You are on page 1of 7

See

discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/4078178

750 kV reactive power control, automatic


reclosing and overvoltage protection

Conference Paper · July 2003


DOI: 10.1109/PTC.2003.1304292 · Source: IEEE Xplore

CITATIONS READS

3 52

3 authors, including:

L. Prikler
Budapest University of Technology and Economics
18 PUBLICATIONS 127 CITATIONS

SEE PROFILE

All content following this page was uploaded by L. Prikler on 16 October 2014.

The user has requested enhancement of the downloaded file.


Paper accepted for presentation at 2003 IEEE Bologna Power Tech Conference, June 23th-26th, Bologna, Italy

750 kV Reactive Power Control, Automatic


Reclosing and Overvoltage Protection
G. BÁN, Fellow, IEEE L. PRIKLER, Member, IEEE G. BÁNFAI, Member, IEEE
Budapest University of Technology and Economics

Abstract - The paper reports on studies, which supported the Fig. 1 shows the scheme of the overvoltage protection of the
projecting, reconstruction and modification of a 750 kV, 479 Albertirsa substation. Conventional silicon carbide arresters
km long transmission line. The changes were demanded by the with passive gaps served for the limitation of overvoltage
technical development and the alteration of the role of the line protection in both ends of the line. Arresters A2 protected
in the power transmission. Authors analyse various ways for
the shunt reactors, while A1 the transformer. Being the ratio
influencing on the interaction of the reactive power control,
relaying and overvoltage protection. The possibility of the of the protecting level of conventional arresters to the rated
operation with incomplete, asymmetrical shunt reactor and voltage quite large, a high shunt compensation degree was
arrester sets is investigated. The paper describes a simple way required to keep the temporary overvoltages below the
of controlled three-phase and adaptive single-phase reclosure. permitted level.

Keywords: automatic reclosing, controlled switching, EHV


transmission, metal oxide arrester, overvoltage protection,
power systems transients, shunt compensation.
I. INTRODUCTION
A 479 km long 750 kV transmission line was put into
exploitation between Hungary and Ukraine in 1979 in order
to create a strong connection between the Hungarian power
system and the Russian-Ukrainian EHV grid. The line was The initial overvoltage protection of Albertirsa substation.
planned for the transmission of nearly 2000 MW active
power. A reconstruction was effectuated in the Hungarian Fig. 1.
750 kV substation (Albertirsa) in the middle of the eighties,
based on the experiences of the initial operation. The 750 On the other hand, high shunt compensation is not
kV line was put out of operation in 1993 due to the political economical when transmitting high power. To solve this
and economical changes. After a long interruption the line problem, shunt reactor circuit breakers have been equipped
has restarted to operate in spring of 2002. The present with air gaps G (see Fig. 1) that had to connect the
system configuration significantly differs from the old one: temporarily disconnected shunt reactors to the line
the supply system in the Ukrainian side became weaker and automatically, when overvoltages arose. The breakdown
the transmitted power lower. The line construction and the voltage of the gap was between 1.4 p.u. and 1.8 p.u. It was
substation equipments have been modified to some extent. supposed, that the steep front wave initiated by the
The new situation necessitated a revision of controlling the breakdown of the gap, travelling along the long shunt
reactive power, the overvoltage protection and the efficiency reactor - gap bus and finally being reflected at the reactor
of reclosing automation. The paper reports on the studies, will result in a transient voltage peak exceeding the SI
which preceded and prepared the above-mentioned protecting level of the arrester (2.1 p.u.). According this idea
modifications. this overvoltage protection scheme accelerates the operation
of arresters: the 2.1 p.u. arrester operates as soon as the
II. INITIAL YEARS: INTERACTION OF overvoltage reaches 1.6 p.u., i.e. at 76% percent of its 2.1
THE REACTIVE POWER CONTROL, p.u. protecting level. It was taught, that such a co-operation
RELAY PROTECTION AND of the gap, the long bus and arrester provides the line
INSULATION CO-ORDINATION insulation with a favourable protection.
Two shunt reactor sets serve for controlling the reactive
power on both ends of the line. The neutrals of the shunt Air blast circuit breakers CB1 and CB2 served for
reactor sets were earthed in the original plan. Since the 750 connecting and disconnecting the shunt reactors. They
kV transmission has been effectuated by means of a single demanded a frequent maintenance, moreover produced
circuit line, single phase reclosing plays a cardinal role in numerous restrikes and high voltage peaks at switching off
the relay protection. On the other hand TNA studies and the shunt reactors. Both restrikes and current chopping
field tests showed, that the self-extinction time of the overvoltages could be responsible for the failures occurred
secondary arc could exceed the dead time of single phase in the shunt reactor windings.
reclosing automation, which was limited by stability
conditions. Therefore both shunt reactor sets in Albertirsa Fig. 2 shows the phase voltages at the shunt reactor and the
and one of the sets in the Ukrainian substation were enlarged record of the multiple restrike. The reduced
provided with neutral reactors. Namely, there is a possibility amplitude of the voltage oscillation following the
to suppress the secondary arc current and reduce the disconnection refers to an arrester operation initiated by
duration of arcing by means of neutral coils of suitable relatively high current chopping.
selected inductance.

