Professional Documents
Culture Documents
i
Moffat, S.J, 19th March 2015, ‘Building Information Modelling: The Adoption of
International Best Practice in the Fulfilment of Energy and Carbon Reduction in the
UK’, MEng (Hons) Civil Engineering, Edinburgh Napier University, MEng Dissertation
Abstract:
ii
Table of Contents
1. Previous Research ............................................................................................................................. 1
2. Introduction ...................................................................................................................................... 12
3.1 BIM Trial Project Evaluation: Progress towards 2016 Compliance ....................................... 17
3.2 A Review of International BIM Practice to Provide a Feasibility Study for Energy and Carbon
Modelling ............................................................................................................................... 17
4.2 The Emergence of a Collaborative Environment within the Construction Industry ............... 21
6. Discussion ........................................................................................................................................ 41
7. Conclusion ....................................................................................................................................... 45
8. References ....................................................................................................................................... 48
iii
Table 1.1.1: Moffat (2014) Case Study General Information .................................................................. 2
Table 1.2.1: Moffat (2014) BIM Benefit Scoring Criteria based on Bryde et al (2013) ........................... 4
Figure 1.2.2: Comparison of Bryde et al (2012) and Moffat (2014) results ............................................ 5
Table 1.2.2: Moffat (2014) Carbon Reduction Scoring Criteria, produced in research .......................... 7
Figure 1.2.3: Moffat (2014) Graph of scoring results with trend lines added to identify link with BIM
benefits and carbon reduction ................................................................................................................. 8
Figure 1.2.4: Moffat (2014) Graph of results with trend lines omitting identified exemplar projects ..... 10
Figure 4.3.2: 5 Year Programme for BIM Delivery (BIS, 2011) ............................................................ 25
Figure 4.3.3: COBie progression adjacent to maturity model (BIS, 2011) ............................................ 27
Figure 4.3.4: COBie project life cycle data exchange (BIS, 2011)........................................................ 27
Table 5.0.1: Proposed Opportunities from BIM-Based Energy Modelling (GSA, 2012) ....................... 35
Figure 5.1.1: Energy Modelling Decision Loop Diagram (GSA, 2012) ................................................. 36
Table 5.1.3.1: Modelling Detail and Depth of Analysis over Project Length (GSA, 2012) .................... 40
Acknowledgments
Firstly I would like to thank Dr Kenneth Leitch of Edinburgh Napier University for his
guidance and invaluable feedback during the course of the Honours and Masters
dissertations. I will also like to thank the Robertson Civil Engineering team and in
particular Tony Fry, Managing Director for granting me part time work experience
during my final year and for the offer of graduate employment on completion of my
university course. Lastly I send my greatest thanks to the support of my parents John
and Jean Moffat, Brother David, girlfriend Mel and the friends whom accompanied me
over the last 5 years. Without the support of these individuals my university journey
and achievements would have never been possible.
iv
1. Previous Research
1.1 Background
The research paper titled, ‘The Benefits of BIM for the Life Cycle Reduction of Carbon
in Building Projects’ (Moffat, 2014) gave an insight into two continuingly developing
practices within the construction industry. Focussing within the UK the research looked
to identify a link in the widespread adoption of BIM and the continued effort to reduce
large number of research focussing around the applications for BIM. However a gap
appeared in the research when considering increased building performance and the
Using benefit indicators identified through analysis of literature based case studies a
scoring matrix was adopted leading to a better understanding of the most found
benefits in BIM use. Acquiring this knowledge pointed the direction for Moffat’s (2014)
research. Therefore the aim of the research was to identify the most found benefits in
The limitation of knowledge in this area was noted to continue through the
that experienced in Bryde et al’s (2012) paper, it was proposed the information of
project cases would be sourced from literature. However the existence of this
information was scarce and none featuring UK cases were to be found. The data
gathering then required to expand and focus the search for cases within publications
1
from construction firms, software vendors and industry award entries. This search
Completion
Project Name Location Value Size Type
Date
Innovate Green Project, Thorpe Park Leeds £5.5 M 4180.6 m2 Office 2007
As noted the data gathering method obtained information from numerous sources
(software vendors, construction firms and award stories). Two areas of interest were
noted when evaluating this information prior to undertaken the research method.
The first was the lack of a standardised format to showcase project information as part
of a collective glance at BIM use. For instance each source had a unique format in
cataloguing the use of BIM and the features which promoted carbon reduction. This
lead to key information being scattered through the publication or in some cases a lack
of clear benefit indication. An idea put forward in this research was for the industry to
provide a single source for BIM case studies. In which each case was categorised by
2
BIM application or project information (type, budget range, etc.) for ease of research
The second area of interest was the link, in the case study publications, between BIM
use and carbon reduction. An initial focus of Moffat’s (2014) research was the
existence of a clear link. This was identified and best promoted via software vendor’s
feasibly design and construct low energy and carbon features within a building. The
other types of case study sources demonstrated both practices independently and on
The method for analysis seen the data gathering results put through a developed two
part assessment process. The first part implemented the already established scoring
matrix in Bryde et al’s (2012) research. A few modifications were required for this
study. The scoring criterion was relatively unchanged with the only modification to the
scope management criteria. This was omitted from the assessment as the process of
analysis failed to identify any benefits which fell into the description.
Another modification was the inclusion of a positive focus in software use. Bryde et al
(2012) concluded that only negative experiences with software use were documented
in the literature cases. Altering the description of software use opened up the
The complete scoring matrix used in the research can be seen in Table 1.2.1.
3
Table 1.2.1: Moffat (2014) BIM Benefit Scoring Criteria based on Bryde et al (2013)
BIM Benefits
Score awarded for
Benefit criteria based
every benefit identified
on Bryde et al (2013), through publications
PMBOK
Following an analysis of the 13 chosen case studies the benefits of BIM use were
25
22
20
16
14
15 13
10 10 10
10
4
5
4
The main finding from this part of the research, to satisfy the overall aim, was that the
primary benefit identified from implementing BIM in low carbon building projects was
quality regarding finish and assurance. This was deemed justified as a great aspect in
As a major part of this research was inspired through the knowledge gained from Bryde
et al’s (2012) literature based benefit analysis. It was interesting to document the
differences in the results. The most striking difference was the existence of cost based
benefits from BIM use. Bryde et al (2012) noted a large quantity through the literature
case study analysis. However when analysing low carbon building projects cost
benefits were somewhat surprisingly low. It was proposed that this may be related to
the cost of implementing BIM with higher capabilities to perform building performance
supported this claim. The complete comparison showing the differences between the
The second section, albeit combined within the main tranche of the study, added
critical value to the research. A second bi-spoke assessment was produced to identify
5
a ‘carbon score’ element based on environmental features. This was undertaken with
the purpose of enhancing the link between BIM and low carbon building production.
