You are on page 1of 154

TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 1 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

PROJEC 70240 CCC SAN LUIS RIO COLORADO


CLIENT: T: Comisión Federal de Electricidad CCF
LOCATION: San Luis Rio Colorado (México)
SUBCONTRACT: 70240-2510 CIVIL WORKS

INDEX

I. SYSTEM OF MEASUREMENT AND PAYMENT. 2


A. OBJECT. 2
B. UNIT PRICE CONTENT AND SYSTEM OF MEASUREMENT. 2
1. General. 2
2. Commodity groups. 4
C. HOURLY RATES. 152
1. General 152
2. Labour. 152
3. Machinery. 152
4. Material. 153

II. SCHEDULE OF RATES. 154


1. Unit Prices. 154
2. Hourly Rates. 154

DATE:

SIGNATURE:

NAME:

PREPARED BY DISCIPLINE LEADER SUBCONTRACT MANAGER

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 2 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

I. SYSTEM OF MEASUREMENT AND PAYMENT.


A. OBJECT.

The object of this document is to define the pricing structure, price content, methodology of
measurement, and prices to apply to quantities obtained from drawings in all Civil Works
activities performed by the Subcontractor in accordance with the awarded Scope of Work.

This system shall be applied to Subcontracts established by Unit Prices, as well as increases
or decreases of quantities for Lump Sum Subcontracts where contractual provisions entitle
to do so.

New prices that could appear during the execution of the works shall follows the same basis
of estimation than quoted prices, and they will be calculated under interpolation and
proportionality rules with unit prices already agreed in the Subcontract.

B. UNIT PRICE CONTENT AND SYSTEM OF MEASUREMENT.

1. GENERAL.

Measurements shall always be taken from contractual documentation such as specifications,


approved for construction standards, approved for construction drawings and/or any other
technical documentation as included within SUBCONTRACT ANNEX II.

“Red Marked” documentation, Protocols, Acts, Notices of Inspection, etc. shall be prepared
by SUBCONTRACTOR as supportive documentation for measurement preparation. Final
measurements shall be settled through “As Built” documentation when its preparation is
contractually required to SUBCONTRACTOR.

Measurement of work units for interim certification purposes shall be carried out on
supportive documentation which shall be handed over by SUBCONTRACTOR to CONTRACTOR
once endorsed by CONTRACTOR’s supervision team as well as by CONTRACTOR’s QC team.
SUBCONTRACTOR shall endeavor to get signatures on supportive documentation from them
in advance of each period cut-off date. Aforesaid signatures shall be a compulsory
requirement for proceeding with measure of quantities and establishing progress payments,
which shall be done by CONTRACTOR’s subcontracts team.

Where the CONTRACTOR deems it necessary, field measurements shall be taken or spot
check shall be done over provided supportive documentation. Field measurements shall be
done jointly with the SUBCONTRACTOR and the results shall be accepted as valid.
CONTRACTOR shall notify aforesaid calls to SUBCONTRACTOR one day in advance. Failing
SUBCONTRACTOR to attend calls for taking field measurements shall lead to accept
CONTRACTOR’s outcomes as valid.
In general, and not exhaustive or limited to, the unit prices shall include as a minimum:
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 3 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

- All necessary resources for timely performance of works (e.g. direct labor, machinery,
Auxiliary Equipment or means, consumables, Materials, Supplies, Technical and
Administrative Support, etc.).

- Methodology, completion and deployment of all resources and operations to comply


faithfully with the quality standards, the approved project plan, essays, test,
pre/commissioning activities, technical specifications, HSE requirements (HSE Plan,
Waste Management Plan, standards and related procedures), permits application,
licenses, etc.

- All labor, operations and other costs for access, unloading, receiving, unpacking,
handling, storage (inclusive of hazardous materials, if any), maintenance and onsite
transportation, preservation, pre-assembly / prefabrication, installation and
pre/commissioning, housekeeping, HSE prevention and mitigation measures, waste
management (inclusive of hazardous materials, if any), mitigation systems to prevent
the effects from dust, noise and vibrations, winterization (heating & hording) etc. into
the WORKS or the surrounding areas.

- All necessary costs related to training of workers by CONTRACTOR or its VENDORS in


order to qualify SUBCONTRACTOR’s workers to execute a specific task.

- Required Construction Engineering development, including but not limited to, Work
Method Statements & Task Risk Analysis.

- To maintain all the working areas free from rain water and/or water table in order to
allow the operability of the construction equipment during all the duration of the
WORKS. In particular the execution of appropriate temporary provisions (i.e. slopes,
earth ditches, earth containing walls, pits, etc.) in such a way to collect the water for its
disposal, including the use of motor pumps where and when necessary

- Topographical set-up (also referred herein below as ‘setting out’) of the foundations
and any other Civil WORKS starting from the bench marks assigned by the
CONTRACTOR, assignment of a qualified team of Surveyors to be approved by
CONTRACTOR

- Daily cleaning of the existing construction and roads eventually made dirty by
SUBCONTRACTOR. Restoration of existing roads and any other existing facility
eventually damaged by SUBCONTRACTOR

- Clearing and cleaning of the work site, access roads, ramps, leveling and preparation of
the work areas to allow the suitable arrival of materials and the timely positioning of
equipment
- QC dossier and needful documentation from SUBCONTRACTOR.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 4 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Measurements shall always be taken from specifications, Approved for Construction standards
and drawings, and/or “as built” drawings whenever possible.

If the Contractor’s Site Manager deems it necessary to take measurements in the field, these
measurements shall be accomplished jointly with the Subcontractor and the results shall be
accepted as valid.

Commodity codes are codified as follows:

CW GG SS PP BB x::x:
CW: Discipline Civil Works
GG: Group Code
SS: Subgroup Code
PP: Part Code
BB: SubPart Code
x::x: Sequence Code

2. COMMODITY GROUPS.

The following table include code groups in which civil discipline is divided.

Commodity
Group Description
Group
CW01 DEMOLITIONS AND DISASSEMBLES
CW01DM Demolitions
CW01DS Disassembles
CW02 GENERAL SITE PREPARATION
CW02GR Grubbing and Clearing
CW02EX Excavations
CW02BK Backfillings and Embankments
CW02SI Soil Improvement
CW02TR Transport of Materials
CW03 EARTH WORKS
CW03EX Excavations
CW03EXFD Excavation In foundations, pits, extrados of walls
CW03EXTR Excavation in trenches and channels
CW03EXLO Large Open excavations
CW03EXMA Excavations with manual means
CW03BK Backfillings
CW03BKFD Backfilling In foundations, pits, extrados of walls, trenches and channels
CW03BKEP Backfilling in earth ponds and tank basins
CW03BKTF Backfilling in tank foundations
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 5 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW03BKMW Backfilling in maritime works slope protections special activities


CW03BKPI Particular items
CW03BKPI Replacement enhanced with lime.
CW03TR Transport of materials
CW04 IN-SITU CONCRETE ELEMENTS
CW04LN Lean & Mass concrete.
CW04CO Concrete.
CW04CO2x Concrete (25-28 N/mm2).
CW04CO3x Concrete (30-32 N/mm2).
CW04CO35 Concrete (35 N/mm2, soil nailing wall).
CW04CO40 Concrete (40 N/mm2).
CW04CO50 Concrete (50 N/mm2).
CW04SF Small foundations.
CW04SFIS Small Foundation Cast “in-situ”
CW04SFPC Small Foundation Precast
CW04TH Thickened slab footing
CW04MO Mortars and resins.
CW04FW Formworks.
CW04FWSI Supply and erection of straight formwork
CW04FWMS Miscellaneous for formworks
CW04RB Reinforcing steel.
CW04EE Embedded elements
CW04EESP Steel plates and profiles. Embedded items.
CW04EEEP Embedded piping, duct banks.
CW04AB Anchor Bolts
CW04ABST Standard anchor bolts.
CW04ABEX Expansion anchor bolts.
CW04ABCH Chemical anchor bolts.
CW04ST Surface Treatments and waterproofing
CW04STTR Concrete surface treatments.
CW04STWP Waterproofing elements.
CW04STPR Surface treatments and protections with concrete.
CW04MS Miscellaneous for concrete.
CW05 UNDERGROUND WORKS
CW05MH CATCH BASIN, MANHOLES AND PITS
CW05MHCOIS Concrete manholes and pits cast “in-situ”.
CW05MHCOPC Concrete manholes and pits precast.
CW05MHMSBK Masonry manholes and pits made with bricks.
CW05MHMSBL Masonry manholes and pits made with Concrete blocks.
CW05MHPL Plastic and cast iron elements
CW05MHCL Clean out and others
CW05MHCO Covers for catch basins, manholes, culverts and trenches pits>12 m³.
CW05UG UNDERGROUND PIPING ELECTRICAL
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 6 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW05UGPV PVC.
CW05UGPP Polypropylene
CW05UGPE HDPE pipes.
CW05UGGJBW GRP/GRE Butt & Wrap
CW05UGGJTT GRP/GRE (Adhesive bonded taper/taper joint).
CW05UGGJMJ GRP/GRE (mechanical joint, seal look joint).
CW05UGCO Concrete.
CW05UGCI Cast Iron.
CW05UGCS Carbon Steel
CW05UGEC Galvanized Steel Piping
CW05UGFV Flanged Valves
CW05UGWR Wrapping
CW05UGEC Electrical conduits (single pipes, not duct banks).
CW06 PAVING AND ROADS
CW06EWEX Paving and roads earthworks. Encasements.
CW06EWGL Paving and roads earthworks. Granular layers.
CW06EWTR Paving and roads earthworks. Transport to dumping areas.
CW06CPPA Concrete in paving.
CW06CPRO Concrete in roads.
CW06APWC Asphalt paving and/or roads. Wearing course.
CW06APBC Asphalt paving and/or roads. Base course.
CW06APPR Asphalt paving and/or roads. Priming.
CW06GP Gravel paving.
CW06CH Gutters, channels, ditches and swales.
CW06SG Signposting and side protections.
CW06MS Miscellaneous paving and roads.
CW07 MASONRY
CW07OP Openings and close-outs.
CW07WL Walls and partitions.
CW08 GROUNDING NETWORKS
CW08GR Grounding Works
CW09 MISCELLANEOUS
CW09UB Urbanization, landscaping and finishing works.
CW09FNTF Temporary and removable fence.
CW09FNPF Permanent Fence.
CW09FNRP Fence Reposition.
CW09ET Electrical trenches miscellaneous.
CW09UG Underground miscellaneous.
CW09MS Rest of Miscellaneous items

2.1 Commodity group CW01. Demolitions and disassembles.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 7 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.1.1 Commodity group CW01DM. Demolitions.

In case those demolitions activities might influence on normal use of other services, SUBCONTRACTOR
shall put all resources to ensure maintenance of service as well as avoid any damage to other structures
or existing facilities.

In case that any facilities or service have to be replaced, this shall be done at time enough to ensure
the continuity of the corresponding services and under CONTRACTOR’s approval. These operations will
be included in the unit prices unless there are explicitly referred and defined in another project unit.

Unit prices shall also include all the required works in this list, but not limited thereto:

- Preparation of a Work Method Statement and Risk Analysis of activities to be performed for
CONTRACTOR/Owner’s approval, indicating decommissioning and demolition/dismantling
procedures, HSE measures, etc.

- Preparation of required lifting / rigging studies.

- Implementation of a LOTO (Lockout / Tagout) procedure to ensure safe working procedures


during dismantling works.
- HSE additional requirements, according to applicable standards, procedures and specifications, as
needed.

- Thorough verification of any available information during execution as well as checkup of hidden
facilities.

- Additional protection measures for existing facilities to prevent dust/vibration/noise…

- Needful specific materials, tools and/or auxiliary means for a timely execution of works, such as
cutting and removal of rebar from reinforced concrete, grinding, excavations, slope stabilizations,
shoring, dewatering, cutting and compacted backfilling up to natural soil elevation with material from
the excavation, as per soil report or another Project specification, once debris have been removed.

- Separation between distinct categories of the materials in order to comply with local environment
agencies (for instance, concrete and rebar need to be separated during demolition of reinforced
concrete elements)

- Management, handling, storage, treatment (if required) and disposal of wastes (as
debris/rubble/leftovers/scraps, etc…) whatever their location into authorized dumpsites or laydown
areas, including fees if necessary.

- For any material that may be reused in the project, the price shall also include cleaning, storage
and transport of the material to a location designed by the Site Manager.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 8 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

- Removal of irrecoverable electrical equipment/material such as conduits, wires, cables, panels,


switches, lighting, telephone, alarms and any other circuit.

- Removal of all irrecoverable mechanical equipment/material, such as pipes, heating, ventilation,


accessories, tanks, etc; including insulation of these elements.

- The execution of these activities shall be performed using mechanical and/or manuals resources.

In case of demolitions by manual means, it will be solely measured units previously approved and
signed by contractor. Quantities not supported under this condition will be measured and paid as the
same manner that demolition by mechanical means.

It will be solely measured under this criteria the corresponding quantities to the elements defined in
demolition and disassembly drawings. Any other element that could appear during the execution of
another works and/or chapters will be measured and paid as the corresponding unit.

SUBCONTRACTOR shall ensure stability of all remaining elements to be demolished at any stage of the
work or stability of a partial demolition.

CW.01.DM_x::x Demolitions
Commodities included: Definition: Demolition of supports, walls, structures,
CW01DM_MCME000000S buildings, pavements, concrete slabs,
CW01DM_MCMA0000L10 foots, etc.
CW01DM_MCMA010R100 Price content: Price includes all work required for the
CW01DM_SLME000000S Included but not demolition, shop machinery, demolition
CW01DM_SLMA000000S limited to: equipment, auxiliary requirements
CW01DM_RCME000000S (scaffolding, etc.), excavation required to
CW01DM_RCME000100S expose the system to be demolished,
CW01DM_RCMA000000S cutting and removal of rebars from
reinforced concrete, loading and
CW01DM_BUME000000S
transporting of debris to an authorized
exterior dump site (including all operations
involved with the removal of debris from
elevated work), intermediate storage,
dumping fees, safety requirements in
accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 9 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

the manner directed by and to a location


designated by Site Manager.

Excluded:
Measurement volume of concrete in each concrete
system: element, as measured on approved
drawings.
Unit of measure: Cubic meter (m3)

CW.01.DM_ROx··x Demolition of agglomerate asphaltic paving road, up to 15 cm


thick, by mechanical means.
Commodities included: Referred to: Demolition of any kind of asphaltic paving
or asphaltic road, up to 15 cm thick, made
CW01DM_ROME0000L15 by mechanical means.
CW01DM_ROMA0000L15 Price content: Price includes all work required for the
CW01DM_ROMA000000S Included but not demolition, shop machinery, demolition
limited to: equipment, auxiliary requirements
(scaffolding, etc.), cutting, loading and
transporting of debris to an authorized
exterior dump site (including all operations
involved with the removal of debris from
elevated work), intermediate storage,
dumping fees, safety requirements in
accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in the
manner directed by and to a location
designated by Site Manager.

Excluded: granular bases and/or subbases below the


asphaltic road/paving
Measurement The measurement of this item shall be the
system: real surface of asphaltic road/paving and
shall be measured “in-situ”. Sketch will be
required to justify the quantity.
Unit of measure: Square meter (m2)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 10 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.01.DM_UGME000000S Demolition of underground piping and/or channels (any type)


by mechanical means.
Commodities included: Referred to: Demolition and dismantling of channels or
underground piping any material using
CW.01.DM_UGME000000S mechanical means
Price content: Price includes all work required for the
Included but not demolition, shop machinery, demolition
limited to: and dismantling equipment, auxiliary
requirements (scaffolding, etc.), cutting,
excavation required to expose the system
to be demolished, loading and
transporting of debris to an authorized
exterior dump site (including all
operations involved with the removal of
debris from elevated work), Backfilling
with adequate material to restore and left
the area as the original state, intermediate
storage, dumping fees, safety
requirements in accordance with
applicable standards and specifications,
irrigation requirements and, in general, all
required materials and labor for the
correct completion of the required unit.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in
the manner directed by and to a location
designated by Site Manager.

Excluded: Demolition of paving if any, over the


underground system.
Measurement The measurement of this item shall be the
system: real length measured “in-situ”. Sketch will
be required to justify the quantity.
Unit of measure: Lineal meter (lm)

CW.01.DM.._UGME000000S Demolition of manholes and/or pits (any type) by mechanical


means.
Commodities included: Referred to: Demolition of any kind of concrete catch
basins, manholes and pits, precast or
performed in-situ

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 11 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.01.DM_UGME000000S Price content: Price includes all work required for the
Included but not demolition, shop machinery, demolition
limited to: and dismantling equipment, auxiliary
requirements (scaffolding, etc.), cutting,
excavation required to expose the system
to be demolished, loading and transporting
of debris to an authorized exterior dump
site (including all operations involved with
the removal of debris from elevated work),
Backfilling with adequate material to
restore and left the area as the original
state, intermediate storage, dumping fees,
safety requirements in accordance with
applicable standards and specifications,
irrigation requirements and, in general, all
required materials and labor for the
correct completion of the required unit.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in
the manner directed by and to a location
designated by Site Manager.

Excluded: Concrete manholes and pit with internal


volume > 12 m3. These shall be measured
under CW01DM_RCME000000S
Measurement This demolition shall be measured by unit
system: of manhole, manholes with double
chamber or higher shall be considered as
the number of chambers. Covers and lean
concrete are part of the manhole and their
demolitions are included in the unit price
and shall not be measured.
Unit of measure: Unit (n)

2.1.2 Commodity group CW01DS. Disassembles.

CW.01.DS_SSME000000S Disassembly of steel structures.


Commodities included: Referred to: Disassembly and dismantling of existing
steel structures.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 12 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.01.DS_SSME000000S Price content: Price includes all work required for the
Included but not disassembly, including cranes, shop
limited to: machinery, auxiliary requirements
(scaffolding, etc.), loading and
transportation of debris to an authorized
external dump site (including all operations
involved with the removal of debris from
elevated work), intermediate storage,
dumping fees, safety requirements in
accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in the
manner directed by and to a location
designated by Site Manager.
Excluded:
Measurement The disassembly of structures shall be
system: measured on as-built drawings.
Unit of measure: Kilogram (kg)

CW.01.DS.._WLME000000S Disassembly of wall cladding and/or roof panel (any type).


Commodities included: Referred to: Disassembly and dismantling of
enclosures of shelters, warehouses and
CW.01.DS.._WLME000000S any other building, any type, as metallic
panels or sandwich type panels
Price content: Price includes all work required for the
Included but not disassembly, including cranes, shop
limited to: machinery, auxiliary requirements
(scaffolding, etc.), loading and
transportation of debris to an authorized
external dump site (including all
operations involved with the removal of
debris from elevated work), intermediate
storage, dumping fees, safety
requirements in accordance with
applicable standards and specifications,
irrigation requirements and, in general, all
required materials and labor for the
correct completion of the required unit.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 13 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

The unit price also includes dismantling of


gutters, external roof drain channels,
special pieces and down pipes

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in
the manner directed by and to a location
designated by Site Manager.
Excluded:
Measurement The disassembly of cladding and roofing
system: panels shall be measured on as-built
drawings, overlaps shall not be considered
nor measured.
Unit of measure: Square meter (m2)

CW.01.DS.._UGME000000S Disassembly of above ground piping lines (any type).


Commodities included: Referred to: Dissasembly and dismantling of pipe lines
aboveground, any material, including
CW.01.DS_UGME000000S fittings, valves and any other in-line
element installed.
Price content: Price includes all work required for the
Included but not disassembly, including cranes, shop
limited to: machinery, auxiliary requirements
(scaffolding, etc.), loading and
transportation of debris to an authorized
external dump site (including all operations
involved with the removal of debris from
elevated work), intermediate storage,
dumping fees, safety requirements in
accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in
the manner directed by and to a location
designated by Site Manager.
Excluded: Pipe line previous cleaning works and
preparation for dismantling.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 14 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Measurement It shall be measured on as-built drawings,


system:
Unit of measure: Kilogram (kg)

CW.01.DS_FNME0000200 Disassembly of permanent metallic wire mesh fence, 2 m


minimum height, with a bayonet with three galvanized barbed
wire lines including demolition of foundations.
Commodities included: Referred to: Disassembly and dismantling of existing
metallic wire mesh fence
CW01DS_FNME0000200 Price content: Price includes all work required for the
Included but not disassembly of wire mesh fence and access
limited to: gates, including cranes, shop machinery,
auxiliary requirements (scaffolding, etc.),
demolition of fence foundations, loading
and transportation of debris to an
authorized external dump site (including all
operations involved with the removal of
debris from elevated work), intermediate
storage, dumping fees, safety requirements
in accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in the
manner directed by and to a location
designated by Site Manager.
Excluded:
Measurement The disassembly of metallic wire mesh fence
system: shall be measured on as-built drawings,
including the disassembly of access gates.
Unit of measure: Lineal meter (lm)

CW.01.DS_ROMEx::x Disassembly of permanent metallic safety guardrail and


signposting in sides of roads including demolition of foundations.

Commodities included: Referred to: Disassembly and dismantling of existing


guardrail
CW.01.DS_ROME000000S Price content: Price includes all work required for the
CW.01.DS_ROME000100S Included but not disassembly, including cranes, shop
limited to: machinery, auxiliary requirements
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 15 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

(scaffolding, etc.), loading and


transportation of debris to an authorized
external dump site (including all operations
involved with the removal of debris from
elevated work), intermediate storage,
dumping fees, safety requirements in
accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.

For concrete foundations the price includes


all work required for the demolition, shop
machinery, demolition equipment,
auxiliary requirements (scaffolding, etc.),
excavation required to expose the system
to be demolished, cutting and removal of
rebars from reinforced concrete, loading
and transporting of debris to an authorized
exterior dump site (including all operations
involved with the removal of debris from
elevated work), intermediate storage,
dumping fees, safety requirements in
accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material in
the manner directed by and to a location
designated by Site Manager.
Excluded:
Measurement The disassembly of structures shall be
system: measured on as-built drawings.
Unit of measure: Lineal meter (lm) for safety guardrail
Each for signposting

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 16 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.2 Commodity group CW02. General Site Preparation.

2.2.1 Commodity group CW02GR. Grubbing and clearing

Grubbing and clearing


CW.02.GR_x::x

Commodities included: Referred to: Removal of natural and organic soil, trees,
plants, bushes, grass, roots.
CW02GR_GCME0000015 The vegetation, including roots tree stumps,
CW02GR_GCME0000020 shall be removed completely.
CW02GR_GCME0000030 Price content. The unit price includes the transport of
CW02GR_GCME0000040 Included but not machinery to and within the job site,
CW02GR_SCME0000015 limited to: positioning time for machinery, cleaning,
ripping, excavation of the surface grade,
intermediate storage, removal and
transport of all materials from the cleaned
area to an authorized external dump area
(including fill dirt, topsoil, vegetation, trees,
brushwood, stumps, plants, underbrush, fall
wood, and all types of undesirable material)
safety requirements and dumping fees.

For earth that may be reused in the project,


the price also includes cleaning, storage, and
transport of the material to the location and
in the manner specified by CONTRACTOR’s
Site Manager.

When required, the unit price also includes


all timbering and shoring, and drainage of
the terrain by whatever means is
appropriate.
Excluded:
Measurement Surface will be measured in its natural state
system: as defined on reference drawings and
topographic profiles. Any swelling, any
excavation apart from those specified on
applicable drawings, or any excavation for
the removal of tree stumps and roots shall
not be measured nor paid
Unit of measure: Square meter (m2)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 17 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.2.2 Commodity group CW02EX. Excavations.

CW.02.EX_TRME000000S General open excavation related to Site Preparation.


Commodities included: Referred to: Excavation required for leaving a working
area to a specific level and to flatten,
CW02EX_TRME000000S compact and prepare the site on a specific
condition. In detail, general excavations are
performed on open areas where removal
equipment can operate at the same level as
the grading with temporary ramps if
necessary.
Price content. Unit Price includes the transport of
Included but not machinery to and within the job site,
limited to: positioning time for machinery, ripping,
excavating, leveling, slope refining,
irrigation, compaction as per specifications,
safety requirements, and intermediate
storage within the work site in the location
specified by the CONTRACTOR’s Site
Manager.

For earth that may be reused in the project,


the price also includes cleaning, storage, and
transport of the material to the location and
in the manner specified by CONTRACTOR’s
Site Manager.

When required, the unit price also includes


all timbering and shoring, and drainage of
the terrain by whatever means is
appropriate.
Excluded: Removal of natural land and organic top soil,
included in commodity codes CW.02.GR_x::x
Measurement Volume for excavation shall be measured in
system: its natural state as is stated on approved
reference plans and topographic profiles.
Any swelling, any additional widening of
grades, or any slopes that differ from the
specifications listed on applicable drawings,
shall not be measured nor paid.
Unit of measure: Cubic meter (m3)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 18 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.02.EX._RKME000000S General open excavation, in rock and for any depth, by


mechanical means. EXCLUDING TIMBERING, SHORING AND,
DEWATERING
Commodities included: Referred to: Excavation required for leaving a working
area to a specific level and to flatten,
CW02EX_RKME000000S compact and prepare the site on a specific
condition. In detail, general excavations are
performed on open areas where removal
equipment can operate at the same level as
the grading with temporary ramps if
necessary. The excavation is performed in
rock and it is required the use of hydraulic
mortars, wedges, drills and/or hydraulic
hammer.
Price content. The unit price includes preliminary
Included but not excavation tests, permits, licenses,
limited to: notifications to local authorities,
administrative procedures, required
preliminary project manual, transport of
machinery to and within the job site,
positioning time for machinery, excavation,
leveling, refining of slopes, supply and
spreading and compacting of borrowed
material for leveling up to theoretical
required profile as per drawings,
compaction as per specifications, materials
(explosives, mortars, wedges, hydraulic
hammer, etc.), special machinery, safety
requirements, and intermediate storage
within the work site in the location specified
by the CONTRACTOR’s Site Manager.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to the
location and in the manner specified by
CONTRACTOR’s Site Manager.

Excluded: Removal of natural land and organic top soil,


included in commodity codes
CW.02.GR_x::x.
When required, the unit price for all
timbering and shoring, and drainage of the

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 19 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

terrain by whatever means is appropriate


included in commodity codes CW09.MS_x::x
.

