Document Control
Revision
Version Author(s) & Role Comments
Date
Commissioning Manager
1 Contents
1 Purpose and scope of this document........................................................................................5
2 Project Description (Process and Non Process).........................................................................5
2.1 List of Process Systems.....................................................................................................................5
2.2 List of Non Process Systems..............................................................................................................5
3 Commissioning Objectives.........................................................................................................6
4 Environment, Health Safety and Sustainability..........................................................................6
4.1 Safety Training..................................................................................................................................7
4.2 Permit to Work.................................................................................................................................7
4.3 Segregation (Construction / Commissioning / Operation)................................................................7
4.4 Safety and Operability Reviews during Commissioning....................................................................7
5 Terminology Definitions.............................................................................................................8
6 Commissioning and handover Activities..................................................................................10
6.1 Construction Completion................................................................................................................11
6.2 Installation Qualification (IQ)..........................................................................................................11
6.3 Authority to Introduce Energy........................................................................................................11
6.4 IQ completion.................................................................................................................................12
6.5 Operational Qualification (OQ).......................................................................................................12
Once finalised, you will need to update the contents page using Update Field >> Update Entire Table” Be
sure to also update the document version number in the header.
Under each section is a set of guidance notes to be deleted once familiar with the suggestion as to what is
to be included.
This template applies to Full Framework Projects and is intended to provide guidance on the key
information to be included in the project Commissioning and Handover Strategy for capital projects with
engineering content that require commissioning activities.
The Commissioning and Handover Strategy is to be produced during the Define phase and presented for
sanction approval – and will be updated during the Implement phase as appropriate.
General guidance: Commissioning is a process for ensuring that a system is designed and operated as
intended. The purpose of commissioning is to verify that the plant is constructed and operates as per
design requirements and process performance criteria.
The scope of the Commissioning and Handover strategy is described in the figure below. The main objective
is to define the documentation, procedures and philosophy used in the preparation for, and carrying out of,
construction, installation qualification (IQ), operational qualification (OQ) and process / performance
qualification (PQ).
Establish the objectives and key requirements for the Commissioning and handover stages of the
project
Identify the main stages involved in the Commissioning and handover of the project
Define the responsibilities for the organisation and control of Commissioning and handover
activities
Define the documentation associated with the Commissioning and handover stages and activities
as appropriate
Commissioning is the documented process of verifying that equipment and systems are installed
according to specifications, placing the equipment and system into active service, and verifying its
proper operation.
This Commissioning plan describes the equipment tagging procedures used to identify the stages at
which Commissioning activities have been completed on a piece of equipment or system. They
comprise of the Internal Qualification (IQ), Operational Qualification (OQ) and Process Qualification
(PQ). IQ are basically applied to equipment that have passed an operational acceptance test under
Manual mode witnessed by the JM engineer and inspected and witnessed by JM system Owner. OQ
are applied to equipment that have passed Site acceptance test (SAT) with SCADA and provided
training to JM and the equipment have been turnover to the JM. PQ are applied to the System as a
whole and its component elements. After handed over to JM, then PQ shall be introduced to the
plant operation for HAZARD study 6 purposes.
Establish the objectives and key requirements for the commissioning and handover stages of the
project
Identify the main stages involved in the commissioning and handover of the project
Define the responsibilities for the organisation and control of commissioning and handover
activities
Define the documentation associated with the commissioning and handover stages and activities as
appropriate
3 Batching URS
4 Infeed URS
5 Lab URS
8 Washcoat URS
Drawing number
System (4014-MH-J313-ME-
S.no code PID-XXXX) Colour Description
1 Wash coat- CSF
T100-1 &T1200-1 equipment and outlet
1.1 WCC-001 1539 Dark Orange lines
T100-3 &T1200-3 equipment and outlet
1.2 WCC-002 1541 Floracent green lines
d) Firefighting systems - Firefighting system scope of work is subject will be under JM. i.e., alarms &
sprinklers (no changes to existing systems, no additional requirements envisaged)
3 Commissioning Objectives
<Provide an overview of the key commissioning objectives and targets/performance measures.
The main objective of Commissioning is to achieve safe, smooth, stable, and reliable operating conditions
while meeting project specifications. Commissioning shall be performed and executed in compliance to
following methodology and requirement in keys activities as described. Commissioning activities
preparation shall start at an early stage of the project as early as engineering. GC shall mobilise its
Commissioning team who shall be involved at every phase of the of the project.
