PROJECT STATUS REPORT

ONLINE BOOK CLUB


6/05/2022 - 13/05/2022

PROJECT STATUS SUMMARY Percent Complete: 33%

Scope Schedule Risks

This is the project status report for the work done between 6th May, 2022 to 13th May, 2022. For
now,

WORK PLANED FOR LAST MONTH

Milestone WBS Planned Forecasted Actual Status


Project Inception 1 03/03/2022 11/03/2022 11/03/2022 Completed
Project Sign Off 2 14/03/2022 08/04/2022 08/04/2022 Completed
Deliverable WBS Planned Forecasted Actual Status
Research on different 1.1 03/03/2022 10/03/2022 10/03/2022 Completed
project topics
Meeting with supervisor to 1.2 11/03/2022 11/03/2022 11/03/2022 Completed
discuss various topics
Write project proposal with 2.1 14/03/2022 07/04/2022 07/04/2022 Completed
supervisor’s guidelines
Presentation of project 2.2 08/04/2022 08/04/2022 08/04/2022 Completed
proposal

1
WORK COMPLETED LAST WEEK

Milestone WBS Planned Forecasted Actual Status


Preparation of Detailed Project 3 03/03/2022 11/03/2022 11/03/2022 Completed
Document
Deliverable WBS Planned Forecasted Actual Status
Learn to use a project 3.1 11/04/2022 18/04/2022 18/04/2022 Completed
management software
Come up with project plan 3.2 18/04/2022 22/04/2022 22/04/2022 Completed
using using PM software
Work on Objectives of the 3.3 25/04/2022 6/05/2022 6/05/2022 Completed
project

WORK PLANNED FOR NEXT WEEK

Milestone WBS Planned Forecasted Actual Status


Preparation of Detailed Project 3 03/03/2022 11/03/2022 11/03/2022 Completed
Document
Deliverable WBS Planned Forecasted Actual Status
Work on literature review 3.4 6/05/2022 13/05/2022 In-
Progress
Requirements gathering 3.5 13/05/2022 16/05/2022 Open
Write software requirement 3.6 17/05/2022 19/05/2022 Open
document

OPEN ISSUES

WBS DESCRIPTION PRIORITY

3.4 Working on the High


literature review
3.5 Requirements Medium
gathering
3.6 Write software Medium
requirement
document

OPEN RISKS

2
None

DELIVERABLES AND MILESTONES

Milestone WBS Planned Forecasted Actual Status


Preparation of Detailed Project 3 11/04/2022 19/5/2022 In Progress
Document
Deliverable WBS Planned Forecasted Actual Status
Learn to use a project 3.1 11/04/2022 18/04/2022 18/04/2022 Completed
management software
Come up with project plan 3.2 18/04/2022 22/04/2022 22/04/2022 Completed
using using PM software
Work on Objectives of the 3.3 25/04/2022 6/05/2022 6/05/2022 Completed
project
Work on literature review 3.4 6/05/2022 13/05/2022 In-
Progress
Requirements gathering 3.5 13/05/2022 16/05/2022 Open
Write software requirement 3.6 17/05/2022 19/05/2022 Open
document

OPEN CHANGE REQUESTS

None