Professional Documents
Culture Documents
LOCATION: TITLE:
SCOPE OF WORK
Q A 1 0 - G - 1 0 5 7 1
SUBCONTRACTOR:
Sheet 1 of 181
SHOAIBA QUAIZA B WATER TRANSMISSION SYSTEM
Scope of Work
Subject: Page 2 of 181
Pipe Laying and Station Construction Works
LIST OF CONTENTS
1 INTRODUCTION 7
1.1 Scope of this Specification 7
1.2 Responsibilities of the Contractor(s) 7
1.3 Survey of Existing Facilities 8
1.4 Drawings 9
1.5 Definitions 9
1.6 Abbreviations 10
2 GENERAL DESCRIPTION 15
3 DESIGN DATA AND SERVICE CONDITIONS 16
3.1 General 16
3.2 System Capacities and Flow Rates 16
3.3 Pipeline Segments and Length 16
3.4 Station, Elevations and Water Levels 16
3.5 Water Quality Data 17
3.6 Utilities 17
3.7 Climatologic Data 18
3.8 Noise Levels 19
4 DESIGN REQUIREMENTS 21
4.1 General Requirements 21
4.2 HCIS Requirements 23
4.3 Civil Engineering 24
4.4 Mechanical Engineering 25
4.5 Electrical and Control Engineering 26
4.6 Performance Guarantee 28
5 HYDRAULICS AND OPERATION 31
5.1 Scope of this Section 31
5.2 Hydraulic Design Principles 31
5.3 Philosophy of Operation 32
5.4 Control Levels and Control Modes 33
5.5 Safety Sequences and Safety Programs 34
5.6 System Control 35
5.7 Station and Unit Control 36
5.8 Station Control Regulation Loops 40
5.9 Stand-by Philosophy 41
1 INTRODUCTION
The scope of this Project Specification G02 is to describe the “SHOAIBA QUAIZA B WATER
TRANSMISSION SYSTEM” and to define the basic layout, the design and construction
requirements and the performances to be guaranteed. Further scope is to list the required key
equipment including the main data and the necessary functions.
This Project Specification also describes the contract limits to existing and future installations, as
well as the internal battery limits between individual Packages, including the necessary co-
ordinations and responsibilities.
In this respect this Project Specification G02 shall be treated as the principal technical document
of the various Contract Documents and is considered to specify the minimum requirements of the
Project. The stipulations in the Project Specification G02 are ruling over the stipulations of the
SWCC Standard Specifications, the room book, the drawings and documents of Volume XII and
XIII.
More detailed information on the layout and characteristics of the above mentioned Water
Transmission System and the procedures to be followed during the project realization can be
found in the drawings, in the standard specifications and in the particular data sheets.
“SHOAIBA QUAIZA B WATER TRANSMISSION SYSTEM” shall be designed to transport water
from the new Shoaiba – Quaiza Pump Station (PS-SH) to the existing Reservoir Station Quaiza
(RS-QA), via the new Reservoir Station Jeddah East (RS-JE).
By definition of the Contract Documents, the Construction Contract comprises the engineering,
procurement and construction of the Works (EPC), including – but not being limited to – the
design, manufacture, shop testing, transport and delivery to the site, storage on site, construction,
finishing, start-up, tests on completion, instruction of Employer’s personnel and warranty
obligations.
The vital parts and components of the Shoaiba Quaiza B Water Transmission System will be
described in detail in this Project Specification G02 and in other sections of the Contract
Documents, however, this description must be considered to be the basic tender design only.
This holds especially true for the Pipeline System itself (consisting of the mainline, pump station,
reservoir station and tie-in station) in order to show the hydraulic, structural and operational
considerations upon which the preliminary calculation of the pipe wall thickness is based.
Following the spirit of a turn-key Contract it shall be the Contractor’s obligation to carefully study
this design and its implication for the pipework and for the system performance.
As the Contractor(s) shall not have any comments concerning this matter, he (they) shall be
deemed to have fully identified himself (themselves) with the basic system layout and the
selection of pipework, after careful investigation, and he (they) shall take full responsibility for the
quality and performance of the entire System as defined in the Contract Documents.
The main responsibilities for all the different Contractor(s), with respect to design, supply and
construction activities are described below:
Pipeline Contractor
Station Contractor
Overall system design, including hydraulics, SCADA, control and communication system
Overall project coordination and interface coordination
Design, supply and construction of pump station, reservoir station and tie-in station
Design, supply and installation of the control and communication system
Supply and installation of fibre optic cables for the complete system
Design, supply and installation of the power supply facilities for the stations
Cathodic protection for the station piping and tanks
Tank construction
Earthworks
Start-up and tests upon completion for the complete system
Maintenance organization, equipment and spare parts
Familiarization and training
For more details reference is made to the stipulations contained in the contract documents, the
price schedules, the standard specifications and the descriptions contained in this Project
Specification G02.
For the detection and identification works of underground facilities the support of the respective
owners and operators of the services may be required.
Temporary or permanent relocation of existing pipes and / or cables may be required to clear the
construction space for the new installations.
In case public roads and traffic areas must be closed partly to allow survey and detection works,
the permission from the responsible traffic police and road department must be obtained. All the
required traffic safety measures (sign boards, barriers, warning lights, etc.) must be considered for
these works and shall be part of the contract scope.
Several as-built and design documents of existing or future projects of SWCC or Third Parties are
provided with Volume XIII. Some drawings of Volume XII are also based on as-built or design
documents. It is the obligation of the Contractor to verify the correctness of the data. No extra
payment will be allowed in case the drawings do not comply with the actual status on site.
1.4 Drawings
The drawings (Volume XII of the Contract Documents) are intended to portray the basic layout of
the SHOAIBA QUAIZA B WATER TRANSMISSION SYSTEM and to define the minimum
requirements regarding dimension and quality according to the specifications.
The drawings cannot show exact final dimensions and requirements, which will depend upon the
size and shape of the equipment selected by the Contractor. This is especially applicable to all
drawings of buildings and, to a certain extent, to the station layout plans. In these cases the
Contractor shall determine the locations, dimensions and internal arrangement of sites in such a
way that they meet the design requirements and all applicable specifications.
No extra payment will be allowed, if during the final design stage it becomes apparent that anyone
site or installation must be enlarged in order to meet the respective requirements.
The overall route maps and kmz-files issued by the Engineer along with the Tender/Contract
Documents shall only define the general route to be followed. In case deviations are necessary
with respect to the pipeline route, it will be the Contractor’s responsibility to conduct all necessary
investigations concerning any possible impact to the costs for the construction works and any
possible impact on the operational costs. Major deviations, which would change the hydraulic
system, are not acceptable. The final approval of the pipeline route will be granted by the
Employer.
As a general rule all drawings shall be produced in A1 size with reduction to A3 size. For pipeline
alignment sheets the size of A0 may be used.
1.5 Definitions
“System“ shall mean the Shoaiba Quaiza B Water Transmission System, containing the
complete works including the pipeline segments and all stations.
“Mainline” shall mean all pipeline segments (with all accessories like cathodic protection
facilities, etc.), which connect the initial pump station and the terminal station with each other. The
pipeline segments together with these stations form the backbone of the system.
“Station” shall mean all works for the system which are related to the initial pump station or a
distributed endpoint as well as all other special locations along the pipeline routes (e.g. vent
station). When referring to a “station” without specifying a certain part thereof, this expression
shall mean all installations at the given location.
“Endpoint Station” shall mean the general term for a station, being the endpoint of a main line.
“Reservoir Station” shall mean all installation at the given high point location of the mainline
including erection of new reservoir(s) or tank(s)
“Tie-in Station” shall mean all installations at the given endpoint location of the main line
including connecting the new pipeline system to an existing pipeline system, station or tanks.
“Final Design / Detail Design” shall mean the design to be performed by the Contractor in
accordance with the requirements stipulated in the Contract Documents.
“Contractor” shall mean the Station Contractor and Pipe Laying Contractor if not otherwise
specified
1.6 Abbreviations
1.6.1 Authorities
SWCC Saline Water Conversion Corporation
HCIS High Commission for Industrial Security
MEWA Ministry of Environment, Water and Agriculture
MOT Ministry of Transportation
NFPA National Fire Protection Association
NWC National Water Company
SAUDI ARAMCO former named ARAMCO (Arabian-American Oil Company)
SEC Saudi Electricity Company
STC Saudi Telecommunication Company
WHO World Health Organization
Pump Station:
PS-SH Shoaiba Quaiza Pump Station
1.6.3 Units
AC Alternating Current
DC Direct Current
km Length or chainage, kilometer
LSI Langlier Saturation Index
mlc Pressure, metres liquid column, according to Bernoulli formula
barg Relative pressure, gauge pressure = bar
bara Absolute pressure, including atmospheric pressure
dB (A) Sound pressure level, decibel
m³/d Flow rate, cubic metres per day
m³/h Flow rate, cubic metres per hour
m³/s Flow rate, cubic metres per second
masl Elevation, metres above sea level
°C Temperature, Degree Celsius
1.6.5 Operation
O&M Operation and Maintenance
SYSAD System Administrator is the Person responsible for configuration and
maintenance of the control system
(adj. SYSAD) This symbol signals that the indicated variable can be adjusted by the
System administrator only, but not by the Operator.
System Operator Person in Central Control Room (CCR), who is responsible for operation of
pipeline system
Station Operator Person receiving instructions form the System Operator, who is responsible
for the operation of a station
PC Pressure Control
PI, PIT Pressure Indicator, Transmitter
PRV Pressure Relief Valve
PAH, PCH Pressure Alarm High, Pressure Control High
PAL, PCL Pressure Alarm Low, Pressure Control Low
PHFP Pump High Flow Protection
PLFP Pump Low Flow Protection
SD Shut-Down
TI, TIT Temperature Indicator, Transmitter
TLA Top Limit Alarm (at valve)
FLOW-PATH The FLOW PATH defines the segments and sections of the system which
are subject of the FLOW PATH supervision (unscheduled valve closure).
MOV Motor Operated Valve
RMU Ring Main Unit
2 GENERAL DESCRIPTION
This chapter intends to give a summarized description of the necessary works, stations, pipelines
and main components of the Project.
More detailed description regarding the equipment to be installed, the station layouts and the
buildings are contained in the subsequent chapters of this Specification G02.
For a general overview of the overall SQWTS-B reference is made to the following drawing:
QP10-U-1125 Overall Route Map, Shoaiba Quaiza B Water Transmission System
The scope of the SQWTS-B is to transport potable water from Shoaiba pump station and storage
tanks to the endpoint Tie-In Station Quaiza via Reservoir Station Jeddah South East.
The starting point of the Shoaiba Quaiza B Water Transmission System (SQWTS-B) is the pump
station PS-SH were the dedicated pump group to the system is located. One line will transport
water to the new Reservoir Station Jeddah South East (RS-JE). At the reservoir station a tank
farm will provide enough capacity to store the potable water from a production of the desalination
plant of one day. A line will connect the RS-JE with the already existing Reservoir Station Quaiza.
At the existing reservoir station a new Tie-In Station Quaiza (TI-QA) will be constructed.
The maximum design flow rate (MDF) of the system as well as the maximum supply rate to the
endpoint are given in the chapter 3 below.
The main components of the (SQWTS-B) are
a) The pump group PS-SH located within the common pump station PS-SH taking suction from
the tank farm with 4 x 150,000 m³ storage tanks, with fixed speed booster pump units and
variable speed driven main pump units in parallel arrangement and all related facilities. Also
included is inlet and outlet connection piping to new Shoiba Phase 4 tank farm for pool
operation.
b) The pipeline with a diameter of 88” from PS-SH to the Reservoir Station Jeddah South East
(RS-JE) of approx. 102.7 km length.
c) The Reservoir Station Jeddah South East (RS-JE) with 2 x 170,000 m³ storage tanks and
additional tank farm platform for another 4 x 170,000 m³ storage tanks, exclusive tanks.
d) A gravity pipeline with a diameter of 72’’ from to the Reservoir Station Jeddah South East
(RS-JE) to the Tie-In Station Quaiza (TI-QA) of approx. 19.0 km length
e) The Tie-In Station Quaiza (TI-QA) located within the boundaries of the existing reservoir
station Quaiza with inlet control facilities.
3.1 General
This chapter provides information on the project design data, the water quality data, the ambient
conditions and climatologic data, etc., to be used by the Contractor(s) for the Design and the
Material Selection of the Shoaiba Quaiza B Water Transmission System.
The design flow rates and capacities for the SQWTS-B are determined considering an operating
factor of 0.95 and are provided in the tables below.
Maximum Design
Station
Flow Rate (MDF)
[m³/d]
Shoaiba Pump Group (PS-SH) to Jeddah (RS-JE) 600,000/0.95 = 631,579
Reservoir Station Jeddah South East (RS-JE) to
300,000/0.95 = 315,789
Tie-In Station Quaiza (TI-QA)
The chainage (kilometer points along the route) and elevations of the individual project locations
are provided with the following tables. The chainage is based on the preliminary routes and shall
be adapted by the Contractor during final design.
The elevation system to be used for the project shall be Tide Staff Shoaiba (TSS), as used for the
existing pipelines in this area.
The below elevations are partially based on topographic survey, as-built or design documents. It
is the obligation of the Contractor to verify by topographic survey all elevations used for the
hydraulic calculations and design. No data of as-built documents shall be considered for design
without transferring it to the project elevation system by surveying a characteristic point of the
relevant structure.
The final station elevation shall be selected by the Contractor based on actual site conditions. All
station platforms shall be on an elevated pad to avoid flooding.
The station elevations shown on the layout drawings and mentioned below are binding for the
Contractor unless otherwise justified and approved by the Engineer. All elevations masl refer to
Tide Staff Shoaiba (TSS).
As majority and permanent supply of water the new Shoaiba desalination plants Phase 6 and 7
will supply to the new Shoaiba tank farm. The following water quality data is applicable.
Table 3-4: Water Quality Data – Design Data for Water Transmission System
Temperature T °C 26-36
pH pH - 8.0 – 8.6
Calcium Hardness CaH mg/l as CaCO3 36 – 50
Total Alkalinity TA mg/l as CaCO3 36 – 50
Chloride Cl mg/l max. 150
Residual Chlorine RCl mg/l 0.2 – 0.5
Total Dissolved Solids TDS mg/l max. 300
Langlier Saturation Index LSI (+)0.1 – (+)0.3
3.6 Utilities
The various voltage levels for electrical power supply feeders and distribution are defined in the
chapter 4.5.3 below.
3.6.7 Lubricants
Lube oil systems including all tanks, pumps, piping and lubricants for pumps, motors or any other
rotating machinery are part of the contract.
3.7.1 General
The air temperatures in the Jeddah area are very high from June to August, being in excess of
38,7°C. Generally winter temperatures remain below 20°C and can drop below 0°C.
Rainfall is very rare between May and October, moderate rain with heavy showers may occur
between November and April.
The maximum allowable noise levels within buildings and rooms shall not exceed the values listed
in the table below:
4 DESIGN REQUIREMENTS
4.1.1 Scope
This chapter covers the main design requirements which are binding for the Contractor’s design
even when presenting alternative proposals.
operation
maintenance
repairs
administration
in safe, reliable, simple and economical way.
The equipment shall be sized for continuous operation at maximum capacity.
The worst case design principles shall be applied.
The design margins shall take into account wear and tear and fouling factors.
The pipeline systems shall be designed to operate satisfactory under all variations of load,
pressure, temperature, etc., as shall occur during normal usage under the prevailing
environmental conditions.
The best design shall be used to facilitate inspection, maintenance and repair.
Every reasonable precaution and provision for the safety of all personnel in charge of operation
and maintenance of the system shall be incorporated into the design.
Systems shall be designed for simple and economic local and remote operation.
The entire material and equipment performing similar duties shall preferably be of the same
manufacture and type, in order to allow interchangeability wherever possible, to reduce the
number of spare parts and to maintain uniformity of plants.
The main equipment for the project shall be produced at the original place of the manufacturer.
Due to the reliability requirements as detailed above only equipment and materials of proven
design and/or quality as defined below shall be used.
Proven design shall mean:
For the SQWTS-B Project all safety and security requirements of HCIS shall be implemented. The
latest version of the HCIS Standards shall be applied. These include the SEC and SAF standards,
with directives for “industrial facilities” and “non-industrial facilities”.
Based on the provided design it is the obligation of the Contractor to develop the security basic
and detail design and construct, install, test, commission all safety and security systems.
For all works the Contractor has to engage an HCIS certified Subcontractor. Furthermore, the
Contractor shall engage independent safety and security consultants (certified by HCIS) for third
party review and supervision as detailed in the HCIS standards.
The following facility classes have been considered in the design (subject to further security
design and approval of HCIS).
Facility Classification
Also complete safety requirements as per HCIS standard shall be implemented by the Contractor.
4.3.1 General
All civil engineering and building works shall be designed in detail by the Contractor according to
the Specifications, the Saudi Building Code (SBC), the European Standard (EN), the German
Standard DIN, British Standard (BS) or relevant American Standards. If not specified elsewhere in
the Contract Documents one subject shall be designed by one standard to be approved by the
Employer (mixing of codes shall be avoided as far as possible).
In general, mechanical engineering shall be done in accordance with good engineering practice.
For piping equipment (valves, joints, flow meters, etc.) with flanged ends of a size ≥ 62”,
coordination between equipment and pipe Manufacturer(s) is required in order to mate both the
equipment and the pipe flanges correctly, meeting the design parameters at the same time.
Attention must be also paid to the extension of the raised face of all these non-standard flanges in
conjunction with the width of the gaskets, so that the full function of the gasket is guaranteed. The
gasket shall not extend inside the line and the full sealing portion shall sit on the raised face.
24 V DC
Voltage levels for medium voltage VSD driven main pump motors shall be in range between 3kV
and 13.8kV.
Separate voltage levels for electronic equipment below 24 V DC are allowed, but shall also be
reduced to a few necessary levels.
4.6.1 General
In order to examine whether the Contractor has performed the final design in accordance with the
design requirements, the Contractor shall perform several tests as soon as the pipeline system is
ready for operation. Comprehensive test procedures shall be prepared by the Contractor and
submitted to the Engineer for approval, as outlined in the relevant item of this Specification. The
Contractor must demonstrate that the results of the tests described below are within the
admissible limits or better than the guaranteed values.
During the specified test run periods no interruption of operation is allowed. Should there be an
interruption, the concerned test must be repeated and the cause of the interruption ascertained
and recorded.
The test run needs not be repeated in case of interruption of operation for reasons beyond the
Contractor’s reasonable control (power failure, water supply shortage, water discharge problems)
provided that the time period of continuous operation exceeds 50 % of the specified period.
The power consumption guarantee shall be based on the following design conditions:
type of material which comes into contact with the water transported is safe for drinking water
purpose. It is to be proven that no substances which shall adversely affect health or taste come
into contact with the transported water during transportation and storage.
In addition the Contractor shall guarantee that the pH value will not exceed the maximum value
defined in the applicable drinking water standard during the entire warranty period.
The necessary analyses are to be performed on the basis of the examinations described in the
latest edition of the ”International Standards for Drinking Water” issued by the World Health
Organization (WHO).
Detailed chemical analysis of the product water and a comparison of the values obtained with the
guaranteed water quality, as per relevant stipulations, shall be performed by the Contractor at
weekly intervals during the period of start-up and tests on completion.
In addition the Contractor shall make comprehensive water analysis at monthly interval during the
entire warranty period. Water samples shall be taken at different points along the pipeline,
especially at the pump station and the inlet piping of the endpoint terminal for different cases of
operation, such as periods of non-operation (line is shut down) and during normal operation.
All test results shall be duly evaluated and handed over to the Employer and the Engineer, who
shall also be notified whether or not the quality of the water does meet the set criteria (guaranteed
water quality).
the total power consumption of the pump station for the test run period minus the base load
consumption of the pump station for the same time period. This base load consumption shall be
measured over a time period of 24 hours when the mainline is out of pumping operation, but with
the same consumers in service as during the test-run period.
The power consumption is to be guaranteed for the hydraulic load case with the specified MDF,
as listed in chapter 3.2 of this Specification. The measured value as obtained during the test run
must be recalculated to the design conditions as stipulated in chapter 4.6.1 above.
The test run for the power consumption guarantee shall be combined with the test run for the
throughput rate guarantee.
4.6.5 Reliability
The Contractor shall prove the reliability of the supplied equipment and installations by operation
at any load and mode of operation as instructed by the Employer over a continuous period of
thirty (30) calendar days.
The Contractor has to demonstrate both, the smooth running of the System and the capability to
operate continuously for the above mentioned period. The stand by units shall be operated during
the duration of this test.
The test run(s) to be done in order to prove that the design flow rate as indicated in item 4.6.3
above and the power consumption are met can be performed during the reliability test period.
The Contractor shall also demonstrate the correct hydraulic behaviour of the pipeline system
under normal and transient flow conditions for all system configurations and modes of operation.
These demonstrations shall prove the correct working (setting and adjustment) of the entire
control and safety equipment (i.e. Surge Vessels, FC, PC, PCH, PSH, PCL, PSL, LCH, LCL, etc.)
installed for the purpose of protecting the pipeline and the equipment at the pump station and the
endpoint stations against the occurrence of overpressures, vapour pressure and other effects
which shall be harmful to the installation.
This section shall summarize the input data, the general and specific requirements as well as the
design principles which have to be considered for the design of the system, from both the
hydraulic and the operation point of view.
The requirements stipulated in this section, together with all relevant drawings and specifications,
shall serve as the basis for the Contractor’s final design.
Under no circumstances the integration of the new system shall have any negative effect on the
hydraulic behaviour of existing facilities. If due to the interconnection works it is required to modify
or amend the existing installations, it must be proven that the safe and undisturbed operation can
be guaranteed also after the implementation of the new system.
