Professional Documents
Culture Documents
Overview:
In this Unit, you will learn how to plan and schedule projects using the Gannt Chart.
Module Objective:
After successful completion of this Unit, you should be able to:
Course Materials:
A. Handout: Project Management: Project Planning & Scheduling with Gannt Chart
Read:
GANNT CHART
The Gannt Chart is a popular tool for planning and scheduling simple projects. It
enables a manager to initially schedule project activities and then monitor progress over
time by comparing planned progress to actual progress.
2. Estimate the activity times: the time required to finish each activity.
A bank plans to establish a new direct marketing department. The project team
has gathered the following data:
The Gannt Chart may be used to answer 4 basic Project Planning questions:
1. When is the earliest project completion?
2. Which activities are critical (should not be delayed)?
3. Which activities are noncritical (can be delayed)?
4. How long can each of the activities be delayed without delaying the whole
project (slack)?
• Draw the bar corresponding to Activity D; it starts at Week 8, since it can only be
started after Activity A is finished; its length is 6 weeks, which is the activity time
of Activity D. Write A just before the bar to indicate its immediate predecessor.
• Draw the bar corresponding to Activity F; it starts at Week 14, since it can only
be started after Activity D is finished; its length is 3 weeks, which is the activity
time of Activity F. Write D just before the bar to indicate its immediate
predecessor.
Move in/startup G
• Draw the bar corresponding to Activity G; it may be started only after ALL of its
3 immediate predecessors – Activities C, E and F – have been finished, which is
at Week 19; its length is 1 week, which is the activity time of Activity G. Write C,
E, F just before the bar to indicate its immediate predecessors.
Move in/startup G C, E, F
Make sure that your most dependable people are assigned to do the critical
activities (A, E, and G);
Make sure that the progress of A, E, and G are closely monitored from start
to completion.
Step 6. Identify the noncritical activities
• The noncritical activities are the activities that may be delayed.
• In this case, since among the Activities A through G the critical activities are A,
E and G, it follows that the noncritical activities are B, C, D and F.
Notice that both Activities A & B can be started ASAP, but A is critical while B is
noncritical. What if we delay the start of B by, say, 4 days and temporarily assign
the interviewer in B to help those assigned to do A?
Given the activities of a project, their time estimates, and their immediate
predecessors shown below: