You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/308966715

CFRP-steel hybrid retrofitting of steel-concrete composite structures

Chapter · January 2016

CITATIONS READS

0 190

2 authors:

Mahbube Subhani Muhammad Ikramul Kabir


Deakin University Deakin University
31 PUBLICATIONS   91 CITATIONS    11 PUBLICATIONS   38 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Condition assessment of wooden poles View project

Applications of hybrid synthetic fibres in high strength self compacting concrete View project

All content following this page was uploaded by Mahbube Subhani on 10 October 2016.

The user has requested enhancement of the downloaded file.


CFRP-steel hybrid retrofitting of steel-concrete composite structures
M. Subhani, R. Al-Ameri and M.I. Kabir
School of Engineering, Deakin University, Victoria, Australia

ABSTRACT: Carbon fiber reinforced polymer (CFRP) is found to be an effective material for the retrofitting
of both reinforced concrete (RC) and steel structures. However, retrofitting such structures using CFRP alone
is shown to exhibit a premature failure due to early de-bonding of the CFRP laminates from the hosting sur-
faces. On the other hand, steel plates are also used separately for the steel and RC structures. However, steel
plates usually add to the self-weight of the structures whereas CFRP is known for its high strength to weight
ratio. In the present study, the advantages of both steel plates and CFRP are used to form a hybrid retrofitting
system that is able to withstand the existing load to prevent the failure of the structures. In order to improve
the retrofitting efficiency of steel-concrete composite structures, an experimental investigation is carried out to
examine the use and effectiveness of a CFRP-steel hybrid retrofitting system.

