Professional Documents
Culture Documents
PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) are two
of the widely used techniques for planning and coordinating large-scale projects. By using PERT or CPM,
managers are able to obtain:
1. A graphical display of project activities – network or precedence diagram.
2. An estimate of how long the project will take – earliest project completion time.
3. An indication of which activities are the most critical to timely project completion – critical activities.
4. An indication of how long any activity can be delayed without delaying the project – slack .
PERT Terminology
Event – a performance milestone representing the start or end of some activity.
Example: Submitting your test paper after an exam
Critical Path – the most time-consuming chain of activities and events in a PERT network.
The critical path is significant because
a) the time required to finish this path would be equivalent to the earliest time required to
complete the project;
b) it is the path that contains the critical activities; i.e., if any of the activities along this path is
delayed, the entire project is delayed accordingly; and
c) if we are to speed up the completion of the project, we need to speed up the completion of the
activities along this path – the critical activities.
PERT
Activity Predecessor/s a m b A - 1 4 13
B A 4 7 16
A - 1 2 3 C A 2 2 2
B - 2 3 4 D C 4 6 14
C A 1 2 3 E - 1 3 5
D B 2 4 6 F E 3 5 13
E C 1 4 7 G - 7 10 13
F C 1 2 9 H G 6 7 14
G D, E 3 4 11 I B, D 1 1 1
H F, G 1 2 3 J F, I, H 13 16 25