On-Site Equipment Inspection

Check Sheet
Fan/Blower
Equipment Title: Project:
System: P&ID:
Author: Date:
Step Item Yes No N/A Comments Sign &
Date
Pre-running
1 Motor nameplate in place & correct
2 Glands and mechanical seals in position
3 Check adequate spares available in stores
4 Loose bolts
5 Impeller in position
6 Pump turns freely Uncoupled
Coupled
7 Alignment checks complete
8 Earthing correct
9 Guarding safe and rigid
10 Bearings greased/oil level OK
11 Inlet pipe clean
12 Relief devices installed and tested to correct
specification
13 Can pump be drained
14 Can pump be easily removed for maintenance
Running
1 Glands and mechanical seals
2 Direction of rotation correct
3 Post running checks of strainers carried out
4 Running checks Date & Time:
Suction Pressure
Delivery Pressure
Flow
Temperature
Ammeter reading
Vibration and noise
Bearing Temps
5 Drain valves closed & blanked
6 Lubrication levels OK

You might also like