1 INTRODUCTION need to be upgraded. FRP composites can be a


suitable option to upgrade and repair steel-conrete
1.1 Preamble composite girders due to their light weight, corrosion
Application of Fibre Reinforced Polymer (FRP) resistance and easy application. Among available
composites has becoming widespread to strengthen FRPs, Glass Fibre Reinforced Polymer (GFRP) is
or repair deficient reinforced concrete (RC) members inexpensive and easily available, and has been used
where the use of conventional techniques such as in concrete and masonry ructures. However, its low
epoxy-bonded steel plates, steel-jacketting, etc. can modulus of elasticity makes it ineffective for repair
be problemetic. Improvement of strength by bonding of steel girders. CFRP, on the other hand, has a
FRP to RC members can significantly improve the higher modulus of elasticity than GFRP and can be
strength without excessive change of stiffness (Bakis applied to the tension face of steel girder to improve
et al., 2002). Flexural strengthening of RC beams is the flexural performance (Tavakkolizadeh and
conducted by applying FRP to beam soffits by epoxy Saadatmanesh, 2003b).
based adhesive. RC slabs can also be retrofitted with
FRP. In the case of one way, simply-supported slabs,
FRP is bonded to the soffit with the alignment of 1.2 Literature review
fibre to the required directions whereas for two way Mertz and Gillespie (1996) strengthened small scale
slabs, FRP is bonded in both directions (Heiza et al., and large scale steel beams with CFRP plates. Six
2014). mm thick CFRP plates were applied to the tension
Although application of FRP in reinforced flanges for the strengthening of small scale
concrete structures has proven its suitability, specimens (W8×10 rolled beams of 1.52 m length).
research on the retrofitting of steel-concrete Beams were tested with four-point bending and
composite structures with FRP composites is still showed more than 50% increase in flexural strength
limited. Steel-concrete composite beams are used as before the termination of tests due to buckling of the
main structural elements in flexure in the top cover plate. Two full scale beams (0.61 m deep
construction of bridges and buildings. The I-beams, of 6.4 m length) were taken from a
deterioration of steel-concrete composite girders in demolished bridge which had severely corroded
bridges can be caused by corrosion of steel beams bottom flanges with about 40% loss of tension
due to environmental attack and poor maintenance flange. These beams were strengthed with 6 mm
(Al-Saidy et al., 2004) and require repair with thick plates bonded to both faces of the bottom
suitable techniques. In addition, to meet the flange. A signifcant increase in strength was
increased traffic density, the strength capacity may reported.
Sen et al. (2001) investigated the suitability of CFRP 12.7 mm diameter and 50.8mm long were used to
epoxy laminates for the repair of steel composite provide shear connection between steel and concrete.
bridge members. They used six specimens consisting The length of each beam was 3.4 m (both steel beam
of 6.1 m long W8×24 wide flange steel beam and concrete slab) with 3.05 m clear span. Among
composite with a 0.114 m thick by 0.71 m wide the six beams, two steel beams were used as
reinforced concrete slab. The composite beams were undamaged controls, one was a control with 50%
initially loaded by four-point bending to yielding of damage, and the remaining three were repaired with
tension flanges of steel beams and then repaired with different CFRP dimensions and placements
3.65 m lengths of 2 mm or 5 mm thick CFRP plates. depending on the degree of damage (50% and 75%).
They reported 21 and 52% strength gains of 310 Two beams with 50% damage were repaired with
MPa (yield strength) steel beams for 2 and 5 mm CFRP on the steel web and CFRP on both the web
thick CFRP, respectively. The corresponding and flange whereas the beam with 75% damage was
strength gains for 370 MPa (yield strength) steel repaired with CFRP on the web.
beam were 9 and 32%, respectively. Al-Saidy et al. (2008) conducted a parametric
Miller et al. (2001) applied CFRP strengthening study on the behavior of short span composite bridge
in the field to upgrade a steel girder in a slab-on- girders strengthened with CFRP plates following a
