Professional Documents
Culture Documents
Method Statement (Fire Protection Work)
Method Statement (Fire Protection Work)
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
REVISION HISTORY
Rev. Revision Information Author Date
This document is the property of ACDC, the information hereon may not be used in any manner without the written permission of
ACDC.
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
Table of Contents
1. OBJECTIVE ……………………………………………………………………………....03
2. SCOPE OF WORK ……………………………………………………………………. ...03
3. REFERENCES ………………………………………………………………………. …..0
3
4. ORGANIZATION, RESPONSIBILITIES, WORK FORCE...........................................04
4.1 ORGANIZATION…………………………………………………………………...04
4.2 RESPONSIBILITIES……….…………….……………………………………….... 04
4.3. Organizational Chart………………………………………………………………...08
4.3 WORK FORCE…………………………………………………………………….. 09
5. METHODOLOGY ………………………………………………………………………. 07
5.1 Methodology for Installation of Crossmain and Branchline………………………..09
5.2 Methodology for Installation of Hanger, Support, Anchors, and Guides………….. 13
5.3 Methodology for Sprinkler heads Installation……………………………………... 15
5.4 Methodology for Hydro Test (Initial Testing)………………………………………16
5.5 Methodology for Riser & Wet Stand Pipe Installation……………………………...17
5.6 Methodology for Fire Hose Cabinet Installation…………………………………... 18
5.7 Methodology for Valves and Equipment Tagging………………………………… 20
5.8 Methodology for Fire Stopping Sealant Application……………………………… 20
5.9 Methodology for Valves Installation………………………………………………. 22
5.10 Methodology for Bursting Sprinkler Heads……………………………………… 23
5.11 Methodology for Pipe Sleeve Installation………………………………………... 24
5.12 Hydrostatic Test Pressure………………………………………………………… 24
5.13 Painting Procedure…………………………………………………………………26
5.14 Testing and Commissioning (Fire Pump & Jockey Pump)……………………….. 27
5.15 Flushing Methodology……………………………………………………………. 28
6. QUALITY CONTROL…………………………………………………………………. 29
7. Working at heights - Operation Guidelines for Manlifts………………………………….29
8. Handover Procedure…………………………………………………………………... 30
9. MATERIALS, MACHINERIES AND TOOLS…………………………………………..30
9.1 Materials………………………………………………………..……………………30
9.2 Machinery and Tools………………………………………………………………...31
10. SAFETY MEASUREMENTS…………………………………………………………...31
10.1 General……………………………………………………………………………...31
10.2 Safety Gears and Equipment………………………………………………………..32
ACDC-MS-QAQC-001 Page 1 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
14. CHECKLIST…………………………………………………………………………….40
ACDC-MS-QAQC-001 Page 2 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
1. Objective
The objective of this statement is to establish the necessary guidelines for the
installation requirement of fire protection system in accordance with the project
scope of work, technical specifications and in conformity with approved drawings
and applicable standards.
2. Scope of work
General Fire Protection Works, Including supply and installation of pipes,
fittings, valves & accessories.
AGCHEM intend to carry out the documentation of installation, testing and
commissioning within the scope of the project. According to the specifications and
construction process, quality, and safety measures.
The main task of this method statement is to demonstrate the procedure for
equipment and the system testing to provide sufficient information on the minimum
requirements of acceptance and eventually turnover of fire protection system to the
client.
3. References
All work process which should be referred to Fire Code of the Philippines,
which is a regulation made under Fire Protection and Prevention Act of 1997
consisting of set of minimum requirements respecting Fire safety within and around
existing buildings and facilities.
ACDC-MS-QAQC-001 Page 3 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
4.2 Responsibilities
ACDC-MS-QAQC-001 Page 4 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 5 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 6 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
Conducts daily tool box meeting with the group before the works
starts. Prepares pre-task planning and job Hazard analysis. Implements
and monitors all safety precautions at all working areas, especially in
high areas, leading edges, execution works and confined spaces. Submits
weekly Safety Accomplishments Report. Prepare incident, accident and
investigation report. Conducts monthly tools and safety equipment’s
inspection. Conducts safety orientation for newly hired workers prior to
start of work at the job site. Conducts safety inspection at the workplace
and identifies and possible work hazard, and recommends control
measures to avoid accidents. Issues notices of violation to project
employees for violation of company safety rules and regulations and
attends weekly safety coordination meeting.
