Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
If all the tasks are listed with the related Risk/Impact?Mode, Select or Write Yes From The next Cell Yes Clik here –Next to Evaluation-Page
Identification of Failure / Aspects /
Hazards CHECKLIST FOR IDENTIFYING MODE / SOURCE (Actual / Potential)
Failure Failure Failure Failure Failure
S/N Activities/Products/Services 1.What Can Go Wrong? Mode
2.What Can Go Wrong? Mode
3.What Can Go Wrong? Mode
4.What Can Go Wrong? Mode
5.What Can Go Wrong? Mode
During Outage. Isolate & untie wire Conflict/missing signals after Failure of signal integration Slip,Trip & Fall due to
termination from common alarm Power restoration due to and non-Acknowledgment of obstruction and unsafe access
panel (open knife TB and isolate Improper cable tagging signals after energization due Slip trip
external wires from both sides, to untight termination Cut Injuries due to the sharp
retagging wires from fully isoldated & object of panels cut injuries
can happen
electrically grounded as per the
Eye Injuries
detailed comperhensive APPROVED
Method of Statement by
1 MARAFIQ of Existing DFR/DSM-SS10J- Machine Machine Ergonomic
380kV SS 10J Cabinet 1 and
DFR/DSMSS10J 380kV SS 10J Cabinet
2 and DFR/DSM-SS10J 115kV SS 10J
Cabinet
1 (Digital Fault Recorder, dynamic
system monitor) Panel before
reconnecting on new DFR-DSM
panels).
Remove all digital interface of Alarm Conflict/missing signals after Failure of signal integration Slip,Trip & Fall due to
Signal between (DRF/DSM & 115kV Power restoration due to and non-Acknowledgment of obstruction and unsafe access
LCC) & (DRF/DSM & 380 KV LCC). And Improper cable tagging signals after energization due Slip trip
remove all digital interface of Alam to untight termination Cut Injuries due to the sharp
Signal between (DRF/DSM & 380KV object of panels cut injuries
2 Machine Machine can happen Ergonomic
Protection panel Line & Transformer)
Eye Injuries
& (DRF/DSM & 115kv BB Protection
Main-1&2) & (DRF/DSM & 380kv BB
Protection Main-1&2)
8 Method Personnel
Panel W =81cm, H=220cm, L=850 cm
Total weight appx= 75 kg
Connect CT wire between DFR/DSM Conflict/missing signals after Failure of signal integration Slip,Trip & Fall due to
and protection panels. Keep CT Power restoration due to and non-Acknowledgment of obstruction and unsafe access
shorted as per step No.5 and slide link Improper cable tagging signals after energization due Slip trip
keep open during each feeder second to untight termination Cut Injuries due to the sharp
outage successively. Further, Connect object of panels cut injuries
10 Machine Machine can happen Ergonomic
VT wire between DFR/DSM and LCC
Eye Injuries
panels. Keep VT Link open as per No.3
Step
Classified as MARAFIQ Internal Use #
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Signature:
Important Remarks: Please read the "notes" before carrying out MIRA.
Note 1 : While applying controls OTP consider the following order of importance:
Classified as MARAFIQ Internal Use #
Hierarchy of Controls
1. Elimination
2. Substitution
3. Engg. Controls
4. Administrative Controls & Singnages, Warnings,training etc.
5. PPE
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Machine may generate misleading 4 2 8 Y Equipment’s) 2 2 4 N
tagging
alarm/measurment Approved MOS by
Marafiq will be
followed. Double cross
check wiring as per
associated schematics
led to lose of accurate drawings and continuity
monitoring of transient check is performed
Effect:
1.During Outage. fault, abnormal behavious
Isolate & untie wire and other essental alarms
termination from
common alarm panel
(open knife TB and
isolate external wires
from both sides,
retagging wires from
fully isoldated &
electrically grounded improper configuration
as per the detailed dueto conflict in wiring
comperhensive Cause: while isoltion and tagging
APPROVED Method due to not following the
of Statement by last updated drawings
MARAFIQ of Existing
DFR/DSM-SS10J- No tripping hazards
380kV SS 10J Cabinet
1 and DFR/DSMSS10J involved in the
380kV SS 10J Cabinet
Page 1 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
reconnecting on new Machine Event: 3 3 9 2 1 2 N
signals after may generate misleading Signal
DFR-DSM panels). energization due to alarm/measurment Following Approved
untight termination MOS by MARAFIQ will
be followed. Double
cross check wiring as per
associated schematics
drawings and Continuity
check is performed
AC/DC power source
will be switch Off and
tagged CBs
led to lose of accurate
monitoring of transient
fault, abnormal behavious
Effect: and other essental alarms
which will require double
work and tracking the
wiring
1.During Outage.
