Professional Documents
Culture Documents
References
13.1.1 Introduction
This section addresses the requirements of pressurised spaces which are used as a means
of escape, with particular reference to:
• air tightness of the protected routes;
• sizing and the selection of fans;
• testing and commissioning of the air distribution system;
• provision for lifts.
These regulations only apply in the UK although the physical principles will apply elsewhere.
Part B of the Building Regulations3 require fire escape routes (staircases, lobbies or
corridors), to be naturally ventilated to reduce the density of smoke in the event of a fire.
Natural ventilation is not always possible and options exist for pressurising escape and
firefighting stairs by the introduction of mechanical ventilation.
The use of pressurisation will also give a greater degree of confidence that the escape route
can be used for extended periods. This may be necessary in tall buildings when a
considerable amount of time is needed to descend the escape stairway.
In essence, the design of staircase pressurisation is straightforward. However, the somewhat
involved nature of BS 5588: Parts 4 and 51,2 can lead to considerable confusion. This section
of the guide aims to provide a basic explanation of the British Standard and simple guidelines
to avoid difficulties that can be experienced in achieving design requirements.
13.1.2 Principles
Pressurisation is not designed to completely oppose smoke flow, but is generally effective
during occupants escape, and for firefighters familiar with the hazards of smoke filled rooms
on fire.The principles involved in stair pressurisation are simple. The relevant British Standard
for pressurisation is BS 5588 Part 41 and Part 52, which gives general information and design
guidance. This section of the Guide should be read in conjunction with these parts of BS
5588.
The aim is to flood the staircase/lobby with fresh uncontaminated air thus limiting the amount
of smoke entering escape routes. Air from supply fans will maintain a static pressure across a
closed door between the stair/lobby and room, or will provide a flow of air to oppose smoke
ingress if the door is open.
There are two options for the supply air system. The simplest is to supply all the required air,
only during a fire condition, upon a suitable alarm, and is known as single stage. Alternatively,
the fans can operate in two stages. Under normal conditions the fans run at a reduced
volume, the higher volume being used during a fire condition triggered by an alarm. The two-
stage system might be employed where the first stage provides the normal ventilation for the
stair, with suitable fans provided for the higher duty. Either system is acceptable.
Once the decision to pressurise has been taken there are three basic arrangements for
pressurising one or more elements in an escape route, and these are summarised in the
Table 13.1.1.
There is no requirement to pressurise a simple lobby. (A simple lobby being defined as a
lobby with no toilets or lifts opening on to it).
A fire lobby on a fire fighting stair is defined differently and can include toilets. Generally,
lobbies should not contain or give access to plant rooms not associated with the fire fighting
stair.
Method 1
• The corridor pressure must be less than or equal to that of the lobby though not more than
5 Pa below with doors closed.
• Self closing doors to accommodation units are required.
Method 3
The majority of situations would utilise stair and lobby, or just stair pressurisation. Stair and
lobby pressurisation is preferred as the pressure drop caused by doors to the stair opening on
other floors will have a lesser effect on the lobby pressure at the fire floor.
A pressurised space will force smoke away from it, therefore the smoke should not be allowed
to spread into a naturally ventilated escape route.
There will be no adverse interactions of the pressurised cores if:
(a) pressurised spaces are separated by large unpressurised spaces, eg open plan offices,
courtyards, etc.
(b) all staircases and lobbies (where appropriate) are pressurised.
The important issue here is to avoid disturbing the trend of keeping smoke away from the
escape routes. Normally the air conditioning system will shut down on fire alarm. Two-stage
systems or smoke extraction using the air conditioning or ventilation system will require
special consideration at the design stage. Air conditioning or ventilation extract equipment
used for smoke exhaust may also require special treatment:
(1) All supply air should be stopped first, prior to operation.
(2) Extract ducts may have to be fire rated.
Extract fans may require fire rated motors.
The required pressure differentials are shown in Table 13.1.2. These are maintained across
doors, taking account of leakage paths. The leakage path is characterised by an effective
area “AE” which is calculated by identifying all complete leakage routes via doors and
windows to outside.
