Greater Colombo Water & Wastewater Management Improvement Investment Programme

System Rehabilitation for NRW Reduction in South Part of Colombo City


Pipe Laying
Required Daily
Daily Required Progress to
Total Scope Cumulative Length to be Balance Pressure
DMA Contractors Progress (m) Progress Complete on
(m) Progress (m) Catch up (m) (To be Laid) Testing (m)
05/12/22 up to now (m) 15/12/2022
(m/Day)
20A Sierra Construction 9,142.00 133.65 6,073.71 8,126.22 2,052.51 3,068.29 340.92 1,029.38
33A Subasinghe Contractors 4,526.00 47.40 3,377.61 4,141.72 764.11 1,148.39 127.60 0.00
Braincode Engineering 2,347.00 35.55 1,379.68 2,069.07 689.39 967.32 107.48 0.00
35A Subasinghe Contractors 1,827.00 0.00 955.12 1,610.64 655.52 871.88 96.88 0.00
Romasha Engineers 719.00 57.75 501.94 527.27 25.33 217.06 27.13 0.00
35B Edward & Christie 3,183.00 35.70 1,224.75 2,785.13 1,560.38 1,958.25 217.58 0.00

35C Braincode Engineering 8,685.90 86.45 5,931.69 6,300.42 368.73 2,754.21 306.02 3,443.54

36B Romasha Engineers 8,351.00 51.76 7,156.96 7,641.95 484.99 1,194.04 132.67 1,568.95

TOTAL 38,780.90 448.26 26,601.46 33,202.42 6,600.96 12,179.44 1,356.29 6,041.87

House Connections
Total Scope Daily Progress (05/12/22) Cummulative Progress Balance
DMA Contractors
Stage 1 Stage 2 Stage 1 Stage 2 Stage 1 Stage 2 Stage 1 Stage 2
20A Sierra Constrcution 87 87 0 0 7 0 80 87
33A Subasinghe Contractors 1440 1440 0 0 0 0 1440 1440
Braincode Engineering
35A 1253 1253 0 0 0 0 1253 1253
Subasinghe Contractors
35B Edward & Christine 1121 1211 0 0 0 0 1121 1121
35C Braincode Engineering 1345 1345 18 0 49 0 1296 1345
36B Romasha Engineers 1211 1211 1 0 40 0 1171 1211

TOTAL 6457 6547 19 0 96 0 6361 6457