Title Page 1 of 11 (Start here, fill in shutdown dates and team members)
Shutdown Audit 2 of 11
Backup Support: The following sections are used to support the "Required Documentation". Alternate formats are also acceptable.
Shutdown FMEA 4 of 11
Shutdown Checklist 8 of 11
Startup Checklist 10 of 11
Facility Checklist 11 of 11
Form #: 75132
Revision #:1
Table of Contents
SHUTDOWN PLAN / AUDIT FOR: Modatek Systems
Customers Shutdown Period Starts (Date Only) Company Address: 400 Chisholm Drive
Customers Shutdown Period Ends (Date Only) Milton, ON, L9T-5V6
mm/dd/yy
DUNS Code or
Issue Date: customer code
Last Updated: (name) (telephone)
Plant Manager
Created By: Quality Manager
(Team Names) Production Manager
Production Manager
Production Manager
Shipping Manager
Purchasing Manager
DISTRIBUTION :
Customer:
Form #: 75132
Revision #: 1
Page 1 of 11
SHUTDOWN PLAN / AUDIT FOR: Modatek Systems
DISTRIBUTION :
Customer:
Form #: 75132
Revision #: 1
Page 1 of 11
SUPPLIER EXTENDED SHUTDOWN AUDIT
Section Name:
DATE
Line / Location:
Yes No N/A Score Status Audit Completed by (Name):
Does Management have a documented Shutdown/Startup Plan with timing for each
1
major department/area that will protect the customer, tooling, machinery, and facilities? x
Has Management reviewed all Customers Bulletins on their website and incorporated
2
them into the Shutdown/Startup Plan.
x
3 Has a high risk list been generated by management identifying areas of major concern? x
Does the Management Team formally review the status of these plans at timely intervals
4
before the shutdown?
x
Has Management taken the initiative to restrict personnel moves the week prior to and
9
after the startup?
x
If personnel moves can't be restricted, has a training plan been incorporated for initial
10
startup, including reduced production rates, until quality and proficiency are validated?
x
If there are significant changes to tools, machinery, processes, or new additions for
11
startup, is there a documented approval plan?
x
QUALITY
Item # YES NO N/A COMMENTS
Are plans in place for increased in-process quality checks the week that shutdown
1
occurs and during the week of startup? x
Is enhanced inspection planned during the week of startup for any new parts, parts with
2 changes, parts that have had customer issues, or major disruptions in the past 12 x
months?
If any significant tooling, machinery, or process changes are to be made, is there a plan
4
for PPAP approval and part try outs? x
Has the Quality Department championed a recent cross functional PFMEA review of the
5
shutdown/startup process on product quality? x
Score 5 0 0
Materials
Item # YES NO N/A COMMENTS
1 Are raw materials and purchased parts at the required inventory levels? x
2 If not, what is the a plan to get up to schedule? x
Are raw material and purchased parts stored to prevent damage/deterioration during the
3
shutdown?
x
Is in-process material stored to protect it from the environment and stacking distortion
4
during the shutdown?
x
Are process materials and wet chemicals stored to protect them during the shutdown
5
and is shelf life checked?
x
Are raw materials, process materials, in-process stock, and partial packs of finished
6
goods checked at shutdown for identification of each container?
x
Machinery/Tooling
Item # YES NO N/A COMMENTS
Is there additional validation required on startup of the above that has been
3
communicated to the quality department and manufacturing personnel?
x
Is there a published list of do's and don'ts for protection of tools and equipment during
5
the down period, such as lubrication or preservatives?
x
If the environment will change during the shutdown (heat/cold), is there a plan to
6
normalize the tooling/equipment prior to startup? x
Do you have a written plan to recalibrate and verify proper operation of all automated
7
checks? (ie - Electrical verification station, part presence probes)
x
Torque Specific - Do you have a written plan to recalibrate all torque monitoring systems
8
after extended shutdown period?
x
Welding Specific - Do you have a written plan to verify weld integrity after extended
9
shutdown period?
x
Score 9 0 0
Facilities
Item # YES NO N/A COMMENTS
Have significant facility/layout changes been reviewed with all departments to prevent
1
disruption at startup? x
Have guidelines been established for safe shutdown and startup of of heating, cooling,
2
and/or water flow for all the facility, with a list of do's and don'ts? x
3 Is there a champion identified to check the facility daily during the shutdown? x
Major Changes
Item # YES NO N/A COMMENTS
If you plan any tooling and/or equipment rebuilds, replacements, relocations, or new
startups for this period, proceed with this section.