Within each case study documentation it was common practice to highlight the
and the overall carbon production throughout the development. The formation of the
carbon scoring matrix was developed with close reference to the information available
in relation to zero carbon buildings and the classifications for assessment of a Building
6
Table 1.2.2: Moffat (2014) Carbon Reduction Scoring Criteria, produced in research
case studies
Monitoring and control Energy level monitors and automatic/manual control of appliances
SAP Ratings Achieving SAP rating for energy and environmental efficiency
7
Combining both assessment models provided a better understanding of the link in
adopting BIM to reach carbon reduction goals. It was noted that in general projects
with the most reported BIM benefits seen a better carbon score. This is shown by
Figure 1.2.3.
25
BIM
20 Carbon
Percentage of total results (%)
Trend (BIM)
15 Trend (Carbon)
10
Figure 1.2.3: Moffat (2014) Graph of scoring results with trend lines added to identify link with BIM benefits and
carbon reduction
Figure 1.2.3 highlighted a trend and insight into BIM best practice potentially bringing
The results achieved provided the developing construction industry with a positive
outlook for a potential future path for BIM adoption within the UK. Using BIM in low
carbon building developments not only brings a large number of benefits but can
incorporate a larger scope to enhance projects carbon goals. However influence was
apparent whilst collating case study information sources. The overall quality and
reliance of the results were mainly cohesive by ensuring that the scoring criteria and
8
method of analysis had clear links to previously established study. However the
Software, Construction firm, Industry (EUROBUILD t/a MassivHaus Ltd. 2014), (Graphisoft UK Ltd, 2012a),
Hadlow College 4
award (Passivhaus Trust, 2012a), (Passivhaus Trust, 2012b)
Affordable Passivhaus 2 Software, Construction firm (Graphisoft UK Ltd, 2012c), (Graphisoft Connect, 2014)
Environmental award, Construction
Cobalt Data Centre 2 2 (BRE Global, 2014), (Woods Bagot, 2014)
firm
Adler Street Hotel 1 Software (Sefaira Ltd, 2013)
E.ON Regional HQ Building 2 Construction firm (BWB Consulting, 2013), (BWB Consulting, 2014)
The first observation is the quantity of publications found for each case study. The
largest scoring cases generally had more than one publication available for analysis.
This echoes the notion that this form of research would be bolstered with a single
destination and format for case study publications. The second influencing factor came
from the case study source type. Both the highest scoring carbon project’s information
was found through award story and firm publications. It was noted that these two
cases, Hadlow College and Cobalt Data Centre 2, were showcased as exemplar
environmental and sustainable projects which were then supported by BIM. These
were exceptions as the majority of cases focused on BIM use as a driver and supporter
for carbon reduction measures. This is clarified in Figure 1.2.4 when the exemplar
9
25
BIM
20
Percentage of total results (%)
Carbon
Trend (BIM)
15
Trend (Carbon)
10
Figure 1.2.4: Moffat (2014) Graph of results with trend lines omitting identified exemplar projects
A provisional idea of how the research can be developed further was put forward in
structured interviews with project parties involved in the focused case studies. The
view of this was to provide additional and more detailed information on the benefits
noted from BIM use and how this directly linked to carbon reduction. This approach
however would become more valuable if a larger quantity of cases were available. It
defined influences and justify that value has been added to the findings. Due to the
scarce availability of project cases this approach was seen to be unavailable at this
present time.
Another recommendation was to refine the carbon scoring methodology in which, with
a specific focus away from BIM, a carbon assessment framework is developed. This
10
would promote normalisation of project carbon reduction scores. Using this framework
it can be assessed how BIM aids in feasibility of carbon reduction. However to best
facilitate this it was recommended that the industry provides quantitative data on
which is rarely noted and most definitely not found in mass throughout industry case
studies. If available this would be valuable information and could provide an initial step
to acquiring carbon reduction benchmarks to be expected from BIM use in carbon and
energy analysis.
The final recommendation for future research, something initially proposed to be the
next step, was to expand the data gathering scope to include international projects.
The aim of this was to gauge the effectiveness of the UK case studies’ approach in
BIM adoption for low carbon buildings against those internationally. The international
(McGraw-Hill, 2010) paper that in North America more BIM adoption is present for
However there is a chance that this research path would produce scattered results
without clear means to compare the UK and international BIM adoption. It is advised
prior to this research to evaluate the supporting information which aims to drive BIM
for the purpose of carbon and energy reduction. This will provide the knowledge in
how ‘green’ BIM is established domestically and internationally. From this knowledge
the case study information can then be related back to the supporting information to
identify areas of best practice, inefficiency or failure and exemplar activity. Adding the
international cases can potential identify future development and experience from the
11
2. Introduction
The global economic crisis swept through the construction industry leaving the UK
Office, 2011). Within this strategy the aim was to reform the methods of procurement
industry value in budget spending and with the intention to contribute to the overall
In the modern age the move towards automation and digital technology has swept
global markets. The construction industry has been noted to lapse in the uptake of
digital technology and failed to grasp the potential growth opportunities associated
(Cabinet Office, 2011) (HM Treasury, 2011). Therefore in a move to counter this trend
the Government has set the industry a challenge in raising the current digital
Information Modelling (BIM). A collaborative, data rich process in which project phase
decisions and life cycle information are contained within a 3D virtual environment.
Having identified the most found benefits in BIM for low carbon building developments
being a prominent influence on BIM uptake, can push for industry development of BIM
closely examining the supporting documentation for BIM adoption will provide a means
to evaluate the progression from the mandate’s inclusion within the construction
reform strategy.
12
The global construction industry has similarly identified the requirement to undertake
more collaborative steps to inject increased efficiency and value. BIM has been a focal
point for streamlining this and hence a global market for BIM support has erupted. The
UK has identified itself as a European leader in BIM adoption (HM Government, 2012).
