Professional Documents
Culture Documents
Email: support@elecosoft.com
http://support.elecosoft.com
Email: training@elecosoft.com
Whilst every effort has been made to ensure complete and accurate information of the
contents in this documentation, Elecosoft UK Ltd cannot be legally responsible for errors and
omissions, or damages or loss of equipment or information caused as a result of the
documentation.
No part of this documentation may be reproduced by any means or stored in any form without
express permission from Elecosoft UK Ltd.
Contents
Course Objectives ...............................................................................................................3
S-Curve set up .....................................................................................................................4
Activity days cost centre set up ....................................................................................................................... 4
Column set up ................................................................................................................................................. 4
Filter for tasks only .......................................................................................................................................... 6
Task per line mode .......................................................................................................................................... 7
Adding the activity day units to the tasks ........................................................................................................ 8
Baselines .............................................................................................................................9
Creating baselines .......................................................................................................................................... 9
Changing the appearance of baseline tasks ................................................................................................. 11
Showing/hiding a baseline ............................................................................................................................ 12
Merging a baseline ........................................................................................................................................ 12
Reverting to a baseline ................................................................................................................................. 14
Progressing the Project....................................................................................................15
Working with Multiple Progress Periods ....................................................................................................... 15
Updating Progress using Multiple Progress Periods .................................................................................... 16
The Progress Cycle ...................................................................................................................................... 18
Displaying specific progress periods in the bar chart ................................................................................... 19
Progress Options .......................................................................................................................................... 19
Using Overall % Complete to update progress ............................................................................................................ 19
Progress Entry Mode ................................................................................................................................................... 20
Snapping ...................................................................................................................................................................... 21
Overall % Complete weighting ..................................................................................................................................... 21
Using Duration % Complete to update progress .......................................................................................................... 22
Reporting Progress in the Spreadsheet ........................................................................................................ 23
Displaying Progress Data for specific progress periods ............................................................................................... 23
Displaying Planned v Actual data in the spreadsheet .................................................................................................. 25
Recording a large volume of notes............................................................................................................................... 26
Jagged Progress View .................................................................................................................................. 27
S-Curve Reporting ............................................................................................................29
Adding Grid lines ........................................................................................................................................... 30
Exporting S-Curves to Excel ......................................................................................................................... 31
S-Curve reporting with the EVA Reporter ..................................................................................................... 32
Running the graph with the EVA Reporter .................................................................................................... 33
S-Curve Graph .............................................................................................................................................. 36
The Variance Table ....................................................................................................................................... 37
ASAP v ALAP S-Curves in Powerproject .......................................................................38
Setting your ASAP v ALAP data ................................................................................................................... 38
Creating an ASAP v ALAP S-Curve .............................................................................................................. 39
Showing Performance in a Table .....................................................................................40
Glossary.............................................................................................................................43
Exercise 1 ..........................................................................................................................46
Exercise 2 ..........................................................................................................................47
Exercise 3 ..........................................................................................................................48
Exercise 4 ..........................................................................................................................49
Progress Analysis and S-Curve Reporting – What Next? .............................................50
Course Objectives
Please feel free to add any notes you feel are relevant.
S-Curve set up
To enable progress reporting using S-Curves in Powerproject, activities must first be loaded with the
relevant measurement units. In the example below we will be loading our tasks with an “Activity Days” unit,
which is added to the task as a cost. The cost added will match the task duration
e.g. a 10 day task will have a value of £10. This will allow us to plot our s-curve according to the planned
and actual durations.
Column set up
Once the cost centre has been set up, add the activity day units to your tasks. The easiest way to do this is
via the spreadsheet.
Click Close
Right Click on your Duration column and select Format Cells...
Under the Number tab select Duration in the Category section
Change the Duration Format to “Decimal (4d, 4.4w)”:
Click Close
Filter for tasks only
To stop the potential double count that would occur in programmes which have summary bars and
expanded tasks, activity days should be assigned only to the tasks.