Measurement Volume for excavation shall be measured in


system: its natural state as is stated on approved
reference plans and topographic profiles.
Any swelling, any additional widening of
grades, or any slopes that differ from the
specifications listed on applicable drawings,
shall not be measured nor paid.
Unit of measure: Cubic meter (m3)

CW.02.EX._RKME000000S General open excavation, in rock and for any depth, by


mechanical means and related to Site Preparation.
Commodities included: Referred to: Excavation required for leaving a working
area to a specific level and to flatten,
CW02EX_RKME000000S compact and prepare the site on a specific
condition. In detail, general excavations are
performed on open areas where removal
equipment can operate at the same level as
the grading with temporary ramps if
necessary. The excavation is performed in
rock and it is required the use of hydraulic
mortars, wedges, drills and/or hydraulic
hammer.
Price content. The unit price includes preliminary
Included but not excavation tests, permits, licenses,
limited to: notifications to local authorities,
administrative procedures, required
preliminary project manual, transport of
machinery to and within the job site,
positioning time for machinery, excavation,
leveling, refining of slopes, supply and
spreading and compacting of borrowed
material for leveling up to theoretical
required profile as per drawings,
compaction as per specifications, materials
(explosives, mortars, wedges, hydraulic
hammer, etc.), special machinery, safety
requirements, and intermediate storage
within the work site in the location specified
by the CONTRACTOR’s Site Manager.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 20 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to the
location and in the manner specified by
CONTRACTOR’s Site Manager.

When required, the unit price also includes


all timbering and shoring, and drainage of
the terrain by whatever means is
appropriate.
Excluded: Removal of natural land and organic top soil,
included in commodity codes CW.02.GR_x::x
Measurement Volume for excavation shall be measured in
system: its natural state as is stated on approved
reference plans and topographic profiles.
Any swelling, any additional widening of
grades, or any slopes that differ from the
specifications listed on applicable drawings,
shall not be measured nor paid.
Unit of measure: Cubic meter (m3)

CW.02.EX.._RKEX000000S General open excavation and related to Site Preparation, in rock


and for any depth, using explosives..
Commodities included: Referred to: Excavation required for leaving a working
area to a specific level and to flatten,
CW02EX_RKEX000000S compact and prepare the site on a specific
condition. In detail, general excavations are
performed on open areas where removal
equipment can operate at the same level as
the grading with temporary ramps if
necessary. The excavation is performed with
explosives.
Price content. The unit price includes preliminary
Included but not excavation tests, permits, licenses,
limited to: notifications to local authorities,
administrative procedures, required
preliminary project manual, transport of
machinery to and within the job site,
positioning time for machinery, excavation,
leveling, refining of slopes, supply and
spreading and compacting of borrowed
material for leveling up to theoretical
required profile as per drawings,
compaction as per specifications, materials

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 21 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

(explosives, mortars, wedges, hydraulic


hammer, etc.), special machinery, safety
requirements, and intermediate storage
within the work site in the location specified
by the CONTRACTOR’s Site Manager.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to the
location and in the manner specified by
CONTRACTOR’s Site Manager.

When required, the unit price also includes


all timbering and shoring, and drainage of
the terrain by whatever means is
appropriate.
Excluded: Removal of natural land and organic top soil,
included in commodity codes CW.02.GR_x::x
Measurement Volume for excavation shall be measured in
system: its natural state as is stated on approved
reference plans and topographic profiles.
Any swelling, any additional widening of
grades, or any slopes that differ from the
specifications listed on applicable drawings,
shall not be measured nor paid.
Unit of measure: Cubic meter (m3)

2.2.3 Commodity group CW02BK. Backfilling and embankments

CW.02.BK._EMME000000S General backfilling/ embankment construction with selected


material from the excavation, by mechanical means and related
to Site Preparation.
Commodities included: Referred to: This work unit refers to backfilling for large
open areas to create a work platform in
CW02BK_EMME000000S required level, compact and prepare the
site on a specific condition. In detail,
general backfilling is performed on open
areas where backfilling equipment can
operate at the same level as the grading
with temporary ramps if necessary. The
material shall be selected material from
excavations.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 22 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Price content. Unit Price includes machinery, spreading


Included but not and compaction of backfill in layers,
limited to: irrigation, refining of the surface finish
grade, refining of slopes, auxiliary means,
safety requirements, in general, all required
materials and labor for the correct
completion of the required unit.
Excluded:
Measurement The filling volume shall be measured as
system: stated on approved reference drawings
and, when required, using topographic
profiles. Any swelling, any additional
widening of grades or any slopes that differ
from the specifications listed on applicable
drawings as well as the removal of excess
material from construction of slopes, shall
not be measured nor paid.
Unit of measure: Cubic meter (m3)

CW.02.BK._BMME000000S General backfilling/ embankment construction with selected


borrowed material, by mechanical means and related to Site
Preparation.
Commodities included: Referred to: This work unit refers to backfilling for large
open areas to create a work platform in
CW02BK_BMME000000S required level, compact and prepare the
site on a specific condition. In detail,
general backfilling is performed on open
areas where backfilling equipment can
operate at the same level as the grading
with temporary ramps if necessary. The
material shall be borrowed material from
outside property limits.
Price content. Unit Price includes material supply,
Included but not transport and intermediate storage within
limited to: the work site, machinery, spreading and
compaction of backfill in layers, irrigation,
refining of the surface finish grade, refining
of slopes, auxiliary means, safety
requirements, in general, all required
materials and labor for the correct
completion of the required unit. The
backfilling material must comply with the
project specifications

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 23 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Excluded: large open areas where there are


foundations at a distance of less than 6
meters.
Measurement The filling volume shall be measured as
system: stated on approved reference drawings
and, when required, using topographic
profiles. Any swelling, any additional
widening of grades or any slopes that differ
from the specifications listed on applicable
drawings as well as the removal of excess
material from construction of slopes, shall
not be measured nor paid.
Unit of measure: Cubic meter (m3)

CW.02.BK._xxME000100S General backfilling/ embankment construction with existing


foundations with selected borrowed material, by mechanical
means.
Commodities included: Referred to: This work unit refers to backfilling for large
open areas where there are foundations, to
CW02BK_BMME000100S create a work platform in required level,
CW02BK_SFME000100S compact and prepare the site on a specific
CW02BK_NSME000100S condition around those foundations. In
CW02BK_MLME000100S detail, general backfilling is performed on
open areas where backfilling equipment can
operate at the same level as the grading
with temporary ramps if necessary but
taking in account the free spaces around the
foundations. It shall be considered as large
open areas where there are foundations
when there is a foundation at a distance of
less than 6 meters. When the distance is
greater the area to be backfilled shall be
considered as General backfilling/
embankment (without foundations). The
material shall be borrowed material from
outside property limits.
Price content. Unit Price includes material supply,
Included but not transport and intermediate storage within
limited to: the work site, machinery, spreading and
compaction of backfill in layers, irrigation,
refining of the surface finish grade, refining
of slopes, auxiliary means, safety
requirements, in general, all required
materials and labor for the correct

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 24 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

completion of the required unit. The


backfilling material must comply with the
project specifications. The area backfilling
will be performed on stages of partial areas
and different levels as required by the
progress of execution of civil works.
Remobilization and demobilizations of
backfilling equipment and personnel as
many times as required are also included in
prices.
Excluded:
Measurement The filling volume shall be measured as
system: stated on approved reference drawings and,
when required, using topographic profiles.
Any swelling, any additional widening of
grades or any slopes that differ from the
specifications listed on applicable drawings
as well as the removal of excess material
from construction of slopes, shall not be
measured nor paid.
Unit of measure: Cubic meter (m3)

2.2.4 Commodity group CW02SI. Soil Improvement

CW.02.SI.._GM000000S Supply and execution of soil improvement by replacement of


existing soil, carried out in layers with granular material.
Commodities included: Referred to: Soil improvement means the general
substitution of existing soil with a new
CW02SI_GM000000S granular material with a specified depth and
surface. Backfilling are performed on open
areas where backfilling equipment can
operate at the same level as the grading with
temporary ramps if necessary.
Price content. Unit Price includes excavation, material
Included but not supply, transport and intermediate storage
limited to: within the work site, machinery, spreading
and compaction of backfill in layers, irrigation,
refining of the surface finish grade, refining of
slopes, auxiliary means, safety requirements,
in general, all required materials and labor for
the correct completion of the required unit.
The backfilling material must comply with the
project drawings and specifications.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 25 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Excluded: Located soil improvements under specific


foundations.
Measurement The volume shall be measured as stated on
system: approved reference drawings and, when
required, using topographic profiles. Any
swelling, any additional widening of grades or
any slopes that differ from the specifications
listed on applicable drawings as well as the
removal of excess material from construction
of slopes, shall not be measured nor paid.
Unit of measure: Cubic meter (m3)

2.2.5 Commodity group CW02TR.Transport of materials.

CW.02.TR.._x::x Loading, transport and unloading of remainder material from


excavation.
Commodities included: Referred to: Load, transport and unload of excess material
form excavations, inside or outside property
CW02TR_IN000000S limits but into an authorized dumping area
CW02TR_OU000000S Price content. The unit price includes the loading, transport,
Included but not and unloading of excess excavated material.
limited to: Unloading should be inside or outside property
limits but into an authorized dumping area. In
case of outside, the price also includes all costs
associated with the obtaining of dumping
permits, any dumping fees, maintenance and
preparation of material, etc.
Excluded:
Measurement The transport shall be measured as the
system: difference between the excavated volume and
the backfilling material from the excavation, in
accordance with the system of measurement
and payment. Bulking, swelling, or any increase
in volume the material may experience during
its transport, is not measurable and shall not be
paid.
Unit of measure: Cubic meter (m3)

2.3 Commodity group CW03. EARTH WORKS.

2.3.1 Commodity group CW03.EX. Excavations

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 26 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.3.1.1 Commodity group CW03.EX.FD. Excavations in foundations, pits and extrados


of walls.

CW.03.EX.FD._x::x Deep excavation in any kind of terrain.


Commodities included: Referred to: This refers to deep excavations for
foundations, catch basins, pits, tie beams,
CW03EXFD_ATME0000U03 etc., performed below the elevation of
CW03EXFD_ATME0003R06 the finishing grade with the mechanical
CW03EXFD_ATME0000H06 excavation equipment shall be located
CW03EXFD_ATME0006R09 outside of the excavation shaft,
CW03EXFD_LSME000U800 considering that the mechanical
CW03EXFD_RKME0000U03 excavation equipment shall be located
CW03EXFD_RKME0003R06 outside when the area of the projection
of the structural concrete element to be
CW03EXFD_RKME0000H06
allocated in the excavated area is lower
CW03EXFD_RKEX0000U03
than 60 m2. Rock excavation refers to the
CW03EXFD_RKEX0003R06
excavation executed with explosives,
CW03EXFD_RKEX0000H06 hydraulic mortar, wedges, drillings
CW03EXFD_RKEX0006R09 and/or hydraulic hammer, as specified by
CONTRACTOR Site Manager, who will
decide the test to be carried out for the
required excavation.

Price content. Unit Price includes transport of


Included but not mechanical excavation equipment to and
limited to: within the job site, the positioning time
for machinery, cutting and ripping,
excavating, leveling, slope refining and
stability dressing the surface to required
level, dressing of sides, irrigation,
ramming/compaction of bottom of
excavation as per specifications, field test
and inspections, topographical survey,
safety requirements, and intermediate
storage within the work site in the
location specified by the CONTRACTOR’s
Site Manager.

When the excavation is performed in


rock, the price also includes preliminary
excavation tests, permits, licenses,
notifications to local authorities,
administrative procedures, required
preliminary project manual, materials

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 27 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

(explosives, mortars, wedges, hydraulic


hammer, etc.), and special machinery.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to
the location and in the manner specified
by CONTRACTOR’s Site Manager.

When required, the unit price also


includes all timbering and shoring,
drainage and dewatering of the terrain by
whatever means is appropriate avoiding
accumulation of water inside the
excavation shaft and preventing the entry
of water runoff.
Excluded:
Measurement Excavated volume will be measured in its
system: natural state considering the elevations
as shown on approved reference
drawings, plans and topographical survey
at the moment of the beginning of the
excavation, and measuring the sidewalls
of the excavated area as vertical,
considering the perimeter of the
excavation as the horizontal projection of
the structural concrete element, no extra
width shall be allowed like over width due
to lean concrete, even when it is
indicated on drawings. Any swelling, any
additional widening of grades, berms, as
well as any slopes that are not as
specified on approved drawings, shall not
be measured nor paid. When the
excavation depth is deeper than 3 m. the
figure 5.1 criteria for the correct
application of commodities shall be
followed
Unit of measure: The unit of measurement shall be the
cubic meter (m3).

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 28 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.3.1.2 Commodity group CW03.EX.TR. Excavations in trenches and channels

CW.03.EX.TR. x::x Trench excavation in any kind of terrain.


Commodities included: Referred to: This is defined as deep linear excavations
for conduits, utilities, gutters, electrical
CW03EXTR_ATME0000U03 and instrument trenches, etc. with the
CW03EXTR_ATME0003R06 mechanical excavation equipment located
CW03EXTR_ATME0000H06 outside the excavation area.
CW03EXTR_RKME0000U03 Rock excavation refers to the excavation
CW03EXTR_RKME0003R06 executed with explosives, hydraulic
CW03EXTR_RKME0000H06 mortar, wedges, drillings and/or hydraulic
CW03EXTR_RKEX0000U03 hammer, as specified by CONTRACTOR Site
Manager, who will decide the test to be
CW03EXTR_RKEX0003R06
carried out for the required excavation.
CW03EXTR_RKEX0000H06
Price content. Unit Price includes transport of machinery
Included but not to and within work site, the positioning
limited to: time for machinery, cutting and ripping,
excavating, leveling, slope refining and
stability, dressing the surface to required
level, dressing of sides,, irrigation,
ramming/compaction of bottom of
excavation as per specifications, field test
and inspections, topographical survey,
safety requirements, and intermediate
storage within the work site in the location

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 29 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

specified by the CONTRACTOR’s Site


Manager.

When the excavation is performed in rock,


the price also includes preliminary
excavation tests, permits, licenses,
notifications to local authorities,
administrative procedures, required
preliminary project manual, materials
(explosives, mortars, wedges, hydraulic
hammer, etc.), and special machinery.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to
the location and in the manner specified
by CONTRACTOR’s Site Manager.

When required, the unit price also includes


all timbering and shoring, required safety
slopes, drainage and dewatering of the
terrain by whatever means is appropriate,
avoiding accumulation of water inside the
trench and preventing the entry of water
runoff. Any over excavation on trenches to
allow welding operation of underground
piping shall not be measured nor paid.
Excluded: Directional drilling and microtunelling
Measurement Excavated volume will be measured in
system: their natural state as shown on approved
reference drawings, plans and
topographical survey at the moment of the
beginning of the excavation, measuring
the sidewalls of the excavated area as
vertical, except for conduits or group of
pipe/conduits with diameter greater than
1,600 mm (When laying a group of pipes,
the values listed on the table apply to the
pipes located at the extreme right and left
of the group.) (see table). Any swelling,
any excavation above those specified on
plans, as well as any additional widening of
grades, berms, as well as any slopes or

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 30 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

widths which differs from the table below,


shall not be measured nor paid.
Additional width values will not apply to
the following:
- Trenches for cables that do not
require cable sleeves.
- Trenches for grounding electrical
networks.
- Concrete lined trenches.
- Trenches with no conduits installed.

When the excavation depth is deeper than


3 m. the figure 5.2 criteria for the correct
application of commodities shall be
followed

Unit of measure: The unit of measurement shall be the cubic


meter (m3).

Additional Width
Diameter of the (S)
conduit /pipe or allowance for each Angle of slope
(mm) side of the conduit
(cm) S
Up to 150 10 Vertical
≥ 151 to 300 15 Vertical
≥ 301 to 500 20 Vertical
≥ 501 to 900 30 Vertical

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 31 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

≥ 901 to 1.600 45 Vertical


≥ 1.601 to 2.400 60 To be agreed
on.
≥ 2.401 90 To be agreed
on.

Table 5. 1 - Additional width and angle of slopes for conduit/piping trenches

CW.03.EX.TR._DDME000000S Directional drilling, in any kind of terrain.


Commodities included: Referred to: This is defined as deep linear excavations
belowground for conduits, utilities,
CW03EXTR_DDME000000S gutters, electrical and instrument
trenches, using a drilling machine,
avoiding open trenches.

Price content. Unit Price includes transport of


Included but not machinery to and within work site, the
limited to: positioning time for mechanical
excavation equipment, cutting and
ripping, excavating, leveling, slope
refining, irrigation, compaction as per
specifications, safety requirements, and
intermediate storage within the work site
in the location specified by the
CONTRACTOR’s Site Manager.

When the excavation is performed in


rock, the price also includes preliminary
excavation tests, permits, licenses,
notifications to local authorities,
administrative procedures, required
preliminary project manual, materials
(explosives, mortars, wedges, hydraulic
hammer, etc.), and special machinery.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to
the location and in the manner specified
by CONTRACTOR’s Site Manager.

When required, the unit price also


includes all timbering and shoring,

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 32 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

drainage and dewatering of the terrain by


whatever means is appropriate.
Excluded:
Measurement Excavated volume will be measured in
system: their natural state as shown on approved
reference plans measuring the length of
the tunnel axis.
Unit of measure: The unit of measurement shall be the
linear meter (lm).

CW.03.EX.TR._MTME000000S Microtunneling, in any kind of terrain.


Commodities included: Referred to: Microtunneling is a process that uses a
remotely controlled Microtunnel Boring
CW03EXTR_MTME000000S Machine (MTBM) combined with the
pipe jacking technique to directly install
pipelines underground in a single pass,
avoiding open trenches.
Price content. Unit Price includes transport of
Included but not mechanical excavation equipment to and
limited to: within work site, the positioning time for
machinery, cutting and ripping,
excavating, execution of attack pit and
trailing with their necessary dimensions,
removal of surplus material to landfill,
leveling, slope refining, irrigation,
compaction as per specifications, safety
requirements, and intermediate storage
within the work site in the location
specified by the CONTRACTOR’s Site
Manager.

When the excavation is performed in


rock, the price also includes preliminary
excavation tests, permits, licenses,
notifications to local authorities,
administrative procedures, required
preliminary project manual, materials
(explosives, mortars, wedges, hydraulic
hammer, etc.), and special machinery.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 33 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

the location and in the manner specified


by CONTRACTOR’s Site Manager.

When required, the unit price also


includes all timbering and shoring,
drainage and dewatering of the terrain
by whatever means is appropriate.
Excluded:
Measurement Excavated volume will be measured in
system: their natural state as shown on approved
reference plans measuring the length of
the tunnel axis.
Unit of measure: The unit of measurement shall be the
linear meter (lm).

2.3.1.3 Commodity group CW03.EX.LO. Large Open Excavation.

CW.03.EX.LO._x::x Large open excavation in any kind of terrain


Commodities included: Referred to: This work unit refers to excavations for
large open areas, basins, trenches, and
CW03EXLO_ATME0000U06 foundations of great proportion, etc.
CW03EXLO_ATME0000U02 performed below the elevation of the
CW03EXLO_ATME0002R06 finish grade, with the machine located
CW03EXLO_ATME0006R12 within the area to be excavated,
CW03EXLO_RKME0000U06 considering that the mechanical
CW03EXLO_RKME0000U02 excavation equipment shall be located
CW03EXLO_RKME0006R12 inside when the area of the projection of
the structural concrete element to be
CW03EXLO_RKEX0000U06
allocated in the excavated area is greater
CW03EXLO_RKEX0006R12
than 60 m2.

Price content. Unit Price includes the transport of


Included but not mechanical excavation equipment to and
limited to: within the job site and the positioning
time for machinery, cutting and ripping,
excavating, leveling, slope refining,
irrigation, compaction as per
specifications, safety requirements, and
intermediate storage within the work site
in the location specified by the
CONTRACTOR’s Site Manager.

When the excavation is performed in rock,


the price also includes preliminary

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 34 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

excavation tests, permits, licenses,


notifications to local authorities,
administrative procedures, required
preliminary project manual, materials
(explosives, mortars, wedges, hydraulic
hammer, etc.), and special machinery.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to
the location and in the manner specified
by CONTRACTOR’s Site Manager.

When required, the unit price also


includes all timbering and shoring,
drainage and dewatering of the terrain by
whatever means is appropriate..
Excluded:
Measurement Excavated volume will be measured in its
system: natural state as shown on approved for
construction drawings, topographical
profiles and/or geotechnical study. Any
swelling, additional widening of grades
and slopes that are not as specified on
these referred documents shall not be
measured nor paid.

When the excavation is for a pipe/conduit


or group of pipe/conduits trench with
diameter greater than 1,600 mm (When
laying a group of pipes, the values listed on
the table 5.1 apply to the pipes located at
the extreme right and left of the group.)
(see table 5.1). Any swelling, any
excavation above those specified on plans,
as well as any additional widths which
differs from the table below, shall not be
measured nor paid.

Additional width values will not apply to


the following:

- Trenches for cables that do not


require cable sleeves.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 35 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

- Trenches for grounding electrical


networks.
- Concrete lined trenches.
- Trenches with no conduits installed.

When the excavation depth is deeper than


6 m. the figure 5.3 criteria for the correct
application of commodities shall be
followed

Unit of measure: The unit of measurement shall be the


cubic meter (m3).

2.3.1.4 Commodity group CW03.EX.MA Deep and trench excavation and/or gallery
excavation with manual means

CW.03.EX.MA._x::x Manual excavation in any kind of terrain


Commodities included: Referred to: This work unit refers to excavations without
excavation machinery or any other
CW03EXMA_AT000000S mechanical tool, made manually.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 36 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW03EXMA_GL000000S Price content. This Unit Price includes cutting and ripping,
CW03EXMA_RK000000S Included but not excavating, leveling, slope refining,
limited to: irrigation, compaction as per specifications,
tools and manual equipment, safety
requirements, and intermediate storage
within the work site in the location specified
by the CONTRACTOR’s Site Manager.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to the
location and in the manner specified by
CONTRACTOR’s Site Manager.

When required, the unit price also includes


all timbering and shoring, drainage and
dewatering of the terrain by whatever
means is appropriate.

Only excavations instructed by


CONTRACTOR to be performed as MANUAL
shall be paid under this commodity.
SUBCONTRACTOR shall assume, on its own
responsibility, any additional costs due to
the execution under “manual” construction
methodology when the works have not been
identified as “MANUAL” by CONTRACTOR

Excluded:
Measurement Excavated volume will be measured in its
system: natural state as shown on approved
reference plans and measuring the sidewalls
of the excavated area as vertical. Any
swelling, any additional widening of grades,
as well as any slopes that are not as specified
on approved drawings, shall not be
measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

2.3.2 Commodity group CW03.BK. Backfillings.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 37 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.3.2.1 Commodity group CW03.BK.FD Backfilling in foundations, pits, extrados of


walls, trenches and channels.

CW.03.BK.FD._x::x Backfilling in foundations, pits, extrados of walls, trenches


and channels.
Commodities included: Referred to: This refers backfillings for foundations,
catch basins, pits, etc., depending on
CW03BKFD_EM000100S project requirements the backfilling
CW03BKFD_EM000200S material can be excavation material or
CW03BKFD_NS000000S material from outside property limits
CW03BKFD_SF000000S
CW03BKFD_BM000000S Price content. The unit price includes material supply
CW03BKFD_CS000000S Included but not with characteristics according with
CW03BKFD_CS000100S limited to: project requirements and
CW03BKFD_CG000000S specifications for each kind of material,
transportation, intermediate storage,
CW03BKFD_CS000200S
preparation of area to be backfilled
CW03BKFD_CS000300S
(scarifying and recompacting),
CW03BKFD_ST000000S
spreading of backfill in layers, irrigation
CW03BKFD_ST000100S requirements, compaction of these
layers, leveling, grading and
compaction of surface finish grade,
refining of slopes, required machinery,
auxiliary means and, in general, all
required materials and labor for the
correct completion of all work. Price
also includes the execution of any test
indicated in the project specifications
or ITP and its report.

Where SUBCONTRACTOR got


CONTRACTOR´s approval for
performing a group of excavation
works together as an addition of
several elements individually defined
within IFC documentation – regardless
of depth – measurement of related
backfilling works (and related material
supply and transport, if applicable)
shall remain as formerly indicated in
the IFC documentation (addition of
individual elements measurements).

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 38 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Same stipulations as declared within


the above paragraph shall become
applicable as well whenever the reason
for gathering excavation works, and
pursuant to that related backfilling
works (and related material supply and
transport, if applicable), comes from
CONTRACTOR’s instruction in order to
mitigate incurred delays and for
reasons attributable to
SUBCONTRACTOR’s performance or
lack thereof.

Excluded: General backfilling around foundations


required to raise the grade level up to
the final level.

Measurement The filling volume shall be measured as


system: specified on approved drawings
considering, as general rule, sidewalls
of the excavated area as vertical,
unless otherwise specified by
Contractor. Whenever exists, it shall be
considered as base quantity for
calculation, the excavation volume
calculated on items CW03EXnn_x::x,
deducting the volume occupied by the
elements to be buried or the volume
not required to be backfilled.
Backfilling due to any additional
widening of grades, any slopes that are
not as specified on approved drawings
as well as the removal of excess
material from construction of slopes,
shall not be measured nor paid
Unit of measure: The unit of measurement shall be the
cubic meter (m3).
Soil improvement of SELECTED MATERIAL FROM
EXCAVATION as per standard specification.
Commodities included: Referred to: improvement of the land,
with lime (2%), following the
CW03BKFD_EM000100S70230 instructions in Chapter
22.2.3. of the Geotechnical
Study.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 39 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Price content. Included but The unit price includes the


not limited to: supply of materials with
characteristics according to
the requirements and
specifications of the project
for each type of material,
transport, intermediate
storage, preparation of the
area to be improved (being
able to be added in the form
of grout in bulk or in bags), if
added in the form of grout, it
dissolves in the water and is
injected into compaction.
spreading the percentages
that will be used will vary
from 2 to 6%, with respect to
the dry weight of the material
to be improved, do not use
higher percentages since it
increases the plasticity of the
terrain. The dosage of the
cementitious, will depend on
the type of soil. Also includes
irrigation requirements,
compaction of these layers,
leveling, grading and
compaction of surface finish
grade, refining of slopes,
required machinery auxiliary
means and, in general, all
required materials and labor
for the correct completion of
all work. Price also includes
the execution of any test
indicated in the project
specifications or ITP and its
report. Recommended
check, chapter 22.2.3. of the
Geotechnical Study.
Excluded:
Measurement system: The volume of improved
material shall be measured

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 40 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

as specified in the approved


drawings.
Unit of measure: The unit of measurement
shall be the cubic meter (m3).

