Discipline:

FIRE PROTECTION PIPE


WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

REVISION HISTORY
Rev. Revision Information Author Date

Authored by Reviewed by Approved by

Edcel P. Fernandez Billy Joe Zacarias Javes Darryl Anastacio


Project QA/QC Engineer Project-In-Charge Project Manager

This document is the property of ACDC, the information hereon may not be used in any manner without the written permission of
ACDC.
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Table of Contents

1. OBJECTIVE ……………………………………………………………………………....03
2. SCOPE OF WORK ……………………………………………………………………. ...03
3. REFERENCES ………………………………………………………………………. …..0

3
4. ORGANIZATION, RESPONSIBILITIES, WORK FORCE...........................................04
4.1 ORGANIZATION…………………………………………………………………...04
4.2 RESPONSIBILITIES……….…………….……………………………………….... 04
4.3. Organizational Chart………………………………………………………………...08
4.3 WORK FORCE…………………………………………………………………….. 09
5. METHODOLOGY ………………………………………………………………………. 07
5.1 Methodology for Installation of Crossmain and Branchline………………………..09
5.2 Methodology for Installation of Hanger, Support, Anchors, and Guides………….. 13
5.3 Methodology for Sprinkler heads Installation……………………………………... 15
5.4 Methodology for Hydro Test (Initial Testing)………………………………………16
5.5 Methodology for Riser & Wet Stand Pipe Installation……………………………...17
5.6 Methodology for Fire Hose Cabinet Installation…………………………………... 18
5.7 Methodology for Valves and Equipment Tagging………………………………… 20
5.8 Methodology for Fire Stopping Sealant Application……………………………… 20
5.9 Methodology for Valves Installation………………………………………………. 22
5.10 Methodology for Bursting Sprinkler Heads……………………………………… 23
5.11 Methodology for Pipe Sleeve Installation………………………………………... 24
5.12 Hydrostatic Test Pressure………………………………………………………… 24
5.13 Painting Procedure…………………………………………………………………26
5.14 Testing and Commissioning (Fire Pump & Jockey Pump)……………………….. 27
5.15 Flushing Methodology……………………………………………………………. 28
6. QUALITY CONTROL…………………………………………………………………. 29
7. Working at heights - Operation Guidelines for Manlifts………………………………….29
8. Handover Procedure…………………………………………………………………... 30
9. MATERIALS, MACHINERIES AND TOOLS…………………………………………..30
9.1 Materials………………………………………………………..……………………30
9.2 Machinery and Tools………………………………………………………………...31
10. SAFETY MEASUREMENTS…………………………………………………………...31
10.1 General……………………………………………………………………………...31
10.2 Safety Gears and Equipment………………………………………………………..32

ACDC-MS-QAQC-001 Page 1 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

10.3 Safety Seminars………………………………………………………………..........34

11.SAFETY TABLE OF ORGANIZATION AT SITE……………………………………35

12. ENVIRONMENTAL SAFETY PROCEDURE ……………………………………….36

13. INSPECTION AND TEST PLAN……………………………………………………...38

14. CHECKLIST…………………………………………………………………………….40

15. WORK PERMIT…………………………………………………………………………44

16. JOB HAZARD ANALYSIS…………………………………………………………......48

ACDC-MS-QAQC-001 Page 2 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

1. Objective
The objective of this statement is to establish the necessary guidelines for the
installation requirement of fire protection system in accordance with the project
scope of work, technical specifications and in conformity with approved drawings
and applicable standards.

2. Scope of work
General Fire Protection Works, Including supply and installation of pipes,
fittings, valves & accessories.
AGCHEM intend to carry out the documentation of installation, testing and
commissioning within the scope of the project. According to the specifications and
construction process, quality, and safety measures.
The main task of this method statement is to demonstrate the procedure for
equipment and the system testing to provide sufficient information on the minimum
requirements of acceptance and eventually turnover of fire protection system to the
client.

3. References
All work process which should be referred to Fire Code of the Philippines,
which is a regulation made under Fire Protection and Prevention Act of 1997
consisting of set of minimum requirements respecting Fire safety within and around
existing buildings and facilities.

This method statement should conform or refer to the following documents.

3.1 Approved For Construction Drawings (FCD)


3.2 Approved Furniture Layout
3.3 Approved Reflected Ceiling Plan (RCP)
3.4 Approved Wall Layout
3.5 Approved Shop Drawings Submittals

ACDC-MS-QAQC-001 Page 3 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

3.6 Approved Material Submittals


3.7 Contract Documents
3.8 Inspection and Test Plan
3.9 Project Technical Specifications
3.10 Construction Safety Health and Environment Program (CSHEP)
3.11 Project Quality Plan (PQP)

4. ORGANIZATION, RESPONSIBILITIES, WORK FORCE


4.1 Organization
During the execution of work under this document the following personnel will
be deployed as minimum:

4.1.1 Area Manager


4.1.2 Project Manager
4.1.3 Project In-Charge/Site Engineer
4.1.4 QA/QC Engineer
4.1.5 Auto Cad Operator
4.1.6 Timekeeper
4.1.7 Safety Officer
4.1.8 Warehouseman
4.1.9 Foreman

4.2 Responsibilities

4.2.1 AREA MANAGER

Responsible for the proper execution of the Project in terms of


quality, Cost and time, submission of Progress Billings by the PM/ PIC,
timely rectification of issued non Compliance Notices and closing out of
punch list, recording and monitoring of all change orders and initiate
consolidation, reconciliation with authorized representatives and
prepares billings by PM/PIC. Ensures that problems, issues critical to the

ACDC-MS-QAQC-001 Page 4 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

project are will attended and to formulate timely resolutions of such


problems / issues.
4.2.2 PROJECT MANAGER

Ensures that the Project Execution Plan are properly implemented


(within budget and quality), timely resolution of problems and issues
and response on the communication among the project team (Owner,
Gencon, PM, Etc.) Responsible for proper discipline of all Project staff,
delivery of materials, deployment, moving out of manpower (as the case
maybe) through direct coordination with the Operations Manager.
Timely action on the PICs evaluation / recommendation of site staff as
to promotions, salary increase, transfer, suspension etc. Responsible for
the development of objectives and goals of each staff, optimum
utilization of project resources (materials and manpower) and for the
proper documentation of the project including the up keep of those
documents. Supervision of the project by all the project staff. Ensures
compliance of all safety requirement of the project.

4.2.3 PROJECT – IN – CHARGE

Responsible for the proper implementation of the Project Execution


Plan (PEP), for the timely delivery of Project resources through constant
coordination with his timekeeper, warehouseman, purchasing etc.,
timely submission of reports billings etc. including their accuracy, for
the proper housekeeping and implementation of safety policies through
coordination of site safety authorities, for the up keep and proper usage
of office equipment such as (Computer/printer, photocopiers,
communication equipment) including those issued power tools and small
equipment, insures the upkeep of project records, documents and
documentation, proper conduct of his site staff and sees-to-it that rules
and regulations are being followed and for the timely rectification of
punch list.