‘We’re a long way behind the achievements of the Nordic countries and North America.
In those countries, the discussion phase is over and people are expanding the benefits
America is an area seemingly unexposed within the UK. The knowledge base of this
practice, and indeed that of carbon reduction modelling, is limited yet encouraging.
The aim of this research is to review the information in support of the Government’s
mandate of minimum level 2 BIM on all procured public sector projects by 2016 and
From this with the use of the U.S General Administration Services BIM Guide for
Energy Performance point the way forward for the UK to incorporate energy and
13
Evaluate the progress of this mandate to date using the available trial projects
Study the GSA BIM Series Guide for energy performance and operation to
summarise the feasibility in widespread roll out of BIM-based energy and carbon
modelling.
Discuss the findings from the study of GSA energy performance best practice
and suggest a path for the UK involvement with aid from previous supporting
research.
As the construction industry begins adjustment to the realisation that digital technology
knowledge base to continue development. Lieyun, Ying and Burcu (Lieyun, Ying and
Burcu, 2014) collected 135 BIM research papers over a 7 year period and categorised
the viewpoints of each paper to provide an outlook of the knowledge base provided.
This concluded with only 2% of papers with a focus on ‘carbon emission calculation’.
The reasoning behind this was proposed by Lieyun, Ying and Burcu (2014),
‘There is a BIM related research gap for the project domains of quality, safety and
carbon emissions. In comparison to other domains, few research studies have been
conducted so far in these domains. The reason might be that these project domains
are more complicated to quantify than cost management and schedule control’.
Something echoed by Moffat (2014) which noted the lack of quantitative data in which
14
Lieyun, Ying and Burcu (2014) continued the carbon focus by expressing the method
emphasis on the inclusion of carbon production and embodiment figures as live data
within the construction programme (Li et al, 2012). Lieyun, Ying and Burcu (2014)
demonstrated the method in production of the 4D model in which, ‘the carbon emission
curve can be generated as the construction process moves forward’ (Lieyun, Ying and
Burcu, 2014). This process also includes the carbon information from consumed
real time BIM process allows the live generation of carbon reduction measures.
However the results at the time of the research were generalised due to the missing
availability of material embodied carbon information (Li et al, 2012). Within the UK this
approach would be beneficial to develop alongside the information now available from
life cycle analysis of building materials. One such database which has been
constructed is the Inventory of Carbon and Energy. A database containing the efforts
of life cycle analysis to produce figures for the raw materials used in building materials
available in the UK supply market (Hammond and Jones, 2011). As such this idea has
been conducted by Capper et al (2012) which produced embodied energy and carbon
BIM.
As noted before Lieyun, Ying and Burcu (2014) identified a lack of research into BIM’s
involvement for carbon emission calculation. On the other hand within the same
Ying and Burcu, 2014). Something that internationally has seen a dramatic
15
2010) produced a market report based within North America which highlighted the
practitioner movements in BIM development. It was noted the top use of ‘green’ BIM
result from the large knowledge base supported by industry research and the
existence of BIM guidance in such practice (GSA, 2012). Not surprisingly then, the
second least used BIM ‘green’ activity was carbon emission analysis (McGraw-Hill,
2010). Another statistic from this survey which brings attention is the top driving factor
for ‘green’ BIM. McGraw- Hill Construction (2010) noted the top driver to be from
‘owner (or client) demand’ with ‘availability of BIM tools’ and ‘saving time and money’
or the larger scale carbon and energy agenda was apparent. Begging the question if
3. Research Method
The first section of this research is a review of the Government’s mandate for BIM use
in public projects. This has been a chosen task to initially understand the catalyst for
BIM use and how the industry is supported. Following this progress to date will be
examined with the evaluation of the trial project reports produced within the
Government publication portal. The final section of this research will undertake a study
of international practice which looks at the U.S General Services Administration (GSA)
Energy Performance and Operation guidelines. This section will extract the feasibility
for a similar existence in the UK’s BIM development. The eventual findings of this will
16
3.1 BIM Trial Project Evaluation: Progress towards 2016 Compliance
The existence of trial project reports within the public domain is a means to provide a
form of progress indicator for the reform in the procurement of construction projects.
This is deemed necessary to measure the impact that the revised construction strategy
has made in current projects. Documenting each project at varying stages allows a
and highlight examples of efficiency and innovation to be rolled out on future projects.
In terms of BIM use 11 trial projects were identified to feature an adoption of level 2
BIM (Cabinet Office, 2012b). The intended evaluation undertaken in this research will
focus on these projects to identify how BIM has aided in the reduction of cost and
carbon.
The trial project publications have only recently been made available in the public
domain. Therefore only 3 BIM compliant projects are published to date out of a
until more cases are available. With under a year left until the mandatory minimum
with only 3 reported BIM projects via the Government’s procurement case study
publications this information source does not provide insight into whether the public
sector construction industry is BIM compliant at this stage. Nevertheless the results
As in the UK, North America, in particular the United States General Services
Administration (GSA) Public Building Services (PBS), have similarly pushed for reform
17
in the construction industry to combat inefficiency and wasteful rework in design (GSA,
2007). The use of BIM in this movement was initially introduced in 2007 (GSA, 2007)
in which all funded projects from this year, being a fiscal year, required a minimum use
BIM guidance allowed feasibility of this. The GSA stated the intent to further develop
the supporting BIM guidance and notably providing direction to best practice in energy
performance modelling.
environment has led to widespread mitigation efforts. North America has taken
initiative and similarly to the UK provided a future date for the existence of zero emitting
buildings over their life cycle. However the GSA has focussed on the need to reduce
the overall energy consumption from its procured public facilities. Hence aspiring to
continuingly reduce energy consumption until the eventual production of net zero
A means to drive this is aligning BIM modelling tools with building performance
simulations in order to understand the optimal option for each project to reach specific
energy reduction goals. Therefore the development of the GSA BIM Series 05 –
Energy Performance and Operation (GSA, 2012), as part of the wider BIM guidance
series, helps create feasibility and best practice with this process. The guidance was
modelling tools thriving with asset information. The guidance is generalised to suit all
applications and cater for all levels of BIM maturity. However it is noted, ‘the scope of
implementing BIM-based energy modelling is typically unique for every project’ (GSA,
2012).