x
Has this information been shared with GM purchasing, Supplier Quality, and the affected
1
assembly plants?
x
Have sufficient banks been built with appropriate safety stock and appropriate level of
2
audit depending on the risk? x
Have bank quantities been reviewed with GM Purchasing, Supplier Quality, and the
3
affected assembly plants? x
Is there a contingency plan developed in event of a failure of the plan, with appropriate
5
levels of immediate communication to the customer?
x
Has the supplier contacted The Engineer at the assembly plant to determine if try out
8
parts are required?
x
Is an extended enhanced inspection plan communicated, understood, and organized for
9
flawless execution?
x
Is feedback from the enhanced inspection planned to be driven upstream for immediate
10
countermeasures?
x
Have alarms been established at the enhanced inspection to trigger an additional level
11
of containment for customer protection?
x
Tier 2/3 Impact - Are there any plans related to tool moves or supplier changes at the
12
tier 2/3 supplier level?
x
Have plans for PPAP and part try outs been developed and communicated to the
14
appropriate customer personnel?
x
Score 12 2 0
Does Management have a documented Shutdown/Startup Plan with timing for each
1
major department/area that will protect the customer, tooling, machinery, and facilities? x
Plan and timing in place
Has Management reviewed all Customers Bulletins on their website and incorporated
2
them into the Shutdown/Startup Plan.
x
Bulletins reviwed on daily basis
3 Has a high risk list been generated by management identifying areas of major concern? x
Does the Management Team formally review the status of these plans at timely intervals
4
before the shutdown?
x
Has Management taken the initiative to restrict personnel moves the week prior to and
9
after the startup?
x
If personnel moves can't be restricted, has a training plan been incorporated for initial
10
startup, including reduced production rates, until quality and proficiency are validated?
x
Team Members are trained prior to new work assignments
If there are significant changes to tools, machinery, processes, or new additions for
11
startup, is there a documented approval plan?
x
Done according to the GM requirements (PPAP)
Is there a documented communication distribution of significant product and process
12
changes to all departments?
x
Is there a published and distributed contact list in case of emergency during the
13
shutdown period?
x
Contact list available in the office area
QUALITY
Item # YES NO N/A COMMENTS
Are plans in place for increased in-process quality checks the week that shutdown
1
occurs and during the week of startup? x
Is enhanced inspection planned during the week of startup for any new parts, parts with
2 changes, parts that have had customer issues, or major disruptions in the past 12 x
months?
If any significant tooling, machinery, or process changes are to be made, is there a plan
4
for PPAP approval and part try outs? x
Crossmember engineering change
Has the Quality Department championed a recent cross functional PFMEA review of the
5
shutdown/startup process on product quality? x
Score 5 0 0
Materials
Item # YES NO N/A COMMENTS
1 Are raw materials and purchased parts at the required inventory levels? x
2 If not, what is the a plan to get up to schedule? x
Are raw material and purchased parts stored to prevent damage/deterioration during the
3
shutdown?
x
Is in-process material stored to protect it from the environment and stacking distortion
4
during the shutdown?
x
Are process materials and wet chemicals stored to protect them during the shutdown
5
and is shelf life checked?
x
Are raw materials, process materials, in-process stock, and partial packs of finished
6
goods checked at shutdown for identification of each container?
x
Machinery/Tooling
Item # YES NO N/A COMMENTS
Is there additional validation required on startup of the above that has been
3
communicated to the quality department and manufacturing personnel?
x
Is there a published list of do's and don'ts for protection of tools and equipment during
5
the down period, such as lubrication or preservatives?
x
If the environment will change during the shutdown (heat/cold), is there a plan to
6
normalize the tooling/equipment prior to startup? x
Do you have a written plan to recalibrate and verify proper operation of all automated
7
checks? (ie - Electrical verification station, part presence probes)
x
Poke Yoke samples are in place
Torque Specific - Do you have a written plan to recalibrate all torque monitoring systems
8
after extended shutdown period?
x Torque verification is in place as part of our current manufactturing
process.
