SATA IRRIGATION PROJECT

COMPUTATION OF PROJECT IRRIGATION WATER REQUIREMENTS

Project Irrigation efficiency 45%

Month J F M A M J J A S
P(mm) 15.1 66.3 137.0 129.3 174.4 214.3 175.5 89.9 165.2
ETo(mm) 117.8 121.4 139.5 132.0 127.1 105.0 105.4 99.2 93.0
Pe(mm) 14.7 59.3 107.0 102.6 125.7 140.8 126.2 77.0 121.5

Crop 1: Wet season maize (35 ha) 01 May - 31 August


kc 0.45 0.75 1.20 0.55
ETc(mm) 57.2 78.8 126.5 54.6
IR(mm) 0.0 0.0 0.3 0.0
IR(103m3) 0.00 0.00 0.10 0.00

Crop 2: Wet season pepper (40 ha) 01 May - 31 October


kc 0.75 0.75 1.10 1.10 1.10
ETc(mm) 95.3 78.8 115.9 109.1 102.3
IR(mm) 0.0 0.0 0.0 32.1 0.0
IR(103m3) 0.00 0.00 0.00 12.85 0.00

Crop 3: Dry season tomato (65 ha) 01 November - 31 March


kc 1.10 1.10 0.65
ETc(mm) 129.6 133.5 90.7
IR(mm) 114.9 74.2 0.0
IR(103m3) 74.67 48.26 0.00

Crop 4: All year sugarcane (20 ha) 01 September - 31 August


kc 1 1 1 1 1 1 1 0.9 0.3
ETc(mm) 117.8 121.4 139.5 132.0 127.1 105.0 105.4 89.3 27.9
IR(mm) 103.1 62.1 32.5 29.4 1.4 0.0 0.0 12.3 0.0
IR(103m3) 20.62 12.42 6.50 5.88 0.28 0.00 0.00 2.46 0.00

∑IR(103m3) 95.29 60.68 6.50 5.88 0.28 0.00 0.10 15.30 0.00
f 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
Q (l/s) 89.87 57.22 6.13 5.55 0.26 0.00 0.09 14.43 0.00
O N D Total
153.3 74.3 25.8 1420
108.5 111.0 99.2 1357
115.7 65.5 24.7 1081

0.10

0.85
92.2
0.0
0.00 12.85

0.75 0.75
83.3 74.4
17.8 49.7
11.54 32.31 166.77

0.5 0.7 0.9


54.3 77.7 89.3
0.0 12.2 64.6
0.00 2.44 12.92 63.51

0.00 13.98 45.22 243.23


1.1 1.1 1.1
0.00 13.18 42.65