To ensure this run a filter which hides the summary bars and expanded tasks before assigning the units.
A box pops up showing all available filters. Choose the ‘Tasks only’ filter:
Click OK
The project is displayed without milestones, summary bars or expanded tasks.
Before:
After:
Or:
If there are numerous occurrences of multiple tasks per line, the Bar chart can be formatted so that all tasks
are displayed on separate lines
On the left hand side, tick the box for Task per line mode and click Close:
If task names have not been given to all tasks on the line the name column could appear empty.
On the Format tab, switch off the Cost Allocation bars icon
Un-tick the Task per line mode option in Format Bar Chart
Turn off the Task Only filter
Save the Table if necessary
The durations of each task are copied to the Activity Days cost centre, which can now be graphed for an S-
Curve.
Baselines
Baselines are created to record the project at a particular point in time (e.g. for recording the contract
programme), this allows current information to be compared with contract/planned information. A baseline is
a record of all or any part of a project including bars, tasks, links, resource/cost allocations, libraries,
histograms and annotations. Creating a baseline allows forecasting using what if scenarios and can be
useful with claim situations
Creating baselines
On the ribbon click the Project tab and select Baseline Manager
Click New on the top right hand side:
The Baseline Wizard box will pop up. Enter a name for the baseline and a description if required,
e.g. Target Programme or Contract Programme
Click Next. The Destination screen is displayed. To savethe baseline in another location to the
directory that has been specified, click Browse. If it is not changed the baseline will be stored in the
same location as the live project
Change the file name for the baseline by deleting the assigned file name and retyping.
Click Next to continue onto the Scope screen. Choose ‘All tasks in the current view’ (If at the top
level of a project this will include any tasks held within expanded tasks or sub charts (N.B.
Alternatively, you can choose to baseline a selection of task from a programme)
Click Next to continue to the Summary screen. Check the information is correct and click Finish. If
not, click Back to make the changes
Live task
Baseline
Notice the
variance
between the
live tasks
and the
baseline
now
Showing/hiding a baseline
Click on the Format tab on the ribbon
Click the drop down box marked as Baselines
Un-tick the baseline that you do not want to be displayed
Merging a baseline
Once a baseline has been created a function is available that will allows extra data to be merged into that
baseline. For example, additional works that should form part of the contract programme.
• Add new data and edit existing data –the baseline will appear under new tasks and will be move
position to match the new position of existing data
• Full update – as above plus any tasks deleted from the programme are also deleted from the baseline
The baseline will be updated to record the changes made to the project
Reverting to a baseline
When planning a project, several ‘what if’ scenarios of the project may be created & baselined. To adopt
one of these scenarios as the project plan, the project can be ‘Reverted’ or changed back to be like that
baselined version of the project.
In the right hand pane, double click on the default ‘Project Report Date’.
Rename it to Week 1; choose a date 1 week into your project.
Edit the Vertical Progress style (Drop down line colour) and Fill Style (Progress colour on task) if
desired
Note that the time of the date defaults to 00:00 (midnight). Therefore, to set a report date at the end of
the working day Friday, change the time or choose the next day at 00:00 to ensure that Friday’s work is
included.
Select Close
Right click in the space below Week 1 and select ‘New Progress Period’
Name it ‘Week 2’ then press Enter on your keyboard
The date of week 2 has defaulted to 7 days after week 1 and the next colour has been selected.
Press Enter
If creating a new table, the following columns could be added to the default table.
Before entering progress, ensure progress is being recorded against the correct progress period. The
current ‘Progress Entry Date’ is shown in the Progress section on the Home Tab.
The first time progress is entered, the earliest date will be set as the progress
report date. In subsequent weeks, change this by editing the drop down in the
Progress section of the home tab
The progress line will appear on the bar chart from the report date and ‘jag’ around to the the left hand side
of any uncompleted tasks
4. Enter Progress
Enter the required progress into the ‘Overall Percent Complete’ column to progress the tasks.
