Piping Coordination Systems - Reference Points

Foreword - Location is Relative


An object's location is always given relative to another reference object.
For example, the location of a Heat Exchanger may be described as five blocks from the
General Service Building. To be more specific, the Heat Exchanger is four blocks east and three
blocks south of the General Service Building. With this illustration, a direction and a distance
from the General Service Building has been established.

Several things are assumed to be known, the place to begin


(General Service Building), and understanding of east and south
(reference directions), and the length of a block (unit of displacement).
Without consensus on these things, communication of the location of a
Process Plant becomes unclear.
Before beginning with making drawings for a new process plant or
building, there must be determine where the new building in the area
will take his place. A coordination system, which refers to an officially
recognized point therefore is necessary.
In the Netherlands, for example, are thousands of official reference
points, distributed across the country ...search on the Internet on
geographic coordinate conversion, triangulation stations, benchmarks,
geography or topography. You'll find a lot of information about how
reference points are measured and identified.

Horizontal Reference
Defining a starting point of the site related to the North / South direction, is one of the first steps
in setting up a coordination system.

http://www.wermac.org/documents/coordination_part1.html 1/3
8/19/2018 Piping Coordination Systems - Reference Points - Elevations - Plant North -

In principle, with a simple reliable compass the direction of the magnetic north can to be
determined. In the image below the true north is at 18°. As a draftsman would work with the true
north coordinates, he will immediately find out that each line from west to east and from north to
south at an angle of 18° must be drawn.
To avoid this, a Plant North will be determined. In the example below, the true north, 18° is
reversed, draftsmen and construction contractors will be grateful for it.
General there will be tried, to approach the true north-south coordinates as close as possible.
A rule is, that the angle between true north and Plant North can not exceed 45°. At 50°, for
example, the Plant North would be on the right side, so on the Eastern side of the image.

1 = Official reference point


2 = South West angle of new plant
X = East West distance from new plant to reference point
Y = North South distance from new plant to reference point

Vertical Reference
Before starting with any building, the site is leveled (graded), what means that the ground is
made as flat as practically possible. After leveling we talking about "finished grade", where the
highest graded point is termed "high point of finished grade".
This highest point of finished grade refers to an official reference point on which all vertical
measurements are related. In the Netherlands, for example, many vertical measurement are in
relation to the "Normaal Amsterdams Peil" (NAP). If the field compared to the NAP is 1 meter
higher, usually the reference point will not become a zero start of 1000 mm, but in this case a
zero start at zero(0).
On a isometric view of a pipe line elevations are indicated by EL.109665 or EL.99450 etc..
What is meant by this vertical dimensions ?

The first EL.109665 you can read as: centerline of pipe is 9665 mm above zero point
The second EL.99450 you can read as: centerline of pipe is 550 mm below zero point

Well, the vertical zero point in this case is 100 meters (100000 mm), and this has the advantage
that no negative (minus) values on drawings need to be applied.

http://www.wermac.org/documents/coordination_part1.html 2/3
8/19/2018 Piping Coordination Systems - Reference Points - Elevations - Plant North -

REMARK(S) OF THE AUTHOR...

CENTER-LINE AND ELEVATION SYMBOL


I have learned, to apply a centerline, a Elevation symbol and a Center-Line symbol to a
isometric.
Namely, the Center-Line symbol at the end of the centerline, and ON that line the
Elevation symbol, followed by the elevation-numbers.

The sign on the left shows the centerline symbol.


Tip for AutoCad users: use the CDT font, lower case Q.

The sign on the left shows the Elevation symbol.


That sign, you will see on almost every isometric.

A combination of both signs, you see rarely nowadays on an isometric. Usually only the
Elevation symbol is applied. Why? There are many reasons to make no old-fashioned
isometrics.
Large-engineering companies can tell you why!

VARIOUS PIPING RELATED ARTICLES (ranked on last addition)

Williams Geismar Olefins Pressure Testing Nord Stream 2 First car


Reboiler Rupture Catastrophic Failure From Russia to Europe powered by formic acid

SHOW ME MORE

© Werner Sölken 2008 - 2018. All rights reserved.