Isolate & untie wire
termination from
common alarm panel not following Approved
(open knife TB and Cause:
MOS Comply with detailed
isolate external wires
APPROVED MOS by
from both sides,
MARAFIQ
retagging wires from
Complying with Marafiq
fully isoldated &
Page 2 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Cut Injuries due to the Event: during isolation 3 3 9 Y 29 Electrical Safety 2 1 2 N
APPROVED Method c
sharp object of panels procedure #37/
of Statement by cut injuries can happen (Personal protective
MARAFIQ of Existing Eye Injuries Equipment’s)
DFR/DSM-SS10J-
380kV SS 10J Cabinet
1 and DFR/DSMSS10J
380kV SS 10J Cabinet
2 and DFR/DSM- Effect: shocks and sever pain
SS10J 115kV SS 10J
Cabinet
1 (Digital Fault
Recorder, dynamic
NO
digital interface of Machine Event: 3 3 9 Y 2 1 2 N
tagging may generate misleading -
Alarm Signal alarm/measurment Conduct Peer Review
between (DRF/DSM and Quality auditing
& 115kV LCC) & before and during
(DRF/DSM & 380 KV activity
Page 3 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Machine 3 3 9 Y SAS/SCADA 1 2 2 N
signals after
energization due to
Representatives using
Event: Dduring the Drilling
untight termination latest updated drwings
as per approved Method
statement
Led to lose of accurate
Effect: monitoring of transient
fault, abnormal behaviors
and other essential alarms
2. During Associated
Outage- Remove all
digital interface of Due to obstruction and
Alarm Signal Cause: unsafe access Slip trip &
between (DRF/DSM falls can happen All works will be
& 115kV LCC) & executed under the
(DRF/DSM & 380 KV Slip,Trip & Fall due to supervision of SIEMENS
obstruction and unsafe
LCC). And remove all Safety Engineer
access Slip trip
digital interface of Ergonomi During the termination or -Suitable PPE (safety
NO
Cut Injuries due to the Event: 3 1 3 1 1 1 N
Alarm Signal c wiring shoes, transparent
sharp object of panels
between (DRF/DSM cut injuries can happen glasses, and hand
& 380KV Protection Eye Injuries gloves, safety helmet,
Page 4 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Electrical Shock 4 2 8 Y 2 2 4 N
& Remove VT wire c Event: During VT cables isolation -
from Both Side All works will be
(DFR/DSM & LCC executed under the
Panels, retagging supervision of Marafiq/
wires) Material & Manpower are Protection/ SAS/SCADA
Representatives
Effect: exposed to Electrical
Shock.
-
AC and DC power
NO
DCDB), retagging Event: 4 3 12 Y 2 2 4 N
c panels procedure #37/
wires before
(Personal protective
reconnecting on new
Equipment’s)
DFR-DSM panels will
Page 5 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Machine Event: 3 3 9 Y rubber hand gloves, 2 1 2 N
side and open slid open terminal end or Commissioning
conflict/ missing wires
helmet, and face mask)
link after each
must be used during site
outage (SHORT
works.
before ISOLATE)
- Use hand tools
safely to prevent
Comply with Marafiq
OHSMS clause/
Mulfunctional & /Procedure#34 (Manual
Effect: Handling)
equipment damagaes
Page 6 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
Mis-handling of AC
secondary current
injection kit, improper
Cause: injection cables sizing , No tripping hazard
improper handling of involved in the
injection kit, not DFR/DSM
grounding replacement activity
NO
injection test from Electrical shock Event: Will intrupt the testiing 3 2 6 Y 2 1 2 N
c All works will be
LCC panels
executed under the
supervision of SIEMENS
Safety engineer
-Suitable PPE (Safety
shoes, transparent
glasses, and hand
gloves, Safety helmet,
and face mask) must be
Lead to Flashover or used during site works.
