1. Pre-shutdown checks
The following will be checked and recorded prior to the shutdown;
Check double insulated bearings;
Recurring problems and discrepancies review;
Present annunciator drops; and
Operating data;
5. Inspection
All results will be recorded on standard inspection forms
Visually inspect/ clean
i. Bearings;
ii. Oil deflectors
iii. Hydrogen seals;
iv. Coolers;
v. Generator field; and
vi. Stator windings;
6. Electrical tests
a) Stator
i. 10-minute insulation resistance with polarization index;
ii. Winding copper resistance;
iii. RTD resistance check and insulation resistance; and
iv. DC leakage;
b) Field:
i. 10-minute insulation resistance with polarization index;
ii. Winding copper resistance; and
iii. AC impedance test;
9. Assemble generator
Install stator cooler heads;
Generator field;
Hydrogen seals;
Bearings;
Oil deflectors;
End shields; and
Collector brush rigging;
10.Assemble lagging
Upper end shield lagging; and
Stator cooler dome lagging