Tasks are shaded along their duration to indicate the progress entered.
5. Reschedule
To see the effects of the progress entered, reschedule Powerproject to straighten the progress line and
move any uncompleted tasks to the right of the report date. This will display any variance against our
baseline.
Select Reschedule
When rescheduling a project with multiple progress periods, the report dates are listed in the Straighten
Progress Period drop down list. Select to reschedule to a specific period or select the ‘Progress entry
period’ to use the current period selected on the Home tab.
The progress line will straighten and the uncompleted section of the project will move to the right of the
report date.
Before After
7. Baseline
After each progress period, a record of the projects progress can be kept by taking another baseline of the
current project dates.
1. Baseline
2. Display
Progress Table
7. Capture delay
reasons
3. Display the
progress line
6. Reschedule
4. Set progress
entry period
5. Enter your
progress
It is also possible to display more than one progress period line or display a line that is not the current
progress period
Progress Options
Using Overall % Complete to update progress
Percentage (%) progress on tasks may be considered in terms of the % of the tasks duration that is
complete or the % of work that is complete, regardless of the duration of the task.
When using Overall Percent Complete to apply progress the % entered will remain the same even if the
overall duration of the task changes. If using a duration Percent Complete the % entered will always be
expressed in relation to the duration of the task & will change if the remaining duration changes.
When entering progress, it is important to consider the options available that can affect how progress is
applied to tasks.
The tasks Actual Duration has been updated in step with the progress % entered so 2d 4h shows as
completed. The progress line shows as ‘jagged’.
A reschedule to straighten the progress line splits the task & moves the remaining duration to the next
working date.
The tasks Actual Duration has been updated up to the progress line, showing that we have spent 1 week
(5d) working on the task but we are only 50% complete.
The remaining duration is calculated based on 50% of the original planned duration, which means the task
duration has changed to 1w 2.5 days.
Snapping
When using Overall % Complete, the Actual duration can snap to the nearest time unit (e.g. Days). If
this is not ticked, the actual duration will be calculated exactly as per the % progress entered (e.g. 5
day task with 50% done will leave 2d 4h remaining. If snapping to the nearest day it will read 3d
remaining)
With Snapping
Without Snapping
By default, all tasks are equally weighted, so, when each task is completed an equal amount is shown to
be progressed.
In the example below you will see a summary bar with 4 tasks. Task One is 1 day long, Tasks Two, Three
and Four are all 1 week long.
When Task One is complete, the summary bar shows 25% complete. This is because currently all the tasks
within the summary have an equal weighting, regardless of duration.
You can choose to manually weight the activities by adding an Overall Percent Complete Weighting Field
which will allow you to decide the weighting for each task or to weight each task automatically by right
clicking on the summary bar and selecting Calculate Task Weightings:
Once this has been done the summary bar will show the percentage complete based on the duration of
each task, rather than it’s weighting:
This will change the ribbon, Object-Edit toolbar and ‘Percent Complete’ field to use a duration-based
measure. The Percent Complete field can be used instead of Overall Percent Complete in your spreadsheet
columns.
Your spreadsheet will show the specific progress percentages you have entered in each week
notice the figures are not cumulative. To show the cumulative % Complete of a task at a specific
progress period use the ‘Overall Percent Complete’ field and in the Attributes section tick the option for
cumulative
In this example, a table is created to show planned and actual start and finish dates of the tasks in a project
The table displays Start, Finish and Actual Start & Actual Finish columns
The Table Definition dialogue appears. Change the ‘Start’ column title to ‘Planned Start’.
Rename the ‘Finish’ column title to ‘Planned Finish’.