The deliverables from each team, including the engineering contractor, procurement, construction
and commissioning team.
Qualification parameters for the process and non-process scope.
Timelines to deliver the project to, including any time constraints.
6. 7.
5. Verified closed Prepare and perform Validate pre-
3. 4.
punch list pre-commissioning commissioning
1. Request for 2. Attend Inspection Generate Punch Closed punch list (GC)
Inspection
Action by GC Action by (EPCM, GC, Action by List Action by List (GC) Action by JM,EPCM Action by GC, Action by JM,EPCM
JM, GC) (JM,EPCM) Veondor
The Project Manager is responsible for ensuring commissioning and handover EHS requirements are well
defined, managed, controlled, and followed during the project – in alignment with construction, JM
operations, JM Operations, JM EHS and regulatory requirements. Where considered necessary / critical for
the safe start-up and integrity of the asset, tests and results shall be witnessed by project commissioning
personnel, operations representatives (JM), certifying authorities and regulatory bodies.
The Commissioning phase is a critical operation, with significant risk of causing major injuries,
damaged equipment and to the environment, have to be strictly monitored, the risks is increased
due to the occurrence of some, or all, of the factors listed below:
Transition through temporary stages; Commissioning activities take place in stages, with
changing degrees of interconnection with existing facilities.
Existence of concurrent activities; some Commissioning activities may proceed concurrently
with, for example construction and production/maintenance activities.
Procedures shall provide general HSE Requirements, and Risk Assessment to be followed during
the activites.
Hydrotest/Air Blowing
Equipment inspection and closure
Chemical handling and first filling
Water flushing
Electrical testing
Lube oil and seal oil flushing
Uncoupled running motor test
Chemical cleaning
System inerting
Tightness test
Piping Dry out and preservation
Machine preparation for Start up
Oven and Heater preparation for Start up
Every time these Risks Assessment don’t cover the tasks or a particular activity is planned the
Commissioning Manager or his Deputy, for these critical activities shall prepare a specific Work
Method Statement where indicates:
Additional Task Risk Assessment has been carried out for the activities of:
These risk assessment (attachment 2) shall be applied in conjunction with other risk assessment
each time shall be applicable for the task to be carried out.
<Describe the EHS requirements for the commissioning and handover of the process. Consider;
All these documents require to be approved by JM Safety, Operation & System:
For registered equipment there will be local arrangements in place which cover requirements for
installation and operation checks. Examples of registered equipment are pressure relief valves and
safety trips
Relief system documentation and verification
Equipment installed in a Hazardous Area
Installation of plant trips, alarms and interlocks
Permanent or temporary changes to existing plant
Safety and operability reviews during commissioning (e.g. Hazard Studies 4 (HS4) and 5 (HS5))
Safety training for staff involved in commissioning activities
Risk assessment
Permit to work system including hazardous work control (e.g. hot work, confined space, live
working) Segregation of area where commissioning will take place
Lock off and tag-off controls
Tenets of SIMOPS:
The proximity between several potential sources of hydrocarbon, energy release and activities
having potential ignition sources.
The coexistence of people who might be unaware of the risks inherent to activities they are not
familiar with.
The risk of physical interference such as heavy lifting, anchorage, etc.
The existence of multiple parties in executing the work.
The Contractor HSE Manager, through his staff, shall provide HSE introduction to all personnel
assigned to Commissioning activities. All personnel shall receive the following training:
The Commissioning Manager shall advice on any specific HSE training requirements for personnel
involved in the Commissioning activities
During Commissioning activities shall be used the system referred in the document (that is
jointly prepared with CA.
For all the construction activities to be carried out inside areas Under Commissioning Authority
shall be applied the commissioning PTW System.
Terminology Definitions
Construction completion Completion of construction, installation and configuration activities during the Construction
Phase. It identifies that work is complete and that commissioning can commence.
In some instances, IQ could also include the verification of functional operability of elements
within the system, this may require energisation of equipment for the running and testing of
power distribution systems, testing of emergency shutdown and control systems and dynamic
trials such as bumping motors prior to OQ. An “Authority to Introduce Energy Certificate” will be
issued prior to any introduction of energy to a system.
