Professional Documents
Culture Documents
LECTURER:
Ts DR SYAMSUL HENDRA MAHMUD
TASK
MARINE STRUCTURE
TABLE OF CONTENTS
NO CONTENTS PAGES
1. INTRODUCTION 3 - 12
1.1 Existing Environment
1.2 Development Proposal Concept
1.3 Environmental Management PLAN (EMP)
1|Page
TABLE OF CONTENTS
NO CONTENTS PAGES
6.0 CONCLUSION 44
7.0 ATTACHMENTS 45 - 47
2|Page
1.0 INTRODUCTION
This study and assignment were conducted for the proposed coastal erosion
control project at Tanjung Pahang beach, Rompin, Pahang Darul Makmur at Tanjung
Pahang Beach, Lot 1913, Mukim Endau, Rompin District, Pahang Darul Makmur
under Tioman DUN (N42) and Rompin Parliament. This Project will be carried out on
an area of 342.49 acres (138.6 hectares). The locality of the Site of this Project is
under the administration of the Rompin District Council.
This project site is located in the district of Rompin, Pahang Darul Makmur.
Cities or towns close to the project site are Tanjung Gemuk Town and Endau Town
next to Pahang and near Mersing Town in Johor Darul Takzim. Geographically, the
Project site is at longitude 2.66732 and latitude 103.620355.
The project site is currently in the coastal area overlooking the South China Sea
and is covered with rhu trees and shrubs. It was found that the rhu trees in the area
next to the beach at the Project site are composed of mature trees that are still
productive. The existing conditions on the Site are as shown in Figure B. The proposed
Project Site is surrounded by secondary plants, institutions, and village residences.
Land use next to the Project Site is as follows:
3|Page
The proposed Project is coastal development of more than 25 hectares as well
as coastal development subject to items seven and 9e (Infrastructure Development -
construction of coastal development) Environmental Quality Act (Designated
Activities) (Environmental Impact Assessment Study) Order 1987; under Section 34A
of the Environmental Quality Act 1974.
Based on the Rompin District Council Local Plan 2017 (Amendment 2), the
proposed Project is located in the Tioman Dun Planning Center Block N24 under the
Small Planning Block (BPK) 3.10 - Alam Sari, which has been set for coastal
development in line with development proposals.
4|Page
iv. EIA Consultant :
EUROPASIA ENGINEERING SERVICES SDN. BHD. (239233-K)
No. 63A-2 & 65-2, Petaling Utama Avenue,
Jalan PJS1/50,Taman Petaling Utama,
46150 Petaling Jaya,
Selangor Darul Ehsan.
U/p. : En. Mohd Farid Bin Othman
(Ketua Kajian EIA)
5|Page
6|Page
7|Page
1.1 EXISTING ENVIRONMENT
a. Topography
• Based on the survey plan, the proposed Project Site has a relatively undulating
surface with an average level of between RL 30m to RL 100 meters above sea
level.
• The highest peak (about RL 116.53m) is at the top of the hill at the far end of
the Project Site, while the lowest area (about RL 21.16m) is in the valley area
of the Sg. endau, which is located in the southern part of the Project Site.
b. Drainage
• The eastern part of the Project Site is composed of acceptable sand beach
metasediments type of skis rock known as Jelebu Skis Formation. In contrast,
the northern part of the Project Site is located in Taman Jadi, Rompin Pahang.
Rompin District Council has appointed
• MAX Engineering Consultant. to carry out Geological Terrain Mapping for
Project Site proposals. Geological Terrain Mapping Report (GTMR) has been
submitted to the Pahang State Department of Minerals and Geosciences
(JMGS / PDM) and
has obtained approval on 6th April 2015 No. References: - JMG. SWP (PPS)
008/40/3 Vol.7 (8) 9.
8|Page
d. Land use
e. Water Quality
• Water policy sampling session was conducted on 12th February 2015 at Nine
(9) sampling points representing two sessions, namely morning and evening.