Table 13.1.2. Required pressure differentials
Pressurisation level (Pa)
Emergency
Building Height Reduced operation for stage 1 of a two stage system
Operation
Up to 12m or below
50* 8
ground
Above 12m 50 15
Principal leakage paths and design allowances are shown in Fig 13.1.1. Detailed examples
are given in BS 5588: Part 4 Annex H The actual leakage rate may not be easily calculated at
scheme design stage, (windows, etc. will not have been specified), but an assessment should
be made in case relief vents are needed. The provision of pressure relief vents is discussed
later.
Leakage
Figure 13.1.1
Usually the worst case design condition for modern double glazed buildings is the egress
velocity, quoted at an “open door” from the lobby or stair to the room. This condition is
particularly dominant with firefighting shafts. If the building is less than 10 storeys this
calculation is usually best done first when determining riser space.Supply ducts should
branch into the lobby at every floor and into the stair at every fourth floor.
Figure 13.1.2
BS 5588: Part 4 requires egress velocities of between 0.5 and 0.75 m/s dependant upon the
stair/lobby arrangement, eg staircase only is pressurised, staircase and lobby independently
pressurised etc. The alternatives available and their consequences are shown in Fig.13.1.3.
Figure 13.1.3
For a quick assessment the maximum likely requirement for a single stair door leading to a
single lobby door measuring 2m x 0.8m is given as follows:
Using 0.5 m/s the flowrate would be 0.8 m3/s. This is only valid for buildings with up to 20
storeys. Above this two doors on different floors must be considered.
To account for inadequate venting from the room the actual volume is assumed to be lower
than that calculated. The required volume is then derived by dividing the calculated volume by
0.6, i.e. for the above examples this would give a revised flow rate of 2.0m3/s. Double doors
have greater leakage but only one leaf is assumed to be open when calculating egress
velocities.
The provision noted under the calculations for leakage in the BS, (which suggests adding
50% to the design flowrate), do not apply to the “open door” calculations. However, when
specifying fans they should be selected with a view to having to increase the flowrates to
meet site conditions, i.e. leaky shafts and doors. It is not uncommon with the more ‘leaky’
forms of construction (eg dry lining) for the actual volume flow for pressurisation to be
substantially greater than that predicted in design. It is important to be aware of the
construction characteristics and provide an appropriate allowance on fan duty.
BS 5588: Part 5 (see Fig. 13.1.2) requires an egress velocity of 2 m/s at the fire floor and also
at the fire service access level. The resulting flow rates are usually quite large compared with
other areas, as indeed are the flowrates if natural ventilation is used. Typically 10 to 11 m3/s
would be required! Where fire fighting lifts are provided the shaft is pressurised but lobby
pressurisation is not mandatory.
Section 13.1.5 gives an allowance in the design calculation for inadequate venting of
pressurisation air, this however does not remove the requirement to provide a path for the air
to leave the building.
There are four methods for dispersing the air which flows on to any given floor from a
pressurised stair or lobby. Venting should, if possible, be uniformly distributed on each side of
the floor to minimise wind effects.
(a) discount the largest side of the building to allow for adverse wind effects.
(b) Special vents: in a “sealed” area provision of vents to outside. The area of the vent in
m2 is given by QN/2.5 (m2) - see clause BS 5588: Part 4: 14.3.2 on discount one side of the
building to allow for adverse wind effects.
(c) Vertical shafts: similar to B above but use : Area = QN/2.5 (m2) - read clause BS
5588: Part 4:
(d) Mechanical extract: extract rate should be greater than QN - ensure no spread of
smoke - read clause BS 5588: Part 4:
QN is the net volume flow rate into the floor (excluding toilets etc.) and should be
based on open-door conditions.
High velocity systems are common to reduce space requirements. Energy and noise are of
secondary importance since the system is operated only during an emergency. Conventional
ductwork of the appropriate classification may be used. All normal rules of design apply, see
also section 10. In addition the following points should be considered:
• Ductwork should be leak tested and an allowance for leakage should be added to the
design volume (if leakage is outside the pressurised space). Tests should be carried out in
accordance with DW142/143.
