance of the risk event from occurring.
Correct Answer
impact
likelihood
Which best describes what is meant by "risk avoidance" in a risk management plan?
Reason: Impossible to do this for everyth ing, but at t imes specific risks can be eliminate before starting a project by taking different
approaches in th e WBS.
Correct Answer
Reason: Transfer will involve a p remium, but the concept is that doing so will result in a break even or lower total cost of the risk.
Reason: The risk is still there, but the cost is passed to another.
Correct Answer
L'!lil It may be difficult to explain the risk and its consequences to an insurance broker.
Reason: The insurance broker is not familiar with the proj ect, and may not understand the circumstances in which risks may occur, or their
consequences.
Reason: The opposite is t rue; it is often easy to define and insure this type of risk event.
Correct Answer
It may be difficult to explain the risk and its consequences to an insurance broker.
Retain
-
Reason: When a risk event is identified and assessed, a decision must be made concerning which response is appropriate for the event.
Responses to risk can be classified as mitigating, avoiding, transferring, sharing, or retention.
Postpone
Reason: Risk happens on its own schedule and is usually more expensive if it happens later in the project life cycle.
L!.I Avoid
-
Reason: When a risk event is identified and assessed, a decision must be made concerning which response is appropriate for the event.
Responses to ris k can be classified as mitigating, avoiding, transferring, sharing, or retention.
L!.I Transfer
Reason: When a risk event is identified and assessed, a decision must be made concerning which response is appropriate for the event.
Responses to risk can be classified as mitigating, avoiding, transferring, shari ng, or retention.
L!.I Mitigate
Reason: When a risk event is identified and assessed, a decision must be made concerning which response is appropriate for the event.
Respon ses to risk can be classified as mitigating, avoiding, transferring, sharing, or retention.
Correct Answer
Retain
Avoid
Transfer
Mitigate
0
As a risk mit igation strategy, It is common to use a ratio between old and new projects to adj ust time or cost.
Blank 1
Correct Answer
Blank 1: ratio
When t he p roject encounters a threat that is outside the scope of the project or the authority of the project manager, what should they do?
Reason: Escalated risks are not monitored further by the project team.
Reason: If it is outside the scope of the project, noting it in the risk plan is not appropriate.
Correct Answer
0
Avoiding risk is changing the project plan to eliminate the risk or condition .
Blank 1
Correct Answer
Blank 1: Avoiding
0
Retaining risk occurs when a conscious decision is made to accept the risk o f an event occurring.
Blank 1
Correct Answer
Blank 1: Retaining
® Identify and document responsibility for absorbing the impact of the risk occurrence.
0 Determine at what point in the project the risk transference should occur.
Reason: Since when a risk may occur is generally unknown, this would seem impractical.
Correct Answer
Identify and document responsibility for absorbing the impact of the risk occurrence.
Which methods may be used to transfer risk in a project?
L'!lil Insurance -
Reason: This is the most obvious. but not always the easiest.
Reason: A fixed price contract transfers risk from owner to contractor; time and material avoids risk to the contractor.
Correct Answer
Insurance
Escalating risk occurs when the project encoun te rs a threat that is outside the scope o f the p roj ect or the authority of the p roject
Bl ank 1
manager.
Correct Answer
Blank 1: Escalating .
~ --------------------------------------------------------·················j
What characteristic s of a risk event may make "accepting the risk" an appropriate strategy?
Reason: By definition, a risk management plan develops respon se for only identified, i.e., k nown, risks.
Reason: Combined with a high impact cost would make tl1is a viable option.
Correct Answer
So unlikely it is ignored. J The project owne r assumes the risk of an event occurri ng
l~--~
Correct Answer
Contingency Planning
Which are ROtential impacts g iven a project with risk responses but no contingency plan?
L'!lil Panic.
Reason: The entire reason for p lanning is to have ideas of what to do, and avoid panic that may e nsue from risk events.
Reason: Many times, initial understanding of a problem is incomplete/incorrect and leads to poor decision making.
Reason: The savings is realized w hen needed, and cost under situation of d uress and panic are often more expensive.
Correct Answer
Panic.
Risk event
-
Response
.-.
Contingency plan
Trigger
Who is responsible
Correct Answer
1. Risk event
2. Response
3. Contingency plan
4. Trigger
5. Who is responsible
Which are appropriate methods for handling technical (project technology related issues) risk?
Reason: Early testing of concepts is an appropriate contingency for managing technical risks.
Reason: Duration and project timing are defined as schedule risks, rather than a technical risks.
Reason: Pricing problems are defined as cost risks, rather than a technical risks.
Correct Answer
Reason: The funds are expended on methods to shorten activities, such as overtime, subcontracting, etc.
0 Back-up strategies
Reason: This strategy deals with reducing the probability, not the impact.
Correct Answer
0
Proj ects of long duration need some contingency for cost changes- which are usually upward.
Bla nk1
Correct Answer
0
A contingency p lan is an alternative plan t hat will be used if a possible foreseen risk event becomes a reality.
Blank 1
Correct Answer
Blank 1: contingency
What are key components of a contingency plan?
