LINEAR PROGRAMMING - SIMPLEX METHOD - MAXIMIZATION CASE: 2 VARIABLES

TRY THIS!
Case:

Solve:
Max.: P= 30x1 + 70x2
S.t.: x1 + 2x2 ≤ 20
x1 +5x2 ≤ 35
x1 and x2 ≥ 0

Solve:
Max.: P= 30x1 + 70x2 + 0S1 + 0S2
S.t.: x1 + 2x2 +S1 = 20
x1 +5x2 + S2 = 35
x1, x2, S1, S2 = 0

Table 0 (Initial simplex Table)

Cj 30 70 0 0
Cbi BV X1 X2 S1 S2 SOLUTION RATIO
0 S1 1 2 1 0 20
0 S2 1 5 0 1 35
Zj 0 0 0 0 0
Cj-Zj 30 70 0 0

Formula to find the values for Zj: should be zero or negative number

Zj = ∑ row1(CBi) (aij) + row2(CBi) (aij)

(1) Zj = 0 1 + 0 1 =
(2) Zj = 0 2 + 0 5 =
(3) Zj = 0 1 + 0 0 =
(4) Zj = 0 0 + 0 1 =
(5) Zj = 0 20 + 0 35 =
TABLE 0 (Initial Simplex Table)

Cj 12 16
CBi BV x1 x2
0 SI 1 2
0 S2 1 5
Zj 0 0
Cj - Zj 12 16

OV KCV KRV KE
1 2 1 5
2 2 5 5
1 2 0 5
0 2 1 5
20 2 35 5
Cj 30 70 0 0
Cbi BV X1 X2 S1 S2
0 S1 1 2 1 0
0 S2 1 5 0 1
Zj 0 0 0 0
Cj-Zj 30 70 0 0

TABLE 1 (Iteration 1)

Cbi Cj 30 70 0 0
0 BV X1 X2 S1 S2
0 70 x2 1/5 1 0 1/5
0 0 S2 3/5 4 1/5 3/5 1
0 Zj 14 70 - 14
0 Cj-Zj 16 0 0 0

To find the NEW values for x2, divide by the key element all other values
(1) 1 / 5 = 1/5
(2) 5 / 5 = 1
(3) 0 / 5 = 0
(4) 1 / 5 = 1/5
(5) 35 / 5 = 7

To find the NEW values for S2, the formula is:

Corr. key column value * Corr. key row value


New Value = Old Value - -----------------------------------------------------------------------
Key element
Corr. key column value * Corr. key row value
New Value = Old Value - -----------------------------------------------------------------------
Key element

(1) 1 - (2x 1) / 5 = 1- 2/5 =


(2) 5 - (2 x 2) / 5 = 5- 4/5 =
(3) 0 - (2 x 1)/ 5 = 0- 2/5 =
(4) 1 - (2 x 0) /5 = 1- 0 =
(5) 35 - (2 x 20) /5 = 35 - 8 =

To find Zj, (CBi * x1) in row 1 + (CBi * x2)in row 2

(1) 70 1/5 + 0 3/5


(2) 70 1 + 0 4 1/5
(3) 70 0 + 0 3/5
(4) 70 1/5 + 0 1

0 0
S1 S2 Solution Ratio Ratio
1 0 20 (20/2) 10
0 1 35 (35/5) 7
0 0 0
0 0

OV NV
1 0.4 0.6
2 2 0
1 0.0 1
0 0.4 0
20 14 6
SOLUTION RATIO
20 (20/2) 10
35 (35/5) 7
0

TABLE 1 (Iteration 1)

Cj 30
SOLUTION RATIO Cbi BV X1
7 70 x2 1/5
27 0 S2 0.6
Zj 14
Cj-Zj 16

nt all other values TABLE 1 (Iteration 1)


Cbi Cj 30
BV X1
70 x2 1/2
0 S2 -1.5
Zj 35
Cj-Zj -5

row value
--------------------------------------
row value
--------------------------------------