Effect:
Electrical Shock
Page 7 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
pain and Event: During the driling 3 3 9 Y 2 1 2 N
c procedure #37/
back injury
(Personal protective
Equipment’s)
Approved MOS by
Marafiq will be followe
Damage to the materials
Effect:
and manpower
NO
Cut Injuries due to the Event: During the driling 3 3 9 Y 2 1 2 N
c shoes, transparent
sharp object of panels
cut injuries can happen glasses, and hand
Eye Injuries gloves, safety helmet,
and face mask) must be
used during site works.
Page 8 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
Exposed/Scrached Cables-
Cause:
Improper sized Inspect drilling machine
cables Peer Review
as Quality assurance
procedure. Apply
MARAIQ Procedure
Ergonomi Electrical shocks due to
NO
Event: During the driling 3 3 9 Y Suitable PPE (safety 2 1 2 N
c the drilling machine
shoes, transparent
glasses, and hand
gloves, safety helmet,
7.preperaion and
and face mask) must be
drilling for the Panel
used during site works.
instalation
Effect: Electrical Shock, Burn
NO
Method Dust during drilling Event: 3 2 6 Y shall be used to clean 1 1 1 N
and actiation of Fire Alrm
the dust particle.
Eye Inflimmation and Toolbox talk shall
Effect: propbably fire Alarm begiven to the
Activation manpower prior to
Page 9 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
There is no
combustible/hazardous
Cause:
material around the area
of work
NO
drilling for the Panel Method Fire Alarm Activation Event: 1 1 1 Y 1 1 1 N
which may cause the Fire installation, including
instalation Alrm activation portable electrical
equipment, is approved
certified equipment.
Effect: No effect,
NO
Method Fallen of Panels Event: During shifting 4 2 8 Y 1 1 1 N
procedure #37/
8.Manual Handling (Personal protective
through pallet truck Equipment’s)
the Dismantling & Approved MOS by
Damage to the materials Marafiq will be followed
shifting Existing Effect:
and manpower injuries
DFR/DSM panels
after verifying signal
isolation & cross
Page 10 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Personnel Event: During shifting 3 3 9 Y 2 1 2 N
pain and back injury trolley for Loading and
unloading of materials.
Safe pathways/Access
for personal movements
will be provide
Effect: Bleeding, Cut injuries
NO
Cut Injuries panels 4 3 12 Y 2 1 2 N
c procedure #37/
Eye Injuries
(Personal protective
Equipment’s)
9.Manual Installation Approved MOS by
of New DFR/DSM Sharp Panel Edges, wrong Marafiq will be followed
(Panels) 10J 380kV Effect: Movement due to wrong
DFR-DSM-01 & 10J Hand Tools
380kV DFR-DSM-02
& 10J 115kV DFR-
DSM-01 &10J 115kV
Page 11 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Machine During Replacement of 2 3 6 Y 1 1 1 N
panels Event: shoes, transparent
panels
glasses, and insulated
rubber hand gloves,
helmet, and face mask)
must be used during site
Damages to the works Use hand tools
Effect:
Equipment safely to prevent
Comply with Marafiq
OHSMS clause/
NO
Machine Event: 4 2 8 Y Equipment’s) 1 1 1 N
tagging may generate misleading
Approved MOS by
alarm/measurment
Marafiq will be
followed. Double cross
check wiring as per
Page 12 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
10.Connect CT wire
between DFR/DSM
and protection
improper configuration
panels. Keep CT
dueto conflict in wiring
shorted as per step
No.5 and slide link Cause: while isoltion and tagging
due to not following the
keep open during
last updated drawings
each feeder second
outage successively.