All necessary investigations and calculations, including the required interface coordination are
part of the Contractor’s scope of work. The detailed operation and control philosophy for the
individual pipeline systems shall be worked out by the Contractor as part of the final design under
consideration of the actual hydraulic calculations.
This part summarizes the general requirements that are to be considered in the layout of the
hydraulic system.
Centralized remote operation and control of the system, including pump station tie-in station and
reservoir station. Only in exceptional cases (tests of equipment, tests of station control, line filling,
etc.) shall the system be controlled locally from the individual stations or units.
Simple operation with maximum possible support of automatic sequences.
Automatic control of unscheduled events by self-contained safety equipment.
Operation without Telecommunication System (TCS) shall be possible with no flow restrictions.
The system operation shall ensure the delivery of the flow rate range from minimum flow to the
MDF at a pipe roughness from 0.005 mm to 0.100 mm (pipes with CM lining). The surge
protection equipment is to be designed for a pipe roughness range of 0.005 mm to 0.100 mm. A
lower roughness may result in higher flow rates than the defined MDF which is to be considered
for the selection respectively dimensioning of the surge protection equipment. Overrides (e.g.
FCH) shall be taken into account, if applicable, to limit maximum occurring flow rate.
The pressures during steady flow conditions must not exceed the line of Maximum Allowable
Operating Pressure (MAOP Line) with a safety factor of 0.72 (=1/1.389) according to the ASME B
31.4 respectively the equipment pressure class.
The maximum pressures occurring during transient conditions must not exceed the MAOP Line
plus 10% according to the ASME B 31.4 respectively the equipment pressure class and therefore
safety measures must be foreseen (e.g. appropriate operating time for valves, etc.).
The minimum pressures during normal pump operation (= steady flow operation and scheduled
transient conditions during start or stop of pumps, scheduled valve closure, etc.) shall not fall
below 1.0 barg above top of pipe. Exceptions may be acceptable in direct proximity to reservoirs.
Surge protection measures and protection equipment against negative pressure in the pipeline
are necessary (surge vessel plants, non-slam type automatic air valves at dedicated pipeline
highpoints). During unscheduled transient conditions the pressure in the pipelines shall not fall
below atmospheric pressure. Exceptions are given where non slam type automatic air vents are
installed. However, respective measures may be chosen to avoid the occurrence of cavitation for
cement mortar lined pipelines.
Slack line operation shall not appear in all cement mortar lined pipes during normal operation due
to its negative effects.
Vapour pressures in the cement mortar lined pipeline are to be avoided due to dangerous
pressure conditions in the vicinity of the collapsing vacuum bubbles, once the pressure starts to
rise again. Where this is not possible to be achieved by reasonable effort, the adverse effects of
negative pressures are to be avoided by respective measures (e.g. appropriate internal lining
within suction side station piping).
Valves within the main flow path which are in locked open position are to be closed at zero flow
rate only (when the pipeline is shut down). In case the valve is not in a locked position, the
transient calculations have to include an unscheduled operation (e.g. closure).
Valve operating times (closing and opening times) that are defined in the valve specifications
must be met by the installed equipment. Valve operation at the correct speed is crucial for the
hydraulic safety of the systems. The operating times can be specified as a minimum value/speed
(defined time or faster), a maximum value/speed (defined time or slower) or as an exact
value/speed (no deviations allowed, neither faster nor slower).
Controller parameters, set points, ramp function, software, etc. must at all time be adjustable (adj.
SYSAD) within a reasonable range in order to allow system tunings or modifications.
For the proposed pipeline system, reference is made to the following documents:
QP50-D-1150 Hydraulic Profile, Shoaiba Quaiza B WTS
5.3.1 General
The philosophy of operation is based on the requirement that the operation has to be as safe and
reliable as possible to guarantee a continuous water conveyance.
A further requirement is that the operation of the pipeline has to be as economic and as simple as
possible in order to reduce the number of highly qualified personnel, required to operate the
System, to a minimum.
To provide centralized and partly automatic operation, an advanced industrial remote control,
communication and central control / supervisory system shall be implemented.
The responsibility for safe operation of the Pipeline System has to be transferred as much as
possible from the operating personnel to the electro / mechanical equipment and, if additionally
required, to the electronic equipment by the implementation of automatic safety functions and
sequences. For increased reliability even in case of a major failure of equipment, which is
foreseen for centralized remote operation, provisions have to be made for local operation from
station and unit level.
In the following chapters the basic requirements for the operation of the pipeline system is
summarized. The main control and regulation loops which are foreseen for the lines and stations
are shown in the System Flow Diagrams and in the individual P&I Diagrams.
SQWTS-B shall fully be integrated in the Shoaiba WPCC. The following requirements are in line
with the implementation in WPCC. In case of deviations the current installed requirements
prevailing and are applicable also for the SQWTS-B system installation.
The SQWTS-B with all relevant stations is to be designed for remote control and monitoring from
the Shoaiba WPCC located within SWCC Shoaiba Pumping Station area.
The possibility to control the systems or parts of it at central, station or unit level (where
applicable) in automatic and/or manual operation modes shall be provided. Field, units and
stations shall allow local as well as remote control.
In automatic mode the system, station and unit control functions support the operator with
command proposals and also performs sequences automatically.
In manual mode, at the appropriate control level, each command has to be initiated by the
operator. At system level the operator shall be supported by station and unit automatic functions,
whereas at station level only unit automatic functions shall be available. A switch to full manual
operation shall also be supported by the system, which means that all logic and closed loop
functions of the control system are not active and the responsibility for operation of the system
rests on the shoulders of the operators.
Safety and ESD functions shall always be active, independent of the operation mode.
Normal System operation shall be performed from WPCC, either in automatic or in manual
operation. In case of communication failure or on demand the operation and control may be
performed locally from the station operators under supervision of the pipeline operator (either by
remote monitoring or telephone instructions).
At WPCC the following operation and control modes must be provided:
Central Automatic:
In this mode, the pipeline system is operated from the Control Center (WPCC) with the
assistance of command proposals and partially also automatic commands reducing the
operator input to a minimum.
Central Manual:
In this mode, the pipeline system is operated from the Control Center (WPCC) using all the
information of advanced display and control facilities but requiring manual commands by
the operator.
In each station the following local control and operation modes must be provided to allow local
operation from the station control room respectively from unit or field level:
Station Automatic:
In this mode, the station is operated by the station personnel. The station personnel is
supported by the station and unit control with logic and closed loop functions which serve to
reduce the manual commands to a minimum.
Station Manual:
In this mode the station is operated locally at station and unit control level. The logic and
closed loop functions of the station control are inactive, whereas unit control logic and
control functions are still supporting. In this mode the station operator shoulders the
greatest amount of responsibility of all the above mentioned modes.
This mode will therefore only be used if absolutely necessary on account of failure in the
operation modes of higher levels or for maintenance and test purposes.
For further details on control levels, operation modes, control modes and control authority refer to
“S04 Distributed Control System”, doc. no. QC10-H-124.
5.5.1 General
The safety programs shall guarantee the safe operation of the system in case of upset conditions.
Upset conditions in the pipeline system have to be recognized and counter measures have to be
initiated within defined periods, in order to meet the requirement for operational safety and
operation at the highest possible throughput rate.
Safety monitoring and control shall in general be performed from the Control Centre (WPCC),
where all information on the pipeline system, as transmitted by the communication facilities is
available.
In the event of a communication failure, it is still possible to continue operation of the SQWTS-B at
full flow rate.
Safety monitoring and control shall make use of the following hardware installations:
The system consists of a pressurized and a gravity section. The supply at the gravity section is
bound to the water demand at the receiving stations only. The supply at the pressurized section is
described in the following 2 sections.
The calculated value controls the Pump Low Flow Protection (PLFP) and Pump High Flow
Protection (PHFP) of the pumps.
Alarms shall be triggered if the present flow conditions are beyond the allowable range (tolerance
of +/- 5 % of defined set-points). An automatic start-up of the pumps is not foreseen. Any pump
start is subject to the Operator’s responsibility.
driven by speed regulated motors. Thus the pumps can be kept within the operating range by
varying the pump speed. In case of low flow conditions (pumps are operating on the left hand side
of the allowable operation range) a running pump must be stopped after a time lapse of 180 sec.
(adj. SYSAD).
5.8.1 General
The main station control regulation loops, which are necessary for overall station and system
control, are described in the following chapters. Reference is made to the P&I Diagrams, see
reference documents.
Set-points are set either by the Operator or by the application software from control centre or by
the station safety sequences at the stations. The control loops are normally active. Only in
exceptional cases (testing, etc.) shall operation without these regulation loops be possible.
5.9.1 General
In general the undisturbed operation of the pipeline systems shall be possible also with single
equipment failure. Consequently the equipment design must include the necessary spare
capacities and stand-by units. This requirement must be considered for all disciplines as
described in detail in the pertinent chapters in this specification and in the technical specifications.
surge vessel is not available (e.g. due to maintenance reasons). During normal operation all
installed surge vessels shall be on duty.
5.9.6 Instrumentation
For the following process instrumentation equipment a configuration N+1 will be foreseen
Level Transmitter in case only one (1) tank/vessel at a certain location shall be foreseen. If
more than one tank will be foreseen at a certain location no redundancy shall be
considered as the redundancy is given with the number of tanks.
Pressure Transmitters, as far as relevant, for pressure control of the stations (PC, PCL or
PCH). For any other pressure transmitter no redundancy shall be foreseen.
For all safety relevant instruments such as station inlet / outlet pressure alarms (switches) a
2oo3 (two-out-of-three) configuration shall be foreseen.
For flow meters no redundancy shall be foreseen.
For each surge vessel plant two (2) vessels must be equipped with full instrumentation (see
corresponding P&I Diagram).
For instrument equipment not directly involved in operation and control of the system, such as
temperature transmitters required for the leak detection system no redundancy shall be foreseen.
Detailed steady state analyses are also to be conducted for the stations considering accurate
local losses for tees, elbows, reductions, valves, etc.
The steady state analysis is to be conducted based on Prandtl-Colebrook Formulae.
6 PIPE STATIC
6.1 General
This chapter defines the pipe design requirements for buried steel pipes of the SQWTS-B project.
It contains the necessary computation method regarding pipe stresses against internal pressure,
the empty pipes stability (buckling) and the deformations of the pipes. The design standards to be
used for these calculations are the relevant AWWA, DIN and ANSI/ASME Codes.
Shoaiba Quaiza B Water Transmission System shall be made out of welded steel pipes with
internal cement mortar lining in accordance with the “Specification M01 Steel Pipes for Mainlines”
and “Specification M03 Cement Mortar Lining”.
For the hydraulic layout the following pipe data have been used. Pipe type and length thereof is
indicated in the Hydraulic Profile drawing. A weld joint factor of 1.0 and a safety factor of
1/0.72=1.389 are considered.
Weld
Wall- Outer Steel Safety Yield Stress
Joint INTERNAL PRESSURE
thickness Diameter Grade Factor Strength Value
Factor
MAOP MAOP +
t Da - - SMYS E S
10 %
[mm] [mm] [-] [-] [Mpa] [-] [Mpa] [bar] [bar]
Diameter 88"
17.48 2,235.2 X42 1.389 290.00 1.00 208.80 32.66 35.92
Diameter 72"
14.27 1,828.8 X42 1.389 290.00 1.00 208.80 31.43 34.57
6.2.1 Loads
a) Pressure
The maximum internal pressure for the new pipelines is indicated in the Hydraulic Profile at
every single location along the pipeline. The minimum internal pressure, the vacuum
pressure, is -0.10 N/mm² (14.50 psi).
b) Earth Fill
The weight of earth (backfill) material is assumed to be 20 kN/m³ (127 lb/ft3 = 0.0737 lb/in³).
This corresponds to medium compacted well graded gravels and gravel – sand mixtures
(acc. to AWWA M11, 5th Edition, Table 6-2).
c) Weight of Water
The weight of water is 9.81 kN/m³ (62.4 lb/ft3 = 0.0361 lb/in³). Groundwater above top of pipe
is not considered.
d) Traffic Loads
For pipes outside of right of way of existing or known future roads and crossings or in
uninhabited areas, the traffic load (= live load) is, based on AWWA M11, 5th Edition, a HS-20
Truck according to AASHTO. An impact factor of 1.50 (= 50%) is included in the values of
Table 5-1 in AWWA M11, 5th Edition.
Where the pipeline is laid inside the right of way of existing or known future roads and
highways and at crossings thereof, the traffic load of a 60 t Heavy Truck (SLW 600 according
to DIN 1072) shall be adopted. An impact factor of 1.20 (= 20%) shall be applied.
Pi Do
t [mm] S 0.72 E SMYS [MPa]
20 S
t … pressure design wall thickness [mm]
Pi … internal design gauge pressure [bar]
Do … outside diameter of pipe [mm]
S … applicable allowable stress value [MPa]
0.72 … design factor = 1/1.389 (1.389 = safety factor) [-]
E … weld joint factor [-]
SMYS … specified minimum yield strength of the material [MPa]
6.3.2 Buckling
The empty pipes are subjected to external loads like the weight of the backfill material and traffic
loads and internal vapour pressure. The calculations for this type of loading shall be done
according to AWWA M11, 5th Edition for normal pipe installation.
According to clause “Buckling of Buried Pipe” of this code the following load condition is to be
applied:
Internal vacuum pressure
For verification of the external loads and the internal vacuum pressure for normal pipe
installations, the following equation applies:
In case live loads are present the internal vacuum transients need not to be considered
simultaneously and the buckling requirement is satisfied by:
6.3.3 Deformation
The pipe deformations due to external loadings like weight of the backfill material and traffic loads
shall be calculated according to AWWA M11, 5th Edition, considering the following cases of live
loads.
For all pipes and for all cases this deformation shall be limited to 3% of the outside diameter of the
steel pipe.
For pipes outside of right of way of existing or known future roads and crossings or in uninhabited
areas, where a HS-20 Truck according to AASHTO shall be applied as traffic load, no compaction
of the backfill material is required.
The minimum earth cover is 1.0 m measured from natural respectively graded surface. The
maximum earth cover is depicted in the following table, based on a compaction level of 85% as
per table 5-3 of AWWA M11, 5th Edition.
Where the pipe is laid inside the right of way of existing or future roads and crossings a traffic load
of a 60 t Heavy Truck (SLW 600 according to DIN 1072) shall be adopted. The backfill
compaction shall be at least equal to 95% standard Proctor density
The minimum earth cover is 1.1 m. The maximum earth cover is depicted in the following table,
based on a compaction level of 95% as per table 5-3 of AWWA M11, 5th Edition.
The above values for allowable pipe covers are given in meters and are preliminary and subject of
further calculations by the Contractor. Higher earth covers are subject to approval by the
Engineer.
The allowable pipe covers are highly dependent on the existing respectively backfilled soil and
achieved degree of compaction of the padding material and the surrounding soil. The values
above are based on soil type “Fine-grained soils: CL, ML, (or CL-ML, CL/ML, ML/CL) with 25% or
less retained on a No. 200 sieve” according to Table 5-3 of AWWA M11, 5th Edition. In pipeline
sections where better soil conditions can be found or where higher compaction is carried out, the
Contractor can re-calculate the pipe cover limits according to the above described procedure after
verification of the input values on site.
For station piping reference is also made to M19 “Fabrication and Installation of Station Piping”,
Doc. No. QC10-H-059.
7 PIPELINES
7.1 General
The pipeline route corridor is described in the Route Verification Report. This report provides an
overview on the main route for the Shoaiba Quaiza B Water Transmission System.
The Route Report (QB10-G-1003) and Overall Route map (QO10-U-1125) is included in the
Volume XIII of the tender documents. An overview of the route can be also found as google
earth kmz in Volume XIII of the tender documents.
Starting point of the Shoaiba Quaiza B WTS is the new Shoaiba Quaiza Pump Station PS-SH at
the existing SWCC Shoaiba desalination plant facility. A reservoir station RS-JE is planned at
Jeddah, approximately kilometer 102.7. The end point of the Shoaiba Quaiza B WTS is located at
the existing tanks of Reservoir Quaiza, approximately kilometer 121.7.
The supplies and works given below are to be performed by the Contractor based on the
appropriate Specifications. This list does not claim to be complete:
Obtaining all authorizations and permits for the performance of the works
Provision of a survey team during construction for land expropriation
Assessment of existing conditions (roads, houses, structures, agricultural land, etc.) before
commencement of construction works
Surveying the pipeline route and soil investigation works
Determination of the number and type of bends including procurement, lining and coating of
all bends
Preparation, staking out and grading of the working strip including the implementation of the
construction road
Construction of access roads from public roads to pipe storage areas and pipeline route
Performance of all survey works necessary in connection with the earthworks and pipe
laying
Locating of the existing above and underground facilities
Protection of the existing pipelines within the common ROW
Determination of the location of vent, drain and washout stations
External coating and internal lining of the bare pipes
Excavation of trench
Transport and laying of the pipes and performance of all required non-destructive tests
Installation of the entire equipment
Keeping of a pipe log (pipe record/book)
Supply and installation of protection conduits for the communication cable in accordance
with the specifications (see also chapter 16.2).
Installation of the temporary and permanent cathodic protection system
Application of lining at welding seams and repair of damaged lining
Coating of welding seams, Tee - pieces and fittings, repair of damaged coating and
insulation testing
Backfilling of trenches, restoration of working strip and all access roads
Provide proper drainage of surface water along the complete pipeline route
Construction of the maintenance road where no access from public roads is possible
Construction of access roads to drain, vent and washout stations and to all feed-in stations
for cathodic protection, as far as required
Installation of all type of pipeline markers
Performance of hydrostatic pressure tests of pipelines and related equipment
Maintaining the water quality in the pipes from the time of the hydrostatic test to the
commencement of commissioning/start up
Reinstatement of ROW
7.5.1 General
In general, for all special points the following procedure is valid:
For all works close to existing or foreign facilities, the Contractor has to apply for and obtain
work permits from the pertinent owner and/or authorities. However, the Contractor will still
be liable for damage.
The Contractor has to make a detailed field survey with staking of the exact alignment of
the pipeline to be constructed and exact determination of the location of existing facilities
such as crossings of existing facilities, or laying of the new line parallel to existing pipelines,
power lines, or within roads.
The Contractor has to investigate the soil conditions at the complete route, but especially at
the above mentioned locations (crossings, etc.) in order to determine the appropriate work
methods.
The Contractor is to prepare a detailed design for each individual crossing or special point
in accordance with the typical drawings and the Specifications. The design must include the
traffic load and additional requirements at areas where the line is laid within the existing or
future roads or other third party corridors. These detailed designs shall be submitted to the
Engineer. After a preliminary check by the Engineer, the design is to be approved by the
pertinent Owner and Authorities and subsequently submitted to the Engineer for final
approval.
Summarizing the main constraints for construction along the pipeline routes, these will be as
follows:
Excavation and re-installation of buried cables (electrical, fibre optical and telephone) and
pipes which are situated within the pipeline route corridor (also where the pipeline is laid
within ROW of roads).
Relocation of OHTL poles or other above ground obstacles
Contractor is responsible to consider all precautions during construction of the new pipeline in
parallel to existing pipelines in order to avoid any damage or other negative impact on the existing
pipelines (e.g. settlements, deformations) and its coating and lining. It is Contractor’s
responsibility to investigate the as-built situation of the existing pipelines on site and adapt the
routing of the new pipeline accordingly. Any damages on existing pipelines occurred during
construction of the new system shall be repaired by the Contractor immediately. Special caution in
this respect is required for sections parallel to existing pipelines made of concrete pipe.
The detailed construction constraints along the route are listed in the chapters below. It is clearly
stated that the lists are not complete, and depending on the results of the topographical surveys,
as well as on the Contractor´s own investigations, additional construction requirements apply. All
lengths and KPs given below are approximate figures and have to be verified by the Contractor.
No extra payment will be allowed in case respective lengths are underestimated or if the below list
or specific requirements mentioned in the tender documents are incomplete (for example due to
missing crossings in the list or in case the route has to be shifted to other side of existing road,
OHL, pipeline and back again due to technical requirements or as a result of coordination with
third parties).
As a general rule for the project, all pipes shall be laid in a pipe trench excavated in undisturbed
soil or rock (only exception is inland Sabkha). No pipe laying in artificial backfill, dumped material
or unstable soil is allowed. Furthermore, pipe laying in Wadis is not permitted. Wadi crossings
shall be perpendicular to the flow direction and crossing lengths shall be minimized. Wadi
protection shall be designed for the pipeline lifetime and developed by an expert with pertinent
experience.
7.5.2 Major Construction Constraints 88’’ Pipeline PS-SH to RS-JE (KP 0.0-102.7)
Referring to the Route Verification Report following constraints have been discovered. It is clearly
stated that the lists are not complete, and depending on the results of the topographical surveys,
as well as on the Contractor´s own investigations, additional construction requirements apply.
7.5.2.1 Coastal Plain - Sabkha
Between approx. KP 0 and 50.0 the route crosses the coastal plain adjacent to the Arabian Gulf
with elevations of max. a few meters above sea level. Consequently high groundwater table and
the occurrence of Sabkha have to be expected throughout this section. Consequently the risk of
high groundwater table, aggressive soil and groundwater, as well as soil with low bearing capacity
have to be investigated during detailed design and adequate mitigation measures shall be
foreseen if required.
