You are on page 1of 122

 

WATANIYA ENVIRONMENTAL SERVICES CO. (W.E.S.)


THE STATE OF KUWAIT

DEVELOPMENT OF THE ENVIRONMENTAL AND


SOCIAL MANAGEMENT PLAN
FOR
THE NEW CONTAINER TERMINAL
DAMIETTA, EGYPT

SUBMITTED TO:
DAMIETTA INTERNATIONAL PORTS CO. (DIPCO)

DECEMBER 2008
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

TABLE OF CONTENTS
SECTION 1
1. INTRODUCTION AND BACKGROUND............................................................ 1 – 4
1.1 Legal and Administrative Framework.................................................. 2 – 4
1.2 Structure of ESMP................................................................................. 4
SECTION 2
2. APPROACH TO ENVIRONMENTAL AND SOCIAL IMPACT
MANAGEMENT.................................................................................................5 – 12
2.1 Egyptian Environmental Regulations.................................................. 5 – 6
2.2 Health, Safety and Environment Policy............................................... 6 – 7
2.2.1 Current HS&E and Emergency Plans and Situation for DPA............ 7
2.3 Oil Spill Contingency Plan.................................................................... 8 – 10
2.4 DIPCO HS&E Plan.................................................................................. 10 – 11
2.5 ESMP Implementation Mechanisms.................................................... 11 – 12
SECTION 3
3. THE PROPOSED PROJECT............................................................................. 13 – 15
SECTION 4
4. IMPACT MITIGATION AND MANAGEMENT PROGRAMS............................. 16 – 28
4.1 Environmental and Social Aspects...................................................... 16
4.2 Impacts during Construction and Operation...................................... 16 – 25
4.3 Health, Safety, Environment and Communities (HSEC).................... 26
4.4 Objectives of HSEC............................................................................... 27 – 28
SECTION 5
5. ORGANIZATIONAL STRUCTURE AND HSEC MANAGEMENT..................... 29 – 34
5.1 Emergency Action Plans.......................................................................33 – 34

QF34 Version No. 1


Page i of v
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 6
6. ENVIRONMENTAL AND SOCIAL MONITORING........................................... 35 – 51
6.1 Water Quality Monitoring...................................................................... 37
6.1.1 Turbidity / Total Suspended Solids (TSS) Thresholds....................... 37
6.2 Marine Ecology...................................................................................... 38
6.3 Quality Assurance Responsibilities.....................................................38 – 39
6.4 Water Quality Instrumentation............................................................. 39
6.5 Sample Collection and Handling.......................................................... 39 – 40
6.6 Reporting................................................................................................ 40
6.7 Monitoring Events................................................................................. 40 – 48
6.8 Monitoring Social and Community Impacts........................................ 49
6.9 Operational Phase Monitoring Program.............................................. 50
6.10 Maintenance Dredged Materials Management Plan (MDMP)............. 51
SECTION 7
7. ESMP Schedule and Costs.............................................................................. 52 – 57

LIST OF FIGURES
Fig. 1.1: Location of Damietta Port......................................................................... 2
Fig. 2.1: Location of Fire-Fighting Facilities.......................................................... 8
Fig. 2.2: National Spill Response Contingency Plan............................................ 10
Fig. 2.3: Steps needed for ESMP............................................................................ 12
Fig. 3.1: The Main Zones of Damietta Port.............................................................15
Fig. 5.1: Organization for HSEC Plan during Construction.................................. 30
Fig. 5.2: Organization for HSEC Plan during Operation....................................... 31
Fig. 6.1: Flow of Information with this Project.......................................................36

QF34 Version No. 1


Page ii of v
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Fig. 6.2: Turbidity Level Contingency Flow Chart.................................................48

LIST OF TABLES
Table 4.1: Environmental Impacts during Construction and Operation................ 18 – 25
Table 4.2: Safety and Emergency Preparation Programs....................................... 28
Table 6.1: Monitoring Events before starting Dredging.......................................... 42
Table 6.2: Monitoring Events during Dredging........................................................ 43
Table 6.3: Monitoring for Dumping Events............................................................... 45
Table 6.4 Sampling Locations, Frequencies and Responsibilities....................... 50
Table 7.1: ESMP Schedule and Costs....................................................................... 52 – 57

QF34 Version No. 1


Page iii of v
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

ACRONYMS
AfDB African Development Bank
BOD Biological Oxygen Demand
CO Carbon Monoxide
COD Chemical Oxygen Demand
DIPCO Damietta International Port Company
DO Dissolved Oxygen
DPA Damietta Port Authority
DMP Dredging Management Plan
EAP Emergency Action Plan
EBS Environmental Baseline Survey
EEAA Egyptian Environmental Affair Agency
EHS&S Environmental Health, Safety & Security
EIA Environmental Impact Assessment
ESIA Environmental and Social Impact Assessment
ESMP Environmental and Social Management Plan
GIS Geographic Information System
HazMat Hazardous Materials
HMMP Hazardous Material Management Plan
HS&E Health , Safety and environment
HSEC Health, Safety, Environments & Community
IFC International Finance Cooperation
KGLPI Kuwait Gulf Link Ports International
MC Marcie Contractor
MDMP Maintenance Dredged Material Management Plan
MoT Ministry of Transportation
NO2 Nitrogen Dioxide
NOSCP The National Oil Spill contingency Plan

QF34 Version No. 1


Page iv of v
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

OC Onshore Contractor
OHSE Occupational Health Safety & Environmental
PM10 Particulate Matter (<10 µm)
PPE Personal Protective Equipment
QA / QC Quality Assurance / Quality Control
SEIA Social and Environmental Impact Assessment
SH&E Safety, Health & Environment
SO2 Sulfur Dioxide
S‰ Salinity
TOC Total Organ Carbon
TPH Total Petroleum Hydrocarbon
TSHD Trailing Suction Hopper Dredge
TSS Total Suspend Sediments
VOC Volatile Organic Compounds
WB World Bank
WESCO Wataniya Environmental Services Company

QF34 Version No. 1


Page v of v
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 1
1. INTRODUCTION AND BACKGROUND
Damietta International Ports Company (DIPCO) is executing a 40-year concession to
construct, develop and operate a green-field container terminal within the Port of Damietta
on Egypt’s Mediterranean coast. The Port of Damietta is located 70 kilometers west of the
Mediterranean entrance of the Suez Canal and lies on the main trade routes between
Asia/North Africa and Europe/North America. The port’s location minimizes a containership’s
deviation from its travel route, thereby minimizing sailing time and operating costs for
transshipment activities. Located 191km from Cairo, the Port of Damietta can also effectively
serve Egypt’s growing import/export market and help shipping lines maximize capacity
utilization on its containerships. The project which will occupy approximately 130 hectares of
land at the port and developed in two phases will include the construction of new quay walls
and container stacking areas in order to service large post Panamax ships. The activities at
new container terminal at Damietta need to be conducted in a way that minimizes the
environmental damages. This project will generate environmental and economic benefits.

This project is classified as category "1" according to the African Development Bank (AfDB).
A project is classified as category "1" if it is likely to have significant adverse impacts that are
sensitive, diverse, or unprecedented. These projects may affect an area broader than the
sites or facilities subjected to physical works. For Category 1 project, the project sponsor is
responsible for preparing a full Environmental Impact Assessment (EIA) report and submits it
to the AfDB's review prior to launching the appraisal mission. Once the EIA has been
finished, the project sponsor will prepare an Environmental and Social Management Plan
(ESMP) (Internet Source: www.afdb.org). The ESMP is aimed at mitigating the possible
adverse impact of the project and for ensuring to maintain the existing environmental quality.

1.1 Legal and Administrative Framework


According to the Egyptian Environmental Affairs Agency (EEAA) environmental legislation of
1994 and according to the EEAA environmental guidelines for ports and marinas, each new
establishment or project as well as expansion of an existing establishment (which is the case
of the new extension of the Damietta port) must be subject to an “environmental and social
impact assessment” (ESIA) before a permit is issued. In this respect, DIPCO had assigned
Wataniya Environmental Services Co. Kuwait (WESCO) to conduct the necessary ESIA
study for the new port extension. EEAA has issued an environmental site approval permit
conditional on the completion and implementation of an ESMP. The ESIA also conforms to
Category 1 requirements of the AfDB’s Environmental and Social Impacts Assessment
Procedures.

QF34 Version No. 1


Page 1 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Fig. 1.1: Location of Damietta Port

The project’s Environmental and Social Management Plan (ESMP) was summarized in
the EIA report (2007). The ESMP consists of a set of mitigation, monitoring, and institutional
measures to be taken during implementation and operation to eliminate adverse
environmental and social impacts, offset them, or reduce them to acceptable levels.

Following a full EIA processes, culminating in submission of an EIA report, an ESMP may be
required as a condition of project approval. These ESMP would be based largely on the
mitigation measures proposed in the EIA, as well as any additional requirements (Lochner,
2005).

The purpose of the ESMP is to ensure that social and environmental impacts, risks and
liabilities identified during the Environmental and Social Impacts Assessment (ESIA) are
effectively managed during the construction and operation of the port. The ESMP will specify
the mitigation and management measures to which DIPCO is committed, and shows how
the Project will mobilize organizational capacity and resources to implement these
measures. The ESMP also shows how mitigation and management measures will be
scheduled.

