TÉCNICAS REUNIDAS
The object of this document is to define the pricing structure, price content, methodology of
measurement, and prices to apply to quantities obtained from drawings in all Civil Works
activities performed by the Subcontractor in accordance with the awarded Scope of Work.
This system shall be applied to Subcontracts established by Unit Prices, as well as increases
or decreases of quantities for Lump Sum Subcontracts where contractual provisions entitle
to do so.
New prices that could appear during the execution of the works shall follows the same basis
of estimation than quoted prices, and they will be calculated under interpolation and
proportionality rules with unit prices already agreed in the Subcontract.
1. GENERAL.
“Red Marked” documentation, Protocols, Acts, Notices of Inspection, etc. shall be prepared
by SUBCONTRACTOR as supportive documentation for measurement preparation. Final
measurements shall be settled through “As Built” documentation when its preparation is
contractually required to SUBCONTRACTOR.
Measurement of work units for interim certification purposes shall be carried out on
supportive documentation which shall be handed over by SUBCONTRACTOR to CONTRACTOR
once endorsed by CONTRACTOR’s supervision team as well as by CONTRACTOR’s QC team.
SUBCONTRACTOR shall endeavor to get signatures on supportive documentation from them
in advance of each period cut-off date. Aforesaid signatures shall be a compulsory
requirement for proceeding with measure of quantities and establishing progress payments,
which shall be done by CONTRACTOR’s subcontracts team.
Where the CONTRACTOR deems it necessary, field measurements shall be taken or spot
check shall be done over provided supportive documentation. Field measurements shall be
done jointly with the SUBCONTRACTOR and the results shall be accepted as valid.
CONTRACTOR shall notify aforesaid calls to SUBCONTRACTOR one day in advance. Failing
SUBCONTRACTOR to attend calls for taking field measurements shall lead to accept
CONTRACTOR’s outcomes as valid.
In general, and not exhaustive or limited to, the unit prices shall include as a minimum:
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
- All necessary resources for timely performance of works (e.g. direct labor, machinery,
Auxiliary Equipment or means, consumables, Materials, Supplies, Technical and
Administrative Support, etc.).
- All labor, operations and other costs for access, unloading, receiving, unpacking,
handling, storage (inclusive of hazardous materials, if any), maintenance and onsite
transportation, preservation, pre-assembly / prefabrication, installation and
pre/commissioning, housekeeping, HSE prevention and mitigation measures, waste
management (inclusive of hazardous materials, if any), mitigation systems to prevent
the effects from dust, noise and vibrations, winterization (heating & hording) etc. into
the WORKS or the surrounding areas.
- Required Construction Engineering development, including but not limited to, Work
Method Statements & Task Risk Analysis.
- To maintain all the working areas free from rain water and/or water table in order to
allow the operability of the construction equipment during all the duration of the
WORKS. In particular the execution of appropriate temporary provisions (i.e. slopes,
earth ditches, earth containing walls, pits, etc.) in such a way to collect the water for its
disposal, including the use of motor pumps where and when necessary
- Topographical set-up (also referred herein below as ‘setting out’) of the foundations
and any other Civil WORKS starting from the bench marks assigned by the
CONTRACTOR, assignment of a qualified team of Surveyors to be approved by
CONTRACTOR
- Daily cleaning of the existing construction and roads eventually made dirty by
SUBCONTRACTOR. Restoration of existing roads and any other existing facility
eventually damaged by SUBCONTRACTOR
- Clearing and cleaning of the work site, access roads, ramps, leveling and preparation of
the work areas to allow the suitable arrival of materials and the timely positioning of
equipment
- QC dossier and needful documentation from SUBCONTRACTOR.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Measurements shall always be taken from specifications, Approved for Construction standards
and drawings, and/or “as built” drawings whenever possible.
If the Contractor’s Site Manager deems it necessary to take measurements in the field, these
measurements shall be accomplished jointly with the Subcontractor and the results shall be
accepted as valid.
CW GG SS PP BB x::x:
CW: Discipline Civil Works
GG: Group Code
SS: Subgroup Code
PP: Part Code
BB: SubPart Code
x::x: Sequence Code
2. COMMODITY GROUPS.
The following table include code groups in which civil discipline is divided.