2.3.2.2 Commodity group CW03.BK.EP Backfilling in earth ponds and tank basins

CW.03.BK.EP._x::x Supply and execution of backfilling in earth dikes for ponds and/or
tank basins, carried out in layers, with granular material.
Commodities included: Referred to:

CW03BKEP_GM000000S Price content. The unit price includes material supply with
CW03BKEP_CS000000S Included but not characteristics according with project
CW03BKEP_CL000000S limited to: requirements and specifications for each
CW03BKEP_MR000000S kind of material, transportation,
intermediate storage, access ramp,
preparation of area to be backfilled
(scarifying and recompacting), spreading of
backfill in layers, irrigation requirements,
compaction of these layers, leveling, grading
and compaction of surface finish grade,
refining of slopes, required machinery,
auxiliary means and, in general, all required
materials and labor for the correct
completion of all work. Price also includes
the execution of any test indicated in the
project specifications or ITP and its report.
Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings considering,
as general rule, sidewalls of the excavated
area as vertical, unless otherwise specified
by Contractor.
Backfilling due to any additional widening of
grades, any slopes that are not as specified
on approved drawings as well as the removal
of excess material from construction of
slopes, shall not be measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

CW.03.BK.EP._GM000100S Supply and execution of granular finishing layer in tank pond


areas, carried out in layers.
Commodities included: Referred to:
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 41 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW03BKEP_GM000100S Price content. The unit price includes material supply with
Included but not characteristics according with project
limited to: requirements and specifications for each
kind of material, transportation,
intermediate storage, access ramp,
preparation of area to be backfilled
(scarifying and recompacting), spreading of
backfill in layers, irrigation requirements,
compaction of these layers, leveling,
grading and compaction of surface finish
grade, refining of slopes, required
machinery, auxiliary means and, in general,
all required materials and labor for the
correct completion of all work. Price also
includes the execution of any test indicated
in the project specifications or ITP and its
report.
Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings.
Backfilling due to any additional widening
of grades, berms, any slopes that are not as
specified on approved drawings as well as
the removal of excess material from
construction of slopes, shall not be
measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

2.3.2.3 Commodity group CW03.BK.TF. Backfilling in tank foundations.

CW.03.BK.TF._x::x Supply and execution of backfilling in tank rings or tank bases,


carried out in layers.
Commodities included: Referred to: Backfilling in tank rings, inside tank rings or
in any other tank basins made with
CW03BKTF_EMTR000000S granular materials from excavation or
CW03BKTF_SFTR000000S from outside property limits.
CW03BKTF_CSTR000000S
CW03BKTF_CSTR000100S Price content. The unit price includes material supply
CW03BKTF_CGTR000000S Included but not with characteristics according with project
CW03BKTF_BMTR000000S limited to: requirements and specifications for each
CW03BKTF_GMTR000000S kind of material, transportation,
intermediate storage, access ramp,

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 42 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

preparation of area to be backfilled


(scarifying and recompacting), spreading
of backfill in layers, irrigation
requirements, compaction of these layers,
leveling, grading and compaction of
surface finish grade, refining of slopes,
required machinery, auxiliary means and,
in general, all required materials and labor
for the correct completion of all work.
Price also includes the execution of any
test indicated in the project specifications
or ITP and its report.
Excluded: priming irrigation and bituminous/ oily
mixture of granular material
Measurement The filling volume shall be measured as
system: specified on approved drawings,
considering, as general rule, sidewalls of
the excavated area as vertical, unless
otherwise specified by Contractor.
Backfilling due to any additional widening
of grades, berms, any slopes that are not
as specified on approved drawings as well
as the removal of excess material from
construction of slopes, shall not be
measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

CW.03.BK.TF._x::x Supply and execution of backfilling inside tank rings or tank


bases with priming irrigation and bituminous/ oily mixture of
granular material.
Commodities included: Referred to: Backfilling in tank bases with bituminous
material or oily mixtures.
CW03BKTF_BMTB000000S
CW03BKTF_ESTB000000S Price content. The unit price includes material supply
CW03BKTF_CMTR000000S Included but not with characteristics according project
limited to: requirements and specifications for each
kind of material, transportation,
intermediate storage, preparation of area
to be backfilled (scarifying and
recompacting), spreading, compaction,
required machinery, auxiliary means and,
in general, all required materials and labor
for the correct completion of all work.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 43 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Price also includes the execution of any


test indicated in the project specifications
or ITP and its report.
Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings
considering, as general rule, sidewalls of
the excavated area as vertical, unless
otherwise specified by Contractor.
Backfilling due to any additional widening
of grades, berms, any slopes that are not
as specified on approved drawings as well
as the removal of excess material from
construction of slopes, shall not be
measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

2.3.2.4 Commodity group CW03.BK.MW. Backfilling in maritime works, slope


protections and other special activities.

CW.03.BK.MW._RRx::x Supply and execution of RIP RAP with stone weight size according
with project standards and specifications.
Commodities included: Referred to: Backfilling with RIP-RAP material

CW03BKMW_RR000000S Price content. The unit price includes material supply with
CW03BKMW_RR000100S Included but not characteristics according with project
limited to: requirements and specifications for each
kind of material, transportation,
intermediate storage, access ramp,
preparation of area to be backfilled
(scarifying and recompacting), geotextile
layer, spreading of backfill in layers,
irrigation requirements, compaction of
these layers, leveling, grading and
compaction of surface finish grade, refining
of slopes, required machinery, auxiliary
means and, in general, all required
materials and labor for the correct
completion of all work. Price also includes
the execution of any test indicated in the
project specifications or ITP and its report.
Excluded:

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 44 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Measurement The filling volume shall be measured as


system: specified on approved drawings.
Backfilling due to any additional widening
of grades, any slopes that are not as
specified on approved drawings as well as
the removal of excess material from
construction of slopes, shall not be
measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

2.3.2.5 Commodity group CW03.BK.PI. Particular Items.

CW.03.BK.PI._CG000000S Backfilling with clean gravel carried out in layers.


Commodities included: Referred to: Spreading and leveling of gravel for soil
improvements, bases under buildings slabs,
CW03BKPI_CG000000S special backfillings in foundations, pits, etc.

Price content. The unit price includes material supply with


Included but not characteristics according project
limited to: requirements and specifications for each
kind of material, transportation,
intermediate storage within the work site,
machinery, preparation of area to be
backfilled (scarifying and recompacting),
spreading in layers and compacting
according with project requirements,
irrigation, auxiliary means, safety resources
and, in general, all required materials and
labor for the correct and completion of all
work. Price also includes the execution of
any test indicated in the project
specifications or ITP and its report.
Excluded: Gravel in non-paved areas
Measurement The filling volume shall be measured as
system: specified on approved drawings.
Backfilling due to any additional widening of
grades, berms, any slopes that are not as
specified on approved drawings as well as
the removal of excess material from
construction of slopes, shall not be
measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 45 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.3.3 Commodity group CW03.TR. Transport of materials.

CW.03.TR.._xx000000S Loading, transport and unloading of remainder material from


excavation.
Commodities included: Referred to: Load, transport and unload of excess material
form excavations, inside or outside property
CW03TR_IN000000S limits but into an authorized dumping area
CW03TR_OU000000S Price content. The unit price includes the loading, transport,
Included but not and unloading of excess excavated material.
limited to: Unloading should be inside or outside property
limits but into an authorized dumping area. In
case of outside, the price also includes all costs
associated with the obtaining of dumping
permits, any dumping fees, maintenance and
preparation of material, etc.
Excluded:
Measurement The transport shall be measured as the
system: difference between the excavated volume and
the backfilling material from the excavation, in
accordance with the system of measurement
and payment. Bulking, swelling, or any increase
in volume the material may experience during
its transport, is not measurable and shall not be
paid.
Unit of measure: Cubic meter (m3)

PRE-CAST ELEMENTS SET UP

2.4 Commodity group CW04. “IN-SITU” CONCRETE ELEMENTS.

2.4.1 Commodity group CW04.LN. Lean and mass concretes.

CW.04.LN.._LNxx0005R10 Supply and pouring of lean concrete, 5 <= e <= 10 cm. Concrete
grade and class of exposure as per project requirements, including

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 46 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

any type of additives as colorants, accelerators, retardants, etc.


retardants, etc.
Commodities included: Referred to:
Price content. The unit price includes all materials supply,
CW04LN_LNFN0005R10 Included but not pouring by any means, any kind of formwork,
CW04LN_LNSL0005R10 limited to: protective layers spreading, leveling, curing,
manpower, tools, machinery and, in general,
supply and installation of all required
materials and activities for timely execution
including but not limited to ramming of
bottom, auxiliary formworks, protective
layers (e.g. bitumen, sheets...), water
depletion... and for any concrete type or
admixtures, including all necessary
resources, auxiliary means, machinery and
materials, etc for its correct completion
according to drawings/specifications and
approved ITPs.
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings and it shall be measured
assigning the same surface as the foundation
that is supported. Excess of in width is not
measurable and shall not be paid (even if it is
shown in approved drawings).

Unit of measure: The unit of measure shall be the cubic meter


(m3)

CW.04.LN.._MA000000S Supply and pouring of mass concrete for filling, piping placement,
supports, etc. Concrete grade and class of exposure as per project
requirements, including any type of additives as colorants,
accelerators, retardants, etc.
Commodities included: Referred to:
Price content. The unit price includes supply of material,
CW04LN_MA000000S Included but not pouring by any means, spreading, vibrating,
limited to: leveling, curing, finishing of surfaces, repair of
any defect that concrete may have,
manpower, tools, machinery and, in general,
all required materials and activities for timely
execution including but not limited to
ramming of bottom, auxiliary formworks,
protective layers (e.g. bitumen, sheets...),
water depletion... and for any concrete type or
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 47 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

admixtures, including all necessary resources,


auxiliary means, machinery and materials, etc
for its correct completion according to
drawings/specifications and approved ITPs.
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings
Unit of measure: The unit of measure shall be the cubic meter
(m3)

CW.04.LN.._CY000000S Supply and pouring of cyclopean concrete for filling, piping placement,
supports, etc. Concrete grade and class of exposure as per project
requirements, including any type of additives as colorants,
accelerators, retardants, etc.
Commodities included: Referred to: Means a special kind of mass concrete that is
having embedded large stones (around 30 cm
CW04LN_CY000000S diameter)
Price content. The unit price includes supply of material,
Included but not pouring by any means, spreading, vibrating,
limited to: leveling, curing, finishing of surfaces, repair of
any defect that concrete may have, manpower,
tools, machinery and, in general, all required
materials and labor for the correct completion
of all work
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings
Unit of measure: The unit of measure shall be the cubic meter
(m3)

2.4.2 Commodity groups CW04.CO. Concretes.

2.4.2.1 Commodity groups CW04.CO.nn Concretes.

CW04COnn_x::x Supply and pouring of reinforced concrete. Concrete grade and


class of exposure as per project requirements, including any
type of additives as colorants, accelerators, retardants, etc.
Commodities included: Referred to: To clarify the application of the different
prices, it is considered as “foundation” all
structural elements in contact with soil
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 48 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04CO25_FD000000S that transmit to the ground the loads of


CW04CO25_EL000000S the supported structures or equipment
CW04CO25_ET000000S (equipment beds, foots, tie beams,
CW04CO25_SL000000S footings for piling, slabs, etc.).
CW04CO28_FD000000S In case of piled foundation, the term
CW04CO28_EL000000S “foundation” shall be applied only to the
CW04CO28_ET000000S foundation over the pile or the pile cap.
CW04CO28_SL000000S
It is considered as “pedestal” all
CW04CO30_FD000000S
monolithic structural elements that lean
CW04CO30_EL000000S
on a foot and support the weight of
CW04CO30_ET000000S structures and equipment.
CW04CO30_SL000000S
CW04CO32_FD000000S Columns, walls and pedestals less than 1
CW04CO32_EL000000S meter high (measured from the upper
CW04CO32_ET000000S side of the foot) shall be considered as
CW04CO32_SL000000S foundations:
CW04CO35_FD000000S
CW04CO35_EL000000S Lining for electrical / piping trenches
CW04CO35_ET000000S includes the concrete for the bottom slab,
CW04CO35_SL000000S as well as the walls (external and
CW04CO35_CH000000S internal).
CW04CO50_FD000000S Figure 8.1 specifies the difference
CW04CO50_EL000000S between concrete in foundation and
CW04CO50_ET000000S concrete in colums, beams and walls
CW04CO50_SL000000S
Price content. The unit price includes supply of material,
Included but not pouring by any means, spreading,
limited to: vibrating, leveling, curing, finishing of
surfaces, repair of any defect that
concrete may have, manpower, tools,
machinery and, in general, all required
materials and all necessary resources,
auxiliary means, consumables, execution
of construction joints, required activities,
etc. for its correct completion according
to drawings, specifications and approved
ITP´s and regardless of ground
conditions..

Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 49 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Unit of measure: The unit of measure shall be the cubic


meter (m3)

2.4.2.2 Commodity groups CW04.CO.35 Concretes.

CW.04.CO.35._SNx::x Construction of Soil Nailing Wall, including equipment


mobilization, perforations, injection, steel corrugated bars,
projection of shotcrete 35 N/mm2 cement MS, and
reinforcement with mesh.
Commodities included: Referred to:
Price content. The unit price includes supply of all
CW04CO35_SN090000U08 Included but not required material, surface preparation,
CW04CO35_SN180008R16 limited to: cleaning of debris and natural land,
perforations, anchoring of bars up to the
required length, injection, mesh
installation, pouring of shotcrete by any
means, spreading, vibrating, leveling,
curing, finishing of surfaces, repair of any
defect that concrete may have,
manpower, tools, machinery and
equipment including mobilization and
demobilization and, in general, all required
materials and labor for the correct
completion of all work.

Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings.

Unit of measure: The unit of measure shall be the square


meter (m2)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 50 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 51 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.4.3 Commodity group CW04.SF.

2.4.3.1 Commodity group CW04.SF.IS. Small foundations cast “in-situ”

CW.04.SF.IS._x::x Supply of materials and execution of small footing cast "in situ"
with reinforced concrete.
Commodities included: Referred to: Small foundations (foots, sleepers, pipe and
CW04SFIS_25000U025 stair supports, etc.) to support equipment
CW04SFIS_25025R050 and pipes. The concrete volume is up to 1 m3.
CW04SFIS_25050R100 When the volume exceeds 1 m3, the small
CW04SFIS_28000U025 foundation shall be measured and paid
CW04SFIS_28025R050 according with the unit prices of the different
CW04SFIS_28050R100 components (excavation, filling, concrete,
CW04SFIS_30000U025 reinforcement, formwork, embedded
elements, etc.)
CW04SFIS_30025R050
Price content. The price includes material supply, work
CW04SFIS_30050R100
Included but not laying out and plotting, demolitions,
CW04SFIS_32000U025
limited to: excavations, fillings, loading and transporting
CW04SFIS_32025R050
of excess material to a dumping area,
CW04SFIS_32050R100 dumping fees, formwork, rebars, embedded
CW04SFIS_35000U025 elements, anchor bolts, concrete works,
CW04SFIS_35025R050 mortars, auxiliary means, tools, machinery
CW04SFIS_35050R100 and, in general, all required materials and
CW04SFIS_40000U025 labor for the correct completion of all work.
CW04SFIS_40025R050 Excluded: Foundations higher than 1 m3
CW04SFIS_40050R100 Measurement The unit shall be measured as stated on
CW04SFIS_50000U025 system: approved drawings. In cases where small
CW04SFIS_50025R050 footings/concrete support are embedded
CW04SFIS_50050R100 into pavement, its volume shall be
CW04SFIS_MC000U025 categorized as shown below for
CW04SFIS_MC025R050 measurement purposes.
CW04SFIS_MC050R100 Unit of measure: The unit of measurement is the element
executed (n)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 52 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.4.3.2 Commodity group CW04.SF.PC. Small foundations precast.

CW.04.SF.PC._COx::x Supply of materials and execution of precast small footing with


reinforced concrete.
Commodities included: Referred to: Small foundations (foots, sleepers, pipe and
stair supports, etc.) to support equipment
CW04SFPC_CO000U025 and pipes. The concrete volume is up to 1
CW04SFPC_CO025R050 m3. Made as precast in a lay-down area
CW04SFPC_CO050R100 When the volume exceeds 1 m3, the small
foundation shall be measured and paid
according with the unit prices of the different
components (excavation, filling, concrete,
reinforcement, formwork, embedded
elements, etc.)
Price content. The price includes material supply, work
Included but not laying out and plotting , demolitions,
limited to: excavations, fillings, loading and transporting
of excess material to a dumping area,
dumping fees, formwork, rebars, embedded
elements, anchor bolts, concrete works,
mortars, auxiliary means, tools, load at
precast area transport and unload of precast
foundations at site, installation and leveling,
machinery and, in general, all required
materials and labor for the correct
completion of all work.
Excluded: Foundations higher than 1 m3
Measurement The unit shall be measured as stated on
system: approved drawings.
Unit of measure: The unit of measurement is the element
executed (n)

2.4.3.3 Commodity group CW04.SF.PC_TI. Transport within Property Limits and


installation of small precast footing.

CW.04.SF.PC._TIx::x Transport within Property Limits and installation of small precast


footing
Commodities included: Referred to: Small foundations setting (foots, sleepers,
pipe and stair supports, etc.) to support
CW04SFPC_TI000U025 equipment and pipes. The concrete volume is
CW04SFPC_TI025R050 up to 1 m3. Made as precast in a lay-down
area

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 53 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04SFPC_TI050R100 When the volume exceeds 1 m3, the small


foundation shall be measured and paid
according with the unit prices of the different
components (excavation, filling, concrete,
reinforcement, formwork, embedded
elements, etc.)
Price content. The price includes, work laying out and
Included but not plotting , auxiliary works, demolitions,
limited to: excavations, fillings, small foundations lifting,
setting, leveling, alignment, loading and
transporting of excess material to a dumping
area, dumping fees, formwork, rebars,
embedded elements, anchor bolts, concrete
works, mortars, auxiliary means, tools, load at
precast area transport and unload of precast
foundations at site, installation and leveling,
machinery and, in general, all required
materials and labor for the correct completion
of all work.
Excluded: Foundations higher than 1 m3
Measurement The unit shall be measured as stated on
system: approved drawings.
Unit of measure: The unit of measurement is the element
executed (each)

2.4.4 Commodity group CW04.TH. Thickened slab footing.

CW.04.TH.._x::x Supply of materials and execution of thickened slab footing cast


"in situ" with reinforced concrete.
Commodities included: Referred to: Means paving or slabs thickened in certain
locations to support additional weight as
CW04TH_25000U025 pipes, stairs, equipment etc., including its
CW04TH_25025R050 corresponding pedestal. The concrete
CW04TH_25050R100 volume is up to 1 m3.
CW04TH_28000U025 When the volume exceeds 1 m3, the
CW04TH_28025R050 thickened slab footing shall be measured
CW04TH_28050R100 and paid according with the unit prices of
CW04TH_30000U025 the different components (excavation,
filling, concrete, reinforcement, formwork,
CW04TH_30025R050
embedded elements, etc.)
CW04TH_30050R100
Price content. The price includes material supply, work
CW04TH_32000U025
Included but not laying out and plotting , demolitions,
CW04TH_32025R050
limited to: excavations, drilling of holes fillings with

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 54 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04TH_32050R100 epoxy, loading and transporting of excess


CW04TH_35000U025 material to a dumping area, dumping fees,
CW04TH_35025R050 formwork, rebars, embedded elements,
CW04TH_35050R100 anchor bolts, concrete works, mortars,
CW04TH_40000U025 auxiliary means, tools, machinery and, in
CW04TH_40025R050 general, all required materials and labor
CW04TH_40050R100 for the correct completion of all work.
CW04TH_50000U025 Excluded: Paving heels (included in concrete paving
commodities)
CW04TH_50025R050
Measurement The unit shall be measured as stated on
CW04TH_50050R100
system: approved drawings. The pair formed by a
thickened slab footing and its
corresponding pedestal if exists shall be
measured as one single small foundation.
To determine the volume, the thickened
slab footing shall be measured from the
lower point of the thickened slab up to the
bottom level of paving, and the pedestal
shall be measured from the top level of
paving up to the top level of pedestal. The
sum of both volumes shall be lower than 1
cubic meter
Unit of measure: The unit of measurement is the element
executed (n)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 55 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.4.5 Commodity group CW04.MO. Mortars and resins.

CW.04.MO.._x::x Supply and application of mortar/resin.


Commodities included: Referred to:
Price content. The unit price includes supply, transportation,
CW04MO_CM000100S Included but not intermediate storage, preservation, handling,
CW04MO_CM000200S limited to: application, preparation, supports, pouring by
CW04MO_NS000100S any means or machinery, formwork (except
for anchor pockets), and any other

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 56 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04MO_SL000100S requirement, regardless of nature, necessary


CW04MO_SR000100S for the correct installation of the required unit
CW04MO_ER000100S as per manufacturer’s instructions manual,
CW04MO_ER000200S project drawings, specifications, standards
and approved ITPs.
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings.
Unit of measure: The unit of measure shall be the cubic meter
(m3)

CW.04.MO.._ER001000S Supply and application of epoxy resin for the union between
concretes of different ages.
Commodities included: Referred to: Application of epoxy treatment over an old
existing concrete prior to extend that
CW04MO_ER001000S concrete volume with a new element
attached.
Price content. The unit price includes supply, transportation,
Included but not intermediate storage, preservation, handling,
limited to: application, preparation, supports, pouring by
any means or machinery, formwork (except
for anchor pockets), and any other
requirement, regardless of nature, necessary
for the correct installation of the required unit
as per manufacturer’s instructions manual,
project drawings, specifications, standards
and approved ITPs.
Excluded: Application of epoxy between concretes due
to construction delays, execution mistakes,
defects or any other reason from
SUBCONTRACTOR responsibility
Measurement The unit shall be measured as stated on
system: approved drawings
Unit of measure: The unit of measure shall be the square meter
(m2)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 57 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.4.6 Commodity group CW04.FW. Formworks.

2.4.6.1 Commodity group CW04.FW.SI. Supply and erection of straight formwork

CW.04.FW.SI._x::x Supply and erection of straight formwork


Commodities included: Referred to: To clarify the application of the different
prices, it is considered as foundation all
CW04FWSI_FD000100S structural elements in contact with soil that
CW04FWSI_PI000100S transmit to the ground the charges of the
CW04FWSI_BE000100S supported structures or equipment (foots, tie
CW04FWSI_SL000100S beams, footings for piling, slabs, etc.).
CW04FWSI_ET000100S Formworks of columns and walls less than 1
meter high (measured from the upper side of
the foot) shall be considered as foundations.

It is considered as “pedestal” all monolithic


structural elements that lean on a foot and
support the weight of structures and
equipment.

Columns, walls and pedestals less than 1


meter high (measured from the upper side of
the foot) shall be considered as foundations.

Formwork for manholes, pits or sum pits with


internal volume bigger than 12 cu. m. shall be
measured in this item.

Lining for electrical / piping trenches includes


the concrete for the bottom slab, as well as
the walls (external and internal).

Piping and equipment supports, sleepers,


paving thickened slab footings, pedestal for
stairs and non-elevated pedestal for turbines
shall be considered as foundations.
In general, the criteria of application of the
different prices is the same as concrete, figure
8.1 clarifies some of them.
Price content. The unit price includes all aspects of
Included but not prefabrication of the required material,
limited to: supply, transportation, handling and
intermediate storage, construction
engineering, layout works and plotting,

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 58 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

installation, shoring, bracing, temporary


supports or any other element to ensure
stability and proper execution, spacers,
removal of formwork, preservation and
safety/housekeeping measures, cleaning and
preparation of surface formwork for
subsequent work, manpower, any material
costs including any proportional part of cost
for use of material, formwork for corners and
molding, chamfers, interior and exterior
curvature formwork, drip edges, sealing
works, all accessories, all required fastening
material (i.e. nails, bolts, etc.), hand tools,
workshop machinery and, in general, all
required materials and labor for the correct
completion of all work according to Project
drawings/specifications and approved ITPs.

Price for elevated slabs and beams also


includes design and calculations, supply,
handling, installation and leveling, load
testing, rental, dismantling of
falsework/shoring systems for elements up to
3 meters of clearance height.

the price also includes the part of formwork


used for safety requirements, holes, access
ways, etc.

Excluded: Formworks for lean concrete, mortars or


precast elements, channels, in situ drainage
elements, concrete paving and roads, small
footings, concrete supports/sleepers with
volume equal or less than 1 m3, pits or sum
pits with internal volume equal or less than 12
m3
Measurement The unit shall be measured as stated on
system: approved drawings, measuring the formwork
in contact with concrete. Curved surfaces
shall be measured under these commodities,
to cover the increase on price because the use
of curved formwork, commodity
CW.04.FW.MS._000100S shall also be used.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 59 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Unit of measure:
The unit of measure shall be square meter
(m2) of formwork in contact with concrete,
measured on approved engineering drawings.
2.4.6.2 Commodity group CW04.FW.MS. Miscellaneous for Formworks.

CW.04.FW.MS._000100S Increase in straight formwork price because of using curve


formwork.
Commodities included: Referred to: Increase on prices CW04FWSI_x::x due to the
use of curved formwork. The unit price shall
CW04FWMS_000100S be only the increase from the straight
formwork price and shall cover the extra
labor manhours, increase on cost of
materials.
Price content. The unit price includes all aspects of
Included but not prefabrication of the required material,
limited to: supply, layout works and plotting,
installation, shoring, bracing, removal of
formwork, cleaning and preparation of
surface formwork for subsequent work,
manpower, any material costs including any
proportional part of cost for use of material,
formwork for corners and molding, interior
and exterior curvature formwork, drip edges,
sealing works, all accessories, all required
fastening material (i.e. nails, bolts, etc.), hand
tools, workshop machinery and, in general, all
required materials and labor for the correct
completion of all work according to Project
drawings/specifications and approved ITPs.

the price also includes the part of formwork


used for safety requirements, holes, access
ways, etc.
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings, measuring the formwork
in contact with concrete
Unit of measure: The unit of measure shall be square meter
(m2)

CW.04.FW.MS._x::x Supply and erection of false work.