3/5 (1) 1 - (2x 1) / 5 = 1- 2/5 = 3/5


4 1/5 (2) 5 - (2 x 5) / 5 = 5- 2 = 3
3/5 (3) 0 - (2 x 0)/ 5 = 0- 0 = 1
1 (4) 1 - (2 x 1) /5 = 1- 2/5 = 3/5
27 (5) 35 - (2 x 35) /5 = 35 - 14 = 21

= 14 0 = 14
= 70 0 = 70
= 0 0 = -
= 14 0 = 14
70 0 0 0 0 Cj 30
X2 S1 S2 SOLUTION RATIO Cbi BV X1
1 0 0.2 7 20 70 x2
4.2 0.6 1 27 45.00 0 x12 1
70 0 14 0 0 Zj
0 0 0 0 0 Cj-Zj -5

Find the value of x1:


70 0 0
X2 S1 S2 SOLUTION RATIO (1) 0.6 /
1 1/2 0 10 (2) 4.2 /
-45 -2.5 1 -265 (3) 0.6 /
70 35 0 0 (4) 1 /
0 -35 0 0 (5) 27 /

Find the value of x2:


OV KCV
(1) 1/2 1/2
(2) 1 1/2
(3) 1/2 1/2
(4) 0 1/2
(5) 10 1/2

Find the value of Zj:

(1) 0 0
(2) 0 0
(3) 0 Dec 30
(4) 0 0
(5) 0 0
70 0 0 0 0
X2 S1 S2 SOLUTION RATIO
20
7 1 1.67 45.00 176.67
0
0 0 0 0 0

0.6 = 1 57
0.6 = 7 58
0.6 = 1 59
0.6 = 1.67 60
0.6 = 45.00 61
KRV KE OV NV
-1 1/2 -1.5 1/2 1/2 -44562.5 63
-45 -1.5 1 0 1 64
-2 1/2 -1.5 1/2 -4/40 1 / 10 65
1 -1.5 0 1/8 -1 / 8 66
-265 -1.5 10 4/1 2 67

+ 0 - = 0 0 = - 69
+ 0 0 = 16 0 = 16 70
+ 0 - = 8/5 -6/5 = 2/5 71
+ 0 - = -2 3 = 1 72
+ 0 - = 32 - = 32 73
LINEAR PROGRAMMING - SIMPLEX METHOD - MAXIMIZATION CASE: 2 VARIABLES
TRY THIS!
Case:
Solve:
Max.: P= 30x1 + 70x2
S.t.: x1 + 2x2 ≤ 20
x1 +5x2 ≤ 35
x1 and x2 ≥ 0

Solve:
Max.: P= 30x1 + 70x2 + 0S1 + 0S2
S.t.: x1 + 2x2 +S1 = 20
x1 +5x2 + S2 = 35
x1, x2, S1, S2 = 0

STEP 1
Table 0 (Initial simplex Table)

Cj 30 70 0 0
Cbi BV X1 X2 S1 S2 SOLUTION RATIO
0 S1 1 2 1 0 20
0 S2 1 5 0 1 35
Zj 0 0 0 0 0
Cj-Zj 30 70 0 0

Formula to find the values for Zj: should be zero or negative number

Zj = ∑ row1(CBi) (aij) + row2(CBi) (aij)

(1) Zj = 0 1 + 0 1 = 0
(2) Zj = 0 2 + 0 5 = 0
(3) Zj = 0 1 + 0 0 = 0
(4) Zj = 0 0 + 0 1 = 0
(5) Zj = 0 20 + 0 35 = 0

TABLE 0 (Initial Simplex Table)

Cj 30 70 0 0
CBi BV x1 x2 S1 S2 Solution Ratio Ratio
0 SI 1 2 1 0 20 (20 / 2)
0 S2 1 5 0 1 35 (35/ 5)
Zj 0 0 0 0 0
Cj - Zj 30 70 0 0

OV KCV KRV KE OV NV
1 2 1 5 1 0.4 0.6
2 2 5 5 2 2 0
1 2 0 5 1 0.0 1.0
0 2 1 5 0 0.4 -0.4
20 2 35 5 20 14 6
x2 is the ENTERING VARIABLE