0-7803-7967-5/03/$17.00 ©2003 IEEE


advantage offered by MOAs in another way. The insulation
of the line and the substation corresponds to the protective
level of the conventional arresters. So MOA with special
parameters was selected: its level of protection was only
slightly lower than that of the conventional arrester, but its
permissible 1s TOV level was 1.7 p.u. (1.4 p.u. for the
conventional arrester). The high permissible value of the
rated voltage made unnecessary high shunt compensation
during arrester operation.
Multiple restrike and arrester operation produced by air blast circuit breaker
at shunt reactor switching off.
Fig. 2. The completed protection in Albertirsa substation rendered
unnecessary to accelerate the operation of shunt reactor
III. RECONSTRUCTION IN THE MIDDLE arresters. The cooperation of the conventional SiC arresters
OF THE EIGHTIES with metal oxide ones, moreover the co-ordination of the
The air blast shunt reactor circuit breakers have been different overvoltage protection philosophies at the
replaced by SF6 ones that were suitable for controlled Hungarian and the Ukrainian line ends were checked as
switching off operation. The distance between the contacts well.
of the new circuit breakers reached the value necessary to IV. RESTARTING THE OPERATION OF
the arc extinction within 10 ms. The way of controlling, THE LINE
elaborated by the authors, effectuated the possible shortest
arcing time at every disconnection. This minimized the A. Overvoltages
erosion of the contacts and reduced the probability of
current chopping. To check the efficiency of controlling, 50 An isolated part of the Ukrainian network supplies the line
tests have been carried out without controlling the new provisionally. Both temporary and transient overvoltages
circuit breakers and in 90% restrikes were experienced. On have increased due to the weak supply system in comparison
the other hand, no restrike was recorded during numerous with the normal operation for which the transmission was
tests carried out with controlled switching off. Thus, planned originally. Overvoltage studies showed, that this
restrikes have been completely eliminated by controlling the growth of the overvoltage level could be compensated in the
disconnecting operation of the new circuit breakers. Shunt majority of cases by keeping the lowest permissible level of
reactors were used for reactive power control of the the operating voltage.
Hungarian 400 kV system between 1993 and 2002, so a 17
years positive experience is available with controlled Considering the nine years interval of being out of operation
operation of the shunt reactors. No shunt reactor failures one had to suppose, that the state of certain substation
occurred since starting the controlled switching off. components would not meet the reliability requirements
temporarily. The conditions of operation with incomplete
The construction of the new breakers precluded the shunt reactor and arrester sets were elaborated in order to
possibility of connecting an air gap in parallel with one of take precautions against the temporary single-phase lack of
the interrupting units. The lack of the gaps has been such apparatuses. The investigation extended to the
compensated by a metal oxide arrester (MOA) set, accidental asymmetries in the Ukrainian substation as well,
connected directly to the line (see Fig. 3). taking into account various rates of the coincidence of
unexpected events. From this viewpoint the former
completion of the overvoltage protection with a MOA set in
Albertirsa substation proved favorable. The operation of the
convential arresters is not endangered by an asymmetry in
one of the reactor sets because the same circuit breaker
connects the reactor and its arrester to the line.
Consequently, the arrester of a disconnected reactor is
separated from the line as well.
The overvoltage protection in Albertirsa substation after the reconstruction. These studies aimed the improvement of the reliability of
Fig. 3.
the line for the further stage of the operation.
MOAs have a favourable feature among others: the ratio of
B. Single phase reclosing
the protective level to the rated voltage is smaller for a
MOV than a silicon carbide arrester. This offers a way for
reducing the protective level of the arrester, i.e. the stress of A basic tool of the reliable operation of the single circuit
the insulation. Besides this ratio depends on the duration of 750 kV line is single phase reclosing of high efficiency.
temporary overveoltage (TOV) stressing theMOA. Disregarding permanent faults, the successfulness of
Consequently, it can be decreased when taking into account reclosing is endangered by long duration secondary arcs.
the real operation time of the relay protection. So replacing The high current fault arc (primary arc) drops after the
the SiC arresters by MOAs renders possible to reduce the moment of tripping the faulty phase conductor and a
requirements against the insulation. secondary arc arises in the hot plasma left by the primary
one.
However, for keeping TOV below the limit permissible for The secondary arc is sustained by the capacitive and
conventional shunt reactor arresters one had to push the inductive coupling with the healthy phases. Its current
depends mainly on the phase-to-phase capacitance, thus the peak value of the phase voltage. By inserting neutral coils
line length. Generally high secondary currents lead to long between the shunt reactor neutral and the ground, Cab can be
duration secondary arcs. compensated partly or completely.