Sampling and analysis are carried out by DSM accreditation laboratory, i.e.,
Spectrum Laboratories Sdn.Bhd.
• Water quality taken is summarized in the Water Quality Index (WQI) as
scheduled in the Schedule
• Based on the WQI index, it shows all samples included in Class I, II, and III
National Water Quality Standards. Water quality is clean and acceptable for
recreation.
9|Page
f. Value of Air
• The air quality assessment will be carried out in three (3) sampling areas from
25 to 27 February 2015, as seen in Table B.
• As all six criteria are within the range permitted by the Malaysian Air Quality
Guidelines, the air quality at the project site and the surrounding area is deemed
acceptable.
g. Sound level
• Noise levels in the sampling areas N1, N2, and N3 (same location as air quality
monitoring) are conducted from 7:00 am to 10:00 pm for the day session and
at 10:00 pm to 7:00 am the session night time.
• The analysis results show that the noise levels of N1, N2, and N3 are above
the allowable levels during the day.
• This may be due to human activities in the villages - nearby villages and the
main route from the south to the east coast).
• The proposed development will be divided into eight (8) phases, namely, Phase
1 - Phase 8. In general, the proposed project will be developed only about 91%
of the total area with buildings and infrastructure will remain as open space,
buffer, and tourism.
• The Commercial Sector, which covers 7.15% (i.e., 24.50 acres) of total
development, will consist of commercial plots. There are three (3) commercial
plots proposed in this, namely development, Commercial Plots 1, 2, and 3.
• Public facilities that will be provided in this development are primary schools,
school complexes, police stations, mosques, clinics, and community centers.
• Meanwhile, the infrastructure and public facilities proposed in this development
are detention ponds, ditch reserves, TNB substations, sewage treatment
plants, road reserves, water tanks, and pump houses.
• The reservoir pond covering 18.03 acres of land (5.26%) will also be upgraded
to a recreation and landscape area.
• Paving roads occupy about 38.22 acres of land, which also includes a parking
area.
10 | P a g e
• Apart from the units built, there is also an allocation for open space, buffer
zones, and recreation. A total area of 30.20 acres (i.e., 8.82% of the project
site) planned for the proposed development's holistic growth.
• The qualitative needs of necessary infrastructure facilities and the amount of
waste generated by the expected equivalent population (PE) of 43 274 people.
Apart from proposing control measures, this report also emphasizes the formulation
and implementation of an environmental management plan (EMP). This plan needs to
be comprised of Developers, consulting engineers, contractors, and environmental
consultants. The management plans and supervision programs proposed for this
Project at the construction and operational stages are as follows:
11 | P a g e
2.0 CONCEPTS AND DESIGN OF CIVIL ENGINEERING PROJECTS
2.1 Coastal Erosion Management Techniques
Coastal erosion and accretion are parts of a natural phenomenon that shapes
the coastlines. Coastal erosion is not a problem for undeveloped (natural) shorelines
where no one lives. In developed coastal areas, however, coastal erosion can threaten
infrastructures, properties, and tourism, necessitating a coastal protection strategy. To
design a successful erosion management, plan the causes of the erosion should be
understood and the natural habitat should be considered as a part of a coastal erosion
management plan which could provide effective coastline stabilization and habitat
enhancement.
12 | P a g e
Common Types of Hard Engineering
13 | P a g e
Common Types of Soft Engineering
14 | P a g e
2.2 METHODS FOR ADDRESSING COASTAL EROSION
1. Planning
2. Regulation
3. Incentives
4. Acquisition
Land use control and land management techniques transfer the responsibility
of shoreline management from the individual to the community and are often perceived
as more difficult to implement than a single action by a property owner. The long-term
individual and cumulative benefits of these measures extend beyond those produced
by other methods, including reduced coastal infrastructure and development,
diminished water quality degradation, improved ecological status of shorelands by
avoidance of fragmentation, no loss of recreational access, increased property values,
and reduced property losses.