Authority to Introduce Energy System construction is substantially complete and the general housekeeping standards and safety
in the area are appropriate to allow the introduction of energy
Documentation required for the Construction Completion Pack and IQ Completion Certificate can
be found in Appendix C.
The OQ completion certificate is the point of transfer of responsibility for the care, custody, and
control of the system.
(ATIC) Authority to Introduce Authority to introduce chemicals is a JM document used to document that the system is ready to
Chemicals accept process and hazardous chemicals and begin Start-Up. The ATIC will be prepared by the
Commissioning Manager and approved by the Plant Operations Manager. The certificate should
ensure that the following has been satisfied:
Notification of Handover An example Notification of handover Certificate can be found in guidance: GCP-SG000050-GN-100
Handover Procedure, Appendix F
Simply put PQ involves small scale manufacturing of real products, testing that all equipment is
fully functional, correctly integrated together, and capable of running stably.
Ideally the full product mix would be tested to show overall capability of the plant, but this is not
always practically feasible in real-world scenarios; instead, a small, representative subset of
products are usually chosen.
Ramp-up / Production Part The final phase of new product and process development, whereby the new product moves from
Approval Process (PAPPs) small-scale production to full-scale manufacturing OR moves into the production part approval
process.
Project Handover The COMPLETE transfer of responsibility for the care, custody, maintenance and EHS
(Completion) management of the WHOLE asset.
<When applicable - Indicate any relevant protocols that will need to be followed to complete the checks
and who is responsible for generating these.>
<For items that have been pressure tested and certified at manufacturer’s works – indicate if they need to
be re-tested after installation.>
<Define how faults and incomplete items shall be identified, tracked and managed- i.e. A ‘Punch List’ of
outstanding items should be defined. Items should be categorized and prioritized in terms of their impact
on the IQ phase completion and managed/addressed accordingly>
<Define arrangements in place to train the Commissioning Team and ensure there is an understanding of
the entire design, operational procedures, HSE requirements and compliance, emergency response
procedures and team roles and responsibilities before Operational Qualification (OQ) and operation of the
assets>
<Define arrangements and minimum deliverables required for IQ Completion and handover from
Construction to the Commissioning Team.
A typical list of the pre-requisites for IQ Completion is shown below (see Appendix C for further detail):
<When applicable - Indicate any relevant protocols that will need to be followed to complete the checks
and who is responsible for generating these.>
<Define how faults and incomplete items shall be identified, tracked and managed- i.e. A ‘Punch List’ of
outstanding items should be defined. Items should be categorized and prioritized in terms of their impact
on OQ phase completion and addressed accordingly>
All OQ activities for equipment shall be carried out in accordance with vendor’s instructions /
recommendations and the operating and maintenance manuals.
<Define the performance testing and operating instructions requirements or reference the relevant
documentation (i.e. commissioning plan / OQ protocols)>.
<Define arrangements in place to train the Operations Team and ensure understanding of the entire design,
operational procedures, HSE requirements and compliance, emergency response procedures and team
roles and responsibilities during the Process/Performance Qualification (OQ) and Process >
<Define arrangements and minimum deliverables required to meet OQ Completion and handover from
Project Team to Operations Team – i.e. A ‘Project Handover Certificate’ or ‘Project Acceptance certificate’
shall be completed by the Commissioning Manager or Project Manager and accepted by the Plant
Operations Manager to permit plant operation.
<When applicable - Indicate any relevant protocols that will need to be followed to complete the checks
and who is responsible for generating these.>
<Define how deviations and actions shall be identified, tracked and managed- i.e. A ‘Punch List’ of
outstanding actions should be defined. categorized in terms of their impact on handover/operations and
managed, addressed accordingly>
A typical list of the pre-requisites for Ready for Start Up is shown below:
The Project Handover (Completion) step is a Stage Gate requirement for the project. The stage is approved
by the XX
Below is an outline of the stage gate deliverables required at the Handover Stage:
<Provide an overview of the commissioning and handover planning approach and work-package set up.
Consider the following:
Systemization of the project scope and how this will be prioritized and communicated through the
project and operations teams. – Preliminary mark ups of the boundaries on PIDs / single lines
should be completed as soon as possible (ideally straight after the HAZOP) as this allows early
costing of any additional isolation requirements (e.g. valves).