Commodities included: Referred to: Falsework is a special structure used to
support elevated formwork. The falsework

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 60 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04FWMS_000200S shall be approved by CONTRACTOR’s Site


CW04FWMS_000300S Manager.
Price content. The price includes design and calculations,
Included but not prefabrication, supply, layout works and
limited to: plotting, installation, shoring, bracing,
adequacy to safety requirements, cleaning
and preparation, accessories, material for
fastening, hand tools, machinery and, in
general, all required materials and labor for
the correct completion of all work.
Excluded:
Measurement For measuring purposes, it will only be
system: considered the horizontal projection of the
falsework in contact with the bottom of the
concrete element. All costs arising from the
false work required for safety issues, openings
and others, shall be included on unit price and
shall not be measured.
Unit of measure: This unit shall be measured and charged by
apparent cubic meter (m3) starting from 3
meters height above High Point Finished
Surface elevation (HPFS).

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 61 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

FALSE WORK VOLUME TO BE


MEASURED

3m 3m
H.P.F.S. SLAB

FALSE WORK VOLUME TO BE


MEASURED

3m
H.P.F.S.

top of Foundation level

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 62 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.04.FW.MS._000400S Supply and installation of lost formwork, deck type or similar in


elevated slabs.
Commodities included: Referred to:
Price content. The unit price includes material supply, laying
CW04FWMS_000400S Included but not out and plotting, installation, shoring,
limited to: bracing, manpower, accessories, material for
fastening, connectors, trimming elements,
tools, machinery and, in general, all required
materials and labor for the correct
completion of all work.
Galvanized steel ribbed metal lath will not be
measurable nor paid if its use is not
previously approved by CONTRACTOR.
Excluded:
Measurement It shall be measured the horizontal projection
system: of the concrete element in contact with deck
formwork and measured on approved
drawings.
Overlaps, surplus, cutting and cropping… are
not measurable and shall not be paid (even if
it is shown in approved drawings).
Unit of measure: The unit of measure shall be square meter
(m2) apparent cubic meter (m3)

CW.04.FW.MS._000500S Execution of pockets for anchor bolts placement.


Commodities included: Referred to: Anchor boxes and pockets in concrete.
Price content. The unit price includes layout works and
CW04FWMS_000500S Included but not plotting, supply and installation of
limited to: formworks, removal of formworks, all
required hand tools and accessories, auxiliary
means, machinery, and any other
requirement, regardless of nature, necessary
for the correct installation of the required
unit.
Galvanized steel ribbed metal lath will not be
measurable nor paid if its use is not
previously approved by CONTRACTOR.
Excluded: Pockets made with Polystyrene/Foam instead
of formworks shall not be measured nor paid.
Measurement The unit shall be measured as is stated on
system: approved drawings.
Unit of measure: The unit of measure shall be cubic decimeter
(dm3)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 63 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.4.7 Commodity group CW04.RB. Reinforcing steel.

CW.04.RB.._SIx::x Supply and installation of corrugated steel or electro welded wire


mesh for reinforcements with yield strength according with project
requirements.
Commodities Referred to:
included: Price content. The unit price includes material supply, bar
Included but not bending drawings, intermediate storage and
CW04RB_SI000100S limited to: transport, labor costs (cutting and bending),
CW04RB_SI000200S installation, manpower, tools, machinery and, in
CW04RB_SI000300S general, all required materials and labor for the
CW04RB_SI000400S correct completion of all work.
CW04RB_SI000500S
Provision for spacers, any type, auxiliary items,
restraining cable, overlaps and splicing not
measurable (see measurement system), cutting
and cropping shall be included on unit price and
therefore shall not be measured.

In case of coated re-bars, the price shall include


supply and application of coating material. The
material shall accomplish with project
standards, specifications and drawings.
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings. Overlaps shall be measured
according to the following criteria:

There are two overlapping types:


1) Bendings, additional reinforcing bars,
construction joints, anchoring, etc. It
shall be measured only when they are
shown on Contractor drawings.
2) Splicing due to exceed of commercial
lengths or splices not related to
construction joints. The overlapped bar
shall not be measured in any case even
when they are specified and shown on
Contractor Drawings. It shall be
measured as a continuous bar.

Regarding the type 1), only when the


overlap/splicing is shown on CONTRACTOR

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 64 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

DRAWINGS, the measuring criteria shall be the


following:

1)a. Bendings at foundations side ends. Both


bottom and top bars shall be measured up to the
half of the foundation thickness.

1)b. Bendings/anchoring due to bars that


crosses from one element to another (starting
of pillars from foundations, anchoring beams
to pillars, etc.) It shall be measured according to
the minimum requirement shown on standard
drawings and or specifications.

1)c. Additional overlapped reinforcing bars. It


shall be measured according to the length
shown on Contractor drawing.

1)d. Construction joints. It shall be measured


according to the length shown on Contractor
drawings.

OVERLAPS NOT SHOWN ON CONTRACTOR


DRAWINGS SHALL NOT BE MEASURED IN ANY
CASE.

To clarify the following figures 7.4.1 shown


some typical examples with the corresponding
applicable code.

Except otherwise specified in written by


CONTRACTOR, bar bending schedules shall not
be considered in any case as a measurable
document.

Unit of measure: The unit of measure shall be kilogram (kg).

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 65 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Fig. 7.4.1 examples of overlapping measurement criteria

type 1)a. H/2


H/2

J = bending measurable length


J
H/2

TYPE 2)
H/2

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 66 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

TYPE 1)b.

TYPE 2)

Not construction joint:


Not Measurable

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 67 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

TYPE 1)b.

Bending according to
standard drawings

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 68 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Standard bending.
Type 1)b.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 69 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Type 1)a.

Construction joint.
Type 1)d.

Standard bending.
Type 1)b.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 70 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Type 2)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 71 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Example: Large length slab >12 m


Type 2)
Type 1)a. Type 1)a.
Type 2)

02070-FCK-CIV-DRW-230

Ejemplo de solape de barras cir

Additional bar
Type 1)c.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 72 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.4.8 Commodity group CW04.EE. Embedded elements.

2.4.8.1 Commodity group CW04.EE.SP Steel plates and profiles and embedded
elements.

CW.04.EE.SP._x::x Supply, prefabrication and installation at site of steel elements to


be embedded in concrete (plates, steel rugs, sleeves, tubes,
profiles) and sliding equipment plates.
Commodities included: Referred to:
Price content. The unit price includes supply of material,
CW04EESP_CS000100S Included but not prefabrication, surface preparation (blasting),
CW04EESP_GS000100S limited to: primer, transportation, intermediate storage,
CW04EESP_SS000100S handling, alignment, leveling and installation,
accurate surveying, temporary supports prior
to concrete pouring, supply and installation of
all templates, drillings (screw and machine
type included), formation of threaded holes,
and any other requirement, regardless of
nature, necessary for the correct installation
of the required unit as per project
specifications, standards and approved ITPs.
Excluded:
Measurement The unit shall be measured on approved
system: drawings, and applying weight as specified in
the manufacturer’s catalog. When these
weights are not specified, weight shall be
calculated applying the density of 7.85 t/m3.

Excesses due to cuttings or cropping,


excessive lamination, ancillary assembling, or
any other temporary material or process are
not measurable and therefore not
chargeable.
Unit of measure: The unit of measure shall be kilogram (kg).

CW.04.EE.SP._IN000100S Installation at site of steel elements to be embedded in concrete,


supply excluded.
Commodities included: Referred to: Steel Materials to be embedded in concrete
supplied by others.
CW04EESP_IN000100S Price content. The unit price includes prefabrication if
Included but not required, surface preparation (blasting),
limited to: primer, transportation, intermediate
storage, handling, alignment, leveling and
installation, accurate surveying, temporary
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 73 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

supports prior to concrete pouring, supply


and installation of all templates, drillings
(screw and machine type included),
formation of threaded holes, and any other
requirement, regardless of nature, necessary
for the correct installation of the required
unit as per project specifications, standards
and approved ITPs.
Excluded: Supply of materials to be embedded except
auxiliary materials required for the correct
execution of the work.
Measurement The unit shall be measured on approved
system: drawings, and applying weight as specified in
the manufacturer’s catalog. When these
weights are not specified, weight shall be
calculated applying the density of 7.85 t/m3.

Excesses due to cuttings or cropping,


excessive lamination, ancillary assembling, or
any other temporary material or process are
not measurable and therefore not
chargeable.
Unit of measure: The unit of measure shall be kilogram (kg).

2.4.8.2 Commodity group CW04.EE.EP. Embedded piping and duct banks.

CW.04.EE.EP._x::x Supply and installation of PVC / CPVC piping, embedded in


reinforced concrete.
Commodities included: Referred to:
Price content. The unit price includes the material supply,
CW04EEEP_PVSIM000020 Included but not transportation, intermediate storage,
CW04EEEP_PVSIM000024 limited to: handling, alignment, leveling and
CW04EEEP_PVSIM000025 installation, layout works and plotting,
CW04EEEP_PVSIM000030 temporary supports, accessories, joints
CW04EEEP_PVSIM000038 (elastic joint can be glued or not),
CW04EEEP_PVSIM000050 lubricants, hand tools, auxiliary means and,
CW04EEEP_PVSIM000075 in general, all required materials and labor
CW04EEEP_PVSIM000090 for the correct completion of all work as per
project specifications, standards and
CW04EEEP_PVSIM000100
approved ITPs.
CW04EEEP_PVSIM000110
CW04EEEP_PVSIM000125
In case of conduits, unit price shall include
CW04EEEP_PVSIM000140 the mandrel test and supply and erection of
CW04EEEP_PVSIM000150 cable pulling guides.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 74 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04EEEP_PVSIM000160
CW04EEEP_PVSIM000180 Installation of fittings and valves shall also
CW04EEEP_PVSIM000200 be included in unit prices
CW04EEEP_PVSIM000250 Excluded: Earth works (excavation and backfillings)
CW04EEEP_PVSIM000300 Measurement The unit shall be measured to axes of the
CW04EEEP_PVSIM000350 system: pipeline of correctly installed piping, as
CW04EEEP_PVSIM000500 specified on approved drawings.
CW04EEEP_PVSUI000400 Unit of measure: The unit of measure shall be linear meter
CW04EEEP_PVINI000400 (lm).
CW04EEEP_PVSUI000600
CW04EEEP_PVINI000600
CW04EEEP_PVSUI000800
CW04EEEP_PVINI000800
CW04EEEP_CPSIM000038

CW04EEEP_HPx::x Supply and installation of HDPE piping, embedded in reinforced


concrete.
Commodities included: Referred to:
Price content. The unit price includes the material supply,
CW04EEEP_HPSIM000025 Included but not transportation, intermediate storage,
CW04EEEP_HPSIM000050 limited to: handling, alignment, leveling and
CW04EEEP_HPINM000050 installation, layout works and plotting,
CW04EEEP_HPSIM000075 temporary supports, accessories, joints
CW04EEEP_HPINM000075 (elastic joint can be glued or not),
CW04EEEP_HPSIM000025 lubricants, hand tools, auxiliary means
CW04EEEP_HPSIM000050 and, in general, all required materials and
labor for the correct completion of all work
as per project specifications, standards and
approved ITPs.

In case of conduits, unit price shall include


the mandrel test and supply and erection
of cable pulling guides.

Installation of fittings and valves shall also


be included in unit prices
Excluded: Earth works (excavation and backfillings)
Measurement The unit shall be measured to axes of the
system: pipeline of correctly installed piping, as
specified on approved drawings.
Unit of measure: The unit of measure shall be linear meter
(lm).

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 75 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04EEEP_GSx::x Supply and installation of HOT DIP GALVANIZED CONDUIT piping,


embedded in reinforced concrete.
Commodities included: Referred to:
Price content. The unit price includes the material supply,
CW04EEEP_GSSII000200 Included but not transportation, intermediate storage,
CW04EEEP_GSSII000400 limited to: handling, alignment, leveling and
CW04EEEP_GSSII000600 installation, layout works and plotting,
temporary supports, accessories, joints
(elastic joint can be glued or not), lubricants,
hand tools, auxiliary means and, in general,
all required materials and labor for the
correct completion of all work as per project
specifications, standards and approved ITPs.

In case of conduits, unit price shall include


the mandrel test and supply and erection of
cable pulling guides.

Installation of fittings and valves shall also be


included in unit prices
Excluded: Earth works (excavation and backfillings)
Measurement The unit shall be measured to axes of the
system: pipeline of correctly installed piping, as
specified on approved drawings.
Unit of measure: The unit of measure shall be linear meter
(lm).

2.4.9 Commodity group CW04.AB. Anchor bolts.

2.4.9.1 Commodity group CW04.AB.ST. Standard anchor bolts.

CW.04.AB.ST._x::x Supply and setting of carbon steel or galvanized carbon steel


anchor bolts with a yield strength as required.
Commodities included: Referred to:
Price content. The unit price includes fabrication, supply
CW04ABST_CS030U350 Included but not (when applicable), materials certificates,
CW04ABST_CS056U350 limited to: transportation, handling, intermediate
CW04ABST_CS076U350 storage, alignment, leveling and installation,
CW04ABST_CS140U350 all related accessories (i.e. sleeves, nuts,
CW04ABST_CS030F351 washers, bearing plates, etc.), layout works
CW04ABST_CS056F351 and setting out, accurate surveying, design,
CW04ABST_CS076F351 fabrication, supply and installation of all
templates (except for turbines), drillings
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 76 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04ABST_CS140F351 (screw and machine type included),


CW04ABST_FP030U350 temporary supports, tack welds, protections,
CW04ABST_FP056U350 preservation of threaded projections,
CW04ABST_FP076U350 labeling and any other requirement,
CW04ABST_FP140U350 regardless of nature, necessary for the
correct complete installation of the required
unit as per project specifications, standards
and approved ITPs.
If required, galvanizing is also included in
supply rate.
Excluded:
Measurement Bent anchor bolts, thread-each end anchor
system: bolts, headed anchor bolts, swedged anchor
bolts, all-thread anchor rods, Portland bolts,
or any other kind of anchor bolt will be
measured as its rod’s weight solely.

For measurement purposes related


accessories (i.e. sleeves, nuts, washers,
plates, etc.) or any temporary material for
the correct completion of required work are
not measurable and therefore not paid
separately.

When its weight is not specified in a


manufacturer’s catalogue, weight shall be
calculated applying the density of 7.85 t/m3.

Unit of measure: The unit of measure shall be kilogram (kg) of


the rod’s weight.

CW.04.AB.ST._SS000100S Extra price for SS anchor bolts


Commodities included: Referred to: additional cost for supplying Stainless steel
bolts. The unit price shall be only the
CW04ABST_SS000100S increase on price from carbon steel material.
Quantities under this commodity are also
included in the above commodities
CW04ABST_CSx::x.
Price content. The unit price includes additional fabrication
Included but not and supply costs,
limited to:
Excluded:
Measurement Bent anchor bolts, thread-each end anchor
system: bolts, headed anchor bolts, swedged anchor
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 77 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

bolts, all-thread anchor rods, Portland bolts,


or any other kind of anchor bolt will be
measured as its rod’s weight solely.

Therefore, for measurement purposes


related accessories (i.e. sleeves, nuts,
washers, plates, etc.) or any temporary
material for the correct completion of
required work are not measurable and
therefore not paid separately.
When its weight is not specified in a
manufacturer’s catalogue, weight shall be
calculated applying the density of 7.85 t/m3.
Unit of measure: The unit of measure shall be kilogram (kg) of
the rod’s weight.

CW.04.AB.ST._ANINx::x Setting of anchor bolts any kind of material. Supply excluded.


Commodities included: Referred to: Anchor bolts to be embedded in concrete
supplied by others.
CW04ABST_ANIN000U030 Price content. The unit price includes surface preparation
CW04ABST_ANIN030R056 Included but not (blasting), primer, transportation,
CW04ABST_ANIN056R076 limited to: intermediate storage, handling, alignment,
CW04ABST_ANIN076R140 leveling and installation, all related
accessories (i.e. sleeves, nuts, washers,
bearing plates etc.), accurate surveying,
temporary supports prior to concrete
pouring, supply and installation of all
templates (except for turbines), drillings
(screw and machine type included),
temporary supports, protections, labeling,
formation of threaded holes, and any other
requirement, regardless of nature,
necessary for the correct installation of the
required unit as per project specifications,
standards and approved ITPs.
Excluded: Fabrication and Supply of Anchor bolts to
be embedded except auxiliary materials
required for the correct execution of the
work.
Measurement Bent anchor bolts, thread-each end anchor
system: bolts, headed anchor bolts, swedged
anchor bolts, all-thread anchor rods,
Portland bolts, or any other kind of anchor

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 78 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

bolt will be measured as its rod’s weight


solely.

For measurement purposes related


accessories (i.e. sleeves, nuts, washers,
plates, etc.) or any temporary material for
the correct completion of required work
are not measurable and therefore not paid
separately.
Excesses due to cuttings or cropping,
excessive lamination, ancillary assembling,
or any other temporary material or process
are not measurable and therefore not
chargeable.
Unit of measure: The unit of measure shall be kilogram (kg).

2.4.9.2 Commodity group CW04.AB.EX. Expansion anchor bolts.

CW.04.AB.EX._x::x Supply and setting of expansion bolts HILTI type or similar.


Commodities included: Referred to: Anchor bolts Hilti model or similar
Price content. Unit price includes the supply, layout works
CW04ABEX_0000U12 Included but not and plotting, surface cleaning, drilling, hole
CW04ABEX_012R018 limited to: blow-out, transportation, intermediate
CW04ABEX_018R030 storage, handling, alignment, leveling and
installation in hardened concrete as per
manufacturer’s instructions manual, project
specifications, standards and approved ITP’s.
Excluded:
Measurement The unit shall be measured by unit in
system: accordance with applicable drawings.
Unit of measure: The unit of measure shall be the installed
anchor bolt (n)

2.4.9.3 Commodity group CW04.AB.CH. Chemical anchor bolts.

CW.04.AB.CH._x::x Supply and setting of Chemical anchor bolts HILTI type or similar.
Commodities included: Referred to: Anchor bolts Hilti model or similar
Price content. Unit price includes supply, layout works and
CW04ABCH_0000U12 Included but not plotting, surface cleaning, drilling, hole blow-
CW04ABCH_012R018 limited to: out and installation in hardened concrete as
CW04ABCH_018R030 per manufacturer’s instructions manual,
project specifications, standards and approved
ITP’s.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 79 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Unit price for chemical anchor bolts also


includes all accessories, consumables and tools
required for installation.
Excluded:
Measurement The unit shall be measured by unit in
system: accordance with applicable drawings.
Unit of measure: The unit of measure shall be the installed
anchor bolt (n)

2.4.10 Commodity group CW04.ST. Concrete surface treatments and waterproofing.

2.4.10.1 Commodity group CW04.ST.TR. Concrete surface treatments.

CW.04.ST.TR._PS000100S Supply and application of polyethylene sheets under foundations,


and cast-in situ concrete channels.
Commodities included: Referred to:
Price content. The unit price includes material supply of
CW04STTR_PS000100S Included but not suitable material according with project
limited to: standards, specifications and drawings,
manpower, overlaps, any additional
widening, cuttings and cropping, tools,
machinery, auxiliary means, and, in general,
all required materials and labor for the
correct completion of all work as per
manufacturer’s instructions manual, project
specifications, standards and approved ITP’s.
Excluded:
Measurement The unit shall be the area of the supported
system: element as specified on approved drawings.
Unit of measure: The unit of measure is the square meter (m2)

CW.04.ST.TR._x::x Supply and application of complete concrete protection as per


project standards, specifications and drawings.
Commodities included: Referred to: Complete system of concrete surface
treatments required for concrete protection,
CW04STTR_001000S as required by project specifications. For
CW04STTR_002000S concrete below ground or above ground.
CW04STTR_CE000100S Price content. The unit price includes material supply of
Included but not suitable material according with project
limited to: standards, specifications and drawings,
application or installation according with
manufacturer recommendations, manpower,
overlaps, any additional widening, cuttings
and cropping, tools, machinery, auxiliary
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 80 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

means, and, in general, all required materials


and labor for the correct completion of all
work as per manufacturer’s instructions
manual, project specifications, standards and
approved ITP’s.
Excluded:
Measurement The unit shall be the area of the protected
system: concrete as specified on approved drawings.
Unit of measure: The unit of measure is the square meter (m2)

CW.04.ST.TR._ATSI000100S Supply and installation of acid resistant tiles/bricks in concrete


surfaces.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04STTR_ATSI000100S Included but not plotting, material supply, transportation,
limited to: intermediate storage and handling,
manpower, surface preparation (cleaning,
epoxy and polyester resin grouting,
potassium silicate mortar, etc.), trimming,
formation and sealing of joints
(polyisobutylene, epoxy sealing, etc.)
sealing of joints between tiles with
polyester resin, tools, machinery, auxiliary
means and, in general, all required
materials and labor for the correct
completion of all work as per
manufacturer’s instructions manual,
project specifications, standards and
approved ITP’s.
Excluded:
Measurement The unit shall be the area of the protected
system: concrete as specified on approved
drawings.
Unit of measure: The unit of measure is the square meter
(m2)

CW.04.ST.TR._x::x Supply and application of acid/caustic resistant protection in


concrete surfaces.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04STTR_ATIN000100S Included but not plotting, material supply, transportation,
CW04STTR_AC000100S limited to: intermediate storage and handling,
CW04STTR_AC000200S application of material following
manufacturer recommendations,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 81 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04STTR_AC000300S manpower, surface preparation, trimming,


CW04STTR_AC000400S formation and sealing of joints, tools,
CW04STTR_CA000100S machinery, auxiliary means and, in general,
CW04STTR_GV000100S all required materials and labor for the
correct completion of all work as per
manufacturer’s instructions manual, project
specifications, standards and approved
ITP’s.
Excluded:
Measurement The unit shall be the area of the protected
system: concrete as specified on approved
drawings.
Unit of measure: The unit of measure is the square meter
(m2)

CW.04.ST.TR._CGSIx::x Supply and installation of cellular glass layer.


Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04STTR_CGSI0000040 Included but not plotting, material supply, transportation,
CW04STTR_CGSI0000080 limited to: intermediate storage and handling,
CW04STTR_CGSI0000100 installation of material following
manufacturer recommendations,
manpower, surface preparation, trimming,
formation and sealing of joints, tools,
machinery, auxiliary means and, in general,
all required materials and labor for the
correct completion of all work as per
manufacturer’s instructions manual, project
specifications, standards and approved
ITP’s.
Excluded:
Measurement The unit shall be the area of the protected
system: concrete as specified on approved
drawings.
Unit of measure: The unit of measure is the square meter
(m2)

CW.04.ST.TR._PBx::x Supply & Installation of expanded polystyrene boards, with a


density of 25kg/m3.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04STTR_PB2500030 Included but not plotting, material supply, transportation,
CW04STTR_PB2500050 limited to: intermediate storage and handling,
installation of material following
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 82 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04STTR_PB2500075 manufacturer recommendations, manpower,


surface preparation, trimming, formation and
sealing of joints, tools, machinery, auxiliary
means and, in general, all required materials
and labor for the correct completion of all
work as per manufacturer’s instructions
manual, project specifications, standards and
approved ITP’s.
Excluded:
Measurement The unit shall be the area of the protected
system: concrete as specified on approved drawings.
Unit of measure: The unit of measure is the square meter (m2)

CW.04.ST.TR._OT000100S Supply and application of joint sealing Tecnokol-40 by


Tecnogrout, Sika or similar, including all necessary auxiliary
materials for the correct application of the product as per vendor
requirements and recommendations.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04STTR_OT000100S Included but not plotting, material supply, transportation,
limited to: intermediate storage and handling
installation of material following
manufacturer recommendations,
manpower, surface preparation, , tools,
machinery, auxiliary means and, in general,
all required materials and labor for the
correct completion of all work as per
manufacturer’s instructions manual, project
specifications, standards and approved
ITP’s.
Excluded:
Measurement The unit shall be length of the joint as
system: specified on approved drawings.
Unit of measure: The unit of measure is the lineal meter (lm)

2.4.10.2 Commodity group CW04.ST.WP. Waterproofing elements.

CW.04.ST.WP._x::x Supply and installation of HDPE or other plastic liner with


chemical resistance to any fluid leak, installed according with
details shown in project drawings and specifications.
Commodities included: Referred to:
Price content. The unit price includes material supply of
CW04STWP_HP0000U06 Included but not suitable material according with project
limited to: standard, specifications and drawings,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 83 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW04STWP_HP0006R10 manpower, overlaps, any additional


CW04STWP_HP0011R15 widening, cuttings and cropping, tools,
CW04STWP_HP0016R20 machinery, auxiliary means, and, in general,
CW04STWP_HP0021R25 all required materials and labor for the
correct completion of all work as per project
specifications, standards and approved
ITP’s.
Excluded:
Measurement The unit shall be the area of the surface to
system: be waterproofed as specified on approved
drawings.
Unit of measure: The unit of measure is the square meter
(m2)

CW.04.ST.WP._WS000100S Supply and installation of water stop joint in reinforced concrete


elements.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04STWP_WS000100S Included but not plotting, material supply, transportation,
limited to: intermediate storage and handling,
installation of material following
manufacturer recommendations,
manpower, surface preparation, , tools,
machinery, auxiliary means and, in general,
all required materials and labor for the
correct completion of all work as per
manufacturer’s instructions manual,
project specifications, standards and
approved ITP’s.
Excluded:
Measurement The unit shall be length of the joint as
system: specified on approved drawings.
Unit of measure: The unit of measure is the lineal meter (lm)

CW.04.ST.WP._WS000200S Supply and application of water stop swellable joint sealing with
SikaSwell system or similar, including all necessary auxiliary
materials for the correct application of the product as per
vendor requirements and recommendations.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04STWP_WS000200S Included but not plotting, material supply, transportation,
limited to: intermediate storage and handling,
installation of material following
manufacturer recommendations,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 84 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

manpower, surface preparation, , tools,


machinery, auxiliary means and, in general,
all required materials and labor for the
correct completion of all work as per
manufacturer’s instructions manual,
project specifications, standards and
approved ITP’s.
Excluded:
Measurement The unit shall be length of the joint as
system: specified on approved drawings.
Unit of measure: The unit of measure is the lineal meter (lm)

CW.04.ST.WP._WS000300S Supply and application of water stop joint sealant with a good
resistance to ACIDS, ALKALIS AND BACTERIOLOGICAL ATTACK
and excellent adherence to concrete, metals and other non-
porous materials, for joints up to 40 mm width and up to 20 mm
thick.
Commodities included: Referred to: Application of Sealant materials in pipe
penetrations and in general joints between
CW04STWP_WS000300S two types of materials or discontinuities on
elements.
Price content. The unit price includes layout works and
Included but not plotting, material supply, transportation,
limited to: intermediate storage and handling,
installation of material following
manufacturer recommendations,
manpower, surface preparation and
cleaning, tools, machinery, auxiliary means
and, in general, all required materials and
labor for the correct completion of all work
as per manufacturer’s instructions manual,
project specifications, standards and
approved ITP’s.
Excluded:
Measurement The unit shall be the length of the joint as
system: specified on approved drawings.
Unit of measure: The unit of measure is the lineal meter (lm)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 85 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.4.10.3 Commodity group CW04.ST.PR. Surface treatments and protections with


concrete.