The objectives of the ESMP is to bring the project into compliance with applicable national
EEAA environmental and social legal requirements and the African Development Bank’s
environmental and social policies with the view to outline the mitigating/enhancing,
monitoring, consultative and institutional measures required to prevent, minimize, mitigate or
compensate for adverse environmental and social impacts, or to enhance the project

QF34 Version No. 1


Page 2 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

beneficial impacts. The key objectives of the ESMP are to:


a. Develop a framework for the implementation of environmental and social
management initiatives outlined in the original ESIA study.
b. Develop a formal plan for disclosure and consultation of the environmental and social
management plan.

1.2 Structure of the ESMP


It is important to mention that, the ESMP will be structured in order to be an active and living
working document and ready to be used during the project life cycle. More specifically, the
ESMP includes the following components.
a. Approach to Environmental and social Impact management.
b. Project Description
c. Impact mitigation and management programs, which includes the social and
environmental positive and negative impacts, the mitigation measures and the
associated program such as Health, safety, environment & community program
(HSEC).
d. Organizational structure and HSEC Management programs, where description of the
roles and responsibilities for implementation and management of the community and
operational phases.
e. Environmental and social Monitoring Program including programs for regular
monitoring of all significant environmental parameters in order to check the
compliance status vis-à-vis the environmental laws and regulations.
f. ESMP schedule and estimated cost (if applicable) which include monitoring and
training schedules as well as cost estimate whenever possible.

QF34 Version No. 1


Page 3 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 2
2. APPROACH TO ENVIRONMENTAL AND SOCIAL IMPACT MANAGEMENT
According to the EEAA, the management strategy for ports and harbors should demonstrate
that sound environmental practice should be followed during establishment, operation,
rehabilitation and end-use of the port (Abul-Azm and Rakha, 2002). This should include:
• Management of construction impacts, if appropriate, erosion and sedimentation
management and re-vegetation plans for areas distributed by construction activities.
• Management of operational impacts, if appropriate include details of materials
management on site, including hazardous and non-hazardous materials
management, air quality management, transport and parking management,
maintenance and site security plan, the contingency plans to respond to emergency,
incidents or any breakdown in the in environments performance.
• Strategies to feed information from the monitoring program back into the
management practices and action plans to improve the environmental performance
and sustainability of all components of the scheme.
• Training program for operational staff and incentive for environmentally sound
performance.
• An indication how compliance with licensing and approval requirements will be
achieved and due diligence attained
• If possible, reporting mechanism on environmental performance and performance
bond and relevant performance parameters.

2.1 Egyptian Environmental Regulations


Law No. 4, passed in 1994, is the main Environmental Law in Egypt concerning the
environment. This law established the Egyptian Environmental Affairs Agency (EEAA) as
the competent authority. The Executive Regulations of this law were set out in 1995. The
EEAA has the power to set criteria and conditions, monitor compliance and to take action
against violators of these criteria and conditions. Various decrees have also been passed
dealing with drainage of liquid wastes, and protection of the River Nile and other waterways
from pollution.

Law 4 dictates that the licensing authority must assess the environmental impacts of
proposed facilities. The assessment shall include a statement of all elements of the facility’s
self-monitoring system, and the expected contaminant levels. The Egyptian Environmental
Affairs Agency shall verify the foregoing whenever necessary (Article 10, Decree 338,
amended by Decree 1741 of 2005 (A10/D338, amended by D1741). The license application
must include comprehensive data about the facility, to fulfill the requirements of the form
structured by the EEAA and the Competent Administrative Authority (CAA) (A12/D338,
amended by D1741).

The EEAA must be notified of any expansions, modifications or renewals to the existing
facility or any work that might result in an adverse impact on the environment or workers.

QF34 Version No. 1


Page 4 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Such expansions/modifications/renewals are subject to Articles 19, 20, 21, and 22 of Law 4
(A19/D338, amended by D1741).

2.2 Health, Safety & Environment Policy


The EIA report which was produced for Damietta project included a section on Health,
Safety & Environment (HS&E). The HS&E was dedicated to providing a safe and healthy
environment not only for the employees, but also for the customers and to ensure the
protection to the public and creating an environmentally, friendly atmosphere. The HS&E
policy was comply with IFC's Occupational health and safety guidelines and included
training, use of personal protective equipments and standard operating procedures.

The HS&E for Damietta aims also to ensure that DIPCO will run parallel to the standard
Damietta Port Authority (DPA), emergency and HS&E plan and policy. It is important to
mention that HS&E of DIPCO will comply with the DPA general HS&E policy and regulations
especially during operation phase.

2.2.1 Current HS&E and Emergency Plans and Situation for DPA:
Damietta Port Authority (DPA), in line with international standards for port operations,
maintains emergency response, fire protection and spill control procedures, equipment and
trained person. In order to study the current situation for HS&E at DPA, meeting was
conducted with the HS&E Department at DPA. According to the HS&E Department at DPA,
the active program now is the emergency response and fire-fighting program. Fig (2) shows
the location of the current fire-fighting facilities at Damietta Port.

Appendix I “in Arabic” illustrates the fire and Civil Defense plan. The plan indicated that, in
case of accident or fire, the main operational center in DPA will be notified. The Civil
Defense Unit has 5 Fire-fighting vehicles with capacity ranging from 2.5 to 7 Tons of water.
In addition to these 5 units, 6 small vehicles are ready for quick responses and logistics. The
document also illustrates all facilities for firefighting within Damietta Port buildings.

Fig. 2.1: Location of Fire-Fighting Facilities

QF34 Version No. 1


Page 5 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

2.3 Oil Spill Contingency Plan


The National Oil Spill Contingency Plan (NOSCP) was prepared in 1986 by the petroleum
sector with some Canadian aid. The Egyptian Environmental Affairs Agency (EEAA) then
updated it in 1998 with some Danish aid (Fig 3). The NOSCP is the national framework for
action in the event of an oil pollution incident. It is based on three levels of response called
tires:
• Tier One: is essentially the responsibility of and all offshore petroleum activities, oil
handling facilities, (offshore installations; terminals, refineries; etc), individual port
authorities and the Suez Canal Authority
• Tier Two: is essentially the responsibility of EEAA. Oil spill response with contingency
plans for geographical sectors of the Egyptian coast should be capable of dealing
with up to 1,000 tons each
• Tier Three: Handling spills larger than 1000 tons is the responsibility of EEAA to
coordinate the response to such major oil spills and establish a minimum level of pre
positioned oil spill combating equipment in accordance with the International
Convention on Oil Pollution Preparedness, Response and Co-operation,1990

Additional contingency plans have been drawn up by the Suez Canal Authority to respond to
spills within the Canal itself and its approaches at Port Said and Suez. The main four ports in
Egypt (Alexandria, Suez Port Said and Damietta Ports) have also developed contingency
plans (The International Tanker Owners Pollution Federation Limited, 2005, The Country
Profiles)

It is important to mention that the Response Policy of the Oil Spill Contingency Plans in
Egypt is that, mechanical recovery of oil at sea is the preferred methods of response. Where
adverse weather conditions or strong currents preclude this, dispersant is permitted. The
port Authorities at the four main ports, all possess stocks of specialized equipments in order
to provide an immediate response to spill from vessels in the harbors.

Fig. 2.2: National Spill Response Contingency Plan


(Source: Bashat, H., 2005 International Oil Spill Conference)

QF34 Version No. 1


Page 6 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

2.4 DIPCO HS&E Plan:


Kuwait Gulf Link – Ports International (KGLPI) prepared a draft Environmental Health &
Safety and Security (EHS&S) policy which will be applied for Damietta Port (Appendix II).
The EHS&S includes 5 components:
a. Emergency Evacuation: which provides a plan for evacuation of all personnel in the
port operated facilities.
b. Emergency Notification: It Provides timely communication of emergency situations to
the proper Authorities, organizations, or departments in order to notify, alert, or
request assistance.
c. Emergency Preparedness: It identifies minimum knowledge, training and skills
required for port operated facilities as First Responders team to manage operational
emergency situations.
d. Military Threat policy: It purposes to ensure that personnel respond appropriately to
civil defense sirens, and
e. Respond to Emergencies: It aims to identify minimum knowledge, training, and skills
required for KGLPI First Responders to contain/control various Emergencies such as,
fire, rescue and hazardous materials-spillages.

It should be noted that these policies will be in compliance with DPA policies. The EHS&S
policy will be applied during both construction and operation phases. DIPCO is required to
fully coordinate with DPA and other authorities (such as Fire-fighting Department) during the
project life cycle.

2.5 ONSHORE WORKS CONTRACT HS&E POLICY:


The assigned contractor for HS&E onshore works is “ARCHIRODON Construction
(Overseas) Co., SA. They had issued full detailed Health and Safety Plan and Onshore
Works Environmental Plan. An updated Health and Safety plan was done and issued on the
20th of October, 2008. These documents explain the HS&E issues during construction of the
on works. Appendices II and III illustrates the HS&E and Environmental Plans for Damietta
Project.

2.6 ESMP Implementation Mechanisms


The mechanism for the implementation of the ESMP documents was as follows:
1. Reviewing the available documents such as:
a. Environmental Baseline and SEIA reports for Damietta project produced by
WESCO
b. Environmental Baseline survey (EBS) and DMP reports produced by
WESCO/ENSR
c. The ARCHIRODON Health & Safety and Environmental Considerations
d. KGLPI EHS&S documents.
e. Any other documents related to the site (Damietta Port) such as any EIA studies
done on other projects in the port (If available).