Maximize the opportunity for schedule optimization by overlapping as many activities as is safe to
do so with construction. In this situation a Safety Management Plan for Transition should be
included- dedicated to ensuring personnel safety during the period of sectional handover.>
<See Appendix A for guidance on how to develop a systemized commissioning schedule, once developed
this should be integrated with the master project schedule.>
<Provide an overview on how the commissioning schedule is structured - it may include the following:
2. If there is a “phased” approach to commissioning and handover, this should be clearly defined
including system boundaries.
3. The plan should also describe if the asset may be sub-divided into systems to enable phased
handover of the plant. The system boundaries for phased handovers shall be clearly defined in
the commissioning plan.
5. Resource requirements including operations, engineering and trades person support as well as
specialist or supplier involvement.
For further details on developing the Commissioning Schedule see Commissioning Planning Guidance.>
It should be noted that execution and contracting strategies for construction, IQ and OQ will differ between
projects and the above is an example. See below guidance on what activities sit best with contractors and
which sit better with JM.
IQ is generally more suitable to contract out, to place this responsibility with supplier
responsible for delivering the physical assets. JM (or agents appointed on JM’s behalf) would
witness and accept final IQ close out documentation.
OQ of building systems, simple systems, non-critical systems and equipment packages is usually
best placed as a responsibility contracted out to the supplier – to hold the supplier responsible
for the performance to specification of the asset they have provided. JM (or agents appointed
on JM’s behalf) would witness and accept final OQ close out documentation.
OQ of critical JM bespoke processes can be a case for a JM commissioning team to take
responsibility for the execution, documentation and approval of OQ with witnessing and
acceptance by JM Operations Team.
In consultation with the Operations Manager or his nominee, the Project Manager shall ensure early
appointment of both a Commissioning Manager and Commissioning Team to ensure the commissioning
and handover strategy is being defined and managed.
The Project Manager shall support the Commissioning Manager during plant commissioning.
<Describe the member and structure of the Commissioning Team – consider including cross-functional
team representation – e.g. Manufacturing team; R&D; Mechanical; Electrical & Instrumentation; Analytical
team.
The manpower plan, roles and responsibilities and competencies of personnel should be considered and
detailed.>
The detailed responsibilities of the Commissioning Manager and Commissioning Team and the ones of the
Main Contractor are summarised in the table below and will be described in detail within the relevant
contracts.
<Complete the below table, for reference an example of the IQ roles and responsibilities is included in
Appendix C>
IQ Outcomes and EPCM Contractor Sub-contractor / Equipment JM Project Manager
Documentation / Works Contractor Vendor
Certification
<Complete the below table, for reference an example of the OQ roles and responsibilities is included in
Appendix D>
OQ Activities EPCM Contractor Sub-contractor / Equipment Vendor JM
Works Contractor
JM Project Engineer
JM Operations Team
JM ICE Supervisor
Operational Readiness
Standard and Emergency EPCm Contractor JM Operations EHS
Operating Procedures Commissioning
Manager
Maintenance Procedures EPCm Contractor JM Maintenance EHS
Commissioning
Manager JM Engineering
Nosie Survey EPCm Contractor JM Industrial EHS
Commissioning Hygienist
Manager
Spare Parts EPCm Contractor JM Reliability Engineer JM Maintenance
Commissioning
Manager
LO/TO Work Orders EPCm Contractor JM EHS JM Maintenance
Commissioning
Manager
Preventive Maintenance EPCm Contractor JM Reliability Engineer JM Maintenance
Plans Commissioning
Manager
Labelling EPCm Contractor JM Operations EHS
Commissioning
Manager
Operations Training EPCm Contractor JM Operations EHS
Commissioning
Manager
Maintenance Training EPCm Contractor JM Maintenance EHS
Commissioning
Manager
Security System Project Engineer JM Security
Commissioning
Manager
Installation Qualification EPCm Contractor JM JM Operations JM Commissioning
(IQ) – See table above for Commissioning Engineer
more definition Manager
JM Engineering
Hazard Studies 4 and 5 JM Project Engineer HS4 and HS5 HS4 and HS5 Hazard Study Leader
Quorum Quorum Members
EPCm Contractor
Members per per G12
G12 Requirements JM Commissioning
Requirements Engineer
Other areas of responsibility to be allocated in agreement with the EPCm contractor include authorised
Permit to Work signatories (including Hot Work, vessel entry, etc.), responsibility for training of
commissioning and operating personnel, signatories for modification certificates and recipients for
commissioning documentation.