Commodity
Group Description
Group
CW01 DEMOLITIONS AND DISASSEMBLES
CW01DM Demolitions
CW01DS Disassembles
CW02 GENERAL SITE PREPARATION
CW02GR Grubbing and Clearing
CW02EX Excavations
CW02BK Backfillings and Embankments
CW02SI Soil Improvement
CW02TR Transport of Materials
CW03 EARTH WORKS
CW03EX Excavations
CW03EXFD Excavation In foundations, pits, extrados of walls
CW03EXTR Excavation in trenches and channels
CW03EXLO Large Open excavations
CW03EXMA Excavations with manual means
CW03BK Backfillings
CW03BKFD Backfilling In foundations, pits, extrados of walls, trenches and channels
CW03BKEP Backfilling in earth ponds and tank basins
CW03BKTF Backfilling in tank foundations
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW05UGPV PVC.
CW05UGPP Polypropylene
CW05UGPE HDPE pipes.
CW05UGGJBW GRP/GRE Butt & Wrap
CW05UGGJTT GRP/GRE (Adhesive bonded taper/taper joint).
CW05UGGJMJ GRP/GRE (mechanical joint, seal look joint).
CW05UGCO Concrete.
CW05UGCI Cast Iron.
CW05UGCS Carbon Steel
CW05UGEC Galvanized Steel Piping
CW05UGFV Flanged Valves
CW05UGWR Wrapping
CW05UGEC Electrical conduits (single pipes, not duct banks).
CW06 PAVING AND ROADS
CW06EWEX Paving and roads earthworks. Encasements.
CW06EWGL Paving and roads earthworks. Granular layers.
CW06EWTR Paving and roads earthworks. Transport to dumping areas.
CW06CPPA Concrete in paving.
CW06CPRO Concrete in roads.
CW06APWC Asphalt paving and/or roads. Wearing course.
CW06APBC Asphalt paving and/or roads. Base course.
CW06APPR Asphalt paving and/or roads. Priming.
CW06GP Gravel paving.
CW06CH Gutters, channels, ditches and swales.
CW06SG Signposting and side protections.
CW06MS Miscellaneous paving and roads.
CW07 MASONRY
CW07OP Openings and close-outs.
CW07WL Walls and partitions.
CW08 GROUNDING NETWORKS
CW08GR Grounding Works
CW09 MISCELLANEOUS
CW09UB Urbanization, landscaping and finishing works.
CW09FNTF Temporary and removable fence.
CW09FNPF Permanent Fence.
CW09FNRP Fence Reposition.
CW09ET Electrical trenches miscellaneous.
CW09UG Underground miscellaneous.
CW09MS Rest of Miscellaneous items
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
In case those demolitions activities might influence on normal use of other services, SUBCONTRACTOR
shall put all resources to ensure maintenance of service as well as avoid any damage to other structures
or existing facilities.
In case that any facilities or service have to be replaced, this shall be done at time enough to ensure
the continuity of the corresponding services and under CONTRACTOR’s approval. These operations will
be included in the unit prices unless there are explicitly referred and defined in another project unit.
Unit prices shall also include all the required works in this list, but not limited thereto:
- Preparation of a Work Method Statement and Risk Analysis of activities to be performed for
CONTRACTOR/Owner’s approval, indicating decommissioning and demolition/dismantling
procedures, HSE measures, etc.
- Thorough verification of any available information during execution as well as checkup of hidden
facilities.
- Needful specific materials, tools and/or auxiliary means for a timely execution of works, such as
cutting and removal of rebar from reinforced concrete, grinding, excavations, slope stabilizations,
shoring, dewatering, cutting and compacted backfilling up to natural soil elevation with material from
the excavation, as per soil report or another Project specification, once debris have been removed.
- Separation between distinct categories of the materials in order to comply with local environment
agencies (for instance, concrete and rebar need to be separated during demolition of reinforced
concrete elements)
- Management, handling, storage, treatment (if required) and disposal of wastes (as
debris/rubble/leftovers/scraps, etc…) whatever their location into authorized dumpsites or laydown
areas, including fees if necessary.
- For any material that may be reused in the project, the price shall also include cleaning, storage
and transport of the material to a location designed by the Site Manager.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
- The execution of these activities shall be performed using mechanical and/or manuals resources.
In case of demolitions by manual means, it will be solely measured units previously approved and
signed by contractor. Quantities not supported under this condition will be measured and paid as the
same manner that demolition by mechanical means.
It will be solely measured under this criteria the corresponding quantities to the elements defined in
demolition and disassembly drawings. Any other element that could appear during the execution of
another works and/or chapters will be measured and paid as the corresponding unit.
SUBCONTRACTOR shall ensure stability of all remaining elements to be demolished at any stage of the
work or stability of a partial demolition.
CW.01.DM_x::x Demolitions
Commodities included: Definition: Demolition of supports, walls, structures,
CW01DM_MCME000000S buildings, pavements, concrete slabs,
CW01DM_MCMA0000L10 foots, etc.