Change these columns look at the Current Baseline instead of the Live data as shown below
If you have a large amount to document in the Notes column of a task, you will notice the column width will
increase accordingly to display them all:
Notes can also be entered directly into the properties of a task using the Bar & Task Properties Pane
Select the ‘Toggle Properties View’ icon at the bottom left hand side of the Powerproject, screen
1) A ‘straight line’ version that has been rescheduled and shows all remaining work in the future. This
type of ‘As-Built’ progress report shows any variance against a baseline & potentially a different
projected end date for the project.
2) A ‘jagged line’ version of the project that shows the tasks in their original contract position but easily
indicates if the project progress is ahead or behind for the current date by the direction of the progress
line.
To satisfy both these requirements a ‘Jagged Progress View’ is available. This uses the baseline positions
of tasks & displays the current live progress values onto these baseline tasks.
This means that an accurate ‘Straight line’ programme can be maintained whilst at any time viewing a
‘jagged line report’ with progress to date displayed on the tasks in their original planned positions.
st
It is necessary to have 1 taken a
baseline to use this feature
Straight-line programme
This programme has been rescheduled after each weekly progress report. The progress line is straight, all
remaining work pushed to the right. The baseline is on display to show the variance against the Original
Plan.
The tasks are shown in their original positions. The line is jagged to show that we are behind. The shading
shows the progress entered each week.
‘Actual’ & ‘Variance’ data is shown in the table even though the tasks are in the original planned positions.
In Jagged Progress view, the smaller ‘baseline’ tasks shown below the main task (in yellow above) actually
show the live task positions. These can be hidden from display by formatting the Bar Chart
S-Curve Reporting
An s-curve can be produced in Powerproject to display the planned v actual position of progressed tasks.
This will work by plotting the position of the tasks using the Activty units which were loaded at the beginning
of the notes.
When the Histogram properties box pops up give it a name and set the Clipboard unit to Elapsed
Days
To display a legend select the Format Histogram button, Row tab and tick Legends
To save this View with the histogram displayed go to View tab > View > Save As then name the
view “S-Curve view”
Right click in the date zone area above the bar chart
Select Grids
Click Add
On the new line which appears type a name in the Name cell
Leave the Interval as 1
Left click on Elapsed Week and change to Variable Date
Left click on the thin black line and change the line style to match that of your progress line (make the
width about 900)
Next, left click in the Variable date space and then select (click to select variable date):
Choose where to save the Excel file, what to call it and use the supplied excel template S- Curve.xlt
Click on OK
Open your Excel file and select the Graph tab from the bottom:
EVA Reporter takes a more global and cumulative view of the progress status and compares this to the
position that should have been achieved when compared to a baseline (history) of the project. This
allows a statement to be made such as if a project is 5% behind schedule that overall this represents 11-
working days.
EVA Reporter takes the percent complete (technically the Overall Percent Complete) and applies this to
the baseline task’s duration (cost or effort) to find how much that task contributes to the cumulative total for
a particular Progress Period.
So EVA Reporter is not graphing the actual values, but the earned values of activity days, cost or effort.
You can run the graph by clicking on the EVA Reporter button on the project ribbon:
Click Next:
Duration - This option will produce a graph based on the number of planned Activity Days (from the
baseline), plotted by date against the number of earned Activity Days for each progress period
Costs - This option will produce a graph based on the cost of planned tasks (from the baseline),
plotted by date against the earned cost for each progress period. Cost assigned to Summary,
Expanded and Hammock tasks are not included
Resource Effort - This option will produce a graph based on the man-days of planned tasks (from
the resources assigned to baselined tasks), plotted by date against the earned man-days for each
progress period. Resources assigned to Summary, Expanded and Hammock tasks are not included
OPC Weighting – This will work in a similar way to ‘Duration’, however the Overall Percent Complete
weighting of each task is taken into account on the planned duration (from the baseline)
Click Next:
This allows you to use S-Curve progress monitoring for code library entries assigned to your tasks,
e.g. you want to produce an S-Curve to show progress for a particular sub contractor you have assigned to
your tasks
If the Report by code library is un-ticked then all tasks in the project are examined
If the Report by code library is ticked and you choose one or more code library entries then a
separate Worksheet (and graph) will be produced for each selected code library entry
Click Next
It is fundamental to the working of the EVA Reporter that a baseline is selected. If you do not have a
baseline then the EVA Reporter will not operate.