ACDC-MS-QAQC-001 Page 5 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

4.2.4 SITE ENGINEER

Responsible for the proper work allocation by the Foreman and


Lead man, determines available work areas materials and manpower
allocation, upkeep of proper use of tools and equipment, checks the
quality and adequacy of materials prior to their installation, adequate
(completeness) of PPE’s of personnel including safety requirements of
work areas and prioritization of work areas in accordance to the
committed schedule.

4.2.5 QA/QC ENGINEER

Responsible for maintaining an acceptance quality in workmanship


or in accordance to contract documents. Sees to it that materials are
approved with proper documents prior to their usage. Complete and keep
of quality records. Enclosure of Non Conformances Notices (NCNs)
issued by the PM/Design team and responsible for the timely closure of
punch list.

4.2.6 AUTOCAD OPERATOR

Responsible for the upkeep of files documents in so far as


drawing is concerned. Production of details and coordinate with the
QA/QC engineer regarding constructability and quality in workmanship.
Proper use and care of office equipment. Timely retrieval of any file /
document in cases that they are needed. Accurate measurements /
dimensions which is verified from actual field condition of all shops
working drawings.

4.2.7 TIME KEEPER

Maintains an accurate track of hours worked by workers for payroll


purposes. Monitors workers inside the project site. Acts as liaison

ACDC-MS-QAQC-001 Page 6 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

between workers and payroll coordinators to ensure the smooth process


of pay distribution. Maintains time sheets accurate inputting time and
attendance data and prepares and verifies daily attendance, hours worked
adjustments while tracking overtime hours.

4.2.8 SAFETY OFFICER

Conducts daily tool box meeting with the group before the works
starts. Prepares pre-task planning and job Hazard analysis. Implements
and monitors all safety precautions at all working areas, especially in
high areas, leading edges, execution works and confined spaces. Submits
weekly Safety Accomplishments Report. Prepare incident, accident and
investigation report. Conducts monthly tools and safety equipment’s
inspection. Conducts safety orientation for newly hired workers prior to
start of work at the job site. Conducts safety inspection at the workplace
and identifies and possible work hazard, and recommends control
measures to avoid accidents. Issues notices of violation to project
employees for violation of company safety rules and regulations and
attends weekly safety coordination meeting.

4.2.9 WAREHOUSEMAN

Responsible for the organized stocking of such materials for easy


access in withdrawal and inventory system. Regular update of Materials
Status in order for the PIC to make requisition promptly or as needed.
Follow – up on the delivery of requested materials through coordination
with the PIC and the Purchasing Department. Responsible for the proper
upkeep of the warehouse, including security of those stored materials.

4.2.10 CONSTRUCTION FOREMAN

Confer with the PIC and other site staff under each area of
responsibility regarding the plan of action, available work areas,

ACDC-MS-QAQC-001 Page 7 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

resources and safety outfit. Evaluate areas of priority as well as the


corresponding logistic support such as materials, manpower,
equipment, including safety paraphernalia. Ensure that every skilled
personnel have the right tools and equipment, including PPE’s. Ensure
that all works are executed accordingly to approved plan, procedures
and report to the PIC any deviation therein. Checks the daily actual
output against the planned output and formulate measures of
improvement in case of negative variance.

4.3. ORGANIZATIONAL CHART

ACDC-MS-QAQC-001 Page 8 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

4.3 Work Force


List of Worker but not limited to the following:
Table 1

Item No Descriptions Quantity


1 Foreman 1 ea
2 Pipe Fitter 3 ea
3 Helper 2 ea

ACDC-MS-QAQC-001 Page 9 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Note:
a. Allotment of workforce shall be determined upon issuance of schedule of
work.
b. The actual and number of persons may vary and shall be selected in
accordance with actual site conditions and site requirements.

5. WORK PROCEDURE/METHODOLOGY

5.1 Methodology for Installation of Cross main and Branch line


5.1.1 Preparation
5.1.1.1 Check the areas if ready for the installation and free from any
debris and unsafe condition.
5.1.1.2 Provide necessary approved/ certified platforms before
starting the works and label it with company name.
5.1.1.3 If there will be hot works, secure the necessary hot work
permit before proceeding to work. Therefore, provide also all
pipes required by workers.
5.1.1.4 First, Clean and paint neatly all the sleeves provided to
beams, girder and walls by using platform.
5.1.1.5 Second, provide necessary measuring tools like meter type
plumb bob, nylon string, L- bar and level bars to ensure the
level of installation.
5.1.2 For Cross main pipe Installation
5.1.2.1 Prepare and secure approval of work permit.
5.1.2.2 Check and Prepare the approved shop drawings and approved
materials for the correct lay-out.
5.1.2.3 Check the area concern before the layout and installation of
cross-main pipe. Coordinate with other trade for guidance and
concern.
5.1.2.4 Mark and layout the piping according to the approved shop
drawings using nylon cord or other marking tools.
5.1.2.5 Install approved and appropriate pipe supports
5.1.2.6 Lift the cross main pipe by fixing it on the scissor lift (450kg
capacity) using tie wire/ropes. At the same time, loop the

ACDC-MS-QAQC-001 Page 10 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

pulleys rope at the both ends of the pipe, this is for additional
support and preventive measure. Operate the scissor lift and
elevate the pipe up to the required elevation. See to it that the
pipe is aligned with the pipe supports before lifting.
5.1.2.7 Check the proper level of the cross-main pipe fit-up then
tracking. See to it that the pipe being layout was already
coated with primer paint (first coating), provide level on both
ends, for proper penetration of rooting pass.
5.1.2.8 Fit-up entire pipe using mechanical level bar to ensure the
levelness of pipes, tack only all joints fittings, (elbow, tee
etc.) before proceeding to boring the pipe using hole saw
machine. Ask the permission of the concerned party for
inspection.

ACDC-MS-QAQC-001 Page 11 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Figure 1. Cross main installation at Admin

Building

Figure 2. Cross main installation at Warehouse

ACDC-MS-QAQC-001 Page 12 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

5.1.3 For Branch line-pipe Connection


5.1.3.1 Prepare and secure approval of work permit.
5.1.3.2 Check and prepare all the approve materials, equipment and
shop drawings.
5.1.3.3 Check the area concern before the layout and installation of
cross-main pipe. Coordinate with other trade for guidance and
concern.
5.1.3.4 Mark and layout the piping according to the approved shop
drawings using nylon cord or other marking tools.
5.1.3.5 Measure and cut the pipe using pipe cutter accordingly.
5.1.3.6 Check and clean the pipe to prevent clogging in the future.
5.1.3.7 Paint the pipes with the 1st coat primer before installation.
5.1.3.8 Thread the end of pipes using the appropriate electric
threading machine or manual pipe threader.
5.1.3.9 Provide Teflon tape on threaded portion of pipe before doing
any connection works.
5.1.3.10 Upon installation of pipe see to it that supports were already
installed properly.

ACDC-MS-QAQC-001 Page 13 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Figure 3. Installation of cross main and branch line

5.2 Methodology for Installation of Hanger, Support, Anchors, and Guides

5.2.1 Quality Assurance


5.2.1.1 All bracket, Clamp and rod sizes and indicated in this
specification are minimum sizes, only.
5.2.1.2 Anchor points shall be located and constructed to permit the
piping to take up expansion and constructed freely in opposite
directions from the anchored points.
5.2.1.3 Guide points shall be located and constructed wherever
required or shown on drawings at each side of an expansion
joint or loop, to permit free axial movement of piping system.