Uc ~
Cab
L* 2Cab
Ub ~
Cab
~
Ua ~ -Ua/2 A
Co Is K Ls
L** Co
N
Ln

a. b.
C0 – zero sequence capacitance of the line; Ls – resultant inductance of the
reactors
Ln – the inductance of the neutral coil; Is – secondary arc current
Ls L2 **
L* = 3 + s L = Ls+3Ln.
2 2 Ln
Scheme (a) and simplified circuit (b) for understanding the effect of neutral
reactors.
a. 750 kV b. 400 kV
Secondary arcing on 750 kV and 400 kV transmission line Fig. 6.
Fig. 4.
The circuit in Fig. 6 explains the condition of compensation.
Figures 4a, and 4b. illustrate the formation of the secondary If L* controlled by the neutral inductance and 2Cab form a
arc. Fig. 4a was recorded during a staged fault in the 750 kV resonant circuit resonating to the power frequency, no
line. This figure shows the initial interval of the primary arc secondary arc current and recovery voltage occur.
when the flashover is just developing along the insulator
surface and also the secondary one. Thus the arcs in Fig.4a To find the optimal neutral inductance to minimize the
are not synchronous. Figure 4b was recorded during a field secondary current, a detailed study is needed. The optimum
test in a 400 kV double circuit line, when the secondary arc value of Ln depends on the actual compensation degree that
was initiated by a thin wire, without primary arc. has to be adapted to the actual value of the transmitted
power.
The secondary arc is sustained by the capacitive and
inductive coupling with the healthy phases. Its current The inductance of the neutral coils in Albertirsa has been
depends mainly on the phase-to-phase capacitance, thus the selected in the eighties supposing that every shunt reactor
line length. Generally high secondary currents lead to long set on both line ends will have a neutral coil. In the present
duration secondary arcs. situation only in Albertirsa substation are neutral reactors in
operation, so the secondary current is not suppressed
In any case, the extinction of the secondary arc is preceded sufficiently. This imperfection is partly compensated by
and prepared by an intermittent interval, consisting of high operating the line on the lowest permitted voltage level: 700
current impulses followed by temporary dropping the kV rms. In the most dangerous case (a single incomplete
restrikes. So mainly the intermittent arcing process shunt reactor set in Albertirsa and one or two complete sets
determines the duration of the secondary arc. in the Ukrainian substation) the expectable peak value of the
continuous secondary current reaches 68 Amps. According
to the international statistics of self-extinction times [6] this
value corresponds to 1.45 s self extinction duration. The
permitted maximum dead time for the investigated 750 kV
transmission is 1.6 s. One has to consider the high amplitude
of the recovery voltage due to the shunt compensation and
the fact that the dead time has to be longer, than the sum of
time delay of tripping the faulty phase and the self-
extinction time. Thus the reserve time does not seem to be
sufficient.
.
Secondary arcing. To eliminate the danger of inefficient single phase reclosing,
Upper curve: arc voltage in the intermittent interval. a variant of adaptive reclosing has been elaborated and
Lower curve: the fault current and secondary one during single phase
reclosing in the 750 kV line. proposed for the detection of the actual extinction time. The
Fig. 5. detection is based on the transients taking place in the
intermittent interval of secondary arcing. In this period arc
Secondary arc in long EHV transmission line may be of re-ignitions and extinctions follow each other. Every re-
