PROJECT REPORT

OF
PIPE LINE WORK , LEVLLING WOORK
Mr. APPASO MARUTI AWATI
AT GAT NO : 1858 &2346 ,A/P BEDAG TAL: MIRAJ DIST :
SANGLI
OMKAR D. PATIL
B.E.(CIVIL)

GOVT. ENGINEER , CONTRACTOR & VALUATOR

AT /PO SANGLI , Tq : MIRAJ . Dist : SANGLI

MOB : 08668680181

INTRODUCTION

Mr. APPASO MARUTI AWATI

AT GAT NO : 1858 &2346 ,A/P BEDAG TAL: MIRAJ DIST : SANGLI

is want install pipe line in His own farm located in bedag Tal: miraj ,Dist : Sangli

for the purpose of cultivations of various traditional crops . ex grapes and sugarcane

he has good knowledge farming and cash crops , due to lack of water system he facing some issue
related with farming so she decided to install his own pipeline through 2 boar wells to well and from
well to land and leveling of land .

Name – Mr. APPASO MARUTI AWATI

Address- AT GAT NO : 1858 &2346 ,A/P BEDAG TAL: MIRAJ DIST : SANGLI

Now he required loan facility from bank of Rs. 941,540.25

If he get finance from bank he will easily achieve the target as per enclosed projection.

I t is assumed that entre amount of term loan is utilized throught the year
OMKAR D. PATIL
B.E.(CIVIL)

GOVT. ENGINEER , CONTRACTOR & VALUATOR

AT /PO SANGLI , Tq : MIRAJ . Dist : SANGLI

MOB : 08668680181

Name of applicant : Mr. APPASO MARUTI AWATI

Age of applicant : 60 years

Gender : male

Address- AT GAT NO : 1858 &2346 ,A/P BEDAG TAL: MIRAJ DIST : SANGLI

Mobile no : 9112626767
OMKAR D. PATIL
B.E.(CIVIL)

GOVT. ENGINEER , CONTRACTOR & VALUATOR

AT /PO SANGLI , Tq : MIRAJ . Dist : SANGLI

MOB : 08668680181

NAME OF THE WORK : PIPE LINE WORK & LEVLLING WORK AT GAT NO : 1858
&2346 BEDAG TAL: MIRAJ DIST : SANGLI

NAME OF THE OWNER : Mr. APPASO MARUTI AWATI

TOTAL COMMAND AREA : 1 ACRES OF GRAPES & 2ACRS OF SUGAR CANE

ESTIMATED COST : Rs 941,540.25 ONLY

IN WORDS : NINE LAKH FORTY ONE THOUSAND FIVE HUNDRED FORTY RUPEES
& TWENTY FIVE PAISA ONLY
OMKAR D. PATIL
B.E.(CIVIL)

GOVT. ENGINEER , CONTRACTOR & VALUATOR

AT /PO SANGLI , Tq : MIRAJ . Dist : SANGLI

MOB : 08668680181

1. SAILENT FEATURES

Name of work : PIPE LINE WORK & LEVLLING WORK AT GAT NO : 1858 &2346 BEDAG TAL:
MIRAJ DIST : SANGLI

Source of water : WELL & BOAR WELL

Toluka : MIRAJ

District: Sangli

Location and approach by road: BEDAG – NAGARGUJE ROAD

Nearest Railway station: Miraj

Discharge available : GOOD

Area under command : 3 ACRS

Cropping pattern :

a) Khariff : 1 ACRS

b) Rabbi : 2 ACRS

Discharge required : 5.23 LPS

Diameter of pipe : 100 mm ( 4 inch ) pipe

Design discharge considered for H.P cal. : 5.23 LPS


CALCULATION OF PIPE DIAMETER

1. Area to be irrigated : 3 acre


2. Discharge required : 0.30 Cusec
3. Assume velocity of water 1 mtr /Sec
= 3.28 mtr / Sec

Discharge = Area x Velocity

Q = 0.78 D2 x 3.281

𝟎.𝟑𝟎
D =
𝟑.𝟐𝟖𝟏 𝒙 𝟎.𝟕𝟖𝟓

D2 = 0.11

D = 0.34 feet

Say 4” inches

So provide 4” dia. (100 mm) P.V.C pipe for rising main line.
HORSE POWER CALCULATION

1. Full supply level : RL. 75m.

2. Low water level : RL. 48m.

3. Length of rising main : 2087 m.

4. Discharge : 5.23 L.P.S.

5. Diameter of pipe : 100 mm.

6. Head calculation :

a) Static head : Full supply level - low water


R.L 75 - R.L 48
= 27 mtr.
b) Frictional loss ( hf ) :
Using Haxen Willims flow formula to time of out the frictional
loss with c-150 and v= 1m/sec.
i.e V = 0.85 x (R)0.63 x (S)0.54 where (R=d/4)
315
= 0.85 x 150 x x (S)0.54 (S = frictional loss .)
4

S =31.66 x 10-3 / mtr.

Total frictional head = (ht) = total length x S


= 2087 x 31.66 x 10-3
= 66.07 mtr.
c) Add 10% for bend valve etc , i.e = 6.6 mtr .
Total head = static head + frictional head + losses Due to bend
valve etc
= 27m. + 66.07m. +6.6 m.
= 99.67 m.
Say 100 m.

𝑄 𝑥 𝐷𝑦𝑛𝑎𝑚𝑖𝑐 ℎ𝑒𝑎𝑑
H.P = 75 𝑥 0.75

5.23 𝑥 100
H.P = (efficiency = 0.75%)
75 𝑥 0.75

= 9.3 H.P
Say 10 H.P

Providing one unit of 2 units of 5 H.P . With suitable centrifugal monoblock


pump sets.
FOR nourishing all crops at same time
Abstract for pipeline work & leveling work
SHEDULE OF ITEMS CIVIL WORK

No Item Quantity Per Rate Amount Remark

1. Cleaning of site from


farm to intech
structure LUMSUM 30,000.00
Including removing
of small plants ,
bushes and other
major obstructions
etc all
2. Excavation in all
type of soil except
rock including
shoring strutting 945.000 Cu.M 185.00 174,825.00
dewatering i.e.
swelling the bottom
disposing of surplus
earth up to a distance
of 100 m etc all
3. Laying of UPVC
100mm pipes with
necessary joints 1300.000 M. 300.00 390,000.00
valves and other
accessories wherever
required etc all
4. Pump set for
pumping water from
river to destiny , 2 unit 18,500.00 37,000.00
kirloskar 5 H.P three
phase monoblock
pump ,KDS-1030
5. Backfilling of
excavated trench
with previously
excavated soil 1363.000 Cu.M 110.00 149,930.00
including spreading
watering leveling
and compaction etc
all
6. Leveling open land
Including cutting 1210 Cu.M 95 114,950.00
filling of rock and
soil at defined R.L
6. Add 5% contenginency and other charges
44,835.25 -

TOTAL 941,540.25

IN WORDS: NINE LAKHS FORTY ONE THOUSAND AND FIVE HUNDRED FORTY RUPEES

& TWENTY FIVE PAISA ONLY..