9 Commissioning Budget
The commissioning budget defines the costs associated with commissioning and start-up of the plant and
generally consists of equipment, materials and resource costs.
<Provide a high-level overview of the commissioning and handover budgeting approach. The contractor’s
commercial bid should contain commissioning sums, what this covers depends on the contracting strategy
which should be well defined. Owners’ costs for commissioning should also be accounted for.
Integrate also any information related to team meeting or other tools as appropriate- e.g. meeting
schedule, query resolving, defect recording
Regular walkdowns of the systems are recommended and development of a flowchart for the timing of
these system walkdowns including responsible parties and outcomes. Define who will be responsible for
completing walkdowns and punch listing. Prioritization of punch items is a must, see Appendix E for
definitions of punch items.
A correctly planned document control system will ensure that during the project the team and
stakeholders are able to locate the correct versions of documents efficiently and will update the
appropriate team members with information as it changes. It will also enable the correct documents to
be filed for future reference or development at the end of the project.
How documents are to be issued to and received from external parties and around the internal
project team.
The contractor must be able to demonstrate that they can manage commissioning documentation (test
packs, commissioning dossiers etc) either electronically or manually. Electronic systems are preferred
where possible.>
Completed commissioning records should be captured electronically and archived as per the Project
information management guidelines/document management system.
There are many interfaces both within and outside the project which are critical to commissioning success. For instance, interfaces with the engineering
discipline teams, the contractor design engineers, the future operators and technicians. It is essential to detail commissioning interfaces in terms of roles and
responsibilities in RACI charts as well as mutual deliverables and associated risks and opportunities. During Implement, the interfaces will be worked via
workshops and regular progress meetings to ensure schedule and quality compliance.
Definitions –
Ref from - The Global Harmonization Task Force, Quality Management Systems - Process Validation Guidance, 2004
(IQ) Installation Qualification Verifies that all aspects of facility, utilities, and equipment that affect product
Does meet specification and is it quality, adhere to the approved design specifications, and that the piece of
installed correctly? equipment or instrument has been; Properly delivered; Correctly installed;
Configured according to standards and recommendations provided by the
manufacturer or by an approved installation checklist.
Simply put, IQ means is it installed correctly? Important IQ considerations are:
• Equipment design features (i.e. materials of construction cleanability, etc.)
• Installation conditions (wiring, utilities, functionality, etc.)
• Calibration, preventative maintenance, cleaning schedules
• Safety features
• Supplier documentation, prints, drawings and manuals
• Software documentation
• Spare parts list
• Environmental conditions (such as clean room requirements,
temperature, humidity)
(OQ) Operational Qualification In this phase the process parameters should be challenged to assure that they will
Does it function/operate as meet all defined requirements under all anticipated conditions of manufacturing,
specified? i.e., worst case testing to determine the robustness of the process and ability to
avoid approaching “worst case conditions.
Simply put, OQ means is it operating correctly? OQ considerations include:
· Process control limits (time, temperature, pressure, line speed, setup conditions,
etc.)
· Software parameters
· Raw material specifications
· Process operating procedures
· Material handling requirements
· Process change control
· Operator Training
· Short term stability and capability of the process, (latitude studies or control
charts)
· Potential failure modes, action levels and worst-case conditions (Failure Mode
and Effects Analysis)
(PQ) Process / Performance Simply put, PQ means to demonstrate that the process will consistently produce
Qualification acceptable product under normal operating conditions,
PQ considerations include:
Does it perform as we wanted? · Actual product and process parameters and procedures
· Acceptability of the product
· Assurance of process capability
· Process repeatability, long term process stability
Challenges to the process should simulate conditions that will be encountered
during actual manufacturing. Challenges should include the range of conditions as
defined by the various action levels allowed in written standard operating
procedures as established in the OQ phase. The challenges should be repeated
enough times to assure that the results are meaningful and consistent.
Process and product data should be analysed to determine what the normal range
Installation Qualification
The purpose of IQ is to check and test the Works (System by System) to confirm that the installation is in accordance
with drawings, specifications, regulations and is ready for the start of Operational Qualification in a safe manner and in
compliance with the project requirements. This includes completion of JM Hazard Study 4 and close out of actions.
