University of Engineering & Technology Taxila

Department of Civil Engineering

MID TERM EXAMINATION


(Take-Home Examination)
Course Name: Drawing Estimation and Construction (Theory)
Course Code: CE-209 Session: 2018
th
Semester: 4 Total Marks: 30
Time: 04 Hours

Note: Attempt all the questions.

Q. No. Question Marks CLO PLO


1. Prepare rough cost estimate for the following scenario: 05 CLO-1 PLO-2
a. Plinth area of apartment: 600 sqm
b. Rate of construction: Rs. 1250 / m3
c. Height of apartment: 16.5 m
d. Water supply, Sanitary and electrical installation: Each
at 7% of the building cost
e. Architectural appearance: 2% of the building cost
f. Unforeseen Item: 3% of the building cost
g. Contingencies: 3%
2. Prepare rough cost estimate of a double storey residential 05 CLO-1 PLO-2
building for the following scenario:
a. Carpet area: 1440 Sft
b. Plinth area rate: 2200 Rs. / Sft
c. 12% of the built-up area will be taken by walls
d. 28% of the built-up area to be occupied by corridors
e. Water supply and sanitary: 4% of the building cost
f. Electrical installation: 13% of the building cost
g. Contingencies: 5%
3. Estimate the quantity of cement bags, sand, aggregate, and 14 CLO-1 PLO-2
number of bricks for the construction of following project up to
foundation and plinth. (Use Center Line Method)
4. Discuss legal aspects of construction projects. 06 CLO-2 PLO-1