Assignment 2

Maximize = 𝑍 = 3𝑋 + 2𝑋 − 𝑋 1. Slack Variable


𝑋 + 𝑋 + 2𝑋 + 𝑆1 = 10
Subject to 𝑋 + 𝑋 + 2𝑋 < 10 2𝑋 − 𝑋 + 𝑋 + 𝑆2 = 20
2𝑋 − 𝑋 + 𝑋 < 20 3𝑋 + 𝑋 + 𝑆3 = 15
3𝑋 + 𝑋 < 15
𝑋 ,𝑋 ,𝑋 > 0
Maximize profit =
𝑍 = 3𝑋 + 2𝑋 − 𝑋 + 0S1 + 0S2 + 0S3

First Tableau
Cbi Cj 3 2 -1 0 0 0 Solution Ratio
Basic
𝑋 𝑋 𝑋 S1 S2 S3
Value
0 S1 1 1 2 1 0 0 10 10.00
0 S2 2 -1 1 0 1 0 20 10.00
0 S3 3 1 0 0 0 1 15 5.00
Zj 0 0 0 0 0 0 0
Cj-Zj 3 2 -1 0 0 0
𝐶𝑜𝑟𝑟𝑒𝑠𝑝𝑜𝑛𝑑𝑖𝑛𝑔 𝑘𝑒𝑦 𝑐𝑜𝑙𝑢𝑚𝑛 𝑣𝑎𝑙𝑢𝑒 𝑥 𝐶𝑜𝑟𝑟𝑒𝑠𝑝𝑜𝑛𝑑𝑖𝑛𝑔 𝑘𝑒𝑦 𝑟𝑜𝑤 𝑣𝑎𝑙𝑢𝑒
𝑂𝑙𝑑 𝑉𝑎𝑙𝑢𝑒 −
𝑘𝑒𝑦 𝑒𝑙𝑒𝑚𝑒𝑛𝑡
Second Tableau
Cj 3 2 -1 0 0 0 Solution Ratio
Basic
Cbi 𝑋 𝑋 𝑋 S1 S2 S3
Value
0 S1 0 2/3 2 1 0 - 1/3 5 7 1/2
0 S2 0 -1 2/3 1 0 1 - 2/3 10 -6
3 𝑋 1 1/3 0 0 0 1/3 5 15
Zj 3 1 0 0 0 1 10
Cj-Zj 0 1 -1 0 0 -1

Third Tableau
Cj 3 2 -1 0 0 0 Solution Ratio
Basic
Cbi 𝑋 𝑋 𝑋 S1 S2 S3
Value
2 𝑋 0 1 3 1 1/2 0 - 1/2 7 1/2
0 S2 0 0 6 2 1/2 1 -1 1/2 45/2
3 𝑋 1 0 -1 - 1/2 0 1/2 2 1/2
Zj 3 2 3 1 1/2 0 1/2
Cj-Zj 0 0 -4 -1 1/2 0 - 1/2
Since all of the values of Cj-Zj are equal or less than 0, this is the optimal solution
𝑋 = 2.5
𝑋 =7.5 𝑍 = 3(2.5) + 2(7.5)

= 22.5
Question 2
𝑎 + 4𝑚 + 𝑏
Most Likely Pessimistic Expected 𝑡=
Activity
Predecessor Optimistic (a) (m) (b) Activitiy Time 6

A - 3 4 5 3 + 4(4) + 5 / 6 = 4

B - 6 7 14 6 + 4(7) + 14 / 6 = 8
C A 2 3 10 2 + 4(3) + 10 / 6 = 4
D - 6 9 12 6 + 4(9) + 12 / 6 = 9

E B,D 4 5 12 4 + 4(5) + 12 / 6 = 6
F E 1 3 11 1 + 4(3) + 11 / 6 = 4
G F 1 2 9 1 + 4(2) + 9 / 6 = 3
H C,G 2 5 8 2 + 4(5) + 8 / 6 = 5
I G,H 1 4 7 1 + 4(4) + 7 / 6 = 4

C 4 H 5
4 8 22 27
A 4 18 22 22 27
0 4
14 18

B 8 E 6 G 3
0 8 9 15 19 22
1 9 9 15 19 22

D 9 F 4
0 9 15 19 I 4
0 9 15 19 27 31
27 31
Critical Pathway D,E,F,G,H,I

Probability complete in 31 weeks


Project variance = 1+1
P(Z ≤ )
P(Z ≤ ) = √2
.
P(Z ≤ 0)
=0.5 = 1.41
Question 3
Slack Time
Immediat
e
Activity Time ES EF LS LF LS-ES LF-EF
Predecess
or
A - 4 0 4 6 10 6 6
B - 5 0 5 0 5 0 0
C A 3 4 7 10 13 6 6
D B 8 5 13 5 13 0 0
E B 2 5 7 16 18 11 11
F C,D 3 13 16 15 18 2 2
G C,D 7 13 20 13 20 0 0
H E,F 2 16 18 18 20 2 2

Critical Path = B,D,G


Question 4 𝑎 + 4𝑚 + 𝑏
𝑡=
6
Expected
Immediate Activitiy ES Critical
Predecessor
Activity (a) (m) (b) Time EF LS LF Slack Path Variables

A - 2 5 4 4.33 0 4.33 0 4.33 0 Yes 0.11


B A 3 6 9 6 4.33 10.33 5.33 11.33 1
C A 4 7 10 7 4.33 11.33 4.33 11.33 0 Yes 1
D B 2 5 14 6 10.33 16.33 11.33 17.33 1
E D 3 3 3 3 16.33 19.33 17.33 20.33 1
F C 6 8 10 8 11.33 19.33 12.33 20.33 1
G E,F 1 1 1 1 19.33 20.33 20.33 21.33 1
6 + 4(10)
+ 14 / 6 =
H C 6 10 14 10 11.33 21.33 11.33 21.33 0 Yes 1.78
3 + 4(4)
+5/6=
I G,H 3 4 5 4 21.33 25.33 21.33 25.33 0 Yes 0.11

Critical Path A,C,H,I


a.)Expected completion time = 25.33 weeks
b.)Variance would be used = Project variance = 0.11+0.11+1.78
= √2
=1.41