5.2.2 Installation Procedure


5.2.2.1 All piping shall be supported only from building structural
steel or galvanized steel inserts imbedded on poured concrete.
Where piping revisions are slabs are poured, 75mm and
smaller may be supported at intermediate points by Hilti, or
other 12mm expansion bolts and shields, provided main
support is not less than 7 meters on centers. All insert
expansion bolts and shields in post-tensioned concrete slabs
shall be submitted to structural engineer for approval prior to
commencement of work. Intermediate support for piping 4’
and larger shall be attached to concrete beams of columns by
means of 100mm x 100mm x 18mm’(horizontal)and
supporting rod at 90 degrees from anchor bolt. Its intent is
only permitted in poured concrete construction.

ACDC-MS-QAQC-001 Page 14 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

5.2.3 Hanger Location for Horizontal Piping

Pipe Size (mm) Rod Size (mm) Spacing (m)


25 10 1.8
32 10 2.4
40 10 2.7
50 10 2.7
65 12 3.0
75 12 3.0
100 16 3.3
150 20 3.7

ACDC-MS-QAQC-001 Page 15 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Figure 4. Installation of Bracket and Hanger support

5.3 Methodology for Sprinkler Heads Installation


5.3.1 Quality Assurance
5.3.1.1 Inspect glass bulb of sprinkler heads at the time of installation
to make sure that the bulbs contain fluid.
5.3.1.2 Any glass bulb that shows evidence of leakage or does not
have any fluid must be discarded.
5.3.1.3 Do not install any bulb type sprinkler heads if the bulb is
cracked or there is loss of fluid from the bulb.
5.3.1.4 With the sprinkler held horizontally, a small air bubble
should be present. The diameter of air bubble is
approximately 1.6 mm for the 13oF/57oC to 2.4 mm for the
360oF/182oC temperature rating. Loss of fluid from a bulb can
cause the sprinkler to fail to activate in a fire.

5.3.2 Installation procedures


5.3.2.1 Install 1/2” and ¾” sprinkler heads in fittings with the pipe in
place. Use standard and quick response sprinkler heads
(upright, pendent, horizontal sidewall, recessed pendent, and
recessed horizontal sidewall) depending on the location.
5.3.2.2 Hand start and then wrench tighten each sprinkler head with
the sprinkler strap in place. The sprinkler may hand-start by
holding onto the sprinkler strap.
5.3.2.3 Do not remove the sprinkler strap until the sprinkler is
completely installed.

5.3.3 Protection
5.3.3.1 The sprinkler heads must be store properly and shield them
from extreme heat. Overheating will damage the sprinkler by
weakening the thermal sensing element resulting to premature
activation.

ACDC-MS-QAQC-001 Page 16 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

5.4 Methodology for Hydro Test (Initial Testing)


5.4.1 Equipment and Materials:
i. Motorized test pump
ii. Empty drum
iii. Water
iv. Pressure gauges
v. Gate valve
vi. Check valve
vii. Drain valve/ Temporary air ventilation

5.4.2. All pipes installed shall be subjected for initial testing in every zone to
determine leakages and to avoid any damages during the final testing and
commissioning.

5.4.3. Initial testing shall be made by our separate testing crew with the
presence of the QA/QC Engineers, and provided the following requirements as
listed below.

5.4.3.1. The piping shall be tested in accordance with the local


requirements and NFPA code (NFPA 20) requirement and the
system shall be tested not less than 200 psi hydrostatic pressure
for two (2) hours.

5.4.3.2. All Defects found shall be marked one by one, then after
makings, release the water injected to the pipes to the nearest
drain. The crew shall be repair or replace the defective materials.

5.4.3.3. After rectification of work, system will be retested until


the works is proven satisfactory and pressure maintained 200 psi
for two (2) hours.

ACDC-MS-QAQC-001 Page 17 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

5.4.4. When testing results satisfies the requirements specified by Inspector,


QA/QC prepares the inspection Work request (IWR) and submits to MEPF
coordinator and QA/QC Engineer for approval of the system.

5.5 Methodology for Riser & Wet Stand Pipe Installation


5.5.1 Preparation
5.5.2.1 Check the areas if ready for the installation and free from any
debris and unsafe condition.
5.5.2.2 Provide necessary approved/ certified platforms before
starting the works and Label it with company name and
permits/ certificate.
5.5.2.3 If there will be hot works, secure the necessary hot work
permit before proceeding to work. Therefore, provide also all
pipes required by workers.
5.5.2.4 First provide pipe sleeve (G.I Sched. 40) on floor where riser
will be passing thru, clean and paint neatly the sleeves that
will be install.
5.5.2.5 Second, provide necessary measuring tools like meter tape
plumb bob. Nylon string, L-bar and level bars to ensure the
levelness.

5.5.2 Installation Procedure


5.5.2.6 Prepare and secure approval work permit.
5.5.2.7 Check the area concern before the layout and installation of
riser. Coordinate with other trade for guidance and other
concerns.
5.5.2.8 Mark and layout the piping according to the approved shop
drawings using nylon cord or other marking tools.
5.5.2.9 See to it that the pipe being laid out was already coated with
primer paint (first coating), provide level on both ends, for
proper penetration of rooting pass.
5.5.2.10 For the wet Stand Pipe riser, just install the pipe with bracket,
and connect the nipple at 900mm above the finish line for the
fire hose valve.
5.5.2.11 Fit-up the entire pipe using mechanical level bar to ensure the
levelness of pipes tack only all joints fittings (elbow, Tee

ACDC-MS-QAQC-001 Page 18 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

etc.) before proceeding to full welding. Ask the permission of


the concerned party (SMCC and DCI) for inspection.

5.5.3 Vertical movements

The system riser (wet) has a provision of mechanical grooved


coupling or Victaulic coupling 600mm above the finish floor line.

5.6 Methodology for Fire Hose Cabinet Installation


5.6.1 Preparation
5.6.1.1 Check the areas if ready for the installation and free from
any debris and unsafe condition.
5.6.1.2 Prepare work permit to be approved prior to installation.
5.6.1.3 Provide the necessary measuring tools like meter tape, plumb
bob, nylon string, L-bar and level bars to ensure the
levelness.

5.6.2 Installation Procedure


5.6.2.1 Surface Mounted Fire Hose Cabinet

ACDC-MS-QAQC-001 Page 19 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Figure 5A. Surfaced Mounted FHC

i. Check and prepare the approved shop drawing FCD/ ISD


and approve materials for the correct layout.
ii. Check the area concern before the layout and installation of
the fire hose cabinet. Coordinate with other trade for
guidance and concern.
iii. Lay out the location of the fire hose cabinet.
iv. Provide anchorage for the fire hose cabinet using 3/8”
expansion shield.
v. Provide 50mmØ hole at the left side of the fire hose cabinet
to hose real pipe.
vi. Install the fire hose Cabinet and make sure that it will fit
properly into the wall

5.6.2.2 Recessed Type Fire Hose Cabinet

ACDC-MS-QAQC-001 Page 20 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Figure 5B. Recessed Type FHC

i. During CHB laying, make sure that opening for recessed type
fire hose cabinet are provided by Architectural contractors
following the approved shop drawing for the installation of
Fire hose cabinet.
ii. Check and prepare the approved shop drawing / FCD and
approved materials for the correct layout.