QF34 Version No. 1


Page 7 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

2. Site visit to Damietta Port in order to discuss the HS&E plan for DP and any other related
programs. Visit was done to HS&E Department and was with Eng. Mohamed El-Sadat
and Eng. Fatma Khalil, Head of Occupational Health and Safety Department.
3. Producing a quick draft report and submitted to DIPCO/Lender for reviewing.
4. Producing the draft final and the final ESMP report and submit this report to DIPCO in its
final format-form.
5. A Geographic Information System (GIS) database information system was suggested to
report all activities such monitoring plan, documentation, training schedules and any
other related information and data.

QF34 Version No. 1


Page 8 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 3
3. THE PROPOSED PROJECT
Damietta is an existing port that has been in operation since 1987. The Damietta Port
Authority (DPA) maintains emergency response, fire protection and spill control procedures
and equipment. The project will coordinate and harmonize with these procedures. Damietta
Port is fully committed to ensuring that all employees and customers are instructed in the
Healthy and safe work practices, and to maintain an environmentally friendly sound port.

Damietta Port will provide general training on policies and procedures to all employees, and
specific training on equipment, whether manual or motorized, and electrical to the
employees work situation.

The present project will involve the extension of the existing harbor area (Figure 3). The
proposed project will occupy approximately 130 hectares of land within the existing port.
There will be some dredging involved for the project, but there will be no changes on the
inlet itself.

The new developments include the construction of a new U-shaped basin with total new
terminals of about 2360 m. These new terminals berths will be able to accommodate giant
container vessels with maximum draft of 16 m, and a length of 400 m and a width of 53 m.
The Damietta port project will consists of:
a. Construction of new quay walls,
b. Dredging the access channel and turning basin,
c. Purchasing and installing the necessary cargo loading and offloading equipment
and
d. Developing the terminal storage area and container yards.

The approach channel and port are regularly dredged as part of maintenance dredging by
the DPA to a depth of 15 meters. As part of the project, the approach channel and turning
basin will be deepened to 18 meters to accommodate ships with larger drafts. Extensive
wave modeling study was conducted as part of the ESIA to investigate the impacts of the
port extension on the sediment accretion/erosion along the coast and sedimentation inside
the port. The study indicates that no adverse impact from accretion or erosion of the
coastline is expected due to the expansion of the current port.

Its estimated additional handling capacity will be of 2.5 million tones making the terminal
one of the largest trans-shipment facilities in the Mediterranean and the only ones capable
of handling the new generation of large containerships.
According to the EEAA guidelines of port and marinas construction projects, the proposed
project is classified as environmental category C or B. This implies that it wouldn't involve
significant environmental problems in any phase of its construction.

QF34 Version No. 1


Page 9 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Apart from this, the project and the new extension is complied with prerequisites and
guidelines approved by the EEAA. This was based on the following facts:
ƒ The proposed land-use is permissible
ƒ The use is compatible with nearby land uses.
ƒ Environmentally sensitive or protected areas are absent in the region

The proposed project is a new development in an undeveloped area at Damietta Port far
from any urban area or public amenity. Large wetlands such as inland coastal lakes or fish
farms or are not common or known at the port area or its vicinity. There are no remarkable
tourist attractions, known historical sites, or archaeological assets near the port or the
proposed extension.

Fig. 3.1: The Main Zones of Damietta Port

QF34 Version No. 1


Page 10 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 4
4. IMPACT MITIGATION AND MANAGEMENT PROGRAMS
4.1 Environmental and Social Aspects
Damietta is an existing port in operation since 1987nel. It should be recognized that as the
proposed project is an extension to the existing port, all land use for the new Terminal and
project falls within the existing port area; thus no new land acquisition or direct or indirect
displacement of people will occur. There are no protected areas or sensitive natural habitats
within the project area. The site is bare sandy land with minimal vegetation that has, in part,
been previously used for dumping sand from excavation within the port. There are no known
indigenous or cultural properties in the area. An archaeological survey conducted at the time
of the establishment of the original port did not discover any cultural property. Furthermore,
the area has been designated as having no historical importance. It is important to note that
there is a small section of the site that was previously used by the Egyptian military for
munitions storage. This area has been certified as free of munitions prior to handing over to
the project.

4.2 Impacts during Construction and Operations


Environmental issues in the port construction and operation primarily include the following
(discussed in detail in the ESIA Study):
a. Land Use
b. Dredged material management
c. Air Emissions
d. General Waste Reception, Waste Water, and Solid Waste Management
e. Hazardous Materials Management Noise
f. Water Quality
g. Biodiversity
h. Terrestrial Flora and Fauna
i. Socio-Economics

The proposed site for the new development is infertile bare land covered with very sparse
shrubs and bushes of no environmental value. There is no any land-use or public community
in this site except for using its northern parts as a dumping site for pilling up of some
dredged materials and solid wastes. There is also no valuable flora and fauna in or near the
project area. Appendix V summarizes the EIA issues, impacts and mitigation measures
during construction and operational phases.

4.3 Health, Safety, Environment and Communities (HSEC)


Impacts on community are expected to be minimal. Anticipated noise and dust are expected
to be within the permissible limits. No impacts on agricultural land or irrigation are expected.

No impacts on community water supply are anticipated as the port will secure its water
needs from the DPA and not the boreholes that supply the local communities.

QF34 Version No. 1


Page 11 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Given that the port is in a urban area, impacts associated with construction influx are
anticipated to be minimal. The sponsor will nevertheless coordinate with the DIPCO with
regard to increased traffic and develop Hazardous Material Management Plan (HMMP) that
addresses all risks to communities associated with transport of material or cargo.

The Government together with the DIPCO will be responsible for overall security, and
access, to the port. Security guards will be trained in the security procedures.

The Health, Safety, Environment and Community (HSEC) policy is dedicated to providing a
Safe and Healthful Environment not only for the Employees, but also the Customers and
community, and to ensure the protection to the public and creating an environmentally
friendly atmosphere. The HS&E Programs aim at reducing and controlling hazards, and
minimizing the risk to the employees, and customers in accidents, injuries, and incidents.

4.4 Objectives of HSEC:


• The HSEC program is aiming at reducing and controlling hazards and minimizing the
risk to employees, customers and communities in the accidents, injuries and
incidents.
• DIPCO is fully committed to ensure that all employees and customers are instructed
in the Health and Safety work practices and to maintain an environmentally friendly
sound port.
• All employees and contractors will be aware of the HS&E rules.
• Safety rules will be posted for customers for the observation and follow up.
• The EIA report, gave a fully detailed on safety rules that will be followed during
stages of the project.

The following programs will be implemented and provided for all employees during project
life cycle.

QF34 Version No. 1


Page 12 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Table 4.1: Safety & Emergency Preparation Programs


Construction Operation Decommission
Program
Included Responsibilities Included Responsibilities Included Responsibilities

Firs Aid Basic DIPCO/ DIPCO/


Yes Yes Yes DPICO/DPA
Procedure Corporate /DPA Corporate /DPA

DIPCO/ DIPCO/ DIPCO/


HS&E Policy Yes Yes Yes
Corporate Cooperators Corporate

DIPCO HS&E DIPCO/ DIPCO/ DIPCO/


Yes Yes Yes
Program Corporate Corporate Corporate

Hazards DIPCO/ DIPCO/ DIPCO/


Yes Yes Yes
Communication Corporate /DPA Corporate Corporate

Haz Materials DIPCO/ DIPCO/ DIPCO/


Yes Yes Yes
spills Corporate /DPA Corporate Corporate

Personal
DIPCO/ DIPCO/ DIPCO/
Protection Yes Yes Yes
Corporate /DPA Corporate Corporate
Equipments

Emergency DIPCO/ DIPCO/ DIPCO/


Yes Yes Yes
Procedures Corporate /DPA Corporate Corporate

Job specific DIPCO/ DIPCO/ DIPCO/


Yes Yes Yes
HazMat Corporate /DPA Corporate Corporate

Fire Fighting Yes DIPCO//DPA Yes DIPCO//DPA Yes DIPCO//DPA

Spill
DIPCO/ DIPCO/DPA/EEA DIPCO/
Contingency Yes Yes Yes
Corporate /DPA A Corporate
Plan

Ship / Shore DIPCO/


No Yes No
Safety Corporate

Emergency
DIPCO/ DIPCO/ DIPCO/
Action Plan Yes Yes Yes
Corporate /DPA Corporate Corporate
(EAP)

QF34 Version No. 1


Page 13 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 5
ORGANIZATIONAL STRUCTURE AND HSEC MANAGEMENT
5.1 The corporate HSEC Structure:
DIPCO is fully committed to ensuring that all employees and customers are instructed in the
Healthy and safe work practices. DIPCO will provide general training on policies and
procedures to all employees, and specific training on equipment, whether manual or
motorized, and electrical to the employees work situation.

The following flow diagram (Fig 5.1) illustrates the Organization of the HSEC Plan during
construction.

Fig. 5.1: Organization Chart for the Health, Safety, Environment and Communities
(HSEC) Plan during Construction

QF34 Version No. 1


Page 14 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

During operation, the HSEC plan will be as illustrated in the following diagram (Fig 5.2.)