CW01DM_MCMA010R100 Price content: Price includes all work required for the
CW01DM_SLME000000S Included but not demolition, shop machinery, demolition
CW01DM_SLMA000000S limited to: equipment, auxiliary requirements
CW01DM_RCME000000S (scaffolding, etc.), excavation required to
CW01DM_RCME000100S expose the system to be demolished,
CW01DM_RCMA000000S cutting and removal of rebars from
reinforced concrete, loading and
CW01DM_BUME000000S
transporting of debris to an authorized
exterior dump site (including all operations
involved with the removal of debris from
elevated work), intermediate storage,
dumping fees, safety requirements in
accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Excluded:
Measurement volume of concrete in each concrete
system: element, as measured on approved
drawings.
Unit of measure: Cubic meter (m3)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.01.DM_UGME000000S Price content: Price includes all work required for the
Included but not demolition, shop machinery, demolition
limited to: and dismantling equipment, auxiliary
requirements (scaffolding, etc.), cutting,
excavation required to expose the system
to be demolished, loading and transporting
of debris to an authorized exterior dump
site (including all operations involved with
the removal of debris from elevated work),
Backfilling with adequate material to
restore and left the area as the original
state, intermediate storage, dumping fees,
safety requirements in accordance with
applicable standards and specifications,
irrigation requirements and, in general, all
required materials and labor for the
correct completion of the required unit.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.01.DS_SSME000000S Price content: Price includes all work required for the
Included but not disassembly, including cranes, shop
limited to: machinery, auxiliary requirements
(scaffolding, etc.), loading and
transportation of debris to an authorized
external dump site (including all operations
involved with the removal of debris from
elevated work), intermediate storage,
dumping fees, safety requirements in
accordance with applicable standards and
specifications, irrigation requirements and,
in general, all required materials and labor
for the correct completion of the required
unit.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Commodities included: Referred to: Removal of natural and organic soil, trees,
plants, bushes, grass, roots.
CW02GR_GCME0000015 The vegetation, including roots tree stumps,
CW02GR_GCME0000020 shall be removed completely.
CW02GR_GCME0000030 Price content. The unit price includes the transport of
CW02GR_GCME0000040 Included but not machinery to and within the job site,
CW02GR_SCME0000015 limited to: positioning time for machinery, cleaning,
ripping, excavation of the surface grade,
intermediate storage, removal and
transport of all materials from the cleaned
area to an authorized external dump area
(including fill dirt, topsoil, vegetation, trees,
brushwood, stumps, plants, underbrush, fall
wood, and all types of undesirable material)
safety requirements and dumping fees.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Additional Width
Diameter of the (S)
conduit /pipe or allowance for each Angle of slope
(mm) side of the conduit
(cm) S
Up to 150 10 Vertical
≥ 151 to 300 15 Vertical
≥ 301 to 500 20 Vertical
≥ 501 to 900 30 Vertical
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
2.3.1.4 Commodity group CW03.EX.MA Deep and trench excavation and/or gallery
excavation with manual means
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW03EXMA_GL000000S Price content. This Unit Price includes cutting and ripping,
CW03EXMA_RK000000S Included but not excavating, leveling, slope refining,
limited to: irrigation, compaction as per specifications,
tools and manual equipment, safety
requirements, and intermediate storage
within the work site in the location specified
by the CONTRACTOR’s Site Manager.
Excluded:
Measurement Excavated volume will be measured in its
system: natural state as shown on approved
reference plans and measuring the sidewalls
of the excavated area as vertical. Any
swelling, any additional widening of grades,
as well as any slopes that are not as specified
on approved drawings, shall not be
measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
2.3.2.2 Commodity group CW03.BK.EP Backfilling in earth ponds and tank basins
CW.03.BK.EP._x::x Supply and execution of backfilling in earth dikes for ponds and/or
tank basins, carried out in layers, with granular material.
Commodities included: Referred to:
CW03BKEP_GM000000S Price content. The unit price includes material supply with
CW03BKEP_CS000000S Included but not characteristics according with project
CW03BKEP_CL000000S limited to: requirements and specifications for each
CW03BKEP_MR000000S kind of material, transportation,
intermediate storage, access ramp,
preparation of area to be backfilled
(scarifying and recompacting), spreading of
backfill in layers, irrigation requirements,
compaction of these layers, leveling, grading
and compaction of surface finish grade,
refining of slopes, required machinery,
auxiliary means and, in general, all required
materials and labor for the correct
completion of all work. Price also includes
the execution of any test indicated in the
project specifications or ITP and its report.
Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings considering,
as general rule, sidewalls of the excavated
area as vertical, unless otherwise specified
by Contractor.
Backfilling due to any additional widening of
grades, any slopes that are not as specified
on approved drawings as well as the removal
of excess material from construction of
slopes, shall not be measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).
CW03BKEP_GM000100S Price content. The unit price includes material supply with
Included but not characteristics according with project
limited to: requirements and specifications for each
kind of material, transportation,
intermediate storage, access ramp,
preparation of area to be backfilled
(scarifying and recompacting), spreading of
backfill in layers, irrigation requirements,
compaction of these layers, leveling,
grading and compaction of surface finish
grade, refining of slopes, required
machinery, auxiliary means and, in general,
all required materials and labor for the
correct completion of all work. Price also
includes the execution of any test indicated
in the project specifications or ITP and its
report.
Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings.
Backfilling due to any additional widening
of grades, berms, any slopes that are not as
specified on approved drawings as well as
the removal of excess material from
construction of slopes, shall not be
measured nor paid
Unit of measure: The unit of measurement shall be the cubic
meter (m3).
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.03.BK.MW._RRx::x Supply and execution of RIP RAP with stone weight size according
with project standards and specifications.
Commodities included: Referred to: Backfilling with RIP-RAP material
CW03BKMW_RR000000S Price content. The unit price includes material supply with
CW03BKMW_RR000100S Included but not characteristics according with project
limited to: requirements and specifications for each
kind of material, transportation,
intermediate storage, access ramp,
preparation of area to be backfilled
(scarifying and recompacting), geotextile
layer, spreading of backfill in layers,
irrigation requirements, compaction of
these layers, leveling, grading and
compaction of surface finish grade, refining
of slopes, required machinery, auxiliary
means and, in general, all required
materials and labor for the correct
completion of all work. Price also includes
the execution of any test indicated in the
project specifications or ITP and its report.
Excluded:
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.LN.._LNxx0005R10 Supply and pouring of lean concrete, 5 <= e <= 10 cm. Concrete
grade and class of exposure as per project requirements, including
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.LN.._MA000000S Supply and pouring of mass concrete for filling, piping placement,
supports, etc. Concrete grade and class of exposure as per project
requirements, including any type of additives as colorants,
accelerators, retardants, etc.
Commodities included: Referred to:
Price content. The unit price includes supply of material,
CW04LN_MA000000S Included but not pouring by any means, spreading, vibrating,
limited to: leveling, curing, finishing of surfaces, repair of
any defect that concrete may have,
manpower, tools, machinery and, in general,
all required materials and activities for timely
execution including but not limited to
ramming of bottom, auxiliary formworks,
protective layers (e.g. bitumen, sheets...),
water depletion... and for any concrete type or
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.LN.._CY000000S Supply and pouring of cyclopean concrete for filling, piping placement,
supports, etc. Concrete grade and class of exposure as per project
requirements, including any type of additives as colorants,
accelerators, retardants, etc.
Commodities included: Referred to: Means a special kind of mass concrete that is
having embedded large stones (around 30 cm
CW04LN_CY000000S diameter)
Price content. The unit price includes supply of material,
Included but not pouring by any means, spreading, vibrating,
limited to: leveling, curing, finishing of surfaces, repair of
any defect that concrete may have, manpower,
tools, machinery and, in general, all required
materials and labor for the correct completion
of all work
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings
Unit of measure: The unit of measure shall be the cubic meter
(m3)
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Excluded:
Measurement The unit shall be measured as stated on
system: approved drawings.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.SF.IS._x::x Supply of materials and execution of small footing cast "in situ"
with reinforced concrete.
Commodities included: Referred to: Small foundations (foots, sleepers, pipe and
CW04SFIS_25000U025 stair supports, etc.) to support equipment
CW04SFIS_25025R050 and pipes. The concrete volume is up to 1 m3.
CW04SFIS_25050R100 When the volume exceeds 1 m3, the small
CW04SFIS_28000U025 foundation shall be measured and paid
CW04SFIS_28025R050 according with the unit prices of the different
CW04SFIS_28050R100 components (excavation, filling, concrete,
CW04SFIS_30000U025 reinforcement, formwork, embedded
elements, etc.)