long duration first of all due to its large Cab. Besides, when ignition and extinction initiates subsequent reflections of
shunt reactors are connected to the line, a recovery voltage steep front waves in the tripped phase conductor.
of beating character occurs at the faulty spot following the
secondary current impulse. Its amplitude can exceed the
1.20
*10 6
The device that detects the final extinction of the secondary
0.76 arc may be utilized in the following ways:
• It effectuates reclosing after detecting the final
0.32 extinction. The dead time is not a constant value.
• Average secondary arc duration is taken as constant
-0.12 dead time. If the secondary arc duration exceeds the
adjusted value, the device elongates the dead time by a
-0.56
pre-determined Δt or prevents it.

-1.00
C. Three-phase reclosing
0.110 0.115 0.120 0.125 0.130 0.135 [s ] 0.140
(file veiporto2new.pl4; x -var t) v:CA c: -XX0014 v:A A
Three-phase reclosure of shunt compensated lines produces
Transients in the faulty phase after a re-strike.
Upper curves: voltages in the line ends. the highest switching overvoltages and the heaviest stresses
Lower curve: the current of the re-strike. in arresters, since the trapped charge in the healthy phases of
Fig. 7. a shunt compensated line is of beating character due to the
transients in the line mode and ground one.
The fundamental harmonic of the extinction transient Three-phase reclosing endangers mainly those lines, which
depends on the line length only (see Fig 7), while that of the contain polluted or foggy zones. Contamination usually
breakdown transient is highly influenced by the location of extends to a large area, where the line insulation is reduced
the fault, Consequently, the detection of the final extinction during foggy weather. It is presumable, that an intensive
has been based on sensing the presence of the intermittent partial arc activity is going along the surface of many line
extinction transients by means of special filters on the line insulators, when one of them flashes over stressed by the
ends. As long as the intermittent secondary arc exists, a high operating voltage. As a rule, the heating effect of the
voltage occurs on the outputs of the filters primary arc dries the faulted insulator, but a high reclosing
350
[kV]
overvoltage is able to initiate partial arcs on some other
insulators. These arcs may be much longer, than they could
250
be at the operating voltage. The temporary overvoltage
following the reclosing transient and then the operating
150 voltage may sustain and elongate the long partial arcs till
occurring the full flashover. This hypothesis is supported by
50 [5], which reports on ''records of failures to reclose having
contamination flashovers and also many examples of
-50 successful reclosing followed by a subsequent flashover''.
The same tendencies show the data about the efficiency of
-150 reclosing Hungarian HV and EHV lines for a four-years
0.20 0.25 0.30 0.35 0.40 0.45 [s ] 0.50
period 1984 - 1988.
Detection of the final extinction in a 400 kV line
Summer Winter
Upper curve: the output voltage of the filter
Lower curve: recovery voltage at the fault Voltage unsucc success unsuccess length
successful
Fig. 8. level essful ful ful (km)
750 kV 5 0 1 2 479
Dropping this output voltage near to zero indicates the final
400 kV 48 20 28 9 1530
extinction of the secondary arc (see Fig.8. A device
operating according the described principle has been 220 kV 83 28 23 47 1687
constructed and tested on 750 kV and 400 kV lines. Fig. 9
120 kV 2437 65 501 177 7039
shows a record about its operation when a single-phase- to-
ground fault turned into a two-phase-to-ground fault (750 ∑ 2573 113 553 235 10733
kV transmission line). Table I

