You are on page 1of 10

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/248879051

Development of a Specification for Bridge Seismic Retrofit with Carbon Fiber


Reinforced Polymer Composites

Article  in  Journal of Composites for Construction · February 2004


DOI: 10.1061/(ASCE)1090-0268(2004)8:1(88)

CITATIONS READS

13 1,134

3 authors, including:

Chris Pantelides Larry Cercone


University of Utah Millik
181 PUBLICATIONS   4,027 CITATIONS    9 PUBLICATIONS   241 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Impact Loading and Shear Brittle Failure Analysis of Galvanized Steel Light Pole View project

Optimizing fiber wetout for composites manufacturing View project

All content following this page was uploaded by Larry Cercone on 15 September 2015.

The user has requested enhancement of the downloaded file.


Development of a Specification for Bridge Seismic Retrofit
with Carbon Fiber Reinforced Polymer Composites
Chris P. Pantelides, M.ASCE1; Larry Cercone2; and Frederick Policelli3

Abstract: The U.S. Interstate 80 bridge over State Street in Salt Lake City is very near the Wasatch fault, which is active and capable
of producing large earthquakes. The bridge was designed and built in 1965 according to the 1961 American Association of State Highway
Officials specifications, which did not consider earthquake-induced forces or displacements. The bridge consists of reinforced concrete
bents supporting steel plate welded girders. The bents are supported on cast-in-place concrete piles and pile caps. A seismic retrofit design
was developed using carbon fiber reinforced polymer 共CFRP兲 composites, which was implemented in the summer of 2000 and the
summer of 2001, to improve the displacement ductility of the bridge. The seismic retrofit included column jacketing, as well as wrapping
of the bent cap and bent cap-column joints for confinement, flexural, and shear strength increase. This paper describes the specifications
developed for the CFRP composite column jackets and composite bent wrap. The specifications included provisions for materials,
constructed thickness based on strength capacity, and an environmental durability reduction factor. Surface preparation, finish coat
requirements, quality assurance provisions, which included sampling and testing, and constructability issues regarding the application of
fiber composite materials in the retrofit of concrete bridges are also described.
DOI: 10.1061/共ASCE兲1090-0268共2004兲8:1共88兲
CE Database subject headings: Bridges, Concrete; Constructivity; Fiber reinforced polymers; Composite materials; Retrofitting;
Specifications.

Introduction the present specifications, ACI Committee 440 was updating the
1996 report with information gathered from research 共ACI 2000兲.
Seismic rehabilitation techniques for concrete bridges involving In 2002, ACI 440 published a guide for the design and construc-
steel jacketing, concrete jacketing, and fiber reinforced polymer tion of externally bonded FRP systems for concrete structures
共FRP兲 composite jackets for columns have been developed re- 共2002兲. In Europe, the EUROCRETE project has produced draft
cently 共Priestley et al. 1996兲. Various circular and rectangular col- recommendations for utilization of non-ferrous reinforcement
umns with carbon FRP composite retrofits have been tested in the using modifications of existing design rules 共Clarke et al. 1996兲.
laboratory 共Seible et al. 1997兲; in addition, in situ tests have been
In 1997, the Japan Society of Civil Engineers 共JSCE兲 published
performed on FRP retrofitted columns 共Gamble and Hawkins
recommendations for design, testing, and construction of concrete
1996兲 and bridge bents 共Pantelides et al. 1999, 2001b, 2002兲. The
structures using continuous fiber reinforcing materials 共JSCE
tests showed that carbon FRP composite jackets are as effective
1997兲. The Canadian Standards Association, included a section in
as comparable steel jackets. FRP composites are increasingly
the Canadian Highway Bridge Design Code containing material
being used as alternatives to steel in rehabilitation projects, due to
their resistance to electrochemical corrosion, higher strength, en- properties and durability issues of FRP composites and fiber re-
vironmental durability, and lower overall cost. inforced concrete 共FRC兲 for deck slabs, concrete beams, tendons,
Standard specifications for externally applied FRP composites and barrier walls 共Bakht et al. 2000兲. Recently, the International
to concrete structures are in an evolutionary stage. The American Conference of Building Officials Evaluation Service 共2001兲 has
Concrete Institute’s Committee 440 report on FRP reinforcement published acceptance criteria for concrete strengthening using
for concrete structures 共ACI 1996兲 includes information on FRP FRP composite systems.
composite materials, properties, and test methods, and design The Interstate 80 State Street bridge in Salt Lake City was
guidelines for external reinforcement. At the time of developing designed in 1965 according to the State of Utah Standard Speci-
fications for Road and Bridge Construction, 1960 Edition and
1
Professor, Dept. of Civil and Environmental Engineering, 122 South Supplements, and the American Association of State Highway
Campus Drive, Suite 104 EMRO, Univ. of Utah, Salt Lake City, Officials 共AASHO兲 Specifications of 1961 with Interim Specifi-
UT 84112 共corresponding author兲. E-mail: chris@civil.utah.edu. cations. The bridge was designed for gravity and wind loads, but
2
President, Navlight Composites, Pasadena, CA 91107. it was not designed to resist earthquake-induced forces and defor-
3
President, Frederick Policelli & Associates, Salt Lake City, mations that are likely to occur. There are two parallel bridges
UT 84117. 共eastbound and westbound兲; each bridge consists of a bent on the
Note. Discussion open until July 1, 2004. Separate discussions must east side and a bent on the west side, for a total of four bents at
be submitted for individual papers. To extend the closing date by one
the site. Each 55 m long bridge has two end spans of length 10.69
month, a written request must be filed with the ASCE Managing Editor.
The manuscript for this paper was submitted for review and possible m and 10.82 m and a 33.83 m middle span as shown in Fig. 1; all
publication on January 3, 2002; approved on January 24, 2003. This spans are simply supported. The substructure is made of cast-in-
paper is part of the Journal of Composites for Construction, Vol. 8, No. place concrete piles, reinforced concrete pile caps, columns, and
1, February 1, 2004. ©ASCE, ISSN 1090-0268/2004/1-88 –96/$18.00. bent caps. The dimensions of a typical bent are shown in Fig. 2.

