Power & Water Utility Company MSSS-1-SF-001

Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 1 of 7

Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011

SECTION 1-Marafiq Department /Contractor: - Al Manar Arabian Corp. Date: May 19, 2011
Facility / Job Location : Specify Activity to be assessed :- Assessment team member Signature
Department:
Projects Behind MARAFIQ Concrete pouring for the Foundation, Grade
Admin. Building beam, Slab, Water Proofing installation and 1 Mohammed Hamdy
Backfilling and Compaction (MASJID and
CAFETERIA)
2 Mohammed Alabiad
3 Walter Castillo
Reviewed By (Marafiq coordinating Department ): Reviewed By ( Marafiq Safety Section): Approved By (Marafiq Operations Department):

Name: Signature: Name: Signature: Name: Signature


Date: Time: Date: Time: Date: Time:

SR JOB STEPS POTENTIAL SEVERITY/ CONTROL MEASURE


HAZARD H/M/L/CONSEQUENCES (What can be done to prevent it from going wrong?)
(What can cause harm?) (What can go wrong?)
1. Foundation, Grade beam, Slab works
a. Steel cutting Protruding objects Puncture, strip Cutting/bending shop with proper working table shall be provided.
Scrap/Dismantled parts shall be separate immediately and pile on safe
place away from the working area.
Sharp edges of the Cuts, strip Wear proper PPEs for the job, hand gloves, safety glass, Face shield,
cutting machine ear plug when using cutting disk of grinding machine
Repeated motion Body pain, strains Proper posture and buddy system is required to avoid too much exert
of power.
Exposed /open Electrocution, Fire And burn When using Electric power tools make it sure cable, outlet and
energized cable machine is free from any defects, look for the inspection color coding
for that month. Any doubt discuss it with supervisor assigned, prior to
PROPRIETARY NOTICE IMPORTANT
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.
Power & Water Utility Company MSSS-1-SF-001
Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 2 of 7

Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011

the activities.
Cuts, eye, face injury Used of cutting disk not a grinding disk, cutting area shall be
surrounded with sheet metal or fire blanket.
Fire Provide fire extinguisher near the working area.
b. Steel bending Improper working Physical injury, body pains Buddy system is required to minimized too much power exertion, that
postures will result to body pains,,
Congested working area Slip, punctured, cuts Unwanted material shall be brought out from the bending working
area.
c. Form work lay out and Tripping Hazard Fall, cut, Provide a Carpentry Shop with proper working table. Maintain good
installation and regular house keeping to have tidy safe working area.
Expose rebar/steel, Puncture, cuts, fall on the See to it that all steel marking shall be capped/cover and flagged with
protruding objects. same level, abrasion safety ribbons.
Contact with the sharp Cuts, Used hand gloves, Safety Glass, dust musk close fitting uniform.
blade of the circular saw Never try to fix any parts of the machine while in motion., safety guard
shall be in place and safe.
Poor house keeping Slip, strip, fall punctured, Scrap and dismantled parts shall be subjected for de nailing and pilled
fracture properly away from the working area.
d. Concrete pouring for column Fall, Pump truck may fall See to it that outrigger of the pump truck was properly place on a hard
grade beam & slab using Ergonomic/Chemical surface, supplemented with wooden blockings and extend to the
pumpcrete truck/Mixer Hazards extreme out reach .
(commercial…)
Moving machinery Hitting workers/facilities Provide watchman to assist the driver /operator during reverse
maneuver of the machines.

PROPRIETARY NOTICE IMPORTANT


THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.
Power & Water Utility Company MSSS-1-SF-001
Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 3 of 7

Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011

RISK ASSESSMENT FORM (Contd.

SR JOB STEPS POTENTIAL HAZARD SEVERITY / CONTROL MEASURE


(What can cause harm?) CONSEQUENCES (What can be done to prevent it from going wrong?)
(What can go wrong?)
Contact with the cement Itching, irritation, burn Wear appropriate PPE for the job, Rubberize hand gloves,
Gumboots, safety glass, and avoid contact with the cement
PROPRIETARY NOTICE IMPORTANT
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.
Power & Water Utility Company MSSS-1-SF-001
Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 4 of 7

Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011

Protruding Slip, fall on the same Expose rebar shall be capped and flagged with warning tape.
objects/tripping hazard level
Excess hardened concrete Slip, fall on the same Excess and hardened concrete shall be properly dispose
level immediately out of the working site.
2 Polyethylene application Concrete Protection Environment/Chemical L physical injury
Hazard
Contact with the chemical Burn, Irritation Supervisor shall informed his people of the precautionary measure
and proper usage that was stated in the MSDS of the product.
Burn, Irritation Use rubberize hand gloves, safety glass in applying the product for
concrete protection.
Liquid chemical Soil contamination Be careful and provide proper plastic on the ground to avoid
(Spillage) spillage.
3 Backfilling Ergonomics/fall hazard L Physical injury
Damage to property.
Fall Hazards Damage to Property Equipment is required to pass to the Safety inspection to avail
working sticker prior to the activities
Collision, crashing Injury to the workers. Employ competent operator certified by a third party inspectorate
recognize by the Saudi Government.
Moving machinery Machine fall down, Provide watch man to assist the operator on the back and forth
hitting workers. movement of the equipment.
Foreign Particles/objects Eye and respiratory Wear safety glass, Dust mask, hand gloves and watered the
problem/injury backfilling materials if needed to reduce the dust exposure and
risk.
4 Compaction Fall Hazard M Physical injury/Fire
a. Safety Inspection Compaction Machine malfunction, oil Fire, soil contaminant Machine is subjected for Marafiq safety inspection prior to the
Machine leakage activities.
b. Un loading compactor machine by Un Certified operator Load may fall Crane operator shall be competent and certified by third party
boom truck inspectorate recognized by the Saudi government.
Equipment malfunction Fracture, cuts Lifting equipment should be first inspected prior to the lifting
work. Shackle, chain, belt including the boom truck.
Under suspended load H Fatal/property damage No one is allowed to work/stay under a suspended load
PROPRIETARY NOTICE IMPORTANT
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.
Power & Water Utility Company MSSS-1-SF-001
Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 5 of 7

Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011

c. Compactor Petrol refilling Environmental Hazard


Petrol and oil Spill Soil contamination Provide portable hand pump to be used for refilling, to avoid
spillage. Engine shall be stop when refilling.
Contact with the petrol Burn, irritation Person work on this activities shall wear rubber gloves, refilling
shall be away from a working machine/Equipment

SECTION 2-List of Materials


(Tools, work equipment, safety and emergency items)
Job should be started only after making provision of suitable and safe tools, work equipment, safety and emergency items on site as stated in risk assessment.
Sr. Tools and other work equipment Qty Sr. Safety and Emergency items Qty

1 Wheel Barrow 3 1 First Aid kits (Marafiq standard) 2


2 Circular Saw 1 2 Fire Extinguisher (6kg) 5
PROPRIETARY NOTICE IMPORTANT
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.
Power & Water Utility Company MSSS-1-SF-001
Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 6 of 7

Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011

3 Boom truck 1 3 Warning/Working sign boards 6


4 Generator set JCB 1 4 Gloves 1 box
5 Shovel 15 5 Cover all
6 Piks 2 6 Safety Shoes
7 Nail Belt bag 4 7 Safety Glass 2 box
8 Ball /Claw Hammer 6 8 Warning tape
9 Claw bar 3 9 Traffic cone 5
10 Bob cat (used after installation of concrete protection) 1 10 Drinking Cooler 1
11 Compaction machine (to be brought in after back filling) 1 11
12
13
14
15
16

SECTION 3-Information to Employees


(Details of job, hazards, risks and safety precautions)

Prior to commencement of job, Authorized Permit Receiver / Supervisor must give information on details of job, hazards, risks and safety precautions to all personnel
involved in the job and obtain their signatures on the form to acknowledge the same.
Sr. Name of the employee Profession ID No. Signature of the employee
I am informed of job details, hazards, risks and safety
PROPRIETARY NOTICE IMPORTANT
THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.
Power & Water Utility Company MSSS-1-SF-001
Document ID No :
for Jubail and Yanbu (MARAFIQ)
Page: 7 of 7

Rev. No.: 0
RISK ASSESSMENT FORM
Valid Until : November 12 - 2011

precautions in order to perform above job safely.


1 Mohammed Hamdy Projects Manager 3196
2 Mohammed Alabiad Project Engineer 3394
3 Mohmmed Abdul Salam Electrical Engineer 3813
4 Mohammed Kamal Foreman 3033
5 Saroj Labor 3499
6 Jit Labor 3497
7 Saidol Labor 3457
8 Sajan Carpenter 2914
9 Ruel Arapoc Operator Hyundai 3664
10 Radio Labor 3353
11 Mukesh Labor 3501
12 Mutho Carpenter 2862
13 Mohammed Carpenter 2895
14 Samen Carpenter 2958
15 Manager Carpenter 3306
16 Vincent Carpenter 3491
17 Amer Steel fixer 3704
18 Khan Carpenter 3724
19 Castillo Safety Officer 3479
20 Badul Rachman First Aid/NURSE 447

PROPRIETARY NOTICE IMPORTANT


THIS DOCUMENT CONTAINS INFORMATION PROPRIETARY TO MARAFIQ. ANY DISCLOSURE OR USE IS EXPRESSLY PROHIBITED
EXCEPT UPON WRITTEN PERMISSION BY MARAFIQ. Only document with stamps are considered official.