girder bridge in Delaware. In order to retrofit the successful experimental study by the authors on
girder, 5.3 mm thick CFRP plate was bonded to the strengthening steel–concrete composite girders using
tension flange. Diagnostic load tests were conducted carbon fiber reinforced polymer (CFRP) plates. The
before and after strengthening and strain comparison parametric study investigated the influence of some
on the inner face of the tension flange revealed that of the important parameters, namely, the concrete
an 11.6% strain reduction (11.6% increase in compressive strength, the yield strength of steel, the
flexural stiffness) could be achieved due to the CFRP plate stiffness, the CFRP plate thickness, the
strengthening technique. ultimate strain of the CFRP plate, and the steel beam
Tavakkholizadeh and Saadatmanesh (2003a) bottom flange area on the behavior of the section. In
investigated the behaviour of damaged steel-concrete addition, they investigated the effect of girder dam-
composite beams repaired with CFRP sheets. A total age on the overall load distribution of a typical short
of three large-scale composite girders were fabricat- span composite bridge for various load cases.
ed of W355×13.6 A36 steel sections and 75-mm- Fam et al. (2009) conducted research on the
thick by 910-mm-wide concrete slabs. Specimens strengthening of intact steel–concrete composite
with 25, 50, and 100% loss of the cross-sectional ar- girders and the repair of notched steel beams apply-
ea of the tension flange of steel beams were repaired ing CFRP materials with Young’s modulus varying
with one, three, and five layers of CFRP sheet, re- from 150 to 400 GPa. They tested three large-scale
spectively. The ultimate load-carrying capacity could (6100mm long) steel–concrete girders scaled down
be restored to 20, 80 and 10% for the beams with 25, (4:1) with accurate proportional dimensions from a
50 and 100% damage, respectively. Also, on a dif- bridge. The cross section of the girders consisted of
ferent study, Tavakkholizadeh and Saadatmanesh W250×25 hot-rolled steel sections with a 65mm
(2003b) reported results of a study on the behaviour thick and 500 mm wide concrete slab. Two compo-
of steel-concrete composie girders strengthened with site beams were strengthened with CFRP sheets of
CFRP sheets under static loading using pultruded two types. In addition, 15 small-scale (1000mm
CFRP sheets on the girders with the same long) W100×19 sections with various levels and
geometrical properties of their previous study. configurations of loss (50% and 100% loss) in the
Constant 1.27 mm thick pultruded CFRP sheets but tension flange, induced by notching, were repaired
with varying numbers of layers (1, 3 and 5) were with CFRP sheets. The increase in flexural strength
applied to retrofit the steel beams. Then the beams of the strengthened composite girders was reported
were tested by four-point bending under monotonic as 51%. Complete cutting of tension flanges in W-
load. Experimental results showed an increase in sections reduced the ultimate capacity of the beams
load-carrying capacity by 44, 51 and 76% for one, by 62%, whereas there was negligible reduction due
three and five layers of CFRP sheets, respectively. to 50% loss of the flanges. CFRP repair schemes re-
Al-Saidy et al. (2004) investigated the behaviour stored the strength up to 79% for the former whereas
of damaged steel composite beams after being insignificant gains were observed for the latter.
repaired with CFRP plates. They induced damage to Sallam et al. (2010) studied the effect of pre-
the steel beams by removing part of the bottom intermediate separation on the behaviour of CFRP
flange and varied the degree of damage between no flexural strengthening of steel-concrete beams either
damage and 75% loss of the bottom flange to by CFRP sheet bonding to steel beams or by weld-
simulate the effect of corrosion of steel. Six steel- ed/bonded steel plate to steel beams. They fabricated
concrete composite beams were fabricated consisting eight steel-concrete composite beams consisting of a
of W8×15 grade A572 structural steel and concrete standard steel I beam of size 16 (web thickness of
slab of 812 mm wide by 76 mm thick. Shear studs of 6.3 mm, flange thickness of 9.5 mm, flange width of