CW.04.ST.PR._GU0000010 Supply and application of projected concrete (gunite) for slope


protections, xx cm thickness (y+y). Electrowelded mesh excluded.
Commodities included: Referred to:
Price content. The price includes all material supply and
CW04STPR_GU0000010 Included but not installation, manpower, wire mesh, tools,
CW04STPR_GU0000015 limited to: machinery, drilling of holes for anchoring,
anchor bars, auxiliary means and, in general,
all required materials and labor for the
correct completion of all work as per project
specifications, standards and approved ITPs.
Excluded:
Measurement The unit shall be the area of the surface to
system: be protected as specified on approved
drawings.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 86 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Unit of measure:
The unit of measure is the square meter
(m2)
2.4.11 Commodity group CW04.MS. Miscellaneous for concrete.

CW.04.MS.._GJx::x Supply and installation of grounding bounding jumper 185 mm2,


jointed to the reinforce of concrete elements with a clamp/cadweld,
2,00 m length.
Commodities included: Referred to: Grounding system inside concrete elements
Price content. The price includes material supply,
CW04MS_GJ000100S Included but not transportation, intermediate storage and
CW04MS_GJ000200S limited to: handling, installation, connection to
reinforcement or other elements (clamp o
Cadweld welding included), tools, auxiliary
means, and, in general, all required materials
and labor for the correct completion of all work
as per project specifications, standards and
approved ITPs..
Excluded:
Measurement The unit shall be measured as the number of
system: items installed
Unit of measure: The unit of measure is the unit (n)

CW.04.MS.._JOx::x Supply of materials and formation of expansion/contraction joints in


slabs or walls with 20 to 30 mm thk of compressible material and
bituminous seal in one or both sides according with project
specifications..
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04MS_JO000100S Included but not plotting, material supply, transportation,
CW04MS_JO000200S limited to: intermediate storage and handling, installation
CW04MS_JO000300S of material following manufacturer
CW04MS_JO000400S recommendations, manpower, surface
preparation, , tools, machinery, auxiliary
means and, in general, all required materials
and labor for the correct completion of all work
as per manufacturer’s instructions manual,
project specifications, standards and approved
ITP’s.
Excluded:
Measurement The unit shall be measured as length executed
system:
Unit of measure: The unit of measure is the unit (lm)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 87 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.04.MS.._PD000100S Supply & installation of Teflon pad plate for sliding supports of
equipment according with project standards, specifications and
drawings.
Commodities included: Referred to:
Price content. The unit price includes material supply,
CW04MS_PD000100S Included but not transportation, intermediate storage and
limited to: handling, drilling holes for bolts surfaces
preparation installation, tools, machinery,
auxiliary means and, in general, all required
materials and labor for the correct completion
of all work as per project specifications,
standards and approved ITPs.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the square meter (m²)

CW.04.MS.._JO000500S Supply and installation of TPER expansion joint system in concrete


slabs including 20mm thick plastic expansion board, waterstop TPER
expansion board cap, dia 20x225-300 speed load transfer sleeve,
staples joining cap to expansion board @600 C/C
Commodities included: Referred to: Joints between paving slab.
Price content. The unit price includes any material supply
CW04MS_JO000500S Included but not manpower, and installation of 20mm thick
limited to: plastic expansion board cap waterstop TPER,
Dia 20x225-300 speed load transfer sleeve,
staples joining cap to expansion board @600
C/C each side (for further reference see figure
7.15.1), equipment, auxiliary means, and in
general all required materials, labor and
equipment for the correct completion of the
work according to project standards,
specifications and drawings, following
manufacturer recommendations.
Excluded: Dowel ROD (Considered as embedded item)
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the lineal meter (lm)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 88 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

FIG.7.15.1 TPER EXPANSION BOARD CAP WATERSTOP SYSTEM JOINT SLABS

CW.04.MS.._JO000510S
Supply and installation of TPER expansion joint system in concrete
slabs for future pouring of concrete in one side of joint. 20mm thick
plastic expansion board, waterstop TPER expansion board cap, dia
20x225-300 speed load transfer sleeve, staples joining cap to
expansion board @600 C/C and 3 layers of nonwoven geotextile. For
protection of the side of the joint to be future poured it is also
included sand backfill to prevent TPER cap damage and 50x250
treated wood plank beleved at 45º and another 50x100 plank glued
and nailed to the 50x250
.
Commodities included: Referred to: Joints between soil and paving slabs
Price content. The unit price includes any material supply
CW04MS_JO000510S Included but not manpower, and installation of: 20mm thick
limited to: plastic expansion board, waterstop TPER
expansion board cap, dia 20x225-300 speed
load transfer sleeve, staples joining cap to
expansion board @600 C/C and 3 layers of
nonwoven geotextile. For protection of the
side of the joint to be future poured it is also
included sand backfill to prevent TPER cap

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 89 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

damage and 50x250 treated wood plank


beleved at 45º and another 50x100 plank
glued and nailed to the 50x250 (for further
reference see figure 7.15.2), equipment,
auxiliary means, and in general all required
materials, labor and equipment for the correct
completion of the work according to project
standards, specifications and drawings,
following manufacturer recommendations.

Excluded: Speed load transfer sleeve (considered as


embedded element)
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the lineal meter (lm)

FIG. 7.15.2 TPER JOINT DETAIL WITH FUTURE POUR

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 90 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.04.MS.._PD000200S Supply and installation of RUBBER LAMINATED ELASOTMERIC


BEARING PADS, with dimensions according to project standards,
specifications and drawings..
Commodities included: Referred to: Pads for supporting loading elements as
bridge beams.
CW04MS_PD000200S Price content. The unit price includes material supply,
Included but not surfaces preparation, installation, tools,
limited to: machinery, auxiliary means and, in general, all
required materials and labor for the correct
completion of all work as per project
specifications, standards and approved ITPs.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the square meter (m²)

CW.04.MS.._JO000600S Supply and installation of BRIDGE EXPANSION JOINT Transflex


system or similar based on reinforced elastomers, according to
project standards, specification and drawings.
Commodities included: Referred to: Expansion joints for beams
Price content. The unit price includes material supply,
CW04MS_JO000600S Included but not cutting, surfaces preparation, installation
limited to: according to manufacturer recommendations,
tools, machinery, auxiliary means and, in
general, all required materials, equipment and
labor for the correct completion of all work as
per manufacturer’s instructions manual,
project specifications, standards and
approved ITPs.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the linear meter (lm)

CW.04.MS.._CONPx::x Supply and Installation of neoprene wrapping tape , around


pipes, installation following manufacturer recommendations and
according to project specifications, standards and drawings.
Commodities included: Referred to: Joints between concrete walls and pipes.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 91 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Price content. The unit price includes material supply,


CW04MS_CONP0000012 Included but not cutting, surfaces preparation, installation
CW04MS_CONP0012R24 limited to: according to manufacturer
CW04MS_CONP0025R36 recommendations, tools, machinery,
auxiliary means and, in general, all required
materials, equipment and labor for the
correct completion of all work as per
manufacturer’s instructions manual, project
specifications, standards and approved ITPs.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the square meter
(m2)

2.5 Commodity group CW05. UNDERGRO UND WORKS

2.5.1 Commodity group CW.05.MH. Cath basin, manholes and pits.

2.5.1.1 Commodity group CW.05.MH.CO.IS. Concrete manholes and pits casted “in-
situ”

CW.05.MH.CO.IS_000100S Supply of materials and construction of "in situ" reinforced


concrete in catch basins, manholes and pits, for an internal
volume <= 12 m3. (Measurement based on cubic meters of
reinforced concrete, all included, even cover).
Commodities included: Referred to:
Price content. The unit price includes the material supply,
CW05MHCOIS_000100S Included but not transportation, intermediate storage,
limited to: handling, layout works and plotting, ,
formation of lean concrete base, plaster
coating on interior and polishing (on block
and brick pits), repair of damages (in
concrete), sloping of the interior (bottom) of
the pit, framing, covers (made of concrete,
steel, cast or a combination of them),
embeddings, rungs, anchorage, surface
preparation (blasting), priming and paint of
steel elements, sleeves for conduits (when
the conduits are within the scope of work of
the SUBCONTRACTOR), joint finishing works

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 92 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

with suitable mortar (cementitious, epoxy


or whatever required) and required sealants
for all pipe penetrations pipe-wall joint
finishing works,, leak tests, supply and
erection of vents, all required hand tools
and machinery, auxiliary and secondary
equipment (scaffolding, etc.) and any other
requirement, regardless of nature,
necessary for the correct installation of the
required unit as per project specifications,
standards and approved ITPs.

Excluded: Catch basins manholes and pits > 12 m³ of


internal volume.
Measurement The unit shall be measured (concrete cover
system: shall not be included) as is stated on
approved drawings. The internal volume
shall be determined as is stated on
approved drawings.
When the element is located on a sloped
area, depth shall be considered as the depth
in the central point of the horizontal
projection. Figure 9.1 explains the
aforementioned measurement system.
Those manholes, catch basin, valve pits etc.
which internal volume exceed 12 m3, will be
measured and paid according to the unit
prices of the different jobs involved
(concrete, rebars, formwork, embedding,
cover, etc.).

Pipe penetration holes greater than 0.3 m2


shall be deducted from concrete quantities.

Unit of measure: The unit of measure is concrete cubic meter


(m3)
Method of Payment breakdown shall be as indicated
payment: below:
Supply and construction 85%
Leak testing (when apply) 15%

2.5.1.2 Commodity group CW.05.MH.CO.PC. Concrete manholes and pits precast

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 93 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.05.MH.CO.PC_000100S Supply of materials, prefabrication, transport to site and


installation of precast concrete in catch basins, manholes and
pits, for an internal volume <= 12 m3. (Measurement based on
cubic meters of reinforced concrete, all included, even cover).
Commodities included: Referred to:
Price content. The unit price includes the material supply
CW05MHCOPC_000100S Included but not prefabrication, load transport and unload
limited to: at the final location, layout works and
plotting, , formation of lean concrete base,
plaster coating on interior and polishing
(on block and brick pits), repair of damages
(in concrete), sloping of the interior
(bottom) of the pit, framing, covers (made
of concrete, steel, cast or a combination of
them), embeddings, rungs, anchorage,
surface preparation (blasting), priming and
paint of steel elements, sleeves for
conduits (when the conduits are within the
scope of work of the SUBCONTRACTOR),
joint finishing works with suitable mortar
and required sealants (cementitious,
epoxy or whatever required) for all pipe
penetrations pipe-wall joint finishing
works, leak tests, supply and erection of
vents, , Lifting lugs cutting, pockets
grouting, sealing of lifting bushing and all
required hand tools and machinery,
auxiliary and secondary equipment
(scaffolding, etc.) and any other
requirement, regardless of nature,
necessary for the correct installation of the
required unit as per project specifications,
standards and approved ITPs.

Excluded: Catch basins manholes and pits > 12 m³ of


internal volume.
Measurement The unit shall be measured (concrete cover
system: shall not be measured) as is stated on
approved drawings. The internal volume
shall be determined as is stated on
approved drawings.
When the element is located on a sloped
area, depth shall be considered as the
depth in the central point of the horizontal

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 94 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

projection. Figure 9.1 explains the


aforementioned measurement system.
Those manholes, catch basin, valve pits
etc. which internal volume exceed 12 m3,
will be measured and paid according to the
unit prices of the different jobs involved
(concrete, rebars, formwork, embedding,
cover, etc.).

Only concrete elements that


CONTRACTOR identifies as “precast” shall
be measured and paid under this
commodity. SUBCONTRACTOR shall
assume, on its own responsibility, any
additional costs due to the execution
under “precast” construction
methodology when the elements have not
been identified as “precast” by Contractor

Pipe penetration holes greater than 0.3 m2


shall be deducted from concrete quantities

Unit of measure: The unit of measure is concrete cubic


meter (m3)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 95 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

CW.05.MH.CO.PC_x::x Only installation of precast catch basins, manholes and pits,


made of reinforced concrete
Commodities included: Referred to: Precasted manholes supplied by others
Price content. The unit price includes load at laydown
CW05MHCOPC_IN000100S Included but not area, transport and unload at the final
CW05MHCOPC_IN000200S limited to: location, layout works and plotting,
excavation, backfill, formation of lean
concrete base, plaster coating on interior
as per requirements, sloping of the
interior (bottom) of the pit, joint finishing
works with suitable mortar and required
sealants (cementitious, epoxy or whatever
required) for all pipe penetrations pipe-
wall joint finishing works, supply and
erection of vents, Lifting lugs cutting,
pockets grouting, sealing of lifting bushing
and all required hand tools and machinery,
auxiliary and secondary equipment
(scaffolding, etc.) and any other
requirement, regardless of nature,
necessary for the correct installation of
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 96 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

the required unit as per manufacturer’s


instructions manual, project
specifications, standards and approved
ITPs.

Excluded:
Measurement The unit shall be measured calculating the
system: weight of concrete for each manhole. It
shall be applied 2.5 ton/m3 as average
unitary weight to the concrete volume (in
m3), calculated according Fig. 9.1. Each
manhole shall be classified into one of the
three commodities depending on its
weight.

Unit of measure: The unit of measure is the ton.


Method of Payment breakdown shall be as indicated
payment: below:
Supply and construction
85%
Leak testing (when apply)
15%

2.5.1.3 Commodity group CW.05.MH.MS.BK. masonry manholes and pits. fabricated


with bricks

CW.05.MH.MS.BK_x::x Supply of materials and construction of catch basins,


manholes and pits, made of bricks
Commodities included: Referred to:
Price content. The unit price includes the material
CW05MHMSBK_000U005 Included but not supply, layout works and plotting, ,
CW05MHMSBK_005R015 limited to: formation of lean concrete base, plaster
CW05MHMSBK_015R035 coating on interior and polishing (on
CW05MHMSBK_035R060 block and brick pits), repair of damages
CW05MHMSBK_060R090 (in concrete), sloping of the interior
CW05MHMSBK_090R120 (bottom) of the pit, framing, covers
(made of concrete, steel, cast or a
combination of them), embeddings,
rungs, anchorage, surface preparation
(blasting), priming and paint of steel
elements, sleeves for conduits (when the
conduits are within the scope of work of
the SUBCONTRACTOR), joint finishing

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 97 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

works with suitable mortar and required


sealants (cementitious, epoxy or
whatever required) for all pipe
penetrations pipe-wall joint finishing
works,, leak tests, supply and erection of
vents, all required hand tools and
machinery, auxiliary and secondary
equipment (scaffolding, etc.) and any
other requirement, regardless of nature,
necessary for the correct installation of
the required unit.
Excluded: Catch basins manholes and pits > 12 m³
of internal volume.
Measurement The unit shall be measured as the
system: number of elements installed.
Internal volume shall be categorized
according to Fig. 9.1.
Only those elements identified by
contractor as any masonry catch basin,
manhole or pit shall be considered under
this commodities, SUBCONTRACTOR
shall assume, on its own responsibility,
any additional costs due to the execution
under masonry construction
methodology when the elements have
not been identified as it by Contractor

Unit of measure: The unit of measure is the unit (each)


Method of Payment breakdown shall be as indicated
payment: below:
Supply and construction
85%
Leak testing (when apply)
15%

2.5.1.4 Commodity group CW.05.MH.MS.BL. masonry manholes and pits. fabricated


with concrete blocks

CW.05.MH.MS.BL_x::x Supply of materials and construction of catch basins, manholes


and pits, made of concrete blocks.
Commodities included: Referred to:

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 98 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

Price content. The unit price includes the material supply,


CW05MHMSBL_000U005 Included but not layout works and plotting, , formation of
CW05MHMSBL_005R015 limited to: lean concrete base, plaster coating on
CW05MHMSBL_015R035 interior and polishing (on block and brick
CW05MHMSBL_035R060 pits), repair of damages (in concrete),
CW05MHMSBL_060R090 sloping of the interior (bottom) of the pit,
CW05MHMSBL_090R120 framing, covers (made of concrete, steel,
cast or a combination of them),
embeddings, rungs, anchorage, surface
preparation (blasting), priming and paint of
steel elements, sleeves for conduits (when
the conduits are within the scope of work of
the SUBCONTRACTOR), joint finishing works
with suitable mortar and required sealants
(cementitious, epoxy or whatever required)
for all pipe penetrations pipe-wall joint
finishing works,, leak tests, supply and
erection of vents, all required hand tools
and machinery, auxiliary and secondary
equipment (scaffolding, etc.) and any other
requirement, regardless of nature,
necessary for the correct installation of the
required unit.
Excluded: Catch basins manholes and pits > 12 m³ of
internal volume.
Measurement The unit shall be measured as the number
system: of elements installed.
Only those elements identified by
contractor as any masonry catch basin,
manhole or pit shall be considered under
this commodities, SUBCONTRACTOR shall
assume, on its own responsibility, any
additional costs due to the execution under
masonry construction methodology when
the elements have not been identified as it
by Contractor.

Unit of measure: The unit of measure is the unit (each)


Method of Payment breakdown shall be as indicated
payment: below:
Supply and construction 85%
Leak testing (when apply) 15%

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 99 OF
MEASUREMENT AND APPLICABLE PRICES 154

RFQ 70240-2510. REV. 01

2.5.1.5 Commodity group CW.05.MH.PL. Plastic and cast-iron manholes and pits.

CW.05.MH.PL._x::x Supply and installation of catch basins made of cast iron,


Commodities included: Referred to:
Price content. The unit price includes the material
CW05MHPL_CBSICI000U025 Included but not supply cover included, layout works and
CW05MHPL_CBSICI025R050 limited to: plotting, , formation of lean concrete
base, priming and paint of steel elements,
sleeves for conduits (when the conduits
are within the scope of work of the
SUBCONTRACTOR), joint finishing works
with suitable mortar and required
sealants for all pipe penetrations pipe-
wall joint finishing works, leak tests,
supply and erection of vents, all required
hand tools and machinery, auxiliary and
secondary equipment (scaffolding, etc.)
and any other requirement, regardless of
nature, necessary for the correct
installation of the required unit.
Excluded:
Measurement The unit shall be measured as the number
system: of elements installed as stated on
approved drawings.

Unit of measure: The unit of measure is the unit (each)


Method of Payment breakdown shall be as indicated
payment: below:
Supply and construction
85%
Leak testing (when apply)
15%

CW.05.MH.PL._x::x Only installation of catch basins made of cast iron, embedded


into a mass concrete block with a minimum concrete
thickness of 150mm each face. Concrete shall be protected
according to project standards and specifications.
Commodities included: Referred to:
Price content. The unit price includes load of catch
CW05MHPL_CBINCI000U025 Included but not basin at laydown area, transport and
CW05MHPL_CBINCI025R050 limited to: unload at site., supply and pouring of
mass concrete including formworks and
required concrete surface treatments,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 100
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

layout works and plotting, formation of


lean concrete base, joint finishing works
with suitable mortar and required
sealants for all pipe penetrations pipe-
wall joint finishing works, leak tests, all
required hand tools and machinery,
auxiliary and secondary equipment
(scaffolding, etc.) and any other
requirement, regardless of nature,
necessary for the correct installation of
the required unit.
Excluded:
Measurement The unit shall be measured as the
system: number of elements installed as stated
on approved drawings.

Unit of measure: The unit of measure is the unit (each)


Method of Payment breakdown shall be as
payment: indicated below:
Supply and construction
85%
Leak testing (when apply)
15%

CW.05.MH.PL._x::x Supply and installation of catch basins made of plastic

Commodities included: Referred to:


Price content. The unit price includes the material
CW05MHPL_CBSIPL000U025 Included but not supply, cover included, layout works and
CW05MHPL_CBSIPL025R050 limited to: plotting, , formation of lean concrete
base, priming and paint of steel
elements, sleeves for conduits (when the
conduits are within the scope of work of
the SUBCONTRACTOR), joint finishing
works with suitable mortar and required
sealants for all pipe penetrations pipe-
wall joint finishing works,, leak tests,
supply and erection of vents, all required
hand tools and machinery, auxiliary and
secondary equipment (scaffolding, etc.)
and any other requirement, regardless of
nature, necessary for the correct
installation of the required unit.
Excluded:
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 101
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Measurement The unit shall be measured as the


system: number of elements installed as stated
on approved drawings.

Unit of measure: The unit of measure is the unit (each)


Method of Payment breakdown shall be as indicated
payment: below:
Supply and construction
85%
Leak testing (when apply)
15%

CW.05.MH.PL._x::x Supply and installation of catch basins made of HDPE.


Commodities included: Referred to:
Price content. The unit price includes the material
CW05MHPL_CBSIHP000U005 Included but not supply, cover included, layout works and
CW05MHPL_CBSIHP005R015 limited to: plotting, formation of lean concrete
CW05MHPL_CBSIHP015R035 base, priming and paint of steel
CW05MHPL_CBSIHP035R060 elements, sleeves for conduits (when the
CW05MHPL_CBSIHP060R090 conduits are within the scope of work of
CW05MHPL_CBSIHP090R120 the SUBCONTRACTOR), joint finishing
CW05MHPL_CBSIHP120R150 works with suitable mortar and required
sealants for all pipe penetrations pipe-
wall joint finishing works,, leak tests,
supply and erection of vents, all
required hand tools and machinery,
auxiliary and secondary equipment
(scaffolding, etc.) and any other
requirement, regardless of nature,
necessary for the correct installation of
the required unit.
Excluded:
Measurement The unit shall be measured as the
system: number of elements installed as stated
on approved drawings.

Unit of measure: The unit of measure is the unit (each)


Method of Payment breakdown shall be as
payment: indicated below:
Supply and construction
85%
Leak testing (when apply)
15%

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 102
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

2.5.1.6 Commodity group CW.05.MH.CL. Clean-Outs and others.

CW.05.MH.CL._SI000100S Supply and construction of clean outs, any type.


Commodities included: Referred to:
Price content. The unit price includes the supply of
CW05MHCL_SI000100S Included but not materials, layout works and plotting,
limited to: excavation, filling and any other
requirement, regardless of nature,
necessary for the correct installation of the
required unit (for any type of clean outs).
Excluded:
Measurement The unit shall be measured as the number of
system: elements installed as stated on approved
drawings.

Unit of measure: The unit of measure is the unit (each)

CW.05.MH.CL._SI000200S Supply of material and construction of bottom drainage sump in


tanks rings.
Commodities included: Referred to:
Price content. The price includes supply, laying out and
CW05MHCL_SI000200S Included but not plotting, demolitions, excavations,
limited to: backfilling, formworks, reinforcements,
concreting, auxiliary means, tools,
machinery and any other requirement,
regardless of nature, necessary for the
correct installation of the required unit.
Excluded:
Measurement The unit shall be measured as the number of
system: elements installed as stated on approved
drawings.

Unit of measure: The unit of measure is the unit (each)

CW.05.MH.CL._SI000300S Supply and installation of funnel.


Commodities included: Referred to:
Price content. The unit price includes the supply of
CW05MHCL_SI000300S Included but not materials, layout works and plotting,
limited to: excavation, filling and any other
requirement, regardless of nature,
necessary for the correct installation of the
required unit (for any type of funnel).
Excluded:

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 103
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Measurement The unit shall be measured as the number of


system: elements installed as stated on approved
drawings.

Unit of measure: The unit of measure is the unit (each)

2.5.1.7 Commodity group CW.05.MH.CO. Cover for catch basins, manholes, culverts,
trenches, pits, etc. with internal volume >12m³.

CW.05.MH.CO._x::x Supply and installation of reinforced concrete covers for catch


basins, manholes, culverts, trenches and pits (internal volume >
12 m3),
Commodities included: Referred to: This unit price refers to covers of catch
basins which exceed the internal volume
CW05MHCO_RCSI0000005 of 12 m3 as well as the cover of channels.
CW05MHCO_RCSI0000010 Price content. This unit price includes material supply,
CW05MHCO_RCSI0000013 Included but not work lay out and plotting, assembly,
CW05MHCO_RCSI0000015 limited to: formworks, metallic elements,
CW05MHCO_RCSI0000020 embeddings (blasting + priming + paint),
CW05MHCO_RCSI0000025 hand tools, auxiliary means, machinery
CW05MHCO_RCSI0000030 and, in general, all required materials and
CW05MHCO_RCSI0000040 labor for the correct completion of all
work.
CW05MHCO_RCSI0000060
Covers with thickness > 30 cm shall be
measured and paid as precast concrete (or
“in situ concrete if applicable”
Excluded: Covers with thickness > 30 cm thickness
Measurement The unit shall be measured as surface of
system: covers as stated on approved drawings.

Unit of measure: The unit of measure shall be the square


meter (m2)

CW.05.MH.CO._x::x Supply and installation of checkered / embossed steel plates or


steel grating covers for channels, catch basins, manholes and
pits (internal volume > 12 m3).
Commodities included: Referred to: This unit price refers to the cover of catch
basins which exceed the internal volume of
CW05MHCO_SPSI000100S 12 m3 as well as the cover of channels.
CW05MHCO_SPSI000200S Price content. This unit price includes material supply,
Included but not surface treatment (blasting + priming if
limited to: required / hot dip galvanizing), finishing
surface paint, special pieces, accessories,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 104
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

general repair (priming/galvanizing, paint,


damages, welding, etc.) and, in general, all
required materials and labor for the correct
completion of all work.

Excesses due to cuttings or cropping of


material, excessive lamination, welding,
bolts and any other any item for the correct
completion of the work are not measured
nor paid.
Excluded:
Measurement The unit shall be measured on approved
system: drawings, and applying weight as specified
in the manufacturer’s catalog. When these
weights are not specified, weight shall be
calculated applying the density of 7.85
t/m3.