Welding Specific - Do you have a written plan to verify weld integrity after extended
9
shutdown period?
x
Weld destruct is done according to the existing validation process
Score 7 1 1
Facilities
Item # YES NO N/A COMMENTS
Have significant facility/layout changes been reviewed with all departments to prevent
1
disruption at startup? x
No facility changes planned during shutdown
Have guidelines been established for safe shutdown and startup of of heating, cooling,
2
and/or water flow for all the facility, with a list of do's and don'ts? x
3 Is there a champion identified to check the facility daily during the shutdown? x Various Team Members will be on the premises;facility will not be
completely shut down
Major Changes
Item # YES NO N/A COMMENTS
If you plan any tooling and/or equipment rebuilds, replacements, relocations, or new
startups for this period, proceed with this section.
x
Has this information been shared with GM purchasing, Supplier Quality, and the affected
1
assembly plants?
x
Have sufficient banks been built with appropriate safety stock and appropriate level of
2
audit depending on the risk? x
Have bank quantities been reviewed with GM Purchasing, Supplier Quality, and the
3
affected assembly plants? x
Is there a contingency plan developed in event of a failure of the plan, with appropriate
5
levels of immediate communication to the customer?
x
Has the supplier contacted The Engineer at the assembly plant to determine if try out
8
parts are required?
x
Is an extended enhanced inspection plan communicated, understood, and organized for
9
flawless execution?
x
Is feedback from the enhanced inspection planned to be driven upstream for immediate
10
countermeasures?
x
Have alarms been established at the enhanced inspection to trigger an additional level
11
of containment for customer protection?
x
Tier 2/3 Impact - Are there any plans related to tool moves or supplier changes at the
12
tier 2/3 supplier level?
x
Have plans for PPAP and part try outs been developed and communicated to the
14
appropriate customer personnel?
x
Score 0 0 14
Instructions: Enter the Name and Contact Telephone Number for the assigned department manager for each day of shutdown
Date
Senior Management
Quality
Production
Shipping
Scheduling
Purchasing
Engineering
Maintenance
Tooling
Finance
Human Resources
Customer Service
Other (Specify)
Other (Specify)
Date
Senior Management
Form #: 75132
Revision #: 1
Page 3 of 11
Quality
Production
Shipping
Scheduling
Purchasing
Engineering
Maintenance
Tooling
Finance
Human Resources
Customer Service
Other (Specify)
Other (Specify)
Form #: 75132
Revision #: 1
Page 3 of 11
Shutdown Contacts and Support Plan
Instructions: Enter the Name and Contact Telephone Number for the assigned department manager for each day of shutdown
Senior Management
Quality
Production
Shipping
Scheduling
Purchasing
Engineering
Maintenance
Tooling
Form #: 75132
Revision #: 1
Page 3 of 11
Finance
Human Resources
Customer Service
Other (Specify)
Other (Specify)
Date
Senior Management
Quality
Production
Shipping
Scheduling
Purchasing
Engineering
Maintenance
Tooling
Finance
Human Resources
Customer Service
Other (Specify)
Other (Specify)
Form #: 75132
Revision #: 1
Page 3 of 11
Shutdown FMEA
Instructions: Insert your Shutdown FMEA on this page. It should be formatted to AIAG standards with RPN's assigned compliant with Rev 3 requirements. Note: this is an EVENT FMEA, specific to the activities and risks
associated with shutting down and starting up equipment, not a part FMEA. Your "backup", "recovery" or "prevention" plan should be described for each risk element in the "Actions Taken" section of the FMEA. Use the
information included in the other pages of this workbook, especially the maintenance items, to determine your risk elements.
POTENTIAL
FAILURE MODE AND EFFECTS ANALYSIS
Print # NA Rev. NA (PROCESS FMEA) FMEA Number:
Item: NA Process Responsibility: Prepared by:
Model Year(s)/Vehicle(s) Key Date N/A Date (Orig.) 20-Oct-22
Team: Date (Rev.)
C Potential O D
Process Potential Potential S l Cause(s)/ c Current e R. Recommended Responsibility Action Results
Function/ Failure Effect(s) of e a Mechanism(s) c Process t P. Actions & Target Actions S O D R.
Require- Mode Failure v s of Failure u Controls e N. Date Taken e c e P.
ments s r Prevention Detection c v c t N.