88 / JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004


The concrete was designed with a compressive strength of 29
MPa and the steel with a yield stress of 280 MPa. The girders are
welded steel plate beams. The carbon FRP 共CFRP兲 composite
design for seismic rehabilitation of the bridge is documented else-
where 共Pantelides et al. 2001a兲. This article presents the provi-
sions developed for specification of CFRP composite materials,
constructability issues related to the application of the CFRP
composite, and quality control aspects of the implementation.
Fig. 1. State Street bridge elevation showing the four bents
Special Provisions for Column and Bent Composite
retrofitted with carbon fiber reinforced polymer composites
Wrap
As part of the ‘‘Supplemental Specifications’’ of the construction
contract 关Utah Department of Transportation 共UDOT兲 1999兴, two

Fig. 2. Dimensions and member cross sections of State Street bridge

JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004 / 89


special provisions were developed by the authors: 共1兲 ‘‘Special Table 1. Minimum Initial Properties of Carbon Fiber Reinforced
Provision 525S’’ for column composite wrap, and 共2兲 ‘‘Special Polymer Composite
Provision 526S’’ for bent composite wrap. The reason for the two Properties at 22°C Minimum values ASTM test method
provisions was that, in addition to the State Street bridge, four
other bridges were to receive strengthening of their columns with Ultimate tensile strengtha 960 N/mm2 D 3039
CFRP composite jackets, whereas the State Street bridge would Tensile modulusa 73,100 N/mm2 D 3039
receive a complete seismic strengthening with CFRP composites, Ultimate elongationa 1.3% D 3039
which included the columns, bent cap, and bent cap column Fiber volume 40% D 3171
joints. This article presents the requirements of both special pro- Glass transition temperature 60°C D 4065
visions of the ‘‘Supplemental Specifications’’ 共UDOT 1999兲, de- a
In primary fiber direction and normalized to 40% fiber volume.
veloped prior to the ACI 440 draft document 共ACI 2000兲, the sure has since replaced the smaller ring. In Table 1, the baseline
ICBO AC125 document 共ICBO 2001兲, and the ACI 440.2R-02 properties were selected from the lower of supplier advertized
document 共ACI 2000兲. properties of carbon fiber/epoxy resin material systems to permit
a wide range of bid responses. The special provisions of the
Materials
‘‘Supplemental Specifications’’ 共UDOT 1999兲 set forth the re-
E-glass fiber composites are used widely because of their lower quirements for verification of proposed material properties and
cost. However, studies have shown possible durability problems property retention under a prescribed set of environmental condi-
in FRP bars made of E-glass in environments with high alkalinity tions. This set of conditions, of both exposure type and exposure
such as in concrete 共Katsuki and Uomoto 1995; Tannous 1997兲. time durations, had been largely developed by the Defense Ad-
An experimental study of cement-based specimens wrapped with vanced Research Projects Agency under the Advanced Compos-
FRP composite sheets, subjected to exposure of wet-dry cycling ites Technology Transfer/ Bridge Infrastructure Renewal program
and freeze-thaw cycling was recently carried out 共Toutanji and 共Seible et al. 1995兲. With respect to the glass transition tempera-
El-Korchi 1999兲; carbon fiber composite specimens showed no ture (T g ), the requirement of a minimum T g of 60°C is based on
effects, whereas glass fiber composite specimens showed signifi- a maximum expected service temperature of 42°C. From actual
cant degradation in strength of the order of 10% for freeze-thaw tests after the CFRP composite application, the mean value of T g
cycling, and 20% for wet-dry cycling. Due to the harsh weather was found to be 71°C. It should also be noted that the value of T g
conditions and the practice of using deicing salts, the Utah De- equal to 60°C is also used in the ICBO AC125 document 共ICBO
partment of Transportation limited the materials selection to car- 2001兲.
bon fiber/epoxy resin composite systems as the only acceptable
fiber reinforced composite materials for the rehabilitation. While
Strength Capacity
the moisture and high alkaline environmental durability of both
E-glass and carbon fiber composites are superior to that of steel, The utilization of ‘‘strength capacity’’ as the structural strength
the carbon fiber composite is substantially more resistant than requirement for column and bent cap CFRP overlays was used in
E-glass fiber composite. The selection of the carbon fiber/epoxy the special provisions of the I-80 ‘‘Supplemental Specifications’’
resin system was also based on the adequate history of successful 共UDOT 1999兲 for the first time in highway bridge retrofit and
application to concrete bridges in Utah and other states. rehabilitation. Strength capacity is force per unit width or the
Considerable development and validation of the improved product of the stress (S) and jacket thickness (T). The material
seismic performance of carbon fiber/epoxy resin materials has allowable stress is defined as the mean ultimate strength, minus
been conducted by the Defense Advanced Research Projects two standard deviations 共2␴兲. In addition, the 共mean 2␴兲 strength
Agency 共DARPA兲 through the Advanced Composites Technology is multiplied by an environmental durability strength reduction
Transfer/Bridge Infrastructure Renewal 共ACCT/BIR兲 Consortium factor 共␾兲 which has a value less than 1. The ‘‘Supplemental
共Seible et al. 1995, 1997兲, and by the University of Utah on I-15 Specifications’’ 共UDOT 1999兲 required testing of 50 samples for
and other I-80 bridge bents 共Gergely et al. 1998; Pantelides et al. the purpose of determining the mean and standard deviation
1999, 2001b, 2002兲. The choices between ambient and high- strength values. The specimens were flat and straight and their
temperature cure, and between machine and hand wrapping tech- length, width, thickness, gripping method and test procedure was
niques for carbon fiber/epoxy resin composites were options according to ASTM D 3039. The allowable strength S a is given as
available to the contractor; however, precured casings were not an S a ⫽␾ 共 S mean⫺2␴ 兲 (1)
option. The high-temperature cure system with carbon FRP com-
posites is a technique that was used previously by the ACCT/BIR The thickness of the CFRP composite to be constructed (T c ) is
Consortium for seismic retrofit of columns 共Seible et al. 1995, related to the design strength S d and design thickness T d using the
1997兲. In 1996, a demonstration project at the I-80 Highland definition of strength capacity as
Drive bridge in Salt Lake City used a high-temperature cure sys-
tem with CFRP composites for the seismic retrofit of a bridge
bent 共Gergely et al. 1998兲.
T c⫽ 冉 冊
Sd
T
Sa d
(2)

