Professional Documents
Culture Documents
Expected Exam Questions - Summary
Expected Exam Questions - Summary
Table of Contents
FRAMEWORK: 1
SCOPE MANAGEMENT: 2
SCHEDULE MANAGEMENT: 4
COST MANAGEMENT: 6
QUALITY MANAGEMENT: 9
RESOURCES MANAGEMENT: 14
RISK MANAGEMENT 19
COMMUNICATION MANAGEMENT: 22
STAKEHOLDER MANAGEMENT: 24
PROCUREMENT MANAGEMENT 27
INTEGRATION MANAGEMENT 30
Framework
During project initiation, you as project manager find that business case is not completed,
what you should do?
Q A) Modify it
Q1
B) Ignore
C) Meet with the sponsor and inform him
A Meet with the sponsor and inform him
Page 1 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Scope Management:
After Defining the project assumptions, constraints and key deliverables What Will you do
Next?
A- Collect Requirements
Q
Q2 B- Decomposition deliverables into smaller component
C- Plan Scope Management
D- Validate Scope
A B- Decomposition deliverables into smaller component
Q
Q3
Q
Q4
Page 2 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q5
A Project Schedule
Q
Q6
Page 3 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Schedule Management:
Q
Q7
A Answer is 5
Q8
Q9 Q
Page 4 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q10
A 17
Page 5 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Cost Management:
During project cost estimating you want to use the tool which considering the risk and
uncertainty, which tool you will select:
A Bottom-Up estimating
Q
Q11 B Analogous Estimating
C Parametric Estimating
D Three-point Estimating\Beta Estimating
A D Three-point Estimating\Beta Estimating
A project manager in construction project, if the Project Sponsor tells you that the project
will be terminated because of Stumbled in the credit limit of the bank. What could have
done by the project manager to prevent this type of situation?
Q A. Funding Limit Reconciliation
Q12 B. Reserve Analysis
C. Critical path method
D. Critical chain method
A A. Funding Limit Reconciliation
Q
Q13
Q
Q14
Page 6 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q15
Q
Q16
Q
Q17
Q
Q18
Page 7 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Page 8 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Quality Management:
Q
Q19
A ) كمدير مشروع ال متوافقش الن تكلفة مراقبة الجودة اعلى من إعادة الشغل نفسهB(
Q
Q20
انت شغال فمشروع والحظت ان في بعض أعضاء الفريق محتاجين تدريب عشان تزود الكفاءات بتاعتهم فده يعتبر
Q
Q21 Cost of quality اى نوع من أنواع ال
A Failures انت بتدفعه عشان تمنعPrevention Cost (Training Cost) يعتبر
You are a project manager of the DFJ Project. Your project is behind Schedule and the
sponsor want to reduce the quality activities. What will the project manager do first?
A- Check options to crash the project
Q
Q22 B- Ignore the Sponsor Request
C- Follow the Quality Management Plan
D- Reduce quality activities to satisfy the project sponsor
A follow project quality management plan
Page 9 of 36
Expected PMP Exam Questions (PMP 6th Edition)
حد من فريق الجودة اقترح على مدير المشروع ان في بعض الخطوات الغير ضروريه اللى بتاخد وقت انت كمدير
Q
مشروع هتتاكد من كالمه ازاى او ايه التكنيك اللى هتستخدمه
Q23
Process analysis (it is a Data Analysis technique in quality management)
A
non-value-added activities الن هو ده اللى بيعرفنى ال
A project needed to monitor the technical performance of the project and capture data
related to how many errors or defects had been identified and how many remained
uncorrected. Which of the following techniques should the project use?
Q A- Scatter diagram
Q27
B- Flowchart
C- Histogram
D- Control chart
A C- Histogram
You are a project manager for Enormous Co. and are currently engaged in a highly visible
project. The company is about to implement an independent review to ensure that the
project work is continuing to comply with the project ‘s policies, processes, and
procedures. During which process would this review occur?
Q
Q29 A- Close Project or Phase
B- Control Quality
C- Monitor Risks
D- Manage Quality
A D- Manage Quality
Page 10 of 36
Expected PMP Exam Questions (PMP 6th Edition)
You are executing a building construction project and you suspect hazardous materials to
be present at site. What is the BEST thing to do?
A- Call a hazardous expert to carry out inspection
Q
Q30 B- Perform integrated change control
C- Stop the work immediately
D- inform the customer
A A- Call a hazardous expert to carry out inspection
Q31
Manage Quality
Control quality
Q32
Page 11 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q33
Immediately meet with the developers and quality control team to
ensure that quality standards are met.
