Professional Documents
Culture Documents
CH-09-001 Work Instruction Baseline and Corrosion Monitoring Rev 1 (3) (Cari Gali Hess)
CH-09-001 Work Instruction Baseline and Corrosion Monitoring Rev 1 (3) (Cari Gali Hess)
1. Scope
2. Purpose
3. Definitions
4. Responsibilities
5. Work Instruction
6. Reporting
Appendix
1. Sample Datasheet
2. Remark / Condition and No Reading Codes
Page 2 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
1.0 SCOPE
This work procedure describes the extent of NDE examination of piping as referenced
on the marked up inspection isometrics and defines the responsibilities and reporting
routines to be employed, to ensure results recording is performed in a transparent
and consistent manner.
2.0 PURPOSE
2.1 Perform the ultrasonic baseline check, ultrasonic corrosion monitoring scan and
corrosion monitoring inspections.
3.0 DEFINITIONS
3.1 Inspection isometric – Pipework schematic marked up with the test points
requiring NDE inspection.
3.2 Test point – Feature or part of feature where NDE inspection is to be performed in
accordance to a readings procedure outlined in this document.
4.0 RESPONSIBILITIES
4.1 Generic test points requiring inspection shall be marked up on the isometric by the
DNV in accordance with the direction of flow.
4.2 The RBI Engineer will verify and identify / mark up locations that require
inspection and identify NDE method which should be applied.
4.3 The Plant Inspectors are responsible for the sustained implementation and
development of this work procedure.
4.4 The NDE Contractors (Danamin or Velosi) are to perform the prescribed
examination and issue inspection report as per Appendix 1 format.
The specific NDE procedure relating to equipment set up, calibration, personnel
qualification etc shall be submitted by the NDE contractor for review and approval
by Carigali Hess, prior to work commencement.
Such documentation issued by the NDE contractor of the client shall consider the
technical and qualification requirements for the scope as described in this
procedure.
4.5 In the case where the prescribed ultrasonic inspection is not possible and an
alternative technique could be used, the NDE Contractor shall advise the Plant
Inspector and the RBI Engineer accordingly.
Page 3 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
4.6 The Plant Inspector is responsible to supervise the NDE contractor(s), ensuring
correct location is identified and work procedure requirements are complied with.
4.7 The Plant Inspector shall review all sections of the historical CVI
Inspection/Recommendation Reports and provide updated information
accordingly based on current condition.
Test points will be marked up for ultrasonic corrosion monitoring (CM1, CM2) or
ultrasonic baseline check (BL1, BL2, BL3) and the marked up isometrics will be
issued as a workpack to the Plant Inspector.
If significant indications of internal corrosion or erosion are noted the extent of the
survey shall be extended in consultation with the Plant Inspector and the RBI
Engineer (if required). The Remark / Condition Code (IC) for internal corrosion or (IE)
for erosion shall be applied accordingly.
Page 4 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
5.1 Straight Pipe (P)
Scan band 2 inch away from the weld centre, and record the minimum thickness at
each of the 4 segments and reported it in thickness report as reading 1, 2, 3, 4. For
pipe size below 4 inch, scan band is 3 inch. For pipe size greater than or equal to 4
inch, scan band is 6 inch.
For pipe size below 4 inch : For pipe size greater than or equal to 4 inch:
Vertical straight
Reading 1 = 0° = NORTH (N) = min. measured between 315°-45°
Reading 2 = 90° = EAST (E) = min. measured between 45°-135°
Reading 3 = 180° = SOUTH (S) = min. measured between 135°-225°
Reading 4 = 270° = WEST (W) = min. measured between 225°-315°
Page 5 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
B. Ultrasonic Corrosion Monitoring Scan (CM2)
Horizontal pipe
Scan band 2 inch away from the weld centre at location between 135° - 225°, and
record the minimum thickness as for Reading no. 3. Additionally, one representative
reading to be taken at Reading 1, 2 and 4 respectively. For pipe size below 4 inch,
scan band is 3 inch. For pipe size greater than or equal to 4 inch, scan band is 6 inch.
For pipe size below 4 inch : For pipe size greater than or equal to 4 inch:
Vertical pipe
Page 6 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
C. Ultrasonic Baseline Check (BL1)
One representative reading to be taken 2 inch away from the weld centre at location
1,2,3,4:
Horizontal straight
Vertical straight
One representative reading to be taken 2 inch away from the weld centre at location 1
and 3 / (0°and 180°) / (NORTH and SOUTH) position.
One representative reading to be taken 2 inch away from the weld centre at location 3
/180° /SOUTH (S) position.