The composite wrap system was required to meet minimum Eqs. 共1兲 and 共2兲 allow different manufacturers with different sys-
initial properties, as shown in Table 1. Other requirements in- tems to proportion their designs according to the properties of
cluded determination of jacket thickness, environmental durabil- their material.
ity rating, Naval Ordnance Laboratory 共NOL兲 ring strength, and
history of use. The NOL ring strength test started out as a 146 mm
Environmental Durability Strength Reduction
diameter ring test for modulus and strength determination of fila-
Factor (␾)
ment wound materials. The ring fabrication is performed accord-
ing to ASTM D 2291, and testing according to ASTM D 2290. A The utilization of an environmental durability strength reduction
larger, 508 mm diameter ring, tested by internal hydraulic pres- factor to account for environmental degradation of the FRP com-

90 / JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004


Table 2. Durability Environment Parameters
Environment Conditioning method Exposure conditions Test duration
Water ASTM D 2247 100% humidity 38⫾10°C Initial, 1,000, 3,000, and 10,000 h
ASTM E 104
Salt water ASTM D 1141 Immersion at 23⫾10°C Initial, 1,000, 3,000, and 10,000 h
ASTM C 581
CACO3 solution ASTM C 581 Immersion in CACO3 at 23⫾10°C and pH 9.5 Initial, 1,000, 3,000, and 10,000 h
Fuel resistance test ASTM C 581 Immersion in diesel fuel at 23°C Initial, 4 h
Dry heat ASTM D 3045 50°C Initial, 1,000, 3,000, and 10,000 h
Freeze/thaw None Cycle between 100% humidity at 38°C and freezing at ⫺18°C Initial, 20 cycles at 24 h/cycle

posite material was used in the ACTT/BIR program for the first Structural Adhesive
time in bridge retrofit and rehabilitation 共Seible et al. 1995兲. This
Minimum structural adhesive properties were required by the spe-
factor is determined for any candidate laminate material by a
cial provisions; these properties were modeled after well-known
log-log regression analysis, from periodic sample test results by
products, which had been used extensively in previous tests both
projecting property data beyond the limitation of fixed-term test
in the laboratory and during in-situ simulated seismic testing of
values. The durability test data required for determining ␾ in the
bridge bents 共Pantelides et al. 1999, 2001b兲. The structural adhe-
‘‘Supplemental Specifications’’ 共UDOT 1999兲 are given in Table
sives are high modulus, high strength, structural, epoxy paste ad-
2, and the expression for obtaining its value is given as
hesives that have been used in many building and bridge repair
ultimate strength 共 projected to life required duration兲 projects. The minimum adhesive properties are shown in Table 3.
␾⫽
ultimate strength 共 initial value兲 It should be noted that a deflection temperature of 47°C is ad-
(3) equate under the present local conditions, where the bridge is
shaded and the maximum expected service temperature is 42°C.
The ‘‘Supplemental Specifications’’ 共UDOT 1999兲 specify that in
the event insufficient data exist for determining a ␾ factor from
Table 2 a prescribed value could be used. This prescribed value Finish Coat
was 共1兲 ␾⫽0.75 for a carbon FRP composite ambient tempera-
ture curing system, and 共2兲 ␾⫽0.80 for a high temperature curing The finish coat material properties, drying times, and developed
system. hardness were specified for an aliphatic urethane waterborne coat-
ing, which is graffiti resistant, abrasion resistant, stain resistant,
and nonflammable. The finish coat provides excellent ultraviolet
Minimum Burst Strength Requirement for Naval resistance and has rapid hardness development. The material
Ordnance Laboratory Rings based on which the specifications were written has been used as a
The minimum burst strength of NOL rings was set forth in the finish coat on many bridge retrofit and rehabilitation projects as a
‘‘Supplemental Specifications’’ 共1999兲 with values for ultimate coating for FRP composite jackets and for coating concrete and
hoop stress of 960 N/mm2 and for a hoop modulus of masonry. The properties of the coating specified for the seismic
73,100 N/mm2 . The above strength and modulus values were retrofit of State Street bridge are given in Table 4. The drying
based on gross section, as normalized to 40% fiber volume. Cyl- requirements for the finish coat material are given in Table 5. The
inders for the excising of test rings were required to be made Konig/Sward index is a thickness measurement of drying paint.
during each day of bridge-site CFRP jacketing or CFRP overlay-
ing. The minimum burst properties described above for NOL Certificate of Compliance
rings are the same values as the flat laminate minimum design
properties of the CFRP composite system, shown in Table 1. The A Certificate of Compliance with the requirements of the special
ring test results are especially useful in determining exact prop- provisions was specified prior to the use of all materials. A copy
erties of cylindrical shapes made by the same process used in FRP of the Certificate of Compliance was to be included in the daily
jacket fabrication, such as the case here for the State Street bridge construction log for quality control/quality assurance 共QC/QA兲
with circular columns, as shown in section B-B of Fig. 2. purposes. The fact that the material was used on the basis of the
Certificate of Compliance did not relieve the contractor of any of
the requirements of the plans and specifications.