Fig. 5.2: Organization Chart for the Health, Safety, Environment and Communities
(HSEC) Plan during Operation

QF34 Version No. 1


Page 15 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

5.2 Role and Responsibilities of implementation and Management HSEC program:


5.2.1 During Construction:
5.2.1.1 DIPCO Responsibilities:
In General, DIPCO will be fully committed to ensure the implementation of HSEC program
during construction. The following points indicated DIPCO Responsibility during construction:

• To ensure the inclusion of SH&E consideration when planning work or work


schedules.
• To take prompt corrective action on observed non-compliance and sub-standard
practices issues.
• To ensure that all employees for DIPCO and its subcontractors are fully aware with
HS&E issues as well as OHSE issues
• To make sure that the contractor and corporate are following the HS&E policy and
regulations.
• To supervise the HS&E work of the contractors.
• To revise all HS&E reports produce by the contractors.
• To supervise the monitoring programs during construction works.
• To prompt response for any environmental violation.
• To coordinate with DPA and other authorities in the HS&E issues.
• To supervise the training program and follow-up issues.
• To maintain a GIS-Database Reporting system that covers all HS& E Issues.

This responsibility for implementation and Management of the HSEC program will be at
different levels. The levels include managerial levels, engineering level and all employees’
levels. Table 5.1 identifies the responsibilities towards implementation of HS&E policy and
regulations during construction works.

Table 5.1: HS&E responsibilities at different levels.


Level Responsibility
• Ensure the application of the HSEC rules and regulations.
• To ensure the inclusion of Environmental, safety & health considerations when planning work or
work schedules.
1. Project Manager

• Promptly responding to all subordinates and other persons of non-compliance with HS&E policy
and regulation.
• Taking prompt corrective action on observed non-compliance with HS& policy and regulations.
• Take prompt corrective action and advice the corporate HSE manager accordingly with regards
with potential adverse impact on the HS&E issues.
• Communicate with DPA and other authorities (MoT, EEAA) in regards of HS&E.
• Adequately contributing to the HS&E investigation and reporting of all environmental incidents
and near misses.

QF34 Version No. 1


Page 16 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

• Ensure the application of the HSEC policy


• Ensure the inclusive of HS&E consideration in all working plans and working schedules.
• Ensure the application of the training program throughout the project stages.
2. HS&E Manager

• Ensuring that all employees make the correct use of personal protective equipment and that such
equipment is in good condition, is suitably rated with consideration to the hazards involved and is,
suitable to the user.
• Be responsible on the reports contents and quality.
• Ensuring through his supervisory line that all facilities, tools, equipment, plant and vehicles in use
within his area of management responsibility, whether owned/operated by DIPCO or corporate.
• Participating in the follow-up and close-out of corrective actions that arise from operational
activities, meetings, incidents, near misses, emergency exercises, inspections or audits that take
place within his area of management responsibility.
• Coordinate with all corporate.
• Participate in any training for which he is nominated.
3. All Employees

• Participate in any HS&E exercises that take places at his work location.
• Become sufficient familiar with safety equipments and HS& rule and regulations.

5.2.1.2 Contractors Responsibilities during construction phase:


The following points represent the contractors’ responsibilities during construction works:
• To make sure that the contractor employees and his sub-contractors are following and
aware by the HS&E and OHSE rules and regulations.
• To make assure that all works are adequate familiar with safety equipments and
regulations.
• To conduct the monitoring program as per-issue in the ESMP report.
• To maintain a log-book for the environmental indicators that they are measuring.
• To report any environmental violation during construction works.
• To reply for any comments that DIPCO/Lender may raise.

5.2.2 DIPCO Responsibilities during operation.


The following are DIPCO responsibilities towards the implementation of HS&E plan and
policy.
• To ensure the implementation of HS&E policy.
• To ensure that HS&E consideration in all activities.
• To coordinate with DPA and other corporate in enhancing HS&E policy and
regulation.
• To conduct long-term monitoring program.
• To maintain the monitoring results in log-book and GIS data format
• To participate in the follow-up and closeout of corrective actions that arise from

QF34 Version No. 1


Page 17 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

operational activities, meeting, incident, emergency exercises or auditing that take


place within the project thematic area.
• To maintain and participate in the schedule of meeting, emergency exercises,
inspections and audits that are programmed for the operational phases.
• To take prompt correction actions on the observed non-compliance and sub-standard
industrial practice with regard to HS&E program.
• To make sure that his employees are fully aware with Safety and environmental
regulation.
• To fully coordinate with all authorities on the SH&E issues.
• To conduct continuous training programs at different levels in order to maintain and
increase the level of employees in regards to HS&E Policy, regulation and
implementation.

5.3. Training programs


Damietta Port is fully committed to ensuring that all employees and customers are instructed
in the Healthy and safe work practices, and to maintain an environmentally friendly sound
port. Damietta Port will provide general training on policies and procedures to all employees,
and specific training on equipment, whether manual or motorized, and electrical to the
employees work situation

The training programs will be conducted for all employees at different levels throughout the
project life cycle.
The corporate-level environmental team will be responsible for ensuring that appropriate
programs of training are carried out by the operating subsidiaries so as to fulfill the corporate
philosophy on environmental health, safety and community issues. The target is to institute
basic guidance at the corporate level so each operation provides basic procedures and work
instruction at all level during construction and operational phases to ensure comprehensive
and consistent environmental management.

Training is necessary for all levels, with program adaptation depending on target audience,
managers, workers, contractors, etc. Training programs will include data on all the most
significant HS&E aspects. The programs will also contain information on roles and
responsibilities of each employee in ESMP implementation and functioning. The following
table (Table 5.2)

QF34 Version No. 1


Page 18 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Table 5.2 Training programs for various employee categories.


Medium level
Training Objective Works Experts To managers
Mangers
Training to maintain Compulsory courses Seminars in professional Individual short-term
necessary (learning new subjects. Participation in programs, participation in
competence level profession qualifying conference international seminars,
for new category) conferences
Training for Target courses on Corporate seminars on Special short-term briefings
competence new equipments, new professional subjects, involving international
development to working rules and involvement of internal experts.
comply with the regulations experts and specialists.
changing business Target training programs
requirements
Training to develop Training programs for top
personal efficiency Open Training, specialized training programs for managers.
skills and managerial divisions.
skills
Independent
development of all Distance Training System.
competence aspects

The training program will be continuous and require constant reviewing of the proposed
programs.

All employees will be trained upon hiring in:


1 First Aid basic procedures
2 DIPCO/Corporate Health, Safety & Environmental Policy & Programs
3 Proper procedures in reporting an Incident, Injuries, or Accident
4 Hazard Communications
5 What To Do, in the event of a Hazardous Material Spill & who will response
6 Personal Protective Equipment (PPE) requirements
7 Emergency Procedures
8 General Housekeeping
9 Job Specific Hazards
10 Job Specific Certifications or Licensing requirements.

5.4 Environmental Recording Reporting system.


5.4.1 Environmental Records:
It is important to have log-books that record all environmental monitoring data, training
records, Incident, inspection and audits reports etc. The HS&E managers for DIPCO and
corporate will maintain all records. These records will be available for inspection.

Among the records that will be included, but not limited to, the following:
• Environmental aspects/objectives/targets/programs.
• Environmental meeting/briefings
• Training record

QF34 Version No. 1


Page 19 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

• Environmental permits
• Incident, inspection and audits reports.
• Results of corrective and preventing actions.
• Environmental monitoring reports
• Relate external and internal communications.

All report will be kept safe; A GIS Database system is suggested to keep reports and
recorded in addition to the hard-copy records.

5.4.2 Reporting
In addition to the GIS data base, a hard copy of monitoring programs and other records will
be submitted to DIPCO through the contractors. The typical monitoring report will contain the
followings:
Table 5.3: Suggested Content of Monitoring Report
1. COVER PAGE
• Environmental Monitoring Report
• Permit Number, Application Number and/or Consent Order Number
• Property Owner or Agent
• Report Type (e.g. Baseline, Time Zero, First Annual etc.)
• Date Submitted
• Consultant or Contact Person
• Consultant or Contact Phone Number
2. INTRODUCTION
• Project Objective and Description
• Sampling Dates and Climatic Conditions
• Project Phase (if applicable)
• Current Construction Schedule
• Monitoring Reporting Schedule (including completed and outstanding reports)
3. SAMPLING METHODOLOGY
• Site location and description (site location map)
• Methods of collections
• Methods of analysis
• Monitoring techniques will address the following: timelines, guidelines, success criteria,
monitoring, adaptive management plan, and equipment use and calibration.
4. RESULTS AND DISCUSSION
• The results and discussion section will provide a summary of the overall data, figures, and
comparing results with standard values (EEPP, WB, AfDB, etc).
• Provide an overall summary of site conditions including any onsite events that may have
occurred since last monitoring event.
• Summary could include recommendations for addressing any deficiencies with the permitted
mitigation plan.

QF34 Version No. 1


Page 20 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 6
ENVIRONMENTAL AND SOCIAL MONITORING
The monitoring program will be carefully designed and related to the predictions made in the
SEIA and the key environmental and social indicators that would demonstrate the potential
environmental sustainability of the project.
The program outline will describe the following monitoring details (Abul Azm and Rakha,
2002):

The key information that will be monitored


• The monitoring locations, interval and duration
• Procedures to be undertaken if the monitoring indicates a non-compliance or
abnormality
• Internal reporting procedure and the links to management practices and action plan
• Reporting procedures to relevant authorities (EEAA, DPA, MOT) and if appropriate to
the consent authority and communities.

The following diagram represents the flow of information in the monitoring processes. Each
contractor will have his own HS&E system and team, who will be responsible for the
monitoring program for his section (such as marine or upland).