1.6 2 High
8.8 2 High
57.8 2 High
79.1 3 High
87.9 2 High
89.4 1 High
97.5 1 High
98.1 1 High
98.5 1 High
99.3 1 High
7.5.2.6 Crossing of Highways and its interchanges, National Roads and Minor Road
109.36 109.40 40
109.50 109.75 250
111.37 111.92 550
114.77 114.80 30
114.29 114.34 50
114.47 114.62 150
115.31 115.38 70
115.46 115.60 140
115.75 116.16 410
7.5.3 Major Construction Constraints 72’’ Pipeline RS-JE to TI-QA (KP 102.7-121.7)
Referring to the Route Verification Report following constraints have been discovered. It is clearly
stated that the lists are not complete, and depending on the results of the topographical surveys,
as well as on the Contractor´s own investigations, additional construction requirements apply.
102.3 1 High
102.9 1 High
103.3 2 High
105.0 2 High
116.5 1 High
119.4 1 High
7.5.3.7 Installation of Pipeline within road areas at sections with limited space
To avoid to total closure of roads at such special sections Contractor is requested to apply special
pipe installation methods.
Whenever necessary trenchless pipe installation method shall be applied and respective cost to
be considered in the offer of the Contractor.
Alternatively construction method shall be optimized by reduced length of sections at which trench
width is limited as much as feasible. Instead of wide trench a state of the art trench support
system shall be installed. In addition Contractor shall consider installing prefabricated sections of
pipes (double or triple joint) to limit welding in confined space and reduce actual time of open
trench. For such sections excavation material cannot be stored beside the trench but has to be
brought to a storage area and re-imported after pipe laying for backfilling purpose. Same applies
for pipes which cannot be strung along these sections.
Total road closure shall be avoided at any circumstances. Whenever feasible at least one traffic
lane of the road must be maintained to allow traffic to flow and access of inhabitants to their living
or working quarters.
Contractor to provide detail description of work procedure to be applied for pipe laying at these
special sections including the equipment which is required as part of their technical offer.
7.5.3.8 Detour at Truck Filling Station for Potable Water next to TI-QA
Close to the existing Reservoir Station Quaiza a tank filling station provides potable water for
tanker trucks. These trucks provide water for local inhabitants. Due to the high frequency of traffic
at this area a traffic concept with detours and/or one-way regulations will be needed during pipe
laying works. The contractor is responsible to provide all necessary measurements to guarantee
an uninterrupted flow of traffic especially in the last kilometre of the 72’’ gravity line.
8 STATIONS
8.1 Scope
The information contained in this chapter shall give a clear picture pertaining to the general
arrangement and layout of the major components at the various stations.
For the pump station, reservoir station and the endpoint station a general layout drawing is
provided showing the arrangement of the buildings, structures and the main piping with
appurtenances. For other auxiliary stations like vent- and drain stations, typical drawings are
prepared.
8.2.1 General
Shoaiba Quaiza Pump Station – PS-SH for SQWTS-B, including the new storage tanks and pump
group, is located at Shoaiba next to the existing facilities for Shoaiba Desalination plants phase 1
to 4. The new erected tanks at this station will operate in pool with tanks from Phase 2,3 and 4.
Also included is the new storage area with a storage building and all necessary facilities. The
Pump station will be inside an overall HCIS Class 1 Perimeter fence of SWCC.
For the design flow rate of the pump group to reference is made to chapter 3.2.
For reference see the following drawings:
QP20-D-1210 Shoaiba Quaiza Pump Station, Tank Farm, P&I Diagram
QP20-D-1211 Shoaiba Quaiza Pump Station, Station Inlet and Booster Pumps, P&I
Diagram
QP20-D-1212 Shoaiba Quaiza Pump Station, Main Pumps and Station Outlet, P&I
Diagram
QP10-Q-1310 Shoaiba Quaiza Pump Station (PS-SH) and Tank Farm, General Overview
QP10-Q-1311 Shoaiba Quaiza Pump Station (PS-SH) and Tank Farm, General Layout
QP10-Q-1312 Shoaiba Quaiza Pump Station (PS-SH), General Layout
QP10-Q-1314 Shoaiba Quaiza Storage Area, General Layout
design flow rate of the connected pump group(s) nor to the incoming supply lines.
The tank inlet header and individual tank inlet piping including all valves and fittings an
connection to the existing 64’’ pipe from desalination plant Phase 4 to tank farm Phase 4,
including all valves and fittings.
The tank outlet header and individual tank outlet piping including all valves and fittings.
The suction header for connection of the booster pump units and the individual booster
pump suction piping including valves, temporary strainers and fittings.
The piping between the booster and main pump units and the individual booster pump
discharge and main pump suction piping, including valves and fittings.
The main pump discharge header, the individual main pump discharge piping and the
station outlet piping including valves, flow meter, and filling by-passes.
The recirculation bypass piping for the booster and main pumps including all necessary
valves, control valves and flow meter.
The surge vessel plant piping at the station outlets.
Connection piping for pool operation with Shoaiba Phase 4 including valves and fittings
and relocation of existing valve inside tank farm Phase 4.
All required vents, drains, valves and fittings and any other piping and equipment not listed
above but shown on the drawings respectively as necessary for proper function of the
pump station.
For more detailed description of piping and mechanical components reference is made to chapter
9 and 13.
More detailed descriptions and requirements for electrical works can be found in chapter 14 and
21, and for instrumentation and control works reference is made to chapter 15.
All earthworks incl. dewatering and soil improvement, especially for the provision of
platform for the entire station and tank farm area of defined elevations (two levels
applicable), including the provided area for SQWTS-B facilities.
All earthworks incl. dewatering and soil improvement, especially for the provision of
platform for the entire storage area, including the provided area for SQWTS-B facilities.
The concrete ring foundations for the steel tanks.
The foundations for the tank inlet, outlet and overflow piping supports.
All structures required for the overflow and drainage system of the tanks, including the sea
outfall pipe.
The booster pump house including foundations to accommodate the booster pump units
and all related piping, valves, CWS and associated process equipment.
The main pump house including foundations to accommodate the main pump units and all
related piping, valves and associated process equipment.
Separate VSD Buildings and VSD transformer structures to house the VSD units for the
main pump motors including all related cabling, cooling piping, chillers, HVAC and
associated process equipment.
The electrical building to house the medium voltage and low voltage switchgears, a battery
room, station control facilities as well as offices, sanitary rooms and further rooms indicated
on the drawings.
The water quality monitoring building
Car sheds
The foundations for the surge vessels and air compressor container etc.
For detailed information on civil works and buildings reference is made to chapters 10, 11 and 12.
8.3.1 General
The Reservoir Station Jeddah South East (RS-JE) being the endpoint of the 88” pipeline of
SQWTS-B, with two (2) steel tanks of a capacity of 170,000 m3 each and four (4) future steel
tanks of a capacity of 170,000 m³, is located at Jeddah. The station platform must be built for all
six (6) tanks but only two (2) steel tanks á 170,000 m³ are included in the scope and will be erect.
For reference see the following drawings:
QP20-D-1220 Reservoir Station Jeddah South East, P&I Diagram
QP10-Q-1320 Reservoir Station Jeddah South East (RS-JE), General Layout
Station inlet and outlet piping including isolation couplings, valves and flow metering
facilities.
All required vents, drains, valves and fittings and any other piping and equipment not listed
above but shown on the drawings respectively as necessary for proper function of the
reservoir station.
For more detailed description of piping and mechanical components reference is made to chapter
13.
More detailed descriptions and requirements for electrical works can be found in chapter 14, and
for instrumentation and control works reference is made to chapter 15.
All earthworks for provision of platform for the tank area for six (6) tanks and inlet facilities
for SQWTS-B.
Slope protection, where slope flattening, erosion, slope collapse and rock fall protection
measures have to be applied. High rock slopes have to be assessed by a geologist and
protected with anchors or intermediate berms.
Rock excavation and backfilling for the entire station platform.
The tank concrete foundations for two (2) steel tanks.
All cable ducts and shafts for all underground equipment such as valves, flow meters,
instrumentation and all other subsystems.
Civil infrastructure such as roads, trenches, paving, lighting, etc. as per their requirements.
Car shed
Civil infrastructures for drainage for storm water and overflow as per their requirements.
An overflow and drainage pipe with approximately 4 km length to the storm water channel
northwest of the reservoir station.
Civil infrastructures for utility water and sewage incl. a septic tank as per their requirements.
All civil works related to power supply from electrical building as per their requirements.
External facilities such as the connection road from the station to the public road network as
per their requirements.
An electrical building type 2 including a platform for the emergency generator and all
necessary civil works.
All works for HCIS requirements according to HCIS standard an stipulations in chapter 4.2.
For detailed information on civil works and buildings reference is made to chapters 10, 11 and 12.
8.4.1 General
The Tie-in Station Quaiza is connecting the 72” main pipeline to the existing Reservoir Station
Quaiza and will be the endpoint of the SQWTS-B. The connection shall be at the spare inlet
nozzle at the existing 90,000m³ steel tank at the reservoir station.
For reference see the following drawings:
QP20-D-1230 Tie-In Station, Quaiza, P&I Diagram
QP10-Q-1330 Tie-In Station Quaiza, General Layout
Station inlet piping including isolation coupling, valves, metering facilities, control valves,
flow and water quality metering.
All required vents, drains, valves and fittings and any other piping and equipment not listed
above but shown on the drawings respectively as necessary for proper function of the tie-in
station.
Connection to existing inlet spare nozzle at 90,000 m³ steel tank.
For more detailed description of piping and mechanical components reference is made to chapter
13.
Equipment and cabling for power supply from existing electrical building at Reservoir
Station Quaiza.
Extension of existing low voltage and UPS system for implementing the power supply to
the new installed equipment
All power supply installations associated with valves and auxiliary process systems such
as control valves.
Level transmitters or provision of level signal from Quaiza tanks including cabling to the
tie-in station.
Instrumentation and control equipment, including unit control and station control.
More detailed descriptions and requirements for electrical works can be found in chapter 14, and
for instrumentation and control works reference is made to chapter 15.
The following battery limits between station construction and pipe laying shall apply:
The following main contract limits are valid for the project:
9.1 General
The steel storage tanks shall be designed and constructed in accordance with the technical
requirements as defined in the chapters below.
The water tanks to be erected at above mentioned locations shall be flat bottom welded steel
tanks. At the PS-SH tank farm 4 (four) tanks shall be constructed with aluminum dome roofs. For
the 2 (two) tanks at RS-JE aluminum dome roofs are foreseen. The tanks shall be designed and
constructed in accordance with the “Specification M09 Steel Tanks”, Doc. No. QC10-H-049. For
tanks with aluminum dome roof the requirements as per API 650, Appendix G shall be
considered. For the internal cathodic protection reference is made to the above mentioned
standard specification M 09, for the cathodic protection of the tank bottom reference is made to
the “Specification E16 Cathodic Protection”, Doc. No. QC10-H-096.
Vent pipes for filling lines and roof vents shall be designed well above the full inlet/outlet air flow
rates.
In order to avoid large dead volumes, the min. water level in the tanks shall be 0.3 m above the
bottom plate. For this purpose the outlet piping will be extended into a pit. Hydraulic verification of
the outlet configuration shall be provided during detailed design, in order to avoid air intake during
operation at low water levels.
All tanks will be equipped with bottom outlet only.
If the roof will be built as dome roof, the roof shall be supported only from the rim of the tank. No
sliding supports between roof and tank shell shall be considered. A tension ring shall be provided
at the interface between roof and shell.
A Finite Element Analysis of the roof structure shall be prepared considering non-linear effects
(buckling). Close collaboration between roof designer and tank designer is mandatory. The
stiffness of the tank shell considered for roof calculation shall be based on the actual tank layout
and determined by a structural analysis. The shell design shall consider all loads from the roof.
For roof and shell design special attention shall be given to non-symmetric load cases (wind,
seismic) and eccentric loads.
All Materials for the tanks (concrete, steel, aluminium, etc.) must be chosen accordingly to all
possible impacts, including chemical attacks from close by facilities (e.g. higher sulphur
concentration in air or rain).
Prior to commencement of construction of the tank foundations soil exploration activities have to
be carried out by the Contractor to ensure that soil conditions at the tank area will be suitable for
the expected loads.
In case of unsuitable bearing conditions, the existing ground conditions shall be improved by a
suitable subsoil improvement method, e.g. but not limited to stone columns, preloading.
The shell of the steel tanks shall rest on a ring beam of reinforced concrete of adequate width.
The bottom plate of the tanks shall be laid on a layer of 300 mm of clean washed sand. The final
surface of the sand layer shall have an inclination of 1.0% rising to the tank centre. Below the
sand a layer of well compacted road base material of approx. 500 mm thickness shall be placed.
The road base material shall be supported by subsoil which has to be compacted to 100% proctor
density.
Depending on the chosen method for cathodic protection of the tank bottom (reference is made to
specification E16 “Cathodic Protection”) an additional, isolating layer (e.g. HDPE foil) will be
required, underneath the anode grid, below the tank bottom.
In order to avoid excessive stresses due to tank shell bulging or differential settlements, the inlet
and outlet piping shall be separated from the station piping with an unrestraint bellow expansion
joint. For top inlets a fixed pipe support shall be provided on both sides of the expansion joint to
account for the thrust force. In case of bottom outlet a fixed support shall be provided on the
downstream side of the expansion joint.
The location and design of the pipe supports inside and outside the tank shall be designed to
meet structural requirements (pipe and tank) and to avoid vibrations at max. flowrate.
9.4 New 150,000 m3 Steel Tanks at Tank Farm Shoaiba Quaiza Pump Station
Four (4) steel tanks with a capacity of 150,000 m³ each are foreseen at the station. The roofs shall
be constructed as aluminum dome roofs to ensure easier maintenance.
Reference is made to the following typical drawings:
QP20-D-1210 Shoaiba Quaiza Pump Station, Tank Farm, P&I Diagram
QP10-Q-1408 "Typical Steel Tank 150,000m³, Shoaiba Quaiza Pump Station (PS-SH),
General Arrangement"
For complete drainage in case of tank isolation it shall be possible to install mobile transfer pumps
at the drain lines to allow saving of water. For this purpose mobile electric driven pump units shall
be provided and suitably sized to allow draining the rest water (water which cannot be pumped
into the main system) within approximately eight (8) hours into a neighboring tank.
For connection of the mobile pumps each tank shall be equipped with two (2) 12” pump out
nozzles including shut off valve and blind flange (in addition to the regular drain connections). At
each 12” pump out a pump basement and a power connection for the mobile pump unit shall be
provided as well as the necessary flexible hose pipes. Two (2) mobile pump units shall be
supplied per station. They shall be equipped with a self-actuated flow control valve to avoid high
flows at low discharge pressures.
For the tanks a minimum of 15 boreholes shall be made per tank with depths varying between 30
and 50 m. The total number and depths of boreholes to be defined by soil expert. In order to
define extent of individual subsoil layers the investigations shall be supplemented by suitable
geophysical methods. In case soil investigation demonstrate the existence of karstified limestone,
more detailed investigations to assess the karst risk are required.
Based on above investigations geological and geotechnical sectional drawings shall be prepared
as input for the 3D settlement calculations to be performed for each tank. The required
geotechnical parameters shall be determined by suitable investigations methods (e.g. SPT, plate
load tests).
9.5 New 170,000 m3 Steel Tanks at Reservoir Station Jeddah South East
Two (2) steel tanks with a capacity of 170,000 m³ each are foreseen at the station.
Reference is made to the following typical drawings:
QP10-Q-1409 Typical Steel Tank 170,000m³, Reservoir Station Jeddah South East,
General Arrangement
QP20-D-1220 Reservoir Station Jeddah South East P&I Diagram
into the main system) within approximately eight (8) hours into a neighboring tank.
For connection of the mobile pumps each tank shall be equipped with two (2) 12” pump out
nozzles including shut off valve and blind flange (in addition to the regular drain connections). At
each 12” pump out a pump basement and a power connection for the mobile pump unit shall be
provided as well as the necessary flexible hose pipes. Two (2) mobile pump units shall be
supplied per station. They shall be equipped with a self-actuated flow control valve to avoid high
flows at low discharge pressures.
For the tanks a minimum of 15 boreholes shall be made per tank with depths varying between 30
and 50 m. The total number and depths of boreholes to be defined by soil expert and may be
reduced in case rock is prevailing. In order to define extent of individual subsoil layers the
investigations shall be supplemented by suitable geophysical methods. In case soil investigation
demonstrate the existence of karstified limestone, more detailed investigations to assess the karst
risk are required.
Based on above investigations geological and geotechnical sectional drawings shall be prepared
as input for the 3D settlement calculations to be performed for each tank. The required
geotechnical parameters shall be determined by suitable investigations methods (e.g. SPT, plate
load tests).
10 STATION BUILDINGS
10.1 General
This chapter describes the layout and construction requirements for the buildings to be erected at
the various stations of the SHOAIBA QUAIZA B WATER TRANSMISSION SYSTEM.
The building layout of the individual buildings is shown in the respective building drawings
The arrangement of the buildings within the stations is shown on the general layout drawings of
the respective stations.
As a general rule the design of the buildings shall be identical for all stations, if not specified
otherwise.
10.2 Buildings
General Description
Two buildings are to house booster / main pumps and the motor units as well as all related
piping facilities, valves and subsystems and lay-down areas. Depending on the length of
the pump houses, the pump houses will be divided by expansion joints (and/or settlement
joints).
The areas for the cooling water system is provided inside of the booster pump house. Also
an area for control panels of HVAC is provided inside of the booster pump house.
The pump houses are equipped with overhead cranes. For crane capacities please refer
chapter 13.10.
The cable ducts on one of the longitudinal sides of the pump houses and adjacent to the
longitudinal side of the VSD building will be connected with the cable cellars of the electrical
buildings via walkable cable ducts. The walkable cable ducts are accessible from the cable
cellar of the electrical building respectively from the cable duct of the pump houses. The
cable connection from walkable cable ducts to the connected buildings shall be done by fire
resistant wall penetrations. Depending on the length of the walkable cable ducts fire
compartments have to be defined and minimum one emergency exit has to be provided
from the walkable ducts.
The cable connection from VSD transformer building to the main pump house will be done
by cable conduits.
For the design of the booster pump house the Contractor has to consider the suction
requirements of the pumps regarding NPSH required and the specified minimum tank level.
Elevations shown on the drawing shall be adapted as required.
For arrangement of ventilation equipment and its support structure, the accessibility and
space for maintenance of main equipment (valves, pumps, motors, etc.) as well as of the
ventilation equipment itself has to be considered. HVAC equipment shall be placed in front
of the building, if possible. If any equipment needs to be protected from weather an
additional protection must be installed.
The elevation of the finished floor level is 0.20 m above station level respectively according
respective building drawings.
For layout and size reference is made to the above mentioned drawings.
Construction
Foundations:
Reinforced concrete foundation slabs (watertight), individual footings for the pump and
motor units (separated from foundation slab and encased in a watertight pit) and pipe and
valve support pedestals.
Load bearing structures:
Below ground: Reinforced concrete walls (water tight) and columns
Above ground: Columns, trusses and longitudinal girders, cantilevering runway girders and
shoulders for crane beam as well as wind bracings made of steel.
Walls:
Below ground: Reinforced concrete walls, watertight.
Above ground: Precast concrete sandwich panels with thermal insulation of min. 80 mm in
between. Inner shell of concrete panels is fair faced and outer shell is beige coloured (by
adding pigments in concrete – colour to be approved by Engineer). Interior surface painted
with dispersion paint, colour selected by Engineer, exterior surface sandblasted
Roofs:
Flat roofs made of precast reinforced concrete slabs with inverted roof construction with
layers of bituminous felt, thermal insulation of min. 100 mm and concrete tiles. Roof
drainage by means of down pipe reservoirs, and down pipes on one longitudinal side.
Smoke escapes in sufficient number have to be provided as well as access to the roofs
(e.g. mounted ladders).
Floors:
Sloped cement screed with slope away from cable ducts. Drainage channels with
connection to drainage system have to be provided. Manholes will be covered by
chequered steel plates. The cable ducts are covered with precast concrete slabs. Pump
sumps covered with grating are provided within the cable ducts.
Windows:
Window strips on both longitudinal sides with fixed glass. Sunscreen according room book
and drawings.
Doors:
Electrically driven sectional doors of aluminum with thermally insulated panels and
pedestrian doors.
Single doors, material and finishing is described in chapter 11.2.5.
Sanitary installations:
Sinks and hose connections in sufficient number have to be provided.
General Description
The electrical building is a one storey structure and will house the LV/MV and control
installations for pipeline and station control as well as offices, a meeting room, a prayer
room with ablution, social and sanitary rooms and technical rooms (HVAC room, firefighting
equipment room, etc.).
Depending on the length of the electrical building, the building will be divided by expansion
joints (and/or settlement joints).
The building consists of a cable cellar and a ground floor. The cable cellar will be
connected by accessible, walkable cable ducts with the VSD transformer structures and
with the pump houses. The cable ducts and the building will be separated by fire walls and
fire resistant cable passages.
The elevation of the finished floor at ground floor level is 1.25 m above station level, the
finished floor level of the basement is 1.40 m below station level, respectively according to
related building drawings.
For layout and size reference is made to the above mentioned drawings.
Construction
Foundations:
Reinforced concrete slabs, watertight
Load bearing structures:
Below ground: Columns and walls made of reinforced concrete, watertight.
Above ground: Columns and beams made of reinforced concrete.
External walls:
Below ground: Reinforced concrete, water tight
Above ground: Precast concrete sandwich panels with thermal insulation of min. 80 mm in
between. Inner shell of concrete panels is fair faced and outer shell is beige coloured (by
adding pigments in concrete – colour to be approved by Engineer). Interior surface painted
with dispersion paint, colour selected by Engineer, exterior surface sandblasted
Interior walls:
Cable cellar: Reinforced concrete walls or hollow concrete block work covered with plaster.