The ratio of the summarized unsuccessful reclosing to the


successful is 0.044 in summer and 0.425 in winter.
Transmission line faults originate mainly from lightning in
summer and predominantly from foggy weather in winter.
Considering, that the unsuccessful/successful ratio in winter
reaches a nearly 10 time higher value, than in summer, a
significant limitation of the reclosing overvoltages is
recommended for the lines containing polluted or foggy
sections to prevent unsuccessful reclosing.

The voltage difference across circuit breaker contacts (∆U)


in the dead time contains power frequency, line mode
Upper curves: phase voltages; lover curve: signal for permission of frequency and ground mode frequency components. The
reclosing.
Fig. 9.
amplitude of ∆U may exceed the double the phase voltage.
Highest overvoltage arises, when reclosing at the maximum Comparing the amplitudes of ∆U minima in Figs. 10 and 11
∆U. one it is evident, that the case with four neutral coils (Fig.
10) is more favourable, then the real configuration (Fig. 11).
Controlled reclosure proves to be advantageous to avoid Nevertheless looking at the curves in Fig.11, one finds
overstresses. The mechanical operation accuracy of the air suitable minimum intervals in which the reclosure would
blast circuit breakers of the 750 kV transmission did not result in relatively low three-phase reclosing overvoltages in
prove satisfactory for precise controlling (as point of wave the healthy phases. Thus 0.6 s is recommended as the most
or polarity control). A simple and efficient way of reasonable dead time.
controlling the reclosure has been elaborated that does not
require a very precise operation of the line circuit breakers. 1.5

The idea is based on the relatively long periods of the [MV]


1.0
beating minima that offer a possibility for controlled
reclosing. It seems to be reasonable to reclose in one of the 0.5
minimum intervals, i.e. to take the dead time duration for an
integral multiple of the beating period of ∆U. The time 0.0