Select the baseline that you want your live project to be compared against from the drop-down list of
baselines in the project
You can select more than one baseline and if the location of tasks within
each baseline is different you will have an envelope to compare to, rather
than a single line.
This is often used to compare the project’s progress compared to the As-
Soon-As-Possible (ASAP) position of tasks in the
baseline and the As-Late-As-Possible (ALAP) position of tasks in the baseline.
If you require a graph line for future tasks then ensure there is a tick in the Show Forecast Line
option. If you do, the Options settings will be applied automatically (see the installation instructions
document via our website (http://support.powerproject.com/ for more information)
If the Show Forecast Line option is un-ticked then the graph will not take into account any tasks that
are not yet progressed
Click Next:
Current View – only those tasks shown in the bar chart whose scope is set via the Project View and
which may be filtered are included in the report. The contents of Summary, Expanded or Hammock
tasks which are not expanded are not included
Branch – only those tasks shown in the bar chart whose scope is set via the Project View
Project – the whole of the file open in Powerproject will be graphed
All Marked as Projects – only those tasks (at any level) contained in Expanded or Summary tasks
which has “Is A Project” set will be included in the report. This option is used for Enterprise Projects
which are a Portfolio of Projects contained within one file
Click Next:
Click the Finish button and the indicators and Message panel will show the progress of the EVA
Reporter being processed
If any errors are produced you will be warned at the end of processing
Click OK and Excel will be opened up automatically with the graphed results
S-Curve Graph
The graph line from completed tasks ends at the final Progress Period date
The value of this line compared to the graph line from the baseline tasks, shows how far
ahead/behind you are in both a percentage of the overall project (or No activity days) and a number
of working days (elapsed days are also possible and this takes into account weekends and holidays)
To keep a copy of this graph for future reference you will need to ‘Save as’. The graph is up- dated
each time it is run.
Then tick the box for ‘Create a graph of Variance by progress period’:
Click Close (circled above) and click Next to choose your graph options as mentioned in the
Running the graph with the EVA Reporter section above
This allows the trend for the progress of the work over an extended period.
In the example, below the work was falling further and further behind schedule every week until some
remedial action was taken at Week 39 and from that time on the work has started to catch up and the trend
of the project is in the right direction:
Select all tasks and right click on one of them and select Properties
Select the Task tab, Constraints and under Placement click on the drop down arrow and choose
ALAP
Click Close
When the Histogram properties box pops up give it a name, with clipboard unit set to Elapsed Days
To reveal the legends, select the Format Histogram button, Row tab and tick Legends
To save this as a Histogram View go to View tab > View > Save As > e.g. “ASAP ALAP S-Curve
view”
Add Fields for Earned Value; Planned Value & Schedule Performance Index to your spreadsheet
from the Earned Value category
In the table definition select the Earned Value field and make changes as follows:
Select View tab > Table > Save As > “Efficiency Table”
Glossary
Allocation
This is the name given to any Permanent resource, Consumable resource or Cost Centre that may be
assigned to a Task. It can be shown on the Bar Chart underneath the task
Bar
Horizontal area, identified by a line number; includes information in the Spreadsheet and one or more
Tasks on the Bar Chart.
Bar Chart
The area of the screen where Tasks are displayed graphically.
Baseline
A copy of the project recorded at a single point in time. Powerproject can record and display multiple
baselines allowing for tracking of major changes; production of what-if scenarios; comparison of
information (e.g. budget cost to actual cost)
Border File
A print function which contains information to be included around your project when printed. A border can
include graphics such as company logo & project information such as the project title and relevant dates.