2.2.2 Vegetate
15 | P a g e
This procedure for addressing erosion is not limited to the shore zone but can
be used elsewhere, such as on upland banks or bluffs. Various forms of
bioengineering techniques can be employed to control groundwater seepage and
surface runoff. Vegetation also can be used to stabilize banks or bluffs—roots from
plants (trees, bushes, grasses) bind soils and form a living, adaptive barrier.
Vegetation can be used in combination with graded banks to provide an effective
approach to reduce erosion.
2.2.3 Harden
The most widely applied shoreline technique is to harden the shore or bluff with
some type of fixed structure such as a bulkhead, seawall, or revetment. The primary
goal of hardening the shore is to protect the coast from wave attack by creating a
barrier to the erosive forces.
Progression of a typical response to bay erosion. When the shoreline is receding (A), the homeowner
builds a bulkhead to protect the upland property (B) which begins to interfere with the nearshore processes,
causing vertical erosion of sediment in front of the bulkhead (C), which leads to loss of the intertidal habitat (the
area between mean high and low water) (D).
For Jabatan Pengairan Dan Saliran (JPS), creating and maintaining a beach
and dune for shore protection is often the most desirable option. Trapping and adding
sand or gravel creates an effective shore planform and cross-section for shore
16 | P a g e
protection. Structures installed perpendicular to the shore (e.g., groins) and parallel to
the shore (e.g., breakwaters) are used to trap sand, frequently in conjunction with
projects that add sand to the shoreline. Groins will reduce the volume of sand
transported downstream, potentially depriving these areas of sand needed to maintain
a beach.
2.2.5 Breakwaters
and installed. Other materials have been used with varying degrees of success,
including broken concrete, formed concrete, and tires. A breakwater or breakwater
system may or may not include the addition of sand to the system depending on the
design, site conditions (whether there is abundant sand in the reach), and the level of
shore protection required.
Stone revetment shortly after construction, and a cross-section of elements necessary for proper
stone revetment design
2.2.5 Groins
17 | P a g e
structure is classified as high, medium, or low energy depending on the percentage of
littoral drift that the groin interrupts.
By capturing sand, the groin reduces the sediment supply to the downdrift
beach, potentially triggering erosion or accelerating the rate of erosion on the downdrift
side of the groin. This accelerated erosion will result in narrowing and loss of beach
habitat. To compensate, additional sand can be added to the groin project. Shows one
such project where the sand was imported to the site and a beach was constructed to
replace a shoreline of graded riprap and broken concrete. From an aesthetic
perspective, groins create a more natural shoreface than bulkheads or revetments but
may present a hazard for boating and other recreational pursuits.
18 | P a g e
3.0 CONSTRUCTION PROCEDURE OF CIVIL ENGINEERING
PROJECTS
• They are usually constructed entirely of armour stone, but may incorporate
concrete armour units
• They have to be constructed under exposed conditions.
19 | P a g e
3.3 DESIGN OF BREAKWATER
Design for the breakwater has to be produced taking into consideration all the previous
data, for example:
• water depths (in deep water, solid vertical sides are preferred to save on
material);
• type of foundation (if ground is soft and likely to settle, then a rubble breakwater
is recommended);
• height of waves (rubble breakwaters are more suitable than solid ones in the
presence of larger waves); and
• availability of materials (if no rock quarries are available in the vicinity of the
project, then rubble breakwaters cannot be economically justified).
20 | P a g e
• The outer slope should not be steeper than 1 on 2 and the inner or harbour
side slope not steeper than 1 on 1.5.
• In general, rock breakwaters absorb most of the wave energy that falls on them
and reflect very little disturbance back from the sloping
The underlayer of stone that protects the core rubble from being washed away,
Figure 1, usually consists of single pieces of stone whose weight varies between a
minimum of half a tonne (500 kilograms) to a maximum of one tonne (1 000
kilograms). These are usually laid in a minimum of two layers at a slope which is
generally shallower than that of the core; 2/1 on the outer slope and 1.5/1 on the inner
slope. A slope of 2/1 means that the level drops 1 metre for every 2 metres forward.