ACDC-MS-QAQC-001 Page 21 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

iii. Check the area concerned before the layout and installation of
the fire hose cabinet. Coordinate with other trade for
guidance and concerned.
iv. Prepare the materials for the fire hose cabinet layout and
layout the location of Fire Hose Cabinet.
v. Install the fire hose Cabinet and after installation retouching
works must be done.
5.7 Methodology for Valves and Equipment Tagging
5.7.1 Tag valves with identifying number and system number valves by the
floor level.
5.7.2 For valves, etc. stamped or engraved with 6.4 mm letters piping
system abbreviation and 13 mm numbers, with numbering scheme.
Provide 4mm hole for fastener. Use 2.4mm thick laminated plastic
with 2 black surfaces and white inner layer, and attached tags with
fastener (brass wire-link or beaded chain: or S-hook.)
5.7.3 Prepare lists of all tagged valves showing location, floor level, tag
number in use prepare separate list for each system. Mount list under
a sheet of clear acrylic in the Equipment Room. Include copies in
each maintenance manual.
5.7.4 Provide chart showing equipment lubrications points, lubrication
required and frequency, and columns for date and initials.
5.7.5 Stencil equipment with identifying letters numbers as used on
drawings, where space is available use full name equipment.
5.7.6 Identify all controls such as motor starter s not in motor control
centers, float switches and alarm.
5.7.7 Mark on the pipeline the flow direction of each piping with white
paint.
5.7.8 Mark if the pipe is cross main, drain, and riser.
5.7.9 Mark the valves, inside the pump room, whether it’s NO or NC
(normally open or normally closed).

5.8 Methodology for Fire Stopping Sealant Application

5.8.1 Quality Assurance


5.8.1.1 Fire stop system installation shall conform to requirement of
qualified designs or manufactures approved modifications as a

ACDC-MS-QAQC-001 Page 22 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

supported by the engineering report. Field inspections shall be


carried out by fire stop manufacturer requirement.
5.8.1.2 Install fire stop materials and system as requires by these
contract documents and meets and be accepted for use by
applicable design building and construction codes.
5.8.1.3 Submit manufacturer product data, letter of certification, or
certified laboratory test report that materials or combination
materials (fire system) meets the requirements specified in
accordance with applicable reference standards.
5.8.1.4 The firestop compound shall not contain any solvent or
inorganic fiber.
5.8.1.5 The penetration of seal materials must be unaffected by
moisture and must maintain the integrity of the floor or wall
assembly for its rated time period when tested.
5.8.1.6 Fire Stopping sealants must be flexible, allowing for normal
pipe movements.
5.8.1.7 Please refer for Architect’s Specification for the stopping
materials
5.8.1.8 Contactors shall perform installation of the stopping materials.

5.8.2 Preparation
5.8.2.1 Clean substrate of dirt, dust grease oil, loose materials, rust or
other matter that maybe affect the proper fitting or adhesion of
the stopping materials.
5.8.2.2 Clean metal and glass surfaces using non- alcohol solvent.

5.8.3 Installation Procedure


5.8.3.1 Installation of the fire stops shall be performing by applicator/
installer that have a proper training.
5.8.3.2 Fire stop sealant shall be applied in accordance with the fire test
resistance requirements, acceptable sample installation and
manufacturers recommendations.
5.8.3.3 Unless specified and approved all insulation used in conjunction
with through penetration, shall remain intact, undamaged and
may not be removed.
5.8.3.4 Seal holes and penetrations to ensure an effective smoke seal.

ACDC-MS-QAQC-001 Page 23 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

5.8.3.5 In areas of high traffic, protect fire stopping materials from


damage. If the opening is large, install fire stopping materials
capable of supporting the weight of a human.
5.8.3.6 Insulation types specified in other section shall not be installed
in lieu of fire stopping materials specified herein.
5.8.3.7 All combustible penetrates (e.g. non- metallic pipes or insulated
metallic pipes) shall be protected using products and systems
tested in a configuration representative of field condition.

5.8.4 Cleaning
5.8.4.1 Remove spilled and excess materials adjacent surface to where
the fire stop installation is.
5.8.4.2 Leave finish work in neat, clean condition with no evidence of
spill over or damages to adjacent

ACDC-MS-QAQC-001 Page 24 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Figure 6. Application of Fire Stopping Sealant

5.9 Methodology for Valves Installation


5.9.1 Quality Assurance
5.9.1.1 Each valve shall have the manufacturer’s name, size, and
reassure rating cast or stamp on body.
5.9.1.2 All fire protection water control valves within the building shall
be constructed so that they maybe repacked while open and
under pressure or slow- closing quarter-turn gear- operated
butterfly valves.
5.9.1.3 All valves shall be with threaded or flanged ends as required by
the piping system in which they are installed.
5.9.1.4 Valves shall be selected for the working pressure indicated on
the drawing.

5.9.2 Installation Procedure


5.9.2.1 All valves shall be installed in the upright vertical or horizontal
position unless specifically otherwise required by the drawings.
5.9.2.2 All valves shall be installed in accessible location to facilitate
easy removal for repair or replacement.
5.9.2.3 Support locations for Vertical Piping
Threading & Mechanical Joint piping: At every floor: but in no
case greater than 6ft. intervals
5.9.2.4 All beam attachments shall be installed on clean, smooth, and
non-fireproofed section of the beam.
5.9.2.5 All the protection piping shall be hung individually from the
structure.

ACDC-MS-QAQC-001 Page 25 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Figure 7. Installation of Valves


5.10 METHODOLOGY FOR BURSTING OF SPRINKLER HEADS
5.10.1 Tools and Equipment
1. Pressure Test Pump
2. Fabricated Manifold 3 Way
a. Calibrated Pressure Gauge (300Psi)
b. Ball Valve
3. Thermometer
4. Water Supply
5. Empty Drum
6. A-Ladder
7. Torch/lighter
8. Square Plug

5.10.2 Pre-testing Procedure

5.10.2.1 Secure first all necessary documents prior to bursting.


5.10.2.2 Check all pipes on feed main and connections including
sprinkler heads for any defect from poor workmanship and if it

ACDC-MS-QAQC-001 Page 26 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

is properly supported with brackets and hangers to support the


initial weight of water and the pressure to be inserted.
5.10.2.3 To avoid air pockets and to ensure that air is released, air
release valve (ball valve installed at the highest point) should
be provided.
5.10.2.4 A temporary manifold should be provided for the bursting w/ 3
type of sprinkler that installed.
5.10.2.5 Provide necessary safety signage’s around the area where
testing is to be done especially at the manifold assembly.
5.10.2.6 Upon completion of the initial check and conditions are
satisfied, proceed with the opening of valves on pump room.
Make sure all isolation valves per floor are closed.