CW04SFIS_30025R050
Price content. The price includes material supply, work
CW04SFIS_30050R100
Included but not laying out and plotting, demolitions,
CW04SFIS_32000U025
limited to: excavations, fillings, loading and transporting
CW04SFIS_32025R050
of excess material to a dumping area,
CW04SFIS_32050R100 dumping fees, formwork, rebars, embedded
CW04SFIS_35000U025 elements, anchor bolts, concrete works,
CW04SFIS_35025R050 mortars, auxiliary means, tools, machinery
CW04SFIS_35050R100 and, in general, all required materials and
CW04SFIS_40000U025 labor for the correct completion of all work.
CW04SFIS_40025R050 Excluded: Foundations higher than 1 m3
CW04SFIS_40050R100 Measurement The unit shall be measured as stated on
CW04SFIS_50000U025 system: approved drawings. In cases where small
CW04SFIS_50025R050 footings/concrete support are embedded
CW04SFIS_50050R100 into pavement, its volume shall be
CW04SFIS_MC000U025 categorized as shown below for
CW04SFIS_MC025R050 measurement purposes.
CW04SFIS_MC050R100 Unit of measure: The unit of measurement is the element
executed (n)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.MO.._ER001000S Supply and application of epoxy resin for the union between
concretes of different ages.
Commodities included: Referred to: Application of epoxy treatment over an old
existing concrete prior to extend that
CW04MO_ER001000S concrete volume with a new element
attached.
Price content. The unit price includes supply, transportation,
Included but not intermediate storage, preservation, handling,
limited to: application, preparation, supports, pouring by
any means or machinery, formwork (except
for anchor pockets), and any other
requirement, regardless of nature, necessary
for the correct installation of the required unit
as per manufacturer’s instructions manual,
project drawings, specifications, standards
and approved ITPs.
Excluded: Application of epoxy between concretes due
to construction delays, execution mistakes,
defects or any other reason from
SUBCONTRACTOR responsibility
Measurement The unit shall be measured as stated on
system: approved drawings
Unit of measure: The unit of measure shall be the square meter
(m2)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Unit of measure:
The unit of measure shall be square meter
(m2) of formwork in contact with concrete,
measured on approved engineering drawings.
2.4.6.2 Commodity group CW04.FW.MS. Miscellaneous for Formworks.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
3m 3m
H.P.F.S. SLAB
3m
H.P.F.S.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
TYPE 2)
H/2
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
TYPE 1)b.
TYPE 2)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
TYPE 1)b.
Bending according to
standard drawings
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Standard bending.
Type 1)b.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Type 1)a.
Construction joint.
Type 1)d.
Standard bending.
Type 1)b.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Type 2)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
02070-FCK-CIV-DRW-230
Additional bar
Type 1)c.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
2.4.8.1 Commodity group CW04.EE.SP Steel plates and profiles and embedded
elements.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW04EEEP_PVSIM000160
CW04EEEP_PVSIM000180 Installation of fittings and valves shall also
CW04EEEP_PVSIM000200 be included in unit prices
CW04EEEP_PVSIM000250 Excluded: Earth works (excavation and backfillings)
CW04EEEP_PVSIM000300 Measurement The unit shall be measured to axes of the
CW04EEEP_PVSIM000350 system: pipeline of correctly installed piping, as
CW04EEEP_PVSIM000500 specified on approved drawings.
CW04EEEP_PVSUI000400 Unit of measure: The unit of measure shall be linear meter
CW04EEEP_PVINI000400 (lm).
CW04EEEP_PVSUI000600
CW04EEEP_PVINI000600
CW04EEEP_PVSUI000800
CW04EEEP_PVINI000800
CW04EEEP_CPSIM000038
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.AB.CH._x::x Supply and setting of Chemical anchor bolts HILTI type or similar.
Commodities included: Referred to: Anchor bolts Hilti model or similar
Price content. Unit price includes supply, layout works and
CW04ABCH_0000U12 Included but not plotting, surface cleaning, drilling, hole blow-
CW04ABCH_012R018 limited to: out and installation in hardened concrete as
CW04ABCH_018R030 per manufacturer’s instructions manual,
project specifications, standards and approved
ITP’s.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.ST.WP._WS000200S Supply and application of water stop swellable joint sealing with
SikaSwell system or similar, including all necessary auxiliary
materials for the correct application of the product as per
vendor requirements and recommendations.
Commodities included: Referred to:
Price content. The unit price includes layout works and
CW04STWP_WS000200S Included but not plotting, material supply, transportation,
limited to: intermediate storage and handling,
installation of material following
manufacturer recommendations,
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.ST.WP._WS000300S Supply and application of water stop joint sealant with a good
resistance to ACIDS, ALKALIS AND BACTERIOLOGICAL ATTACK
and excellent adherence to concrete, metals and other non-
porous materials, for joints up to 40 mm width and up to 20 mm
thick.
