This document contains a mid-term examination for a course on Drawing Estimation and Construction Theory. It includes 4 questions assessing CLO-1 and PLO-2. Question 1 and 2 require students to prepare rough cost estimates for apartment and residential building construction projects based on given parameters. Question 3 requires estimating construction materials for a project up to the foundation and plinth level using the Center Line Method. Question 4 requires discussing legal aspects of construction projects.
This document contains a mid-term examination for a course on Drawing Estimation and Construction Theory. It includes 4 questions assessing CLO-1 and PLO-2. Question 1 and 2 require students to prepare rough cost estimates for apartment and residential building construction projects based on given parameters. Question 3 requires estimating construction materials for a project up to the foundation and plinth level using the Center Line Method. Question 4 requires discussing legal aspects of construction projects.
This document contains a mid-term examination for a course on Drawing Estimation and Construction Theory. It includes 4 questions assessing CLO-1 and PLO-2. Question 1 and 2 require students to prepare rough cost estimates for apartment and residential building construction projects based on given parameters. Question 3 requires estimating construction materials for a project up to the foundation and plinth level using the Center Line Method. Question 4 requires discussing legal aspects of construction projects.
This document contains a mid-term examination for a course on Drawing Estimation and Construction Theory. It includes 4 questions assessing CLO-1 and PLO-2. Question 1 and 2 require students to prepare rough cost estimates for apartment and residential building construction projects based on given parameters. Question 3 requires estimating construction materials for a project up to the foundation and plinth level using the Center Line Method. Question 4 requires discussing legal aspects of construction projects.
(Take-Home Examination) Course Name: Drawing Estimation and Construction (Theory) Course Code: CE-209 Session: 2018 th Semester: 4 Total Marks: 30 Time: 04 Hours
Note: Attempt all the questions.
Q. No. Question Marks CLO PLO
1. Prepare rough cost estimate for the following scenario: 05 CLO-1 PLO-2 a. Plinth area of apartment: 600 sqm b. Rate of construction: Rs. 1250 / m3 c. Height of apartment: 16.5 m d. Water supply, Sanitary and electrical installation: Each at 7% of the building cost e. Architectural appearance: 2% of the building cost f. Unforeseen Item: 3% of the building cost g. Contingencies: 3% 2. Prepare rough cost estimate of a double storey residential 05 CLO-1 PLO-2 building for the following scenario: a. Carpet area: 1440 Sft b. Plinth area rate: 2200 Rs. / Sft c. 12% of the built-up area will be taken by walls d. 28% of the built-up area to be occupied by corridors e. Water supply and sanitary: 4% of the building cost f. Electrical installation: 13% of the building cost g. Contingencies: 5% 3. Estimate the quantity of cement bags, sand, aggregate, and 14 CLO-1 PLO-2 number of bricks for the construction of following project up to foundation and plinth. (Use Center Line Method) 4. Discuss legal aspects of construction projects. 06 CLO-2 PLO-1