Table 3. Structural Adhesive Minimum Properties


Properties Minimum/maximum values Test method
Tensile strength 24.8 N/mm2 共min兲 ASTM D 638 Table 4. Finish Coat Material Properties
Minimum elongation 1% 共min兲 ASTM D 638 Property Requirement
at break
Modulus of elasticity 4,480 N/mm2 共min兲 ASTM D 638 Color Concrete hue
Flexural strength 46.8 N/mm2 共min兲 ASTM D 790 Texture Gloss
Shear strength 共14 days兲 24.8 N/mm2 共min兲 ASTM D 732 Density 共specific gravity兲 1.02⫾0.06 g/cm3
Deflection temperature 47°C 共min兲 ASTM D 648 Solids content by volume 30%
Water absorption 0.03% 共max兲 ASTM D 570 Volatile organic compounds 0.06 g/cm3

JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004 / 91


Table 5. Drying Requirements for Finish Coat Material Listing of Quality Control Personnel
Dry time Hardness Konig/Sward A list of QC personnel, their work history and their training was
Dryness 共min兲 development index requested in the special provisions of the ‘‘Supplemental Specifi-
Set to touch 25 At 2 h 20/16 cations’’ 共UDOT 1999兲; this is especially needed in construction
At 4 h 32/20 of relatively new materials and processes. This is the first appli-
Dry to touch 55 At 8 h 39/24 cation of requiring such listing and resumes of QC personnel for
At 24 h 56/36 a FRP composite bridge retrofit project.
Through dry 120 At 48 h 84/46
At 1 week 103/50
Installation Requirements
The special provisions of the ‘‘Supplemental Specifications’’
Construction Requirements 共UDOT 1999兲 require certain installation procedures for the
CFRP composite column jackets, and different installation proce-
The contractor was required under the ‘‘Supplemental Specifica- dures for the CFRP composite bent cap overlays with respect to
tion’’ 共UDOT 1999兲 to submit certain construction-related items surface preparation.
in the submittal as follows.
Surface Preparation
The requirement in the special provisions for the columns was
History-of-Use Documentation
that the surface should be free of fins, sharp edges and protrusions
Requiring a history-of-use documentation is standard practice for that could damage the fibers or cause voids or depressions behind
most relatively new construction products. The ‘‘Supplemental the installed CFRP jacket. Surfaces should be cleaned and free of
Specifications’’ 共UDOT 1999兲 required that the CFRP composite dust, grease or any other foreign matter. Depressions greater than
system shall have been in use for at least two years on related 25 mm in diameter by 2 mm deep were to be filled with structural
transportation projects. A history of such projects with material adhesive. By contrast, the requirements for the bent cap were that
quantities, dates, and locations was required. During the present the surfaces should be hydroblasted with a minimum pressure of
project, the contractor, the Utah DOT inspectors, the manufactur- 276 MPa, at a rate of 189 mL/s; a thickness not less than 2 mm of
er’s representative, and the Quality Control and Quality Assur- the concrete substrate should be removed by hydroblasting. Prior
ance inspectors were required to attend a training session in to application of the CFRP composite, the bent cap surface was to
which the details of the ‘‘Supplemental Specifications’’ 共UDOT be coated with a layer of structural adhesive of 2 mm minimum
1999兲 were discussed and demonstrated to the extend possible on thickness. The provisions for the surface preparation of the bent
scaled-down specimens for hands-on experience and establish- cap were more stringent than the columns, since the bond of the
ment of good practice. CFRP composite to the bent cap is critical for improved structural
performance 共Pantelides et al. 2001b兲.
Test Data for Strength and Modulus of Elasticity
Application Conditions
Required test data for mean and standard deviation of the strength
and modulus properties of the CFRP composite were to be for the The special provisions specified that concrete surfaces should be
same fabric type, areal weight, resin formulation, weight fraction, dry at the time of installation of the CFRP composite, and the
and cure conditions as those to be used in construction. The test hydroblasted surfaces should be dried thoroughly for a minimum
data included 50 tensile coupons from plates as well as ten NOL of three days prior to the installation of the CFRP composite. The
rings. ambient air temperature was to be at least 5°C, and the relative
humidity no greater than 80% at the time of application of the
CFRP composite. This provision necessitated the application of
Test Data on Environmental Aging
the CFRP composite in two summers of consecutive years due to
Environmental test data used in determining the environmental cold weather conditions. The two east bents shown in Fig. 1 共one
durability strength reduction factor 共␾兲 by the statistical method for the eastbound bridge and one for the westbound bridge兲 were
were to be for the same fabric type, areal weight, resin formula- retrofitted during the summer of 2000 and the two west bents in
tion, weight fraction, and cure conditions to be used in construc- the summer of 2001.
tion.
Material Application
Requirements for Detailed Thickness of Composite
A total of 3,300 m2 of a carbon fiber/epoxy resin composite sys-
Calculations
tem were used in the retrofit, which is the largest amount to be
The requirements for detailed thickness calculations considered used in a bridge retrofit project in the United States. The align-
the definition of the strength capacity as outlined previously. De- ment, orientation, and fitting of the carbon fibers in the special
tails of fabric impregnation, application, curing, drawing details provisions was to be in accordance with the detailed design draw-
of column and bent cap CFRP overlays, materials, aspects of the ings as submitted. Splices were to be staggered so that the mini-
repair procedure, material suppliers lists, product data sheets, ma- mum distance between splices would be 150 mm. The horizontal
terial safety data sheets, storage and handling requirements, and orientation of the carbon fibers should not deviate from a hori-
certification of compliance for all materials were required. These zontal line more than 15 mm over a length of 300 mm. This is
requirements are believed to constitute the minimum for standard similar to the allowable fiber misalignment of the ACI 440.2R-02
practice in FRP composite retrofit projects. draft document 共ACI 2002兲.