The JM Capital Project Team have overall accountability for the business case, however the EPCM will be held
accountable for the delivery of the Works during the IQ phase.
Documentation Required for the Construction Completion Pack and IQ Completion Certificate
Each System requires a completed Construction Completion Pack containing required certificates of completion for
the constituent equipment, piping, instrumentation, electrical items etc throughout both phases of IQ and OQ.
The Construction Completion Pack shall contain as a minimum the documents described below. In addition to this the
EPCM Contractor shall compile the full IQ package based on their experience, industry best practice, their procedures
and any relevant local, national or international standards.
The EPCM Contractor is free to use their own templates with prior approval from the Purchaser’s Representative
Installation Qualification encompasses all disciplines and its activity includes the checking of fabrication and
installation work.
The EPCM Contractor shall complete the checks and Construction Completion Pack as required for the scope of each
System.
The deliverables in each Construction Completion Pack shall include for each of the discipline related categories
below:
IQ Completion Certificate is a form completed by the Contractor after all IQ checks are carried out. Only when
an IQ completion certificate has been signed by both the contractor and purchaser will it mean the
equipment / installation is ready for the start of OQ.
Inspection and test plan (ITP) A copy of this document shall be included which references the relevant
Inspection and tests undertaken on the plant, system or equipment, along with the completed Inspection and
test plan results.
Check Records (CR) shall be included on which the EPCM Contractor records the results of all checks,
inspections and tests carried out for each individual item in the System.
Punch List Register (PLR) containing details of punch list items and their status.
Carry Over Work Register (COWR) including details of punch list items which have been agreed with the
Purchaser’s Representative to be carried over for completion into the Operational Qualification stage.
Electrical
Visual inspection for complete and correct installation.
Insulation and continuity testing of cables.
Insulation testing of generator, transformers and motors, panels, distribution board etc.
EFLI (Earth Fault Loop Impedance) testing.
Phase rotation checks.
Earthing and Bonding.
Lightning protection.
Functional check of switches and control devices.
Battery preparations.
Lighting and socket outlet checks.
Area completion.
Heat tracing.
Preventive maintenance carried out on equipment before it is taken into use.
As Built drawings, Documentation and test certificates
Piping
HVAC
Visual inspection for complete and correct installation.
Cleaning of ductwork.
Leak testing of ductwork.
Alignment checks.
Mechanical function checks of equipment.
Preventive maintenance carried out on equipment before it is taken into use.
Flow & contents identification.
As Built Drawings, Documentation and test certificates.
Safety Facilities
Visual inspection for complete and correct installation.
Functional testing of safety facilities.
Preventive maintenance carried out on equipment before it is taken into use.
As Built Drawings, Documentation and test certificates.
Although the JM project team are accountable for the business case, we will hold the EPCM accountable for
the delivery of the Works. Therefore, a typical RASCI matrix for the delivery of the works during the IQ
Process is shown below:
Instrumentation A R - I
and Control
Piping A R - I
Vendor Packaged A S R I
Equipment
Safety Facilities A - R I
Civil, Structural A R - I
and Architectural
Hazard Study 4 S - - A,R
Once OQ is completed for the Works, the Purchaser will then undertake Process Qualification (a collection of process
performance test)s which will be supported by the JM Capital Project Team, and (where needed) equipment vendors
to verify that a System or Systems perform as expected under process conditions and that the requirements defined
in the User Requirements Specification, Basis of Design, and Business Case have been delivered. The EPCM Contractor
may still be supporting the project with closing out any mutually agreed items from the COWR (Close Out Work
Register) but they will not be directly supporting the Process Qualification.
In order to demonstrate completion of the OQ stage and to enable the Purchaser to commence Process Qualification,
the EPCM Contractor shall provide to the Purchaser’s Representative the documentation outlined below.
Documentation Required for the System Handover Pack and OQ Completion Certificate
Each System will have a System Handover Pack which contains status information from the preceding IQ stage for that
System. The EPC Contractor shall add the required OQ checks and results to this System Handover Pack, with final
sign off by appropriate EPCM Contractor staff and witnessed by the Purchaser’s Representative (or nominee). At
least 8 weeks prior to commissioning the OQ protocols shall be provided by the EPCM Contractor to the Purchaser’s
Representative. The Purchaser Representative will confirm that the OQ tests will be sufficient to enable the Purchaser
to commence Process Qualification after OQ completion.