Surfaces shall be painted, colour selected by Engineer
Above ground: Reinforced concrete walls and hollow concrete block work plastered and
painted, colour selected by Engineer. Lavatory rooms tiled (room high).
Stairs:
Stairs and pedestal made of reinforced concrete, bottom view fair faced and painted.
The cable connection between the VSD transformers and the VSD rooms and the cable
connection between the VSD building and the pump house will be done by cable conduits.
Depending on the length of the buildings, expansion joints and/or settlement joints shall be
implemented.
For the elevation of the finished floor, layout and size of the buildings refer to the respective
building drawings.
Separation walls:
Interior walls are 120 min fire rated walls made of reinforced concrete with visible aggregate
surface.
Floors:
Double floor partly covered by grating or reinforced concrete.
Doors:
The double door and single doors are constructed of aluminium or steel profiles with wire
mesh
General Description
The storage building is one-storey building and will house a storage room. Depending on
the length of the buildings they will be dived by expansion joints. One part of the building is
equipped with a crane (refer chapter 13.10).
The elevation of the finished ground floor levels is 0.20 m above station level.
For layout and size reference is made to the above mentioned drawings.
Construction
Foundations:
Individual footings for the steel columns, reinforced concrete slab with skirting of reinforced
concrete.
Load bearing Structure:
Columns, trussed girders and longitudinal girders, cantilevering runway girders and
shoulders for crane beam as well as wind bracings made of steel.
External Walls and roofs:
Metal sandwich panels consisting of an external and an internal metal sheet with thermal
insulation core. Insulation core will be of structural grade mineral fibre wool, minimum
thickness of insulation core 100 mm. Panel finish will be pre-applied polyester coating.
Standard colour according manufacturer, colour selected by Engineer. Roof drainage by
means of down pipe reservoirs, and down pipes on one longitudinal side. Access to the roof
(e.g. mounted ladders) has to be provided.
Floors:
composite cement screed with heavy duty top coating.
Windows:
Windows and window strips, sashes opening to the inside. Sunscreen according drawings
and room book.
Doors:
Exterior doors shall be either double leaf doors or single doors. Material and finishing is
described in chapter 11.2.5.
General Description
The car sheds are standard structures and comprise canopied parking areas. The size of
clear parking spot shall be minimum 2.70 m x 5.50 m (width x length). The number of
parking spots can be depicted in the respective station layout drawings.
Construction
Foundations:
Single reinforced concrete foundations under columns.
Load bearing structures:
Columns of steel profiles with cantilever galvanized steel frames above.
Roofs:
Tensioned membranes (composite material) resistant to degradation from UV rays to
erosion, colour changes, etc.
Floors:
Asphalt laid on subgrade and subbase material.
General Description
The building is to house the pumps for firefighting, the pumps for station water supply with
all related piping, valves and subsystems as well as the emergency generator rooms and
the oil storages.
Spaces for lay-down areas are provided in the firefighting pump room. The firefighting
pump room and the emergency generator room are each equipped with an overhead crane.
For crane capacities please refer chapter 13.10.
The elevation of the finished floor levels is 0.20 m above station level.
For layout and size reference is made to the above mentioned drawings.
Construction
Foundations:
Reinforced concrete foundation slab (watertight), individual footings for the pump and motor
units and the supports for pipes and valves.
General Description
The buildings are one story structures and house the water quality monitoring.
The elevation of the finished floor level is 0.30 m above station level.
For layout and size reference is made to the above mentioned drawing.
Construction
Foundations:
Reinforced concrete foundation slab with skirting (watertight) and a duct.
Walls:
Precast concrete sandwich panels with thermal insulation of min. 80 mm in between. Inner
shell of concrete panels is fair faced and outer shell is beige coloured (by adding pigments
to concrete, colour to be approved by Engineer). Interior surface painted with dispersion
11.1 General
The scope and extent of the various requirements pertaining to finishing works and building
installations is described in this chapter as well as in the pertinent specifications. The information
provided therein is intended to supplement each other.
Special attention must be given to ensure that all foundations, concrete floor slabs and the
perimeter walls of all underground structures are watertight. In general, this applies to all
underground concrete works, and is, therefore, not limited to buildings, but is rather equally valid
for retaining walls, equipment shafts, etc. All buried concrete surfaces shall in addition be
protected against any attack of harmful substances through the application of tanking membrane.
All architectural and finishing materials shall be of highest quality specification.
The Contractor shall strictly comply with the as-built situation as far as extension of existing
facilities and station areas are concerned.
11.2.1 Walls
Fire rating of external and internal walls according applicable standards and rules has to be
considered.
Except otherwise stated, external walls shall be made of precast concrete sandwich panels. The
inside concrete panels are fair faced with dispersion painted interior surface (colour selected by
Engineer). The outside concrete panels are beige colored (by adding pigments in concrete –
colour to be approved by Engineer) with sandblasted exterior surface.
The thickness of the sandwich panels shall be minimum 34 cm and is mainly depending on the
panel length and the necessary cover layer on the reinforcement. The external surface finishing of
the precast sandwich elements is subject to approval by the Engineer.
Deviating from the description above, external walls made out of reinforced concrete (thermally
insulated) plastered and painted or of metal sandwich panels.
External walls of HV substation will be of CMU (concrete masonry units) reinforced and fully
grouted. Inside surface of CMU are covered with insulation blankets (thickness approx. 70 mm)
and fire rated gypsum boards (thickness min. 16 mm). Exterior surface and interior surface of
external walls will be painted, colour selected by Engineer. Exterior surface shall be sandblasted.
Internal walls are made of reinforced concrete or hollow block work and plastered and painted.
Colour inside and outside shall be subject of approval by Engineer.
Room high porcelain tiles in wet rooms. Porcelain tiles at areas of sinks. Anti-acid porcelain tiles
up to min. 1.50 m height in battery rooms.
11.2.2 Ceilings
Below ground:
Reinforced concrete fair faced and painted (e.g. cable cellar). Colour shall be subject of approval
by Engineer.
Ground floor:
Reinforced concrete and precast reinforced concrete slab fair faced and painted.
In habitable rooms suspended ceiling with aluminium panels. Colour shall be subject of approval
by Engineer.
Battery rooms:
Composite cement screed, porcelain tiles, acid resistant, antistatic, dissipative. Skirting and
thresholds are also of porcelain tiles, acid resistant, antistatic, dissipative
Prayer rooms:
Composite cement screed, marble tiles with standard size.
Wet rooms (bathroom, toilet, etc.), HVAC room, clean agent room, store, kitchen, WQM room:
Composite cement screed, porcelain tiles with standard size.
Staircase:
Marble tiles with standard size.
Cable ducts:
Covering with heavy duty precast concrete slabs; manholes with chequered steel plate covers
have to be foreseen.
Pipe chambers and shafts:
Hot-dip galvanized gratings or chequered steel plates.
All screed / concrete surfaces shall receive a durable heavy duty PVC coating, if not protected
otherwise.
For the walkways to all the access doors of the buildings and structures, to the manholes of the
shafts and around the buildings interlock tiles of width as indicated in the drawings but min. width
of 1.50 m and with a thickness of min. 6 cm shall be foreseen. The colour and shape has to be
approved by the Engineer. The walkways shall be surrounded by curb stones (40 x 15 cm, 30 cm
11.2.4 Windows
All window frames shall be of aluminium, insulated construction.
Upper window strip with insulated glass, partly stationary, partly bottom-hung sashes. All easily
operable by hand, sand and dustproof.
In habitable rooms, sashes partly side- and bottom-hung. All with glass panes and special
dustproof.
Aluminium surfaces shall be anodized, and shall be special sand resistant.
Acoustically insulated windows for rooms with high noise level, according to the requirements of
work safety and local standards, made of acoustic panel system.
11.2.5 Doors
Fire rating of external and internal doors according applicable standards and rules has to be
considered
All exterior doors shall be either sectional doors, double leaf doors or single leaf doors of
aluminium or steel construction, insulated, metal-sheet paneled or with glass panes. Some of the
doors have an upper window strip of unbreakable, insulated glass panes.
Sectional doors:
Electrical driven, aluminium construction with thermally insulated panels and acryl glass panes.
One section with pedestrian door.
Roller-Shutter:
Electrical driven, aluminium construction with thermally insulated slats, mounted internal.
All exterior doors shall be sand- and dustproof.
Interior doors to offices consist of steel frames with wood veneer panels, room high with fan light.
Doors to technical rooms consist of steel frames and steel panels. Doors to corridors consist of
steel frames and steel panels with glass panes. Fire proof steel doors in fire walls.
Aluminium surfaces shall be anodized. Steel surfaces shall be coated.
System cylinder locks are required for all doors.
Acoustically insulated doors for rooms with high noise level, according to the requirements of work
safety and local standards, made of acoustic panel system.
11.2.7 Miscellaneous
All paints and colours are subject to approval and must be coordinated with SWCC.
Key system shall be implemented for all lockable facilities (gates, doors, shafts etc.) according to
the approved key lock system. Integration into an existing master key system is required.
11.2.8 Insulation
Thermal insulation:
External walls minimum 80 mm insulation with vapour barrier, roof insulation of min. 100 mm
thickness. Minimum thickness of insulation core of metal sandwich panels has to be 180 mm.
Acoustic Insulation:
Rooms with high noise level, according to the requirements of work safety and local standards,
have to be equipped with acoustic insulation.
Ladders, platforms, gratings, steps and handrails of steel (hot-dip galvanized) profile sections
shall be provided for all pump units, valves and other equipment to which access is required for
operation and maintenance. Handrails have to be removable. Ladder rungs have to be slip
resistant.
Offices, kitchens, social and sanitary rooms, etc. within technical buildings shall be furnished and
equipped equivalent to non-technical buildings (please refer to chapter 11.5).
For additional information reference is made to the pertinent specification. All furnishing and
equipment is subject to SWCC approval.
Furnishing and equipment of the highest quality applies for all office furniture, kitchen facilities
(including all utensils), washroom and toilet equipment, etc. to make the buildings ready for use.
For additional information reference is made to the pertinent specification. All furnishing and
equipment is subject to SWCC approval.
The buildings shall be provided with appropriate electrical installation, mainly consisting of:
Lighting system fed from the low voltage switchboards via sub distribution boards
Escape way lighting with built-in batteries
Socket outlets fed from the low voltage switchboards via sub distribution boards
Sub distribution boards, junction boxes, switches, conduits, wires, cables for the above mentioned
equipment and for all other auxiliary equipment like cranes, ventilators, etc.
Conduit system for telephone
Conduit system for office LAN (if applicable)
Conduit system for fire & gas alarm system (if applicable)
The fire detection and alarm system for the buildings is described in chapter 15.6 of this
document.
12 CIVIL WORKS
During design phase the Contractor shall submit design documents in the following sequence:
The design criteria shall not be limited to a summary of the requirements listed in the relevant
specifications but shall serve as a guideline for the subsequent design steps. These documents
shall include as minimum requirement information on the used materials, applied loads, interfaces
to other structures and disciplines, design codes, design guidelines, standard details, etc.
At least the following design criteria documents shall be prepared and submitted for approval:
The Guide Drawings of buildings shall contain equipment and installations from all disciplines
(HVAC, mechanical, electrical, instrumentation & control, etc.) and shall be based on equipment
vendor data (mechanical, electrical, HVAC, etc.) from approved manufacturers.
Along with the earthworks soil explorations are to be carried out for all stations. The
reconnaissance works shall be conducted in such a manner that the structure of the subsoil is
known completely. In the area of the tanks, pump houses, electrical and transformer buildings,
surge vessels and other station buildings a sufficient number of boreholes with dynamic subsoil
explorations have to be carried out. After the reconnaissance works the Contractor has to submit
to the Engineer a foundation proposal including the respective calculations for examination and
approval. The earthworks to be performed subsequently are to be carried out in accordance with
the specifications, paying particular attention to sufficient compaction of the subsoil.
The foundation proposal shall include soil improvement works if required. Soil improvement works
shall be designed in order to avoid negative impact on existing facilities.
The Contractor shall consider in his work approach for excavation and backfilling works at the
stations, that especially those next to or close to existing installations shall only be carried out by
hand or by the use of very small machinery. Special care shall be exercised to avoid damages to
existing installations and disruption of operation.
All backfilled or cut slopes at the Pump Station, the Reservoir, Tie-in, Vent and Drain Stations,
access roads or any other project location shall be protected against washouts or erosion by a
All paved areas including access roads, if any, as well as the internal roads of the stations shall
be constructed according to the approved plot plan, the individual longitudinal road sections, the
typical cross-sections, the pertinent contract specifications and the specifications for road and
bridge construction issued by the Ministry of Transport (MOT).
In addition to the works mentioned above all the existing roads, paved areas and sidewalks which
are damaged during the construction works have to be repaired. At the border line between roads
and station area, curb stones shall be installed and sidewalks shall be envisaged at frequently
used locations. The use and location of temporary access roads for construction have to be
discussed with and approved by SWCC, SAUDI ARAMCO, SEC, MOT operation department and
any other authorities which hold land or ROW ownership.
Rainwater will run off as a result of the longitudinal slope or cross fall of the roads and shall be
drained off via road gullies. In some cases a bituminous rim is to be constructed in order to
prevent the surface runoff from flowing to open areas.
For further details reference is made to the “Specification C04 Roads and Traffic Areas”, Doc.No.
QC10-H-144 and the typical drawings.
At areas around and between buildings inside stations asphalt roads with 6 m width with curb
stones and walkways according to type 1 (QP10-Q-1403). shall be provided. For tank areas or
inner patrol roads design of roads and traffic areas shall be according to type 2 (QP10-Q-1403).
All station access roads of the project shall be constructed with cross section as per the typical
drawing (7 m wide plus 1 m hard shoulder at each side) up to a suitable location of the public road
network approved by the road owner. Suitable location is an asphalt road of same width.
The roads and traffic areas of minor stations shall be asphalted roads according to type 2 (QP10-
Q-1403). No curb stones or road drainage is required. Access roads to such stations and pipeline
maintenance roads shall be gravel roads with 3.0 m width and 1 m hard shoulder on both sides.
The station areas, which are not protected by any other means, shall be covered by a layer of
5 cm of crushed gravel, size 5 - 20 mm.
Prior to the application of the gravel, the station areas should be graded and compacted to ensure
proper run-off of the surface water.
Reinforced concrete foundations for equipment located at the various stations shall be designed
according to the static/dynamic requirements and considering the prevailing soil conditions.
Main and booster pump foundations shall not be placed directly on the subsoil. A pit
(monolithically connected to the pump house base slab) shall be provided for the foundation
block. The pit and the block shall be separated at pit walls and base with a layer of adequate
material (Sylomer or equivalent) to fulfil the vibration requirements. Dynamic calculation to be
provided.
Shafts shall be of reinforced concrete in various thickness (min. 25 cm), watertight, according to
the typical drawings and the pertinent specifications. Shafts are required for valves, metering
equipment etc. at the Pump Station, Tie-in and Reservoir Station, as well as Drain, Vent and
Washout Stations.
The shafts shall be covered with removable concrete slabs (with lifting lugs) and equipped with
watertight access manholes (number depends on the size of the shaft), lockable type, with a
ladder and removable supporting handle. A ventilation system for the shafts (aeration pipes) is to
be foreseen. For easy access of the concrete cover slab a ladder shall be foreseen, if the
difference in elevation exceeds 600 mm.
All pipe penetrations through the shaft walls shall be provided with proper watertight maintenance-
free pipe wall ducts - Link Seal or equivalent.
All shafts located within road areas of stations or within existing or future highways along the
pipeline shall not be higher than the adjacent road area. The shaft cover shall be designed for a
traffic load of SLW 60. Ventilation pipes of shafts located within road areas shall be routed outside
the road area (edge of ROW of the road).
All shafts shall have a pump sump.
The purpose of the station water supply system is to distribute drinking and utility water inside the
pump stations and reservoir stations.
For the station water supply system the following main works shall be performed:
All piping and equipment between the take-off point of the water from the main piping and
the feeding points to the water installations of buildings, such as wash basins, hose
connections for cleaning purposes etc. are to be installed. The water shall be taken from
the product water piping.
It likewise includes the supply and installation of drinking and utility water piping within the
station area, including all valves within the drinking and utility water network.
The purpose of the sewage system for the Stations is the collection, removal and treatment of
sewage and domestic waste water.
The following main work items are listed below; however the works are not given in detail:
Complete external sewage lines including maintenance shafts; the internal installations
within buildings are part of the buildings.
If required, at the deepest point of the sewerage system a lift station shall be provided,
equipped with all installations and equipment for automatic operation.
At new Stations (incl. all minor stations where sanitary installations will be implemented)
Sewage Treatment Facilities shall be provided. Minimum requirement for minor stations is a
septic tank and soak away pit.
Close to PS-SH a new sewage treatment plant will be erected. PS-SH shall be connected
to the new facilities. Reference drawing (GE-A1-004) is provided in Volume XIII of this
tender.
At urban areas the sewage system may be connected alternatively to the public network if
available and technically feasible.
The above work items shall include all mechanical, electrical, instrumentation and control
equipment (pumps, valves, etc.) required for the proper function of the system.
Particular attention shall be paid to the requirement that no storm water shall enter the
sewage system.
For the pump houses, the transformer structures, diesel generator rooms and the air
compressor containers a separator for light liquids according the pertinent specification has
to be installed and connected to the sewage system afterwards.
For the sewage system pipe material must be chosen according to the Specification C05 –
Drainage and Sewage Systems.
shall be provided.
At existing stations the storm water drainage system of the new station area shall be connected to
the existing drainage facilities. If required existing capacities shall be extended. In case this is not
feasible, a new system shall be provided.
All stations shall be surrounded by a security fence and gates as per HCIS Security Directive
SEC-02. The gates shall meet the requirements of Security Directive SEC-03. In addition a
property fence shall be provided around complete area available to the Owner.
For construction works which will take place within existing stations, damages on the existing
fencing or boundary walls and fence lighting etc. have to be repaired by the Contractor after
completion of the installation works.
13 MECHANICAL WORKS
This chapter describes the main construction requirements for mechanical works at all stations of
the System.
As a general rule the design of the mechanical components, mechanical systems and materials
shall be identical for all Stations, if not specified otherwise.
At least the following design criteria documents for mechanical works shall be prepared and
submitted for approval:
Pressure Design of Piping and Equipment
This document shall summarize the design criteria regarding the determination of internal
design pressures of all pressure containments such as piping, fittings and equipment
including the determination of hydrostatic test pressures.
Piping and Arrangement Design
This document shall summarize the principles to be considered for the design of the piping
and the arrangement of equipment. It shall address topics like safety distances,
accessibility, required distances between installations in piping (e.g. free lengths after
control valves, straight lengths on both sides of flow meters, etc.), support requirements,
design criteria for provision of dismantling joints, expansion joints, drains, vents, safety
valves, etc.
Corrosion Prevention
This shall include a Contractor’s detailed strategy for the prevention of all kinds of corrosion
and shall cover all piping and equipment installed into and onto the product water system. It
shall address the principles of material selection and the corrosion control measures to be
taken by the equipment vendors including all internal parts coming in contact with the
conveyed water.
The strategy shall also include in detail the philosophy of the materials and execution of
flange connections. Considering that part of the flanges can come in contact with the water,
internal lining of piping and equipment shall be at least extended over raised face of the
flanges and pulled underneath of the gasket soft portion. Fillets and radii of flange edges
shall be large enough to ensure adhesion of the coating.
The document shall be prepared or at least endorsed by a corrosion expert or expert
organization which shall be subject to approval by the Employer/Engineer.
For longer suction piping to the pumps with direct impact on pump head, lower maximum
allowable flow velocities may apply. For tanks located on elevated position to the pumps,
providing sufficient NPSH, or direct connection to water networks, higher velocities up to 3.5 m/s
may be acceptable.
Higher velocities than listed above are acceptable at special piping sections only, such as control
valves, flow meters, relief valves, drain lines, surge vessel lines, etc. but shall not exceed 6 m/s.
The Contractor shall carefully check the suction requirements of the pumps with respect to NPSH
(Net Positive Suction Head) and flow pattern and if necessary lower velocities shall be selected.
For the pressure design of the piping system Contractor shall calculate the highest possible
pressures occurring in the individual piping sections, taking into account all steady and unsteady
state conditions.
The required minimum wall thickness for the station piping shall be calculated using the equation
stated in the design code ASME B 31.4. Because the station piping is internally protected by
lining, no corrosion allowance is required.
After the minimum wall thickness has been determined, the appropriate nominal wall thickness
from standard ASME B 36.10 M shall be selected. The standard manufacturing tolerances shall
be checked to confirm that the tolerance will not reduce the nominal wall thickness below the
minimum required as calculated.
In addition, the following criteria shall also be considered for selection of minimum wall thickness
of the piping:
For materials of a group different than 1.1 (e.g. compressed air system, instrument flanges, etc.),
Contractor shall calculate the pressure-temperature ratings as mentioned above.
causing excessive stresses in the piping material, excessive bending moments at joints, or
excessive forces or moments at points of connection to equipment or at anchorage or guide
points.
This shall be achieved by using piping arrangement such as L-shaped, U-shaped or Z-Shaped
configurations in the normal routing of any piping system.
The above ground piping shall be laid on pipe supports. Supports shall be designed to support the
pipe without causing excessive local stress in the pipe and keep the desired freedom of
movement.
Contractor shall carry out a pipe stress analysis as part of the final design proving that stresses
for piping and equipment, including tanks, are kept within the allowable limits.
13.2.9 Strainers
Temporary strainers shall be installed upstream of each booster pump unit for SQWTS-B pump
group located at PS-SH and upstream the control valve of the booster pumps recirculation line
according to relevant P&ID.
The strainers shall be used for start-up of piping system only and shall be removed afterwards.