18
Using this established international guidance document. This research will identify
best practice guidance in implementing energy modelling and adapt this into a
feasibility case for the UK’s goal of carbon reduction. This is documented in Section 5
By the time the Government office and supporting departments seen a refresh in 2010
the UK’s industries were suffering a lack of clear direction to enable growth in the
investment and development of the country’s infrastructure and facilities has had an
impact on the country growing as a whole (HM Treasury, 2011). The general view is
that the UK construction industry has undervalued its capacity for growth through the
procurement of public sector projects (Cabinet Office, 2011). This hasn’t always been
a reality and the UK has come to this conclusion following a period of decline in the
international economy, ‘the global financial crisis and the associated recession has
ended a 15 year period of continuous growth’ (HM Treasury, 2011). The agenda to
rejuvenate the industry was initiated in the HM Treasury’s (2011) ‘Growth Plan’
document (HM Treasury, 2011). The plan is to benefit construction with changes to
the planning system, agreement of public sector funding, reform in the procurement
method for projects and the injection of the carbon initiative particularly in housing
be spent in both the public and private sector on infrastructure until the end of the
Government term (2015). With the public sector having a 40% stake in the investment
19
and workload, considerable growth can be extracted in the public domain (Cabinet
Office, 2011).
With the growth agenda firmly in place a strategy was to be produced and
subsequently adopted throughout the industry. The Cabinet Office (2011) produced
reducing costs and reducing the burden on the carbon output of the country. The aim
for the strategy is to change the relationship between the Government Authorities and
the industry in the public sector resulting in the Government as a client getting the best
value for money while maintaining a constant improvement and procurement of the
country’s infrastructure (Cabinet Office, 2011). With this the ideal model for
procurement is to be examined.
Contractors engage key members of their supply chain in the design process
Value for money and competitive tension are maintained by effective price
benchmarking and cost targeting, by knowing what projects should cost, rather
Supply chains are, where the programme is suited, engaged on a serial order
informed choices (at its own risk) about where to invest in products, services,
20
There is an alignment of interest between those who design and construct facility
and those who subsequently occupy and manage it. (Cabinet Office, 2011)
In review of this the public sector is seen to shift to become a more informed and co-
ordinated market and in challenging the procurement model the industry will promote
In 2007 The British Standards Institute (2007) published BS 1192:2007. This standard
governs the best practice for the production, recording and distribution of construction
and share data efficiently without loss, contradiction or misinterpretation’ (BSI, 2007).
The notable benefits to this ‘environment’ is a higher quality of information, greater re-
collaboration increased, an action for more efficient information sharing was targeted,
information to be shared between all members of the project team. This is a repository,
21
Figure 4.2.1: Data management repository (BSI, 2007)
With this standard published in the industry from 2007 the methodology for
collaboration and information exchange was established (BSI, 2007). However it was
noted in the Cabinet Office (2011) Construction Strategy that the industry had failed
by not taking the initiative and lost direction with collaboration and technology
adoption. The document noted, ‘…construction has generally lagged behind other
industries in the adoption of the full potential offered by digital technology’ (Cabinet
Office, 2011).
Following the realisation that growth in the construction industry can be driven with a
collaborative environment the Cabinet Office’s (2011) objectives included the push for
for BIM adoption was set for 2016 with the mandate that, ‘Government will require fully
22
collaborative 3D BIM (with all project and asset information, documentation and data
For the Government’s benefit BIM will improve the quality of construction information
typical characteristics of BIM models are summarised in Crotty’s (2012) book which
and insertion point location. They can also carry many more attributes than
geometry; all of these other attributes can be equally accurate and well specified.
BIM components are said to be ‘intelligent’ in the sense that they can be
BIM components are interoperable; at least in theory, objects created in one BIM
widespread adoption. The BIM Industry Working Group (2011) chose rather to focus
on the outputs of BIM to develop a strategy for increased use leading to the 2016
Government target. This provided the hypothesis, ‘Government as a client can derive
significant improvements in cost, value and carbon performance through the use of
The target set by the Cabinet Office (2011) translates in BIM terminology as equal to
‘Level 2’ which is defined, ‘BIM – File Based Collaboration and Library Management.
23
This approach may also include 4D and 5D elements as well (4D cost, 5D programme)’
(BIS, 2011). The ‘maturity model’ of BIM is the UK BIM Groups’ staged model which
clearly defines the increasing data and processes associated with a level of
competency (Level 0 – 3) (BIS, 2011). The model which is explained in the BIM
Working Party Strategy Report (2011) is intended to clear up the confusion which was
present with BIM at the time and provides transparency for what data and standards
It is noted that level 3 is remaining under development and therefore no timeline for
Level 0: Unmanaged CAD probably 2D, with paper (or electronic paper) as the
24
structures and formats. Commercial data managed by standalone finance and
(proprietary). The approach may utilise 4D programme data and 5D cost elements
Level 3: Fully open process and data integration enabled by “web services”
The BIM Industry Working Group (2011) was the initial contributor for the UK
construction industry’s target of Level 2 BIM by 2016. The document collected the
information with the view that all Government suppliers (construction services) should
adopt at least Level 2 BIM with the use of the five year programme (BIS, 2011). The
25
The phases within the 5 year programme are explained:
Phase 0: This will allow detailed planning and delivery of the support,
Phase 1: To use the new process documents and contracts to deliver COBie
specifications.
Phase 3 & 4: This will be future capabilities that make use of the work underway
For the purpose of clarity in this plan, COBie is the collection and distribution of all
asset data in spreadsheet format which is passed on to the Client for immediate
ownership and responsibility of the finished building (BIS, 2011). This provides a
complete information package of the asset from each project phase to be used
throughout the lifecycle operation and occupation of the building (BIS, 2011). The
vision of this in its developed form, alongside Level 2 BIM, is a fully web based portal.
