The learner independently installs formwork components based on
construction standards.
LEARNING RESOURCES
https://theconstructor.org/building/formwork-oil-types-uses/32505/
https://theconstructor.org/building/formwork-shuttering/types-formwork-
shuttering/3767/
This study source was downloaded by 100000797165521 from CourseHero.com on 11-14-2022 00:29:45 GMT -06:00
https://www.coursehero.com/file/120497224/TLE10Q4W4docx/
III. PROCEDURE
Question: In your
own opinion what will
happen if you create
formworks without
using oil.
C. Presenting
examples/instances
of the lesson
This study source was downloaded by 100000797165521 from CourseHero.com on 11-14-2022 00:29:45 GMT -06:00
https://www.coursehero.com/file/120497224/TLE10Q4W4docx/
True or False
2. Shuttering oil protects the formwork and hence the formwork can be
reused several times.
3. Shuttering oil helps provide good finishing surface of the concrete with
minimum defects.
CARPENTRY 10
This study source was downloaded by 100000797165521 from CourseHero.com on 11-14-2022 00:29:45 GMT -06:00 Page | 3
https://www.coursehero.com/file/120497224/TLE10Q4W4docx/
a direct application on required places. It should be applied in light film either
by brush or mould oil sprayer. If it is over applied, excess oil should be
drained before it dries. Pools of DSO cannot be allowed to dry as it causes
surface retardation of concrete.
The use of barrier paints extends the life of the formwork by producing a
hard-wearing surface on the formwork. If barrier paints are not used, it is
advised to use three coats of shuttering oil before the shuttering is used for
the first time.
This study source was downloaded by 100000797165521 from CourseHero.com on 11-14-2022 00:29:45 GMT -06:00
https://www.coursehero.com/file/120497224/TLE10Q4W4docx/
3. The joints in the formwork should be tight against leakage of cement
grout.
4. Construction of formwork should permit removal of various parts in
desired sequences without damage to the concrete.
5. The material of the formwork should be cheap, readily available, and
should be suitable for reuse.
F. Developing mastery
Fill in the blanks. Choose the best answer from the choices above
Shuttering oil protects the formwork and hence the formwork can be reused
several times. Shuttering oil helps provide good finishing surface of the concrete
CARPENTRY 10
This study source was downloaded by 100000797165521 from CourseHero.com on 11-14-2022 00:29:45 GMT -06:00 Page | 5
https://www.coursehero.com/file/120497224/TLE10Q4W4docx/
with minimum defects. In the case of wooden formwork, shuttering oil prevents
water absorption from concrete by the wooden formwork.