The strainers shall be of conical type with mesh size of approx. 5 mm and wire diameter of
minimum 1.6 mm. The mesh material shall be stainless steel in 316L grade.
The strainers shall be designed with sufficient safety against deformation taking into account the
flow velocity with foreign matters in the water. Pressure rating of the strainers shall be according
to the pressure rating indicated on the P&IDs
Pump discharge ball valve with a size of 24” and above shall be top entry type.
No gate valves shall be used in the project (except for the valves used for fire water system, for
which relevant NFPA codes shall be considered).
Quaiza Tie-in CV
Special attention shall be paid to the fact that each control valve will meet its specific performance
requirements and will be suitable for continuous operation without cavitation damage. This
includes the operation between the defined control conditions.
Generally, axial flow piston type control valves with suitably designed throttling elements shall be
used. All control valves shall be equipped with an electric actuator.
In order to minimize energy losses the control valves to be installed into the main stream and
therefore permanently flown through shall be designed for minimum losses in open position which
shall not be more than 3 m at maximum design flow rate except where otherwise specified.
The number of the control valves depicted in the P&IDs represents a preliminary layout. The
performance requirements of the control valve based on preliminary hydraulic study are
summarized in the tables below. The sizes, types and performance data shall be subject to final
design based on hydraulic calculations.
In the control valves specifications below, the following abbreviations are used:
Hu Travel of trim, %
Hudesired Travel of trim for design case, %
Hvmax Maximum losses in open position, m
Kv Valve capacity coefficient, m³/h
Kv100 Valve capacity coefficient of fully opened valve (Hu=100%), m³/h
Kvmin Minimum valve capacity coefficient for possible operating condition, m³/h
Kv - Hvmax Valve coefficient for maximum losses in open position, m³/h
Kv-ΔPmin Valve coefficient for minimum pressure differential between inlet and outlet
side, m³/h
Kv_100 Kv_min
Vapor Maximum
Hu Kv_min
No Q_mdf Density Pressure CV's Hv_max P_up P_do P_up P_do
desired factor
(P_va) on duty
[-] [m³/h] [kg/m³] [bara] [-] [m] [barg] [barg] [%] [- ] [barg] [barg]
DC 16,666.7 995.7 0.042 1 2.4 2.1 90.0 50.0 4.0 1.9
GENERAL INFORMATION
Location: SHOAIBA PHASE 4 TANKS Control Valve (at tank farm inlet)
Number of valves: 1
Total closing time Tc: approx. 360 s (to be defined during final design)
Total opening time To: approx. 360 s (to be defined during final design)
Pressure class ASME #150
Valve diameter Subject to Vendor
OPERATING CONDITIONS Calculation of Cavitation Index Sigma: Sigma= (P_do - P_va) / (P_up - P_do) [-]
No. of Caclulated
Kv % of
No Description Valve in Q Q_valve P_up P_do Kv Hu Cavitation
Kv_100
Operation Index
[-] [-] [-] [m³/h] [m³/h] [barg] [barg] [m³/h] [%] [%] -
MAX FLOW, MIN DELTA
1 1 16,666.7 16,666.7 2.4 2.1 30,747.4 90.0 90 11.54
P
MIN FLOW, MAX DELTA
2 1 1,666.7 1,666.7 4.0 1.9 1,156.6 3.4 12 2.40
P
Note: Also intermediate flow and pressure conditions, which are not explicitly documented, might be operated.
GENERAL INFORMATION
Location: PS_SH Control Valve (at tank farm inlet)
Number of valves: 1
Total closing time Tc: approx. 360 s (to be defined during final design)
Total opening time To: approx. 360 s (to be defined during final design)
Pressure class ASME #150
Valve diameter Subject to Vendor
OPERATING CONDITIONS Calculation of Cavitation Index Sigma: Sigma= (P_do - P_va) / (P_up - P_do) [-]
No. of Caclulated
Kv % of
No Description Valve in Q Q_valve P_up P_do Kv Hu Cavitation
Kv_100
Operation Index
[-] [-] [-] [m³/h] [m³/h] [barg] [barg] [m³/h] [%] [%] -
MAX FLOW, MIN DELTA
1 1 16,666.7 16,666.7 2.4 2.1 30,747.4 90.0 90 11.50
P
MIN FLOW, MAX DELTA
2 1 1,666.7 1,666.7 4.0 1.9 1,156.6 3.4 12 2.39
P
Note: Also intermediate flow and pressure conditions, which are not explicitly documented, might be operated.
Kv_100 Kv_min
Vapor Maximum
Hu Kv_min
No Q_mdf Density Pressure CV's Hv_max P_up P_do P_up P_do
desired factor
(P_va) on duty
[-] [m³/h] [kg/m³] [bara] [-] [m] [barg] [barg] [%] [- ] [barg] [barg]
DC 7,894.8 995.7 0.042 1 5.9 0.7 90.0 50.0 9.2 2.5
GENERAL INFORMATION
Location: PS_SH Recirculation Valve, Booster Pumps
Number of valves: 1
Total closing time Tc: approx. 30 s (to be defined during final design)
Total opening time To: approx. 30 s (to be defined during final design)
Fail safe position: closed
Pressure class ASME #300
Valve diameter Subject to Vendor
OPERATING CONDITIONS Calculation of Cavitation Index Sigma: Sigma= (P_do - P_va) / (P_up - P_do) [-]
No. of Caclulated
Kv % of
No Description Valve in Q Q_valve P_up P_do Kv Hu Cavitation
Kv_100
Operation Index
[-] [-] [-] [m³/h] [m³/h] [barg] [barg] [m³/h] [%] [%] -
Note: Also intermediate flow and pressure conditions, which are not explicitly documented, might be operated.
Kv_100 Kv_min
Vapor Maximum
Hu Kv_min
No Q_mdf Density Pressure CV's Hv_max P_up P_do P_up P_do
desired factor
(P_va) on duty
[-] [m³/h] [kg/m³] [bara] [-] [m] [barg] [barg] [%] [- ] [barg] [barg]
DC 8,424.0 995.7 0.042 1 24.6 5.7 90.0 50.0 32.0 9.0
GENERAL INFORMATION
Location: PS_SH Recirculation Valve, Main Pumps
Number of valves: 1
Total closing time Tc: approx. 30 s (to be defined during final design)
Total opening time To: approx. 30 s (to be defined during final design)
Fail safe position: open
Pressure class ASME #300
Valve diameter Subject to Vendor
OPERATING CONDITIONS Calculation of Cavitation Index Sigma: Sigma= (P_do - P_va) / (P_up - P_do) [-]
No. of Caclulated
Kv % of
No Description Valve in Q Q_valve P_up P_do Kv Hu Cavitation
Kv_100
Operation Index
[-] [-] [-] [m³/h] [m³/h] [barg] [barg] [m³/h] [%] [%] -
1 Wlmin, Q120 %, max n 1 8,424.0 8,424.0 24.6 5.7 1,933.6 90.0 90 1.35
4 Wlmin, Q 120 %, min n 1 4,212.0 4,212.0 12.2 7.5 1,934.6 90.0 90 2.79
Note: Also intermediate flow and pressure conditions, which are not explicitly documented, might be operated.
Kv_100 Kv_min
Vapor Maximum
Hu Kv_min
No Q_mdf Density Pressure CV's Hv_max P_up P_do P_up P_do
desired factor
(P_va) on duty
[-] [m³/h] [kg/m³] [bara] [-] [m] [barg] [barg] [%] [- ] [barg] [barg]
DC 13,157.9 995.7 0.042 1 3.1 1.2 90.0 50.0 5.0 1.2
GENERAL INFORMATION
Location: TI_QA Control Valve
OPERATING CONDITIONS Calculation of Cavitation Index Sigma: Sigma= (P_do - P_va) / (P_up - P_do) [-]
No. of Caclulated
Kv % of
No Description Valve in Q Q_valve P_up P_do Kv Hu Cavitation
Kv_100
Operation Index
[-] [-] [-] [m³/h] [m³/h] [barg] [barg] [m³/h] [%] [%] -
MAX FLOW, MIN DELTA
1 1 13,157.9 13,157.9 3.1 1.2 9,378.0 90.0 90 2.09
P
MAX FLOW, MAX DELTA
2 1 13,157.9 13,157.9 5.0 1.2 6,698.2 64.3 75 1.55
P
MIN FLOW, MAX DELTA
3 1 1,315.8 1,315.8 6.4 1.0 566.3 5.4 18 1.36
P
Note: Also intermediate flow and pressure conditions, which are not explicitly documented, might be operated.
Location
Number of Max. Air Intake during Max. Air
(Chainage as per ASME Class
Valves Transients Release *)
Hydraulic Profile)
[km] [-] [m³/s] [m³/s] [-]
To ensure safe and reliable surge protection, these valves shall be installed with a configuration
1 duty + 1 stand-by and both valves shall be connected with the pipeline.
The above number of vents and location are tentative only since they are based on tender route.
The final location and number of the air vents is depending on the final pipeline profile and shall
be defined based on the Contractor’s hydraulic investigations.
13.4 Pumps
13.4.1 General
This subchapter refers to the pumps for the pump group to be installed at the Shoaiba-Quaiza
Pumping Station.
All pumps shall be of the horizontal centrifugal type with axially split casing to allow for dismantling
of the rotating equipment without disconnecting the piping or removing the pump driver. All pumps
shall comply with specification M05 “Main and Booster Pumps”, Doc. No. QC10-H-045.
The performance data listed below are based on preliminary hydraulic calculations carried out
during preparation of the tender document. During Detail Design Contractor shall carry out his
own calculations.
Pumps with best available efficiency shall be selected, however without violating their
performance and lifetime requirements. The efficiency for booster pumps and main pumps shall
be not less than 86% at Best Efficiency Point (BEP). They shall preferably be selected out of the
manufacturers standard production range.
Special attention shall be paid to the material selection for all wetted parts regarding their
suitability for the quality of the pumped water.
The seal flush piping and vent piping shall be manufactured of corrosion resistant stainless steel.
The coupling hubs on the shafts shall be designed for easy maintenance. A coupling design with
high pressure removal and shrink fit hubs is not permitted.
The lube oil drainage piping shall be constructed with suitable facilities to dispose the lube oil.
An automatic air vent shall be provided on the top of the casing of each pump unit.
The pumps will be directly driven by electric motors. Pumps and electric motors shall preferably
be mounted on a common base plate.
Replacement of mechanical seals on driven and on non-driven end shall be possible without
removal of the upper part of the pump casing.
The main pumps in the pump stations shall be driven by variable speed drives. The booster
pumps have to be equipped with fixed speed drives. The electric motors are described in section
14 “Power Supply and Electrical Works” hereinafter.
(𝑝𝑒 + 𝑝𝑏 − 𝑝𝐷 ) ∙ 100,000 𝑣𝑒 2
𝑁𝑃𝑆𝐻𝐴 = + − 𝐻𝑣,𝑠 + 𝐻𝐺𝑒𝑜
𝜌∙𝑔 2𝑔
With
pe: overpressure inside the tank [bar]
pb: Barometric (atmospheric) pressure [bar]
pd: Vapour pressure of liquid at its design temperature [bar]
ρ: Density of liquid at its design temperature [kg/m3]
installed. This selection covers the operating cases as shown below by using variable speed
drives (VSD) for the main pump units. Booster pumps will be operated in fixed speed.
The pumping equipment to be installed shall meet the following station performance
requirements:
Maximum design flow MDF:
* The differential head results from consideration of the maximum and minimum tank level and the
maximum and minimum possible pipe roughness. The differential head includes geodetic head of
122.8 m till 160.7 m, depending on tank water level.
** Selected pump manufacturer shall define the minimum possible flow within the preferred
operating region of the selected pumps. The MDF shall be considered for Optimization and
selection of the pumps. Minimum flow will be depending on the pump characteristic.
Based on the hydraulic performance requirements above the following equipment has been
selected to be installed in PS-SH:
The Design Point (BEP) of the main pumps has been selected in order to operate all possible
operating points with the different heads as shown above as close as possible to the best
efficiency line.
The NPSHA value for the booster pumps as shown above is a preliminary value considering the
minimum tank level and estimated friction losses with full flow of the pump. The exact NPSHA
needs to be verified by the Contractor during detail design stage considering final elevations and
maximum friction losses on suction side.
With reference to the respective P&I Diagram QP20-D-1262 and QP20-D-1263, a cooling water
system shall be provided for the following consumers in Shoaiba-Quaiza Pump Station PS-SH:
booster pump/motor units
main pump/motor units
lube oil system for main pump units
fan filter units for the pump houses
water-cooled chillers for the VSDs
Contractor shall carefully calculate the highest possible pressures occurring in the individual
piping sections, taking into account all steady and unsteady state conditions, to define the
pressure rating of the cooling system accordingly.
For fan filter units and water-cooled VSD chillers, the heat load shall be determined on basis of all
duty units.
The temperature difference between the heat exchanger entering and the heat exchanger leaving
water temperature shall be approximately 5 Kelvin.
For more detailed description see “Particular Requirements” in this chapter.
The expansion vessel shall be built according to DIN EN 12828, DIN EN 13831 and
approved according to DIN 4807-5 and provided with a replaceable membrane, a pressure
gauge in the gaseous phase, support construction suitable for fixation in vertical position.
Instrumentation and Controls
The cooling systems shall be equipped with all necessary instrumentation and controls
required for a proper operation and shall be provided for with a unit control which will be
connected to the station control system. Automatic (including automatic change-over of
duty/stand-by units) and manual operation must be possible. Operation of the respective
cooling system shall be a start-up precondition for the pumps.
Water-Cooled Chiller Units for VSDs
Regarding these components reference is made to “Specification M15 HVAC Equipment -
Doc. No. QC10-H-055” and the standards and documents referenced therein.
13.6.1 General
This subchapter refers to the surge vessel plant including surge vessels and air compressors,
which shall be installed at the pump station outlet for PS-SH.
A surge protection system shall be provided to confine pressure surges caused by pump start,
pump stop, set point change, valve opening or closure, etc. within permissible limits in order to
protect the water transmission system from destructive high and low pressures. The system
attenuates the high pressures by relieving a portion of the pipeline fluid and low pressures by
maintaining flow of water into the pipeline in the case of a pump trip.
The vessels will contain water from the water transmission system as well as air from a
compressed air source.
The surge vessel plants shall be equipped with a stand-by unit in order to provide a reliable
supply of the defined flow rates even during maintenance periods.
Configuration of the surge vessels are shown on the relevant P&I Diagrams.
The Contractor shall be responsible for the dimensioning and functioning of the surge vessel plant
taking into consideration the finally required hydraulic conditions.
Number
Surge Volume Reference Reference
Pressure Design and Volume of
Vessel without Air total Air
Class Pressure arrange- each vessel
Location spare unit Pressure Volume
ment
[-] [barg] [-] [m³] [m³] [barg] [m³]
PS-SH 8+1,
#300 36 1,000 125 26.1 180
Discharge Horizontal
The water received at Shoaiba-Quaiza Pump Station has been pretreated and therefore no
additional chlorination is required.
At the tie-in and reservoir stations injection facilities shall be provided to allow connection of
mobile chlorination units.
For fire protection system the latest version of the HCIS safety and fire regulations shall be
applied (incl. Safety directives for industrial and non-industrial facilities). The fire protection
concept is described separately as part of safety design package (preliminary design) which is
prepared by HCIS approved fire protection consultancy (to be added with Addendum).
The supplier of the fire protection system shall be licensed and registered to supply, install, test,
inspect and maintain specific fire protection systems (water based system, automatic
extinguishing system etc.) in accordance with the applicable laws and regulations of the KSA
including approval by HCIS.
Office 24 60 20 40 4 40
Prayer Room 24 60 20 40 4 45
Meeting Room 24 60 20 40 6 40
Control Room 24 60 20 40 4 40
Instrumentation
24 60 20 40 1 45
Room
MV Switchgear
30 80 5 40 1 65
Room
LV& UPS Room 30 80 5 40 1 65
Kitchen/Tea
27 - 20 - 4 60
Lounge
Lavatory Room
27 - 24 - 6 45
Ablution Room
Security Room 30 80 5 - 1 65
Battery Room 30 80 5 - 1 65
Electrical Room 30 80 5 - 1 65
VSD Room 30 80 5 - 1 65
Cooling Pump
30 - 5 - 2 65
Room
Water Quality Monitoring Building / Water Metering & Online Monitoring Building
Water Quality
30 - 22 - 1 65
Monitoring Room
5K + max.
Pump Room
ambient - - - 1 80
Firefighting
temperature
Pump Room 5K + max.
- - - 1 90
Station Water ambient
Store - - - - 0,5 80
HV Substation – requirements for all rooms according SEC standards – see chapter 21. High Voltage
Substation
For those rooms which are cooled by central air conditioning system and where no data regarding
fresh air proportion according to ASHRAE standard are given, min.10% fresh air proportion should be
considered in the calculations. This doesn’t apply to the rooms cooled by split air-conditioning units.
Min. air change per hour is to be understood as air exchange in the room.
Further requirements:
All equipment shall comply with “Specification M15 HVAC Equipment”, Doc.No. QC10-H-
055.
All equipment shall be designed for high humidity, sand laden air and saline environment.
Air conditioning loads shall include all electric or mechanical equipment losses, lighting, fan
motor losses, personnel, solar radiation and infiltration air gains.
Heating loads, in general, shall be based upon night time conditions with no credit for
equipment or personal loads.
The supply air temperature to rooms and areas to be air-conditioned shall not be less than
10°C below room temperature.
All HVAC equipment shall have a margin for accessory internal equipment of ~15%.
Conditioned rooms (i.e. office) shall be provided with an adjustable thermostat for
temperature control (i.e. +/- 3 °C).
Specific requirements for the different HVAC systems are given in the following subchapters. The
requirements and equipment specified are the minimum requirements for the final expansion.
rooms shall enter the room at a low level. 50% of the exhaust air shall leave at a low level and the
other 50% at high level of the battery room (according to DIN EN 50272-2).
The arrangement of the single fan filter units shall be chosen in a way, to avoid non ventilated
areas within the building during fail of one single fan filter unit. Moved by its higher pressure within
the building the heated up exhaust air will be discharged via motor operated multi-leaf dampers
mounted in the opposite wall to outdoors.
The pump houses shall be slightly pressurized (max. 30 Pascal) to prevent the ingress of sand
and dust. However, care shall be taken that the pressure inside is not too high to prevent easy
opening of the doors.
For the cooling load calculation all duty pumps plus one stand-by pump must be considered. See
also Design Requirements of cooling water system 13.5.
For all stations the fan filter units are additionally equipped with cooling coils, which will be
connected to the cooling water system. Reference is made to the P&I Diagram QP20-D-1262.
The specified cooling water temp. of 36°C is to be seen as a design parameter.
For all stations the fan filter units are additionally equipped with cooling coils, which will be
connected to the cooling water system. Reference is made to the P&I Diagram QP20-D-1262.
The specified cooling water temp. of 36°C is to be seen as a design parameter.
13.9.7 Water Quality Monitoring Building / Water Metering & Online Monitoring Building
The building shall be provided with two split air-conditioning units, one of them on duty, the other
one providing 100% standby. Each system is fully equipped with a fan, a filter system, cooling
coil, external condensing unit and a heating set. Outdoor units shall be positioned on the ground
next to the building or on the roof of the building.
13.10 Cranes
13.10.1 General
For material handling, for maintenance purposes and to allow for disassembly/assembly of
equipment requiring overhaul or repair cranes shall be installed within various buildings of the
project.
The lifting capacity of the cranes shall be such that the heaviest object which cannot be
dismantled further in situ can be safely lifted and transported. The lifting capacity shall be at least
125 % of the heaviest object, but not less as defined below.
Cranes shall comply with specification M13 “Cranes and Hoists”, document no. QC10-H-053.
The cranes shall not be used for construction purposes.
In the booster and main pump buildings a compressed air system shall be installed for
maintenance and cleaning purposes. The system shall consist of:
industrial type electric motor driven workshop air compressor 500 l/min., 10 bar
air receiver ca. 100 l
inlet filter
outlet filter, water separator
instrumentation
all internal controls and cabling
noise protection cabinet with integrated unit control panel
air distribution piping with condensate traps, manual valves and outlet with coupling close to each
pump unit
air hoses with couplings on both ends.
The service air connections shall be provided for pump houses and the distance between the air
connections shall be less than 15m.
For design and execution of the electrical works special attention is required to consider the actual
voltage level and network data of any existing or new equipment and installations. This is
especially valid for all existing Stations where extension and/or upgrading works are required, or
from where new feeder circuits to new installations will be derived.
The necessary investigation and interface coordination works are part of the contract.
As part of the electrical works the Contractor is responsible to carry out the following design
calculations, studies and activities. Before commencement of the design works the Contractor
shall submit the corresponding design criteria documents.
All design studies, calculations, measurements and tests must be performed by approved
specialists and accepted international programs. The test methods and formats are subject to
approval.
The following general requirements are to be considered for the final design of the power supply
systems, in addition to the technical specifications:
a) The 13.8 kV network within the SWCC Stations shall have preferably low resistance earthing.
This shall be coordinated with SEC/SWCC and depending on the final agreement the earthing
grid including all protective devices have to be designed and installed accordingly. If
necessary, separate earthing transformers must be provided and a separate earthing grid will
have to be introduced and connected to the neutral of these earthing transformers.