The main armour layer, as its name implies, is the primary defence of the
breakwater against wave attack. The stone sizes for the cross-section in the shallow
water example should be in the range of 1 tonne (1 000 kilograms) to 3 tonnes (3 000
kilograms). Any defects in the quality of the rock, grading (size too small) or placing
(slope uneven or too steep) will seriously put the whole breakwater at risk. Hence,
great care must be taken when choosing and placing the stone for the main armour
layer.
21 | P a g e
vehicles with rubber tyres over rockfill. However, by spreading fines over the surface
with a bulldozer it should be possible to maintain access on stones. If the design does
not permit such an impermeable layer to remain in place, the fines may have to be
partially removed afterwards by water jetting. This is a costly operation and should be
implemented only when absolutely necessary for stability reasons. Access can also
be obtained by using crawler mats or by creating a temporary roadway next to the
breakwater.
22 | P a g e
dimensions dictated by the equipment. In many cases the type of crane required for
the construction of the toe and armour layer dictates the crest width.
Core material placed by cranes is usually supplied by dump trucks and the
capacity of the crane will determine the progress of the work. Cranes can use an open-
tine grab or a cactus grab or clamshell to dig into the stock of core material dumped
by trucks, or work with skips or rock trays which are filled by a loading shovel or directly
by dump trucks. In the first case, space should be provided for a shovel or front-end
loader and a truck. In the latter case, heavy cranes are required, which need
considerable space on the breakwater.
The first layer of stone may be placed by a hydraulic excavator. The excavator
should place the heavier stone as quickly as possible without leaving too much core
rubble exposed to wave action. If a storm strikes the site with too much core exposed,
there is a grave danger of the core being washed away and spread all over the
intended port area.
Main armour stone being placed by a crawler crane or tracked crane, which is
by far the best equipment for placing large stones. The large stones should be lifted
singly using a sling or stone grapple and placed in the water with the aid of a diver
swimming over the placing area. The armour layer should be placed stone by stone in
a sequence which ensures interlocking, for example, stone 2 is held in place by stone
23 | P a g e
1 and 3 whereas stone 4 is jammed between stones 3 and 5. This ensures that waves
cannot pull one stone out and cause the upper stones to topple down the slope, breach
the armour layer and expose the smaller rubble underneath. To ensure proper placing,
the swimmer or boat crew should direct the crane operator each time a stone is placed
until the stone layer breaks the surface.
As with the first underlayer, two layers of armour stones are required to
complete the main armour layer. Slope profiles should be set up at regular 5 metre
intervals using the same procedure as described previously. Figure 2 (17d), bottom,
shows how the nearly complete breakwater is closed off layer by layer. It shows the
excavator backtracking to the root of the breakwater closing the top layers
simultaneously. The end or head of the breakwater is the most delicate part of the
breakwater and requires extra care. The outer slope of 2.5/1 should be increased to
3/1 to improve its stability.
Objective
Scope
This method statement covers the requirements for all marine works up to and
including the preparation of formation level. This method statement is to be adopted
during breakwater activities for protect an anchorage from the effects of both weather
and longshore drift. This method statement describes the controlling elements during
the exaction of breakwater works.
Reference
- Construction drawing
24 | P a g e
Equipment
- Bulldozer - Roller
- Back pusher
Manpower
Appropriate Safety Signboards, barriers and lighting and other safeguards shall
be provided as required by the nature of and location of the works. All operations shall
be carried out in accordance with the safety requirements.
All field personnel will use PPE safety requirements like safety shoes, helmets, cover
all, dust mask, etc. ad required.
Procedure
Methodology
Setting Out
25 | P a g e
Preparation of Site
When any material is disposed outside the site, the disposed material shall be
graded to a neat appearance and shall not obstruct natural drainage or cause damage
to beach or property. All precautions shall be taken to prevent any erosion of the soil
on the affected areas. All unsuitable material and surplus suitable material shall be run
to spoil in tips approved by the Engineer.