2
74 mm and height of 160 mm) composite with a material properties of the steel beam and stiffener
concrete deck slab of 500 mm width by 100 mm plates. Concrete slabs were fabricated from seven
thickness. The composite beams had a clear span of batches with same mix ratio. Wire mesh (N10 bars
1800 mm. In the first group, three beams were with 100 mm spacing in both direction) was used as
strengthened with steel plates attached to the tension longitudinal and transverse reinforcement for the
flange of I beams with three different patterns: dis- concrete slab. A maximum coarse aggregate size of
continuous welding, U-shape welding at both ends, 9.5 mm was used due to the small slab thickness.
and bonding with adhesive together with U-shape The properties of concrete related to each beam are
welding at both ends. In the second group, two given in Table 2 which were obtained from the
beams were strengthened either by bonding of two cylindrical test based on Australian Standard (AS
layers of CFRP wet lay-up sheets to the tension 1012). A total of 18 M8 grade 8.8 bolts (spacing =
flange of an I beam or by bonding of CFRP sheets 100 mm) were welded to the top flange of the steel
(two layers) to the tension flange together with beam in one row to provide shear connection
wrapping around the part of the web on both sides of between the steel beam and concrete. The
the I beam. In the same group, two beams were mechanical properties of the shear connectors are as
strengthened with the similar patterns except for the listed in Table 3. The cross-section of composite
inclusion of artificial debonding (50 mm × flange beams can be seen in Figure 1.
width) between the bottom of the steel flange and the
first layer of CFRP sheet at mid-span. One beam was Table 1. Mechanical properties of steel beam and stiffener.
used as an unstrengthen beam for comparison. Test Yield strength Tensile modulus of Ultimate strength
results showed that there was no growth of interme- (MPa) elasticity (GPa) (MPa)
diate debonding before the yielding of the lower 320 210 440
flange for all CFRP strengthened beams. The beams
with pre-debonding showed lower flexural capacity Table 2. Mechanical properties of concrete for composite
than those with full bonding after yielding. In the beams.
case of steel plate bonding, no difference in yield Beam ID W/C ratio Mean compressive strength (MPa)
load was observed between three patterns except a 1 0.38 60.4
negligible difference in the elastic stiffness. 2 0.38 62.3
Based on the literature review and according to 3 0.38 66.3
the authors’ best knowledge, no studies considered 4 0.38 54.5
strengthening the tension face of concrete slabs to- 5 0.38 50.9
gether with the bottom flange of the steel beam in 6 0.38 54.4
composite girder systems. Considering this research 7 0.38 52.5
gap, the current study aims to investigate the effec-
tiveness of six different strengthening schemes for Table 3. Mechanical properties of shear connector.
scaled down steel-concrete composite bridge girders Min. tensile strength (MPa) Min. yield stress (MPa)
under static load, employing strengthening of the 830 660
concrete slab soffit only, the steel bottom flange only
and the steel beam flange together with the concrete
slab soffit using CFRP only, steel plate only and a 2.2 Strengthening scheme
combination of both. After curing of concrete for 28 days in humid air
(covered with wet hessian), sand blasting of the ten-
sion flange of the steel beams was conducted. Sand
2 EXPERIMENTAL PROGRAM blasting of the concrete slab soffits was also con-
ducted for bonding of steel plate/CFRP to the con-
2.1 Fabrication of specimen
crete. Beam 1 was used as a control beam which was
A total of seven composite beams were fabricated not strengthened with any technique. Beam 2 was
consisting of a 2 m long, 500 mm wide by 50 mm strengthened with the application of one layer of
thick concrete slab composite with 2.2 m long high tensile CFRP sheet with the dimension of 1 m
150UB18.0 steel beam (overall depth of 155 mm, length, 50 mm width and 0.17 mm thickness on both
flange width of 75 mm, flange thickness of 9.5 mm sides of the concrete slab soffit (middle of each sof-
and web thickness of 6.5 mm). Ten mm thick steel fit) by two part-epoxy resin primer and epoxy resin
plates were welded to the both ends of the steel saturant. Beam 3 was strengthened with one layer of
beam covering the full cross-section (155 mm height CFRP sheet (the same dimension as used for the
and 75 mm width). Two more steel plates with the concrete slab) bonded to the steel beam tension
same thickness (136 mm height and 34.5 mm width) flange. In the case of beams 4, 5 and 7, a steel plate
were welded on both sides of the steel web at 95 mm with 1 m length, 50 mm width and 10 mm thickness
clear distance from each end of steel beam in order was welded to the steel bottom flange. The only dif-
to stiffen the support regions. Table 1 provides the ference among these three beams was in the concrete
strengthening. In beam 4, no concrete retrofitting includes Beam 4, 5 and 7 that had steel plates
was applied. Beam 5 had steel plates (1 m length, 50 attached to the soffit of the steel beam.
mm width and 10 mm thickness) bonded to both Beam 1 yielded at about 172 kN. The large drop of
sides of the concrete bottom surface with Master- load after reaching maximum load of 216.7 kN
Brace 1444 epoxy binder (two parts). Both sides of indicates initiation of shear connector failures at
the concrete bottom surface in Beam 7 were retrofit- both ends of the composite beams which can also be
ted with CFRP sheets. In case of Beam 6, both steel seen at Figure 4(b). The beam was unloaded at about
and concrete was strengthened with one layer of 60 mm deflection after cracks extended to the
CFRP sheet with the same dimension used for Beam concrete top fibre. In addition to the major flexural
2, 3 and 7. Some of these repairing techniques are crack at mid-span there were several minor cracks.
shown in Appendix. Before bonding of CFRP sheets Yield loads for Beams 2, 3 and 6 was 175 kN,
to concrete, a primer layer (MasterBrace P 3500) respectively, whereas maximum loads for the same
was applied to the concrete or steel surface where were 216.1, 215.7 and 219.3kN, respectively. For
CFRP needs to be bonded. After curing of primer for beam 2, the CFRP on the concrete started to debond
24 hours, CFRP sheets were applied with epoxy sat- after the load reached the maximum value with
urant (MasterBrace 4500). The mechanical proper- consecutive load drops which represent extension of
ties of CFRP and steel plate are provided in Table 4. the debonded zone (Figure 5).
The CFRP sheets bonded to concrete and steel beam
and steel plates bonded to concrete were cured for at 10 10
least two days before testing. 100 100 100 100