Holes higher than 1 m2 shall be discounted


from measure.
Unit of measure: The unit of measure shall be expressed in
kilograms (kg)

CW.05.MH.CO._MPSI000100S Supply and installation of metallic profiles channels, catch


basins, manholes and pits (internal volume > 12 m3).
Commodities included: Referred to: This unit price refers to metallic profiles
covers of catch basins and channels
CW05MHCO_MPSI000100S which exceed the internal volume of 12
m3. Metallic profile embedded in
concrete are no included and shall be
measured according with the standard of
measurement and payment.
Price content. This unit price includes material supply,
Included but not surface treatment (blasting + priming /
limited to: hot dip galvanizing), finishing surface
paint, special pieces, accessories,
machinery, tools, auxiliary means general
repair (priming/galvanizing, paint,
damages, welding, etc.) and, in general,
all required materials and labor for the
correct completion of all work.

Excesses due to cuttings or cropping of


material, excessive lamination, welding,

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 105
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

bolts and any other any item for the


correct completion of the work are not
measured nor paid.
Excluded:
Measurement The unit shall be measured on approved
system: drawings, and applying weight as
specified in the manufacturer’s catalog.
When these weights are not specified,
weight shall be calculated applying the
density of 7.85 t/m3
Unit of measure: The unit of measure shall be expressed in
kilograms (kg)

CW.05.MH.CO._CCIN000100S Only installation of precast covers (supply by others) for


manholes, made of reinforced concrete, 25 cm thick. including
eveling to required slope, manhole edge termination if
required and grouting. The price also includes placing of cast
iron cover (cast iron frame previously installed on concrete
cover)
Commodities included: Referred to: This unit price refers to precast concrete
covers for catch basins, supplied by
CW05MHCO_CCIN000100S others.
Price content. This unit price includes load at laydown
Included but not area, transport to site and installation at
limited to: place, lay out and plotting, levelling to
required slope, supply of materials for
manhole edge termination, grouting,
sealing, placing of cast iron cover hand
tools, auxiliary means, machinery, labor
and, in general, everything required for
the correct completion of all work.

Excluded:
Measurement The unit shall be measured as surface of
system: covers as stated on approved drawings.

Unit of measure: The unit of measure shall be the square


meter (m2)

2.5.2 Commodity group CW.05.UG. Underground Piping Electrical.

2.5.2.1 Commodity group CW.05.UG.PV.SA. Sanitary PVC piping.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 106
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW.05.UG.PV.SA_x::x Supply and installation of PVC sanitary underground piping,


elastic joint..
Commodities included: Referred to:
Price content. This unit price includes the material
CW05UGPVSA_SIM000050 Included but not supply, layout works and plotting, wedges,
CW05UGPVSA_SIM000075 limited to: spacers, special pieces, accessories and
CW05UGPVSA_SIM000090 piping fittings, joints (elastic joints could
CW05UGPVSA_SIM000110 be glued or not), testing (leak, pneumatic
CW05UGPVSA_SIM000125 and/or hydraulic test according with
CW05UGPVSA_SIM000140 project requirement), pumping and
CW05UGPVSA_SIM000150 measuring equipment, dismantling and
CW05UGPVSA_SIM000160 reinstallation of sensitive accessories,
supply, installation and dismantling of
CW05UGPVSA_SIM000180
temporal accessories (blind caps,
CW05UGPVSA_SIM000200
temporary spools, filters, etc.), lubricants,
CW05UGPVSA_SIM000250
tools, auxiliary means, machinery and, in
CW05UGPVSA_SIM000300 general, all required materials and labor
CW05UGPVSA_SIM000350 for the correct completion of all work.
CW05UGPVSA_SIM000400 Excluded: Excavation and backfilling of trenches
CW05UGPVSA_SIM000450 Measurement The unit shall be measured as the length of
CW05UGPVSA_SIM000500 system: piping correctly installed, theoretical
CW05UGPVSA_SIM000550 measurement in approved drawings
CW05UGPVSA_SIM000600 considering the axes of the pipe.
CW05UGPVSA_SIM000650 Unit of measure: The unit of measure shall be the lineal
CW05UGPVSA_SIM000700 meter (lm)
CW05UGPVSA_SIM000750 Method of Payment breakdown shall be as indicated
CW05UGPVSA_SIM000800 payment: below:
CW05UGPVSA_SIM000850 Supply and installation
CW05UGPVSA_SIM000900 70%
CW05UGPVSA_SIM000925 Testing 30%

2.5.2.2 Commodity group CW.05.UG.PV.PR. PERFORATED PVC PIPING

CW.05.UG.PV.PR_x::x Supply and installation of PVC perforated underground piping,


elastic joint.
Commodities included: Referred to:
Price content. This unit price includes the material
CW05UGPVPR_SIM000050 Included but not supply, layout works and plotting, wedges,
CW05UGPVPR_SIM000075 limited to: spacers, special pieces, accessories and
CW05UGPVPR_SIM000090 piping fittings, joints (elastic joints could
be glued or not), supply and installation of
CW05UGPVPR_SIM000110
cable pulling guides, lubricants, tools,
CW05UGPVPR_SIM000125 auxiliary means, machinery and, in
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 107
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGPVPR_SIM000140 general, all required materials and labor


CW05UGPVPR_SIM000150 for the correct completion of all work.
CW05UGPVPR_SIM000160 Excluded: Excavation and backfilling of trenches
Measurement The unit shall be measured as the length of
CW05UGPVPR_SIM000180
system: piping correctly installed, theoretical
CW05UGPVPR_SIM000200 measurement in approved drawings
considering the axes of the pipe.
Unit of measure: The unit of measure shall be the lineal
meter (lm)
Method of Payment breakdown shall be as indicated
payment: below:
Supply and installation
70%
Testing 30%

2.5.2.3 Commodity group CW05UG.HP. Handling and setting of underground plastic


piping.

CW05UGHP_HSx::x Handling and Setting of underground plastic piping.


Commodities included: Referred to:
CW05UGHP_HSI000050 Price content. This unit price includes all necessary
CW05UGHP_HSI000075 Included but not activities, as minimum: erection of piping in
CW05UGHP_HSI000100 limited to: any position according to isometric drawings,
CW05UGHP_HSI000200 cutting, adjustement, end beweling, fit up,
CW05UGHP_HSI000300 hydraulic testing, reinstatement of elements
CW05UGHP_HSI000400 in circuits, handling of all materials (i.e.
CW05UGHP_HSI000600 loading in storage area or in erection areas,
CW05UGHP_HSI000800 lifting, leveling, and provisional supports if
necessary, etc.) and, in general, all
CW05UGHP_HSI001000
requirements necessary for the correct
CW05UGHP_HSI001200
installation
CW05UGHP_HSI001400
CW05UGHP_HSI001600
CW05UGHP_HSI001800 Excluded: Excavation and backfilling of trenches.
CW05UGHP_HSI002000 Measurement The unit shall be measured as the piping
CW05UGHP_HSI002200 system: length correctly installed, theoretical
CW05UGHP_HSI002400 measurement in approved drawings
CW05UGHP_HSI002600 considering the axes of the pipe.
CW05UGHP_HSI002800 Unit of measure: The unit of measure shall be the lineal meter
CW05UGHP_HSI003000 (lm)
CW05UGHP_HSI003200
CW05UGHP_HSI003600
CW05UGHP_HSI004000 Payment system:

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 108
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGHP_HSI004200 Payment shall be by linear meter of erecting


CW05UGHP_HSI004400 piping.
CW05UGHP_HSI004600 Breakdown payment shall be as indicated
CW05UGHP_HSI004800 below, unless otherwise indicated in the
CW05UGHP_HSI005000 <progress Control Procedure:
CW05UGHP_HSI005200
CW05UGHP_HSI005400 Finalization of line erection 70 %
CW05UGHP_HSI005600 Hydraulic Test 30 %
CW05UGHP_HSI006000
CW05UGHP_HSI006400
CW05UGHP_HSI006600
CW05UGHP_HSI006800
CW05UGHP_HSI007200
CW05UGHP_HSI007800
CW05UGHP_HSI008000
CW05UGHP_HSI009600
CW05UGHP_HSI010400
CW05UGHP_HSI010600
CW05UGHP_HSI010800
CW05UGHP_HSI012000
CW05UGHP_HSI012800
CW05UGHP_HSI013200
CW05UGHP_HSI014000
CW05UGHP_HSI016000

2.5.2.4 Commodity group CW05.UG.PP. Polypropylene.

2.5.2.5 Commodity group CW05.UG.PE.HD. HDPE PIPING.

CW.05.UG.PE.HD_x::x Only installation of underground pipe of HDPE.


Commodities included: Referred to:
Price content. This unit price includes layout works and
CW05UGPEHD_INI000025 Included but not plotting, wedges, spacers, special pieces,
CW05UGPEHD_INI000050 limited to: accessories and piping fittings, joints
CW05UGPEHD_INI000063 (elastic joints could be glued or not),
CW05UGPEHD_INI000075 hydrotesting, pumping and measuring
CW05UGPEHD_INI000100 equipment, dismantling and reinstallation
CW05UGPEHD_INI000150 of sensitive accessories, supply,
CW05UGPEHD_INM000025 installation and dismantling of temporal
accessories (blind caps, temporary spools,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 109
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGPEHD_INM000050 filters, etc.), lubricants, tools, auxiliary


CW05UGPEHD_INM000075 means, machinery and, in general, all
CW05UGPEHD_INM000080 required materials and labor for the
CW05UGPEHD_INM000090 correct completion of all work.
CW05UGPEHD_INM000100 Excluded: Excavation and backfilling of trenches
CW05UGPEHD_INM000110 Measurement The unit shall be measured as the length
CW05UGPEHD_INM000125 system: of piping correctly installed, theoretical
CW05UGPEHD_INM000140 measurement in approved drawings
CW05UGPEHD_INM000150 considering the axes of the pipe.
CW05UGPEHD_INM000160 Unit of measure: The unit of measure shall be the lineal
meter (lm)
CW05UGPEHD_INM000180
CW05UGPEHD_INM000200
CW05UGPEHD_INM000250
CW05UGPEHD_INM000300
CW05UGPEHD_INM000350
CW05UGPEHD_INM000400
CW05UGPEHD_INM000450
CW05UGPEHD_INM000500
CW05UGPEHD_INM000600
CW05UGPEHD_INM000700
CW05UGPEHD_INM000800
CW05UGPEHD_INM000900
CW05UGPEHD_INM001000
CW05UGPEHD_INM001100
CW05UGPEHD_INM001200
CW05UGPEHD_INM001300
CW05UGPEHD_INM001400 Method of Payment breakdown shall be as indicated
CW05UGPEHD_INM001500 payment: below:
Supply and installation
CW05UGPEHD_INM001600
70%
Testing
30%

2.5.2.6 Commodity group CW05.UG.PE.JO. Execution of underground piping


Thermofusion & Electrofusion joint, by dia-inch."

CW.05.UG.PE.JO_x::x Execution of underground piping Thermofusion & Electrofusion


joint,.
Commodities included: Referred to:
CW05UGPEJO_I000200 Price content. This unit price includes all necessary
CW05UGPEJO_I000300 Included but not activities, as minimum: joint execution
limited to: according to manufacturer recommendation

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 110
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGPEJO_I000400 of piping, in any position (according to


CW05UGPEJO_I000600 isometric drawings), handling of all
CW05UGPEJO_I000800 consumable materials (i.e. loading in storage
CW05UGPEJO_I001000 area or in erection areas, etc.) and, in general,
CW05UGPEJO_I001200 all requirements necessary for the correct
CW05UGPEJO_I001400 execution of the joint
CW05UGPEJO_I001600
CW05UGPEJO_I001800
Excluded: Excavation and backfilling of trenches.
CW05UGPEJO_I002400
Measurement The unit of measure shall be the number of
CW05UGPEJO_I002800
system: dia-inches of laminated joints according to
CW05UGPEJO_I003000
the diameter, theoretical measurement in
CW05UGPEJO_I003200
approved drawings.
CW05UGPEJO_I003600
Unit of measure: The unit of measure shall be dia-inches (dia-
CW05UGPEJO_I004000 inch)
CW05UGPEJO_I004800 Method of payment: Payment breakdown shall be as indicated
CW05UGPEJO_I006400 below:
CW05UGPEJO_I008000 Supply and installation
70%
Testing
30%

2.5.2.7 Commodity group CW05.UG.GJ.BW. Execution of underground piping


GRP/RTR lamination joint, by dia-inch."

CW.05.UG.GJ.BW_x::x Execution of underground piping GRP/RTR lamination joint,.


Commodities included: Referred to:
CW05UGGJBW_I000200 Price content. This unit price includes all necessary
CW05UGGJBW_I000300 Included but not activities, as minimum: joint execution
CW05UGGJBW_I000400 limited to: according to manufacturer recommendation
CW05UGGJBW_I000600 of piping, in any position (according to
CW05UGGJBW_I000800 isometric drawings), handling of all
CW05UGGJBW_I001000 consumable materials (i.e. loading in storage
CW05UGGJBW_I001200 area or in erection areas, etc.) and, in
CW05UGGJBW_I001400 general, all requirements necessary for the
correct execution of the joint
CW05UGGJBW_I001600
CW05UGGJBW_I001800
CW05UGGJBW_I002000
Excluded: Excavation and backfilling of trenches.
CW05UGGJBW_I002400
Measurement The unit of measure shall be the number of
CW05UGGJBW_I002800 system: dia-inches of laminated joints according to
CW05UGGJBW_I003000 the diameter, theoretical measurement in
CW05UGGJBW_I003200 approved drawings.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 111
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGGJBW_I003600 Unit of measure: The unit of measure shall be dia-inches (dia-


CW05UGGJBW_I004000 inch)
CW05UGGJBW_I004200 Method of payment: Payment breakdown shall be as indicated
CW05UGGJBW_I004400 below:
CW05UGGJBW_I004600 Supply and installation
CW05UGGJBW_I004800 70%
CW05UGGJBW_I005000 Testing
CW05UGGJBW_I005200 30%
CW05UGGJBW_I005400
CW05UGGJBW_I005600
CW05UGGJBW_I005800
CW05UGGJBW_I006000
CW05UGGJBW_I006400
CW05UGGJBW_I006600
CW05UGGJBW_I006800
CW05UGGJBW_I007200
CW05UGGJBW_I007800
CW05UGGJBW_I008000
CW05UGGJBW_I009600
CW05UGGJBW_I010400
CW05UGGJBW_I010600
CW05UGGJBW_I010800
CW05UGGJBW_I012000
CW05UGGJBW_I012800
CW05UGGJBW_I013200
CW05UGGJBW_I014000
CW05UGGJBW_I016000

2.5.2.8 Commodity group CW05.UG.GJ.TT. Execution of underground piping


GRP/RTR adhesive bonded taper/taper joint.

CW.05.UG.GJ.TT_x::x Execution of underground piping GRP/RTR adhesive bonded


taper/taper joint.
Commodities included: Referred to:
CW05UGGJTT_I000200 Price content. This unit price includes all necessary activities,
CW05UGGJTT_I000300 Included but not as minimum: joint execution according to
CW05UGGJTT_I000400 limited to: manufacturer recommendation of piping, in
CW05UGGJTT_I000600 any position (according to isometric
CW05UGGJTT_I000800 drawings), handling of all consumable
materials (i.e. loading in storage area or in

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 112
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGGJTT_I001000 erection areas, etc.) and, in general, all


CW05UGGJTT_I001200 requirements necessary for the correct
CW05UGGJTT_I001400 execution of the joint
CW05UGGJTT_I001600
CW05UGGJTT_I001800
CW05UGGJTT_I002000 Excluded: Excavation and backfilling of trenches.
CW05UGGJTT_I002400 Measurement The unit of measure shall be the number of
CW05UGGJTT_I002600 system: dia-inches of laminated joints according to
CW05UGGJTT_I002800 the diameter, theoretical measurement in
approved drawings
CW05UGGJTT_I003000
Unit of measure: The unit of measure shall be dia-inches (dia-
CW05UGGJTT_I003200
inch)
CW05UGGJTT_I003600
Method of payment: Payment breakdown shall be as indicated
CW05UGGJTT_I004000
below:
CW05UGGJTT_I004800 Supply and installation
CW05UGGJTT_I006000 70%
CW05UGGJTT_I006400 Testing
CW05UGGJTT_I008000 30%

2.5.2.9 Commodity group CW05.UG.CO. CONCRETE PIPING.

CW.05.UG.CO_x::x Supply and installation of underground concrete pipe, elastic joint.


Commodities included: Referred to:
CW05UGCO_SIM000100 Price content. This unit price includes the material supply,
CW05UGCO_SIM000110 Included but not layout works and plotting, wedges, spacers,
CW05UGCO_SIM000125 limited to: special pieces, accessories and piping
CW05UGCO_SIM000140 fittings, joints (elastic joints could be glued
CW05UGCO_SIM000160 or not), testing (leak, pneumatic and/or
CW05UGCO_SIM000180 hydraulic test according with project
CW05UGCO_SIM000200 requirement), pumping and measuring
CW05UGCO_SIM000250 equipment, dismantling and reinstallation of
sensitive accessories, supply, installation
CW05UGCO_SIM000300
and dismantling of temporal accessories
CW05UGCO_SIM000350
(blind caps, temporary spools, filters, etc.),
CW05UGCO_SIM000375
lubricants, tools, auxiliary means, machinery
CW05UGCO_SIM000400 and, in general, all required materials and
CW05UGCO_SIM000450 labor for the correct completion of all work.
CW05UGCO_SIM000500 Excluded: Excavation and backfilling of trenches
CW05UGCO_SIM000600 Measurement The unit shall be measured as the length of
CW05UGCO_SIM000700 system: piping correctly installed, theoretical
CW05UGCO_SIM000750 measurement in approved drawings
CW05UGCO_SIM000800 considering the axes of the pipe.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 113
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGCO_SIM000900 Unit of measure: The unit of measure shall be the lineal meter
CW05UGCO_SIM001000 (lm )
CW05UGCO_SIM001100 Method of payment: Payment breakdown shall be as indicated
CW05UGCO_SIM001200 below:
CW05UGCO_SIM001300 Supply and installation
CW05UGCO_SIM001350 70%
CW05UGCO_SIM001400 Testing
CW05UGCO_SIM001500 30%
CW05UGCO_SIM001600
CW05UGCO_SIM001800
CW05UGCO_SIM002000
CW05UGCO_SIM002100

2.5.2.10 Commodity group CW05.UG.CI. CAST IRON PIPING.

CW.05.UG.CI._x::x Only installation of underground pipe CAST IRON.


Commodities included: Referred to:
CW05UGCI_INM000050 Price content. This unit price includes, layout works and
CW05UGCI_INM000075 Included but not plotting, wedges, spacers, special pieces,
CW05UGCI_INM000100 limited to: accessories and piping fittings, joints (elastic
CW05UGCI_INM000150 joints could be glued or not), testing (leak,
CW05UGCI_INM000200 pneumatic and/or hydraulic test according to
CW05UGCI_INM000250 project requirement), pumping and
CW05UGCI_INM000300 measuring equipment, dismantling and
CW05UGCI_INM000350 reinstallation of sensitive accessories,
supply, installation and dismantling of
CW05UGCI_INM000400
temporal accessories (blind caps, temporary
CW05UGCI_INM000450
spools, filters, etc.), lubricants, tools,
CW05UGCI_INM000500
auxiliary means, machinery and, in general,
CW05UGCI_INM000600 all required materials and labor for the
CW05UGCI_INM000700 correct completion of all work.
CW05UGCI_INM000750 Excluded: Excavation and backfilling of trenches
CW05UGCI_INM000800 Measurement The unit shall be measured as the length of
system: piping correctly installed, theoretical
measurement in approved drawings
considering the axes of the pipe.
Unit of measure: The unit of measure shall be the lineal meter
(lm)
Method of payment: Payment breakdown shall be as indicated
below:
Supply and installation
70%

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 114
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Testing
30%

2.5.2.11 Commodity group CW05.UG.CS.BW. CARBON STEEL PIPING.

CW.05.UG.CS.BW_x::x Only installation of underground pipe CARBON STEEL,


buttwelded or socketwelded.
Commodities included: Referred to:
CW05UGCSBW_INI000075 Price content. This unit price includes, layout works and
CW05UGCSBW_INI000100 Included but not plotting, wedges, cuttings, spacers, special
CW05UGCSBW_INI000150 limited to: pieces, accessories and piping fittings, ,
CW05UGCSBW_INI000200 gamma ray tests and any other required
CW05UGCSBW_INI000300 non-destructive tests, post weld heat
CW05UGCSBW_INI000400 treatments, testing (leak, pneumatic
CW05UGCSBW_INI000600 and/or hydraulic test according to project
CW05UGCSBW_INI000800 requirement), pumping and measuring
equipment, dismantling and reinstallation
CW05UGCSBW_INI001000
of sensitive accessories, supply,
CW05UGCSBW_INI001200
installation and dismantling of temporal
CW05UGCSBW_INI001400
accessories (blind caps, temporary spools,
CW05UGCSBW_INI001600 filters, etc.), lubricants, tools, auxiliary
CW05UGCSBW_INI001800 means and consumables, machinery,
CW05UGCSBW_INI002000 qualification and testing of welders and, in
CW05UGCSBW_INI002400 general, all required materials and labor
CW05UGCSBW_INI002800 for the correct completion of all work.
CW05UGCSBW_INI003000 Excluded: Excavation and backfilling of trenches.
CW05UGCSBW_INI003200 Measurement The unit shall be measured as the piping
system: length correctly installed, theoretical
measurement in approved drawings
considering the axes of the pipe.
Unit of measure: The unit of measure shall be the lineal
meter (lm )
Method of Payment breakdown shall be as indicated
payment: below:
Supply and installation
70%
Testing
30%

2.5.2.12 Commodity group CW05.UG.EC.GT. GALVANIZED STEEL PIPING.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 115
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW.05.UG.EC.GT_x::x Only installation of underground galvanized steel pipe, threaded


NPT/PG with accessories
Commodities included: Referred to:
CW05UGECGT_INI000050 Price content. This unit price includes, layout works and
CW05UGECGT_INI000075 Included but not plotting, wedges, cuttings, spacers, special
CW05UGECGT_INI000100 limited to: pieces, accessories and piping fittings, ,
CW05UGECGT_INI000150 gamma ray tests and any other required
CW05UGECGT_INI000200 non-destructive tests, post weld heat
treatments, testing (leak, pneumatic
and/or hydraulic test according to project
requirement), pumping and measuring
equipment, dismantling and reinstallation
of sensitive accessories, supply, installation
and dismantling of temporal accessories
(blind caps, temporary spools, filters, etc.),
lubricants, tools, auxiliary means and
consumables, machinery, qualification and
testing of welders and, in general, all
required materials and labor for the correct
completion of all work.
Excluded: Excavation and backfilling of trenches.
Measurement The unit shall be measured as the piping
system: length correctly installed, theoretical
measurement in approved drawings
considering the axes of the pipe.
Unit of measure: The unit of measure shall be the lineal
meter (lm)

Commodity group CW05.UG.FV. Installation of Valves and Fanged Elements.

2.5.2.13 Commodity group CW05.UG.EC.PV. ELECTRICAL CONDUITS (SINGLE PIPES


NOT DUCT BANK), PVC.

CW.05.UG.EC.PV_x::x Supply and installation of PVC underground piping for electrical


conduits, elastic joint, single or dual-wall.
Commodities included: Referred to: Electrical conduit not embedded in
concrete.
CW05UGECPV_SIM000025 Price content. This unit price includes the material
CW05UGECPV_SIM000050 Included but not supply, layout works and plotting, wedges,
CW05UGECPV_SIM000075 limited to: spacers, special pieces, accessories and
CW05UGECPV_SIM000090 piping fittings, joints (elastic joints could
be glued or not), supply and installation of

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 116
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGECPV_SIM000100 cable pulling guides, lubricants, tools,


CW05UGECPV_SIM000110 auxiliary means, machinery and, in
CW05UGECPV_SIM000125 general, all required materials and labor
CW05UGECPV_SIM000140 for the correct completion of all work.
CW05UGECPV_SIM000150 Excluded: Excavation and backfilling of trenches
CW05UGECPV_SIM000160 Measurement The unit shall be measured as the length of
CW05UGECPV_SIM000180 system: piping correctly installed, theoretical
CW05UGECPV_SIM000200 measurement in approved drawings
CW05UGECPV_SIM000250 considering the axes of the pipe.
CW05UGECPV_SIM000300 Unit of measure: The unit of measure shall be the lineal
meter (lm)
CW05UGECDC_SIM000075
CW05UGECDC_SIM000090
CW05UGECDC_SIM000110
CW05UGECDC_SIM000125
CW05UGECDC_SIM000140
CW05UGECDC_SIM000160
CW05UGECDC_SIM000180
CW05UGECDC_SIM000200
CW05UGECDC_SIM000250
CW05UGECDC_SIM000300
CW05UGECDC_SIM000400
CW05UGECDC_SIM000500
CW05UGECDC_SIM000600
CW05UGECDC_SIM000800

2.5.2.14 Commodity group CW05.UG.EC.GS. ELECTRICAL CONDUITS (SINGLE PIPES


NOT DUCT BANK), GALVANIZED STEEL.

CW.05.UG.EC.GS_x::x Supply and installation of rigid galvanized steel pipe, conduit


type, connection to concrete trenches, sealing &
identificating material as well, as per specification.
Undergroud.
Commodities included: Referred to: Electrical conduit not embedded in
concrete.
CW05UGECGS_SII075R010 Price content. This unit price includes the material
CW05UGECGS_SII150R020 Included but not supply, layout works and plotting,
CW05UGECGS_SII250R300 limited to: wedges, spacers, special pieces,
CW05UGECGS_SII400R500 accessories and piping fittings, joints
CW05UGECGS_SII600R800 (elastic joints could be glued or not),
supply and installation of cable pulling

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 117
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

guides, lubricants, tools, auxiliary means,


machinery and, in general, all required
materials and labor for the correct
completion of all work.
Excluded: Excavation and backfilling of trenches
Measurement The unit shall be measured as the length
system: of piping correctly installed, theoretical
measurement in approved drawings
considering the axes of the pipe.
Unit of measure: The unit of measure shall be the lineal
meter (lm)

2.5.2.15 Commodity group CW05.UG.EC.GI. ELECTRICAL CONDUITS (SINGLE PIPES


NOT DUCT BANK), GALVANIZED STEEL. ONLY INSTALLATION

CW.05.UG.EC.GI_x::x Only installation of rigid galvanized steel pipe, conduit type,


connection to concrete trenches, sealing & identificating material
as well, as per specification. Undergroud
Commodities included: Referred to: Electrical conduit not embedded in
concrete.
CW05UGECGI_INI000100 Price content. This unit price includes, layout works and
CW05UGECGI_INI000150 Included but not plotting, wedges, spacers, special pieces,
CW05UGECGI_INI000200 limited to: accessories and piping fittings, joints (elastic
joints could be glued or not), supply and
CW05UGECGI_INI000300
installation of cable pulling guides,
CW05UGECGI_INI000400 lubricants, tools, auxiliary means,
CW05UGECGI_INI000600 machinery and, in general, all required
materials and labor for the correct
completion of all work.
Excluded: Excavation and backfilling of trenches
Measurement The unit shall be measured as the length of
system: piping correctly installed, theoretical
measurement in approved drawings
considering the axes of the pipe.
Unit of measure: The unit of measure shall be the lineal
meter (lm)

2.5.2.16 Commodity group CW05.UG.FV. Installation of Valves and Fanged


Elements.