Excessive inventory of components Develop rust Poor E-Coating 6 Poor Scheduling 1 Releases done according to the Min/Max and Physical Inventory done on regular 5 30
customer requirements basis; bar code scanning ensures
automatic inventory update
Expired Shelf life (lube) Sticky lube Difficulty in assembly 2 Poor stock rotation 1 FI/FO 7 14
Equipment malfunctioning Line down Customer downtime 9 Poor maintenance 1 Preventative maintenance 4 36
Power failure PM Action Plan Support personnel on the
premises during the summer
shutdown; warm up line prior to
going back to regular production
Manpower Insufficient Manpower to address production Manufacturing difficulties/Quality Poor planning Review vacation plan with all departments to Daily monitoring
needs over shutdown Issues ensure enough personnel is available to
7 1 support required activities. 3 21
Un-trained Manpower running equipment Manufacturing difficulties/Quality Poor Planning Training plan in place; training matrix captures Layered audits;
over shutdown Issues status of training by station. Work is assigned
7 1 based on Skill and Ability 4 28
Conveyor Change Cannot Transfer Parts Manufacturing difficulties/ Quality Poor Planning Review plans, timeline for implementation of First run of new conveyor
Issues 7 1 conveyor to ensure that it is working properly verification. Team buyoff at 4 28
integrators.
Difficulty In Welding Manufacturing difficulties/ Quality Loose Cables Verification of welds by weld technician after Visual/cut and etch analysis.
Issues 7 1 change of cables. First/Last Off 4
Ground Cable Changes (Welding System) 28
Wrong Cables Verification of cables with OEM blue prints to Visual/cut and etch analysis.
7 1 ensure conformity. First/Last Off 4
28
Robot Program Lost Manufacturing difficulties/ Quality Connectivity Issue After PM complete, robot is verified for correct Visual
Issues 7 1 program, TCP, and weld path. 7
Robot Preventative Maintenance 49
Form #: 75132
Revision #:1
Page 4 of 11
POTENTIAL
FAILURE MODE AND EFFECTS ANALYSIS
Print # NA Rev. NA (PROCESS FMEA) FMEA Number:
Item: NA Process Responsibility: Prepared by:
Model Year(s)/Vehicle(s) Key Date N/A Date (Orig.) 20-Oct-22
Team: Date (Rev.)
C Potential O D
Process Potential Potential S l Cause(s)/ c Current e R. Recommended Responsibility Action Results
Function/ Failure Effect(s) of e a Mechanism(s) c Process t P. Actions & Target Actions S O D R.
Require- Mode Failure v s of Failure u Controls e N. Date Taken e c e P.
ments s r Prevention Detection c v c t N.
Logic Issues Manufacturing difficulties/ Quality Poor Planning Verification of electrical system through Verification to schematic drawings.
Issues 7 1 panels. Logic verification. 4 28
Electrical PM
Form #: 75132
Revision #:1
Page 4 of 11
POTENTIAL
FAILURE MODE AND EFFECTS ANALYSIS
Print # NA Rev. NA (PROCESS FMEA) FMEA Number:
Item: NA Process Responsibility: Prepared by:
Model Year(s)/Vehicle(s) Key Date N/A Date (Orig.) 20-Oct-22
Team: Date (Rev.)
C Potential O D
Process Potential Potential S l Cause(s)/ c Current e R. Recommended Responsibility Action Results
Function/ Failure Effect(s) of e a Mechanism(s) c Process t P. Actions & Target Actions S O D R.
Require- Mode Failure v s of Failure u Controls e N. Date Taken e c e P.
ments s r Prevention Detection c v c t N.
Form #: 75132
Revision #:1
Page 4 of 11
Shutdown Team Planning Meetings
Meeting 1- Kick Off: 6 to 8 weeks prior to scheduled shutdown.
Meeting 2- Updates- Scheduled as required
(if necessary)
Finalization Meeting: 2 weeks prior to shutdown.
Agenda
- review maintenace projects, timeline, contractors, skilled trade manning, service shutdowns
- review engineering projects, timelines, contractors, skilled trade manning, service shutdowns
Form #: 75132
Revision #:
Page 5 of 11
Shutdown Production Plan As of (Date):
mm/dd/yy
Enter all of your customers part numbers, names and destination locations in Column B in the appropriate section. Enter a new line for each of multiple destinations. These will be copied to the enhanced ispection matrix sheet found in this workbook. Insert rows as needed
to include all of your customers parts. Include Tier 2 parts
Instructions Based on current releases and plant memos, fill in the requirements and past due information as of the date shown above. Update this information weekly or as required by your customer contact.