92 / JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004


Protection of Adjacent Surfaces end of construction; material preparation and placement se-
quence, the number of layers, and total thickness measurements;
The special provisions specified that during application of the
ambient air temperature and humidity readings at the beginning
CFRP composite, the contractor must protect adjacent surfaces
and end of each shift; sequence of curing operations and surface
not receiving the material from contamination.
temperature monitoring data; all material certificates, laboratory
test results, on-site test results, quality control observations, and
Curing significant directives for remedial action.
The special provisions specified that before applying a finish coat
the CFRP composite should be adequately cured. The degree of Manufacturer’s Representative
cure of the FRP composite was indicated by tests of core samples
according to ASTM D 4065 for glass transition temperature. The Under the special provisions, the contractor was required to pro-
work should be protected during the curing process from large cure the services of a representative of the FRP composite mate-
temperature variations, and the temperature should remain within rial supplier to inspect the surface preparation and witness appli-
the temperature range, as recommended by the manufacturer. If a cation and curing of the material. At completion of the
high temperature cure were to be used, the contractor was re- installation, the manufacturer’s representative provided the
quired to maintain the temperature of the entire curing surface project engineer with a Certificate of Compliance that the instal-
within 10°C of that recommended by the manufacturer, and lation, including the surface preparation and curing, was per-
monitor the surface temperature hourly during the curing process. formed in accordance with the supplier’s recommendations. Other
similar projects have allowed this activity but have not required it.
Finish Coat
Finish Coat Inspection
In the special provisions, the entire bridge bent was required to
receive a finish coating. However, the coating was not to be ap- The special provisions required a wet thickness gauge measure-
plied until after curing was adequate, all QC/QA testing was per- ment of coating. This measurement is important to ensure long-
formed, and any required repairs had been made. term durability of the finish and is used on most structural coating
applications.
Cooperation with Owner
The University of Utah in cooperation with the UDOT is cur- Sampling and Testing
rently performing long-term evaluation of the CFRP composite
Under the special provisions, the contractor manufactured two
retrofit of State Street bridge. In the special provisions, this was
types of FRP composite samples daily: 共1兲 six flat panels
stated explicitly with the clarification that part of this evaluation
300 mm⫻300 mm⫻two layers thick, and 共2兲 three cylinders of
would be occurring at the time of installation, which might entail
508 mm inside diameter, 610 mm tall, and a thickness of five
attachment of sensors and wiring. The contractor was informed
layers. The flat panels were used in producing tensile coupons and
that he would have to cooperate during this installation.
the cylinders were used in the production of NOL rings. The
testing for the coupons was performed at an independent labora-
tory while construction was on-going. The NOL rings were stored
Quality ControlÕQuality Assurance
for future long-term research. With the exception of the on-site
The ‘‘Supplemental Specifications’’ 共UDOT 1999兲 distinguished NOL ring cylinders, all other specimens have been used for the
between quality control and quality assurance. Specifying the ap- same purpose in other FRP composite retrofit projects. However,
propriate responsibilities of each is important in FRP composite the details of the special provisions of the ‘‘Supplemental Speci-
bridge retrofit and rehabilitation. Quality control was the respon- fications’’ 共UDOT 1999兲 prescribed a highly organized means of
sibility of the contractor, and required continuous monitoring. carrying out the sample preparation, collection, storage, identifi-
Quality assurance was the responsibility of the project engineer. cation, and testing of the samples by an independent testing labo-
The following items were required. ratory.
In addition, core samples were collected randomly by the in-
dependent testing laboratory, which were 13 mm in diameter and
Quality Control and Quality Assurance Inspectors extended to the thickness of the CFRP composite material ap-
Quality control inspectors provided continuous monitoring of the plied, for determination of the CFRP composite’s thickness, glass
work under the special provisions. They had full stop-work au- transition temperature according to ASTM D 4065, and the fiber
thority based on quality and technical merit. Quality assurance volume according to ASTM D 3171; 15 such samples were taken
inspectors made periodic visits to the site and determined whether from State Street bridge. The holes created by this sampling were
repairs were needed, and inspected the remedial actions. filled with a highly filled epoxy.