4.2.9 WAREHOUSEMAN
Confer with the PIC and other site staff under each area of
responsibility regarding the plan of action, available work areas,
ACDC-MS-QAQC-001 Page 7 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 8 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 9 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
Note:
a. Allotment of workforce shall be determined upon issuance of schedule of
work.
b. The actual and number of persons may vary and shall be selected in
accordance with actual site conditions and site requirements.
5. WORK PROCEDURE/METHODOLOGY
ACDC-MS-QAQC-001 Page 10 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
pulleys rope at the both ends of the pipe, this is for additional
support and preventive measure. Operate the scissor lift and
elevate the pipe up to the required elevation. See to it that the
pipe is aligned with the pipe supports before lifting.
5.1.2.7 Check the proper level of the cross-main pipe fit-up then
tracking. See to it that the pipe being layout was already
coated with primer paint (first coating), provide level on both
ends, for proper penetration of rooting pass.
5.1.2.8 Fit-up entire pipe using mechanical level bar to ensure the
levelness of pipes, tack only all joints fittings, (elbow, tee
etc.) before proceeding to boring the pipe using hole saw
machine. Ask the permission of the concerned party for
inspection.
ACDC-MS-QAQC-001 Page 11 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
Building
ACDC-MS-QAQC-001 Page 12 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 13 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 14 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 15 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
5.3.3 Protection
5.3.3.1 The sprinkler heads must be store properly and shield them
from extreme heat. Overheating will damage the sprinkler by
weakening the thermal sensing element resulting to premature
activation.
ACDC-MS-QAQC-001 Page 16 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
5.4.2. All pipes installed shall be subjected for initial testing in every zone to
determine leakages and to avoid any damages during the final testing and
commissioning.
5.4.3. Initial testing shall be made by our separate testing crew with the
presence of the QA/QC Engineers, and provided the following requirements as
listed below.
5.4.3.2. All Defects found shall be marked one by one, then after
makings, release the water injected to the pipes to the nearest
drain. The crew shall be repair or replace the defective materials.
ACDC-MS-QAQC-001 Page 17 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 18 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 19 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 20 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
i. During CHB laying, make sure that opening for recessed type
fire hose cabinet are provided by Architectural contractors
following the approved shop drawing for the installation of
Fire hose cabinet.
ii. Check and prepare the approved shop drawing / FCD and
approved materials for the correct layout.
ACDC-MS-QAQC-001 Page 21 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
iii. Check the area concerned before the layout and installation of
the fire hose cabinet. Coordinate with other trade for
guidance and concerned.
iv. Prepare the materials for the fire hose cabinet layout and
layout the location of Fire Hose Cabinet.
v. Install the fire hose Cabinet and after installation retouching
works must be done.
5.7 Methodology for Valves and Equipment Tagging
5.7.1 Tag valves with identifying number and system number valves by the
floor level.
5.7.2 For valves, etc. stamped or engraved with 6.4 mm letters piping
system abbreviation and 13 mm numbers, with numbering scheme.
Provide 4mm hole for fastener. Use 2.4mm thick laminated plastic
with 2 black surfaces and white inner layer, and attached tags with
fastener (brass wire-link or beaded chain: or S-hook.)
5.7.3 Prepare lists of all tagged valves showing location, floor level, tag
number in use prepare separate list for each system. Mount list under
a sheet of clear acrylic in the Equipment Room. Include copies in
each maintenance manual.
5.7.4 Provide chart showing equipment lubrications points, lubrication
required and frequency, and columns for date and initials.
5.7.5 Stencil equipment with identifying letters numbers as used on
drawings, where space is available use full name equipment.
5.7.6 Identify all controls such as motor starter s not in motor control
centers, float switches and alarm.
5.7.7 Mark on the pipeline the flow direction of each piping with white
paint.
5.7.8 Mark if the pipe is cross main, drain, and riser.
5.7.9 Mark the valves, inside the pump room, whether it’s NO or NC
(normally open or normally closed).
ACDC-MS-QAQC-001 Page 22 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
5.8.2 Preparation
5.8.2.1 Clean substrate of dirt, dust grease oil, loose materials, rust or
other matter that maybe affect the proper fitting or adhesion of
the stopping materials.
5.8.2.2 Clean metal and glass surfaces using non- alcohol solvent.
ACDC-MS-QAQC-001 Page 23 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
5.8.4 Cleaning
5.8.4.1 Remove spilled and excess materials adjacent surface to where
the fire stop installation is.
