Curso Primavera p6 Conceptos Claves Tipo
Curso Primavera p6 Conceptos Claves Tipo
Duration Type
Determines how remaining duration, units, and units/time are calculated when you update an
activity that has resources assigned. The activity's duration type should correspond to the
dominant factor, that is, the least flexible factor in the project: schedule, costs/work effort, or
resource availability.
Fixed Units/Time: The resource units per time are constant when the activity duration or
units are changed. Use this duration type when an activity has fixed resources with fixed
productivity output per time period.
Fixed Duration & Units/Time: The activity duration is constant as the units or resource units
per time are changed. Use this duration type when the activity must be completed within a
fixed time period regardless of the resources assigned.
Fixed Units: The activity units are constant when the duration or resource units per time are
changed. Use this duration type when the total amount of work is fixed, and increasing the
resources can decrease the activity duration.
Fixed Duration & Units: The duration and units remain constant as the units/time is
changed. Use this duration type when the activity must be completed within a fixed time
period and the total amount of work is fixed.
CURSO PRIMAVERA P6
Conceptos Claves: Tipos de Duración
CURSO PRIMAVERA P6
Conceptos Claves: Progresando datos de actividades
Activity % Complete
The percent of the activity that has been completed.
The calculation is based on the formula for the selected Percent Complete Type. The
Percent Complete Type can be Units, Duration, Physical, or Scope.
If the selected activity's percent complete type is Duration, the percent complete is calculated
as (Planned Duration minus Remaining Duration) divided by Planned Duration.
If the activity's percent complete type is Units, the percent complete is calculated as (Actual
Labor Units plus Actual Nonlabor Units) divided by (Actual Labor Units plus Actual
Nonlabor Units plus Remaining Labor Units plus Remaining Nonlabor Units).
If the activity's percent complete type is Physical, either the user records the percent
complete manually or the field is set to calculate using steps. To calculate using steps, the
Calculate Activity % Complete from activity steps option must be set in Project
Preferences.
If the activity's percent complete type is Scope, the percent complete is calculated by Oracle
Prime Projects and cannot be modified in P6.
CURSO PRIMAVERA P6
Conceptos Claves: Progresando datos de actividades
Cost % Complete
The percent complete of costs for all labor resources, nonlabor resources, and expenses for
the activity or project.
Calculated as Actual Total Cost divided by At Completion Total Cost multiplied by 100.
Duration % Complete
The duration percent complete for an activity, WBS, or project.
Calculated as Planned Duration minus Remaining Duration divided by Planned Duration
multiplied by 100. The value is always between 0 and 100.
CURSO PRIMAVERA P6
Conceptos Claves: Progresando datos de actividades
Performance % Complete
The percentage of the activity or project planned work that is currently complete.
Performance % Complete is used to calculate earned value. It can be based on the activity
percent complete, on the 0/100 rule, on the 50/50 rule, depending on the technique for
computing earned-value percent complete for the activity's WBS.
CURSO PRIMAVERA P6
Conceptos Claves: Progresando datos de actividades
Physical % Complete
The activity percent complete, which is either user-entered or calculated from activity steps.
To calculate Physical % Complete from activity steps, the Calculate Activity % Complete
from activity steps option must be enabled for the project.
CURSO PRIMAVERA P6
Conceptos Claves: Progresando datos de actividades
CURSO PRIMAVERA P6
Conceptos Claves: Progresando datos de actividades
Units % Complete
The percent complete of units for all labor and nonlabor resources assigned to the activity.
The percent complete is always in the range 0 to 100.
Calculated as Actual Units divided by At Completion Units multiplied by 100.