5.10.3 Testing Procedure

5.10.3.1 Bursting test shall conduct in the presence of inspector and


bureau of fire protection.
5.10.3.2 Gradually fill the pipe with isolation valve at the highest/lower
level and let the purging valve open to release the excess air
and to avoid air packets during filling the pipe.
5.10.3.3 When the system is fully filled, close the air release valve. It is
now ready to receive pressure.
5.10.3.4 Then prepare the torch/lighter to lightened the manifold w/
installed 3 type of sprinkler
5.10.3.5 After bursting have been approved, drain the system. It will
serve as preliminary flushing to remove unwanted foreign
material that may have entered during and after installation.
Then remove the temporary manifold.
5.10.3.6 Clean the area.

5.11 Methodology for Pipe sleeve installation


5.11.1 Product/ Preparatory
5.11.1.1 Provide sleeves for each pipe passing through wall partitions,
beams and floors.
5.11.2 Installation
5.11.2.1 Cut the pipe sleeve prior to the beam length. Apply primer
paint prior to installation.
5.11.2.2 Prepare Z bars to be used as per approved size dimension.

ACDC-MS-QAQC-001 Page 27 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

5.11.2.3 Installation of pipe sleeve referring to the approved shop


drawing with the reference to elevation & location.
5.11.2.4 Use tansi for lay-outing and alignment of pipe sleeve prior to
installation.

Figure 8. Pipe Sleeve Installation

5.12 Hydrostatic Test Procedure

5.12.1 General
All new system including yard piping shall be
hydrostatically tested at 150 percent of the working pressure
but not less than 200 psi pressure for 2 hours.
5.12.2 Materials and requirements
A. Motorized Test Pump.
B. Pressure Gauge
C. Gate Valves
D. Check Valves
E. Drum or Water Container
F. Water
G. Hand Hose
5.12.3 Preparation
5.12.3.1 Operating test shall be made of the system when completed,
except where such test may risk water damage.

ACDC-MS-QAQC-001 Page 28 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

5.12.3.2 The required pressure gauge shall be of the approved type and
shall have a maximum limit not less than twice the normal
working pressure at the point installed.
5.12.3.3 Monitor the area where such test may risk water damage.
5.12.3.4 Check all piping lines, fittings, valves, and other to
be tested.
5.12.3.5 Provide temporary gate valve at the end of piping for flushing
purposes.
5.12.3.6 Provide enough for the individual system or portion of the
system being tested.
5.12.3.7 Release the pressure gauge at the elevation of the individual
system or portion of the system being tested.
5.12.4 Conduction
5.12.4.1 Through test pump water transfer from the piping system being
tested.
5.12.4.2 Open for the new minutes the gate valve provided at the end of
the piping to release excess all the pressure (release all from the
highest point of piping tested)

5.13 Painting Procedure


5.13.1 General
For protection of piping against corrosion. It must be painted
with two (2) coat of Primer Oxide and one (1) one coat of the
international Red Enamel paint.
5.13.2 Materials
5.13.2.1 Paint brush
5.13.2.2 Red primer Oxide
5.13.2.3 Red enamel Paint Rag (Cloth)
5.13.3 Preparation
5.13.3.1 Make sure to remove all dirt and debris on the pipes before
applying coatings on it.
5.13.3.2 Exposed black steel piping, pipe covering, equipment and
support piping and enclosures shall have two (2) coats of
primer Oxide paint after installation, then (1) one coat of red
Enamel paint for final coating after testing of pipes.
5.13.3.3 All pipes hangers, anchor, and supports shall be coated with
Primer Oxide before installation
5.13.3.4 At the end of each workday, Remove empty cans, rags, rubbish,
and other discarded paint materials from the project site.

ACDC-MS-QAQC-001 Page 29 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

5.13.3.5 Provide “Wet Paint” signs to protect newly painted finishes.


5.14 Testing and Commissioning (Fire Pump & Jockey Pump)
5.14.1 Procedure

5.14.1.1 Check all the wiring of electrical control panels at pump room
prior to operation of fire pump & jockey pump.
5.14.1.2 Check the proper rotation of the fire pump and jockey pump
motor.
5.14.1.3 Close the main gate valve and operate fire pump and jockey
pump is a bypass operation and obtain the following
parameters.
a. Flow meter reading
b. Pressure reading
c. Ampere reading per Phase
d. Voltage reading: Line to line
e. Grounding/ Megger test
f. RPM reading
5.14.1.4 If the entire requirement for fire pump and jockey pump
already completed, checked first all AFSS riser valves and
supervisory Switches prior testing of the system.
5.14.1.5 Start to operate the jockey pump to pressurize the AFSS riser
until the required pressure (cut-ins). Observed the pipe that has
been tested within 2 hours in order to pressurize it zone by
zone.
5.14.1.6 All pipes shall be hydrostatically tested to the required working
pressure as per specification requirements.
5.14.1.7 The pressure shall be read from a gauge located at the low
elevation point of the individual system or portion of the
system being tested.
5.14.1.8 All pipe lines installed are subjected for flushing after testing
inspection activity, installation of sprinkler to remove all debris
inside the pipe lines or system which may have enter during the
course of installation or which may have been present in
existing piping.

Maintain the pressure without loss shall be determined by a drop in a gauge


pressure or visual leakage.

ACDC-MS-QAQC-001 Page 30 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Dropped in pressure thru visual leakage must be repaired, just drain or water
and repeat the conduction method. Read and record the pressure for final reading.
Flushing must be done after the testing activity.

5.15 FLUSHING METHODOLOGY


5.15.1 Preparation of works
5.15.1.1 Determine location and floor level for flushing.
5.15.1.2 Prepare work permit to be approved prior to testing.
5.15.1.3 Prepare the required materials and tools to be used.
5.15.2 Procedure in execution of works
5.15.2.1 Test the system by hydrostatic pressure test. Once the system
passed the quality assurance, prepare the system for flushing
procedures.
5.15.2.2 Upon approval of the preliminary testing, the water in the
system should be released at the lowest portion of the system
either in auxiliary or Inspector Test Drain to be flush out of the
debris inside the pipe or system. Use drums to contain water
discharge from the system.
5.15.2.3 Once the system is completely drain pump water again to the
system using electric driven test pump and allowing it to
overflow in order to flushed out the debris or foreign materials.
5.15.2.4 Flushing shall proceed and stop only once water flowing from
the cross main pipe is clean and free of debris, then the system
is close and installation of sprinkler heads is ready.
5.15.2.5 Clean the area of activities where flushing is done.
5.15.3 Materials and Equipment to be use
5.15.3.1 Electric Driven Test Pump.
5.15.3.2 Drums
5.15.3.3 Ladder

6. Quality Control
6.1. Comply with the current applicable codes, ordinance and regulations of the
authorities. (NFPA 13 – Standard Installation of Sprinkler System)

ACDC-MS-QAQC-001 Page 31 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

6.2. We shall conduct test in the presence of the SMCC and DCI inspectors.
6.3. Piping system of a certain area to be tested shall be check if it complies with
the requirements based on plans and specifications.
6.4. Each section of cross-main and branch-line shall be filled with water and
specified test pressure (200 psi-230 psi). Measured at all point of lowest
elevation shall be applied by means of pumps connected to the system. Testing
will be done per section.
6.5. All defective pipes and fittings, valve joints and coupling shall be removed
and replaced.
6.6. After leak test completed all manifolds must remove.
6.7. Use level tools to ensure the good quality of supports and piping’s.
6.8. All testing devices to be used for inspection and test must have updated
calibration and valid calibration certificates.
6.9. All test forms shall be filled out and signed by the inspectors and contractor
representative during the testing inspection.
6.10. During roughing-ins works all pipes should apply primer paint then apply
international paint before final testing.

7. Working at heights - Operation Guidelines for Man lifts


7.1. Only authorized and trained personnel are permitted to operate man lifts.
7.2. Man lifts are to be inspected before being place in service each day using
Safety Procedure. Man lifts without current inspections are not be used.
7.3. The maximum basket load limit is 450 kg. Maximum of three people in the
basket.
7.4. Tools should be place in a tool pouch or tool box otherwise secured; tools
should not protrude from the handrails of the man lift.
7.5. Man lifts that do not meet inspection criteria are to be taken out of service and
are not to be used until repaired.
7.6. Safety harness must be worn at all times when operating or riding a man lift.
7.7. When operation man lift in a production unit, special precautions must be
taken to avoid coming in contact with overhead obstructions such as conduit or
process piping and equipment.
7.9. Before rising the basket make sure it can be maneuvered safely to reach the
intended destination. Survey the area to identify a clear unobstructed path and

ACDC-MS-QAQC-001 Page 32 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

operate the lift slowly and deliberately. If necessary, use spotter to watch you
from ground to help you maneuver in tight man lift.
7.10. The operator must know the total weight of the load (personnel, tools and
supplies) if additional manpower will be handled in the man lift.
7.11. Operation man lift on stable ground; do not drive man lifts in mud and water.
7.12. Man lift should be driven on plant roads with the boom retracted all the way.
7.13. Man lift speed should be reduced to the lowest speed at railroad crossing and
on all uneven surfaces.
7.14. Man lift should be test run in safe location before use the check the sensitivity
of the controls.
7.15. After initial testing, lift the BI Pipes up to required elevation and suspend it by
using rope initially tied on the installed bracket and clevis support.
7.16. Fix and level the cross main pipes to the bracket and clevis support.

8. Handover Procedure
8.1. Internal testing and inspection with SMCC MEPF
8.2. Final inspection and testing with DCI
8.3. Official letter/email to SMCC informing them the area to be handed

9. Materials, Machinery and Tools


9.1.Materials
9.1.1. Riser
9.1.1.1. Black Iron Pipe ERW (Supreme)
9.1.1.2. Grooved Type Coupling (Victaulic)
9.1.1.3. Grooved Type Fittings (Victaulic)
9.1.1.4. Grooved Type Gate Valve (Fireking)
9.1.1.5. Waterflow Switch (System Sensor)
9.1.1.6. Alarm Check Valve (Firelock)
9.1.1.7. Supervisory Switch (System Sensor)
9.1.1.8. Alarm Test Module (Victaulic)
9.1.2. Crossmain & Branchline
9.1.2.1. Black Iron Pipe Schd.40 (Supreme)
9.1.2.2. Fittings (SCI)
9.1.2.3. Mechanical Tee (Victaulic)
9.1.2.4. Sprinkler Heads (Viking)

ACDC-MS-QAQC-001 Page 33 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

9.1.2.5. Clevis Hanger (Hokki)


9.1.2.6. Firestop Sealant (Hilti)
9.1.2.7. Expansion Shield (Hilti)
9.1.2.8. Primer/International Paint (Boysen)
9.1.3. Pump Room
9.1.3.1. Pressure reducing valve (OCV Brand)
9.1.3.2. Pressure Gauge (Weksler)
9.1.3.3. Butterfly Valve (Firelock)
9.1.3.4. Check Valves (Firelock)
9.1.4. Pre-action
9.1.4.1. Pre-action System (Firelock)
9.2.Machinery and Tools
9.2.1. Grooving Machine
9.2.2. Welding Machine
9.2.3. Holesaw Machine
9.2.4. Power Puncher
9.2.5. Threading Machine
9.2.6. Speed Cutter
9.2.7. Rotary Hammer
9.2.8. Baby Grinder
9.2.9. Chipping Gun
9.2.10. Pipe Wrench
9.2.11. Adjustable Wrench
9.2.12. Electric Drill

10. Safety Measurement

10.1. GENERAL

As an authorized organization and enforcer of safety standards and


practices, Agchem will abide by and continually consult with the implementing
rules and guidelines set forth by the Safety Organization of the Philippines
(SOFI).
For this project, Agchem shall deploy a full-time and qualified Safety
Engineer at site as an implementing authority for all the Safety concerns

ACDC-MS-QAQC-001 Page 34 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

specially that of the Project Management Team (PMT).


Provisions for the required and necessary equipment for issuance to all
workers and site personnel shall be faithfully complied with and issued by
Agchem. A budgetary allocation for this item will be integrated in our bid
proposal as an insurance that acquisition for safety items will not be
compromised.

10.2. SAFETY GEARS AND EQUIPMENTS


Agchem shall maintain sufficient quantity and inventory of basic and essential
safety gears and equipment’s at site equal in number or percentage requirements
of all its workers. The following safety gear specifications shall be implemented
by Agchem for site use:

10.2.1. Safety Helmet (White)


To be used by engineers, supervisors, and consultants. This shall be
of required impact resistance complete with neck strap. Each Agchem
Engineer will be issued his or her own helmet, while three spare helmets
will be made available at site for use by its consultant or visitors.

10.2.2. Safety Helmet (blue or as per approved color)


For use by workers from foremen down to lead men, workers and
labors. Final color will depend on the approved or assigned scheme as
directed by the project management team.

10.2.3. Safety belt


All workers or personnel who will be working on elevated areas or as
per elevation directed by the project management team, will be provided
and obliged to wear safety belt. Fifteen sets of safety belt will be
maintained at site to be utilized by workers who are issued job orders on
elevated areas and platforms.

10.2.4. Full-Body Harness


On elevated work area which on assessment of the safety engineer or
supervisors possess grave danger to the assigned worker, a full body
safety harness will be required and issued to worker which shall be made
obligatory.

ACDC-MS-QAQC-001 Page 35 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

10.2.5. Safety Shoes (steel toed)


As a Basic safety gear, all engineers, supervisors, and workers will
be issued a set of safety shoes. This will be subject for salary deductions
on the worker salary as a company insurance on the workers’ longevity
vs. cost, however, this item shall be fully reimbursed upon worker(s)
proper separation.

10.2.6. Welding glass


All welders will be obligated to use a darkened welding glass. A
one-is-to one ratio for welding machine and welding glass will be
maintained at site.

10.2.7. Welding Gloves


All welders and welder’s helpers will be issued with new and good
quality welding gloves on one welder/helper one gloves ratio. Use of
these gloves shall also be obligatory.