Fig. 6.1: Flow of Information with this Project


The contractor will then keep results of monitoring program in a form of hard and soft
versions. The hard version will be as log-book, while the soft version will be in a form of data
sheets. Each contractor will report to DIPCO on bi-weekly, monthly, seasonally and annually
bases. DIPCO will be responsible for QA/QC of the data and report any un-usual data.
DIPCO will keep all the mentoring data in a GIS Database information system. In this way,
there will be a uniformity of information system used. DIPCO will them produce reports.

These reports will be submitted to relevant authorities (EEAA, MoT and DPA) as well as to
the AfDB.

GIS database will be available any time and updated regularly.


Monitoring of the project will cover the different phases of the project, including, construction
and operational phases.

QF34 Version No. 1


Page 21 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

6.1. CONSTRUCTION PHASE MONITORING PROGRAMS:


The monitoring program during construction will cover the following areas:
• Coastal and marine Environmental monitoring program
• On-shore works environmental Monitoring Program (New Terminal location)
• Social and community monitoring program.

Each of these programs will be divided into different components which will cover the life
cycle of the project.

6.1.1 Coastal and marine Environmental Monitoring:


The EIA and Dredging Management Plan (DMP) reports identified the required monitoring
program during the construction phase.

The dredging contractor will be required to maintain a daily log book to record the disposal
volume of the dredged material by every load. The dredging contractor is also required to
submit certified allege tables, which relate hopper volume to depth in the hopper, for each
TSHD and disposal barge in operation at the project site. This information can be used to
audit the dredging rates and disposal operations.

The coastal and marine monitoring will include the following:


• Water quality monitoring plan at dredging sites
• Water quality at disposal site
• Marine Ecology at dredged and disposal sites
• Coastal impacts

Appendix VII illustrates the water quality monitoring plan during the dredging activities.
It is important to mention that Turbidity is considered the most important environmental
indicators during dredging activities. Since turbidity is the most important environmental
measures during construction and dredging activities, the following diagram shows the
turbidity contingency flowchart.

QF34 Version No. 1


Page 22 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Fig. 6.2: Turbidity Level Contingency Flow Chart

QF34 Version No. 1


Page 23 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

6.1.2 Onshore works Monitoring Program.


The onshore work monitoring program is included in the “Onshore Works Environmental
Plan” (Appendix V). The main environmental Parameters that will be monitor are:
ƒ Dust (Daily)
ƒ Emissions (SO2, CO, NO2) (monthly)
ƒ Noise (Daily)
ƒ Drinking Water (monthly)

The detailed on the monitoring methodology and frequency are present in Appendix V.

6.1.3 Monitoring Social and community Impacts


According to IFC Performance Standard 1, section 21 regarding Consultation in the Social
and Environmental Assessment and Management Systems (April, 30, 2006) “If affected
communities may be subject to risks or adverse impacts from a project, the client will
undertake a process of consultation in a manner that provides the affected communities with
opportunities to express their view on project risk, impact, and mitigation measures and
allows the client to consider and respond to them.”

The present project had no negative impacts on the surrounding communities. Positive
impacts are expected to the economy and social components due to the construction
activities where there will be an increase in employment activities. However it is proposed
that consultation processes will continue during the project life cycle. The consultation
activities will be at several levels as follows:

Local Community: At the local community level, numerous formal and informal information
sharing sessions about the project, will be held at various venues.

Government Authorities: From the beginning of the proposed project, DIPCO has kept each
level of government authorities (EEAA, DPA and MoT) informed regarding the different
aspects of the project. The communities in district in which the project is located will also
given the responsibility of being involved in the planning and implementation of the project
by using an integrated approach to address local needs and achieve sustainable
development.

6.2 OPERATIONAL PHASE MONITORING PROGRAM


The operational phase monitoring program will be developed for the followings:
a. Operational Phase Environmental Monitoring Plan.
b. Maintenance Dredged Materials Management Plan.

6.2.1 Operational Phase Environmental Monitoring Plan:


The following table summarizes the environmental monitoring program during operation. The
table shows also the responsibilities and location and frequency of sampling.

QF34 Version No. 1


Page 24 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Table 6.1: Sampling Locations, Frequencies and Responsibilities


Environmental Monitoring
Frequency Methods Target Responsibilities
Indicator Locations

2 location “New EEAA


Noise Daily In situ DIPCO/DPA
Terminal” Regulation

Inside
EEAA
Noise Administration Weekly In Situ DIPCO/DPA
Regulation
office

1 location New EEAA


PM10 Weekly In situ DIPCO/DPA
Terminal Regulation

One Location EEAA


VOC Monthly In situ DIPCO/DPA
Terminal Regulation

Water Quality
1 location, new EEAA
(pH, DO, S‰, Monthly In situ DIPCO/DPA
terminal Regulation
COD)

Water Quality
(Nutrient salts, 1 location, new Lab EEAA
TPH Seasonally DIPCO/DPA
terminal analysis Regulation
Chlorophyll,
BOD)

Sediment
Quality (TOC, 1 location, new Lab EEAA
Annually DIPCO/DPA
Heavy metals, terminal analysis Regulation
TPH)

6.2.2 Maintenance Dredged Materials Management Plan (MDMP)


In Case that maintenance is needed and dredged materials need to be disposed, Dredging
Management Plan will be needed. The following points will be taken into account:
• Responsibilities: DIPCO/DPA in corporate with EEAA and MoT and coastal Institute.
• Dumping Location:
o The designated offshore disposal site is the first option.
o Any other Disposal location selected by local authorities (MoT, Maritime
Sector/EEAA).

• Dredging Plan:

QF34 Version No. 1


Page 25 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

o MDMP will be prepared to assure that offshore site has sufficient remaining
capacity for maintain disposal materials.
o MDMP will indicate other disposal options such as, re-use, upland filling, etc.
• Analyses: Chemical analysis and toxicity test will be conducted in order to select the
best practice for disposal activities.
• Long-term Disposal Site Monitoring Plan:
o The long-term Monitoring Plan will be prepared in order to maintain the
selected disposal location and to test the capacity of the offshore disposal
location.
o Monitoring program will include, water physical parameters on seasonally
bases, and sediment quality, on yearly base.

QF34 Version No. 1


Page 26 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 7
7. ESMP SCHEDULE AND COSTS
The following table summarizes the activities during different stages project life
cycle. The estimated cost is based on annual rate with 10% increased annually.

Table 7.1: ESMP Schedule and Costs

Estimated
Implementation
Stage Action Description Responsibility Annual
Schedule
Cost (US$)

Environmental Management

Management Responsibility
• Ensure that the items included
Pre-Construction

in the EAP of the EIA report


will be implemented under the
share responsibility of
DIPCO/Corporate and
DIPCO 100,000 (+
according to the AfDB, WB
Prior to the
and EEAA regulation and Corporate 20% Over
construction
requirements. DPA head)
• Building-up a GIS data base
for the project.
• Reporting the different items in
AP

QF34 Version No. 1


Page 27 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Estimated
Implementation
Stage Action Description Responsibility Annual
Schedule
Cost (US$)

Monitoring Programs

Monitoring Program for Dredging


activities (Appendix VII).
• Undertaking the monitoring Dredging Events MC/Subcontractors
program.
• Being responsible for field 2 weeks after MC/Subcontractors
study and laboratory analysis Dredging Events
including collection of water or as stated in
samples and field Appendix VII
measurements
Construction

• Supervising the contractor Dredging events MC/Subcontractors


80,000 +
during the dredging activities
20% over
• Reporting for any up-normal Based on events MC/Subcontractors head
conditions to DIPCO. /DIPCO
(if any)
• Applying the needed Based on events
mitigation measures MC/Subcontractors

• Building up a GIS-data base /DIPCO


Dredging events
for all analysis and activities
related to monitoring activities MC/Subcontractors
during dredging events. /DIPCO

QF34 Version No. 1


Page 28 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Estimated
Implementation
Stage Action Description Responsibility Annual
Schedule
Cost (US$)

Monitoring Program for Disposal


activities (Appendix VII).
• Undertaking the monitoring Dredging Events MC/Subcontractors
program..
• Being responsible for field 2 weeks after MC/Subcontractors
study and laboratory analysis Dredging Events
including collection of water or as stated in
samples and field table 2.
measurements
Construction

• Supervising the contractor Dredging events MC/Subcontractors 80,000 +


during the Disposal activities 20% over
• Reporting for any up-normal Based on events MC/Subcontractors head
conditions during disposal to (if any) /DIPCO
DIPCO/DPA.
• Applying any needed Based on events
mitigation measures MC/Subcontractors

• Building up a GIS-data base Dredging events


for all analysis and activities MC/Subcontractors
related to monitoring activities /DIPCO
during disposal events.

