PROYEK : FIRE PROTECTION SBE PLANT PT.

KUTAI REFINERY NUSANTARA - BALIKPAPAN


LAPORAN HARIAN
PEMBERI TUGAS KONTRAKTOR
HARI : Rabu
TANGGAL : 23 November 2022
No. MANPOWER JUMLAH PEKERJAAN VOLUME SAT

1 Project Manager 0 1. Pemasangaan pipa 6" bagian belakang bundwall area SBE 920 cm
2 Supervisor 1 2. Instal pipa 6" 4 batang area SBE
3 QC 1
4 HSE 1
5 Mandor 1
6 Fitter 2
7 Welder 1
8 Helper 3
9 Civil 1
TOTAL 11
INSTRUKSI/CATATAN SUPERVISOR :
Mengetahui : PT. CITRA AQILA PROTEKSI
C = CERAH G = GERIMIS H = HUJAN
NAMA : MULYONO
06.00 - 07.00 C 18.00 - 19.00 C JABATAN : SUVERVISOR
07.00 - 08.00 C 19.00 - 20.00 C TANDA TANGAN :
08.00 - 09.00 C 20.00 - 21.00 C
09.00 - 10.00 C 21.00 - 22.00 C
10.00 - 11.00 C 22.00 - 23.00 C
11.00 - 12.10 C 23.00- 24.00 C Dibuat Oleh
12.00 - 13.00 C 00.00 - 01.00 C NAMA : AYUNI
13.00 - 14.00 C 01.00 - 02.00 C JABATAN : HSE
14.00 - 15.00 C 02.00 - 03.00 C TANDA TANGAN :
15.00 - 16.00 C 03.00 - 04.00 C
16.20 - 17.00 C 04.00 - 05.00 C
17.00 - 18.00 C 05.00 - 06.00 C
DOKUMENTASI

Pemasangaan pipa 6" bagian belakang bundwall area SBE

Install pipa 6" 4 batang area SBE