Commodities included: Referred to: Application of Sealant materials in pipe
penetrations and in general joints between
CW04STWP_WS000300S two types of materials or discontinuities on
elements.
Price content. The unit price includes layout works and
Included but not plotting, material supply, transportation,
limited to: intermediate storage and handling,
installation of material following
manufacturer recommendations,
manpower, surface preparation and
cleaning, tools, machinery, auxiliary means
and, in general, all required materials and
labor for the correct completion of all work
as per manufacturer’s instructions manual,
project specifications, standards and
approved ITP’s.
Excluded:
Measurement The unit shall be the length of the joint as
system: specified on approved drawings.
Unit of measure: The unit of measure is the lineal meter (lm)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Unit of measure:
The unit of measure is the square meter
(m2)
2.4.11 Commodity group CW04.MS. Miscellaneous for concrete.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.MS.._PD000100S Supply & installation of Teflon pad plate for sliding supports of
equipment according with project standards, specifications and
drawings.
Commodities included: Referred to:
Price content. The unit price includes material supply,
CW04MS_PD000100S Included but not transportation, intermediate storage and
limited to: handling, drilling holes for bolts surfaces
preparation installation, tools, machinery,
auxiliary means and, in general, all required
materials and labor for the correct completion
of all work as per project specifications,
standards and approved ITPs.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the square meter (m²)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.04.MS.._JO000510S
Supply and installation of TPER expansion joint system in concrete
slabs for future pouring of concrete in one side of joint. 20mm thick
plastic expansion board, waterstop TPER expansion board cap, dia
20x225-300 speed load transfer sleeve, staples joining cap to
expansion board @600 C/C and 3 layers of nonwoven geotextile. For
protection of the side of the joint to be future poured it is also
included sand backfill to prevent TPER cap damage and 50x250
treated wood plank beleved at 45º and another 50x100 plank glued
and nailed to the 50x250
.
Commodities included: Referred to: Joints between soil and paving slabs
Price content. The unit price includes any material supply
CW04MS_JO000510S Included but not manpower, and installation of: 20mm thick
limited to: plastic expansion board, waterstop TPER
expansion board cap, dia 20x225-300 speed
load transfer sleeve, staples joining cap to
expansion board @600 C/C and 3 layers of
nonwoven geotextile. For protection of the
side of the joint to be future poured it is also
included sand backfill to prevent TPER cap
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
2.5.1.1 Commodity group CW.05.MH.CO.IS. Concrete manholes and pits casted “in-
situ”
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Excluded:
Measurement The unit shall be measured calculating the
system: weight of concrete for each manhole. It
shall be applied 2.5 ton/m3 as average
unitary weight to the concrete volume (in
m3), calculated according Fig. 9.1. Each
manhole shall be classified into one of the
three commodities depending on its
weight.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
2.5.1.5 Commodity group CW.05.MH.PL. Plastic and cast-iron manholes and pits.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
2.5.1.7 Commodity group CW.05.MH.CO. Cover for catch basins, manholes, culverts,
trenches, pits, etc. with internal volume >12m³.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Excluded:
Measurement The unit shall be measured as surface of
system: covers as stated on approved drawings.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW05UGCO_SIM000900 Unit of measure: The unit of measure shall be the lineal meter
CW05UGCO_SIM001000 (lm )
CW05UGCO_SIM001100 Method of payment: Payment breakdown shall be as indicated
CW05UGCO_SIM001200 below:
CW05UGCO_SIM001300 Supply and installation
CW05UGCO_SIM001350 70%
CW05UGCO_SIM001400 Testing
CW05UGCO_SIM001500 30%
CW05UGCO_SIM001600
CW05UGCO_SIM001800
CW05UGCO_SIM002000
CW05UGCO_SIM002100
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Testing
30%
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW05UGFV_INF90000024
CW05UGFV_INF90000026
CW05UGFV_INF90000030
CW05UGFV_INF90000036
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
Excluded:
Measurement The filling volume shall be measured as
system: specified on approved drawings.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
2.6.3.2 Commodity group CW06.AP.BC. Asphalt paving and/or roads. Base Course.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.06.MS.._OT000100S Execution of asphalt paving repair all the layers, any type.
Commodities included: Referred to:
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.06.MS.._OT003100S Supply and installation of TPER expansion joint system in roads and
paving including 20mm thick plastic expansion board, waterstop
TPER expansion board cap, dia 20x225-300 speed load transfer
sleeve, staples joining cap to expansion board @600 C/C
Commodities included: Referred to: Joints between concrete paving and road
slabs.
