Drawing Control
Copyright © Aurizon 2013 - This document is for general information only and no part of this document may be reproduced, copied, altered or transmitted in
any form without the express written permission of Aurizon Operations Limited ABN 47 564 947 264 or its related entities (Aurizon). Aurizon does not
warrant, guarantee or make any representations regarding the currency, accuracy, correctness, reliability, useability, or any other aspect of material
contained in this document nor of material provided by others to Aurizon and contained in this document. Aurizon has no liability to any person in respect
of any loss or damage (including consequential loss or damage) which may be suffered or incurred or which may arise directly or indirectly in respect of
information contained in this document.
Document Approval
TITLE APPROVAL ROLE APPROVAL DATE
Table of Contents
1. PURPOSE AND SCOPE ........................................................................................... 4
2. PROCESS FLOWCHART.......................................................................................... 5
2.1 FLOW OF DRAWINGS FOR NEW BUSINESS ............................................................ 5
2.2 FLOW OF DRAWINGS DURING MAJOR OR COMPLEX DESIGN .................................. 6
2.3 FLOW OF DRAWINGS DURING MINOR DESIGN ....................................................... 7
2.4 FLOW OF DRAWINGS AFTER CONSTRUCTION ....................................................... 8
3. PROCESS DETAILS ................................................................................................. 9
3.1 REQUIREMENTS.................................................................................................. 9
3.1.1 Procedure for New Business Drawing 9
3.1.2 Procedure for Design Drawings 9
3.1.3 Procedure for Redrawing Existing Designs 13
3.1.4 Procedure for Standard and Mechanical Drawings 14
3.1.5 Procedure for Non-Design Changes to Drawings 14
3.1.6 Version Control of Drawing 14
3.1.7 Drafting Request Form 17
4. GENERAL INFORMATION ..................................................................................... 18
4.1 DEFINITIONS AND RESPONSIBILITIES .................................................................. 18
4.2 REFERENCE DOCUMENTS ................................................................................. 18
4.3 ASSOCIATED DOCUMENTS ................................................................................ 18
5. APPENDICES ......................................................................................................... 18
1. Signalling arrangements
4. Local panels
6. Points layouts
7. Mechanical devices
9. Control tables
2. Process Flowchart
2.1 Flow of Drawings for New Business
Request issue
of drawings for Drawings produced
scoping
Drawings
marked up for
proposal Drawings returned to
Design Production
Manager for drafting
Copy existing
Drawing check drawings to Working
directory for drafting
Transfer drawings to
Pending directory if
File hard copy Future Work
OR
Leave in Working if
project is certain
Resolve priority/staging
Client
with client
Plot or photocopy
required copies
Recipient
Project
Coordinator
Design Drafter
Plot or photocopy
required copies
Recipient
Drafting check
Asset
Issue Maintenance
for
maintenance
Update office copy TN & AS
plans copied
to Xsite
Achieve test copy and signed office copy and
register
3. Process Details
3.1 Requirements
3.1.1 Procedure for New Business Drawing
3.1.1.1 Requesting Signalling Drawings for Scoping and Estimating
The Manager New Business shall request the TLDP to issue existing drawings for scoping purposes.
3.1.1.4 Drafting
The Design Production unit have the following responsibilities in relation to drawings:
a) Copy the current drawings to the working state and create new drawings as necessary,
or assign current drawings to the working state if project is certain;
e) Check the drawings to ensure that only the required changes have been made and that
they have been made completely and accurately;
f) Forward both the superseded and new copies of the drawings to the Manager New
Business.
1. Consolidate the multiple jobs into one job with one Designer
2. Treat the different jobs as separate consecutive jobs where the design of a subsequent set
of modification shall not commence until the As-built drawings for the previous modification
have been checked and issued.
3. Specific approval from the Engineering Delivery Manager shall be sought by submitting a
Design Plan, which deals with the management of all risks associated with the specific
concurrent design/engineering project.
The Drafting Services unit have the following responsibilities in relation to drawings:
b) Checking the contents of the working and construction states of the ICS.
If there is existing work in progress, then the TLDP shall return the request to the Technical Coordinator
together with details of the work in progress. (Refer to section 3.1.2.2).
If there is no existing work in progress, the TLDP shall advise the Project or Technical Coordinator and/or issue
drawings for Design.
e) CAD check the drawings to ensure that only the required changes have been made and
that they have been made completely and accurately;
g) Forward both the out of date and new copy of the drawings to the Designer
2. Photocopy construction copies, which must include one copy on Pink paper. The Pink
copy is the Test Copy.
3. The Construction copies may be bulk plotted, in which case signatures are to be inserted
electronically prior to plotting.
5. The original signed hard copies are to be filed in the “Works in Progress” cabinet.
6. Prepare appropriate transmittal, listing new, altered or cancelled drawings and enter
details in the drawing control record and forward as requested by the Project or Technical
Coordinator.
1. Authorise a drafter to change the relevant drawings from the construction state to the
working state;
2. Enter the project sub-description change and increase the version number alphabetically
e.g. 1A to 1B;
4. CAD check the drawings to ensure that only the required changes have been made and
that they have been made completely and accurately;
5. Transfer the necessary Title Block signatures in accordance with section 3.1.2.5.4.
2. CAD check the drawings to ensure that only the required changes have been made and
that they have been made completely and accurately;
3. Ensure that the changes for each stage are coloured in accordance with Circuit
Modification Mark-ups;
4. Transfer the necessary Title Block signatures in accordance with section 3.1.2.5.4; and the
drawings are reissued in accordance with section 3.1.2.5.4.
3. Submitting any drawing suspected of being incorrect to the Engineering Delivery Manager
for Design Checking
4. Ensuring redrawn drawings can be identified by entering “Redrawn from the Original” into
the description field in the title block
3.1.3.2 Signing
The drafter shall update the Title Block Description on the next available line with the next sequential number
and a text description of the work and alter the Version number to match that shown in the title block. The CAD
version number shall be reset to 001 for the first round of alterations. E.g.: -
No. DE 64
Description
SHEET
NUMBER
103
VERSION
2A
001
2A
Straight Rd. LX
1
Original
No. DE 64
Description
SHEET
NUMBER
103
VERSION
2A
002
2A
Straight Rd. LX
1
Original
No. DE 64
Description
SHEET
NUMBER
103
VERSION
2A
003
2A
Straight Rd. LX
1
Original
No. DE 64
Description
SHEET
NUMBER
103
2B VERSION
Speed increase to 100kph 2B
001
2A
Straight Rd. LX
1
Original
Each major change shall be shown and shall receive the next sequential sub-description letter. E.g.: -
No. DE 64
Description
SHEET
2C NUMBER
Convert to half booms
103
2B VERSION
Speed increase to 100 kph 2C
001
2A
Straight Rd. LX
1
Original
No. DE 64
Description
SHEET
NUMBER
103
VERSION
2 2
Straight Rd. LX 001
1
Original
4. General Information
4.1 Definitions and Responsibilities
The following definitions and responsibilities apply throughout this document:
TERM DEFINITION/RESPONSIBILITY
Manager
The Manager Signalling and Operational Systems has
Signalling and
responsibility and authority for determining the requirements of
Operational
this document.
Systems
The designated Line Mangers are responsible for ensuring the
Line Managers
implementation of, and adherence to, this procedure.
TLDP Team Leader Design Production
5. Appendices
Nil.