Fill in whether your current production schedule reflects extra production for any parts for which you do not have a bank meeting the shutdown requirements; add details (ie extra shift scheduled, added daily production) of how you will meet the delivery requirements
Complete the column Yes or No for whether you intend at this time to run production for these parts during the customers shutdown period.
Bank build
Requirements Past due Running during
Inventory on plan on
Part Number Part Description Destination Plant during Shutdown today Shutdown? (Yes Comments
hand (Today) Schedule?
(pieces) (pieces) / No)
(Yes / No)
New Parts
Form #: 75132
Revision #: 1
Page 6 of 11
Form #: 75132
Revision #: 1
Page 6 of 11
Shutdown Production Plan As of (Date):
mm/dd/yy
Enter all of your customers part numbers, names and destination locations in Column B in the appropriate section. Enter a new line for each of multiple destinations. These will be copied to the enhanced ispection matrix sheet found in this workbook. Include Tier 2 parts.
Instructions Based on current releases and plant memos, fill in the requirements and past due information as of the date shown above. Update this information weekly or as required by your customer contact.
Fill in whether your current production schedule reflects extra production for any parts for which you do not have a bank meeting the shutdown requirements; add details (ie extra shift scheduled, added daily production) of how you will meet the delivery requirements.
Complete the column Yes or No for whether you intend at this time to run production for these parts during the customers shutdown period.
Bank build
Requirements Past due Running during
Inventory on plan on
Part Number Part Description Destination Plant during Shutdown today Shutdown? (Yes Comments
hand (Today) Schedule?
(pieces) (pieces) / No)
(Yes / No)
New Parts
25776302 GMX001 RR FE1 NON ABS Rear Twist Axle GM Lordstown 0 0 1 Day Inventory No No
25776301 GMX001 RR FE1 ABS Rear Twist Axle GM Lordstown 0 0 1 Day Inventory No No
25776300 GMX001 RR FE1-5 LUG Rear Twist Axle GM Lordstown 0 0 1 Day Inventory No No
25776303 GMX001 RR FE3 Rear Twist Axle GM Lordstown 0 0 1 Day Inventory No No
25793738 GMX001 RR SS ABS Rear Twist Axle GM Lordstown 0 0 1 Day Inventory No No
15918778 GMX001 FRT FE1 Front Engine Cradle GM Lordstown 0 0 1 Day Inventory No No
15918779 GMX001 FRT FE3 Front Engine Cradle GM Lordstown 0 0 1 Day Inventory No No
25796153 GMX001 FRT SS Front Engine Cradle GM Lordstown 0 0 1 Day Inventory No No
15917891 GMT001 FRT WLD Front Engine Cradle GM Ramos 0 0 1 Day Inventory No No
All Other customer 25861148 GMT966/967/968 Base Level Frame Asm- Drivetrain & Frt Susp GM Lansing Delta Township 0 0 1 Day Inventory No No
parts including 25861149 GMT966/967/968 Up Level Frame Asm- Drivetrain & Frt Susp GM Lansing Delta Township 0 0 1 Day Inventory No No
Service orders 25876169 GMT966/967/968 Steering Gear Package (non-variable effort) GM Lansing Delta Township 0 0 1 Day Inventory No No
25876166 GMT966/967/968 Gear Asm - Strg (variable effort) GM Lansing Delta Township 0 0 1 Day Inventory No No
25876168 GMT966/967/968 Steering Gear Package (variable effort) GM Lansing Delta Township 0 0 1 Day Inventory No No
25876167 GMT966/967/968 Gear Asm - Strg (non variable ratio) GM Lansing Delta Township 0 0 1 Day Inventory No No
25857752 GMT966/967/968 PWR Train MNT Package- Switchable GM Lansing Delta Township 0 0 1 Day Inventory No No
25857745 GMT966/967/968 PWR Train MNT Package GM Lansing Delta Township 0 0 1 Day Inventory No No
Form #: 75132
Revision #: 1
Page 6 of 11
Form #: 75132
Revision #: 1
Page 6 of 11
SHUTDOWN CHECK LIST
Instructions: Identify all Shutdown Activities and
detail them on this sheet
Form #: 75132
Revision #: 1
Page 8 of 11
Note: Bold items must be executed
Form #: 75132
Revision #: 1
Page 8 of 11
Production Champion Timing Initial Comments
Form #: 75132
Revision #: 1
Page 8 of 11
SHUTDOWN CHECK LIST
Instructions: Identify all Shutdown Activities and
detail them on this sheet
Form #: 75132
Revision #:1
Page 8 of 11
Production Champion Timing Initial Comments
Empty twist bolt on production line of all
product.Each station will be stocked with current
level parts ready for next production run as per
schedule
Empty 001 bolt on production line of all
product.Each station will be stocked with current
level parts ready for next production run as per
schedule
Empty sub cell 310 of all finished product.All
stations will be emptied.
