The document summarizes the radio system architecture for phases 4A and 4B of a metro line project. Phase 4A includes 4 underground stations and 2 above-ground stations, with base transceiver stations (BTS) installed at two underground stations and one above-ground station. Leaky cable and antenna systems will provide coverage. Phase 4B includes 4 above-ground stations and a workshop, with BTSs at two stations and the workshop, and antennas installed. Repeater systems will provide redundancy for both phases.
The document summarizes the radio system architecture for phases 4A and 4B of a metro line project. Phase 4A includes 4 underground stations and 2 above-ground stations, with base transceiver stations (BTS) installed at two underground stations and one above-ground station. Leaky cable and antenna systems will provide coverage. Phase 4B includes 4 above-ground stations and a workshop, with BTSs at two stations and the workshop, and antennas installed. Repeater systems will provide redundancy for both phases.
The document summarizes the radio system architecture for phases 4A and 4B of a metro line project. Phase 4A includes 4 underground stations and 2 above-ground stations, with base transceiver stations (BTS) installed at two underground stations and one above-ground station. Leaky cable and antenna systems will provide coverage. Phase 4B includes 4 above-ground stations and a workshop, with BTSs at two stations and the workshop, and antennas installed. Repeater systems will provide redundancy for both phases.
RADIO SYSTEM ARCHITECTURE FOR PHASE 4A & 4B STATIONS
Phase 4a stations are composed of 2 types of stations:
1- Stations under ground
It will follow the same way of deployment done in previous phases of Metro line 3 project. There are 4 underground stations of a distance around 3.6 Km. 2 BTSs will be installed at Heliopolis and El Shams stations. Radiating system will be through Leaky cable system. 2- Stations over ground There are 2 over ground stations of a distance around 2 Km 1 BTS will be installed at Hesham Barakat station 3 Antenna system will be installed as shown in the figure below
3- Repeating system will be installed also to insure double coverage in each
location of the track and public areas. 4- The following figure shows the deployment for the Phase 4 A of the project
5- For phase 4B stations there will be the following:
4 over ground stations of a distance around 5Km and workshop 2 BTSs will be installed at Omar Ebn ElKatab and Adly Mansour stations and workshop Antenna system will be installed. Repeater system will be used to ensure the redundancy of the coverage.
6- The following figure shows the deployment for the Phase 4 B of the project
7- The following figure shows the deployment of all Phase 4 stations .
8- It is needed one pair of frequency for each BTS and one for each Repeater, as shown in the overall figure below. 9- The following table explains the locations needed for each Antenna
Station LOT Top of No. Of
name station Latitude Longitude Antennas (m) 28 +55.479 30.12825909 31.36076920000005 2 EL NOZHA HISHAM 32 +59.982 30.13113105 31.373912750000045 2 BARAKAT 34 +64.484 30.1345496 31.383941359999994 2 QUBAA 36 +67.852 30.14008728 31.393880330000002 2 Omer Khatab 38 +79.045 30.14386033 31.40694136000002 2 HYKSTEP ADLY 40 +82. 528 30.1472759 31.42225719999999 2 MANSOUR End of +50 30.12590644 31.349546000000032 1 tunnel Workshop +80 30.14548417 31.423120460000064 2