Excavation
The excavation shall be carried out in accordance with the relevant approved
drawings and to the levels, widths and heights shown thereon. Hauling of material
from cuttings or the importation of fill material to the embankment or other areas of fill
shall proceed only when sufficient compaction plant is operating at the place of
deposition to ensure compliance with the specification requirements.
Any excess depth excavated below the formation level exceeding tolerance of
300mm shall be made good by backfilling with suitable material of similar characteristic
of that removed and compacted in accordance with specifications.
Breakwater
It will be necessary to protect the slope of dune sand layer between the areas
at different elevation using fabric material such as non-woven geotextile (PET short
fibre needle punched, 100g/m2) fixed on base and top with a layer of structural fill
material or equivalent.
Where shown and required, approved block stone consisting of good, shall be
provided and laid to the thickness shown in the Drawings, well rammed, and
compacted.
26 | P a g e
4.0 THE USE OF MATERIALS, PLANT / EQUIPMENT AND LABOUR
Materials, plant/equipment and labour are essential resources used during the
construction process of civil engineering projects. Project management must be
involved in managing all three elements. Materials, plant/equipment and labour are
very important to ensure that the main goal at the construction stage is achieved which
is to ensure that the project can be completed according to time, cost, quality and not
cause any form of injury to employees.
Therefore, this technical report of group 4 will explain the use of the following
items for the sea wall construction project at Tanjung Pahang beach, Rompin, Pahang
Darul Makmur.
• Materials
• Plant
• Equipment
• Labour
4.1 MATERIALS
27 | P a g e
Cost
4.1.2 Geotextile
28 | P a g e
4.1.3 Geogrid
For this coastal erosion control project, geogrid used to strengthen and stabilize
the soil for the construction of the Accessible Interlocking Unit (AIU).
Cost
29 | P a g e
4.2 PLANT
4.2.1 EXCAVATOR
Excavator is the main plant used in this coastal erosion control project and it is
also widely used in the civil construction industry. The operator maneuvers the heavy
equipment, from the cab of the excavator, throughout the construction site the cabin
arrangement can be rotated up to 360 degrees, giving the operator the ability to work
in multiple areas from one location.
The uses of the excavator for this project is for excavation work and lay rock
armour with a digging clamshell attached at the end. they are also used for other
purposes like heavy lifting and cutting of trees.
Cost
For this coastal erosion control project, the contractor has rented KOMATSU
PC200-8 from Maju Jaya Enterprise at Kuantan Pahang. The company manages
rentals including transportation and excavator operators. The rental price of this
excavator is RM 1200/day.
Loaders are a piece of a plant used for this coastal erosion control project. It's
used for earthwork which is to level backfilled and imported soil. It is also to load the
excavated soil onto dump trucks. A loader contains a large-sized bucket at its front
with a short moving arm. Loaders have higher productivity and a lower maintenance
cost unlike most of the other large-scale construction machines.
30 | P a g e
Type and Specifications
The wheel loader used in this project is SDLG LG936L. It has turbocharged
with 2200 rpm. The operating weight of this loader is 10,700 KG with a 3,000 KG lift
capacity.
Cost
For this coastal erosion control project, the contractor also rented SDLG
LG936L from Maju Jaya Enterprise at Kuantan Pahang. The rental price of this wheel
loader including transportation and operator is RM 1100/day.
There are several types of the roller such as sheep foot roller, pneumatic tyred
roller, vibrator roller, etc. The vibratory roller is one of the plants used for this coastal
erosion control project. This type of roller incorporates a large steel drum at the front
and one or two wheels or drums at the rear. For this project, a vibratory roller is used
for compacting materials such as soil and gravel.
Cost
For this coastal erosion control project, the SAKAI SW652-1 was also rented
from Maju Jaya Enterprise at Kuantan Pahang. The rental price of this wheel loader
including transportation and operator is RM 1400/day.
31 | P a g e
load and the movement depend on. They are usually diesel engine. A towing eye
is equipped for use as a tractor secondary site. There are various sizes of dumpers in
the present construction industry.