QF34 Version No. 1


Page 29 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Estimated
Implementation
Stage Action Description Responsibility Annual
Schedule
Cost (US$)

General Monitoring Program


activities (Appendix V).
• Undertaking the monitoring Construction MC/Subcontractors
program. activities /DIPCO
• Being responsible for field Daily, Weekly, bi-
study and laboratory analysis weekly, monthly MC/Subcontractors
including collection of water and seasonally /DIPCO
and sediment samples and during the
field measurements. construction
activities (table
1).
Construction

80,000 +
• Supervising the contractor
Construction MC/Subcontractors 20% over
during construction
events . /DIPCO head
• Reporting for any up-normal
conditions during construction Based on events
to DIPCO. (if any) MC/Subcontractors
/DIPCO
• Applying any needed
mitigation measures Based on events
as stated in
table1. MC/Subcontractors
• Building up a GIS-data base
for all analysis and activities
related to monitoring activities Dredging events MC/Subcontractors
during construction events. /DIPCO

GIS Database and reporting

Building a GIS database during 70,000 +


construction 20% over
head
• Ensure that all data are
presented in accessible format
Construction

• Building any need GIS maps During MC/Subcontractors


showing the different sampling construction DIPCO
events, locations, data and
any other remarks
• Supervising the log-book of
the contractor

Reporting (monthly, seasonally 40,000 +


and one annually 20% over
head

QF34 Version No. 1


Page 30 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Estimated
Implementation
Stage Action Description Responsibility Annual
Schedule
Cost (US$)

Training

Develop and implement training


programs a component of an
Environmental management
System to ensure that all
responsible personnel are
equipped with the necessary
expertise to conduct their
Construction

individual tasks. Programs will


include
During 50,000 +
• Spill Contingency Plan construction DIPCO/Contractor/DPA 20% over
• Hazardous waste handling period head
and storage
• Health, Safety and
Environment
• Sampling and analysis of
water samples
• Operational and maintenance
of pollution control equipments

Supervising contractor and HS&E Auditing

Ensure that the contractor is


Construction

following the EAP as stated in the


EIA report and the HS&E
requirements and regulations. 50,000+
During
DIPCO/Corporate/DPA 20% over
Ensure the implementation of AfDB Construction
head
EEAA, IFC and WB regulations and
requirements.

BTHYMETERIC SURVEY

Bathymetric survey after dredging Seasonally and


Construction

and disposal events after major


4 times/year at two areas (offshore disposal and
and access channel) dredging 160,000+
activities MC/Subcontractors /
20% over
DIPCO/ DPA
head

QF34 Version No. 1


Page 31 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Estimated
Implementation
Stage Action Description Responsibility Annual
Schedule
Cost (US$)

Monitoring Programs

General Monitoring Program


activities (Appendix V).
• Undertaking the monitoring
50,000+
program.
20% over
• Being responsible for field head
study and laboratory analysis
including collection of water
and sediment samples and
field measurements 20,000+
• Reporting for any up-normal OC/Subcontractor / 20% over
As stated head
conditions during operation to DIPCO / DPA
DIPCO.
• Applying any needed
mitigation measures
20,000+
• Building up a GIS-data base 20% over
for all analysis and activities head
Construction

related to monitoring activities


during construction events.
• Reporting (4 Seasonal and 1
annual)

Supervising HS&E and Auditing


• Undertake and supervising
the environmental, health
and safety audit of all
terminal sites and activities.
• Implement actions arising
from the above mentioned
points including monitoring 50,000 +
results and HS&E plan. During operation OC / DIPCO / DPA 20% over
head
• Implement an emergency
Response plan and ensure it
is compatible with the on-
going and existing plans
(DPA)
• Implement and supervising
the plan for fuel storage and
handling, Hazardous

QF34 Version No. 1


Page 32 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

Estimated
Implementation
Stage Action Description Responsibility Annual
Schedule
Cost (US$)
materials and ship sewage
disposal and any other plan

Total estimated cost/year 850,000


Total estimated cost/year (+ 20% overhead) 1,022,000

MC = Marine Contractor
OC = Onshore Contractor

QF34 Version No. 1


Page 33 of 34
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Final Report
DAMIETTA PORT ENVIRONMENTAL
December 14th, 2008
MONITORING – DREDGING

SECTION 8
8. CITATION
• Abul Azm, A.G. and Rakha, K.A. EIA Guidelines for Development of Ports,
Habrours and Marinas in Egypt. Littoral 2002, The Changing Coast,
EUROCOAST/EUCC Portogal, 255-262
• The International Tanker Owner Pollution Federation Limited (2005). The Country
Profile, Egypt.
• Lochner, P. (2005). Guidelines for Environmental Management Plans, CSIR Report
No ENV-S-C, 2005-53 H. Republic of South Africa, Provincial Government of West
Cape, Department of Environmental Affairs & Development Planning, Cape Town.

QF34 Version No. 1


Page 34 of 34
Issue Date:12/04/07 Version date: 12/04/2007
 
 

APPENDIX I
FIRE FIGHTING AND CIVIL
DEFENSE PROGRAM (DPA)
 
 

APPENDIX II
KGL ENVIRONMENTAL, HEALTH,
SAFETY & SECURITY POLICY
MANUAL
 
 

APPENDIX III
OFFSHORE WORKS PROJECT
HEALTH AND SAFETY PLAN
 
 

APPENDIX IV
ONSHORE WORKS PROJECT
HEALTH AND SAFETY PLAN
 
 

APPENDIX V
ENVIRONMENTAL PLAN
 
 

APPENDIX VI
ENVIRONMENT IMPACTS DURING
CONSTRUCTION AND
OPERATION
Appendix VI
Environment Impacts during Construction and Operation
Issue Environmental Measures Impacts Mitigation Measure
Construction Operation Construction Operation
Land- and water- uses in the proposed area as well as in the No impact is expected due to the Increased activities The area of the Best Practice,
nearby affected areas, was investigated by using recent high homogeneity of the new will need more project is un- complain with existing
resolution images, in addition to ground survey. Image development within the proposed infra-structure such used area within facilities.
interpretation and application of remote sensing mapping area. as waste disposal, the existing The existing waste
methods determined that the landscape of the New Damietta sewage, traffic, fence of the port. disposal facilities
Land Use

port area is dominated by man-made cover types and electric power, etc. (incineration) and the
infrastructures, rather than natural land covers. Some impact could be occurred
due to increased traffic activities. No need for proposed facilities will
Also some relocation to the road These facilities, will mitigation accommodate the
It is important to mention that all the activities related to the may be required. cause impacts on measure. increase in solid
port extension would be confined within the existing port area. the existing waste.
infrastructures Some additional need
for liquid waste is
needed.

The main points that were undertaking during the Social and According to the Environmental Baseline Study No need for mitigation measure.
demographical task are: Demographic Characteristics, Social conducted, the extension of the Damietta Port project
Demography and
Socioeconomics

Characteristics, and Economic activities of the local residential will occur within the current borders and premises of the
people. The factors that were studied in this task included: port, and will thereby have no negative impact towards
Four local communities were identified: the surrounding communities.

ƒ Bedouin (non-resident)
ƒ Sale-people for seasonal agricultural products
ƒ Khamsa Village (Eizbet Khamsa)
ƒ Nasr Village (Eizbet Nasr)

Based on the field observations and the texture constitutes, the There is no impact due to the seismic risk or geology of No need for mitigation measure.
Geology and
seismic risk
assessment

study area surface geology can be divided into: River sand, the project area.
coastal sand, accretion ridge sand, beach dune and nearshore
sand.
The area of study is just on the border of two seismic source
zones. These sources are: Al-Fayoum Northeastern Egypt
sources zone and south-eastern Mediterranean source zone.
Issue Environmental Measures Impacts Mitigation Measure
Construction Operation Construction Operation
Groundwater samples were collected from two drilled No impacts on the groundwater Groundwater Groundwater Regular monitoring
boreholes around the investigated area. Eight (8) subsurface in the nearby locations. modeling indicated should be studied program should be
soil samples, about 0.5m from the ground surface were also that no risk from and monitored in performed.
collected covering the total area of study. the project of the order that no affect
Regarding soil and the slightly ground water of the water table
Groundwater and Soil Characterization

Modeling on the effect of new terminal on ground water quality high level of TPH, this is due to
and water table were conducted in an area covering the nearby quality. increase as well as
the surface contaminated soil by on the water quality
delta area. man-activities in the project area especially salinity.
and probably from some The quality of
The results of the physical and chemical analysis of machines of oil from machines in ground water will
groundwater and soil samples showed the groundwater is of this area. It is expected that no not be significantly
low oxygen concentration less than 4 mg/l; high concentration impact or slightly –ve impact affected by the
in ammonia 0.24 mg/l; very high concentration of Nitrate (NO3); could occurred due to this dredging processes
High concentration of phosphate; and high water salinity. contaminated soil since salt water
intrusions already
Persistent organic pollutants (POPs) were also revealed in occurs due to the
groundwater and soil samples. Concentration of total shallow ground
pesticides ranged from 20 to 22 ng/L. water table, there
are no downstream
users of
The average concentrations of total petroleum hydrocarbons
groundwater and
recorded in soil samples were above the admissible
groundwater is not
environmental levels.
used for drinking or
The soils can be classified as sand, ranging from very fine to agricultural uses.
medium sand, most of samples are well to moderately sorted,
which indicates that oil sediments are composed from one or
two size classes and sources. No Impact on soil.
Issue Environmental Measures Impacts Mitigation Measure
Construction Operation Construction Operation
The marine hydrographical parameters that were measured in Coastal and marine environment No direct impacts • Best practice
this study indicated healthy conditions except for a suspected are the most affected area by the on marine activities dredging • No Mitigation
eutrophication problem at the southern part of the Port. new project. The effect is mainly are expected. operations (e.g. measures is
Depleted bio-available nutrients (nitrite, nitrate and dissolved due to: optimising cutter needed
inorganic phosphate) were recognized during discussion of the • Dredging in the offshore area head speed and
obtained results. Total nitrogen and phosphorous were It is expected that ensuring pumping • Monitoring
(Channel and port entrance) the conduction of program
abundant during the sampling time. capacity meets
• Dumping of dredged marine production; should be
materials in the selected site. environment will continue
Water contamination with metals indicated low concentration of return to its natural • Monitoring of according to
• Direct effect from increasing resulting silt
iron and manganese, suggesting their incorporation in the condition. the proposed
turbidity and TSS into the plumes to ensure
rapid growth of phytoplankton. The harbour is contaminated by program.
water column, which will have acceptable level
both copper and cadmium, while very high concentrations were
some direct and cumulative (<50 mg/l
detected for zinc and lead. On the other hand, high oil pollution
Coastal Marine Environment

