Professional Documents
Culture Documents
net/publication/308966715
CITATIONS READS
0 190
2 authors:
Some of the authors of this publication are also working on these related projects:
Applications of hybrid synthetic fibres in high strength self compacting concrete View project
All content following this page was uploaded by Mahbube Subhani on 10 October 2016.
ABSTRACT: Carbon fiber reinforced polymer (CFRP) is found to be an effective material for the retrofitting
of both reinforced concrete (RC) and steel structures. However, retrofitting such structures using CFRP alone
is shown to exhibit a premature failure due to early de-bonding of the CFRP laminates from the hosting sur-
faces. On the other hand, steel plates are also used separately for the steel and RC structures. However, steel
plates usually add to the self-weight of the structures whereas CFRP is known for its high strength to weight
ratio. In the present study, the advantages of both steel plates and CFRP are used to form a hybrid retrofitting
system that is able to withstand the existing load to prevent the failure of the structures. In order to improve
the retrofitting efficiency of steel-concrete composite structures, an experimental investigation is carried out to
examine the use and effectiveness of a CFRP-steel hybrid retrofitting system.
2
74 mm and height of 160 mm) composite with a material properties of the steel beam and stiffener
concrete deck slab of 500 mm width by 100 mm plates. Concrete slabs were fabricated from seven
thickness. The composite beams had a clear span of batches with same mix ratio. Wire mesh (N10 bars
1800 mm. In the first group, three beams were with 100 mm spacing in both direction) was used as
strengthened with steel plates attached to the tension longitudinal and transverse reinforcement for the
flange of I beams with three different patterns: dis- concrete slab. A maximum coarse aggregate size of
continuous welding, U-shape welding at both ends, 9.5 mm was used due to the small slab thickness.
and bonding with adhesive together with U-shape The properties of concrete related to each beam are
welding at both ends. In the second group, two given in Table 2 which were obtained from the
beams were strengthened either by bonding of two cylindrical test based on Australian Standard (AS
layers of CFRP wet lay-up sheets to the tension 1012). A total of 18 M8 grade 8.8 bolts (spacing =
flange of an I beam or by bonding of CFRP sheets 100 mm) were welded to the top flange of the steel
(two layers) to the tension flange together with beam in one row to provide shear connection
wrapping around the part of the web on both sides of between the steel beam and concrete. The
the I beam. In the same group, two beams were mechanical properties of the shear connectors are as
strengthened with the similar patterns except for the listed in Table 3. The cross-section of composite
inclusion of artificial debonding (50 mm × flange beams can be seen in Figure 1.
width) between the bottom of the steel flange and the
first layer of CFRP sheet at mid-span. One beam was Table 1. Mechanical properties of steel beam and stiffener.
used as an unstrengthen beam for comparison. Test Yield strength Tensile modulus of Ultimate strength
results showed that there was no growth of interme- (MPa) elasticity (GPa) (MPa)
diate debonding before the yielding of the lower 320 210 440
flange for all CFRP strengthened beams. The beams
with pre-debonding showed lower flexural capacity Table 2. Mechanical properties of concrete for composite
than those with full bonding after yielding. In the beams.
case of steel plate bonding, no difference in yield Beam ID W/C ratio Mean compressive strength (MPa)
load was observed between three patterns except a 1 0.38 60.4
negligible difference in the elastic stiffness. 2 0.38 62.3
Based on the literature review and according to 3 0.38 66.3
the authors’ best knowledge, no studies considered 4 0.38 54.5
strengthening the tension face of concrete slabs to- 5 0.38 50.9
gether with the bottom flange of the steel beam in 6 0.38 54.4
composite girder systems. Considering this research 7 0.38 52.5
gap, the current study aims to investigate the effec-
tiveness of six different strengthening schemes for Table 3. Mechanical properties of shear connector.
