SECTION 1-Marafiq Department /Contractor: - Al Manar Arabian Corp. Date: May 19, 2011
Facility / Job Location : Specify Activity to be assessed :- Assessment team member Signature
Department:
Projects Behind MARAFIQ Concrete pouring for the Foundation, Grade
Admin. Building beam, Slab, Water Proofing installation and 1 Mohammed Hamdy
Backfilling and Compaction (MASJID and
CAFETERIA)
2 Mohammed Alabiad
3 Walter Castillo
Reviewed By (Marafiq coordinating Department ): Reviewed By ( Marafiq Safety Section): Approved By (Marafiq Operations Department):
Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011
the activities.
Cuts, eye, face injury Used of cutting disk not a grinding disk, cutting area shall be
surrounded with sheet metal or fire blanket.
Fire Provide fire extinguisher near the working area.
b. Steel bending Improper working Physical injury, body pains Buddy system is required to minimized too much power exertion, that
postures will result to body pains,,
Congested working area Slip, punctured, cuts Unwanted material shall be brought out from the bending working
area.
c. Form work lay out and Tripping Hazard Fall, cut, Provide a Carpentry Shop with proper working table. Maintain good
installation and regular house keeping to have tidy safe working area.
Expose rebar/steel, Puncture, cuts, fall on the See to it that all steel marking shall be capped/cover and flagged with
protruding objects. same level, abrasion safety ribbons.
Contact with the sharp Cuts, Used hand gloves, Safety Glass, dust musk close fitting uniform.
blade of the circular saw Never try to fix any parts of the machine while in motion., safety guard
shall be in place and safe.
Poor house keeping Slip, strip, fall punctured, Scrap and dismantled parts shall be subjected for de nailing and pilled
fracture properly away from the working area.
d. Concrete pouring for column Fall, Pump truck may fall See to it that outrigger of the pump truck was properly place on a hard
grade beam & slab using Ergonomic/Chemical surface, supplemented with wooden blockings and extend to the
pumpcrete truck/Mixer Hazards extreme out reach .
(commercial…)
Moving machinery Hitting workers/facilities Provide watchman to assist the driver /operator during reverse
maneuver of the machines.
Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011
Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011
Protruding Slip, fall on the same Expose rebar shall be capped and flagged with warning tape.
objects/tripping hazard level
Excess hardened concrete Slip, fall on the same Excess and hardened concrete shall be properly dispose
level immediately out of the working site.
2 Polyethylene application Concrete Protection Environment/Chemical L physical injury
Hazard
Contact with the chemical Burn, Irritation Supervisor shall informed his people of the precautionary measure
and proper usage that was stated in the MSDS of the product.
Burn, Irritation Use rubberize hand gloves, safety glass in applying the product for
concrete protection.
Liquid chemical Soil contamination Be careful and provide proper plastic on the ground to avoid
(Spillage) spillage.
3 Backfilling Ergonomics/fall hazard L Physical injury
Damage to property.
Fall Hazards Damage to Property Equipment is required to pass to the Safety inspection to avail
working sticker prior to the activities
Collision, crashing Injury to the workers. Employ competent operator certified by a third party inspectorate
recognize by the Saudi Government.
Moving machinery Machine fall down, Provide watch man to assist the operator on the back and forth
hitting workers. movement of the equipment.
Foreign Particles/objects Eye and respiratory Wear safety glass, Dust mask, hand gloves and watered the
problem/injury backfilling materials if needed to reduce the dust exposure and
risk.
4 Compaction Fall Hazard M Physical injury/Fire
a. Safety Inspection Compaction Machine malfunction, oil Fire, soil contaminant Machine is subjected for Marafiq safety inspection prior to the
Machine leakage activities.
b. Un loading compactor machine by Un Certified operator Load may fall Crane operator shall be competent and certified by third party
boom truck inspectorate recognized by the Saudi government.
Equipment malfunction Fracture, cuts Lifting equipment should be first inspected prior to the lifting
work. Shackle, chain, belt including the boom truck.
Under suspended load H Fatal/property damage No one is allowed to work/stay under a suspended load
PROPRIETARY NOTICE IMPORTANT
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.
Power & Water Utility Company MSSS-1-SF-001
Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 5 of 7
Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011
Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011
Prior to commencement of job, Authorized Permit Receiver / Supervisor must give information on details of job, hazards, risks and safety precautions to all personnel
involved in the job and obtain their signatures on the form to acknowledge the same.
Sr. Name of the employee Profession ID No. Signature of the employee
I am informed of job details, hazards, risks and safety
PROPRIETARY NOTICE IMPORTANT
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.
Power & Water Utility Company MSSS-1-SF-001
Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 7 of 7
Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011