Q34
Answer is C
Q35 Q
Page 12 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Pareto chart - Histogram
Page 13 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Resources Management:
بيجى سؤال يقولك اتنين من الفريق عندك اتخانقوا فى جزئيه معينه من الشغل وكل واحد يقول دى مش بتاعتى فانت
Q
Q36 كمدير مشروع ترجع اليه عشان تتاكد
A team member بالactivity الن هى اللى بتربط كلRACI او الRAM هترجع لل
Q عندك واحد من الفريق مشى وال مات ازاى تقنع المواراد البشريه او االداره انك محتاج واحد مكانه
Q37
A team member بالactivity الن هى اللى بتربط كلRACI او الRAM هترجع لل
You are working in a matrix organization and managing a project. The functional manager
transferred some resources you need from your project to another project. What should
you do next?
Q A Negotiate with Functional manager to assign a new resource
Q38
B Escalate this problem to the sponsor
C Complete the project without these resources
D Update Risk Register
A A Negotiate with Functional manager to assign a new resource
You are managing a large infrastructure project. two important team members are having
some issues. You met the team members and documented the problem and target
resolution date. What is the document the project manager used it?
Q A) Risk register
Q41
B) Issue log
C) Stakeholder register
D) Change log
A Issue log
Page 14 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q42
Q
Q43
Page 15 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q44
You are managing a large construction project. Your project team works in two different
buildings across the city. You want to communicate the vision and inspire the project
team to achieve high performance. Which of the following skills help the project
manager?
Q
Q45 A Feedback
B Emotional intelligence
C Leadership
D Political awareness
A C Leadership
Q
Q46
Page 16 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q47
Resource Management Plan
Q48
Answer is C
Page 17 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q49
Q50
Withdraw
Page 18 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Risk Management
Q اللى بتستخدم فى التخطيط و تعريف وتحليل ومراقبه المخاطرtool &technique ممكن يجى سؤال ايه هى ال
Q51
A monitor risk ماعدا الrisk موجود فى كل عمليات الExpert Judgement
Q اللى انت محتاجهاtool and technique ايه الhigh risk للمخاطر عشان تركز الprioritizing عايز تعمل
Q53
A Probability and impact matrix
Q After preparing the risk management plan and identify the risk what you will do next
Q54 You should do qualitative risk analysis, but the answer was the meeting as it is a tool and
A
technique used in qualitative risk analysis
اللى انت بتستخدمه فى التحليل الكمى اللى بيساعد فى تحديد اكبر المخاطر اللى ليهاtool and technique ايه ال
Q
Q55 اكبر تأثير محتمل على مخرجات المشروع
A Tornado diagram or sensitivity analysis
You are a project manager in Critical Project for your organization, you expect that the
generator that used may breaks down, and you don’t have any other generators
available. Therefore, you planned to call your friend who have an equipment supplier to
rent generator at a reasonable price. This is an example of:
Q
Q56 A-Risk Mitigation
B-Workaround
C-Risk Avoid
D-Risk Acceptance
A A-Risk Mitigation
You are a project manager to construct a new building in a typhoon prone area and may
impact the schedule and quality. As a project manager, what should you do?
A-Outsource the project and transfer the risk
Q
Q57 B-Establish a contingency reserve
C-Perform Quantitative Risk Analysis, and plan risk response
D-Develop the risk management plan and establish a management reserve
A A-Outsource the project and transfer the risk
Page 19 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q58
A Project Charter
Q59
Q
Q60
Page 20 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q61
A Mitigation
Q
Q62
Page 21 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Communication Management:
You are using PMIS to upload the dashboard reports to a web site and people can
Q
Q63 download it, which communication method you are using
A Pull Communication
A problem happened because the contractor did not understand or mistakenly sent you
Q
Q64 wrong or not completed reports, what should you did to prevent this.
A Interactive communication
You are in closing stage at your project, the financial manager requested some reports
from your project, as a project manager what should you do?
Q
A) You will neglect his order
Q65
B)You will send
C)You will review the communication management plan
A You will review the communication management plan
You are a project manager managing a large software project. Your project team sent
confidential information to the subcontractor by mistake. What could have prevented this
situation?
Q A Reviewing the Communication management Plan
Q66
B Review stakeholder register
C Reviewing the stakeholder engagement Plan
D Reviewing the Scope management Plan
A Reviewing communication management plan
You are at the end of the project and you sent final reports to stakeholders and they find
Q some non-resolved issues were removed from the reports, what should you did to
Q67
prevent this.