effect on the marine ecology according to


in the harbor was noticed compared to marine environment.
and water Quality. WB/EEAA) of TSS
• Disposal of the upper 20 cm is attained (refer
The bed sediments indicated an elevated load of organic of sediments into offshore to mitigation
matter, trace metals and oil pollution. The grain size results dumping location, Upland section, for
showed poor sorting, fine sediments inside the Port. dumping will be the best details)
practice. • Appropriate use of
The study indicated that the upper 20 Cm are probably • No impact was predicted on silt trap, water
contaminated with heavy metals the marine ecology. Study box, weir
indicates that dredging arrangement or
activities may increase similar for storm
The coastal marine environment is rich in its biodiversity. productivity as the sediments drainage system.
Phytoplankton, zooplankton and marine benthic animals have that will re-suspension into • The site is not
been identified. the water column are mostly deemed to contain
Detailed information about the quality of other components of alluvial deposits from the Nile sensitive
the eco-system (sediments, phytoplankton and fish) is River. This sediment organisms.
contained in the full baseline study. contained large amount of
nutrient salts. • Minimizing losses
through best
• Temporary loss of modified management
habitat, flora and fauna practices.
• Monitoring
programs should
be followed.
Issue Environmental Measures Impacts Mitigation Measure
Construction Operation Construction Operation
The coastal dynamic studies included shoreline stability, • This area is highly dynamic No impact is Careful monitoring for the changing coastal
dominant hydrodynamic forces and coastal issues. Damietta area where coastal expected due to should be done.
Harbor is located on the northeastern coast of the Nile delta, geomorphologic changes the new terminal on
Egypt. Adjacent geomorphologic areas include Damietta occurred during the last 50%. coastal dynamics.
promontory, beach, backshore sand-flat, backshore This change is mostly due to
depression, distributor channel, and cultivated and arable land. the reduction of River
The spatial distribution of mean grain size shows a general sediments as a consequence
decrease of grain-size seaward as well as in the long shore of building Aswan Dam
direction toward the vicinity of the harbor. (1967).
Coastal Dynamics

• The study of geomorphologic


change could be done using
satellite image at different
Net sediment transport is to the east. The coastline is typical of time interval (Before
microtidal semi-diurnal nature with tidal range of 75 cm. construction, during
construction) and hence
Based on analyses of beach profiles and satellite images measure change detection.
acquired between 1984 and 2000 maximum accretion (14.7
m/yr) occurred along the western coast due to the construction
of the western breakwater, whereas, greatest erosion (-14.5
m/yr) dominated along the down-drift beach of the eastern
breakwater. The erosion/accretion pattern is resulted from the
NW wave-induced longshore current to the east. Beaches on
both sides of the harbour are relatively still unused except the
two recreation beaches at the New Damietta City about 6.7 km
west of the harbour and the artificially-protected resort at Ras El
Bar, 6.0 km east.

An ecological survey based on the available data, site The project area, contain no importance terrestrial fauna No need for mitigation measure.
Terrestrial

reconnaissance and field trips along the study area is carried and flora. No impact could be found.
Ecology

out. The wildlife study included terrestrial fauna and flora. The
investigation indicated that the new proposed port area is
considered moderate or less important areas as it contains few
fauna and flora that are found elsewhere in Egypt and are
affected with the landscape due to rapid urbanization.
Issue Environmental Measures Impacts Mitigation Measure
Construction Operation Construction Operation
The air quality mobile laboratory was used for field The increased dust may affect Impact may Use of
measurements in the vicinity of the proposed study site. the surrounding communities. occurred from appropriate
Measured data were analysis to obtain a baseline increased noise methods and
concentration level for major pollutants in the area. The and ship and traffic equipments to The best management
measured values for both SO2 and NO2 were well below the Noise also can be increased due increase. minimize the practice for minimizing
standard values provided by EEAA-Egypt at both sites. to construction work. These expected noise level should be
effects are of temporarily nature. emission. used. Monitoring
Noise pollution is expected to be Pollution such as equipments should be
The levels of both total suspended particulate (TSP) and localized and not affected the toxic organics installed to indicate
Ambient Air and Noise Pollution

particulate matter less than 10 micron (PM10) were higher than nearby communities. and metals that noise levels are
air quality limits (AQL) as recommended by Egyptian should not within the acceptable
Environmental law 4/94 in some sites which exposed to air exceed risk- limits. The site is
pollution sources. specific levels or within the operating
reference air port, Pile driving is not
concentration at anticipated
The major inorganic gases SO2, Nox, CO and others measured
the receptor end Best Practice should
gases had average levels, however, below permissible limits.
as indicated by be followed up.
the World
Noise levels exceeded the permissible levels in several sites Bank/IFC. The
along the terminals. These stations are mainly affected with annual arithmetic
traffic noise and noise from the diesel-fired Gantry Cranes. mean for
Noise levels in the areas surrounding the Port showed particulate
acceptable levels. This is considered to be normal for port matter should
operations. not exceed 50
3
μg/m
In general, the ambient noise background in Port area should
be around 50 dB. One km away from the Port, the noise
contribution was around 50 dB; and at two-km distances, the
contribution was about 42 dB. Therefore, it is reasonable to
believe that after the completion of the new Damietta
extension, the noise level will be at most about 80 dB at a one-
kilometer distance; and at a two-kilometer distance
 
 

APPENDIX VII
WATER QUALITY MONITORING
PROGRAM FOR DREDGING
ACTIVITIES
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

APPENDIX VII
WATER QUALITY MONITORING PROGRAM FOR DREDGING ACTIVITIES

1.1 Turbidity/Total Suspended Solids (TSS) Thresholds


Law No. 4 for 1994, states that TSS from discharges to the marine environment
should not exceed 60 mg/l. However, it is not clear whether this standard applies
to short-term turbidity associated with dredging or dredged material disposal.
World Bank guidance requires limiting discharges to 50 mg/l for process
wastewater, domestic sewage and stormwater. There is no guidance specifically
for dredging and dredged material disposal. It should be noted that the EIA
stated that there are no specific sensitive environmental areas in the vicinity of
the dredging and offshore disposal sites.

1.2 Marine Ecology


The distribution of sampling sites has been arranged with some considerations to
fit the expected changes. The monitoring study will be concentrated on
measuring biological parameters (phytoplankton, zooplankton and bottom fauna).
Marine communities in the water column and in the marine sediments will be
studied. Phytoplankton and zooplankton communities will be examined in the
water column. Macrofaunal and meiofaunal communities in the marine sediments
will be documented.

Marine plankton nets will be used to collect the water column plankton
communities. Each net will be towed at the dredged and the disposal sites at the
minimum speed of the vessel. Van Veen Grab sampler will be used for collecting
marine benthic communities. Samples will be preserved in formalin after adding
Rose Bengal for staining the living materials. Samples will be placed in an ice
box for later examination.

QF34 Version No. 1


Page 1 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

1.3 Quality Assurance responsibilities


Project Quality Assurance (QA) Officer will have overall responsibility for quality
assurance oversight. The Project QA Officer communicates directly to the
Dredged Material Suitability Task Manager. Specific responsibilities include:
• Ensuring the QAPP is communicated to the project personnel,
• Reviewing and approving QA procedures, including any modifications to
existing approved procedures,
• Ensuring that QA audits of the various phases of the project are
conducted as required,
• Providing QA technical assistance to project staff,
• Ensuring that data validation/data assessment is conducted in
accordance with the QAPP, and
• Reporting on the adequacy, status, and effectiveness of the QA program
to the Dredged Material Suitability Task Manager.

The water quality monitoring plan will continue during the project life cycle.
The different stages of water quality monitoring plan are shown in
following tables.

1.4 Water Quality Instrumentation


The most efficient method to make the necessary measurements is to use a
multi-parameter water quality sonde to measure temperature, conductivity,
dissolved oxygen, turbidity, and depth within the water column. The instrument
should provide both internal recording of data as well as direct readout.

A detailed data sheet as produced by the manufacturer should be included in the


monitoring plan submitted by the contractor.
For the monitoring surveys, the instrument will be used in surface readout mode,

QF34 Version No. 1


Page 2 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

attached to a V-fin or other downwater system, for deployment. The sonde will be
lowered over the full water column depth to generate vertical profiles and/or
towed obliquely to further characterize water column conditions. The data stream
will also be time/position tagged for later presentation.

1.5 Sample Collection and Handling


Water samples will be collected using a pump and tubing system. The intake for
the pump system will be connected to the instrument sonde, allowing for direct
measurement of water quality parameters at the time of sampling.
A diaphragm pump will be used in conjunction with fluoropolymer tubing (only if
chemical samples are needed). Following purging of the tubing, the pumped
water will be dispensed directly into the appropriate sample containers.
At the end of each monitoring event, analytical testing samples will be transferred
from the field team to the testing laboratories. A sampling and analysis plan will
be provided.