Cj 30 70 0 0
CBi BV x1 x2 S1 S2 Solution Ratio
0 SI 1 2 1 0 20
0 S2 1 5 0 1 35
Zj 0 0 0 0 0
Cj - Zj 30 70 0 0

KEY Column 70
KEY Row 7
KEY Value 5

TABLE 1 (Iteration 1)

Cj 30 70 0 0
CBi BV x1 x2 S1 S2 Solution Ratio
70 X2 1/5 1 0 1/5 7
0 S2 3/5 0 1 - 2/5 6
Zj 14 70 - 14
Cj - Zj 16 0 0 -14

To find the NEW values for x2, divide by the key element all other values
Ratio (1) 1 / 5 = 1/5
10 (2) 5 / 5 = 1
7 (3) 0 / 5 = 0
(4) 1 / 5 = 1/5
(5) 35 / 5 = 7

To find the NEW values for S2, the formula is:

Corr. key column value * Corr. key row value


New Value = Old Value - -----------------------------------------------------------------------
Key element

(1) 1 - (2 x 1) / 5 = 1 0.4 = 3/5


(2) 2 - (2x 5) / 5 = 2 2 = 0
(3) 1 - (2 x 0)/ 5 = 1 0 = 1 8/20
(4) 0 - (2 x 1) /5 = 0 0.4 = - 2/5
(5) 20 - (2 x 35) /5 = 20 14 = 6

To find Zj, (CBi * x1) in row 1 + (CBi * x2)in row 2

(1) 70 1/5 + 0 3/5 = 14


(2) 70 1 + 0 0 = 70
(3) 70 0 + 0 1 = 0
(4) 70 1/5 + 0 - 2/5 = 14
x1 is ENTERING VARIABLE

Cj 30 70 0
Ratio CBi BV x1 x2 S1
(20 / 2) 10 70 X2 1/5 1 0
(35/ 5) 7 0 S2 3/5 0 1
Zj 14 70 -
Cj - Zj 16 0 0

KEY Column 16
KEY Row 10
KEY Value 3/5

Cj 30 70 1
CBi BV x1 x2 S1
70 X2 1/5 1 0
70 S2 3/5 0 1
Zj 14 70 -
Cj - Zj 16 - 1
---------

4/10 2/5

0 = 14
0 = 70
0 = -
-0 = 14
0 Cj 30 70
S2 Solution Ratio CBi BV x1 x2
1/5 7 35 70 X2 0 1
- 2/5 6 10 30 x1 1 0
14 Zj 30 70
-14 Cj - Zj - -

Find the value of x1:

(1) 0.60 / 3/5


(2) 0 / 3/5
(3) 1 / 3/5
- 2/5 (4) - 2/5 / 3/5
S2 Solution Ratio (5) 6 / 3/5
1/5 7 35
- 2/5 6 10 Find the value of x2:
14 OV KCV KRV
(14.40) (1) 1/5 1/5 3/5
(2) 1 1/5 0
(3) 0 1/5 1
(4) 1/5 1/5 - 2/5
(5) 7 1/5 6
Find the value of Zj:

(1) 70 0 +
(2) 70 1 +
(3) 70 - 1/3 +
(4) 70 0 +
(5) 70 5 +
0 0
S1 S2 Solution Ratio
- 1/3 1/3 5 OPTIMALITY REACHED!!!
1 2/3 - 2/3 10
2/5 3 650 Values: x1 = 10
2/5 3 x2 = 5

= 1
= 0
= 1 2/3
= - 2/3
= 10

KE OV NV
3/5 1/5 1/5 0
3/5 1 0 1
3/5 0 0.3 - 1/3
3/5 1/5 - 1/8 1/3
3/5 7 2 5
30 1 = 0 30 = 30
30 0 = 70 0 = 70
30 1 2/3 = (23) 50 = 2/5
30 - 2/3 = 23 -20 = 3
30 10 = 350 300 = 650
x 30 = 300 Optimum Solution = 650
x 70 = 350
650