Table 4. Mechanical properties of CFRP and steel plate.


Material CFRP Steel 40 mm
(Mbrace CF plate 10
230/4900)
Thickness (mm) 0.17 10
Yield strength (MPa) N/A 320
Ultimate tensile strength 4900 440 N10 steel mesh
(MPa)
Tensile modulus of elasticity 230 210
(GPa)
Steel beam: 150UB18
500
2.3 Test setup and instrumentation All dimensions are in mm
Figure 1. Cross-section of the composite beam (not to scale).
All beams were tested under three point bending
with load control at a speed of 0.05 kN/sec up to 60
kN followed by displacement control at a speed of
0.6 mm/min until the beam failed. The test set-up of
the beam is shown in Figure 2. The mid-span deflec-
tion was also measured using a 100 mm capacity
LASER.

3 RESULT AND DISCUSSION


3.1 Load vs mid-span deflection and failure mode
Figure 2. Test set up of three point bending loading.
Load vs. mid-span deflection curves were plotted
for all composite beams in order to compare the Unlike Beam 1, Beam 2 showed progressive flexural
behaviour of retrofitted beams (Beams 2 – 7) to that cracks from mid-span to both ends of the CFRP
of the control beam (Beam 1). reinforcement because of debonding propagation in
From the load-deflection plots (Figure 3), it is the concrete layer.
clearly visible that, when comparing against Beam 1, Although a gap between the steel beam and
Beams 2, 3 and 6 behaved almost similarly whereas concrete at both ends and a longitudinal crack along
Beam 4, 5 and 7 have higher values in terms of yield the shear connector on the top of the concrete slab
load and maximum load. Thus, the analysis of the was seen in Beam 2, there was no indication of
load-deflection curve can be discussed in two failure in the shear connector unlike Beam 1. CFRP
groups. Group A - consisted of Beam 2, 3 and 6 on both sides completely debonded from the same
which are related to CFRP, and Group B which end while the top concrete fibre was crushed.

4
representing gradual failure of the shear connectors.
Beam 5
Finally, the concrete crushed at about 68 mm
Beam 4 deflection with continuous decrease in load carrying
Beam 7
capacity. Figure 8 shows the mode of failure of beam
4. Beam 5, showed non-linearity at 175 kN like
beam 4. However, the non-linearity was not due to
Beam 6 yielding of steel; a large slip in the shear connector
Beam 1 was the contributing factor for the non-linearity. The
Beam 2 steel plate bonded to the concrete debonded very
Beam 3
early in the loading regime at about 50 kN when the
first flexural crack appeared. After reaching a
maximum load of 246.2 kN, there are several load
drops representing shear connector failures (Figure
9).

Figure 3. Load-deflection plots of all beams.

Beam 3 showed slightly higher post-elastic sfiffness (a)