26
Figure 4.3.3: COBie progression adjacent to maturity model (BIS, 2011)
Figure 4.3.4: COBie project life cycle data exchange (BIS, 2011)
development was present throughout the industry (Cabinet Office, 2012a). The
Cabinet Office (2012a) produced a ‘One Year Report’ document which presented the
progress to date. This included a designated BIM Task Group haven been launched,
movement in the launch of COBie UK 2012 and a network of BIM hubs being
introduced as advice centres for local Governments across the country (Cabinet
27
Office, 2012a). There was an existence of positive BIM capabilities with the Ministry
examples (Cabinet Office, 2012a). The Cabinet Office (2012a) also included, within
the action plan, the provision of trial projects which will be evaluated on a yearly basis
(Cabinet Office, 2012a). This was committed and trial projects were published in a
separate document ‘Construction Trial Projects’ highlighting that BIM has been
featured in a number of projects across all 7 departments (Cabinet Office, 2012b). The
time until the 2016 target is reality. With the evidence that progress and commitment
to the strategy exists, it is promising that the UK looks set on reaching the 2016 target
The UK’s goal for BIM is now developing recognition globally. The HM Government
(2012) stated, ‘The UK is now recognised by its peers as one of the leading nations in
centrally-led programme’ (HM Government, 2012). The document identified that the
UK is stretching its influence of the strategy and commitment to the 2016 target. HM
Government (2012) explained, ‘The digital applications (in construction) ‘genie’ is well
and truly outside of the lamp and cannot be put back in. The UK is well placed to
and development’ (HM Government, 2012). This continued, ‘We will identify key
actions to support and accelerate this programme to ensure that the UK is able to take
operation of assets’ (HM Government, 2012). The action plan contained within this
28
Table 4.4.1: Action Plan adapted from HM Government (2012)
Work with the BIM Technologies Alliance to identify the opportunities Cultivating and nurturing
4 in the expanding BIM market and investigate the need for a innovation in software and
technology hub to incubate/stimulate ICT start-ups/spinouts from BIM services sector
Government will build the capability to accept and handle BIM data to Review public sector portals and
8 support our aspiration to be a recognised global force in Building establish a strategy to accept
Information Modelling digital information
The UK will take a leading role and seek global partners in developing
10 International BIM standards to enable software to work together more Sustaining a UK leadership
effectively
As the BIM strategy picks up steam towards 2016, the most relevant section in this
document is the future actions. Action 10, ‘The UK will take a leading role and seek
together more effectively’, works on the realisation in the BIS (2011) BIM Strategy of
the importance of international alliances (HM Government, 2012). The BIS (2011) BIM
Strategy document recognised that connecting BIM strategies with other nations can
push for a BIM policy enabling a larger scale adoption internationally (BIS, 2011).
However the UK needs to remain close to the adopted strategy to remain competitive
29
within the technology and software market which develops through fluctuation of the
investing in the UK in delivering the technology needed, assisting with strategy and
develop a standard BIM implementation policy featuring best practice whilst remaining
independent with the current strategy to maintain a UK BIM software and knowledge
As part of the continued effort in the reform of the Government procurement methods.
The Cabinet Office (Cabinet Office, 2012b) developed progress indicators through the
issue of case study reports of industry trial projects. Three of these trial projects within
One year on from the Government Construction Strategy (Cabinet Office, 2011) it was
noted that the Ministry of Justice looked to excel in BIM adoption and roll out BIM
processes with all future procured assets earlier than any other department (Cabinet
Office, 2012a). Therefore it is no surprise that two of the BIM trial project publications
come from the Ministry of Justice, including the most beneficial indicating project
30
(Cookham Wood Young Offenders Institution). The available projects are summarised
in Table 4.5.1.
It is noted that all three projects chose the two stage open book procurement method.
In the first stage of this method the contractor-consultant teams compete for the
contract with the most competitive all round package being awarded the project. The
second stage allows the winning team to produce a proposal based on an open book
cost which meets the clients intended project output and benchmark cost. The
Cookham Wood project (Cabinet Office, 2014a) trialled the involvement of BIM at the
earliest stage of the project reporting the positive impact in the selection of the delivery
team and acquiring the best price for the project. This was achieved with the availability
of additional information at an early stage from the collaboration of project teams and
projected through to project completion. Furthermore the use of COBie data drop
guidance allowed the data transfer to an acquired facility management hub in order to
continuingly develop asset information and generate cost savings through the life cycle
of the asset. The use of BIM in this project has allowed the Ministry of Justice to
evaluate the potential for cost savings in future projects. As seen in the New Prison
North Wales project (Cabinet Office, 2014b), lessons learned will be rolled out to
achieve the predicted cost savings in this larger more complex project.
31
The Property Services Cluster (Cabinet Office 2014c) is a development of 12
education projects. Two of which are the focus of the trial project publication. The
project stated the compliance of level 2 BIM adopted by the client on selected
individual facilities. However noted that the programme has developed standardised
and innovative designs. The use of BIM was noted in one of the project to develop the
design and create employer’s requirements for use in other projects within the master
plan. The standardised designs have reduced costs from benchmarks yet has not
critically explained the effectiveness of BIM in realising this saving. In general this
project has not led to clear indication of progress in the use of BIM. It was hoped that
this case study would provide evidence that a similar adoption rate apparent in the
The Government trial projects have successfully shown the progress in the reformed
stage open book procurement route suggests that best practice in combatting
inefficiency and a lack of innovation is through BIM adoption. The Cookham Wood
industry leader in BIM adoption the MOJ has strengthened the benefits of BIM use by
noting the findings from an innovative example. Overall the project has noted an
exemplar case in BIM use in which the construction industry and Government
departments would value a close analysis to develop a similar framework for adoption.
and construction phases of the project. Virtual and actual prototypes have been
32
produced to engineer out potential defects and clashes. It is also envisaged that the
data that BIM will capture will positively inform the future facilities management of the
The final observation of BIM progression following the Construction Strategy (Cabinet
Office, 2011) is the striking absence, within the BIM featured trial projects, of any
actions to reduce energy and carbon consumption. Something which has become a
major focal point of modern construction and noted as an important step to introduce
However potentially the carbon and energy goals in the procurement trial projects are
not yet a focus due to the prominent emphasis on residential developments over
nearest future. The Construction Strategy procurement trial case studies have
specified the scope to include cost reduction methods as the progress indicator.
However it was expected to find evidence of the wider construction strategy elements,
for instance carbon reduction measures, to be reported. Being the primary source for
focus) in the reform of the procurement and supply of public projects has been
presently neglected.