CW.05.UG.FV._x::x Installation of Valves and Fanged Elements.


This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 118
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Commodities included: Referred to:


CW05UGFV_INU30000002 Price content. This unit price includes all necessary
CW05UGFV_INU30000003 Included but not operations for installation, including gland
CW05UGFV_INU30000004 limited to: flange adjustment, the eventual
CW05UGFV_INU30000006 replacement of packing during hydraulic
CW05UGFV_INU30000008 tests, and stem lubrication. Also includes
CW05UGFV_INU30000010 cleaning, installation of elements of small
CW05UGFV_INU30000012 thickness between flanges, if any
CW05UGFV_INU30000014 (spectable blinds, blind disks, orifice plate,
etc.), gasket, stud bolts and nuts
CW05UGFV_INU30000016
installation, and tightening as per
CW05UGFV_INU30000018
specifications.
CW05UGFV_INU30000020
Excluded: Excavation and backfilling of trenches.
CW05UGFV_INU30000024
Measurement The unit of measure shall be the number
CW05UGFV_INU30000026 system: (each) of flanged valves/elements
CW05UGFV_INU30000030 installed.
CW05UGFV_INU30000036 Unit of measure: The unit of measure shall be the unit
CW05UGFV_IN300R90002 (each).
CW05UGFV_IN300R90003
CW05UGFV_IN300R90004
CW05UGFV_IN300R90006
CW05UGFV_IN300R90008
CW05UGFV_IN300R90010
CW05UGFV_IN300R90012
CW05UGFV_IN300R90014
CW05UGFV_IN300R90016
CW05UGFV_IN300R90018
CW05UGFV_IN300R90020
CW05UGFV_IN300R90024
CW05UGFV_IN300R90026
CW05UGFV_IN300R90030
CW05UGFV_IN300R90036
CW05UGFV_INF90000002
CW05UGFV_INF90000003
CW05UGFV_INF90000004
CW05UGFV_INF90000006
CW05UGFV_INF90000008
CW05UGFV_INF90000010
CW05UGFV_INF90000012
CW05UGFV_INF90000014
CW05UGFV_INF90000016
CW05UGFV_INF90000018
CW05UGFV_INF90000020
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 119
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW05UGFV_INF90000024
CW05UGFV_INF90000026
CW05UGFV_INF90000030
CW05UGFV_INF90000036

2.6 Commodity group CW06. PAVING AND ROADS

2.6.1 Commodity group CW06.EW. Paving and road earthworks.

2.6.1.1 Commodity group CW06.EW.EX. Paving and road earthworks. Encasement.

CW.06.EW.EX._x::x Excavation for paving encasement


Commodities included: Referred to: This excavation should be as maximum
the excavation from final grade to bottom
CW06EWEX_ATME000100S level of infrastructure as represented on
CW06EWEX_ATMA000100S figure 10.1
CW06EWEX_RKME000100S Price content. This Unit Price includes the transport of
CW06EWEX_RKMA000100S Included but not machinery to and within the job site and
limited to: the positioning time for machinery,
cutting and ripping, excavating, leveling,
slope refining, irrigation, compaction as
per specifications, safety requirements,
and intermediate storage within the work
site in the location specified by the
CONTRACTOR’s Site Manager.

When the excavation is performed in


rock, the price also includes preliminary
excavation tests, permits, licenses,
notifications to local authorities,
administrative procedures, required
preliminary project manual, materials
(explosives, mortars, wedges, hydraulic
hammer, etc.), and special machinery.

For material that may be reused in the


project, the price also includes cleaning,
storage, and transport of the material to
the location and in the manner specified
by CONTRACTOR’s Site Manager.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 120
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

When required, the unit price also


includes all timbering and shoring, and
drainage of the terrain by whatever
means is appropriate.
Excluded: Excavation above final grade according
with figure 10.1
Transport to dumping area.
Measurement Excavated volume will be measured in its
system: natural state as shown on approved
reference plans and measuring the
sidewalls of the excavated area as
vertical. Any swelling, any additional
widening of grades, as well as any slopes
that are not as specified on approved
drawings, shall not be measured nor paid.
In case of excavation by manual means, it
will be solely measured units previously
approved and signed by contractor.
Quantities not supported under this
condition will be measured and paid as
the same manner that excavation by
mechanical means.

Unit of measure: The unit of measurement shall be the


cubic meter (m3).

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 121
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

2.6.1.2 Commodity group CW06.EW.GL. Paving and road earthworks. Granular


layers.

CW.06.EW.GL._x::x Supply and execution of sub-bases/bases for paving and/or road


with material according with project standards and specifications.
Commodities included: Referred to:
Price content. The unit price includes material supply with
CW06EWGL_000100S Included but not characteristics according project requirements
CW06EWGL_000200S limited to: and specifications for each kind of material,
transportation, intermediate storage,
preparation of area to be backfilled (scarifying
and re-compacting), spreading, irrigation,
compaction, grading, machinery, auxiliary
means and, in general, all required materials
and labor for the correct completion of all
work.
Price shall also include any swelling, any
additional widening of grades or any slopes
that differ from the specifications listed on
applicable drawings as well as the removal of
excess material from construction of slopes

Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 122
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Backfilling due to any additional widening of


grades that are not as specified on approved
drawings as well as the removal of excess
material from sloping, shall not be measured.
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

CW.06.EW.GL._000800S Supply and spreading of GRAVEL in roads or shoulders areas.


Commodities included: Referred to: This work unit refers to backfilling in roads or
shoulders layers up to required level.
CW06EWGL_000800S Price content. Unit Price includes material supply, transport
Included but not and intermediate storage within the work site,
limited to: machinery, existing ground preparation
(scarifying, compaction, leveling, irrigation,
etc.), spreading and compaction of material,
irrigation, refining of the surface finish grade,
refining of slopes, auxiliary means, safety
requirements, in general, all required
materials and labor for the correct completion
of the required unit.

Price shall also include any swelling, any


additional widening of grades or any slopes
that differ from the specifications listed on
applicable drawings as well as the removal of
excess material from construction of slopes.
Excluded:
Measurement The filling volume shall be measured as stated
system: on approved reference drawings and, when
required, using topographic profiles. Any
swelling, any additional widening of grades or
any slopes that differ from the specifications
listed on applicable drawings as well as the
removal of excess material from construction
of slopes, shall not be measured.
Unit of measure: Cubic meter (m3)

CW.06.EW.GL._000900S Execution of granular layers with material from excavation.


Commodities included: Referred to: Subgrade or road layers

CW06EWGL_000900S Price content. The unit price includes selection of adequate


Included but not materials from excavations with
limited to: characteristics according to project

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 123
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

requirements and specifications,


transportation, intermediate storage, any
loading and unloading of material,
preparation of area to be backfilled (scarifying
and re-compacting), spreading, irrigation,
compaction, grading, any machinery and
equipment, auxiliary means and, in general,
all required materials, labor and equipment
for the correct completion of all work.
Price shall also include any swelling, any
additional widening of grades or any slopes
that differ from the specifications listed on
applicable drawings as well as the removal of
excess material from construction of slopes.

Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings.

Any swelling, any additional widening of


grades or any slopes that differ from the
specifications listed on applicable drawings as
well as the removal of excess material from
construction of slopes, shall not be measured.
Unit of measure: The unit of measurement shall be the cubic
meter (m3).

2.6.1.3 Commodity group CW06.EW.TR. Paving and road earthworks. Transport to


dumping areas.

CW.06.EW.TR._x::x Loading, transport and unloading of remainder material from


excavation.
Commodities included: Referred to: Load, transport and unload of excess material
form excavations, inside or outside property
CW06EWTR_000100S limits but into an authorized dumping area
CW06EWTR_000200S Price content. The unit price includes the loading, transport,
Included but not and unloading of excess excavated material.
limited to: Unloading should be inside or outside property
limits but into an authorized dumping area. In
case of outside, the price also includes all costs
associated with the obtaining of dumping

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 124
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

permits, any dumping fees, maintenance and


preparation of material, etc.
Excluded:
Measurement The transport shall be measured as the
system: difference between the excavated volume and
the backfilling material from the excavation, in
accordance with the system of measurement
and payment. Bulking, swelling, or any increase
in volume the material may experience during
its transport, is not measurable and shall not
be paid.
Unit of measure: Cubic meter (m3)

2.6.2 Commodity group CW06.CP.

2.6.2.1 Commodity group CW06.CP.PA. Concrete in paving.

CW.06.CP.PA._x::x Supply and execution of concrete in paving, reinforced with


single/double mesh.
Commodities included: Referred to:
Price content. The unit price includes material supply,
CW06CPPA_SM0000075 Included but not mesh supply & installation, formwork,
CW06CPPA_SM0000100 limited to: removal of formwork, concrete pouring by
CW06CPPA_SM0000120 any mean, spreading, vibrating, leveling,
CW06CPPA_SM0000130 curing, slope forming, floating, troweling,
CW06CPPA_SM0000150 forming and sealing of joints, heels as
CW06CPPA_DM0000150 required, finishing works against piping,
CW06CPPA_SM0000200 pedestals and other elements (including
CW06CPPA_DM0000200 supply of materials), marking and painting of
horizontal signalizations as borders,
CW06CPPA_DM0000250
direction arrows, zebra crossings, letters,
CW06CPPA_DM0000300
etc. with anti-slip painting, according with
project standards, specifications or
approved drawings, tools, auxiliary means,
machinery, and, in general, all required
materials and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: the approved drawing. Surfaces of holes
greater than 1 m2 (pillars, foots, catch basin,
sinks, etc.) shall be deducted from the
surfaces quantities of the paving.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 125
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Unit of measure: The unit of measure shall be the square


meter (m2)
Method of payment: Payment breakdown shall be as indicated
below:
Execution of concrete in paving
85%
Marking and painting 15%

2.6.2.2 Commodity group CW06.CP.RO. Concrete in Roads.

CW.06.CP.RO._x::x Supply and execution of concrete in roads, reinforced with


single/double mesh.
Commodities included: Referred to:
Price content. The unit price includes material supply,
CW06CPRO_SM0000075 Included but not mesh supply and installation, formwork,
CW06CPRO_SM0000100 limited to: removal of formwork, concrete pouring by
CW06CPRO_SM0000120 any mean, spreading, vibrating, leveling,
CW06CPRO_SM0000150 curing, slope forming, floating, troweling,
CW06CPRO_DM0000150 forming and sealing of joints, heels as
CW06CPRO_DM0000180 required, finishing works against piping,
CW06CPRO_SM0000200 pedestals and other elements (including
CW06CPRO_DM0000200 supply of materials), marking and painting
of horizontal signalizations as borders,
CW06CPRO_DM0000250
direction arrows, zebra crossings, letters,
CW06CPRO_DM0000300
etc. with anti-slip painting, according with
CW06CPRO_GM0000300
project standards, specifications or
approved drawings, tools, auxiliary means,
machinery, and, in general, all required
materials and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: the approved drawing. Surfaces of holes
greater than 1 m2 (pillars, foots, catch basin,
sinks, etc.) shall be deducted from the
surfaces quantities of the paving.

Unit of measure: The unit of measure shall be the square


meter (m2)
Method of Payment breakdown shall be as indicated
payment: below:
Execution of concrete in roads
85%
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 126
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Marking and painting 15%

2.6.3 Commodity group CW06.AP. Asphalt paving and or roads.

2.6.3.1 Commodity group CW06.AP.WC. Asphalt paving and or roads. Wearing


Course.

CW06APWC_x::x Supply and execution of asphalt wearing course.


Commodities included: Referred to:
Price content. The unit price includes the material supply,
CW06APWC_0000030 Included but not spreading by any means, compaction,
CW06APWC_0000040 limited to: forming and sealing joints, tools, auxiliary
CW06APWC_0000050 means, machinery, road marking and painting
CW06APWC_0000060 of horizontal signalizations as borders,
CW06APWC_0000070 direction arrows, zebra crossings, letters, etc.
CW06ARWC_0000030 with anti-slip painting, according with project
CW06ARWC_0000040 standards, specifications or approved
CW06ARWC_0000050 drawings and, in general, all required
materials and labor for the correct
CW06ARWC_0000060
completion of all work.
CW06ARWC_0000070
Excluded:
Measurement The unit shall be measured as specified on the
system: approved drawings. Holes greater than 1 m2
(pillars, foots, catch basin, sinks, etc.) shall not
be measured nor paid.
Unit of measure: The unit of measure shall be the square meter
(m2)
Method of payment: Payment breakdown shall be as indicated
below:
Execution of wearing course
85%
Marking and painting 15%

2.6.3.2 Commodity group CW06.AP.BC. Asphalt paving and/or roads. Base Course.

CW.06.AP.BC._x::x Supply and execution of asphalt base course.


Commodities included: Referred to:
Price content. The unit price includes the material supply,
CW06APBC_0000030 Included but not spreading by any means, compaction, forming
CW06APBC_0000050 limited to: and sealing joints, tools, auxiliary means,
CW06APBC_0000060 machinery, road marking and painting of
horizontal signalizations as borders, direction
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 127
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW06APBC_0000070 arrows, zebra crossings, letters, etc. with anti-


CW06APBC_0000080 slip painting, according with project standards,
CW06APBC_0000090 specifications or approved drawings and, in
CW06APBC_0000100 general, all required materials and labor for the
CW06ARBC_0000030 correct completion of all work.
CW06ARBC_0000040 Excluded:
CW06ARBC_0000050 Measurement The unit shall be measured as specified on the
CW06ARBC_0000060 system: approved drawings. Holes greater than 1 m2
(pillars, foots, catch basin, sinks, etc.) shall not
CW06ARBC_0000070
be measured nor paid.
CW06ARBC_0000075
Unit of measure: The unit of measure shall be the square meter
CW06ARBC_0000080
(m2)
CW06ARBC_0000090
CW06ARBC_0000100

2.6.3.3 Commodity group CW06.AP.PR. Asphalt in paving and/or road priming/tack


coats.

CW.06.AP.PR._x::x Supply and application of tack coat in asphalt paving.


Commodities included: Referred to:
Price content. The unit price includes material supply,
CW06APPR_AG000100S Included but not installation, surface treatment, tools,
CW06APPR_AA000100S limited to: auxiliary means, machinery and, in general,
CW06ARPR_AG000100S all required materials and labor for the
CW06ARPR_AA000100S correct completion of all work.
CW06ARPR_BI000100S Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Holes greater than 1 m2
(pillars, foots, catch basin, sinks, etc.) shall
not be measured nor paid.
Unit of measure: The unit of measure shall be the square
meter (m2)

2.6.4 Commodity group CW06.GP. Gravel Paving

CW.06.GP.._000100S Supply and spreading of gravel in non-paved areas.


Commodities Referred to:
included: Price content. The unit price includes material supply with
Included but not characteristics according project requirements
limited to: and specifications for each kind of material,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 128
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW06GP_000100S transportation, intermediate storage within the


work site, machinery, preparation of area to be
backfilled (scarifying and re-compacting),
spreading, irrigation, auxiliary means, safety
resources and, in general, all required materials
and labor for the correct and completion of all
work.
Excluded: Gravel under concrete paving
Measurement The unit shall be measured as specified on
system: approved drawings. Backfilling due to
unauthorized excavations or slopes, removal of
excess material due to refining, and any other
item not specified here is not measurable and
shall not be paid.
Unit of measure: The unit of measure shall be the cubic meter (m³)

2.6.5 Commodity group CW06.CH. Gutters, Channels, ditches and swales

CW.06.CH.._x::x Execution of road ditches or swales any type.


Commodities included: Referred to:
Price content. The unit price includes excavation,
CW06CH_DT0000U0050 Included but not backfilling, refining, loading and
CW06CH_DT0051R0100 limited to: transporting to an authorized dumping
CW06CH_GUU05000100 area, dumping fees, compaction, tools,
CW06CH_GUU05000125 auxiliary means, machinery and, in general,
CW06CH_GUU05000150 all required materials and labor for the
CW06CH_GUU05000200 correct completion of all work.
CW06CH_GUU05000250 Excluded:
CW06CH_GUU05000300 Measurement The unit shall be measured along the axis as
CW06CH_GU05R100100 system: specified on approved drawings.
CW06CH_GU05R100125 Unit of measure: The unit of measure is the lineal meter (lm)
CW06CH_GU05R100150
CW06CH_GU05R100200
CW06CH_GU05R100250
CW06CH_GU05R100300
CW06CH_GU10R200100
CW06CH_GU10R200150
CW06CH_GU10R200200
CW06CH_GU10R200300

2.6.6 Commodity group CW06.SG. Signposting and side protection.


This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 129
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW.06.SG.._PBSI000200S Supply and complete installation of metallic safety guardrail in


sides of roads, including foundation.
Commodities included: Referred to:
Price content. The unit price includes material supply
CW06SG_PBSI000200S Included but not (materials shall be according with project
limited to: standards, specifications and drawings),
excavation, refining, backfilling, loading and
transporting to an authorized dumping area,
dumping fees, compaction, piping, complete
foundation, barrier installation and
anchoring according with manufacturer
recommendations, painting as per
specification and installation of any required
reflecting fittings.
Excluded:
Measurement The unit shall be measured along the axis as
system: specified on approved drawings.
Unit of measure: The unit of measure is the lineal meter (lm)

CW.06.SG.._PBSI000300S Supply and complete installation of concrete barrier type "New


Jersey" or similar in sides of roads including foundation.
Commodities included: Referred to:
Price content. The unit price includes material supply
CW06SG_PBSI000300S Included but not (materials shall be according with project
limited to: standards, specifications and drawings),
excavation, refining, backfilling, loading and
transporting to an authorized dumping area,
dumping fees, compaction, piping, complete
foundation, barrier installation and
anchoring according with manufacturer
recommendations, painting as per
specification and installation of any required
reflecting fittings.
Excluded:
Measurement The unit shall be measured along the axis as
system: specified on approved drawings.
Unit of measure: The unit of measure is the lineal meter (lm)

CW.06.SG.._SPSI000100S Supply and erection of vertical signposting in ways.


Commodities included: Referred to:
Price content. The unit price includes supply, excavation,
CW06SG_SPSI000100S Included but not backfilling, loading and transporting to an
limited to: authorized dumping area, dumping fees,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 130
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

complete foundation, tools, auxiliary means,


machinery and, in general, all required
materials and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be as specified on approved
system: drawings.
Unit of measure: The unit of measure is the unit (each)

2.6.7 Commodity group CW06.MS. Miscellaneous paving and roads.

CW.06.MS.._SH000100S Supply and installation of polyethylene sheets under pavements.


Commodities included: Referred to:
Price content. The unit price includes material supply of
CW06MS_SH000100S Included but not suitable material according with project
limited to: standards, specifications and drawings,
manpower, overlaps, any additional
widening, cuttings and cropping, tools,
machinery, auxiliary means, and, in general,
all required materials and labor for the
correct completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings, considering only the
concrete surface in horizontal projection to be
protected. Holes greater than 1 m2 (pillars,
foots, catch basin, sinks, etc.) shall not be
measured nor paid.
Unit of measure: The unit of measure is the square meter (m²)

CW.06.MS.._ST000100S Supply and installation of acid resistant tiles/bricks in concrete


pavements.
Commodities included: Referred to: General Paving or paving inside buildings.
Price content. The unit price includes layout works and
CW06MS_ST000100S Included but not plotting, material supply, manpower, surface
limited to: preparation (cleaning, epoxy and polyester
resin grouting, potassium silicate mortar,
etc.), trimming, formation and sealing of
joints (polyisobutylene, epoxy sealing, etc.)
sealing of joints between tiles with polyester
resin, tools, machinery, auxiliary means and,
in general, all required materials and labor for

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 131
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

the correct completion of all work. Always


following manufacture’s recommendations
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings,
Unit of measure: The unit of measure is the square meter (m²)

CW.06.MS.._x::x Supply and application of acid/caustic resistant protection in


concrete surfaces with lining.
Commodities included: Referred to: General Paving or paving inside buildings.
Price content. The unit price includes layout works and
CW06MS_ST000200S Included but not plotting, material supply, manpower, surface
CW06MS_ST000300S limited to: preparation, trimming, formation and sealing
CW06MS_ST000400S of joints, tools, machinery, auxiliary means
CW06MS_ST000500S and, in general, all required materials and labor
for the correct completion of all work. Always
following manufacture’s recommendations
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings,
Unit of measure: The unit of measure is the square meter (m²)

CW.06.MS.._ST000600S Supply and execution of surface finishing in paving with corundum


as per project requirements.
Commodities included: Referred to:
Price content. The unit price includes material supply,
CW06MS_ST000600S Included but not application, tools, auxiliary means,
limited to: machinery, and, in general, all required
materials and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on the
system: approved drawing. Surfaces of holes greater
than 1 m2 (pillars, foots, catch basin, sinks,
etc.) shall be deducted from the surfaces
quantities of the paving.

Unit of measure: The unit of measure shall be the square meter


(m2)

CW.06.MS.._x::x Supply and installation of kerbs precast/”in situ”


Commodities included: Referred to:

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 132
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Price content. The unit price includes material supply,


CW06MS_KB000100S Included but not excavation, filling, load and transport to
CW06MS_KB000200S limited to: dumping area, dumping fees, compaction,
mesh and rebars installation, formwork,
removal of formwork, concrete pouring by any
means, spreading, vibrating, leveling, curing,
floating, troweling, forming and sealing of
joints, tools, auxiliary means, machinery and, in
general, all required materials and labor for the
correct completion of all work.
Excluded:
Measurement The unit shall be measured along the outer face
system: of the element, as specified on the approved
drawing.
Unit of measure: The unit of measure shall be the linear meter
(lm)

CW.06.MS.._x::x Supply and installation of concrete sidewalk floating, single


reinforced mesh.
Commodities included: Referred to:
Price content. The unit price includes material supply,
CW06MS_SW0000100 Included but not excavation, backfilling, loading and
CW06MS_SW0000150 limited to: transporting to an authorized dumping area,
dumping fees, compaction, granular base,
polyethylene layer, mesh installation,
formwork, removal of formwork, concrete
pouring by any mean, spreading, vibrating,
leveling, curing, sloping, floating, troweling,
surface finishing, kerb forming, forming and
sealing of joints, tools, auxiliary means,
machinery and, in general, all required
materials and labor for the correct completion
of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Surfaces of holes greater
than 1 m2 shall be deducted from the surfaces
quantities of the sidewalk.
Unit of measure: The unit of measure shall be the square meter
(m² )

CW.06.MS.._SW000100S Supply and installation of tiled sidewalk with cementious mortar..


Commodities included: Referred to:

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 133
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Price content. The unit price includes supply of all materials


CW06MS_SW000100S Included but not required, excavation, backfilling, loading and
limited to: transporting to an authorized dumping area,
dumping fees, compaction, granular base
and/or concrete base, sand bed, mortar,
tiling works, sloping, sealing of joints, tools,
auxiliary means, machinery and, in general,
all required materials and labor for the
correct completion of all work according with
project specifications.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Surfaces of holes greater
than 1 m2 shall be deducted from the
surfaces quantities of the sidewalk.
Unit of measure: The unit of measure shall be the square meter
(m² )

CW.06.MS.._SW000200S Supply and installation of concrete walkway with Monolithic


concrete steel trowel finish.
Commodities included: Referred to:
Price content. The unit price includes material supply,
CW06MS_SW000200S Included but not excavation, backfilling, loading and
limited to: transporting to an authorized dumping area,
dumping fees, compaction, granular base,
polyethylene layer, mesh installation,
formwork, removal of formwork, concrete
pouring by any mean, spreading, vibrating,
leveling, curing, sloping, floating, troweling,
surface finishing, kerb forming, forming and
sealing of joints, tools, auxiliary means,
machinery and, in general, all required
materials and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Surfaces of holes greater
than 1 m2 shall be deducted from the
surfaces quantities of the sidewalk.
Unit of measure: The unit of measure shall be the square
meter (m² )

CW.06.MS.._OT000100S Execution of asphalt paving repair all the layers, any type.
Commodities included: Referred to:
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 134
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Price content. The unit price includes material supply,


CW06MS_OT000100S Included but not excavation, backfilling, loading and
limited to: transporting to an authorized dumping area,
dumping fees, granular bases, compaction,
irrigation, asphalt priming (tack coat),
asphaltic base and wearing courses,
compaction, sloping, forming and sealing of
joints, finishing painting everything according
with the existing roads/pavings and/or owner
specifications. Tools, auxiliary means,
machinery and, in general, all required
materials and labor for the correct completion
of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Surfaces of holes greater
than 1 m2 shall be deducted.
Unit of measure: The unit of measure shall be the square meter
(m² )

CW.06.MS.._OT000200S Execution of concrete paving repair all the layers.