Daily Construction Log Remedial Actions and Repairs


The contractor maintained a daily log, to be submitted to the Upon notification by the project engineer regarding rejection of
project engineer, which included information on the structure lo- any portion of the work, the contractor was required to take re-
cation and number; the date and the name of the contractor’s shift medial action to correct the cause of the rejection. The contractor
supervisor, names of crew members and contractor’s QC inspec- was responsible for the cost of the remedial action and for coor-
tor; materials traceability and process records; fabrication, instal- dinating the performance of the remedial action with the overall
lation, and inspection data to prepare as-built documents at the project schedule.

JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004 / 93


Repair procedures were performed according to the manufac-
turer’s recommendations and the ‘‘Supplemental Specifications’’
共UDOT 1999兲. All repairs were subjected to the same application,
curing and quality control provisions of the original work. All
defects including bubbles, delaminations and fabric tears covering
more than 15 mm⫻15 mm (225 mm2 ) of the surface area were
repaired. The types of repairs allowed were 共1兲 injection with a
compatible epoxy in such a way as not to trap air in the void area;
this method when used alone was applicable for small bubbles
and for delaminations less than 150 mm in diameter
(17,700 mm2 ); 共2兲 application of additional layers of FRP com-
posite; this method when used alone was applicable to tears and
to deficiencies found during testing; the number of layers to be
added and the overlap was approved by the project engineer; and
共3兲 combination of epoxy injection and application of additional
layers; this method was applicable to large bubbles, voids and
delaminations greater than 150 mm in diameter (17,700 mm2 ).
The ACI 440.2R-02 document 共ACI 2002兲 contains similar de-
fault limits and repair method requirements.

Design Deficiencies Fig. 3. Carbon fiber reinforced polymer composite design number of
The ‘‘Supplemental Specifications’’ 共UDOT 1999兲 prescribed that layers (n), and construction number of layers (N), for columns, bent
in the event that concurrent field installation testing determines cap, and joint ankle wrap
that the properties of any given material lot are less than the
values in the contractor’s submittal data, the contractor shall retest
and/or submit a design revision for review and approval by the figures. It should be noted that the thickness of one layer of CFRP
project engineer. The adequacy of material properties was deter- composite used in the actual retrofit application was less than that
mined as follows: The special provisions specified that if the assumed in the design, which increased the number of layers ap-
thickness, glass transition temperature, tensile strength from cou- plied.
pons, or fiber volume of three of the five samples from each site During construction, a saturating machine was used, which
fell below prescribed values, assumed in the design by the con- assured uniformity of the CFRP composite properties. In order to
tractor, another set of five samples should be tested; if three of the maintain a relatively constant fiber volume the following proce-
additional five samples fell below the prescribed values this con-
stituted failure of the CFRP composite material at that bridge site
and was cause for rejection by the project engineer. The submittal
included engineering calculations and drawings to justify the
number of additional carbon composite wrap layers to be applied,
the orientation of the additional layers and the overlap length.

Implementation
A total of five bridges were rehabilitated in the period 2000–2001
on I-80 in Salt Lake City using the special provisions of the
‘‘Supplemental Specifications’’ 共UDOT 1999兲. Four of the bridges
had their columns strengthened with CFRP composites. A total of
73 columns were strengthened with CFRP composites with the
same carbon fiber/epoxy resin system as the State Street bridge
with a wet-layup under ambient temperature curing conditions;
the columns were circular with a diameter of 914 mm, and the
column height ranged from 7.00 to 7.93 m; the number of CFRP
layers varied along the column height. Only the State Street
bridge was seismically retrofitted and the retrofit included the four
bridge bents as shown in Figs. 1– 4. The goal of the seismic
rehabilitation on the I-80 State Street bridge was to improve the
displacement ductility of the bridge. The design for the CFRP
composite is given elsewhere 共Pantelides et al. 2001a兲. A carbon
fiber/epoxy system was implemented using a wet layup under
ambient temperature curing conditions. The required number of
layers is shown in Figs. 3 and 4 as lower case n. Using the
Fig. 4. Carbon fiber reinforced polymer composite design number of
concepts of strength capacity and environmental durability
layers (n), and construction number of layers (N), for column to
strength reduction factor, the number of layers used in construc-
bent cap U Strap
tion was determined as shown in capital letters N in the same