The construction industry has seen a dramatic move to clean up the phasing process
and minimise the effects on the environment. The UK mentioned the requirement and
construction to eventually completely omitting the industry from the overall carbon
generation of the country (HM Treasury, 2011). However it is not yet discovered how
33
this will be aligned, or indeed feasibly possible to align, with the recommended and
mandated steps to include digital technology throughout the life cycle development of
projects.
of energy within the national building stock has led to a target of net zero energy
buildings, embodied and operational, as early as 2030 (GSA, 2012). With the
existence of guidance to achieve this via BIM-based energy modelling this eventual
To feasibly achieve this a focal point in the U.S. General Service Administration’s BIM
Guidance Series (GSA, 2012) was to include guidance information to support best
to improve the accuracy of design level energy and building performance calculation.
simplifying the process with the aid from the contained asset information including
generated without additional rework reducing the time when conducting design
simulation. The GSA (2012) energy performance and operation guidance summarised
the potential opportunities available with BIM-based energy modelling (Table 5.0.1).
34
Table 5.0.1: Proposed Opportunities from BIM-Based Energy Modelling (GSA, 2012)
Accurate modelling of as-built Consistent and accurate Life-cycle cost and estimated
conditions, calibration of energy energy predictions that result annual energy consumption
Renovation and Modernisation models, reliable evaluation of in the identification of the that meets or exceeds project
existing mechanical design and most cost effective energy goals, accuracy and
performance efficient retrofits consistency in energy models
Optimised energy
Continuous commissioning using Develop an energy modelling
performance, meeting or
real-time energy modelling to feed-back loop which
Existing Building exceeding design intent,
evaluate actual future building evaluates building
accuracy and consistency in
performance performance in real-time
energy models
The GSA (2012) demonstrated the project level decisions which are required in
providing clearance for the adoption of energy modelling within BIM. This forms a
decision loop in which the four decisional inputs, project team experience, budget and
schedule, scope and detail and technology, initiate the process of answering, ‘How
can the project team implement BIM-based energy modelling?’ (GSA, 2012). This is
35
Figure 5.1.1: Energy Modelling Decision Loop Diagram (GSA, 2012)
The experience of project teams first starts with the capabilities in integrating the
information from collaborative working of each project discipline into BIM. The level of
collaborative working and engineering processes are the foundation of Integrated BIM
collaboration in the UK, albeit currently under development, remains in the early
stages as guidance and support from the reform in procurement methods are in trial
36
Secondly the experience in BIM-based energy modelling is similarly limited. The cases
modelling. However this experience relates to individual private sector companies and
The GSA (2012) energy modelling guide states, ‘Energy modelling itself is a complex
successful’ (GSA, 2012). This suggests that the overall level of knowledge in building
This knowledge then supported with the reliability of BIM provides a means of
simulating energy performance to best replicate that of the actual outputs of the
completed asset.
carbon design and align within the collaborative BIM movement to raise
The price tag associated with BIM adoption is rarely a focus in supporting information.
The BIS BIM Working Group (BIS, 2011) mentioned the support for BIM at a cost
effective and feasible state. However did not provide guidance in costing BIM within a
project. Trebilcock (2015) summarised the existence of increased fees from tender
packages due to a ‘BIM factor’ charge (Trebilcock, 2015). However stated that it may
be impossible to set a nominal expenditure on BIM due to the differing project abilities
Adding energy and carbon modelling with BIM processes is assumed to cause some
37
‘With increased attention to the sustainable design of buildings, more and more design
teams are enhancing their in-house energy modelling expertise and/or working more
with the continued development and improved usability of energy simulation programs,
has resulted in a decrease in energy modelling costs in recent years.’ (GSA, 2012)
In addition to this GSA (2012) proposed the use of software vendors’ consultation and
potential support to not only procure software packages but to produce a cost effective
The GSA (2012) as a client requires energy calculations and environmental award
the GSA (2012) stated, ‘Energy modelling commenced during design development or
construction document phases typically has very limited impact compared to modelling
3) Project teams should evaluate and decide the inclusion of energy and carbon
38
5.1.3 Scope and Detail
of energy and carbon modelling, a form of execution document can be included during
concept phase (GSA, 2012). This is aimed at defining the project constraints and
performance goals and how these elements impact the scope for energy and carbon
modelling. This is produced within the collaborative BIM direction plan in providing
The influencing factors in scope and detail stem from the project itself. Be it size and
importance of the project or control measures set by industry targets. Each project’s
developments. As noted in the Government’s carbon goals (Cabinet Office, 2011) (HM
Treasury, 2011) the inclusion of zero carbon homes by 2016 signifies the first industry
milestone. Yet in some cases the requirement for BIM-based analysis of building
performance is not deemed necessary. With the GSA (2012) stating, ‘In smaller
projects it can be faster to make adjustments to the building design in the energy model
application to a simulation tool’ (GSA, 2012). However this does not take into account
Project phasing provides a heavy influence on the level of detail. Table 5.1.3 indicates
that with the earliest design phase adoption brings a continued expansion of modelling
39
Table 5.1.3.1: Modelling Detail and Depth of Analysis over Project Length (GSA, 2012)
Site location, building orientation, massing and Quickly assess large-scale impacts of
Preliminary Concept Design
default assumptions design alternatives
GSA (2012) concluded, ‘When properly used with building performance analysis tools,
BIM has the potential to enable completely different design mentalities and strategies,
creating a completely new design process that expands a design team’s capabilities
and allows for information typically considered during later design to be used upstream
4) Provide transparent project energy and carbon reduction goals and provide
the process best suited to achieve this through a BIM Execution Plan.
5.1.4 Technology
The most critical element in feasibly undertaking energy and carbon modelling is the
analysis tools to combine all life-cycle assessments requires the inclusion of third party
aims may be better supported than others, ‘Though software capabilities are
increasing rapidly, the project team may find that a particular project proposal or
40
desired analysis is simply not well supported by a give tool’s functionality and/or the
The feasibility for increased BIM add-in software in the UK market relies heavily on the
training of project team members and the availability in supply from vendors. In
particular the BIM software support has a tendency to target the most developing
market in which demand and profitability is thriving (BIS, 2011) (GSA, 2012).
Nevertheless the existence of software support for analysis has been documented in
Moffat’s (2014) paper. In which a number of case studies were identified via software
vendor publications.