than beam 1, 2 and 6 after yielding of the steel beam
due to the contribution of CFRP bonded to the steel
beam.. Then, at about 25 mm deflection, it showed a
small drop of load indicating initiation of debonding
followed by a large drop to 175 kN due to separation
of the connection between the concrete and steel
beam at both ends. The CFRP debonded completely (b)
after a slight increase in load to 180 kN at a
deflection level of 33 mm. The beam failed by
crushing of concrete at a deflection close to 60 mm
(Figure 6). In beam 6, after steel yielding at 175 kN,
the CFRP debonded from the steel beam at 210 kN
when the deflection was only 18 mm. A small drop
of load was observed at this point of loading. A large
drop in load to about 170 kN after maximum load
indicates failure in the shear connector (at about 40 Figure 4: Failure modes of Beam 1: (a) cracks in concrete and
mm deflection). Then the load slightly increased (b) separation of shear connection
followed by few small drops indicating CFRP
debonding from concrete. The beam failed by
crushing of concrete as soon as the CFRP debonded
from the concrete (Figure 7). It can be noted that the
CFRP failed in the primer layer from the steel beam,
the steel surface was complete smooth and clean
without any epoxy attached to it. Whereas, theCFRP
debonded from the concrete had some concrete
debris as well as epoxy attached.
Group B beams (beams 4, 5 and 7) which had
steel plate welded to the steel beam in common, Figure 5: Failure modes of Beam 2
showed almost similar load-deflection behaviour in
terms of maximum load. In beam 4, non-linearity
started at 175 kN due to the steel plate yielding.
Then at about 235 kN, the deflection became more
pronounced with a very small increase in load,
possibly because of yielding of the web of the steel
beam as well as at other locations far from mid-span.
After reaching a maximum load of 248.1 kN a large
drop in load to less than 200 kN indicates failure of Debonded CFRP
the shear connector at both ends, which was
followed by several drops (load increased slightly Figure 6: Failure modes of Beam 3
after the first shear connector failure) of load
ly attributed to steel beam retrofitting not to concrete
retrofitting, since, Beam 4 and Beam 7 showed ex-
actly the same increase in load-carrying capacity
whereas beam 5 showed slightly lower capacity. It is
evident from the observations that steel plate welded
to the steel beam is the main contributing factor to
the strength increase, since beam 4 retrofitted with
steel plate welding at the steel beam soffit showed a
similar strength improvement to beams 5 and 7.
Figure 7: Failure modes of Beam 6 CFRP attached to the steel plate did not show any
improvement and debonded very early in the load
The crack in the concrete slabs (of Beam 5) regime probably in the primer layer, as there was no
propagated diagonally upward parallel to the glue attached to the steel beam. The glue layer was
direction of the debonded steel plate and coincided seen only on the debonded CFRP sheet which did
with another major flexural crack (forming a wedge not allow the CFRP to participate much in resisting
shape). The significant crack widening induced by the tensile stress at the extreme bottom fiber of any
the self-weight of the debonded steel plate from the cross section.
concrete can be the reason for the loss of composite Hence, it can be concluded that steel plate
action and failure of the shear connectors. The large welded to steel beam compared to CFRP attached to
deflection without signifcant increase in load steel beam is the better technique.
represents a high slip between steel and concrete.
The steel yielded just before failure of the beam by Table 5: Comparison of maximum load with Beam 1
concrete crushing at about 58 mm deflection. Beam Beam ID 2 3 4 5 6 7
7 reached a plastic stage with the yielding of the %increase in
steel plate at 175 kN indicated by the non-linearity maximum -0.3 -0.4 +14.5 +13.6 +1.2 +14.5
load
of the load-deflection curve. At about 240 kN
(deflection of 15 mm), there is slight drop of load
when the debonding of CFRP from concrete
initiated. After reaching a maximum load of 248.2
kN, there were several load-drops due to both
initiation of shear connector failures and debonding
crack propagation of concrete. Load dropped to
about 206 KN at a deflection level of 28 mm. This is
due to failure of the shear connector at both ends
Figure 8: Failure modes of Beam 4
(Figure 10). Immdiately, after failure of the shear
connector, the FRP completely debonded on both
sides of the concrete slab with no noticeable increase
in load. Then gradual failures of the shear connector
occurred until the beam failed by concrete crushing.
Figure 10 shows the failure modes of Beam 7.

3.2 Maximum load


Figure 9: Failure modes of Beam 5
In terms of maximum loads (Figure 11) of the retro-
fitted beams with CFRP only, beam 2 (CFRP on
concrete), beam 3 (CFRP on steel) and beam 6
(CFRP on concrete and steel) did not show any sig-
nificant improvement. In fact, beam 2 and beam 3
reached maximum loads slightly lower than the con-
trol beam (Beam 1).
Beams 4, 5 and 7, which were retrofitted with
steel plate welded to the steel beam soffit only, steel
plate glued to concrete in addition to a steel plate
Figure 10: Failure modes of Beam 7
welded to the steel beam soffit and CFRP bonded to
concrete in addition to steel plate at the steel beam
soffit, respectively, showed significant improvement
in load-carrying capacity. The percent increases were
14.5, 13.6 and 14.5, respectively (Table 5). Howev-
er, the increased load-carrying capacity can be main-