Reason: It is doubtful th at t he contingency p lan w ould require a WBS, but something like a responsibility matrix would be appropriate.
Reason: If nobody is named as responsible, t hen odds of success are greatly diminished.
~ Defining the event that will initiate/trigger the plan into action.
Correct Answer
Defining the event that will initiate/trigger the plan into action.
0
Technical risks are problemati c; they can often be the kind that cause the project to be shut down.
Bla nk 1
Correct Answer
Blank 1: Technical
0
Crashing is reducing the time it takes to complete a project.
Blank 1
Correct Answer
0
Freeway proj ects can fall sl1ort o f the original intentions but st ill add value for each mile completed. This is called • Chunkability ". (Enter
8 Iank1
only one word per blank.)
Correct Answer
Reason: Duration and project t iming are defined as schedule risks, rathe r than a technical risks.
Reason: Avoid a lump-sum approach to developing contingency funds; too often, it w ill not address where price protection is needed.
Reason: Purchases and cont racts that change should be ident ified and estimates should be made of the magnitude of t he change.
Correct Answer
What are the potential actions o f project fund ing cut s such as the reduct ion or elimination of the source of project cash inflow 7
Reason: If the cost to cancel is less than the cost to contin ue, this is a viable option.
Reason: Crashing means reducing the durat ion of a project by shortening one or more activities and not ending t he p roject.
Correct Answer
Contingency Reserves
0
Contingency funds are established to cover project risks.
Bla nk 1
Correct Answer
Blank 1: Contingency
Match the type of contingency wit h the correct definition.
Management
l ~-------
s_e_t_u_
p_t_o_c_o_v_e_r_u_n_k_n_o_w_n
_r_u_n_id_e_n_t-if-ie_ d_ri_
s_k_
s ._ _ _ _ _ __
Time
l ~
Set up to cove r id entified and/o r unknown risks.
- - ~
Correct Answer
0
Contingency reserves are identified for specific work packag es o r segme nts of a project fou nd in the baseline budget o r w o rk
Blank 1
breakd ow n structure.
Correct Answer
Blank 1: Contingency
Reaso n: Cover major unforeseen risk and are t herefore part of the whole project.
Reason: Management reserves cover major unforeseen risk and are therefore part of the w ho le project.
0 Management reserves are established after the budget reserves are identified.
Reason: Manag ement reserves are established after the budg et rese rves are ident ified and funds established.
_.
® The funds for management reserves are included in the total baseline project cost.
Reason: These are separate, and are red uced as the proje ct progresses.
Correct Answer
Management reserves are established after the budget reserves are identified .
Which of t he following types of act ivities might need time buffers?
Act ivities with high costs to make sure the high cost does not negatively imp act t he budg et
Reason: Having a hig h cost does not nece ssarily ind icate the need for a time buffer.
Noncritical activities to reduce the likelihood that they w ill create another critical path
Correct Answer
Noncrit ical activit ies to reduce the likelihood that they w ill create another critical path
Merge activities
Reaso n: As explained in t he chapte r, most risk is negative but the re should be funds available to exploit opportunities if t hey occur.
Reaso n: As explained in t he chapte r, most risk is negative but the re should be funds available to exploit opportunities if t hey occur.
Rea so n: Continge ncy funds are not part of baseline cost and are su pp orted throug h a risk management plan.
Reason: Conting ency funds are not part o f baseline cost, so they ar e not ro lled up with individ ual WBS est imat es.
Correct Answer
A rese rve to manag e all kno w n and unknown proj ect risks.
0
Management reserves are set up to cover un ide ntified risks and are allocated to risks associated w ith the total proj ect.
Blank 1
Correct Answer
Bla nk 1: Management
0
Contingency reserves reduces as the proj ect prog resses.
Blank 1
Correct Answer
0
Management reserves are established after cont ing ency reserves are identified and funds established.
Bla nk 1
Correct Answer
Blank 1: after
Reason: Buffers are added to activities with sever risks, merge activities that are prone to delays due to one or more preceding activities
being late, activ'ities that require scare resource.
Reason: Buffers are added to activities with sever risks, merge activities that are prone to delays due to one or more preceding activities
being late, activities that require scare resource.
Reason: This leads to too many buffers and is more like padding.
Reason: Buffers are added to activities with sever risks, merge activities that are prone to delays due to one or m ore preceding activities
being late, activities that require scare resource.
Correct Answer
0
Contingency reserves are identified for specific work packages or segments of a proj ect found in the baseline budget or work
Bla nk 1
breakdown structure.
Correct Answer
Blank 1: Contingency
0
Contingency and manageme nt reserves sho uld b e kept separate
Blank 1
Correct Answer
Blank 1: separate
® Buffers are a fo rm of estimate padding added by t he p roject manager rather than by the w ork package estimator. -
Reason: Estimates should be done using normal time and before ri sk management p lanning.
Reason: Unc ertainty is defined and d ocumented in the risk management p lan.
Reason: This would imply pad ding, whereas buffers should be used at critical merge activities or project phases.
Correct Answer
0
In the face of overall schedule unc ertainty, b uffers are sometimes added to the end of the proj ect.
Blank 1
Correct Answer