Respective coordination with SEC/SWCC is part of the contract.
b) The selected short circuit rating of bus bars must be based on the detailed short circuit study
calculations. The network data must be obtained from SEC.
c) For all stations with supply voltage 13.8 kV or 400 V the requirements and location of fiscal
metering shall be coordinated with SEC (Energy Provider).
d) Generally in PS-SH station with high inductive loads the necessary power factor
compensation equipment shall be provided if the overall power factor of the installed
equipment is lower than 0.95 during normal operations. If available, the existing power factor
compensation shall be checked and adapted for the new installations, if required. The
requirements of SWCC/SEC must be obtained and considered.
e) Generally in PS-SH station the harmonic content of the alternating circuits at the supply
network side must be reduced as much as possible. The Contractor has to provide a detailed
investigation and calculation based on the actual network conditions at site and considering
all installed equipment which may produce harmonic distortion.
The design and study with respect to the harmonic load content and harmonic distortion in the
power supply system shall be subject to approval. Limits of harmonic distortion shall comply
with the requirements of approved international standards and SEC requirements. However,
the total voltage distortion at the worst case location of the 13.8 kV side shall not exceed 2.5
%, if the SEC requirements are not more stringent.
All necessary fixed installed components and equipment necessary to achieve above
mentioned limits must be provided and are part of the contract.
f) All costs for the external power supply connection of stations (reservoir station and tie-in
station) as required by SEC are to be paid by the Contractor as part of the contract price.
g) All works related to external power supply connection with SEC shall be done according to
SEC specifications and by SEC approved Contractors.
shall be installed.
For distribution of electrical energy inside the Pumping Station PS-SH, one (1) 13.8 kV switchgear
shall be installed, which feeds the booster and main pump motors, as well as the 13.8/0.4 kV
distribution transformers for low voltage consumers of pumping station. Each of the two 13.8 kV
switchgear bus bar sections will be supplied from one (1) of the 13.8 kV cable circuits coming
from the power transformers.
Performing site survey and finalizing cable routes from new 380 kV substation till new 110 kV
substation, as well as from new 110 kV substation to the power transformers is part of the
contract. The subject HV cable circuits from 110 kV substation till pump station power
transformers will be installed in sand backfilled concrete duct except for road crossing where
concrete duct banks (with pipe sleeves) will be used. For the 380 kV cables, concrete duct banks
are available in the area of the 380 kV substation. These banks have to be extended till 110 kV
substation. All relevant works are part of the Contract. In this regard all SWCC’s requirement for
detailed cable route shall be considered. For the 380 kV cable laying, SEC standards shall be
considered.
The principle of power supply of the pumping station PS-SH is shown on the following drawings:
QP20-T-1700 Shoaiba Quaiza Pump Station, Medium Voltage Single Line Diagram
QP20-T-1701 Shoaiba Quaiza Pump Station, Low Voltage Single Line Diagram
The estimated maximum power for the pump motors at defined operating point and other station
equipment for the selected design are given in the table below. The values are based on
estimated efficiency values of equipment. The auxiliary consumption reflects an average base
value, not a peak value. In this respect, the distribution transformer rating shall not be smaller
than shown in the corresponding single line diagram.
Table 14-1 Power Requirements – Shoiba Quaiza PS-SH
Booster Pump
(4) x 1,450 kW (4) x 1,254 kW 94.9 - 5,249 kW
Motors
Auxiliary
600 kW
Consumers
Total Apparent
Power @ 26,533 kVA
PF=0.95
The above power data are based on max. pump shaft power and estimated values for motor
efficiency and VSD efficiency and are subject to confirmation during final design. Assumed power
factor is minimum 0.95 according to ECRA requirements.
Motors ratings are selected according to pump design point. Related shaft power values not given
in table above; please refer to P&I Diagrams.
The principle of power supply of these stations is shown on the following drawing:
QP20-T-1702 Highpoint Reservoir Station Single Line Diagram
QP20-T-1709 Tie-In Quaiza Station Single Line Diagram
Table 14-2 Power Requirements –Tie-in Station, Reservoir Station Jeddah South East
Voltage Distance
Location Type kVA E N Provider E N
** App.
Reservoir
Station
Jeddah Point 1:
South 70* ~1200m
Reservoir 13.8 kV cable network neighboured
1 East Normal SEC 13.8 kV
Station to reservoir area
10* UPS Point 2:
RS-JE ~1400m
Tie-In
16* New 400 V Panel for WQM and
Station
2 Tie-In Station Normal 5* SWCC 400, 230V Varies modification at existing
Quaiza
UPS switchboards and related cabling
TI-QA
* The contractor shall define final transformer input voltage and capacity
** Voltage level will be defined based on availability of SEC network in vicinity of subject stations
The Pumping Station will be supplied with 13.8 kV medium voltage via power transformers with
the following main data:
Pump station PS-SH is equipped with a 13.8 kV medium voltage switchgear. The 13.8 kV
Electric motors for main pumps, as well as for booster pumps, will be on 13.8kV operating
voltage. The main pumps in the pump station will be driven by variable speed motors.
Medium voltage motors part of variable speed drives will be with voltage level in range between
3kV and 13.8kV.
Motors for booster pumps will be fixed speed 13.8 kV medium voltage motors.
For the MV booster and main pump motors asynchronous squirrel cage induction motors with
air/water heat exchangers shall be installed.
Power rates of main and booster pump motors are given in the table below:
Table 14-3 Electrical Motors Power Ratings
The motor size indicated in the above table and various documents and drawings are preliminary
only, and must be verified by the Contractor during final design on basis of the actual pipeline
survey, the hydraulic calculation and the final number, type, size and efficiency of the selected
pumps.
For technical requirements reference is made to the “Specification E03 Electrical Motors”, Doc.
No. QC10-H-083, including the relevant data sheets.
The main pumps for the pump station will be driven by medium voltage asynchronous motors/
variable speed drives with the following main data:
One (1) Converter Transformer of oil-immersed type, ONAN cooling, primary voltage 13.8
kV,
Frequency converter with minimum 24-pulse rectifier and 6-pulse inverter with full sine
wave filter in outgoing power path to motor, water-cooled,
MV motors, asynchronous squirrel cage induction motors with air/water heat exchangers.
For the frequency converter a closed circuit water cooling system with the respective cooling
circuits, water treatment, instrumentation, etc. shall be provided. The heat removal from the drives
shall be accomplished with means of an outdoor water/water heat exchanger - chiller.
The converters in the pump station shall be installed in the VSD Buildings close to the respective
Main Pump Building; the transformers shall be placed in boxes close to the VSD Buildings.
Generally, harmonic filter shall be avoided by the design of the variable speed drives. Anyhow, if
requirements for harmonic distortion according to IEEE 519 and The Saudi Arabian Grid Code
cannot be met, harmonic filters shall be provided. These harmonic filter, one per busbar section,
shall be designed for outdoor installation as specified, but installed indoors in dedicated filter
buildings, located next to the electrical building. The general design criteria for the electrical
building, specified in this document, shall apply also for these filter buildings.
For technical requirements reference is made to the “Specification E27 Medium Voltage Variable
Speed Drives”, Doc. No. QC10-H-107, including the relevant data sheets.
The pump station will be equipped with a 13.8 kV medium voltage reactive power compensation
equipment (capacitor banks) in order to insure that power factor is min. 0.95 inductive. This
compensation units are, if required for the new installations, in the scope of the contractor. For
each bus section one unit shall be provided, designed for the compensation of the respective
section.
The medium voltage reactive power compensation equipment shall be metal enclosed and
located indoor in the Electrical Building.
The capacitor banks shall be of modular construction that means that each capacitor bank stage
shall have its own compartment. One capacitor bank will be connected to each bus bar section of
medium voltage switchgear.
For the pump stations PS-SH which have fixed speed motors for booster pumps, estimated size
of each capacitor bank would be as follows:
Table 14-4 Capacitor Bank Capacity
The above data are based on estimated power factor value for main and booster pump motors,
VSDs, Converter Transformers and required power factor of 0.95. Final values are subject to
detailed design and depended on the actual data from vendors and product types. The detailed
power factor correction calculation/exact capacitor bank stage size for all stations is part of the
final design and shall be done by the Contractor according to actual motor data.
Additional reactive power compensation may be needed at low voltage switchboards, depending
on the equipment installed.
For technical requirements reference is made to the “Specification E28 Medium Voltage Reactive
Power Compensation Equipment”, Doc. No. QC10-H-108, including the relevant data sheets.
The power supply for the low voltage station consumers at the Shoiba Quaiza B pump station
shall be derived out of the following switchboards:
Main Distribution Board (MDB)
The MDB is the low voltage main distribution board for all station consumers. The MDB in
the pump station consists of two (2) bus bar sections with two (2) feeder breakers and two
(2) bus-tie breaker with automatic change over to the auxiliary service. The MDB is placed
in the LV and UPS Room of the respective Electrical Building.
Auxiliary Service Board (ASB)
For all essential station consumers, which must remain in operation with the support of the
low voltage emergency diesel generator. The ASB consists of one (1) bus bar section with
one (1) feeder breaker for connection of the emergency diesel generator.
Sub-distribution Boards (SDB)
The SDB’s feeding all LV-consumers will be supplied from the MDB. The SDB’s are
distributed within the station area for power supply of buildings and other process package
units like HVAC, outdoor lighting, etc. Depending on their function the supply of SDB’s will
be carried out via one or via both bus bar sections of MDB.
The principle configuration of the low voltage switchboards at the pump station is shown on the
following drawings:
QP20-T-1701 Shoiba Quaiza Pumping Station, Low Voltage Single Line Diagram
Tie-in and Reservoir Station will be equipped with a low voltage distribution board with 2 bus bar
sections, where one section is Main Distribution Board (MDB) and another Auxiliaries Service
Board (ASB). Incomer to MDB will be either from distributive transformer (pole mounted or ground
installed and fenced) provided by SEC or from 400 V network close to the station.
Incomer to ASB will be from emergency diesel generator set. Automatic change over device will
be provided as well.
The principle configuration of the low voltage switchboards with two bus bar sections is shown on
the following drawing:
QP20-T-1702 Highpoint Reservoir Station Single Line Diagram
For technical requirements reference is made to the “Specification E07 Low Voltage
Switchboards”, Doc. No. QC10-H-087, including the relevant data sheets.
14.9.1 General
For power supply of the essential station consumers, connected to the ASB’s or essential bus
bars of the stations, diesel driven low voltage emergency generator (EMG) units are required.
The EMG for the pumping station shall be placed together with all auxiliary facilities in a separate
generator room of the Emergency generator / Firefighting Building.
The stationary EMG for Reservoir Station shall be containerized and will be placed next to the
Electrical Building of the respective station.
The detailed DG sizing calculation for all stations is part of the final design and shall be performed
by the Contractor. The estimated size of the new EMG are as follows:
Shoiba Quaiza, ASB power supply: 500 kVA
distribution board,
lighting, separated for engine room and control room
outside mounted entrance lighting
switches, cabling, cable transitions etc.,
maintenance power sockets (16A) in the engine room,
Convenience sockets (16A) in the engine room and control room
standstill heating/anti condensate-system for engine and generator
pre-heating of cooling water, lubrication oil, fuel, combustion chamber, prelubrication
circulation
earthing bus bars
In general for a continuous and uninterrupted power supply of selected instrumentation, control
and communication equipment of the various stations and as well for security equipment the
installation of one (1) complete-redundant uninterruptible power supply (UPS) per station with
battery back-up and 230 V AC, 60 Hz output power supply and distribution board is required.
The UPS for pumping station will be installed in the LV and UPS Room of the Electrical Building,
for the batteries a separate Battery Room is foreseen.
For the generation of the 48 V DC, 24 V DC and all other lower voltage levels, which may be
required for the various control and telecommunication devices, separate power supply units
located in the respective cabinets are to be provided. These power supply units shall be fed from
the UPS by 230 V AC.
The principle schematic diagram of UPS is shown on the following drawing:
QP20-T-1704 Typical Single Line Diagram, Uninterruptible Power Supply
For technical requirements reference is made to the “Specification E09 UPS Equipment”, Doc.
No. QC10-H-089, including the relevant data sheets.
14.11 Cabling
The connection of the entire electrical equipment with the power supply source is generally done
by cables laid in sand backfilled concrete ducts, the cable cellars, raised floors or walkable cable
ducts on trays, in cable conduits and for auxiliary cable routes also in direct buried trenches.
The same applies in general to the entire instrumentation and control equipment.
The necessary field junction boxes, required for collection of individual sensor or signal cables on
machinery or package units are part of the cabling works.
For technical requirements of cable types and the cable laying works reference is made to the
“Specification E12 Cable and Cable Laying”, Doc. No. QC10-H-092.
Excavation works at areas of existing cable trenches must be performed by hand only or with
special supervision by machine, if the existing cable routes have been verified by trial pits.
For the entire station areas an equipotential meshed grounding network is to be provided.
For stations, which are to be extended, the existing earthing network shall be considered. The
new and the existing earthing network is to interconnect at least at two (2) locations.
Each new building and high structure within the stations shall be provided with lightning protection
facilities.
For technical requirements of earthing and lightning protection reference is made to the
“Specification E13 Earthing and Lightning Protection”, Doc. No. QC10-H-093.
The outdoor lighting required for each station contains the following subsystems:
Road lighting
Area lighting including structures, valve and flow meter shafts, platforms and other working
places or areas outside of buildings
Fence lighting
The new installations for outdoor and fence lighting within existing stations shall meet the used
types (poles and lighting fixtures), as far as still available on the market. The respective
coordination and if necessary, extension and relocation of existing lighting systems are part of the
Contract.
For technical requirements of outdoor lighting reference is made to the “Specification E15 Outdoor
Lighting”, Doc. No. QC10-H-095. Especially for the fence lighting the HCIS requirements must be
fulfilled. Security design must also be coordinated with the SWCC security department, separate
approval is required.
15.1 Scope
The subsequent section describes the general requirements of the control and monitoring of the
SQWTS-B:
The new pipeline shall be monitored from the Water Pipeline Control Center (WPCC) located at
Shoaiba as described in chapter 5.4 of this document and monitored and controlled from the
Pump Station control room as described in chapter 15.3.1.and monitored from Dispatch Center
Shoaiba and Riyadh as described in section 15.7.
The dominating overall function of the instrumentation and control equipment is to guarantee a
continuous water flow throughout the water transmission system. This means that the
technological process for operating the pipeline shall be considered as an entire unit from the
related supply tanks at Shoaiba PS up to Quaiza tanks.
Therefore the objective of the control system is not reduced to monitoring and control of the
several stations, it has also to handle following overall functions:
Start-up and shutdown of the pipeline system as a results of start-up and shutdown
according to the operation scenarios
Monitoring and control of the pipeline flow rate according to the system conditions (e.g.
levels of tanks)
Emergency and safety functions
Operation optimization (e.g. pump scheduler)
Monitoring of cathodic protection
Monitoring of power consumption
Leak detection and leak location detection for the pipeline system
Time synchronization off all control system equipment (hierarchical principle)
Continuous alarm management - control center and station
The control system of new WTS shall include the following main components:
CC - Control Centre
Monitoring and control of the main process, the CC itself and all relevant systems at
any station, including monitoring of the communication system, leak detection and
third party intervention system.
SCS - Station Control System
Station local control with HMI for monitoring and control of the process within the
station (e.g. STATCON, ESD, UNCONs) at pumping stations
Redundant STATCON with HMI for monitoring and control of the process within the
station and all relevant UNCON’s
UNCON’s with HMI for local monitoring and control of related sub-systems
ESD (with dedicated panels) and Station Safety Functions
Fire detection system
Pipeline control for monitoring and control of the process of the pipeline (e.g.
STATCON)
Optimization, pipeline management and leak detection
Pipeline Safety Functions
Central and local components of a third party intervention system
and interfaces. Further the Contractor has to obtain and verify all information which is required to
implement the specified functionality and to perform all coordination works for internal and
external interfaces with SWCC (e.g. WPCC), other contractors and authorities.
During modification, extension or replacement works at any station it is mandatory not to disturb
safe operation of existing systems in operation. Necessary shut down period, if required, must be
limited to the absolute minimum and must be coordinated with the responsible O&M department
of SWCC respectively NWC. If necessary, suitable temporary provisions must be foreseen to
allow continuation of operation.
Two (2) workstations with two (2) 24’’ monitors each, with four (4) network interfaces for
redundant connections to the redundant pumping station network and redundant
connection to the redundant Shoiaba WPCC Server/Client network
Network (industrial Ethernet switches, cables, etc.) with connection to the SQWTS-B
pipeline communication network
Network (cables, firewalls, etc.) with connection to the existing Shoiaba WPCC
Client/Server network
For details of the general structure of Shoaiba Quaiza WPCC extension refer to the following
drawing:
“Control Center Block Diagram”, doc. no. QP20-T-1801
Leak detection system HMI as well as HMI of the intrusion detection system of the pipeline
system shall be integrated into the HMI of the operator workstations at PCC.
All modification, extension or replacement works incl. required material/hardware for integration
into the existing WPCC implementation are part of the scope. This includes, but is not limited to,
the integration into the existing video wall and the assignment of the existing SQWTS-A PCC
related printers. The control system (supported by a leak detection system (LDS)) shall provide,
via hydraulic profile, the essential data (e.g. elevation profile, MAOP, pressure, temperature, flow,
velocity, friction, status of pumps) of the pipeline system, integrated into the HMI of the operator
workstations at WPCC.
15.3 All required extensions (e.g. hardware, software, licenses) are part of the scope of
work. Modification/replacement works at WPCC is subject to final design and
approval by SWCC/Engineer. Station and Unit Control
A station control system shall be installed at pumping, tie-in and high point reservoir stations. All
station control systems shall be directly linked, via redundant communication system, to the
control center.
Two (2) engineering/operator workstation with two (2) 24’’ LCD monitors each for
engineering works/monitoring and control of the entire station (combined with server
functionality – if required), two (2) network interfaces
Two (2) redundant application and database servers (application and database server
functionality maybe combined in a hardware) with KVM (1 x 17’’ LCD monitor), four (4)
network interfaces for connection to redundant LAN, incl. necessary Software and Licenses
One (1) color laser printer size A4, redundant network interfaces
Independent networks (switches, cables, etc.) with connection to the pipeline
communication system
One (1) redundant SYSCON for pipeline overall functions, redundant network interfaces
One (1) redundant STATCON for station overall functions (e.g. surge vessel, air
compressors), redundant network interfaces
Unit control systems for unit functions (e.g. pump strings), which are linked to the
STATCON:
One (1) single UNCON for each booster pump with remote I/Os and remote LCP
One (1) single UNCON for each main pump with remote I/Os and remote LCP
One (1) single VSD control for each main pump
Unit control systems of package units or subsystems (station utility systems), which are
linked to the STATCON
Air compressor
Cooling water system
Several additional plant bus systems (if required)
Marshalling racks with connections to water quality monitoring, desalination plant (where
applicable), power supply (MV, LV, UPS, etc.), cathodic protection, HVAC, fire
detection,field I/Os and/or field buses including over voltage protection
Additional remote I/O’s (if necessary)
Interface and multiplication cabinets to third party equipment (e.g. existing station control
systems - where applicable)
All necessary Software and Licenses
Third party intervention system central and local components (hardware installed in
instrumentation room, HMI extended via KVM extender to control room)
Computer hardware (e.g. workstations) shall be installed in cabinets located in the instrumentation
room of the related station. Keyboard, mouse and monitors shall be extended to the control room
via KVM extender.
Remote-I/O panels with LCP for operation and control of the individual pump unit shall be installed
in a distance to the pump at the walkway along the wall. These panels shall be installed on a
suitable stand with cable entry from bottom. The height shall be dimensioned that the cabinet will
not get wet in case of flooding in the pump hall. Stairs and stages are part of scope if required.
For details on the proposed structure of the control system see following drawing:
“Typical Pumping Station Control System Block Diagram”, doc. no. QP20-T-1802
After recovery of a total communication failure to central control shall local archived data (events,
alarms, measurement values) automatically be recovered at the central archive.
Server archive and configuration synchronization shall be handled via dedicate LANs, shall not
cause load on process related networks.
The control system (supported by a leak detection system (LDS)) shall provide, via hydraulic
profile, the essential data (e.g. elevation profile, MAOP, pressure, temperature, flow, velocity,
friction, status of pumps) of the pipeline system, integrated into the HMI of the
engineering/operator workstations.
Shoaiba Phase 4 tanks and new tank farm supplied from the desalination plant are pool operated,
Water quantity delivered in both directions, to Shoaiba Phase 3 PS and PS Shoaiba Quaiza, shall
be measured via bidirectional flow meter. Details shall be provided to both control systems and
integrated in the PCC. Further processing, if required, shall be also part of the scope of supply.
An interface to the desalination plant shall be implemented to provide the custody metering data,
water quantity and water quality data, at the physical interface between desalination plant and
tank farm. All required coordination with the desalination plant contractor, material and
integration work to establish this interface, data provision and integration is part of the scope of
work.
At RS-JE an interface for process data exchange with the Jeddah North Consumer custody
metering installation, water quantity and water quality data shall be provided. All required
coordination, material and integration work to establish the interface in the furure is part of the
scope of work. In addition shall sufficient spare capacity be considered in the design of the control
system for integration of the future extension as per P&ID.
Tie-in Station Quaiza:
The existing Electrical Building at Quaiza receiving station shall be utilized to install the equipment
related to the new TI-QA. Modification/rearrangement of the existing installation and coordination
works with SWCC O&M is part of the scope of work.
A communication interface with the existing tank farm installation shall be established for process
data exchanged. This includes, but is not limited to following signal:
• Water quantity and quality shall be provided to the existing tank farm.
• Level signal of the existing tank are required for a proper tie-in station operation.
Required coordination works to establish the communication interface with the tank owner as well
as integration of the signals in the functional logic of the tie-in station is part of the scope of work.
The pipeline system, from the initial pump station up to the RS-JE and endpoint station TI-QA and
tap-off to Jeddah North Consumers, shall be monitored by leak detection software (LDS) during
pipeline steady state operation, based on measurement value readings.
