UPPERHILL; NAIROBI
EIGHTH FLOOR
A Strip off all the floor pvc floor tiles and cart away. 380 SM
Hack and remove all floor screed under pvc floor finish and skirting
B 380 SM
and cart away arisings from site. Level surfaces for new works.
NEW WORKS
TILING WORKS
Supply and lay 22mm thick cement:sand (mix 1:3) screed, wood
C 380 SM
trowelled level ready to receive floor tiles (m.s)
Supply and fix 600x300mm x 8mm thick imported matt granitto floor
D tiles on screed to regular pattern edding and jointing in cement slurry 380 SM
and pointed in matching clour cement grout to approved samples.
Hack surfaces of wall average 10mm and cart away arisings, supply
E and fix 10mm x 100mm high porcelain tile skirting on block walls , on 81 LM
cement slurry, pointed in matching colour cement grout.
PARTITIONING, RENOVATION
8TH FLOOR BGT/PR.8/1 (C) QS
PROPOSED OFFICE PARTITIONING AND RENOVATION WORKS FOR KIPPRA ON FIFTH AND EIGHTH FLOORS AT BISHOPS GARDEN TOWERS, UPPERHILL; NAIROBI
DRY PARTITIONS
Ditto but 2100mm high overall; 1200mm glazed panel above MDF
B 194 SM
panel; ditto.
Supply and fix 50mm thick x 900x2100mm high solid core flush door,
D 15mm thick hardwood lipping all round and veneered to both sides 17 NO
in 3mm thick hardwood veneer to details.
Supply and fix aluminium cylinder lock, double action complete with
J 17 NO
lever handles with latch including a pair of escutchion
K Supply and fix aluminium door hinges, 100mm long… 33.5 PRS
Supply and fix overhead door closer as "BRITON" with cover REF N
L 19 NO
8834SR or other and approved fixed to timber doors to approval.
Supply and fix oval 50mm thick rubber door stoppers fixed of floor
M 21 NO
or wall.
CEILING
PARTITIONING, RENOVATION
8TH FLOOR BGT/PR.8/3 (C) QS