It is important to note as the energy and carbon modelling goals develop in complexity.
The more fragmented the compatibility becomes (GSA, 2012). Inclusion of renewable
energy simulation and complex comfort control analysis brings more and more
additional software into practice creating the constant need in research and
development.
6. Discussion
Prior to conducting this additional study it was understood the lack of research in the
area of focus. Moving forward from the previous research (Moffat, 2014), a target was
including the information in support of the Government’s aim for BIM adoption. Having
identified a means of progress indicator, Government trial projects, its believed that a
missing opportunity in trialling BIM energy and carbon costing is apparent. Rather the
41
Government trial projects have provided only an overview of the involvement that BIM
has in early design decisions to feasibly achieve cost reductions. Hence a similar
The exclusion at this stage may be reality following a movement initiated by the HM
‘The Government will introduce more realistic requirements for on-site carbon
appropriate levels of on-site reductions as the starting point for future consultation,
along with their advice to move to an approach based on the carbon reductions that
are achieved in real life, rather than those predicted by models.’ (HM Treasury, 2011)
However as seen with Leiyun, Ying and Burcu (2014) and Li et al (2012) the
Lockley’s (2012) research may be the industry defining option to use the already
supported BIM progress to help catalogue and reduce carbon of building projects
(Leiyun, Ying and Burcu, 2014) (Li et al, 2012) (Capper, Matthews and Lockley, 2012).
Hence potentially streamlining the construction industry’s goal of zero carbon buildings
It is not quite sure how the industry will react to this movement. The lack of already
established progress in BIM adoption for carbon reduction within the public sector
provides no justification of forecasted movement towards this practice. Also the lack
of clear knowledge base in the practice, cemented by the literature study undertaken
in Leiyun, Ying and Burcu’s (2014) paper, is seen to revolt the industry practitioners
42
back to the standard methods of carbon and energy performance analysis. Highlighted
gathered over time, with many industry professionals showing a tendency to stay with
tried and tested methods. This reluctance for change was noted through the scoping
stage discussions and supported by the experiences of the interviewees who are
currently promoting LCA tools and BIM software.’ (Ariyaratne and Moncaster, 2014)
The guidance available from the GSA BIM programme (GSA, 2007) has provided the
North American construction industry with a base of support to feasibly stretch beyond
project practice, sustainable and environmental design, to find a place in the life cycle
decision making process from project teams (Section 5.1) (GSA, 2012). In the UK
carbon reduction is the main focus with the inclusion of a carbon budget. BIM is
feasibility decision process would be more suited to be driven by the project client and
based around the aims set out in the Government’s carbon goals. This would provide
a better use of the already established BIM progress with the Government mandate
and introduce digital technology to reach the wider industry carbon budget, rather than
individual project goals. However as noted in Section 5.1 the four inputs to the decision
loop requires significant contribution from project teams during preliminary phasing.
Therefore the increased collaboration between the client and project teams is essential
43
A major finding in the feasibility study during this research is the emphasis on the
requirement for additional software in energy and carbon modelling. An area missing
from the GSA (2012) guidance on this practice is the existence of training support and
how this has an impact on project team’s experience level and competence.
Within the UK the level of BIM knowhow and industry experience is annually
catalogued in the NBS BIM Report: BIM Survey (Malleson, 2014). This documents an
increase in BIM adoption throughout the years most importantly from the year in which
the Government mandate was produced (Malleson, 2014). Most notably is that 70%
of survey respondents source the information regarding BIM from colleagues and
other professionals (Malleson, 2014). Providing a notion that BIM users gain
completion.
The basis of individual project BIM creation is defined from the AEC (UK) BIM Protocol
(AEC (UK), 2012) document founded by the existence of industry standards. This
coupled with the BIS BIM Strategy’s (BIS, 2011) existence of contractual language
provides a more official stance in BIM adoption and provides the UK construction
industry with a comprehensive means of including BIM at all project levels. The
protocol performs a basis for a complete software generic solution to create models
and project information. However it notes, ‘a consistent software platform will aid the
Therefore the inclusion of additional energy modelling software would require some
44
collaboration and does not alienate the specialist users. It is also a recommendation
for generation of training solutions via the BIM and additional software protocols to lift
The final note warns the UK BIM movement that in order to move towards integrated
BIM and inclusion of BIM-based energy and carbon modelling. There is a requirement
to aim for a transparent direction for this practice in order to generate a software
support market which is noted to be setup in North America (GSA, 2012). A potential
method for this has already been discussed by the BIM Working Group (BIS, 2011).
In which an alliance may be formed to create parallel markets and to not leave the UK
7. Conclusion
The purpose of this research was to evaluate the progress of the UK Government’s
mandate for BIM adoption and following this provide a feasibility path for the
development of BIM have been compiled into one location. From this the identification
of the Government’s method of progress was noted. This took the shape of industry
trial projects in which three had featured BIM and had published case study
documents.
Following this discovery a means of which to evaluate the progress of the BIM
mandate was facilitated. Using the Government published case studies provided a
45
quality assurance in the reliability of the information source. However limited the study
to only three projects which does not allow a comprehensive valuable review.
Nevertheless the progress was noted in cost savings due to the inclusion of BIM at an
early stage during the new two stage open book procurement model. Yet surprisingly
be found. The particular importance of finding this progress was based on the inclusion
Following this the study into the feasibility of energy and carbon modelling was ignited.
Having identified the inclusion of this within the North American BIM guide series, this
would form the best practice document in which to base the feasibility study upon. The
North American guidance suggests a decision process in which project teams decide
on four elements; project team experience, budget and schedule, scope and detail
and availability of technology. The outcomes of these inputs decides whether the
execution of energy modelling is viable for the intended project. Following review of
this in light of the UK situation a series of recommendations from the researcher were
carbon design and align within the collaborative BIM movement to raise
3) Project teams should evaluate and decide the inclusion of energy and carbon
46
4) Provide transparent project energy and carbon reduction goals and provide
the process best suited to achieve this through a BIM Execution Plan.
The discussion into the findings of this research suggested that to aid in the inclusion
of BIM-based carbon and energy modelling the UK strategy should revaluate its tried
and tested means for carbon and energy calculation and potentially look to include this
within the scheduling (4D) section of BIM. This can be supported with the now
developed existence of carbon costing databases from life cycle analysis research.