• Velocities can be high during operation. Correspondingly duct pressures can be high and
balancing dampers should be of a robust quality capable of withstanding high pressures, and
provide good regulating control. Simple butterfly dampers or opposed blade dampers behind
grilles are generally inadequate.
• Flexible or bendable ducts should not be used as they can come adrift with high velocities
and pressures.
• Fans and motors should be generously selected in the sense that they should have plenty
of scope for upgrading or downgrading their duty to allow for actual site conditions during
testing and commissioning. The electrical supply and switchgear should accommodate this
requirement.
• BS 5588: Part 4, suggests 50% should be added to the design volume for ‘uncertainties’
and ‘unidentified’ leakage. Uncertainties is one thing, unidentified is another. All potential
leakage paths should be identified and allowances made for them. Classic examples would
be service penetrations and where fittings go into walls, eg dry riser boxes, hose reel
cabinets, water drinking points, etc.
• Although these systems are essentially used in an emergency, noise should still be
considered; they should not be so noisy that people cannot communicate in escape routes
whilst evacuating the building. Grille exit velocities should not exceed noise levels of NR50.
Usual good air distribution design should be adhered to.
• Equipment should be protected from fire.
• Electrical supplies should be maintained either from an essential distribution board or an
alternative emergency stand-by generator.
• Adequate redundancy should be built in:
- If only 1 staircase or a firefighting shaft then duplicate fan/motor sets should be
provided.
- If more than 1 staircase then dual motors only are needed
• Avoid fire dampers in any pressurisation duct as they are unlikely to operate, failure could
prevent the necessary airflow reaching the designated space.
• Systems should be actuated by detectors/sprinklers/ manual call, and provided with
separate isolating switches.
• Air intakes on the mechanical ventilation plant should be carefully positioned to avoid
bringing smoke from a fire back into the building.
• Sometimes pressure stabilisers are necessary to satisfy all the design criteria,
(particularly fire fighting shafts) and offer a safety factor in design.
• The use of variable volume fans based on presssure sensors in the stair/lobby are
particularly useful for fire fighting shafts.
13.1.9 Lifts
Lifts and pressurised spaces pose a different set of problems. If a lift is contained in a space
which requires pressurisation, it is essential to liase with the lift engineer and be mindful of
possible leakage paths. There are a number of issues which need to be considered:
• BS 5588 Part 4: 14.2.4 will provide guidance on lift doors; they are a major source of
leakage and a specified rate would be advantageous. It is possible to have brush seals fitted
on some lift doors which will restrict the passage of air.
• Smoke seals should not be fitted to lift doors in firefighting shafts.
• The main source of air leakage is the lift shaft itself; on high rise buildings the stack effect
may intensify the leakage rate. Apart from the regulatory 0.1m2 of vent area at the top of the
shaft, mentioned specifically in the BS, there are many other air leakage paths through
access holes for power and lifting gear cables. Great care should be taken when considering
sealing these holes for lifting cables because they move constantly and must not be allowed
to be degreased with brush seals.
13.1.10 Commissioning
The majority of buildings will require a Fire Certificate. The proper functioning of these
systems needs to be demonstrated in order to obtain a Fire Certificate. This is a life safety
system. It is important to ensure the systems are fully operational, well ahead of practical
completion. Adequate time/space should be allowed for any remedial work or necessary
adjustments, before the building is occupied. Consider also the following provisions:
• Arrange for early pressure test if a false ceiling or false floor is being used in the
pressurised space. At the very least carry out a visual inspection of ceiling and floor voids
before they are inaccessible.
• If the building is to be fitted out for tenants, carpets may not have been installed at the
time the tests are performed and therefore giving rise to air paths through the gaps under the
doors. In this instance specify temporary or permanent door thresholds to restrict air flow.
Note: For fire fighting shafts, only the services associated with firefighting facilities may pass
through the shaft. Toilets are the exception but ducts must be separated and risers suitably
stopped.