Commodities included: Referred to:
Price content. The unit price includes supply of all materials,
CW06MS_OT000200S Included but not excavation, backfilling, loading and
limited to: transporting to an authorized dumping area,
dumping fees, compaction, granular base,
polyethylene layer, mesh installation,
formwork, removal of formwork, concrete
pouring by any mean, spreading, vibrating,
leveling, curing, sloping, floating, troweling,
surface finishing, kerb forming, forming and
sealing of joints, finishing painting, everything
according with the existing roads/pavings
and/or owner specifications. Tools, auxiliary
means, machinery and, in general, all required
materials and labor for the correct completion
of all work all also included under this
commodity.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Surfaces of holes greater
than 1 m2 shall be deducted.
Unit of measure: The unit of measure shall be the square meter
(m²)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 135
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW.06.MS.._OT003100S Supply and installation of TPER expansion joint system in roads and
paving including 20mm thick plastic expansion board, waterstop
TPER expansion board cap, dia 20x225-300 speed load transfer
sleeve, staples joining cap to expansion board @600 C/C
Commodities included: Referred to: Joints between concrete paving and road
slabs.
CW06MS_OT003100S Price content. The unit price includes any material supply
Included but not manpower, and installation of 20mm thick
limited to: plastic expansion board cap waterstop TPER,
Dia. 20x225-300 speed load transfer sleeve,
staples joining cap to expansion board @600
C/C each side (for further reference see figure
6.12.1), equipment, auxiliary means, and in
general all required materials, labor and
equipment for the correct completion of the
work according to project standards,
specifications and drawings, following
manufacturer recommendations.
Excluded: Dowel ROD (Considered as embedded item)
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the lineal meter (lm)

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 136
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

FIG.6.12.1 TPER EXPANSION BOARD CAP WATERSTOP SYSTEM JOINT SLABS

CW.06.MS.._OT003200S Supply and installation of TPER expansion joint system in roads and
paving for future pouring of concrete in one side of joint. 20mm
thick plastic expansion board, waterstop TPER expansion board
cap, dia. 20x225-300 speed load transfer sleeve, staples joining cap
to expansion board @600 C/C and 3 layers of nonwoven geotextile.
For protection of the side of the joint to be future poured it is also
included sand backfill to prevent TPER cap damage and 50x250
treated wood plank beveled at 45º and another 50x100 plank glued
and nailed to the 50x250.
Commodities included: Referred to: Joint preparation with one side finished and
future pouring of concrete in the other side of
CW06MS_OT003200S the joint.
Price content. The unit price includes any material supply
Included but not manpower, and installation of: 20mm thick
limited to: plastic expansion board, waterstop TPER
expansion board cap, dia. 20x225-300 speed
load transfer sleeve, staples joining cap to
expansion board @600 C/C and 3 layers of
nonwoven geotextile (for further reference
see figure 9.12.2). For protection of the side
of the joint to be future poured it is also
included sand backfill to prevent TPER cap
damage and 50x250 treated wood plank

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 137
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

beveled at 45º and another 50x100 plank


glued and nailed to the 50x250, equipment,
auxiliary means, and in general all required
materials, labor and equipment for the
correct completion of the work according to
project standards, specifications and
drawings, following manufacturer
recommendations.

Excluded: Speed load transfer sleeve (considered as


embedded element)
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the lineal meter (lm)

FIG. 9.12.2 TPER JOINT DETAIL WITH FUTURE POUR

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 138
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

2.7 Commodity group CW07. MASONRY

2.7.1 Commodity group CW07.OP. Opening and close-outs.

CW.07.OP.._DRUx::x Execution of drilled opening in elevated slabs, walls or


reinforced/mass concrete paving, carried out with a specialized
drilling equipment.
Commodities included: Referred to:
Price content. Price includes layout works and plotting,
CW07OP_DRU3006R15 Included but not drilling equipment (including transportation
CW07OP_DRU3015R30 limited to: to job site, positioning and repositioning,
CW07OP_DRU3030R60 spare parts, etc.), supply of electricity and
CW07OP_DRU6006R15 water from work site connection points,
CW07OP_DRU6015R30 loading and transportation of debris to an
CW07OP_DRU6030R60 authorized external dump site (including all
operations required for the removal of debris
of high altitude work), dumping fees and
permits, auxiliary requirements (scaffolding,
etc.) and, in general, all required materials
and labor for the correct completion of all
work.
Excluded:
Measurement The unit shall be measured as number of
system: drillings really performed.
Unit of measure: The unit of measure shall be the unit (each).

CW.07.OP.._SEUx::x Supply and execution of pipe penetration sealing on concrete walls.


Using mortar or resins. Wall thickness.
Commodities included: Referred to:
Price content. Price includes supply of all materials, layout
CW07OP_SEU3000U20 Included but not works and plotting, drilling equipment
CW07OP_SEU3020R40 limited to: (including transportation to job site,
CW07OP_SEU3040R60 positioning and repositioning, spare parts,
CW07OP_SEU6000U20 etc.), area cleaning, formworks, mortar or
CW07OP_SEU6020R40 resin filling, reinforcing bars if required,
CW07OP_SEU6040R60 drilling for anchoring, supply of electricity and
water from work site connection points,
loading and transportation of debris to an
authorized external dump site (including all
operations required for the removal of debris
of high altitude work), dumping fees and
permits, auxiliary requirements (scaffolding,
etc.) and, in general, all required materials
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 139
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

and labor for the correct completion of all


work.
Excluded:
Measurement The unit shall be measured as number of
system: fillings performed.
Unit of measure: The unit of measure shall be the unit (each).

2.7.2 Commodity group CW07.WL. Walls and partitions.

CW.07.WL.._CBx:x Supply and erection of concrete block masonry wall, with


cementious mortar, in trenches and walls..
Commodities included: Referred to:
Price content. The unit price includes the layout works
CW07WL_CBTR40X20X20 Included but not and plotting, material supply,
CW07WL_CBTR41X21X21 limited to: manpower, formation and sealing of
CW07WL_CBTR40X20X25 joints, joint cleaning and, in general, all
CW07WL_CBEN40X20X20 required materials and labor for the
correct completion of all work.
Excluded: Reinforcing bars
Measurement The unit shall be measured as specified
system: on approved drawings. Holes greater
than 1 m2 shall be discounted from
measurement.
Unit of measure: The unit of measure shall be the square
meter (m²).

CW.07.WL.._x:x Supply and erection of split face concrete block masonry wall,
with cementious mortar in walls.
Commodities included: Referred to:
Price content. The unit price includes the layout works
CW07WL_CBWL40X20X20 Included but not and plotting, material supply, manpower,
CW07WL_SFEN40X20X20 limited to: formation and sealing of joints, joint
cleaning and, in general, all required
materials and labor for the correct
completion of all work.
Excluded: Reinforcing bars
Measurement The unit shall be measured as specified on
system: approved drawings. Holes greater than 1
m2 shall be discounted from
measurement.
Unit of measure: The unit of measure shall be the square
meter (m²).

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 140
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW.07.WL.._CBMS00000100 Increase in concrete block masonry price because of including


steel corrugated reinforcement.
Commodities included: Referred to: Reinforcing bars every n rows and m
columns as specified on project
CW07WL_CBMS00000100 specifications
Price content. The unit price includes supply of
Included but not materials, layout works and plotting,
limited to: manpower, fill-up of concrete block hole,
and, in general, all required materials and
labor for the correct completion of all
work.
Excluded:
Measurement The unit shall be measured as the wall
system: surface to be reinforced.
Unit of measure: The unit of measure shall be the square
meter (m²).

CW.07.WL.._BKTRx:x Supply and erection of brickworks wall, with cementious mortar,


in trenches and walls.
Commodities included: Referred to:
Price content. The unit price includes the layout works and
CW07WL_BKTR00000100 Included but not plotting, material supply, manpower,
CW07WL_BKTR00000150 limited to: formation and sealing of joints, joint
cleaning and, in general, all required
materials and labor for the correct
completion of all work.
Excluded: Reinforcing bars
Measurement The unit shall be measured as specified on
system: approved drawings. Holes greater than 1
m2 shall be discounted from measurement.
Unit of measure: The unit of measure shall be the square
meter (m²).

CW.07.WL.._CO000100S Rough-casting screed, finishing and floating with cementiuos


mortar on vertical brick or concrete block facing walls.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW07WL_CO000100S Included but not plotting, material supply, manpower,
limited to: machinery, tools, auxiliary means
(scaffolding, etc.) and, in general, all required
materials and labor for the correct
completion of all work.
Excluded:

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 141
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Measurement The unit shall be measured as specified on


system: approved drawings. Holes greater than 1 m2
shall be discounted from measurement.
Unit of measure: The unit of measure shall be the square meter
(m²).

2.8 Commodity group CW08. GROUNDING NETWORKS

2.8.1 Commodity group CW08.GR. Grounding Works.

CW.08.GR.._CAx::x Laying of insulated or bare copper conductor on trench or inside


foundations
Commodities included: Referred to:
Price content. The price includes trench excavation, laying of
CW08GR_CA000U016 Included but not cable and backfilling with excavated materials.
CW08GR_CA025R070 limited to:
CW08GR_CA095R300 Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the linear meter
(lm).

CW.08.GR.._COx::x Simple or double Clamp connection, as per project specifications.


Commodities included: Referred to:
Price content. The price includes material supply and
CW08GR_CO000100S Included but not installation, auxiliary means, tools, manpower
CW08GR_CO000300S limited to: and in general, everything required for the
correct completion of all works
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the unit (each)
really installed.

CW.08.GR.._COx::x Cadweld welding connection


Commodities included: Referred to: Aluminothermic welding used for joining
grounding cables
CW08GR_CO000200S Price content. Supply of any joint material, preparation of
Included but not surface, joint execution, auxiliary materials and
limited to: means, labor, any test required and in general
all required material labor and equipment for
the correct completion of the work according

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 142
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

to project standards and specifications and


manufacturer recommendations.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the unit (each)
really installed.

CW.08.GR.._PIx::x Supply and Installation of CS pipe up to Ø 1 1/2" and 550 mm long


for stub up.
Commodities included: Referred to:
Price content. The price includes material supply and
CW08GR_PICSU1500550 Included but not installation, place preparation, any auxiliary
limited to: excavation and backfilling, auxiliary means,
tools, manpower and in general, everything
required for the correct completion of all
works
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the unit (each)
really installed.

CW.08.GR.._PIPVUx::x Supply and Installation of PVC pipe up to Ø 1 1/2" and 600 mm


long for stub up.
Commodities included: Referred to:
Price content. The price includes material supply and
CW08GR_PIPVU1500600 Included but not installation, place preparation, any auxiliary
limited to: excavation and backfilling, auxiliary means,
tools, manpower and in general, everything
required for the correct completion of all
works
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the unit (each)
really installed.

CW.08.GR.._OT000100S Supply and Installation of connection pad for grounding network


welded on concrete reinforcement, as per project specifications.
Commodities included: Referred to:

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 143
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Price content. The price includes material supply,


CW08GR_OT000100S Included but not installation, connection to reinforcement or
limited to: other elements (clamp o Cadweld welding),
tools, auxiliary means, and, in general, all
required materials and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the unit (each)
really installed.

CW.08.GR.._OT000200S Measurements of step and contact voltage, equipotentiality and


earthing resistance per process unit.
Commodities included: Referred to:
Price content. The price includes supply of measuring
CW08GR_OT000200S Included but not devices, measurement of step and contact
limited to: voltage, equipotentiality and earthing
resistance according to the particular study
shall be performed by subcontractor upon
completion and it shall be done per process
unit.
Excluded:
Measurement It shall be performed per process unit
system: considering each one as a LS
Unit of measure: The unit of measure shall be the Lump Sum by
process unit (LS x process unit)

2.9 Commodity group CW09. MISCELANEOUS

2.9.1 Commodity group CW09.UB. Urbanization, landscaping and finishing works.

CW.09.UB.._GA000100S Supply and execution of complete gardening with irrigation system


in non-paved areas.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW09UB_GA000100S Included but not plotting, manpower, excavation, backfilling,
limited to: loading and transporting to an authorized
dumping area, dumping fees, supply and
installation of any material such as soil,
fertilizer, grass, complete irrigation system
from connection point (catch basin, piping,
accessories, clocks, sprinklers, etc.) and, in

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 144
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

general, all required materials and labor for


the correct completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Only the gardening area
will be measured, the area from the
connection point to the gardening area (in
case of connection point is out of the
gardening area) shall not be measured.
Unit of measure: The unit of measure shall be the square meter
(m²).

2.9.2 Commodity group CW09.FN. Fencing

2.9.2.1 Commodity group CW09.FN.TF. Urbanization, landscaping and finishing


works.

CW.09.FN.TF._FNx:x Temporary metallic wire mesh fence, galvanized structure, 2 m


minimum height, set with clamps.
Commodities included: Referred to:
Price content. The unit price includes material supply,
CW09FNTF_FN0100H200 Included but not installation, concrete footing, metal bands
CW09FNTF_FN0100H300 limited to: (clamps), accessories, tools, auxiliary means,
machinery, equipment and, in general, all
required material and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Temporary gates shall be
measured as Temporary metallic wire mesh.
Unit of measure: The unit of measure shall be the lineal meter
(lm).

2.9.2.2 Commodity group CW09.FN.PF. Permanent Fence.

CW.09.FN.PF._FNx:x Permanent metallic wire mesh fence, set with clamps, with a
bayonet with three galvanized barbed wire lines.
Commodities included: Referred to:
Price content. The price includes material supply,
Included but not excavation, backfilling and filling, concrete
CW09FNPF_FN0100H200 limited to: pouring, clamps, accessories, earthing,
tools, auxiliary means, machinery and, in

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 145
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

CW09FNPF_FN0200H200 general, all required material and labor for


CW09FNPF_FN0300H200 the correct completion of all work.
CW09FNPF_FN0100H155 Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the lineal
meter (m).

CW.09.FN.PF_DOx:x Supply and installation of doors


Commodities included: Referred to:
Price content. The price includes material supply,
Included but not layout works and plotting,
CW09FNPF_DOMA0100W060 limited to: excavation, backfilling and filling,
CW09FNPF_DOAD0060R110 concrete pouring, installation, lock,
CW09FNPF_DOMA0100W046 all hardware required for hanging,
elements for opening (wheels,
CW09FNPF_DOMA0200W060
guides, rails, etc.) tools, cabling,
CW09FNPF_DOMA00100W073 control system, calibrating auxiliary
CW09FNPF_DOMA0200W073 means, machinery and, in general all
CW09FNPF_DOMA0100W083 required material and labor for the
CW09FNPF_DOMA0100W100 correct completion of all work.
CW09FNPF_DOMA0100W180 Excluded:
Measurement The unit shall be measured as
CW09FNPF_DOMA0200W180
system: specified on approved drawings.
CW09FNPF_DOMA0100W010 Unit of measure: The unit of measure shall be the unit
CW09FNPF_DOMA0100W012 (each) of door installed.
CW09FNPF_DOMA0100W040
CW09FNPF_DOMA0100W019

CW.09.FN.PF._OT000100S Supply and installation of surrounding barrier made of posts


and removable chains between them as per project
standards and specifications.
Referred to:
Commodities included: Price content. The price includes material supply,
Included but not layout works and plotting, excavation,
limited to: backfilling and filling, concrete pouring,
CW09FNPF_OT000100S installation, lock, all hardware required
for hanging, elements for opening
(wheels, guides, rails, etc.) tools,
auxiliary means, machinery and, in

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 146
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

general all required material and labor


for the correct completion of all work.
Excluded:
Measurement The unit shall be measured as specified
system: on approved drawings.
Unit of measure: The unit of measure shall be the linear
meter (lm) of barrier installed.

CW.09.FN.PF._OT000200S Supply and installation of access point to process areas including


access movable barrier according with project standards and
specifications.
Referred to:
Commodities included: Price content. The price includes material supply, layout
Included but not works and plotting, excavation, backfilling
limited to: and filling, concrete pouring, installation,
CW09FNPF_OT000200S lock, all hardware required for hanging,
elements for opening (wheels, guides, rails,
etc.) tools, auxiliary means, machinery and,
in general all required material and labor for
the correct completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the unit (each)

CW.09.FN.FP._DOMA0100W020 Supply and installation of Geogrid sand fence 2 m.


minimum height, galvanized structure. Sand fence material
made of HDPE UV-stabilized fixed to the tension wires.
With soil stabilization around posts and fence if required.
Everything according to manufacturer recommendations,
and project standards, specifications and drawings.
Commodities included: Referred to: Geogrid sand fence 2 m. minimum
height, consisting on: posts made of
galvanized steel pipe or equivalent
CW09FNPF_DOMA0100W020 profiles with the required straining
post, posts shall be driven into the
ground to a depth of 900mm minimum,
galvanized or PVC coated tension wires
and sand fence made of HDPE UV-
stabilized fixed to the tension wires.
Surfaces susceptible to wind erosion, 2
m width strip both sides of the fence

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 147
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

shall be stabilized with crude oil or


other soil stabilized agents
Price content. The unit price includes material supply
Included but not and installation of posts, wires and
limited to: sand fences, excavation for posts,
concrete for post anchoring and all
required means as machinery, labor,
tools, minor and auxiliary supplies, etc.,
required for the correct completion of
the work, soil stabilization with
stabilizer agents if required. Everything
according to manufacturer
recommendations, and project
standards, specifications and drawings.
Excluded:
Measurement The unit shall be measured in
system: horizontal projection as specified on
approved plan drawings.
Unit of measure: The unit of measure shall be the lineal
meter (lm).

2.9.2.3 Commodity group CW09.FN.RP. Fence Reposition

2.9.3 Commodity group CW09.ET. ELECTRICAL TRENCHES MISCELLANEOUS.

CW.09.ET.._000100S Supply and installation of warning tile any type and size in
underground systems.
Commodities Referred to:
included: Price content. The unit price includes the material supply,
Included but not installation, overlaps, tools, auxiliary means,
CW09ET_000100S limited to: and, in general, all required materials and labor
for the correct completion of all work.
Excluded:
Measurement The unit shall be measured as the width used for
system: trench excavation with the length indicated on
drawings measured along the trench axis.
Unit of measure: The unit of measure shall be the square meter
(m² )

CW.09.ET.._000200S Supply and installation of warning tape for underground systems.


Commodities Referred to:
included: Price content. The unit price includes the material supply,
Included but not installation, overlaps, tools, auxiliary means,
CW09ET_000200S limited to:
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 148
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

and, in general, all required materials and labor


for the correct completion of all work.

Excluded:
Measurement The unit shall be measured with the trench
system: length indicated on drawings measured along
the trench axis.
Unit of measure: The unit of measure shall be the linear meter
(lm)

CW.09.ET.._001100S Supply of Router marker sitting by others.


Commodities Referred to:
included: Price content. The unit price includes the material supply.
Included but not
CW09ET_001100S limited to:
Excluded:
Measurement The unit shall be measured by unit, counted
system: using the theoretical criteria stated on project
specifications.
Unit of measure: The unit of measure shall be the unit (each)

2.9.4 Commodity group CW09.UG.Unerground miscellaneous

2.9.5 Commodity group CW09.MS. Rest of Miscellaneous items.

CW.09.MS.._x:x Supply and installation of geotextile sheet.


Commodities Referred to:
included: Price content. The unit price includes material supply,
Included but not manpower, grip, overlaps, any additional
CW09MS_000000S limited to: widening, cuttings and cropping, tools,
CW09MS_001000S machinery, auxiliary means, and, in general, all
required materials and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings.
Unit of measure: The unit of measure shall be the square meter
(m²).

CW.09.MS.._010000S Supply, installation and removal of recovery sheet piling system with
plate thickness as per project standards, specifications or drawings.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 149
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Supply, prefabrication, erection and removal of auxiliary steel


structure is included.
Commodities Referred to:
included: Price content. The price includes material supply, layout works
Included but not and plotting, installation, Removal, truck load
CW09MS_010000S limited to: and transport out of property limits, tools,
auxiliary means, specialized machinery and, in
general all required material and labor for the
correct completion of all work. Supply,
prefabrication, erection and removal of auxiliary
steel structure is included.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings, taking into account that the
height shall be carried out from the theoretical
top of the steel sheet to the actual driven level
or IFC design level (whichever comes first). For
width measurement it shall be taken the
theoretical measurement between inner edges
of metal sheet wall (straight length) as per IFC
drawing.. Excess of sheets length from above
specified shall not be measured nor paid.
Unit of measure: The unit of measure shall be the square meter
(m²) of sheets.

CW.09.MS.._011000S Supply and installation of permanent or lost sheet piling system with
plate thickness as per project standards, specifications or approved
drawings.
Commodities Referred to:
included: Price content. The price includes material supply, layout works
Included but not and plotting, installation, tools, auxiliary means,
CW09MS_011000S limited to: specialized machinery and, in general all
required material and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings, taking into account that the
height shall be carried out from the theoretical
top of the steel sheet to the actual driven level
or IFC design level (whichever comes first). For
width measurement it shall be taken the
theoretical measurement between inner edges
of metal sheet wall (straight length) as per IFC

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 150
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

drawing. Excess of sheets length from above


specified shall not be measured nor paid.
Unit of measure: The unit of measure shall be the square meter
(m²) of sheets.

CW.09.MS.._012000S Monthly renting for recovery sheet piling.


Commodities Referred to:
included: Price content. The price includes all cost regarding with
Included but not maintenance of sheet piling as rent of sheets,
CW09MS_012000S limited to: etc.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings, taking into account that the
height shall be carried out from the theoretical
top of the steel sheet to the actual driven level
or IFC design level (whichever comes first). For
width measurement it shall be taken the
theoretical measurement between inner edges
of metal sheet wall (straight length) as per IFC
drawing.. Excess of sheets length from above
specified shall not be measured nor paid.
Uncompleted months shall be measured and
paid as the correspondent fraction of the
month.
Unit of measure: The unit of measure is the square meter x day
(m2/day) of sheets

CW.09.MS.._020000S Design, supply and installation of dewatering system using well points
method or similar to dewater large open areas.
Commodities Referred to:
included: Price content. The price includes design of the system, supply
Included but not of materials and equipment required, complete
CW09MS_020000S limited to: execution and installation of the system and
removal.
This item covers massive dewatering in large
areas but does not cover the dewatering
included in excavation items.
Excluded:
Measurement The unit shall be measured as the horizontal
system: area to be dewatered as specified on approved
drawings and or CONTRACTOR instructions.
Unit of measure: The unit of measure is the square meter (m2)

CW.09.MS.._021000S Dewatering system monthly renting.


This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 151
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

Commodities Referred to:


included: Price content. The price includes all cost regarding with
Included but not maintenance of massive dewatering system as
CW09MS_021000S limited to: pump fuel cost, equipment maintenance costs,
filter maintenances costs, etc.

Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings and or CONTRACTOR
instructions. Uncompleted months shall be
measured and paid as the correspondent
fraction of the monthly rate
Unit of measure: The unit of measure is the square meter per
month (m2*month)

CW.09.MS.._030000S Supply and installation of GALVANIZED STRAIGHT HANRAILING AND


VERTICAL LADDERS as per project requirements..
Commodities Referred to:
included: Price content. The price includes material supply, site or
Included but not workshop prefabrication, hot dip galvanizing,
CW09MS_030000S limited to: transport to site and erection, bolted, welded or
any other fixing system, painting according with
project specifications. Manpower, tools,
equipment and, in general, everything required
for the correct completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings and applying weight as
specified in the manufacturer’s catalog. When
these weights are not specified, weight shall be
calculated applying the density of 7.85 t/m3.
Unit of measure: The unit of measure is the Kilogram (kg)

2.10 OTHER TYPES OF WORK UNITS.

For any type of work not previously listed in this document, criteria of the Contractor’s Site
Manager shall apply.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 152
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

C. HOURLY RATES.

1. General

The Subcontractor shall not begin any work using Hourly Rates without prior written approval
by Contractor’s Site Manager. Any unauthorized or additional work performed without
written approval shall not be measured nor paid.

The Contractor’s Site Manager will expect on receiving a level of production officially
recognized in each aspect of labor and machinery operation.

Contractor will only accept for reviewing and signing, when applicable, those time sheets
which have been turned in up to 24 hours following the completion of the work to which
they apply.

All charges for Hourly Rates shall be paid using the same payment conditions as other work
units in the subcontract. Under no circumstances will special terms or conditions of payment
be accepted.

For the purpose of measurement and payment of Hourly Rates, the following conditions
apply to the different hourly classifications:

a. Normal Hours: Refers to the first ten (10) hours of each workday, from (and including)
Monday, through (and including) Saturday.

b. Overtime Hours: Refers to any additional hours completed during the above-
mentioned description.

c. Holiday Hours: Refers to the twenty-four (24) hour period of Sunday and official local
holidays celebrated in the province where the project shall be completed.

2. Labour.

These prices include all levels of supervision above the level of Foreman, tools, safety and
security items, transportation to/from and within work site, wear and tear of tools and
depreciation costs, standard consumables (welding materials, gases, etc.), travel, per-diem,
general costs, profit, insurance, salaries, bonuses, social securities, taxes, and any other type
of charge which can, for whatever reason, affect the cost of the item.

3. Machinery.

Prices refer only to production work hours. Any loss of time due to equipment breakdown,
transit time for transportation from point of origin to work site, transport back to point of

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 153
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

origin, or any other circumstances that may affect the work to be accomplished are not
chargeable and will not be paid.

Price includes: Transportation costs to/from and within work site, fuel, lubricants,
maintenance, repair, wear and tear of machinery and depreciation costs, taxes, general costs,
and the cost of any other equipment, tools or accessories which are not specified in the
Schedule of Rates but may be required for the completion of the work that has been
requested.

For mobile machinery and transportation vehicles, price includes driver, operator, as well as
auxiliary personnel required for its operation.

4. Material.

Prices are for material delivered to the job site in the place specified by Contractor’s Site
Manager, and include general costs, profit, insurance, bonuses, taxes, transportation to and
within work site, safety and security items, and any other type of charge which can, for
whatever reason, affect the cost of the item.

For any other type of material received that has not been covered herein and is intended for
use at the work site, payment will be as stipulated on the purchase invoice plus a 10% mark
up for handling costs and profit but must have been previously approved in writing by the
Contractor’s Site Manager.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS

PROJECT: 70240 CCC SAN LUS RIO COLORADO


ANNEX I - WORK UNITS, UNITS OF SHEET 154
MEASUREMENT AND APPLICABLE PRICES OF 154

RFQ 70240-2510. REV. 01

II. SCHEDULE OF RATES.

The Subcontractor should complete, in its entirety, the following list of Unit Prices and Hourly
Rates. Consideration should be given to definitions listed in specifications and Technical
Requisitions, as well as the following:

1. UNIT PRICES.

Supply: Comprises all the costs associated with the supply and delivery of permanent
materials (by work unit) to the work site. This includes general costs and profit.

Erection: Comprises all costs of direct labor for a work unit. Includes unloading of
material, intermediate transportation within work site, consumable material, temporary
installations and facilities, all running costs, work costs, erection equipment costs (i.e.
scaffolding, cranes, machinery, tools, etc.), indirect personnel, general costs and profit.

2. HOURLY RATES.

Includes all costs applicable to each work unit, including indirect personnel, general
costs and profit.

The Subcontractor must complete the price list, including those items without quantities
shown, in the format provided and be aware that any bid which does not meet this prerequisite
will be rejected.

If the Subcontractor wishes to provide to any amplifying information to this price list it should be
submitted in a separate sheet attached to this document.

Prices will be entered using two position decimal points (hundredths) only. All other decimal
values will be rounded up to the nearest hundredth.

This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden

You might also like