10.2.8. Welding Jacket


Blue denim jacket will be issued to a welder and helper. Its use shall
also be made obligatory.

10.2.9. Safety goggles


At least, twelve (12) sets of safety goggles will be made available at
site warehouse for ready issuance to workers who have job orders for
drilling, grinding, and chipping works. Supervisors, foremen, and lead
men shall see to it that workers with said job assignments shall be
obligated to wear these goggles.

10.2.10. Working Gloves


All workers shall be issued with working gloves. Since, this item is
for short term service, replacements shall always be made available at
site provided that a record of first issuance indicates that the first gloves
are used for at least three (3) months.

10.2.11. Rain coat with neon markings

ACDC-MS-QAQC-001 Page 36 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

An inventory of twelve (12) sets of nylon raincoat with neon


markings will be made available at site for use by workers who has to
work on exposed areas during rainy condition. Workers will only be
allowed to work on slightly rainy condition but not during stormy
weather or where lightning is imminent.

10.2.12. Safety illustration boards


An illustration board showing the essential safety gears and its use
will be posted on the timekeeper’s area, warehouse, office, and
fabrication area. Also, boards showing safety reminders and proper
safety procedures will be posted as well on those areas.

10.2.13. Safety Stickers


Required safety stickers including stickers-showing company name
and logo on helmets, tools, and work areas will be issued constantly at
site. SOFI stickers will also be purchased if required by the PMT

10.2.14. Rain Boot


Engineers and workers will be issued rain boots on a one-is-to-one
ratio. This is to avoid accidental slips or fall at site where muddy
condition exists.

10.2.15. Working at Heights


All workers who are working at heights will be provided with safety
harness (double lanyard), prior to assembling of scaffold. Scaffold must
be with complete components such as; top rail, mid rail, platform, and
step/ladder, cross brace, tubular, joint pin, base jack, and base plate.

10.3. SAFETY SEMINARS


Agchem will send its safety engineers and supervisors (if required) by Project
Management Team, or Gen. Con. Sponsored project safety seminars and
orientation. The company will bear the cost of said seminars of its employees as
a requirement on the project.

ACDC-MS-QAQC-001 Page 37 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

11. SAFETY TABLE OF ORGANIZATION AT SITE

PROJECT AGCHEM SAFETY


MANAGEMENT ORGANIZATION AT SITE
TEAM SAFETY
ORGANIZATION

AGCHEM
PROJECT MANAGER
SAFETY MANAGER

AGCHEM
SAFETY OFFICER

FOR IMPLEMENTATION
TO AGCHEM SITE
OPERATIONS

ACDC-MS-QAQC-001 Page 38 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

12. ENVIRONMENTAL PROTECTION MEASURES


Process Operation
Condition Control Condition for
Health and
Hazard Hazard and
Safety Non- Risk
Code Risk to
Hazards Routin Direc Indirec
routin Happen
e t t
e

Unavailability
of vehicles for
Manual lifting
hauling of BI
1 or hauling of     Pipes to the
Stress,
BI Pipes Injury
fabrication and
accessible area
for vehicles
lack of safety
Falling BI caution or
2 pipes during   danger which Injury,
installation tied around the
perimeter works

lack of safety
Expose from caution or skin
3 welding   danger which burned
flames tied around the out
perimeter works

Improper
Improper use coordination
with co- Fracture
4 of materials &    
workers. Not / Injury
equipment familiar to the
equipment.

Lack of
illness,
5 Over Fatigue     Manpower
injury
deploy at site

Untrained or Workers not illness,


6    
worker who Undergo EHS injury
did not Orientation.

ACDC-MS-QAQC-001 Page 39 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

Poor
coordination
with the
undergo EHS concerned
orientation personnel

Excess BI Pipes
not properly Stress,
7 Slip, trip  
arrange in the Injury
working area

Descriptions:

Daily activities
of equipment,
operations and
Routine processes

Planned
maintenance,
periodic or
emergency
shutdown,
Non-
process
routine
startup,
emergency
repair,
troubleshootin
g

Under direct
management
Direct control

Indirect No direct
management
control but has

ACDC-MS-QAQC-001 Page 40 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

influence (e.g.
supplier
activities)

13.Inspection and Test Plan

START

CONTRACTOR TO DO
ACDC-MS-QAQC-001 INSTALLATION WORKS Page 41 of 53
ACCORDING TO Rev 0 /24 JUL. 2020
APPROVE SUBMITTALS
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

CONTRACTOR TO
COMMIT INTERNAL
INSPECTION WITH
SMCC

YES
NO
ACCEPTABLE?

NO
APPROVED?

YES

DCI TO ISSUE APPROVED


COPY OF IWR TO END
14. CHECKLIST
CONTRACTOR

SPRINKLER HEADS INSTALLATION


COMPLIED? N/A REMARKS
CHECKLIST
YES NO
1. Check the sprinkler heads are installed as per

ACDC-MS-QAQC-001 Page 42 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

approved drawing.
2. Check temperature & type of sprinkler heads
as per approved submittal.
3. Check heads appears free of leakage and
damage.
4. Check heads free of paint.
5. Check heads are in appropriate position.
PIPE SLEEVING
A Pipe Blockout to Concrete Wall, Slab etc.
1. Reinforcement Supports with rebars & tie
wire are properly installed.
2.Covering Protection and Marking of blackout
are properly installed.
3. Installed blockout as per drawing.
4.Alignment orientation and elevation of
blockout
5. Blockout are properly supported prior to
concrete pouring.
SPRINKLER PIPING
A. Piping System
1. Ensure piping route/layout as per approved
drawing
2. Ensure pipe size and material complied with
the specification
3. Ensure pipe sleeves are installed on pipes
passing through wall/floor
4. Ensure pipe joints and fittings are properly
installed
5. Ensure pipes are installed level and plumb
6. Ensure hanger and supports size and spacing
is per project specifications.
7. Ensure fire stopping material applied between
pipe and sleeve
8. Ensure finished paint properly applied
9. Ensure piping system passed hydrostatic
pressure test
10. Ensure flushing and cleaning of piping
system performed and accepted
11. Ensure pipe identification and flow

ACDC-MS-QAQC-001 Page 43 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

directional arrows installed


12. Ensure valve tags installed
B. Sprinkler Specialty fittings
Ensure the following sprinkler specialty fittings
are approved product and properly
installed/connected to the system
1. Listed fire protection valves (ball, butterfly,
gate, globe and check valves)
2. Specialty valves and trim
2.1. Sprinkler system control valve
2.2. Main sprinkler check valve
2.3. Sprinkler test drain and alarm test fittings
2.4. Automatic drain valve
3. Sprinkler heads (concealed, pendent, sidewall
and upright)
4. Hose connection
5. Fire department connection
6. Tamper switches, Flow switches and bells
7. Water flow indicator
8. Valve supervisory switch
9. Pressure gage w/ calibrated sticker
10. Inspector test connection
FIRE PUMP SET
1. Check the entire pipe work carried out as per
approved drawing.