5.8.4.2 Leave finish work in neat, clean condition with no evidence of
spill over or damages to adjacent
ACDC-MS-QAQC-001 Page 24 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 25 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 26 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 27 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
5.12.1 General
All new system including yard piping shall be
hydrostatically tested at 150 percent of the working pressure
but not less than 200 psi pressure for 2 hours.
5.12.2 Materials and requirements
A. Motorized Test Pump.
B. Pressure Gauge
C. Gate Valves
D. Check Valves
E. Drum or Water Container
F. Water
G. Hand Hose
5.12.3 Preparation
5.12.3.1 Operating test shall be made of the system when completed,
except where such test may risk water damage.
ACDC-MS-QAQC-001 Page 28 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
5.12.3.2 The required pressure gauge shall be of the approved type and
shall have a maximum limit not less than twice the normal
working pressure at the point installed.
5.12.3.3 Monitor the area where such test may risk water damage.
5.12.3.4 Check all piping lines, fittings, valves, and other to
be tested.
5.12.3.5 Provide temporary gate valve at the end of piping for flushing
purposes.
5.12.3.6 Provide enough for the individual system or portion of the
system being tested.
5.12.3.7 Release the pressure gauge at the elevation of the individual
system or portion of the system being tested.
5.12.4 Conduction
5.12.4.1 Through test pump water transfer from the piping system being
tested.
5.12.4.2 Open for the new minutes the gate valve provided at the end of
the piping to release excess all the pressure (release all from the
highest point of piping tested)
ACDC-MS-QAQC-001 Page 29 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
5.14.1.1 Check all the wiring of electrical control panels at pump room
prior to operation of fire pump & jockey pump.
5.14.1.2 Check the proper rotation of the fire pump and jockey pump
motor.
5.14.1.3 Close the main gate valve and operate fire pump and jockey
pump is a bypass operation and obtain the following
parameters.
a. Flow meter reading
b. Pressure reading
c. Ampere reading per Phase
d. Voltage reading: Line to line
e. Grounding/ Megger test
f. RPM reading
5.14.1.4 If the entire requirement for fire pump and jockey pump
already completed, checked first all AFSS riser valves and
supervisory Switches prior testing of the system.
5.14.1.5 Start to operate the jockey pump to pressurize the AFSS riser
until the required pressure (cut-ins). Observed the pipe that has
been tested within 2 hours in order to pressurize it zone by
zone.
5.14.1.6 All pipes shall be hydrostatically tested to the required working
pressure as per specification requirements.
5.14.1.7 The pressure shall be read from a gauge located at the low
elevation point of the individual system or portion of the
system being tested.
5.14.1.8 All pipe lines installed are subjected for flushing after testing
inspection activity, installation of sprinkler to remove all debris
inside the pipe lines or system which may have enter during the
course of installation or which may have been present in
existing piping.
ACDC-MS-QAQC-001 Page 30 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
Dropped in pressure thru visual leakage must be repaired, just drain or water
and repeat the conduction method. Read and record the pressure for final reading.
Flushing must be done after the testing activity.
6. Quality Control
6.1. Comply with the current applicable codes, ordinance and regulations of the
authorities. (NFPA 13 – Standard Installation of Sprinkler System)
ACDC-MS-QAQC-001 Page 31 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
6.2. We shall conduct test in the presence of the SMCC and DCI inspectors.
6.3. Piping system of a certain area to be tested shall be check if it complies with
the requirements based on plans and specifications.
6.4. Each section of cross-main and branch-line shall be filled with water and
specified test pressure (200 psi-230 psi). Measured at all point of lowest
elevation shall be applied by means of pumps connected to the system. Testing
will be done per section.
6.5. All defective pipes and fittings, valve joints and coupling shall be removed
and replaced.
6.6. After leak test completed all manifolds must remove.
6.7. Use level tools to ensure the good quality of supports and piping’s.
6.8. All testing devices to be used for inspection and test must have updated
calibration and valid calibration certificates.
6.9. All test forms shall be filled out and signed by the inspectors and contractor
representative during the testing inspection.
6.10. During roughing-ins works all pipes should apply primer paint then apply
international paint before final testing.
ACDC-MS-QAQC-001 Page 32 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
operate the lift slowly and deliberately. If necessary, use spotter to watch you
from ground to help you maneuver in tight man lift.