The dedicate LDS shall be provided for each segment, pressurized and gravity.
A leak study shall be provided for the pipeline system defining the required measurements, the
functionality and the detection accuracy with respect to leak size versus time.
For technical requirements reference is made to the following specification:
“S06 SCADA and Process Specific Software”, doc. no. QC10-H-126
The field instrumentation required for continuous measurement and monitoring of the main
process and auxiliary equipment, during all possible modes of operation, has to be provided.
Electrical remote transmitters are required with local installed indication. In addition, remote
installed indication shall be foreseen.
The main instrumentation, as minimum requirement, including the basic control and regulation
loops are shown in the relevant P&I Diagrams. Instrumentation, depending on the selected
system equipment and the functional needs, is subject to final detailed design.
Temperature and pressure measurement shall be considered for leak detection at each beginning
and end point of the pipeline system (even if not explicitly shown in the related P&IDs).
Instruments required for tank level measurement shall be provided, installed and considered in
the control system as well as the signal cabling and all necessary installation auxiliaries. Signals
of existing tanks, required for operation and control, shall be provided via PLC to PLC
communication or signal doubling, if required.
Pressure indicators necessary for proper maintenance of equipment shall be installed where
required, e.g. downstream and upstream of valves to locally check the pressure difference and to
safely manually operate such valves.
The contractor is responsible to design and select the field instrumentation depending on the
purpose, application and environmental conditions in line with the following listed specifications
and drawings:
S01 “Design and Construction of I&C Systems”, doc. no. QC10-H-121
S02 “Field Instrumentation”, doc. no. QC10-H-122
S03 “Installation and Start-up of Field Instrumentation”, doc. no. QC10-H-123
“Typical Hook-ups for Instrumentation”, doc. no. QP20-T-1805
The field instrumentation for the main process pipeline equipment is necessary at least for the
following major tasks:
Pipeline monitoring and control
Flow, pressure and level measurements are the main parameters used for the system
control and regulation loops as shown in the P&ID’s. This includes also possible
redundancies of instruments due safety or overall availability aspects (minimizing single-
point-of-failures)
Leak and leak location detection
The measurements as listed in item a) above shall to be used for leak detection The water
temperature shall be considered for temperature compensation.
Instruments not mentioned in the P&ID’s (e.g. temperature measurements), but necessary
to fulfill the requirements of the leak detection system (e.g. accuracy), are part of the scope
as essential for the provided solution.
Water quality monitoring
Chlorine dioxide as applicable, conductivity, pH and temperature shall be measured, if not
defined otherwise in station related P&IDs.
Dependent on location of installation shall additional safety measures be foreseen to avoid
damage of the measuring elements by pressure surges.
Water/flood detectors shall be installed above the floor of all shafts that contain equipment
controlled and/or monitored by the control system for detection of leaks or inundation.
These signals shall be integrated to the control system and transferred to PCC/WPCC.
The fire detection and alarm system shall be installed in accordance with HCIS SAF
requirements.
The fire detection and alarm system consists mainly of:
SWCC established a Dispatch Center at Shoaiba and Riyadh to monitor and manage its fleet of
power and desalination plants, water transmission pipelines and reservoirs in Saudi Arabia.
The solution is based on a data management infrastructure for collecting, archiving, displaying,
analysing and reporting real-time operational and asset health related information in which the
Shoaiba Quaiza B WTS control system shall be integrated. The existing installation at Shoaiba
shall be used to be established the data provision at the Dispatch Centers.
The connection and integration works required to provide Shoaiba Quaiza B WTS data at the
Dispatch Center interface and at Shoaiba and Riyadh Dispatch Center, including testing, is part of
the of the scope of work. This includes, but is not limited to, the following:
Hardware to establish the redundant communication link (e.g. switches, fire wall) to
Shoaiba Dispatch Center interconnection
Provision and configuration OPC Client at Shoaiba database/archive servers (only Shoaiba
Quaiza B WTS)
Configuration of new tags in existing OSIsoft PI interface servers and configure OPC
servers for data exchange
Configuration of existing OSIsoft PI servers to provide new tags to the Dispatch Center
modification, update or new installation to the existing facilities at Shoaiba Dispatch Center
or Riyadh Dispatch Center
The existing licenses, at least the OSIsoft PI licenses, shall be extended by 1000 tags.
It is the responsibility of the Contractor to inform himself about the actual situation and to make all
necessary checks and investigations in order to verify the actual system status of the dispatch
center interface hardware and software at Shoaiba and at Shoaiba and Riyadh Dispatch Center.
Further the Contractor has to obtain and verify all information which is required to implement the
specified functionality and to perform all coordination works to implement the extension.
Coordination with SWCC IT department for interfacing/modification and SWCC Dispatch Centers
shall also be part of scope.
To reduce maintenance effort and provide uniformity instrument and control system equipment
shall, as far as possible and under consideration of contract requirements, be of same make and
type as already installed at local stations.
The clarification of all software functions shall be supported by a virtual environment. This virtual
software environment shall cover all stations. Any verification/clarification of the individual
software functions as well as of the individual screens shall be based on the approval of the
relevant specifications as well as on the presentations of the control software implementation,
using this virtual environment. This presentations shall be part the engineering meetings or other
regular meetings.
An integrated FAT (IFAT) shall be performed to demonstrate that the implemented control and
communication system functionality including interfaces systems (e.g. Water Meter and Online
Monitoring System) is as per project requirements.
16 COMMUNICATION
16.1 General
For the Shoaiba Quaiza B WTS various communication systems shall be installed, that ensures
and secures the reliable communication between all stations along the new pipeline system and
provision of process information across the pipeline borders.
Communication includes the following independent networks:
a) Process Networks
A fully redundant optical communication system, based on industrial Ethernet switches, and
routing functions shall be set-up for process data exchange of the pipeline system in a
redundant ring configuration.
Telephone and Office Networks
An optical communication system, based on industrial Ethernet switches, shall be set up for
pipeline system in a single ring configuration.
Security Networks
An optical communication system, based on industrial Ethernet switches, shall be set up for
the pipeline system in compliance with HCIS SEC requirements.
Network Management System
Monitoring and engineering system for all communication system components within the
independent networks, including data transfer monitoring to identify and/or to avoid cyber-
attacks.
New FOC shall be installed along the new pipeline to interconnect all stations of the new system,
including the relevant accessories and termination at optical distribution boards.
For detailed technical requirements reference is made to the following specifications:
“S07 Fibre Optic Cable for Pipelines”, doc.no. QC10-H-127
“S08 Fibre Optic Cable Conduit and FOC Installation”, doc.no.QC10-H-128
“S09 Communication System”, doc.no.QC10-H-129
It is the responsibility of the Contractor to inform himself about the actual situation on site and to
make all necessary checks and investigations in order to verify the actual as-built status and the
configuration of the communication system as well as the available space/system capacity for
extensions and interfaces. Further the Contractor has to obtain and verify all information which is
required to implement the specified functionality and to perform all coordination works for internal
and external interfaces with SWCC O&M, other contractors and responsible authorities.
During modification, extension or replacement works it is mandatory not to disturb the safe
operation of the existing pipelines. Necessary shut down period, if required, must be limited to the
absolute minimum and must be coordinated with SWCC O&M. If necessary, suitable temporary
provisions must be foreseen to allow continuation of operation.
Final set-up and configuration of communication network is subject to SWCC/Engineer approval.
If further network protocols are required to build a logical loop-free topology for different Ethernet
networks only non-proprietary routing protocols shall be applied. Ethernet networks. In light of this
a Rapid Spanning Tree Protocol (RSTP) or Multiple Spanning Tree Protocol (MSPT) or Media
Redundancy Protocol (MRP) or equivalent shall be used. It is essential that the spanning tree for
each network or for each VLAN group and blocks are independent. Also the usage of MPLS (Multi
protocol Label Switching) or only MPLS-TP is acceptable. Shall routing between different
networks be required routing protocol like OSPF (Open Shortest Path First) shall be used.
The communication system security shall be improved following cyber security recommendations
and HCIS security directives listed in SEC-12 (latest version). Therefore networks shall be
established using dedicate IP address ranges, disable unused ports of network equipment and
secure for unauthorized access, allow administrative access at dedicated equipment only and log
all attempts of access and modifications.
A verification of the software integrity shall be also included (operation system, control software
packages, engineering tools, etc.), e.g. by using anti-virus software modules, whitelisting,
hardened operating systems or other methods.
The topology of the telecommunication system based on ring configuration of industrial Ethernet
switches along the water transmission system connecting the networks to the WPCC.
Reference is made to the relevant drawings:
“Process Network Block Diagram”, doc. no. QP20-T-1800
“Telephone and Office Network Block Diagram", doc. no. QP20-T-1804
The security network shall be designed and installed in accordance with HCIS SEC requirements.
A dedicated office and telephone network, based on a separate physical ring, shall be set up
The new telephone system shall be interconnected and integrated into the existing PABX of
Shoaiba WPCC.
The new telephone system shall be interfaced to the local public telephone system through
the existing PABX of Shoaiba WPCC.
VoIP telephones shall be connected to the station UPS.
In case power supply of VoIP telephones will be implemented with Power over Ethernet, the
applied Ethernet switches need to support this feature or additional power injectors are
required to be provided.
For field installations analogue telephones are acceptable.
Telephones installed outdoor shall be suitable to operate at harsh environmental conditions
(e.g. below ground).
Each station shall be equipped with at least one telephone. In addition the following minimum
number of telephones shall be foreseen:
a) Control Room:
1 per workstation
b) Control Room:
1 per workstation +1 per DAS workstation + 1 additional
c) Offices:
1 per working place
d) Meeting rooms, lounges:
1 per room
e) Instrumentation rooms, electrical switchgear and other rooms of subsystems:
1 per room
f) Booster and Main Pump House and VSD Building:
1 per entrance
g) Emergency Generator - Fire Fighting Building:
1 per room
The telephone system and the relevant network components shall be designed such that
maximum half of the telephones in one room fail due to a single component’s failure. In addition it
shall be ensured also that in case of a single component failure and in rooms with only a single
telephone at least the neighboring room’s telephone is still working.
Standard features such as conference call, missed call list, call diversion, group call, calling party
identification, etc. shall be provided.
The telephones shall be integrated in the central management system located in Shoaiba WPCC.
Dial plan and call routing shall be integrated with existing Shoaiba dial plan. Alarms shall be
forwarded to the control system at the Control Center
All modification and/or upgrade works of the existing PABX of Shoaiba WPCC, shall also be part
of the scope of work.
All active components of the communication system shall be permanently monitored and
controlled via a network management system. The new components shall be integrated in the
existing network management system (NMS) located at Shoaiba WPCC. The NMS
communication shall be implemented at the new installations using dedicate VLANs with a
defined minimum bandwidth.
Alarms indicating equipment faults, loss of connectivity or unavailability of links (e.g. backup links)
shall be forwarded to the control system at WPCC.
The NMS shall also monitor the entire data traffic for online analysis and detect any unauthorized
data access or unusual data transfer within one of the networks. In case of identification of an
event an appropriate alarm shall be initiated at the control system.
inside the building, will not be used in a defined time frame from entering into the building.
17 CATHODIC PROTECTION
17.1 General
In addition to the good passive corrosion protection and coating of all buried metallic pipes and
structures, the new pipeline and the station piping shall have an active corrosion protection by
means of cathodic protection in line with the requirements defined in respective Specification
Cathodic Protection, and relevant technical data sheet.
Special care is required to avoid any negative influence from cathodic protection installations to
other existing pipes or foreign installations and vice versa. Also the possible high voltage
interference from overhead lines, power cables or other HV installations in the vicinity of the new
pipes and structures must be considered and limited.
The dedicated pipeline cathodic protection system (CPS) shall be separated from the Shoaiba
Quaiza Pump Station (PS-SH), Tie-In station Quaiza (TI-QA) and the Reservoir Station Jeddah
South East (RS-JE) by means of respective isolation couplings. Any further isolation couplings as
required are part of the scope independent if they are shown on the layouts/P&IDs or not.
Design and installation of CPS shall be performed by well experienced and approved companies
only. Detailed site survey and investigation of existing facilities is mandatory and part of the final
design.
If existing transformer/rectifier stations will be used, these stations shall be upgraded and refitted,
accordingly. This is especially valid for all pipeline sections where new pipelines will be routed in
parallel to existing steel pipelines with CPS. Detailed investigations are required and all provisions
to avoid negative influence between the existing and new installations are part of the Contract,
including the calculations, design, supply and installation of equipment.
17.2.1 Pipelines
The individual pipes of the new pipeline system are welded together, the pipes are equipped with
factory applied 3-layer HDPE coating; the welding seam will be coated on site after welding. The
pipes are internally lined with cement mortar.
Cathodic protection of the steel pipeline will be achieved by an impressed current cathodic
protection system consisting of transformer/rectifier stations, anode groundbeds and test points
installed along the pipelines.
The number of transformer/rectifier stations, type and number of anodes and number of test
points depends on the final pipeline route, the soil resistivity survey, the number of crossings,
foreign installations, availability of low voltage power, crossings or parallel routed HV overhead
lines, etc.
Special care is required for the pipeline segments where the new pipelines will be laid in parallel
to existing pipelines. Design and construction of new CPS must consider existing installations and
respectively existing CPS. Any interference and/or negative impact or disturbance must be
avoided. Interactive bonding must be provided.
Before starting the works, the Contractor shall perform a complete survey and potential
measurement of all the existing CP installations. After implementation of the new systems the
measurements shall be repeated to prove the correct operation and protection of both, the new
and the existing CP systems.
All buried new steel pipes, all the other underground metallic structures and the reinforced
concrete foundations at the all stations (pump, tie-in and reservoir station) shall be protected by
the implementation of dedicated and suitably designed impressed current local cathodic
protection systems. The station CPS will operate independently and fully separated from the
pipeline CPS.
For the tie-in station Quaiza, the existing buried piping and metallic structures is protected by an
existing CP system. This system shall be extended for the new installations. Contractor shall be
responsible for complete coordination with SWCC in this regard and provide solution in CP design
considering all buried metallic structure in these station.
Details on the number, type and size of transformer/rectifiers, anodes and test points depends on
the final station layout. Any existing CP installations shall be considered and incorporated. The
Station Contractor shall work out the final design for layout of the local CPS, considering the
actual soil resistivity and all other effects influencing the good performance of the CPS.
Also for the station CP systems the requirement to avoid any negative impact to any existing
installations or vice versa is valid. All necessary survey works, measurements and the
implementation of bonding stations and any other equipment are part of the scope of work.
For each above ground steel storage tank a separate cathodic protection system for the tank
bottom shall be provided. The impressed current system with rectifier and buried impressed
current anodes / anode grid shall be used. An isolating layer (e.g. HDPE foil) shall be installed
underneath the anodes, if MMO type grid anodes are installed, below the tank bottom.
In addition to the cathodic protection of the tank bottom, each steel storage tank shall have
separate internal cathodic protection with impressed current rectifier and anodes installed within
the tanks. Tank internal cables shall be installed in conduits.
For the continuous effectiveness supervision of the CPS for the pipelines and the stations
including the tanks, the installation of a remote monitoring system is required.
At least the following parameters must be continuously measured at various locations, transmitted
to the control centre, recorded and alarmed in case values are not within a pre-defined limit:
Pipe to soil protection potential at the drain points
Pipe to soil protection potential at starting and endpoints of each pipeline and at intermediate
points with access to communication system.
Rectifier DC output potential and current
The remote controlled and synchronized on/off switching of the transformer/rectifier stations shall
be possible.
For data transmission to the control centre the CPS shall be directly connected to the station
related control system or forward the required data via the communication network (Ethernet
interface) to the CPS central control. Data interface is to be coordinated by the Contractor. If it is
not possible to provide reasonable access to a station control system at the location of the CPS
rectifiers and/or monitoring stations, the installation of wireless or cable hubs to the next possible
station equipped with a station control system shall be foreseen as part of the Contract.
The temporary cathodic protection shall be performed with sacrificial anodes of suitable size,
terminated on the test points.
For temporary CP of the pipeline sacrificial anodes are to be placed in distances of not more than
10 km.
Prior to commissioning of the permanent CP all temporary anodes must be disconnected.
The temporary CP is not necessary, if the pipes will be without permanent CP for less than
one (1) month. The Contractor shall work out a respective detail procedure to ensure, that no
segment of pipeline/station will be in the ground without any CP (temporary or permanent) for
more than the mentioned period of time.
17.7 Interference
Special measures are required to limit the admissible touch voltage for personnel safety and to
avoid AC corrosion along the new pipeline system, if any interference due to HV installations is
likely.
In addition all negative effects on the pipeline CPS due to HV interference and stray current
influence from/to existing CPS installations or foreign lines must be considered and the
appropriate counter measures must be designed, supplied and implemented.
Detailed measurements, investigations and calculations are necessary as part of the final design
to define the necessary provisions to be supplied and installed as part of the contract.
The installation and commissioning of CPS, including all necessary site survey and field
measurements must be performed in accordance with the requirements contained in the
respective Specification Cathodic Protection.
Within the scope of work for the construction of the Shoaiba Quaiza B Water Transmission
System, the Station Contractor shall be responsible for setting up of an efficient maintenance
organization, considering already existing maintenance organizations, in order to fulfil the
following key requirements:
Based on the general descriptions in the Tender Documents the work concerning the upgrading
and extension of the maintenance organization shall include but shall not be limited to:
Elaboration of an organizational scheme for the operation & maintenance of the Shoaiba
Quaiza B Water Transmission System, under consideration of the already existing SWCC
O&M organization at Shoaiba WPCC.
Definition of policies and procedures for maintenance & operation
Preparation of qualification requirements and job descriptions for all personnel
Elaboration of a familiarization and training program for the maintenance personnel and
operating staff including a detailed time schedule
Preparation of detailed lists of equipment and tools
Elaboration of a program concerning the intervals and scope of preventive maintenance
measures and overhauls required for the equipment provided under the contract.
Submission of the documents mentioned in a) through f) above in form of a proposal, which
is subject to approval by the Engineer
Integrate the approved version of the maintenance organization proposal into the final
design of the buildings for workshops, spare part storage and garage
Elaboration of a maintenance manual based on the approved maintenance procedures and
list of tools.
Supply of all special tools following the approved proposal, familiarization of the personnel
and supply of all forms according to the approved procedure in sufficient numbers for a two
years operation period.
The staff located at the stations will be responsible for all daily routine maintenance
activities at their location of assignment.
For special maintenance works, repairs and overhaul of equipment at the pump station and
the other stations, crews with equipment and tools will be sent from the maintenance center
already existing at Shoaiba.
The maintenance organization will be directed by the chief maintenance engineer, who reports to
the manager of the Water Transmission System.
Based on the Contractor’s approved proposal SWCC will delegate the staff foreseen for
familiarization.
Following the approved familiarization program the Contractor shall organize and conduct
familiarization sessions for operation and maintenance, explaining in detail all the requirements
and procedures. Such sessions shall be held for personnel who will later on execute the work as
well as for the supervising staff.
The scope of work concerning the familiarization of the Employer’s personnel is described in
chapter 20 of this Project Specification G02.
Classification of spare parts including code system for computer application (MESC Code)
Level of spare part storing, considering the Supplier’s recommendations and the average
procurement time in Saudi Arabia
Method of preservation and storage requirements
Material control and recording system
Spare part interchangeability record sheets (SPIR forms) have to be provided by the Contractor
after completion of equipment design. These forms shall be filled for two (2) years wear and tear
parts and five (5) years spare parts. The SPIR forms to be used, including the filling in procedure,
are enclosed in the SWCC project procedure manual.
A stock of bilingual forms resulting from the maintenance procedures mentioned above shall be
supplied by the Contractor and shall include but not be limited to the following:
Schedules for periodical maintenance work
Check lists for
During the warranty period the Contractor shall replace all equipment items and special tools that
prove to be improper and do not meet the requirements for effective maintenance works.
Tools, equipment and other facilities/items provided under this Contract shall not be used in any
way for the purpose of construction.
19.1 General
This Chapter describes in general terms the activities the Contractor has to perform with regard to
commissioning, start-up and completion tests. For the entire procedure, starting with the check-
out tests required for Mechanical Completion up to and including the Reliability Test, the
Contractor has to prepare and submit for approval detailed procedures and programs including,
but not limited to:
Time schedule for the entire period and for the individual tests
Detailed descriptions of test procedures and modalities
Manpower details
Lists and specifications of measuring and control devices intended to be used for the tests
Method and calculation for evaluation of test results
Definition of activities which will be performed by the Contractor himself and which are to be
carried out by the Subcontractors/Suppliers under the Contractor’s supervision
List of the Contractor’s personnel authorized to perform and/or witness and certify the tests
Sample forms for the documentation of test results
Detailed testing instructions
The activities shall be covered by the following detailed specifications:
1) Pipeline Tests
2) Check-Out, and Tests for Mechanical Completion and Commissioning
3) Line Fill, Start-Up, and Tests on Completion
The documentation, test forms and procedures prepared by the Contractor must be in full
compliance with the SWCC Project Procedure Manual.
These activities have to be performed by the Contractor before issuing of the “Mechanical
Completion Notice” and shall be a precondition for issuing of the Mechanical Completion
Certificate by the Client.
The main purpose of the check-outs and the tests is to prove that the pipeline and its
components, subsystems, individual functional groups, and the equipment installed at the Project
are in compliance with the specifications, are complete and functionally operable.
The precondition for any test performed on site is the availability of the shop test certificate for
each individual component or subsystem, which therefore shall be held in evidence by the
Contractor and a copy of which shall form part of the test documentation.
