Professional Documents
Culture Documents
Rotary Table IQ
Rotary Table IQ
ROTARY TABLE
INSTALLATION QUALIFICATION
The equipment must be fully installed and integrated with site utilities and safety systems. It must be
possible to control all recipe parameters and all outputs must be capable of being trended from the PLC.
Responsible Resources
Regional Projects Regional Projects
Regional Manufacturing Technology
JM Nilai - Malaysia Operations
Requirement Acceptance criteria
Signature:
Previously identified snags must be All previously identified snags
closed out to ensure minimum should be rectified.
disruption to OQ PQ Date:
Test Method Results Initials Date
5.1. Ensure that all snags for individual items of equipment
identified at manufacturer FAT have been closed out: Pass / Fail
Comments
Responsible Resources
Regional Projects Regional Projects
Requirement Acceptance criteria
Signature:
Electrical installation completed to All installation work
ensure safe operation of the completed to good industry
equipment, meeting all equipment practice and all specific Date:
specific needs requirements of the
equipment have been met.
Test Method Results Initials Date Reference
Document
7.1 Cable tray installation complete with level & plumb Yes / No
tray and covers installed.
7.2 All cables routed properly inside of cable tray and Yes / No
properly secured.
7.3 All cables routed and dressed properly from tray to Yes / No
device.
7.4 All cables and wires properly terminated per Yes / No
electrical drawing.
7.5 All network cables installed and terminated per Yes / No
electrical drawing.
7.6 All cables and electrical system properly grounded. Yes / No
7.7 I/O checks complete. Yes / No
Comments
Approval
Approval for
Operational Qualification Project team Process Engineering Production