Cost
The SINOTRUK: 47 TONS dump trucks are rented from Maju Jaya Enterprise
at Kuantan Pahang. The rental price for this dump truck including transportation and
operator is RM 7,000/month.
4.3 EQUIPMENT
32 | P a g e
• Objective aperture : 42mm
• Minimum focus : 20cm
• Length : 215mm
• Weight : 1.85kg
Cost
The price of AT-B2 TOPCON automatic level is RM 2,600.
Cost
The price of TKCM 7T TOKUDEN concrete mixer is RM 6,000.
33 | P a g e
4.3.3 PLATE COMPACTOR
A plate compactor is used to compress some types of soil and gravel for
construction projects that require a stable subsurface. Plate compactors come in many
different designs with different accessories, though the major features are stable. The
core of the machine is a heavy, flat plate that rests on the ground when the machine
is off. The plate is driven or vibrated up and down with either gasoline or diesel
engines.
As a plate compactor runs, the heavy plate on the bottom of the machine moves
up and down quickly. The combination of rapid impacts, plate weight and impact forces
the soil underneath to compact or pack together more tightly. Plate compactors are at
their best when they are used on granular soil types, such as those that have higher
sand or gravel content. In some cases, it is beneficial to add some moisture to the soil
before using the plate compactor. Two to four passes over the soil are generally
sufficient to achieve proper compaction, but the compactor manufacturer or rental
establishment should be able to provide some guidance on a case-by-case basis.
For this project, a plate compactor was used to compress grade B rock and
compress soil in geogrid.
Cost
The price of IM80 TOKUDEN plate compactor is RM 1,600.
34 | P a g e
4.4 LABOUR
4.4.1 SUPERVISOR
The job supervisor acts as an intermediary between the field workers and the
management office to ensure effective communication. Many supervisors benefit from
the use of communication technology on their mobile devices that allow them to
streamline this constant communication. Aside from this, they are responsible for any
problems or conflicts that may arise between the field and the office. Day work rate for
the supervisor in this project is RM 210/day.
4.4.2 FOREMEN
The foreman is the head of the workers in the field. He oversees the project on-
site and tracks worker’s timecards and completion of tasks on schedule. The foreman
is directly responsible for any problems or injuries that occur on a job site. He is also
in charge of personnel including timecards, payroll, and often hiring or promotion.
Mobile technology aids the foreman in his communication from the job-site to the back
office. Day work rate for the foremen in this project is RM 180/day.
35 | P a g e
4.4.4 SKILLED WORKER
A skilled worker is any worker who has special skill, training, knowledge, and
(usually acquired) ability in their work. A skilled worker may have attended a college,
university or technical school. Alternatively, a skilled worker may have learned their
skills on the job. The following are the skilled workers involved in this project.
i. Fitter (RM 140/day)
ii. Concretor (RM 120/day)
iii. Steel Bar Bender and Fixer (RM 120/day)
General labour is the driving force for every project. Once the project is planned,
the workers get their hands dirty to make it a reality. They demolish old structures and
work to create new ones following specific specifications. They must be able to operate
heavy machinery, lifting large objects, and perform typical construction tasks.
Aside from their physical requirements, they must be able to effectively
comprehend the instructions they receive from their supervisors and work
collaboratively with other team members. The day work rate for the general labour in
this project is RM 90/day.
36 | P a g e
5.0 ELEMENTS OF PROJECT MANAGEMENT
A project usually requires tools and skills outside the production system. The project
organization will be formed to facilitate the project travel process to be smoother and
more perfect.
Planning
Scheduling
Controlling
For the coastal erosion project carried out in Tanjung Pahang Beach, Rompin,
Pahang Darul Makmur, the three stages are Planning, Scheduling and Controlling
using Critical Path Method (CPM) techniques.
What is Critical Path Method (CPM)? In project planning, the critical path is the
longest sequence of tasks that must be done to successfully complete the project.