Further, Connect VT No tripping hazards
wire between
DFR/DSM and LCC involved in the
panels. Keep VT Link
open as per No.3 DFR/DSM
Step
replacement activity,
since the schamtics
Failure of signal
integration and non- DFR/DSM will not be involve only Alarm
Acknowledgment of functioning properly and
NO
Machine Event: 3 3 9 Y 2 1 2 N
signals after may generate misleading Signal
energization due to alarm/measurment Following Approved
untight termination MOS by MARAFIQ will
be followed. Double
cross check wiring as per
associated schematics
drawings and Continuity
check is performed
Page 13 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Cut Injuries Event: 3 3 9 Y Equipment’s) 1 2 2 N
outage successively. c panels
Eye Injuries Approved MOS by
Further, Connect VT
Marafiq will be
wire between
followed. Double cross
DFR/DSM and LCC
check wiring as per
panels. Keep VT Link
associated schematics
open as per No.3 Sharp Panel Edges, wrong drawings and continuity
Step
Effect: Movement due to wrong check is performed
Hand Tools
Page 14 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Machine Event: 3 3 9 Y Equipment’s) 1 1 1 N
tagging may generate misleading
Approved MOS by
alarm/measurment
Marafiq will be
followed. Double cross
check wiring as per
associated schematics
led to lose of accurate drawings and continuity
monitoring of transient check is performed
Effect:
fault, abnormal behavious
and other essental alarms
improper configuration
11.Connect Digital
dueto conflict in wiring
alarm signal between
DFR/DSM, Cause: while isoltion and tagging
due to not following the
Protection, LCC &
last updated drawings
Common alarm
panel. Keep
Terminal block Kinfe No tripping hazards
type open at
DFR/DSM. involved in the
Page 15 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
replacement activity,
since the schamtics
Failure of signal
integration and non- DFR/DSM will not be involve only Alarm
Acknowledgment of functioning properly and
NO
Machine Event: 3 3 9 Y 2 1 2 N
signals after may generate misleading Signal
energization due to alarm/measurment Following Approved
untight termination MOS by MARAFIQ will
be followed. Double
cross check wiring as per
associated schematics
drawings and Continuity
check is performed
AC/DC power source
will be switch Off and
tagged CBs
Page 16 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Cut Injuries Event: 3 3 9 Y Equipment’s) 1 1 1 N
panel. Keep c panels
Eye Injuries Approved MOS by
Terminal block Kinfe
Marafiq will be
type open at
followed. Double cross
DFR/DSM.
check wiring as per
associated schematics
Sharp Panel Edges, wrong drawings and continuity
Effect: Movement due to wrong check is performed
Hand Tools
No tripping hazards
involved in the
Due to Short circuited VT DFR/DSM
lead to overheating the replacement activity,
Cause:
wire and consequent since the schamtics
damage involve only Alarm
12.Connect DC&AC
Signal
between DFR/DSM &
Conduct Peer Review
(ACDB &DCDB).
between Testing
and Proceed further
Engineers to verify VT
with VT loop from Ergonomi During VT cables Loop
NO
Electrical Shock Event: 4 3 12 Y loops by Following 2 2 4 N
LCC Protection panel c Termination
Approved MOS by
directed to DFR/DSM
MARAFIQ will be
panel to check VT
followed. Double cross
loop
check wiring as per
associated schematics
Material & Manpower are drawings and Continuity
Effect: exposed to Electrical check is performed
Shock. Ensure AC/DC power
source will be switch Off
before cable
Page 17 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
NO
Machine Event: 4 3 12 Y - 2 2 4 N
Verification at 10JSS tagging may generate misleading
All works will be
& LDC/SCADA alarm/measurment
executed under the
supervision of Marafiq/
led to lose of accurate Protection/ SAS/SCADA
monitoring of transient Representatives
fault, abnormal behaviors
and other essential- - Al
Effect:
Farabi. Co DFR/DSM will
not be successfully
interfaced- Loss of
Contractor repetition
Signature:
Page 18 of 19
Classified as MARAFIQ Internal Use #
Power & Water Utility Company for Jubail & Yanbu (MARAFIQ) - Integrated Management System Risk Assessment (MIRA)
Important Remarks: Please read the "notes" before carrying out MIRA.
Note 1 : While applying controls OTP consider the following order of importance:
Note 2 : Additional OTP/IMP is necessary for Risk/Impact where RPN score is 20 or more. Risk/Impact less than 20 shall be considered "Acceptable as Significant Risk/Impact
Note 3 : Human Factors include Physical and mental capabilities, Behavioral elements etc.
Hierarchy of Controls
1. Elimination
2. Substitution
3. Engg. Controls
4. Administrative Controls & Singnages, Warnings,training etc.
5. PPE
Page 19 of 19