Buffer
A Task that is used to collect Float and protect the Critical Path through the project. It achieves this by
having a duration which increases or decreases in response to project
Code (Colour)
A facility to allow the assignment of colours to tasks to represent information about the task.
Code Library
This is the library (or folder) that contains Codes, allowing you to have multiple ‘categories’ of codes
Constraint (Flags)
These are used to enforce dates when a Task can happen outside of the logic defined by the links.
(stopping a task starting before a certain date, or stopping a task finishing after a certain date). Using
Constraint Flags within the project can have a major effect on your Critical Path
Consumable Resource
This is a resource that once used, no longer exists to be used again (e.g. materials)
Cost Centre
These are items that represent the costs you wish to record in a project (e.g. Labour, materials, plant ) They
are used to assign costs to Tasks either directly or indirectly via Cost and Income Rates on a Permanent
resource. Cost Centers can be used to represent money coming in to the project (Income) aswell as
money leaving the project
Critical Path
This is the sequence of tasks though a project whose duration affects the project end date & the overall
project duration. If any of the Tasks on the critical path are changed the end date of the project will change.
It is shown as a red outline on Tasks and as red Links.
Date Zero
Date Zero is the point where the elapsed week ruler in the Date Zone starts counting. By default set to be
at the start of the project, but can be moved without affecting the project
Date Zone
This is the area above your project that contains rulers of information (e.g. Elapsed week numbers, week
start).
Exceptions
These are time periods that are different to the usual work pattern. e.g. holidays, working etc.
Expanded Task
This type of task is similar to a Summary Task in that it is used to group together Tasks within the project.
Unlike a Summary Task, the content is held off the main chart in its own Sub Chart.
Filter
This is a tool that will leave on screen only those items that meet a particular criteria, for example all the
items that a particular contractor is doing (Code based filtering) or everything happening during a 6 week
period (time based filtering) even to show only those items that have been completed (Progress based
filtering)
Float
This appears on items that are not on the Critical Path. Float is the amount of time a Task may be delayed
or extended before the item re-joins the critical path and pushes out the end date of the project.
Free Float
Free float means that if the task is extended or delayed in anyway during its period of float only this item is
affected, nothing else will move.
Lag (Links)
A Link that has a delay at its start or finish end. Usually used at the start end of a link to allow a period of
waiting time before the successor task. It is shown as the horizontal part on a Link (e.g. Concrete curing
time, paint drying time or just delivery times).
Library Explorer
An area that allows you to navigate all of the folders of items used in your project. (Cost Centres,
Calendars, Codes, Permanent Resources etc.) Some library items are displayed in the Project View others
can only be viewed & edited from the Library explorer (e.g. Exceptions, Link Categories, and Currency)
Link
The relationship between two tasks, displayed as an arrow. If shown in red then the link is Critical.
Milestones
Milestones are points in time; they have no duration of their own (0 days) and are used to represent key
events within projects (e.g. handover)
Permanent Resource
This is a resource that once used, remains to be used again. (e.g. People, machinery)
Progress (Period)
The progress report date; the date at which progress is updated to the project. Can be displayed as a line
going down the screen that will bend to the left to show items behind time and bend to the right to show
items ahead of time.
Project View
The white window that opens on the left hand side of the screen. Used to navigate around the project and to
view & assign items into the project like Code Libraries, Cost Centres, Permanent Resources,
Consumable Resources and Calendars.
Sort
To Re-order the project according to a set of criteria. E.g. the project tasks could group together all the
tasks according to the code that has been assigned to them.
Spreadsheet (Table)
This is the yellow and white stripped table down the left hand side of the screen (assuming the Project View
is closed) The Spreadsheet is made up of different columns which contain data fields. Columns can be
removed, added and moved within a table.