locations of ∆U minima usually are not simultaneous in the


-0.5
individual phases and depend on the kind of the fault. When
selecting the value of the neutral coil according to the -1.0
equation Ln= Ls*Cab/C0 the capacitive coupling between the
phase conductors ceases during the dead time and the -1.5
0.0 0.2 0.4 0.6 0.8 1.0
[s ]
location in time of ∆U minima becomes constant: Fig. 11
simultaneous an independent on the kind of the fault [4].
According to Fig. 8 one can find suitable minimum intervals
Being the symmetry of the investigated 750 kV line not in which the reclosure results in relatively low overvoltages
perfect (the causes of that will be analyzed in the next in the healthy phases. Thus 0.6 s dead time is recommended.
chapter), the location in time of ∆U minima would not
completely simultaneous even if every shunt reactor set
would be provided by neutral coils. Fig.10. involves ∆U V. THE METHODS OF THE
voltages in the healthy phases for single-phase-to-ground INVESTIGATION
and two-phase-to-ground faults with the supposition that
each reactor sets are four legged ones. Transient network analyser (TNA) of the Budapest
1 .5
[M V ]
University of Technology and Economics served as the
1 .0 main tool before and during the commissioning the line and
substation in the seventies. A sophisticated line model
0 .5
formed the fundamental component of the TNA, that was
0 .0 verified by numerous field tests. Later 750 kV transients’
- 0 .5
studies were carried out by means of a coordinated
application of TNA and the Electromagnetic Transient
- 1 .0
Program (EMTP). In the nineties a complete changeover to
- 1 .5 EMTP has been realized. Transformers and components of
0 .0 0 .2 0 .4 0 .6 0 .8 [s ] 1 .0
supplying systems were often simulated by lumped
Fig. 10. parameter models in the former studies. The recent 750 kV
simulation considers every component as a distributed one
The possibility of utilizing the favourable effect of the and the 750 kV tansformer models are highly sophisticated.
neutral coils for controlling the 750 kV line circuit breakers The architecture of the model used for the recent studies is
in the present configuration, the time position of ∆U minima shown in Fig. 12. The Hungarian substation Albertirsa
has been studied for the case, when only in Albertirsa (AISA) and the simulation of the Hungarian system are in
substation are neutral coils. the left side.
Fig. 11 involves ∆U voltages in the healthy phases for
single-phase-to-ground and two-phase-to-ground faults.

EMTP simulation of the 750 kV transmission.


Fig. 12.
The real line shows various asymmetries. The tower
constructions of the Ukrainian and the Hungarian part are
not the same. Therefore the longitudinal symmetry is not
perfect. Besides, one of the ground wires has replaced by
OPGW conductor in the Hungarian side before restarting the
operation of the line and the OPGW ground wire has been
earthed at every tower. The earthing of the other,
conventional ground wire has been effectuated only in the
substations and at the state border, corresponding to the
original design. All the asymmetries have been taken in
account in the system simulation shown in Fig. 10.

VI. CONCLUSIONS
The application of metal oxide arresters of special
characteristics significantly weakens the strong connection
between the degree of shunt compensation, the relay and
overvoltage protection.
The efficiency of single-phase reclosing can be improved by
a simple variant of detecting the secondary arc extinction
time.
Using the effect of four legged shunt reactors on the
capacitive coupling between phase conductors, a cheap
method of controlled three-phase reclosing can be
effectuated for older types of circuit breakers as well.
Controlled disconnecting offers an efficient protection for
shunt reactor insulation.

VII. ACKNOWLEDGEMENT

The activity reported in the paper has been partly supported


by the Hungarian Research Fund under contract No. OTKA
T-035178.

VIII. REFERENCES

[1] Akopyan, A.A. et al.: “Switching Overvoltages and the System of


Protection against them in 750 kV Networks of the USSR” CIGRE,
1972. Rep. 33-07
[2] Benko, I. Ban,G., Banfai, G.: "Interaction of the Reactive Power
Compensation and the Insulation Coordination at a 75O kV Power
Transmission" CIGRÉ 199O Rep. 33-2O1.
[3] Prikler, L., Ban,G. Banfai,G.: ''EMTP Models for Simulation of
Shunt Reactor Switching Transients'' Electrical Power & Energy
Systems, Vol.19, No.4. pp. 235-240, 1997.
[4] Ban, G., Prikler, L., Said, A.R.:: “Use of Neutral Reactors for
Improving the Successfulness of three Phase Reclosing” Proc. of
IEEE Power Tech’99 Budapest, 1999
[5] Kawai, M.'' Research at Project UHV on the Performance of
Contaminated Insulators Part I. Basic Problems''. IEEE PAS vol.
PAS-92, 1973. pp.1102-1110
[6] Rashkes, V.S.: “Generalization of the Operation Experiences
Connected with the Efficiency of Single-Phase Reclosing,
Experimental Data about the Extinction Time of the Secondary
Arc” Elektricheskie Stancii 1989 No. 3. (in Russian)

View publication stats

You might also like