CW06MS_OT003100S Price content. The unit price includes any material supply
Included but not manpower, and installation of 20mm thick
limited to: plastic expansion board cap waterstop TPER,
Dia. 20x225-300 speed load transfer sleeve,
staples joining cap to expansion board @600
C/C each side (for further reference see figure
6.12.1), equipment, auxiliary means, and in
general all required materials, labor and
equipment for the correct completion of the
work according to project standards,
specifications and drawings, following
manufacturer recommendations.
Excluded: Dowel ROD (Considered as embedded item)
Measurement The unit shall be measured as specified on
system: approved drawings. Cutting, cropping and
excess of material shall not be measured nor
paid
Unit of measure: The unit of measure is the lineal meter (lm)
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.06.MS.._OT003200S Supply and installation of TPER expansion joint system in roads and
paving for future pouring of concrete in one side of joint. 20mm
thick plastic expansion board, waterstop TPER expansion board
cap, dia. 20x225-300 speed load transfer sleeve, staples joining cap
to expansion board @600 C/C and 3 layers of nonwoven geotextile.
For protection of the side of the joint to be future poured it is also
included sand backfill to prevent TPER cap damage and 50x250
treated wood plank beveled at 45º and another 50x100 plank glued
and nailed to the 50x250.
Commodities included: Referred to: Joint preparation with one side finished and
future pouring of concrete in the other side of
CW06MS_OT003200S the joint.
Price content. The unit price includes any material supply
Included but not manpower, and installation of: 20mm thick
limited to: plastic expansion board, waterstop TPER
expansion board cap, dia. 20x225-300 speed
load transfer sleeve, staples joining cap to
expansion board @600 C/C and 3 layers of
nonwoven geotextile (for further reference
see figure 9.12.2). For protection of the side
of the joint to be future poured it is also
included sand backfill to prevent TPER cap
damage and 50x250 treated wood plank
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.07.WL.._x:x Supply and erection of split face concrete block masonry wall,
with cementious mortar in walls.
Commodities included: Referred to:
Price content. The unit price includes the layout works
CW07WL_CBWL40X20X20 Included but not and plotting, material supply, manpower,
CW07WL_SFEN40X20X20 limited to: formation and sealing of joints, joint
cleaning and, in general, all required
materials and labor for the correct
completion of all work.
Excluded: Reinforcing bars
Measurement The unit shall be measured as specified on
system: approved drawings. Holes greater than 1
m2 shall be discounted from
measurement.
Unit of measure: The unit of measure shall be the square
meter (m²).
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.09.FN.PF._FNx:x Permanent metallic wire mesh fence, set with clamps, with a
bayonet with three galvanized barbed wire lines.
Commodities included: Referred to:
Price content. The price includes material supply,
Included but not excavation, backfilling and filling, concrete
CW09FNPF_FN0100H200 limited to: pouring, clamps, accessories, earthing,
tools, auxiliary means, machinery and, in
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.09.ET.._000100S Supply and installation of warning tile any type and size in
underground systems.
Commodities Referred to:
included: Price content. The unit price includes the material supply,
Included but not installation, overlaps, tools, auxiliary means,
CW09ET_000100S limited to: and, in general, all required materials and labor
for the correct completion of all work.
Excluded:
Measurement The unit shall be measured as the width used for
system: trench excavation with the length indicated on
drawings measured along the trench axis.
Unit of measure: The unit of measure shall be the square meter
(m² )
Excluded:
Measurement The unit shall be measured with the trench
system: length indicated on drawings measured along
the trench axis.
Unit of measure: The unit of measure shall be the linear meter
(lm)
CW.09.MS.._010000S Supply, installation and removal of recovery sheet piling system with
plate thickness as per project standards, specifications or drawings.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.09.MS.._011000S Supply and installation of permanent or lost sheet piling system with
plate thickness as per project standards, specifications or approved
drawings.
Commodities Referred to:
included: Price content. The price includes material supply, layout works
Included but not and plotting, installation, tools, auxiliary means,
CW09MS_011000S limited to: specialized machinery and, in general all
required material and labor for the correct
completion of all work.
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings, taking into account that the
height shall be carried out from the theoretical
top of the steel sheet to the actual driven level
or IFC design level (whichever comes first). For
width measurement it shall be taken the
theoretical measurement between inner edges
of metal sheet wall (straight length) as per IFC
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
CW.09.MS.._020000S Design, supply and installation of dewatering system using well points
method or similar to dewater large open areas.
Commodities Referred to:
included: Price content. The price includes design of the system, supply
Included but not of materials and equipment required, complete
CW09MS_020000S limited to: execution and installation of the system and
removal.