Summary
This type of task groups together Tasks on screen. The tasks can be rolled up & hidden so only the
summary is shown. Items are grouped because they share certain information, for example, summaries
could be used to group together all the Tasks on different floors. A Summary could also be used to show
different phases or stages within a project. Multiple summaries can be placed inside of each other allowing
a project structure or hierarchy to be created.
Task
The activities that appear within a Bar on the Bar Chart and represent project work to be completed.
Task Pool
A series of Tasks that are saved to be re used. Useful if the same sequence of tasks is repeated regularly.
The Task Pools are displayed in the project view.
Template
A template is a project file that is used when creating a new project. A Template typically contain items
needed in all new projects i.e. Calendars, Permanent Resources, Cost Centres, Code Libraries, Task
Pools.
Total Float
Total float means that if the task is extended or delayed during its period of float, then all items directly after
it (those containing Float) will also be affected.
UDF
A User Defined Field. The software already has a large range of data fields that can be used. UDF’s are
created by the user for additional reporting needs e.g. to record notes or have a tick box to indicate whether
an H&S check has been completed.
View
A view is the method used for the software to remember screen settings. When saved the
‘View’ will remember if the Project View is opened or closed, it will remember the current column
configuration within the Spreadsheet. It will also remember the current settings of the Bar Chart, the Date
Zone and finally whether there are any Filters or Sorts running within the program. Putting all of this
together a view is the ability to change all of these settings to a predefined set by only doing one click of the
mouse. The software can have unlimited number of views saved.
Exercise 1
Open the Shed Build project
• Add a Cost column in the existing table so that you now have Line, Name, Duration, Start, Finish
and Cost columns
Format Cells
• On the Duration column right click and select Format Cells > Number tab > Duration
o Click on the drop down arrow under Duration Format
o Select (Decimal 4d, 4.4w)
o Un-tick the “Export time unit” box
o OK
• Right click on Programme in the project view and choose Select and Filter > All Levels
• From the pop up box which appears, select the ‘Tasks Only’ filter
• Remember to select ‘Task per line mode’ by right clicking in the bar chart > Format Bar Chart >
General tab > tick ‘Task per line mode’
• Right click on the Duration column header and copy it
• Right click on the Activity Days column and paste the data
• Go to View > Filter > No Filter
• Right click the Duration column header > Table Definition > change the ‘Overide time unit’
back to ‘Week’ > Close
• Right click the Duration column header again > Format Cells > Duration tab > Duration section
> change the Duration Format back to ‘<Default>’
Select View tab > Table > Save As and call it “Activity Days Table”
Exercise 2
• Create 4 progress periods in the Library Explorer for the next 4 weeks starting with the end of the
first week of your project
• Save
Name
Duration
Planned Start
Actual Start (Date category)
Planned Finish
Actual Finish (Date category)
Planned Percent Complete (Progress category)
Overall Percent Complete (Progress category)
Finish Variance (Date category)
Notes (Identification category)
• Remember to go into Table Definition and point the following columns to the correct data source:
• Save this table by selecting the View tab > Table > Save As and call it Progress Table
• Against Week 1, apply 20% of progress on the first task, showing the drop line for this week
Exercise 3
Open the Shed Build project
Exercise 4
Open the Shed Build project
This should give you 4 colours across your tasks to denote the 4 progress periods
• Open the “Training S-Curve” histogram for the ‘Activity Days’ cost centre that you created
earlier (it will have been saved from the last time you created it) Look at your progress S-Curve
histogram now with more progress on the project
• Run the EVA Reporter for Duration and looking at the “Shed Build Target
Programme” baseline
2. Find out your Serial Number and write it here. You’ll need this should you have to call our
Helpdesk
3. Use your serial number to create a login to the Customer Support Portal at
http://support.elecosoft.com for access to FAQ’s, advice & the latest software releases.
Support lapsed?
A current support contract provides unlimited access to our Helpdesk & access to the latest
software releases via our Online Support Portal.