Empty sub cell 320 of all finished product.All
stations will be emptied.
Form #: 75132
Revision #:1
Page 8 of 11
Maintenance Shutdown Plan
Form #: 75132
Revision #: 1
Page 9 of 11
Maintenance Shutdown Plan
Form #: 75132
Revision #: 1
Page 9 of 11
Maintenance Shutdown Plan
Form #: 75132
Revision #: 1
Page 9 of 11
Maintenance Shutdown Plan
Form #: 75132
Revision #: 1
Page 9 of 11
Maintenance Shutdown Plan
Front Weld Line Lambda Tooling PM's 22-Dec 30-Dec N/A N/A
Rear Weld Line Lambda Tooling PM's 22-Dec 30-Dec N/A N/A
door is in
Rear Weld Line Lambda Install roll-up door at stn 80 22-Dec 28-Dec N/A N/A
house
batteries are in
All robots Lambda / JS replace all backup batteries 22-Dec 28-Dec N/A N/A
house
Form #: 75132
Revision #: 1
Page 9 of 11
START- UP CHECK LIST
Instructions: Identify all pre-start up activities
and detail them on this sheet
Form #: 75132
Revision #: 1
Note: Bold items must be executed
Form #: 75132
Revision #: 1
START- UP CHECK LIST
Instructions: Identify all pre-start up activities
and detail them on this sheet
Form #: 75132
Revision #: 1
Note: Bold items must be executed
Twist bolt on production line will run a All quality and productivity checks
minimium of one hour approx 80 axles to will be supported by QA and
Craig Ferrans 2-Jan CF
make sure line has no quality or productivity maintainance and once verified
issues normal production to follow
001 bolt on production line will run a All quality and productivity checks
minimium of one hour approx 60 cradles to will be supported by QA and
Craig Ferrans 2-Jan CF
make sure line has no quality or productivity maintainance and once verified
issues normal production to follow
Fill Lambda Rear Line with product. Each All quality and productivity checks
station will be stocked with current level parts Rick Coulombe 30-Dec RC will be supported by QA and
ready for next production run as per schedule. maintainance and materials
Fill Lambda Bolt on line with product. Each All quality and productivity checks
station will be stocked with current level parts Rick Coulombe 30-Dec RC will be supported by QA and
ready for nect production run as per schedule. maintainance and materials
Form #: 75132
Revision #: 1
Note: Bold items must be executed
Form #: 75132
Revision #: 1
Facility Check During Shutdown
Instructions: Identify all areas to be checked and list in Column A (Examples are given).
Identify person(s) responsible for checking these areas; they are to initial this sheet daily to verify that they have checked and all is OK.
Form #: 75132
Revision #: 1
Page 11 of 11
Facility Check During Shutdown
Instructions: Identify all areas to be checked and list in Column A (Examples are given).
Identify person(s) responsible for checking these areas; they are to initial this sheet daily to verify that they have checked and all is OK.
Facilities
Oil Storage Area A/L, T/L
Materials
Shipping - North A/L, T/L
Facilities
Waste Treatment A/L, T/L
E-Coat A/L,
E-coat Filter Pump T/L
E-Coat A/L,
E-coat Circulating Pump T/L
Materials
Shipping - South A/L, T/L
Facilities
Compressor Room - South A/L, T/L
Facilities
A/L, T/L
Lighting retrofit
Facilities
Repair grouting in office floor A/L, T/L
tiles
Snake out urinals in men's Facilities
washrooms A/L, T/L
Facilities
A/L, T/L
P M's
Form #: 75132
Revision #:1
Page 11 of 11