2. Check pipe supports and hangers are secured.


3. Check the pump unit is complete with all
accessories.
4. Check the check valve direction and confirm
the arrow shown as per direction of water flow.
5. Check pump properly secured & bolted on
foundation.
6. Check all bolts are tightening properly.
7. Check the Jockey Pump installation for the
piping & accessories are completed.
8. Check sensing Lines.
9. Check Controller Cable Insulation / continuity
Test.

ACDC-MS-QAQC-001 Page 44 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

10. Check all Electrical connections are


connected.
11. Check all valves are in position and have no
passing during the hydrotesting.
FIRE EXTINGUISHERS
1. Check the fire extinguisher size and type in
accordance with the approved drawing and
submittal.
2. Make sure the location is easily accessible and
in accordance with NFPA.
3. Check the bracket is properly installed.
4. Check the pressure & weight are normal.
5. Check the local seal and confirm if fully
operational.
PIPING LINES VALVES
A. Preplanning
1. Preplan the valve installation.
2. Perform required receiving inspection.
3. Check that valves are properly handled, stored
and maintained.
4. Check building areas for interference with
valves installation and operation.
5. Verify that valves are the correct size, type,
and pressure rating and are installed in their
correct location and orientation. (Read the
manufacture tags and not the vendors tags to
verify valves information.)
6. Perform req'd valves installation in-process
inspections.
7. Complete valve installation progress
reporting.
8. Perform periodic valve inventories and initiate
field purchases of valve if necessary.
9. Monitor P&ID deviations and obtain required
designs approval for changes.
10. Ensure that extra valve stem packing, bonnet
gaskets, pressure seals, plugs, and flange gaskets
needed for repairs are available.
11. Review piping design drawings and vendor

ACDC-MS-QAQC-001 Page 45 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

valve detail sheets for compatibility including


material and end preps.
12. Ensure required operating and setting
instructions and procedures are available.
13. Check that operating & setting activities are
performed per applicable instructions,
procedures and valve/operator manufacturer
instructions.
14. Ensure that changes which may results in
interference or which may cause delays are
coordinated with other disciplines.
B. Installations

1. Ensure that required exception reports are


prepared and processed.
2. Verify that required valve operator supports
are installed.
3. Make sure measures are taken to protect valve
bodies and internal form heat effect of welding.
C. Testing
1. Check valve pressures capacity and ensure it
is greater than the required piping pressure test.

15. WORK PERMIT

ACDC-MS-QAQC-001 Page 46 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

16.

ACDC-MS-QAQC-001 Page 47 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

ACTIVITY HAZARDS CONTROL MEASURE

ACDC-MS-QAQC-001 Page 48 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

1.Preparation  Caught in between  Proper handling of materials.


of B.I Pipes  Body Pain Use hand gloves
and Howling  Proper posture when lifting
2. Laying out  Eye and hand injury  Provide safety goggles and
and cutting of  Inhalation of fumes gloves
Pipes  Fire  Isolate the area
 Provide face mask
 Remove all combustible
materials
3.Installation  Slip/Trip  Isolate the area
of Pipes  Hand Injury  Remove all obstruction
 Proper PPE
4.Scaffoldings  Falling of materials  All scaffolding materials
 Fall of personnel should be inspected and
 Collapse of scaffolding approved.
 Improper access and  Inspection of all scaffolding
egress structure should be carried out
after each deconstruction of all
scaffoldings by a qualified
scaffolding inspector.
 Obtain scaffold construction
permit prior to start of work
 Ensure area barricaded to
prevent any unauthorized
personnel entry.
 All scaffoldings shall be
erected by qualified and
competent personnel under the
supervision of the gencon.
 No alteration of scaffolding
w/o permission from
scaffolding supervisor
 Scaffoldings must be fitted
with toe boards to prevent the
fall of materials and tools. All
tools and materials shall be
properly secured in the scaff
platform

ACDC-MS-QAQC-001 Page 49 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

 All personnel entering the


scaffolding must be physically
fit for the job and shall not be
afraid of heights.
 Personnel must wear full
safety harnesses while working
at heights. 100% tie-off shall
be maintained while working
at heights.
 Scaff tag should be available
on all scaffoldings

5.Working at  Fall from Heights  Any person working above 2m


heights  Unsafe Working height shall be considered as
platforms and working working at height.
conditions  Ensure all personnel assigned
 Unsafe access/egress to work at height are not afraid
 Hit by structure of height and medically fit for
height works.
 Work shall not be allowed to
be carried out standing over
wooden boxes; empty barrels
and other makeshift
arrangements,
 In case of any practical
difficulties to provide proper
working platforms, safety
harness with fall arrestors shall
be installed and used.
 Temporary edge protection
with top hand rails at a height
of 1.1m and mid rail at height
of 0.55, and with toe board
shall be installed in all around
the openings in floor slabs
 For small openings floor
covers shall be provided with
adequate strength
 Stop work at height in high

ACDC-MS-QAQC-001 Page 50 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

wind velocity. Homemade


ladders not to be used; Ladders
with broken rug not be used:
Placement of ladder to be in
proper securing position.
6.Grinding  Rotating equipment  Make sure guards are fitted to
sparks all moving parts
 Damaged grinding disc  Ensure proper use of guards
 Electrocution  Inspect the grinding discs prior
 High Pressure air to starting work (ring test)
 Eye injuries  Make sure that disc is
compatible with the grinding
machine
 Check the RPM of disc and
machine
 Proper PPE (Gloves, Mask and
Goggles)
 Only experienced personnel to
use the equipment.
 Wear a face shield while
grinding

7.Gas Cutting  Burns  Proper isolation of system


 Fire Hazard  All cylinders to be secured
 Explosion  Flame arrestor between the
 Tripping cylinder and torch
 Damaged or leaking  Hoses in good condition
cylinders or hoses  Proper PPE
 Fire extinguishers
 Fire Blanket
 Inspect the cylinders and hoses
before starting the job
8.Welding  Fire hazard  Before starting welding make
 Burns sure the area is clear of all
 Electrocution/Spatter types of combustible material
burns  Provide fire blanket on site
 Damage cable  Make sure fire extinguishers
 Hot tabs end pieces of are available on site

ACDC-MS-QAQC-001 Page 51 of 53
Rev 0 /24 JUL. 2020
Discipline:
FIRE PROTECTION PIPE WORKS
Project Name:
SOUTHERN STAR AEROPACK
PROJECT
Reference No.:

Document Tittle:
METHOD STATEMENT
FOR THE INSTALLATION WORKS OF FIRE PROTECTION SYSTEM

welding rods  Wear proper PPE for welding


 Sparking (leather jacket, Gloves,
 Damage cable welding goggles/welding
 UV rays mask)
 Gas Monitor correctly sited
 Certified equipment and to be
sited as near as possible to
work site.
 Proper earthing of equipment.
 Certified welder
 Make sure spark containment
is used such as welding
hood/fire blanket
 Ensure that rod holder is in
good condition
 Ensure that forwards and
return cables are in good
working condition
 Use proper cable connector for
extension
 If cables are crossing the road,
then ensure proper protection
 The welder and welder helpers
must wear welding goggles

ACDC-MS-QAQC-001 Page 52 of 53
Rev 0 /24 JUL. 2020