This item covers massive dewatering in large
areas but does not cover the dewatering
included in excavation items.
Excluded:
Measurement The unit shall be measured as the horizontal
system: area to be dewatered as specified on approved
drawings and or CONTRACTOR instructions.
Unit of measure: The unit of measure is the square meter (m2)
Excluded:
Measurement The unit shall be measured as specified on
system: approved drawings and or CONTRACTOR
instructions. Uncompleted months shall be
measured and paid as the correspondent
fraction of the monthly rate
Unit of measure: The unit of measure is the square meter per
month (m2*month)
For any type of work not previously listed in this document, criteria of the Contractor’s Site
Manager shall apply.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
C. HOURLY RATES.
1. General
The Subcontractor shall not begin any work using Hourly Rates without prior written approval
by Contractor’s Site Manager. Any unauthorized or additional work performed without
written approval shall not be measured nor paid.
The Contractor’s Site Manager will expect on receiving a level of production officially
recognized in each aspect of labor and machinery operation.
Contractor will only accept for reviewing and signing, when applicable, those time sheets
which have been turned in up to 24 hours following the completion of the work to which
they apply.
All charges for Hourly Rates shall be paid using the same payment conditions as other work
units in the subcontract. Under no circumstances will special terms or conditions of payment
be accepted.
For the purpose of measurement and payment of Hourly Rates, the following conditions
apply to the different hourly classifications:
a. Normal Hours: Refers to the first ten (10) hours of each workday, from (and including)
Monday, through (and including) Saturday.
b. Overtime Hours: Refers to any additional hours completed during the above-
mentioned description.
c. Holiday Hours: Refers to the twenty-four (24) hour period of Sunday and official local
holidays celebrated in the province where the project shall be completed.
2. Labour.
These prices include all levels of supervision above the level of Foreman, tools, safety and
security items, transportation to/from and within work site, wear and tear of tools and
depreciation costs, standard consumables (welding materials, gases, etc.), travel, per-diem,
general costs, profit, insurance, salaries, bonuses, social securities, taxes, and any other type
of charge which can, for whatever reason, affect the cost of the item.
3. Machinery.
Prices refer only to production work hours. Any loss of time due to equipment breakdown,
transit time for transportation from point of origin to work site, transport back to point of
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
origin, or any other circumstances that may affect the work to be accomplished are not
chargeable and will not be paid.
Price includes: Transportation costs to/from and within work site, fuel, lubricants,
maintenance, repair, wear and tear of machinery and depreciation costs, taxes, general costs,
and the cost of any other equipment, tools or accessories which are not specified in the
Schedule of Rates but may be required for the completion of the work that has been
requested.
For mobile machinery and transportation vehicles, price includes driver, operator, as well as
auxiliary personnel required for its operation.
4. Material.
Prices are for material delivered to the job site in the place specified by Contractor’s Site
Manager, and include general costs, profit, insurance, bonuses, taxes, transportation to and
within work site, safety and security items, and any other type of charge which can, for
whatever reason, affect the cost of the item.
For any other type of material received that has not been covered herein and is intended for
use at the work site, payment will be as stipulated on the purchase invoice plus a 10% mark
up for handling costs and profit but must have been previously approved in writing by the
Contractor’s Site Manager.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden
TÉCNICAS REUNIDAS
The Subcontractor should complete, in its entirety, the following list of Unit Prices and Hourly
Rates. Consideration should be given to definitions listed in specifications and Technical
Requisitions, as well as the following:
1. UNIT PRICES.
Supply: Comprises all the costs associated with the supply and delivery of permanent
materials (by work unit) to the work site. This includes general costs and profit.
Erection: Comprises all costs of direct labor for a work unit. Includes unloading of
material, intermediate transportation within work site, consumable material, temporary
installations and facilities, all running costs, work costs, erection equipment costs (i.e.
scaffolding, cranes, machinery, tools, etc.), indirect personnel, general costs and profit.
2. HOURLY RATES.
Includes all costs applicable to each work unit, including indirect personnel, general
costs and profit.
The Subcontractor must complete the price list, including those items without quantities
shown, in the format provided and be aware that any bid which does not meet this prerequisite
will be rejected.
If the Subcontractor wishes to provide to any amplifying information to this price list it should be
submitted in a separate sheet attached to this document.
Prices will be entered using two position decimal points (hundredths) only. All other decimal
values will be rounded up to the nearest hundredth.
This document is property of Tecnicas Reunidas. Its reproduction without a written permission is strictly forbidden