6
5 REFERENCES

Al-Saidy, A., Klaiber, F., Wipf, T., Al-Jabri, K. & Al-Nuaimi,


A. 2008. Parametric study on the behavior of short span
composite bridge girders strengthened with carbon fiber re-
inforced polymer plates. Construction and Building Mate-
rials, 22, 729-737.
Al-Saidy, A. H., Klaiber, F. & Wipf, T. 2004. Repair of steel
composite beams with carbon fiber-reinforced polymer
plates. Journal of Composites for Construction, 8, 163-172.
Bakis, C., Bank, L. C., Brown, V., Cosenza, E., Davalos, J.,
Lesko, J., Machida, A., Rizkalla, S. & Triantafillou, T.
2002. Fiber-reinforced polymer composites for construc-
tion-state-of-the-art review. Journal of Composites for Con-
struction, 6, 73-87.
Fam, A., Macdougall, C. & Shaat, A. 2009. Upgrading steel–
Figure 11: Comparison of maximum load capacity concrete composite girders and repair of damaged steel
beams using bonded CFRP laminates. Thin-Walled Struc-
tures, 47, 1122-1135.
Heiza, K., Nabil, A., Meleka, N. & Tayel, M. 2014. State-of-
4 CONCLUSIONS the Art Review: Strengthening of Reinforced Concrete
Structures–Different Strengthening Techniques. Sixth In-
This study aimed to investigate six techniques to ternational Conference on Nano-Technology in Construc-
strengthen steel-concrete composite beams incorpo- tion, 22-24 March 2014. Cairo-Egypt.
Mertz, D. & Gillespie, J. 1996. Rehabilitation of steel bridge
rating retrofitting of the concrete slab soffit only, ret- members through the application of advanced composites.
rofitting of the steel beam only and a combination of Final Report. NCHRP-93-ID01.
both applying CFRP wet lay-up sheets and steel Miller, T. C., Chajes, M. J., Mertz, D. R. & Hastings, J. N.
plate. Based on the experimental results of the load- 2001. Strengthening of a steel bridge girder using CFRP
deflection behavior of retrofitted steel-concrete plates. Journal of Bridge Engineering, 6, 514-522.
composite beams, the following conclusions can be Nie, J., Cai, C. & Wang, T. 2005. Stiffness and capacity of
steel–concrete composite beams with profiled sheeting. En-
drawn- gineering structures, 27, 1074-1085.
Nie, J. & Cai, C. S. 2003. Steel-concrete composite beams con-
 There was no significant effect of CFRP on sidering shear slip effects. Journal of Structural Engineer-
the retrofitting of steel-concrete beams in ing, 129, 495-506.
terms of load-carrying capacity. The beams Sallam, H. E. M., Badawy, A. A. M., Saba, A. M. & Mikhail,
retrofitted with CFRP on concrete, CFRP on F. A. 2010. Flexural behavior of strengthened steel–
concrete composite beams by various plating methods.
steel beam and CFRP on concrete and steel Journal of Constructional Steel Research, 66, 1081-1087.
showed almost the same load-carrying capac- Sen, R., Liby, L. & Mullins, G. 2001. Strengthening steel
ity as unstrengthened beams. bridge sections using CFRP laminates. Composites Part B:
 The beams which were retrofitted with steel Engineering, 32, 309-322.
plate welded to steel beam in common Tavakkolizadeh, M. & Saadatmanesh, H. 2003a. Repair of
showed an almost similar increase in load- damaged steel-concrete composite girders using carbon fi-
ber-reinforced polymer sheets. Journal of Composites for
carrying capacity (13.6 to 14.5 %) regardless Construction, 7, 311-322.
of the retrofitting of the concrete slab. Hence, Tavakkolizadeh, M. & Saadatmanesh, H. 2003b. Strengthening
the hybrid retrofitting is the most suitable one of steel-concrete composite girders using carbon fiber rein-
in terms of improvement of load capacity. forced polymers sheets. Journal of Structural Engineering,
 Although all beams except one yielded first, 129, 30-40.
gradual failure of shear connectors followed
the steel yielding before complete failure by
crushing of concrete. Further investigation 6 APPENDIX
needs to be carried out on how to increase the
performance of shear connections in existing Appendix – Repair layouts of different beams
composite beams.
Steel plates

Beam 4 Beam 5

Figure A1: Retrofitting technique of beam 4 and 5

CFRP Steel plate

Beam 6 Beam 7

Figure A2: Retrofitting technique of beam 6 and 7

8
View publication stats

You might also like