Page 7 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
5.2 Elbow / Bend (E)
100% Scan on the component. Elbow is divided into 3 equal section and record
minimum thickness as Reading 1, 2 and 3
100% Scan on the component. Elbow is divided into 5 equal section and record
minimum thickness as Reading 1, 2, 3, 4 and 5
Note:
180° is always on the outer radius of the elbow. Degree orientation is read from the
upstream section in the direction of flow. Each location has to be equally spaced.
Page 8 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
B. Ultrasonic Corrosion Monitoring Scan (CM2)
Note:
180° is always on the outside of the bend. Degree orientation is read from the
upstream section in the direction of flow. Each location has to be equally spaced.
For elbow size below than 4 inch, one representative reading to be taken at outer
radius of the elbow (180°) at location 1, 2 and 3 respectively..
For elbow size greater than or equal to 4 inch, one representative reading to be taken
at outer radius of the elbow (180°) at location 1, 3 and 5 respectively..
For elbow size below than 4 inch, one representative to be taken at outer radius of the
elbow (180°) at location 2.
For elbow size greater than or equal to 4 inch, one representative reading to be taken
at outer radius of the elbow (180°) at location 3.
Page 9 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
5.3 Tee Main (Tx-1) and Tee Branch (Tx-2)
100% Scan on the component, and record the minimum thickness at each of the 4
segments and reported it in thickness report as Reading 1, 2, 3, 4, 5, 6, 7, 8 and 9 (for
Tee Main) and location 1, 2, 3 and 4 (for Tee Branch).
Location Reading 1 (min. measured between 315°-45°) of the branch is always at the
front side (view from isometric). Degree orientation is read from the upstream section
in the direction of flow.
Note for Horizontal Tee: Location Reading 1 (min. measured between 315°-45°) of
the main and branch is always on top portion. Degree orientation is read from the
upstream section in the direction of flow.
Page 10 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
B. Ultrasonic Corrosion Monitoring Scan (CM2)
4 inch scan band at location 2 inch away from the weld centre, and record the
minimum thickness at each of the 4 segments and reported it in thickness report as
lReading 1, 2, 3, 4, 5, 6, 7 and 8 and Reading 1, 2, 3 and 4 (for Tee Branch).
Scan area “Y x Y” on Tee Main is equal to area of “main diameter x main diameter”
and record the minimum thickness as Reading 9 (for Tee Main).
Page 11 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
5.4 Reducer
100% scan on component and record the minimum thickness at each of the 4
segments. For reducer below than 4 inch, minimum thickness shall be reported as
Reading 1, 2, 3 and 4. For reducer size greater than or equal to 4 inch, reducer is
divided into 2 equal length and minimum thickness shall be reported as Reading 1, 2,
3, 4, 5, 6, 7 and 8.
For reducer size below 4 inch : For pipe size greater than or equal to 4 inch:
Vertical reducer
Page 12 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
B. Ultrasonic Corrosion Monitoring Scan (CM2)
Scan between 135° – 225° along the component and record the minimum thickness
for location 3. Additionally, for reducer size below 4 inch, one representative reading
to be taken at location 1, 2 and 4 respectively. For pipe size greater than or equal to 4
inch, reducer is divided into 2 equal length and one representative reading to be
taken at location 1,2,4,5,6 and 8 respectively.
For reducer size below 4 inch : For pipe size greater than or equal to 4 inch:
Vertical reducer
For reducer size below 4 inch, one representative reading to be taken at location
1,2,3 and 4 respectively.
For reducer size greater than or equal to 4 inch, one representative reading to be
taken 2 inch away from the weld centre at location 1,2,3,4,5,6,7 and 8 respectively.
For reducer size below 4 inch, one representative reading to be taken at location1
and 3.
For reducer size greater than or equal to 4 inch, one representative reading to be
taken at location1 and 3 on the large end and one representative reading to be taken
at location 5 and 7 on the smaller end. Readings are to be taken 2 inch away from
the weld centre.
Page 13 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
5.5 Cap End
100% scan on component and record the minimum thickness at each of the 4
segments (including knuckle radius) and minimum reading on cap apex (rounded
portion).
Page 14 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
B. Ultrasonic Corrosion Monitoring Scan (CM2)
2 inch scan band at location 2 inch away from the weld centre, and record the
minimum thickness at each of the 4 segments and reported it in thickness report as l
Reading 1, 2, 3 and 4.
2 inch diameter scan at the apex of the cap and record the minimum thickness as
Reading 5.
Page 15 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
6.0 REPORTING
Table below show the data to be tabulated in the thickness report. White box under
test point location is mandatory to be filled unless if there is restriction as per
Appendix 2.
Page 16 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
Appendix 1
Sample Datasheet
Page 17 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc
Appendix 2
No reading Codes:
Page 18 of 18 CH-09-001 Work Instruction Baseline and Corrosion Monitoring rev 1.doc