7.10. The operator must know the total weight of the load (personnel, tools and
supplies) if additional manpower will be handled in the man lift.
7.11. Operation man lift on stable ground; do not drive man lifts in mud and water.
7.12. Man lift should be driven on plant roads with the boom retracted all the way.
7.13. Man lift speed should be reduced to the lowest speed at railroad crossing and
on all uneven surfaces.
7.14. Man lift should be test run in safe location before use the check the sensitivity
of the controls.
7.15. After initial testing, lift the BI Pipes up to required elevation and suspend it by
using rope initially tied on the installed bracket and clevis support.
7.16. Fix and level the cross main pipes to the bracket and clevis support.
8. Handover Procedure
8.1. Internal testing and inspection with SMCC MEPF
8.2. Final inspection and testing with DCI
8.3. Official letter/email to SMCC informing them the area to be handed
ACDC-MS-QAQC-001 Page 33 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
10.1. GENERAL
ACDC-MS-QAQC-001 Page 34 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 35 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 36 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 37 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
AGCHEM
PROJECT MANAGER
SAFETY MANAGER
AGCHEM
SAFETY OFFICER
FOR IMPLEMENTATION
TO AGCHEM SITE
OPERATIONS
ACDC-MS-QAQC-001 Page 38 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
Unavailability
of vehicles for
Manual lifting
hauling of BI
1 or hauling of Pipes to the
Stress,
BI Pipes Injury
fabrication and
accessible area
for vehicles
lack of safety
Falling BI caution or
2 pipes during danger which Injury,
installation tied around the
perimeter works
lack of safety
Expose from caution or skin
3 welding danger which burned
flames tied around the out
perimeter works
Improper
Improper use coordination
with co- Fracture
4 of materials &
workers. Not / Injury
equipment familiar to the
equipment.
Lack of
illness,
5 Over Fatigue Manpower
injury
deploy at site
ACDC-MS-QAQC-001 Page 39 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
Poor
coordination
with the
undergo EHS concerned
orientation personnel
Excess BI Pipes
not properly Stress,
7 Slip, trip
arrange in the Injury
working area
Descriptions:
Daily activities
of equipment,
operations and
Routine processes
Planned
maintenance,
periodic or
emergency
shutdown,
Non-
process
routine
startup,
emergency
repair,
troubleshootin
g
Under direct
management
Direct control
Indirect No direct
management
control but has
ACDC-MS-QAQC-001 Page 40 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
influence (e.g.
supplier
activities)
START
CONTRACTOR TO DO
ACDC-MS-QAQC-001 INSTALLATION WORKS Page 41 of 53
ACCORDING TO Rev 0 /24 JUL. 2020
APPROVE SUBMITTALS
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
CONTRACTOR TO
COMMIT INTERNAL
INSPECTION WITH
SMCC
YES
NO
ACCEPTABLE?
NO
APPROVED?
YES
ACDC-MS-QAQC-001 Page 42 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
approved drawing.
2. Check temperature & type of sprinkler heads
as per approved submittal.
3. Check heads appears free of leakage and
damage.
4. Check heads free of paint.
5. Check heads are in appropriate position.
PIPE SLEEVING
A Pipe Blockout to Concrete Wall, Slab etc.
1. Reinforcement Supports with rebars & tie
wire are properly installed.
2.Covering Protection and Marking of blackout
are properly installed.
3. Installed blockout as per drawing.
4.Alignment orientation and elevation of
blockout
5. Blockout are properly supported prior to
concrete pouring.
SPRINKLER PIPING
A. Piping System
1. Ensure piping route/layout as per approved
drawing
2. Ensure pipe size and material complied with
the specification
3. Ensure pipe sleeves are installed on pipes
passing through wall/floor
4. Ensure pipe joints and fittings are properly
installed
5. Ensure pipes are installed level and plumb
6. Ensure hanger and supports size and spacing
is per project specifications.
7. Ensure fire stopping material applied between
pipe and sleeve
8. Ensure finished paint properly applied
9. Ensure piping system passed hydrostatic
pressure test
10. Ensure flushing and cleaning of piping
system performed and accepted
11. Ensure pipe identification and flow
ACDC-MS-QAQC-001 Page 43 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 44 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 45 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 46 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
16.
ACDC-MS-QAQC-001 Page 47 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 48 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 49 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 50 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 51 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:
Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM
ACDC-MS-QAQC-001 Page 52 of 53
Rev 0 /24 JUL. 2020