1.6 Reporting
Monitoring data will be incorporated into a survey report for each individual or
combined monitoring event and will include the following elements:
• Introduction noting background on the event and relevant thresholds
• Survey log noting timing of events and relevant information
• Overview figure showing the locations of monitoring and sampling
• Profile(s) of ADCP backscatter measurements supporting plume definition
and sampling locations
• Profile(s) of water quality measurements characterizing the water column
• Tables of laboratory results
• Brief discussion of results (with a contingency plan if a project specific
criterion has been exceeded)

QF34 Version No. 1


Page 3 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

The completed monitoring reports will be submitted to the project engineer within
a 10-day time period. However, should conditions (such as multiple surveys)
delay the completion of the report; the laboratory data will be transmitted alone
within the specified period.

1.7 Monitoring Events


It is estimated that a total of 31 monitoring events will be needed for this project
as detailed below and including the following:
• Six events at dredging sites
• 25 events at the disposal area (assuming dredging duration of 19 months)
• A contingency for additional monitoring is required based on changes in
dredged material, monitoring results showing significant observed
changes.
Prior to each event, background or ambient TSS and currents will be measured.
Background or ambient measurements shall be taken as close as possible to
specify monitoring locations but not within observed plumes from previous
dredging or disposal events. Each monitoring event will include ADCP plume
tracking to locate maximum TSS/Turbidity levels, and recording current direction,
tide level, water sampling, weather and sea conditions.

QF34 Version No. 1


Page 4 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

PHASE ONE
Project phase: BEFORE DREDGING
Locations: TURNING CIRCLE –POR`T BASIN- ACCESS CHANNEL
Responsibility: Dredging Contractor, DK, DIPCO, DPA.

Table 1: Monitoring Events before starting Dredging


Parameter(s) Location Frequenc # of Survey Methods of Samplin
y Sample Method Analysis g Depth
s
TOTAL TC BS 4 points Visual test Visual Testing/In (-1m)
SUSPENDED PB (must not situ
Solid (TSS) AC exceed Measurements
WATER PARAMETERS

DA 50mg/l)
Physical TC BS 4 points Multisensory In Situ (-1m)
Water PB Probe Measurements
Parameters AC Sampling
(Temp, DA
Salinity, pH,
Transparency,
Turbidity)
BOD TC BS 4 points Water Laboratory (-1m)
NS PB Sampler analysis
TM AC
TPH DA
Phytoplankton TC BS 4 points Plankton Microscopic
ECOLOGICAL

Zooplankton PB nets Identification Sub-


AC surface
SURVEY

DA
Meiofauna TC BS 4 points Van Veen Microscopic
Macrofauna PB Sampler Identification Bottom
AC
DA
TM TC BS 4 points Van Veen Laboratory bottom
SEDIMENT
QUALITY

TPH PB Sampler Analysis


AC
DA

TC=Turning circle; PB= Port Basin; BOS=Biological Oxygen Demand;


NS=Nutrient salts; TM= Trace Metals; TPH=Total Petroleum Hydrocarbons;
TL=Task Leader; NB=New Basin; RP=Reference Point; BS=Before Starting; BL
= Background level; DA=Dumping Area; LA= Lab Analysis)

QF34 Version No. 1


Page 5 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

PHASE TWO
Project Phase: Dredging activities (after two hours of dredging)
Location: TURNING CIRCLE -PORT BASIN- ACCESS CHANNEL
Responsibility: Dredging Contractor, DK, DIPCO, DPA

Table 2: Monitoring Events during Dredging


Number
Samplin
of Survey Methods of
Parameter(s) Location Frequency g Depth
Sample Method Analysis
s
TOTAL TC Daily Field Visual test Visual Testing/In (-1m)
SUSPENDED PB survey (must not situ
Solid (TSS) exceed Measurements
50mg/l)
Temp, TC Biweekly 2 points Multisensor In Situ (-1m)
Salinity, pH, PB Probe Measurements
WATER PARAMETERS

Transparency, Sampling
Turbidity
BOD TC Biweekly 2 points Water Laboratory (-1m)
NS PB Sampler analysis
TM
TPH
Temp, TC Seasonall 2 points Multisensor In Situ (-1m)
Salinity, pH, PB y Probe Measurements
Transparency, Sampling
Turbidity
BOD NB Seasonall 2 points Water Laboratory (-1m)
NS RP y Sampler analysis
TM
TPH
Phytoplankto TC Monthly 3 points Plankton Microscopic
ECOLOGICAL

n PB nets Identification Subsurfa


Zooplankton ce
SURVEY

Meiofauna Yearly 2 points Van Veen Microscopic


Macrofauna NB Sampler Identification Bottom
RP

TM TC Monthly 3 points Van Veen Laboratory bottom


TPH PB Sampler Analysis
SEDIMENT
QUALITY

AC
TM Yearly 2 points Van Veen Laboratory bottom
TPH NB Sampler Analysis
RP

QF34 Version No. 1


Page 6 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

(TC=Turning circle; PB= Port Basin; BOS=Biological Oxygen Demand;


NS=Nutrient salts; TM= Trace Metals; TPH=Total Petroleum Hydrocarbons;
TL=Task Leader; NB=New Basin; RP=Reference Point; D= Daily; B= Biweekly;
M= Monthly; Y= Yearly).
Two sampling times (Morning and Afternoon) after at least three hours of
continuous dredging, track plume development and collect sample at a
distance of 200 meters from the dredge - locate maximum TSS and record
level.

Note: Repeat the above monitoring when one or more of the following events
occurs:
• The dredging method is changed within the dredging area that has been
monitored
• A contingency measure is implemented to reduce turbidity
• The percentage of clay in the dredged material increases by 75%

QF34 Version No. 1


Page 7 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

PHASE THREE
PROJECT PHASE: DUMPING ACTIVITIES.
Locations: Dumping area (as stated and approved in the DMP report)
Responsibility: Contractor, DK, DIPCO, DPA.

Table 6.3: Monitoring for Dumping Events


Number Sampling
Parameter(s) Location Frequency of Survey Method Methods of Analysis Depth
Samples
TOTAL DA 3 hrs after Field Visual test Visual Testing/In (-1m)
SUSPENDED survey (must not situ Measurements
Solid (TSS) exceed 50mg/l)
Temp, Salinity, DA Biweekly 2 points Multisensor In Situ (-1m)
pH, Probe Measurements
WATER PARAMETERS

Transparency, Sampling
Turbidity)
BOD DA Biweekly 2 points Water Sampler Laboratory analysis (-1m)
NS
TM
TPH
Temp, Salinity, DA Seasonally 2 points Multisensor In Situ (-1m)
pH, Probe Measurements
Transparency, Sampling
Turbidity)
BOD DA Seasonally 2 points Water Sampler Laboratory analysis (-1m)
NS
TM
TPH
Phytoplankton DA Monthly 2 points Plankton nets Microscopic
ECOLOGICAL

Zooplankton Identification Sub-


SURVEY

surface

Meiofauna Yearly 2 points Van Veen Microscopic


Macrofauna DA Sampler Identification Bottom

TM DA Monthly 2 points Van Veen Laboratory Analysis bottom


TPH Sampler
SEDIMENT
QUALITY

TM Yearly 2 points Van Veen Laboratory Analysis bottom


TPH DA Sampler

(TC=Turning circle; PB= Port Basin; BOS=Biological Oxygen Demand; NS=Nutrient salts;
TM= Trace Metals; TPH=Total Petroleum Hydrocarbons; TL=Task Leader; NB=New
Basin; RP=Reference Point; D= Daily; B= Biweekly; M= Monthly; Y= Yearly).

QF34 Version No. 1


Page 8 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

IMPORTANT NOTES:
A) AFTER DISPOSAL – (HIGH OR LOW TIDE)
o Track plume development
o Collect samples following disposal for a three hour period or until
a suspended solids plume is no longer detected within the water
column (whichever is sooner)
o Locate maximum TSS and record level.
B) 24 HOURS AFTER FIRST DISPOSAL EVENT
o Locate and measure max.
o TSS value occurring at perimeter of disposal area.
o If exceeds water quality criteria, locate max. Point beyond
perimeter.
o Record value and location.
C) FIRST WEEK AFTER FIRST DISPOSAL EVENT
o Locate and measure max. TSS value occurring at perimeter.
o If exceeds water quality criteria, locate max. point beyond
perimeter.
o Record value and location.
D) EACH MONTH – PERFORM PERIMETER MONITORING
o Locate and measure max. TSS value occurring at perimeter.
o If exceeds water quality criteria, locate max. TSS point beyond
perimeter.
o Record value, and location
E) ONCE PER WEEK1
o Locate and measure max. TSS value occurring at perimeter.
o If exceeds water quality criteria locate max. point beyond
perimeter.
o Record value, and location

QF34 Version No. 1


Page 9 of 10
Issue Date:12/04/07 Version date: 12/04/2007
Quality / Environmental
Management

Appendix VII

st DAMIETTA PORT ENVIRONMENTAL


December 1 , 2008
MONITORING – DREDGING

Note:
Repeat monitoring events 1 through 5 when one or more of the following occurs:
• The average volume per load or frequency of disposal increases by greater
that 25% for more than three days
• A contingency measure is implemented to reduce turbidity
• Repeat monitoring event 5 if the percentage of clay in the dredged material
increases by 75%) or greater or if there are visual signs that the plume is
increasing in extent or duration.
If, monitoring events 4, 5, or 6 show that TSS values greater than water quality
criterion have reached beyond the perimeter of the disposal area, then perform
monitoring event 7 until criteria is met.

QF34 Version No. 1


Page 10 of 10
Issue Date:12/04/07 Version date: 12/04/2007

You might also like