The OQ content for each completed System Handover Pack shall contain as a minimum the documents described
below. In addition to this the EPCM Contractor shall compile the full OQ package based on their experience, industry
best practice, their procedures and any relevant local, national or international standards needed to demonstrate that
the Systems or equipment may safely be started up, operated and maintained.
Example OQ protocols can be provided however the EPCM Contractor is free to use their own templates with prior
approval of the Purchaser’s Representative.
For completion of the OQ stage, each System Handover Pack shall contain as a minimum:
OQ Completion Certificate is a form completed by the Contractor after all OQ checks are carried out. Only
when an OQ completion certificate has been signed by both the contractor and purchaser will it mean the
equipment / installation is ready for the introduction of hazardous process material and PQ. NOTE: prior to
the introduction of chemicals an Authority to Introduce Chemicals certificate is required.
A completed set of IQ checks and IQ completion certificates (including required signatures) for all the
Systems
Updated Carry Over Work Register showing any items agreed to be carried over into the Product
Qualification Stage
Close out report for EPCM Contractor’s actions from Hazard Studies 4 and 5.
Permitting close out report (PCR) the EPCM Contractor shall compile a permitting close out report which will
indicate the status of any permits under his control at the time of OQ
Handover at OQ
Handover of the Works at the end of OQ by the EPCM Contractor to the Purchaser’s Representative shall be
documented by the OQ Completion Certificate.
The EPCM Contractor shall ensure that the following are completed, signed off by the EPCM Contractor authorised
staff and witnessed by the Purchaser’s Representative (or nominee):
General
All previous hazard study and design safety review actions, signed off and accepted for ongoing operation
Regulatory approvals as required prior to Authority to Introduce Chemicals (ATIC) (see JM template).
Although this is Purchaser’s Representative’s responsibility the EPCM Contractor will need to prepare in
advance the Systems within their scope of supply and provide to the Purchaser’s Representative final test
results and certification as required, examples are:
o Fire and alarm Systems certification
o Safety Systems certification
o ATEX certification
All calibration certificates, Pressure Test certificates, Electrical Test certificates and Final O&M documentation
Noise measurements and approvals
Results of short running-in tests on machinery
Testing of systems using inert materials
Mechanical
All Category A and B punch list items closed out, (see Appendix E for punch list category definition).
Restrictor flow orifice plates verified for correct flow
Systems cleaned, purged and ready to accept chemicals, including drainage, waste and effluent routes
Utilities and enabling Systems fully charged & dosed (e.g. fire water, chilled water (glycol / inhibitor), cooling
towers, fuel oil, etc
Sample and environmental Systems as per design and specification
Electrical
Instrumentation
Piping
HVAC
Vendor Packaged A - R I
Equipment SAT
Hazard Study 5 S - - A,R
ATIC S A, R
Handover By System
In this situation the EPCM Contractor will supply the documentation outlined above and will also include for the
relevant plant sections a Safety Management Plan for Transition - dedicated to ensuring personnel safety during the
period of sectional handover, for prior approval by the Purchaser’s Representative. The Safety Management Plan for
Transition shall be delivered to the Purchaser’s Representative at an agreed time in the Approved Programme and
contain:
On a daily basis as part of morning toolbox talks, the EPCM Contractor shall provide an updated set of documentation
to staff under management by the EPCM Contractor and Purchaser’s Representative with updates to the above to
enable clear understanding by all parties which areas and equipment are live (or not) and which permit Systems are to
be applied to each.
When requested by the construction manager, the commissioning manager and commissioning team will inspect and
check the system, this typically happens when installation is 80% complete. During check out punch items will be
recorded on a standard punch list form and ideally these punch items would be corrected as soon as possible. As some
punch list items will have a greater impact on commissioning, they will be categorized with the aim of prioritizing the
corrective work and spreading the workload. Once prioritized each action must be given an ‘action on’ column to
clarify who is responsible for resolving the punch item.
Exception items must be kept to a minimum and must not impact the safe commissioning or operation of
the plant. It is recommended that punch items are only categorised as exception items as a last resort when
other attempts to rectify the items have been exhausted. A target date for completion of these items must
be agreed between all relevant parties.