The check-outs and the tests shall aim at having the components and subsystems in the condition
“ready for start-up”. Therefore the tests shall also include operational tests and trial runs of all
machinery and equipment. However, the performance of tests requiring electric medium voltage
power and/or product water to be provided by SWCC or others (i.e. running of booster and main
pumps) shall not be a precondition for issuing of the Mechanical Completion Certificate.
All the tests required for the pipeline such as initial sterilization, etc. shall form part of these
activities, but shall be described in a separate specification.
19.3.1 Preconditions
The following activities must be performed and successfully completed prior to commencement of
line fill:
19.3.3 Start-Up
Start-up shall mean that the operation of the Pipeline System is commenced under the same
conditions as prevailing during commercial operation.
The Station Contractor is responsible for the familiarization of the Employer’s O&M personnel for
all disciplines. In addition the particular training requirements regarding operation and
maintenance of the SCADA System, which will be supplied under this Contract, are part of the
contract.
The objective of familiarization is to prepare the Employer’s O&M personnel to manage, operate
and maintain the System, which include among the other components especially the aspects of
instrumentation, control and communication works, as well as safety installations.
The familiarization shall be performed on the actual plant equipment and shall be organized and
structured in such a way, that due allowance is made for the phased assignment of O&M staff in
accordance with the hand-over program of the individual sections of the Works.
The Contractor shall also instruct, advice and supervise the SWCC personnel in the correct
application of procedures and practices of operation and maintaining of the system during the
entire warranty period.
The Contractor shall observe regularly the activities of the designated personnel, evaluate their
performance, give them technical advice and conduct special tutorial sessions, if deemed
necessary.
To accomplish this objective, the Contractor shall prepare a detailed familiarization program,
which shall consider the following:
The minimum familiarization period shall be three (3) months and shall be completed before
issuing the Preliminary Acceptance Certificate (PAC).
In preparing the familiarization plan the Contractor shall refer to the already established
SWCC O&M organization set up for other pipeline systems originating at Shoaiba.
The personnel shall be divided into the two groups, operation (including engineers) and
maintenance, which shall undergo a supervised, task- and performance oriented on-the-job
training.
Disciplines, number of SWCC staff and duration of training shall comprise of
Factory training for (6) operators for (6) weeks on Central Control operation
On-site training for (6) operators for (6) weeks on Central Control operation
Overseas detailed system training for (5) engineers for (3) months
Factory training for (6) maintenance personnel for (6) weeks
On-site training for (6) maintenance personnel for (6) weeks
Contractor shall bear all cost for travel, boarding and lodging of the trainees.
Final number of O&M personnel, to be assigned by SWCC for the familiarization, must be
considered.
The Contractor’s O&M Manuals shall be the basis for the familiarization, brief handouts in
Arabic and English according to each position shall be prepared.
The familiarization program, including the time schedule, the procedures and handouts are
subject to SWCC approval.
The familiarization program for the DCS/SCADA equipment and instrumentation shall be
performed on site and in the manufacturer’s premises and shall last at minimum three (3) months
(45 days on site and 45 days outside KSA).
The familiarization program shall include at least the following:
General:
Brief introduction of the pipeline system
System structure and modes of operation
Handling of command power and change over
Automatic and Manual mode
Documentation
Introduction – structure of the documentation
Operation Manual
Maintenance Manual
Drawings
In order to provide electrical power supply to Shoaiba Quaiza B pumping station, electric power
from 380 kV switchgear located at new 380 kV substation shall be transmitted on 380 kV high
voltage level to the new 110 kV substation. Two (2) power transformers, located in 110 kV
substation, will provide 110 kV to the new 110 kV switchgear.. The substation design and all
equipment shall be according to SEC material specifications and standards. The design shall be
prepared by a consultant approved by SWCC and the works shall be implemented by a (sub-)
contractor approved by SWCC.
The scope of work is mainly consisting of: one (1) 110 kV GIS, two (2) power transformers
380/110 kV, 210/280/350 MVA (ONAN/ONAF1/ONAF2 or OFAF) with 380 kV and 110 kV cables,
MV switchgear cubicles for auxiliary supply, AC/DC LV auxiliary supply, protection control SCADA
& telecommunication, civil and mechanical works as described in chapters below. Also, scope
includes all necessary SAS, protection, control, communication and SCADA systems.
Furthermore, scope includes all necessary modifications of the 380 kV feeders and related
existing control & protection (C&P) panels including adding new C & P panels if it appears as
necessary. All components and accessories required for the satisfactory operation of the facilities
of the Project, whether specifically mentioned in detail or not, shall be supplied and installed as
necessary.
In addition all civil, mechanical, control, instrumentation, communication, etc. works shall be
designed and implemented according to SEC standards.
21.2.1 General
Provision and installation of following electrical equipment and facilities as per
requirements/ratings indicated in chapters below for Shoiba Quaiza B HV-Substation.
High Voltage Installations
The supply of Pumping Station will be derived out of new 380 kV substation, located close to
location of new 110 kV Substation, realized by usage of existing spare feeders.
Contractor is responsible for design and installation of: any required upgrade and extension in
existing SEC 380 kV substation, and new 380/110 kV transformers.
The new substation will include a 110kV SF6 insulated switchgear. Switchgear shall be of double
bus-bar configuration, 3ph, 60Hz, 2500A and 40kA for 1sec.
Contractor shall also provide 380kV cables for connection between the existing 380kV Substation
and new power transformers 380/110kV.
Contractor shall also provide 110kV cables for connection between new 380/110kV power
transformers and new 110 kV GIS.
The principle configuration of the high voltage switchgear and power transformers in pump station
is shown on the following drawing:
QP20-T-1705 Shoaiba Quaiza B Pump Station, HV-Substation High Voltage Single Line
Diagram
High voltage installations and accessories shall be according to SEC material specifications and
standards
Power Transformers
For power supply from existing substation 380 kV Shoaiba Quaiza HV-Substation will be
equipped with two (2) power transformers with the following main data:•
Primary voltage 380 kV
• Secondary voltage 110 kV
Tertiary voltage 13.8 kV
• Power 210/280/350 MVA per SEC
• Cooling method ONAN/ONAF1/ONAF2 or OFAF
• Short circuit voltage 21 % (related to 350 MVA)
Vector group YNautod1
The power transformers will be installed in 110 kV substation area.
Each power transformer 380/110kV shall be designed for the total load of Shoaiba Quaiza HV-
Substation and loads of future pump stations and RO (preliminary evaluation about 350 MVA).
Each power transformer shall have on-load tap changer (OLTC) at the primary voltage and
voltage regulation as per SEC standards. Power transformers and accessories shall be in
accordance with SEC Technical Specifications and standards.
These power transformer will be installed in outdoor boxes with oil catch basin and fire protection
wall.
Distribution Transformers
Substation shall be equipped with two (2) distribution transformers where one (1) is designed for
the full station load.
The distribution transformers will be installed in outdoor transformer boxes with oil catch basin
and fire protection walls.
Distribution transformers for substation shall be according to SEC material specifications and
standards.
The power supply for the low voltage station consumers at the substation shall be derived out of
Main Distribution Board which consists of two (2) bus bar sections with two (2) feeder breakers
and one (1) bus-tie breaker with automatic change over. The MDB shall be placed in the LV and
UPS Room of the respective Substation Building.
The principle configuration of the low voltage switchboards at the pump station is shown on the
following drawings:
QP20-T-1707 Shoaiba Quaiza B Pump Station, HV-Substation, Low Voltage Single Line
Diagram
Low voltage switchboards for substation shall be according to SEC material specifications and
standards.
DC UPS Equipment
For a continuous and uninterrupted power supply of substation equipment dedicated redundant
uninterruptible power supply (UPS) with battery back-up and 125V DC output power supply and
distribution board is required. An additional UPS with 48V DC shall be installed for
telecommunication systems.
The UPS will be installed in the LV and UPS Room of the Substation Building, for the batteries a
separate Battery Room is foreseen.
The principle schematic diagram of substation UPS is shown on the Shoaiba Quaiza B Pump
Station HV-Substation, Typical Single Line Diagram DC UPS, Dwg. No QP20-T-1708.
All DC and UPS equipment within the pump station shall be designed for total station load.
UPS for substation shall be according to SEC material specifications and standards.
Cabling
The connection of the entire electrical equipment with the power supply source is generally done
by cables laid in sand backfilled concrete ducts, the cable cellars, raised floors or walkable cable
ducts on trays, in cable conduits and for auxiliary cable routes also in direct buried trenches.
The same applies in general to the entire instrumentation and control equipment.
Cabling for substation shall be according to SEC material specifications and standards.
ambient indoor, 40 kA (sym. 1 sec) short circuit and 104kA peak withstand current rated. GIS
consisting of the following major equipment arranged in a double bus single breaker configuration
as indicated in SLD drawing QP20-T-1705. The 110 kV GIS shall be designed to have provision
for installing four (4) additional new bays (2 at each end) if required in future, apart from the
required items:-
a) Totally two (2) nos., 2500 A continuous at 40'C ambient, 40 kA (sym. 1 sec) interrupting
current capability, 104 kA Rated Peak Making current, three phase circuit breakers for two
(2) nos. incoming feeders.
b) Totally two (2) nos., 2500 A continuous at 40'C ambient, 40 kA (sym. 1 sec) interrupting
current capability, 104 kA Rated Peak Making current, three phase circuit breaker, for two (2)
nos. Bus coupler.
c) Totally two (2) no., 2500 A continuous at 40'C ambient, 40 kA (sym. 1 sec) interrupting
current capability, 104 kA Rated Peak Making current, three phase circuit breaker, for two (2)
nos. Bus sectionalizer.
d) Totally four (4) nos., 1600 A continuous at 40'C ambient, 40 kA (sym. 1 sec) interrupting
current capability, 104 kA Rated Peak Making current, three phase circuit breakers, for four
(4) nos transformer feeders.
e) Totally six (6) nos., 2500 A continuous at 40'C ambient, 40 kA (Sym 1 sec) short circuit
current rated, 104 kA Peak Withstand current, three-phase motor operated disconnecting
switches for incoming feeders.
f) Totally four (4) nos., 2500 A continuous at 40'C ambient, 40 kA (Sym 1 sec) short circuit
current rated, 104 kA Peak Withstand current, three-phase motor operated disconnecting
switches for two (2) Bus couplers.
g) Totally four (4) nos., 2500 A continuous at 40'C ambient, 40 kA (Sym 1 sec) short circuit
current rated, 104 kA Peak Withstand current, three-phase motor operated disconnecting
switches for two (2) Bus sectionalizer.
h) Totally twelve (12) nos., 1600 A continuous at 40'C ambient, 40 kA (Sym 1 sec) short circuit
current rated, 104 kA Rated Peak Withstand current, three-phase motor operated
disconnecting switches for twelve (4) nos. Transformer feeders.
i) Totally eight (8) nos., 40 kA (Sym 1 sec) short circuit current rated, 104 kA Rated Peak
Withstand current, three-phase motorized grounding switches for two (2) nos. incoming
feeders
j) Totally four (4) nos., 40 kA (Sym 1 sec) short circuit current rated, 104 kA Rated Peak
Withstand current, three-phase motorized grounding switches for two (2) Bus coupler.
k) Totally four (4) nos., 40 kA (Sym 1 sec) short circuit current rated, 104 kA Rated Peak
Withstand current, three-phase motorized grounding switches for two (2)Bus sectionalizer.
l) Totally sixteen (16) nos., 40 kA (Sym 1 sec) short circuit current rated, 104 kA Rated Peak
Withstand current, three-phase motorized grounding switches for four (4) nos. transformer
feeders
m) Lot: three phase Voltage Transformers 110/√3kV / 110/√3V x 110/√3V, dual class 0.2/3P,
burden 100VA (minimum) for each winding, with manual disconnecting switches as per one
line diagram QP20-T-1705. However, VT with higher burden shall be provided if required
based on the design calculation.
Note: All GIS electromagnetic voltage transformers shall have primary disconnecting link or
device that must be of proven design, operating manually with monitoring system at Bay
Control Panels (BCPs)/ Local Control Cubicle (LCC) and remote control room.
n) Lot: Current transformers (protection cores) as per SEC protection requirements and (CT
metering cores) as SEC requirements for metering.
o) Lot: Required 2500 A continuous at 40degC ambient, 40 kA (sym1sec.) short circuit current
rated, 110 kV SF6 (GIS) / interface bushings suitable for connection of SF6 bus ducts
connecting switchgear’s transformer feeders to power transformers as per QP20-T-1705
drawing.
p) Lot: Required 2500 A continuous at 40degC ambient, 40 kA (sym1sec.) short circuit current
rated, 110 kV SF6 (GIS) / XLPE interface bushings suitable for connection of cable
connecting switchgear’s incomer feeders to power transformers as per QP20-T-1705
drawing.
q) Lot: Station class GIS Surge Arresters as per the drawing QP20-T-1705. Contractor shall
provide more GIS type surge arresters as deemed necessary by respective study.
r) Lot: SF6 gas density and pressure monitoring equipment, which shall include but not
necessarily be limited to one filling/vacuum port, one graduated gas monitoring gauge,
density switch/switches for gas pressure low I & II & blocking of operations & if available,
high density alarm, etc.
s) Lot: Local Control Cubicles (LCCs)/Bay Control Panels (BCPs), one (1) set for each CB.
Each LCC/BCP should be provided with BCU for Local control (of CB, and all disconnectors,
and grounding switches), integrated with SAS (Substation Automation System). Each
LCC/BCP should be provided with Mimic Board for Emergency control (of CB, and all
disconnectors, and grounding switches), complete with bus diagram, auxiliary relays,
devices, moulded case circuit breakers, contactors, control switches, semaphore indicators, .
etc. Each LCC/BCP should also be provided with Annunciator and nameplate.
Both BCU and Mimic Board shall be interfaced to operate when the SAS/BCU fails. Four
position Local/Off/Emergency/Remote (LOER) selector switches shall be provided.
t) Lot: On-Line Partial discharge monitoring system shall be provided for the whole 110 kV
installations such as GIS, GIB, etc, shall be designed by mounting couplers at appropriate
location to facilitate PD monitoring from a central unit. On-Line Partial discharge monitoring
system shall be provided for the 110 kV GIS as per SEC specification. The contractor shall
include in base design & detail design. It must be integrated with SAS and feasible to
monitor/annunciate to HMI / Remote control centres.
u) Permanent ladders and platforms shall be provided across the breakers and removable
ladder with platform for outdoor GIB for the easy access to the GIS bus ducts for the
maintenance and repair works. The GIS bus ducts shall be provided with compression joints
for easy repairing and minimum dismantling of sections.
Notes:
i. The 110 kV GIS shall be in accordance to SEC material specifications and engineering
standards.
ii. The sizes of the 110 kV GIS and control buildings shall be adequate to accommodate
the present requirements and future expansions. The power transformers and the major
outdoor equipment shall be suitably arranged to have provision for installation of 110 kV
feeder positions in future.
iii. SVL shall be provided according to SEC specifications.
iv. Trays/ladders for 110 kV outgoing feeders shall be done by contractor.
Totally two (2) nos. draw-out type, 630 A continuous at 40degC ambient, 40 kA interrupting
capability, 3 pole, circuit breaker, SF6 / Vacuum breaker suitable for terminating transformer
feeders.
Lot: Grounding of 13.8 kV voltage level and accessories as per QP20-T-1705 drawing.
Lot: Protection and Metering cubicle with three phase VTs for station service transformers.
Voltage ratio of VTs shall be 13.8kV/√3V - 100Vx100/√3V - 100Vx100/√3V , dual class
0.2/3P.
Lot: 13.8 kV Current Transformers (protection cores) as per relaying SEC requirements.
Metering cores as per SEC requirements for metering. Each 13.8 kV feeder switchgear panel
shall be provided with dedicated spare CT core of 0.2 accuracy class for AMI / revenue
metering.
Lot: Control & protection relays, feeders, metering devices and other switchgear accessories
as per relaying and metering SEC requirements, complete with all devices, accessories,
wiring and other control, indication, alarm and protection needs.
Notes:
i. The 13.8 kV Switchgear shall be in accordance to SEC material specifications and
engineering standards.
ii. The 13.8 kV Switchgear shall be controlled through SAS normally. Manual controls shall
also be possible with selector switch provided in the switch gear. All 13.8kV support
Insulators (if applicable) shall be interchangeable.
Notes:
Power transformers shall be in accordance to SEC material specifications and
engineering standards.
Necessary neutral grounding cables shall be provided.
The transformers shall be designed based on 55°C ambient temperature.
Surge Arrestors shall be in accordance to SEC material specifications and engineering standards.
21.2.10 Low Voltage Power and Control and Instrumentation (Shielded) and Communication
Interface Cables
Multi-core and/or multi-pair control cables and low voltage AC/DC and shielded instrumentation
and communication interface cables, as necessary to interconnect various substation equipment
and devices to achieve a complete working system for this project, it shall be in accordance with
SEC requirements complete with conduits, ducts, trays etc.
The substation will be controlled by SWCC operating personal, either from local or from remote
SWCC control room. Therefore, SAS shall not be integrated in the overall SCADA-system of SEC.
The following specifications have to be seen in the light, that SAS in principle shall be designed as
per SEC requirements, but not be integrated in the overall SEC system. All modifications to SEC
standard system necessary to meet this requirement are within the scope of Contractor.
The Contractor shall design, procure (from an approved equipment manufacturer), deliver to the
site, install, inspect, test (at the manufacturer’s works and at site) and commission a complete and
fully operational Substation Automation System (SAS) at HV-Substation. The offered SAS shall
comply with the latest SEC requirements. The SAS shall be from a manufacturer/systems
integrator who must have designed, manufactured, tested, installed and commissioned Substation
Automation System(s) which must be in satisfactory operation on 110 kV electric power systems
(or higher primary voltage) for at least 2 (two) years as of the bid opening date.
Contractor should be responsible for all items pertaining to SAS for the substations. Moreover, the
contractor is responsible for SAS integration of all voltage levels protection/ communication/
control IEDs of the main substation.
At the site, SAS supplier/Contractor shall interact with the other Contractors regarding the
required interfaces. These interfaces may include the interaction of the SAS with
the switchgear and other hardware (VTs, CTs, etc.),
the control functions of the substation,
the protection functions of the substation,
other SAS monitoring functions which may include SCADA related data acquisition functions
conventionally performed by a SCADA RTU, SOE (Sequence of Events) monitoring functions
as well as other functions,
The control and protection functions of transformer feeders in existing 380 kV Switchgear
dedicated for new 380/110 kV power transformers. All necessary upgrade and modification
jobs including material are scope of work the Contractor.
Local controls at bay levels from Bay Control Unit (BCU) and Local Control Cubicle (LCC)
and station control facilities with all required items.
Supervisory control from SCADA (Power Control Center) – if required by SEC.
Remote control from station HMI and Power Control Center.
The Contractor shall provide an integral control system along with the 13.8 kV switchgear in
accordance with SEC material standards. Normally 13.8 kV switchgear shall be controlled
through SAS. Manual control shall also be possible with the selector switch provided in the
switchgear.
The SAS shall be installed to control and monitor all the substation equipment connected to the
SAS from a remote control center of SWCC as well, through local means within the substation
(e.g. Bay Oriented Local Control with Mimic, Local HMI contained in the Control IED and Station
HMI).
The SAS shall comprise full station and bay protection as well as control, monitoring and
communication functions and provide all functions required for the safe and reliable operation of
the substation.
It shall enable local station control via a PC by means of a HMI and control software package,
which shall contain an extensive range of Supervisory Control and Data Acquisition (SCADA)
functions. It shall include communication gateways, station bus, inter-bay bus, time
synchronization system and Intelligent Electronic Devices (IEDs) for bay control & protection
Mechanical work shall include supply of equipment, materials and tools for the installation of
below described systems. The work shall also include equipment for start-up, testing and
commissioning for these systems and to execute other related services for the safe, efficient and
reliable performance and complete installation of this project in conformance with the
requirements as prescribed below.
TES B-106.06 Fixed Installation Total Flooding Clean Agent Fire Extinguishing
21.4.3 Crane
In HV switchgear room one (1) crane shall be installed with the below given nominal carrying
capacity. The given capacity values have to be taken as preliminary, final requirements are
subject to the weights of the offered equipment.
HV Substation (Switchgear room) 50 kN (Double Girder Overhead Crane)
General Description
The HV substation building is a one story structure with a cable cellar (partial) and will
house the HV and MV switchgear rooms, LV and UPS room, control and protection room,
SEC metering room, clean agent room, battery room, telecom room, record room, HVAC
room, lavatories, storage, staircases and corridors. The HV switchgear room is equipped
with an overhead crane (refer chapter 21.4.3). The SEC metering room and the LV and
UPS room are equipped with double floors.
The elevation of the finished floor level is 0.30 m above station level, the finished floor level
of the cable cellar is approx. 3.45 m below station level.
Power transformer boxes are situated adjacent to the HV Substation buildings.
For layout and size reference is made to the above mentioned drawings.
Construction
General:
For design and erection of the HV Substation buildings applicable SEC (Saudi Electricity
Company) standards and the related regulations have to be considered.
The following list of SEC standards shall be followed, but does not claim to be complete:
78-TMSS-12, Revision No.0 Floor systems for substations
TES-P-119.01, Revision No. 0 Introduction to substation design and standards
TES-P-119.02, Revision No. 01 Basic design aspects
TES-P-119.08, Revision No. 01 Clearances
TES-P-119.19, Revision No. 02 Substation Building and site development
TES-P-119.21, Revision No. 01 Fire and loss prevention and security requirements
Foundations:
Reinforced concrete slabs, watertight. Reinforced concrete slabs, watertight with skirting of
reinforced concrete at areas without cable cellar.
For further details on station civil works refer to Chapter 12 above. The SEC standards shall be
considered in addition. In case of conflicts, SEC standard shall prevail.