94 / JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004


Fig. 7. State Street bridge bent in Salt Lake City after being
Fig. 5. Carbon fiber reinforced polymer composite detail near seismically retrofitted with carbon fiber reinforced polymer compos-
footing ites

dure was used: a small area of dry carbon fiber was weighed, and The sequence of CFRP composite application was as follows:
was then saturated through the saturator and weighed again. From 共1兲 the first layers were placed on the columns (N⫽3) as shown
previous testing of tensile coupons the optimum ratio of the two in Fig. 3; 共2兲 the remaining layers were placed on the columns to
weight measurements was known; the opening of the saturator complete the required number N starting at the column bottom
was then adjusted to produce the desired weight ratio. This was and proceeding to the top; the CFRP composite was continued
done at the beginning of every working day in order to minimize underneath the soil all the way to the top of the footing, as shown
variations in the CFRP composite properties. Visual inspection of in Fig. 5, but was stopped short of the footing surface by 51 mm
the bridge had revealed that there was limited delamination of the to avoid any strength and stiffness increase; 共3兲 the flexural
concrete cover at the bent cap. However, there was no evidence of strengthening of the bent cap was accomplished by successively
electromechanical corrosion. For a CFRP composite retrofit de- applying the layers at the bottom of the beam as shown in Figs. 3
sign to be successful, it is very important that the delaminated and 4 共at the ends of the beam, near the columns the sheets were
concrete be removed, and be replaced by shotcrete or equivalent terminated 51 mm from the end of the previous sheet, to avoid
material at the substrate to achieve a satisfactory force transfer stress concentrations from the retrofit as shown in Fig. 4兲; this is
from sound concrete to the CFRP overlays. It should be noted that less than the ACI 440.2R-02 report recommendations for allow-
before any application of CFRP composites, new concrete had to able termination points of 150 mm 共ACI 2002兲; 共4兲 the diagonal
be cast as shown in Fig. 4, to form a suitable surface for the sheets were applied over the bent cap to column joints in the
vertical overlay sheets going over the bent cap and onto the col- ankle wrap configuration at ⫾45 degrees from the horizontal, as
umn to form the U strap. The straps were brought down 305 mm shown in Figs. 3 and 6; 共5兲 the four-sided wraps were then ap-
below the bottom of the bent cap before they were clamped, to plied on the bent cap as shown in Fig. 3 at the various thicknesses
avoid stress concentration effects, as shown in Fig. 4. The gap left N, which varied from N⫽4 to N⫽7; 共6兲 the U strap vertical
between the strap, the bent cap and the column was filled with
structural foam.

Fig. 8. State Street bridge detail of column-bent cap joint retrofitted


Fig. 6. Carbon fiber reinforced polymer composite detail near bent with carbon fiber reinforced polymer composites after finish coating
cap-column joint was applied

JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004 / 95


sheets were applied as shown in Fig. 4 over the bent cap and American Concrete Institute 共ACI兲. 共2000兲. ‘‘State-of-the-art report on
down to the column, and subsequently the circular clamping fiber-reinforced plastic reinforcement for concrete structures.’’ Rep.,
CFRP sheets were applied over the U strap sheets as shown in ACI Committee 440, Detroit.
Fig. 7; and 共7兲 the protective coating was applied over the CFRP. American Concrete Institute 共ACI兲. 共2002兲. ‘‘Guide for the design and
A detail of the bent cap–column joint after the coating and struc- construction of externally bonded FRP systems for stengthening con-
tural foam were applied is shown in Fig. 8. crete structures.’’ Rep. ACI 440.2R-02, Farmington Hills, Mich.
Two bents were overlaid with CFRP composite simulta- Bakht, B., Al-Bazi, G., Banthia, N., Cheung, M., Erki, M. A., Faoro, M.,
neously. The total time required for the retrofit of all four bents Machida, A., Mufti, A. A., Neale, K. W., and Tadros, G. 共2000兲. ‘‘Ca-
with the CFRP composite was approximately three months. The nadian bridge design code provisions for fiber-reinforced structures.’’
J. Compos. Constr., 4共1兲, 3–15.
four bridge bents required a total of 3,300 m2 of carbon fiber
Clarke, J. L., O’Regan, D. P., and Thirugnanendran, C. 共1996兲. ‘‘EURO-
fabric, 1,900 L of epoxy resin, 400 L of adhesive gel, and 500 L
CRETE project: Modification of design rules to incorporate non-
of finish coating. Approximately 110 strain gauges were installed
ferrous reinforcement.’’ EUROCRETE Project Rep., Sir William Hal-
both in interior layers as well as the exterior CFRP composite
crow & Partners, London.
layer in both the columns and the bent cap for long-term health Gamble, W. L., and Hawkins, N. M. 共1996兲. ‘‘Seismic retrofitting of
monitoring of the FRP composite, as shown in Fig. 5. bridge pier columns.’’ Proc., Structures Congress XIV, ASCE, Reston,
The FRP composite flat coupon tests during bridge-site con- Va., 1, 16 –23.
struction showed that the FRP composite met the specifications; Gergely, I., Pantelides, C. P., Nuismer, R. J., and Reaveley, L. D. 共1998兲.
in addition, no other design deficiencies were found in terms of ‘‘Bridge pier retrofit using fiber-reinforced plastic composites.’’ J.
the FRP composite material. Remedial actions involved epoxy Compos. Constr., 2共4兲, 165–174.
injection of voids; no other repairs were necessary such as addi- International Conference of Building Officials Evaluation Service
tional FRP composite layers. 共ICBO兲. 共2001兲. ‘‘Acceptance criteria for concrete and reinforced and
unreinforced masonry strengthening using fiber-reinforced polymer
共FRP兲 composite systems.’’ ICBO Rep. No. AC125, Whittier, Calif.
Conclusions Japan Society of Civil Engineers 共JSCE兲. 共1997兲. ‘‘Recommendations for
design and construction of concrete structures using continuous fiber
The special provisions developed for the seismic rehabilitation of reinforcing materials.’’ Concrete Engineering Series 23, A. Machida,
a reinforced concrete bridge are described, which included speci- ed., Tokyo, Japan.
fications, construction and installation requirements, and quality Katsuki, F., and Uomoto, T. 共1995兲. ‘‘Prediction of deterioration of FRP
control and quality assurance guidelines. Several requirements of rods due to alkali attack.’’ Proc., 2nd Int. Symp. on Nonmetallic (FRP)
the specifications were implemented for the first time in highway Reinforcement for Concrete Structures (FRPRCS-2), E&FN Spon,
bridge rehabilitation. These include 共1兲 utilization of ‘‘strength London, 82– 89.
capacity’’ as the structural strength requirement for FRP jackets; Pantelides, C. P., Alameddine, F., Sardo, T., Okahashi, Y., and Moran, D.
共2兲 use of an environmental durability strength reduction factor to 共2001a兲. ‘‘Seismic rehabilitation of State Street bridge.’’ Proc., 9th Int.
account for degradation of the CFRP composite; 共3兲 fabrication of Conf. and Exhibition, Structural Faults and Repair, Engineering
NOL rings during bridge site construction; 共4兲 cooperation of the Technics Press, Edinburgh, U.K.
contractor with the owner in the performance of long-term health Pantelides, C. P., Duffin, J. B., Ward, J., Delahunty, C., and Reaveley,
monitoring of the CFRP composite, during the CFRP composite L. D. 共2002兲. ‘‘In-situ tests at South Temple bridge on Interstate 15.’’
application and while the bridge was in service; 共5兲 requirement Proc., 7th U.S. National Conference on Earthquake Engineering,
that the contractor procure the services of a manufacturer’s rep- Earthquake Engineering Research Institute, EL Cerrito, Calif.
resentative of the CFRP composite material; 共6兲 thickness gauge Pantelides, C. P., Gergely, J., and Reaveley, L. D. 共2001b兲. ‘‘In-situ veri-
measurement for inspection of the finish coat; and 共7兲 a highly fication of rehabilitation and repair of reinforced concrete bridge bents
organized means of carrying out the sample preparation, collec- under simulated seismic loads.’’ Earthquake Spectra, 17共3兲, 507–530.
tion, storage, identification, and testing of the CFRP composite Pantelides, C. P., Gergely, J., Reaveley, L. D., and Volnyy, V. A. 共1999兲.
‘‘Retrofit of RC bridge pier with CFRP advanced composites.’’ J.
test samples. The seismic retrofit of the I-80 State Street Bridge,
Struct. Eng., 125共10兲, 1094 –1099.
and the strengthening of the columns of four other bridges with
Priestley, M. J. N., Seible, F., and Calvi, G. M. 共1996兲. Seismic design
CFRP composites, using the supplemental specifications, were
and retrofit of bridges, Wiley, New York.
implemented successfully and involved epoxy injection of voids Seible, F., Hegemier, G., Policelli, F., Karbhari, V., Randolph, R., and
as the only remedial action. Belknap, F. 共1995兲. ‘‘Earthquake retrofit of bridge columns with con-
tinuous carbon fiber jacket.’’ Advanced Composite Technology Trans-
fer Consortium/Bridge Infrastructure Renewal, Rep. No. ACTT-95/07,
Acknowledgments
DARPA, Univ. of California at San Diego, La Jolla, Calif., I–IV.
Seible, F., Priestley, M. J. N., Hegemier, G., and Innamorato, D. 共1997兲.
The project was funded by the Federal Highway Administration
‘‘Seismic retrofit of RC columns with continuous carbon fiber jack-
and the Utah Department of Transportation. The writers would
ets.’’ J. Compos. Constr., 1共2兲, 52– 62.
like to thank Mr. Sam Musser and Mr. Doug Anderson of the
Tannous, F. E. 共1997兲. ‘‘Durability of non-metallic reinforcing bars and
Research Division, and Mr. Michael Fazio, Project Engineer, of prestressing tendons.’’ PhD dissertation, Dept. of Civil Engineering
the Utah Department of Transportation, and Mr. Allen Gerber of and Engineering Mechanics, Univ. of Arizona, Tucson, Ariz.
Gerber Construction, Inc. Toutanji, H. A., and El-Korchi, T. 共1999兲. ‘‘Tensile durability of cement-
based FRP composite wrapped specimens.’’ J. Compos. Constr., 3共1兲,
References 38 – 45.
Utah Department of Transportation 共UDOT兲. 共1999兲. ‘‘Supplemental
American Concrete Institute 共ACI兲. 共1996兲. ‘‘State-of-the-art report on specifications—Special provisions.’’ Rep., I-80 Bridge Rehabilitation,
fiber reinforced plastic reinforcement for concrete structures.’’ Rep., Project No. IM-80-3(126)123, Salt Lake City, Utah, Section 525S,
ACI Committee 440, Detroit. 121–143, Section 526S.

96 / JOURNAL OF COMPOSITES FOR CONSTRUCTION © ASCE / JANUARY/FEBRUARY 2004

View publication stats

You might also like