A. LABOR
TOTAL A 1,097.53
B. EQUIPMENT
TOTAL B 3,351.16
C. TOTAL (A + B) 4,448.69
D. OUTPUT (Sq.m./Hr.) 120.00
E. UNIT COST ( C ÷ D ) 37.08
F. MATERIALS
TOTAL F 822.06
A. LABOR
TOTAL A 1,177.98
B. EQUIPMENT
E07.1.004 Concrete Paver Rex Concrete Finisher , 120 Hp 1 unit 1.00 1,483.00 1,483.00
Concrete Saw, 6-3/4" Cutting Depth , 13 , Hp
E14.5.006 1 unit 1.00 206.64 206.64
16-18" Self Propelled blade diameter
Concrete Vibrator - Motor-in-head Type, 4-6
E14.3.015 1 unit 1.00 239.94 239.94
m Shaft 60mm
E08.5.005 Water Truck, All Makes , 360 Hp , 16000 lit. 1 unit 0.50 2,524.00 1,262.00
Minor Tools (5% of the above) 159.58
TOTAL B 3,351.16
C. TOTAL (A + B) 4,529.14
D. OUTPUT (Sq.m./Hr.) 80.00
E. UNIT COST ( C ÷ D ) 56.62
F. MATERIALS
TOTAL F 1,504.38