scaled down steel-concrete composite bridge girders Min. tensile strength (MPa) Min. yield stress (MPa)
under static load, employing strengthening of the 830 660
concrete slab soffit only, the steel bottom flange only
and the steel beam flange together with the concrete
slab soffit using CFRP only, steel plate only and a 2.2 Strengthening scheme
combination of both. After curing of concrete for 28 days in humid air
(covered with wet hessian), sand blasting of the ten-
sion flange of the steel beams was conducted. Sand
2 EXPERIMENTAL PROGRAM blasting of the concrete slab soffits was also con-
ducted for bonding of steel plate/CFRP to the con-
2.1 Fabrication of specimen
crete. Beam 1 was used as a control beam which was
A total of seven composite beams were fabricated not strengthened with any technique. Beam 2 was
consisting of a 2 m long, 500 mm wide by 50 mm strengthened with the application of one layer of
thick concrete slab composite with 2.2 m long high tensile CFRP sheet with the dimension of 1 m
150UB18.0 steel beam (overall depth of 155 mm, length, 50 mm width and 0.17 mm thickness on both
flange width of 75 mm, flange thickness of 9.5 mm sides of the concrete slab soffit (middle of each sof-
and web thickness of 6.5 mm). Ten mm thick steel fit) by two part-epoxy resin primer and epoxy resin
plates were welded to the both ends of the steel saturant. Beam 3 was strengthened with one layer of
beam covering the full cross-section (155 mm height CFRP sheet (the same dimension as used for the
and 75 mm width). Two more steel plates with the concrete slab) bonded to the steel beam tension
same thickness (136 mm height and 34.5 mm width) flange. In the case of beams 4, 5 and 7, a steel plate
were welded on both sides of the steel web at 95 mm with 1 m length, 50 mm width and 10 mm thickness
clear distance from each end of steel beam in order was welded to the steel bottom flange. The only dif-
to stiffen the support regions. Table 1 provides the ference among these three beams was in the concrete
strengthening. In beam 4, no concrete retrofitting includes Beam 4, 5 and 7 that had steel plates
was applied. Beam 5 had steel plates (1 m length, 50 attached to the soffit of the steel beam.
mm width and 10 mm thickness) bonded to both Beam 1 yielded at about 172 kN. The large drop of
sides of the concrete bottom surface with Master- load after reaching maximum load of 216.7 kN
Brace 1444 epoxy binder (two parts). Both sides of indicates initiation of shear connector failures at
the concrete bottom surface in Beam 7 were retrofit- both ends of the composite beams which can also be
ted with CFRP sheets. In case of Beam 6, both steel seen at Figure 4(b). The beam was unloaded at about
and concrete was strengthened with one layer of 60 mm deflection after cracks extended to the
CFRP sheet with the same dimension used for Beam concrete top fibre. In addition to the major flexural
2, 3 and 7. Some of these repairing techniques are crack at mid-span there were several minor cracks.
shown in Appendix. Before bonding of CFRP sheets Yield loads for Beams 2, 3 and 6 was 175 kN,
to concrete, a primer layer (MasterBrace P 3500) respectively, whereas maximum loads for the same
was applied to the concrete or steel surface where were 216.1, 215.7 and 219.3kN, respectively. For
CFRP needs to be bonded. After curing of primer for beam 2, the CFRP on the concrete started to debond
24 hours, CFRP sheets were applied with epoxy sat- after the load reached the maximum value with
urant (MasterBrace 4500). The mechanical proper- consecutive load drops which represent extension of
ties of CFRP and steel plate are provided in Table 4. the debonded zone (Figure 5).
The CFRP sheets bonded to concrete and steel beam
and steel plates bonded to concrete were cured for at 10 10
least two days before testing. 100 100 100 100
4
representing gradual failure of the shear connectors.
Beam 5
Finally, the concrete crushed at about 68 mm
Beam 4 deflection with continuous decrease in load carrying
Beam 7
capacity. Figure 8 shows the mode of failure of beam
4. Beam 5, showed non-linearity at 175 kN like
beam 4. However, the non-linearity was not due to
Beam 6 yielding of steel; a large slip in the shear connector
Beam 1 was the contributing factor for the non-linearity. The
Beam 2 steel plate bonded to the concrete debonded very
Beam 3
early in the loading regime at about 50 kN when the
first flexural crack appeared. After reaching a
maximum load of 246.2 kN, there are several load
drops representing shear connector failures (Figure
9).
6
5 REFERENCES
Beam 4 Beam 5
Beam 6 Beam 7
8
View publication stats