Tasks that are in the critical path cannot start until the previous task has been
completed. These are tasks that, if delayed for a certain amount of time, will throw the
whole project off schedule.
Calculating the critical path, then, is key to managing a project. Identifying the
critical path lets project managers know which activities must happen for the project
to be successful. If any activities on the critical path change, then the project end date
will ultimately be affected.
37 | P a g e
Once done by hand, nowadays, the critical path is calculated automatically by
project scheduling software. That makes the CPM method a whole lot easier.
Once we map a critical path, we can use CPM to help create our project
schedule. CPM is used to model a project, and is done by looking at all the tasks and
knowing the timeline for completing the project. This includes:
• The critical path for any project, or our to-do list within a set timeframe,
represents our set of objectives for our clients. Keeping these details in mind while
overseeing a project is much more difficult than relying on software to track it and detail
the purpose for us.
• CPM scheduling helps prevent delays, wasted time, or time lost juggling a
series of necessary tasks. We can schedule our time wisely to prevent waste and stay
on schedule with the help of software and consultants.
38 | P a g e
In project management, a project team will be formed which will play an
important role in implementing the three stages of project management mentioned
above.
5.2 PLANNING
PROJECT
ACTIVITIES
ORGANIZATION MATRIX
39 | P a g e
Thus, an activity can be carried out more smoothly by each individual with the
availability of manpower and time required by the supervisor and management control
division.
5.3 SCHEDULING
After the planning process, a scheduling process is required for estimate the
time required to complete each project activity. The estimated time to complete the
project is set by comparing the company's project objectives. What will happen if the
time set exceeds the time limit?
If this happens, the project preparation period must be reduced either by adding
manpower resources or by using other means that can complete the project quickly.
Apart from adding manpower resources, one of the ways that can be used to complete
the project quickly is by working overtime.
In this way the cost of completing the project will increase. How we overcome
the problem of cost increase, will be explained in the next unit. Why does project
scheduling need to be done in implementing a project?
5.4 CONTROLLING
After the planning and scheduling stage, project activities will run. During that
time, project managers will focus on the level of control which includes resource
control, quality costs and budgets.
40 | P a g e
Control aims to:
For Control activities, the technique used for the Land Erosion project at Pantai
Tanjung Pahang, Rompin, Pahang Darul Makmur is the Gantt Chart technique.
41 | P a g e
to the occurrence of soil erosion and sedimentation problems from EIA projects as
follows:
• Erosion and Sediment Control Plan (Erosion and Sediment Control Plan -
ESCP) must be prepared as set out in the Guideline for Erosion and Sediment
Control in Malaysia - October 2010 published by Department of Irrigation and
Drainage, Ministry of Natural Resources and Environment.
• All soil and sediment erosion control measures shall implement as in the ESCP
drawing that has been verified by a Certified Engineer (Professional Engineer)
and certified (endorsed) by the Jabatan Pengairan dan Saliran Negeri Pahang.
Two (2) copies this ESCP document must be submitted to the Jabatan Alam
Sekitar Negeri Pahang within two weeks after being certified.
• Rain gauge shall be installed in an open area within the project site.
42 | P a g e
➢ Perform in-situ measurements of turbidity parameters at the
discharge point within a period not exceeding 30 minutes after
rain. If the rain continues for more than 24 hours, measurements
should be carried out once daily
• Disposal of excess soil outside the project site must be approved by the Pihak
Berkuasa Tempatan
6.0 CONCLUSION
Where project management is left to the team to work out by themselves, you’ll
find teams work without proper briefs and without a defined project management
methodology. Projects lack focus, can have vague or nebulous objectives, and leave
the team not quite sure what they’re supposed to be doing, or why.
Often a project’s goals have to change in line with a materializing risk. Again,
without dedicated oversight and management, a project could swiftly falter but good
project management (and a good project manager) is what enables the team to focus,
and when necessary refocus, on their objectives.
43 | P a g e
7.0 ATTACHMENTS
44 | P a g e
45 | P a g e
46 | P a g e