A Monitor communication
Q68 Q
Page 22 of 36
)Expected PMP Exam Questions (PMP 6th Edition
A Pull Communication
Q
Q69
لما يسأل دايما عن ازاى تمنع حاجه يبقى االجابه هتكون خطة Plan
لو بيسأل هات referاليه غالبا االجابه هتكون خطه او مستند
Page 23 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Stakeholder Management:
Q70
Identify stakeholder
risk االحسن انك تعرفهم فى خطتك وتعرف تأثيرهم و متطلباتهم وتضيفهم للخطه احسن من انك تخليهم فى ال
A
وبيبقوا مجهولين بالنسبه ليك
identify risk بيكون قبلstakeholders و اصال تعريف ال
A Stakeholder has become supportive after he was resistive, what is the first document
you shall update as a project manager?
A communications Management plan
Q
B Risk Register
Q71
C Stakeholder engagement assessment matrix
D issue log
C-Stakeholder engagement assessment matrix OR Stakeholder register (If mentioned)
A
OR stakeholder engagement plan
Q
Q72
Q
Q73
A Keep Informed
Page 24 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q74
Q75
Update Stakeholder Register
Page 25 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q76
Q77
Answer is C
Page 26 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Procurement Management
A project is contracted on a Cost-Plus Fixed Fee (CPFF) basis with a fee of 10 percent of
estimated costs. The estimated cost is US$ 50,000. If the project comes in at US$ 60,000
with no changes in project scope, what would be the total cost of the contract?
Q A US$ 55,000
Q78 B US$ 125,000
C US$ 75,000
D US$ 65,000
Fee is calculated as 10 % of 50,000 = 0.01 X 50,000 = 5,000
A
Total cost of the contract is 60,000 + 5,000 = 65,000
Q
Q79
A Bottom Up estimating
Q
Q80
Page 27 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q81
A D) ADR
Q
Q82
A Pay to the Seller with a formal written commitment to complete the work
Q83 Q
Page 28 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Page 29 of 36
)Expected PMP Exam Questions (PMP 6th Edition
Integration Management
كمدير مشروع الحظت ان ال business caseغير مكتمله او فيه مشاكل ايه اللى المفروض تعمله
هتكبر و مش هتعمل حاجه
Q هتغيرها
Q84 هتجتمع بال Sponsorوتعرفه
هتعمل طلب تغيير
هتجتمع بال Sponsorوتعرفه ,الن التعديل عليها مش من صالحيات مدير المشروع وهى اصال مش Project
A
document
انت كمدير مشروع المدير المالى/المدير الوظيفى مش بيديلك موارد فى المشروع ايه الوثيقه اللى ناقصه و مذكور
Q
Q86 فيها بيقول من حقك تاخد الموارد وال ال
A Project Charter
Q Kickoff meetingعليه 4اسئله فى االمتحان ( بيتعمل امتى وليه و مين هيعمل ايه)
Q87
A
Page 30 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q Approved change requests are processed through which process for implementation?
Q90
A Direct and Manage Project Work (Execution)
Q
Q93
A Answer is D
Q
Q94
A Answer is D
Page 31 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q
Q95
Q96
Page 32 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Closing procurement
Q97
Q98
Page 33 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q99
Q
Q100
A Statement of work
Which of the following describe the reason why the project is authorized?
A. Project charter.
Q B. Business case.
Q101 C. Scope statement of work.
D. Project management plan
B. Business case.
A
بس اختارهproject charter لو جاب
Page 34 of 36
Expected PMP Exam Questions (PMP 6th Edition)
You are in the process to get the final acceptance on the deliverables which have been
developed as part of your project. This was done to make sure that project scope and
deliverables are achieved. Which process are we currently performed?
Q A. Close Project or phase.
Q102 B. Validate Scope.
C. Develop Project charter.
D. Control quality.
Final acceptance= Close Project or phase
A
Formal acceptance= Validate Scope
During creating the Project charter, Sponsor tell you that the government has been issued
a new law and may be affect the project, this law will apply after 6 months. what is the
FIRST thing should you do as a project manager?
Q A. Add new law in EEF.
Q103
B. Ignore the new law.
C. Ask your management what you should do.
D. Meeting with SH and evaluate the impact.
A A. Add new law in EEF.
Q104
Answer is A
Page 35 of 36
Expected PMP Exam Questions (PMP 6th Edition)
Q105
Page 36 of 36