The feasibility decision loop analysis contributed to the eventual realisation that the
collaborative efforts between the client and project teams. From the feasibility study
there is a realisation that the UK will require more stringent training into BIM processes
is to establish a software support market and to include solutions for software inclusion
To conclude the research provided findings which contributed to knowledge of the BIM
No existence of progress towards BIM use for energy and carbon modelling can
achieve clearance that this activity can be viable and in which phase to include.
47
Emphasis is found on additional software and knowledge to undertake this
push for training, software support and simulation and analysis usage protocol.
The next step in this research to provide overall value to the feasibility of BIM-based
energy and carbon modelling spawns from the limited knowledge of supporting
software. It is proposed to study the available software associated with this practice
and collate the information and usage into a software database. From this a
comparative study can be conducted to attempt to provide a review of the best found
software in combination to maximise the scope of BIM analysis. With this there is also
process. The overall aim of any future research into energy and carbon modelling is
pioneer the usage of this practice within the UK. Providing examples in order to
research best practice and formulate a proposal to include this within the widespread
BIM movement.
8. References
AEC (UK), (2012), ‘AEC (UK) BIM Protocol: Implementing UK BIM Standards for the
Architectural, Engineering and Construction Industry, Version 2.0, September 2012
[Online] Available at: https://aecuk.wordpress.com/documents/ (Accessed: 18th
November 2013)
Ariyaratne, C.I., Moncaster, A.M, (2014) ‘Stand-alone Calculation Tools are not the
Answer to Embodied Carbon Assessment, Energy Procedia 62, pp. 150-159, Science
direct [Online] ISSN 1876-6102, Available at:
http://www.sciencedirect.com/science/article/pii/S1876610214034079 (Accessed: 3rd
March 2015)
48
British Standards Institution (2007). BS 1192:2007 Collaborative production of
architectural, engineering and construction information – Code of practice. London:
British Standards Institution (Accessed: 19th January 2015)
Bryde, D., Broquetas, M., Marc Volm, J. (2013) ‘The project benefits of Building
Information Modelling (BIM)’ International Journal of Project Management 31 (7), pp.
971-980, Science direct [Online]. Available at:
http://www.sciencedirect.com/science/article/pii/S0263786312001779 (Accessed:
2nd October 2013)
Cabinet Office (2012a) Government Construction Strategy: One Year On and Action
Plan Update. London: Cabinet Office. Available at:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/61151/
GCS-One-Year-On-Report-and-Action-Plan-Update-FINAL_0.pdf
(Accessed: 7th February 2014)
Cabinet Office (2014a) Procurement trial case study: Cookham Wood Prison. London:
Cabinet Office. Available at:
https://www.gov.uk/government/collections/government-construction (Accessed: 12th
February 2015)
Cabinet Office (2014b) Procurement trial case study: New Prison North Wales.
London: Cabinet Office. Available at:
https://www.gov.uk/government/collections/government-construction (Accessed: 12th
February 2015)
49
Cabinet Office (2014c) Procurement trial case study: Property Services Cluster - iESE.
London: Cabinet Office. Available at:
https://www.gov.uk/government/collections/government-construction (Accessed: 12th
February 2015)
Department for Business, Innovation & Skills (2011) A report for the Government
Construction Client Group BIM Working Party Strategy Paper. July 2011, URN 11/948
(Accessed: 15th January 2015)
Hammond, G., Jones, C, (2011) Embodied Carbon: The Inventory of Carbon and
Energy (ICE). A BSRIA Guide, Bracknell: University of Bath, ISBN 978 0 86022 703 8
(Accessed: 2nd March 2015)
HM Government, Department for Business, Innovation & Skills, (2010) Low Carbon
Construction: Final Report. [URN/10/1266]. Available at:
https://www.gov.uk/government/publications/low-carbon-construction-innovation-
growth-team-final-report (Accessed: 13th February 2014)
HM Treasury, Department for Business Innovation & Skills (2011). The Plan for
Growth. London: ISBN 978-184532-842-9 Available at:
https://www.gov.uk/government/publications (Accessed: 7th February 2015)
50
Li, B., Fu, F.F., Zhong, H., Luo, H.B. (2012) ‘Research on the computational model for
carbon emissions in building construction stage based on BIM’, Structural Survey 30
(5), pp.411 – 425, Emerald Insight [Online] Available at:
http://dx.doi.org/10.1108/02630801211288198 (Accessed: 20th February 2015)
Lieyun, D., Ying, Z., Burcu A. (2010) ‘Building Information Modeling (BIM) application
framework: The process of expanding from 3D to computable nD’, Automation in
Construction 46, pp. 82-93, Science direct [Online] ISSN 0926-5805 Available at:
http://www.sciencedirect.com/science/article/pii/S092658051400096X (Accessed:
21st February 2015)
Malleson, A. (2014) ‘BIM Survey: Summary of findings’ NBS National BIM Report 2014
Available at: http://www.thenbs.com/topics/BIM/articles/ (Accessed: 1st January 2015)
Moffat, S.J, 21st March 2014, ‘The Benefits of BIM for the Life Cycle Reduction of
Carbon in Building Projects’, MEng (Hons) Civil Engineering, Edinburgh Napier
University, Honours Year Project (unpublished)
Nick Nisbet, buildingSMART News. (2010) ‘Getting the industry on-side with BIM: In
the author’s view’, buildingSMART UK Newsletter no.24, June 2010. Available at:
http://www.buildingsmart.org.uk/newsletter/2010-newsletters/buildingsmart-news-24-
2010-06/at_download/file (Accessed: 13th January 2015)
Trebilcock, P, (2015) ‘What is the cost of BIM?’, January 2015, Building.co.uk Online
Comment, Available at: Building.co.uk (Accessed: 15th January 2015)
U.S. General Services Administration, Public Building Service (2007). GSA BIM Guide
Series 01 – BIM Guide Overview. Washington, Available at: http://www.gsa.gov/bim
(Accessed: 9th January 2015)
U.S. General Services Administration, Public Building Service (2012). GSA BIM Guide
Series 05 – Energy Performance and Operations. Washington, Available at:
http://www.gsa.gov/bim (Accessed: 9th January 2015)
51