Professional Documents
Culture Documents
RIGGING DEPARTMENT
THINK SAFE
DO SAFELY
SAFETY FIRST
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
17 July
A Issued For Review HaGun SAFETY CM
2011
TABEL OF COUNTENT
CHAPTER 1
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 2 of 14
TABLE OF CONTENT
1 GENERAL ...........................................................................................................................4
2 PURPOSE ..........................................................................................................................4
3.2.2 Job Safety Assessment (JSA) must be carried out for all crane lifts and all other
tasks that have potential risk to personnel of equipment. ....................................................4
3.2.3 Install scaffolding where necessary to install bolt in trestles / support legs
connection...........................................................................................................................4
3.2.5 Lift briefing and Safety briefing before any lift; assign responsibility to all personnel
involved. (Hand signals, Rigger to crane driver, etc.) ..........................................................4
3.2.6 Insure all equipment required for installation is on hand and in position before lift
i.e. Chain blocks, Level blocks, Podgy, Drifts, Hammer, Spanners. Etc. ..............................4
3.2.9 Set up safety rope around lifting area of Separator Tank area and put notice
board entered “KEEP OFF EXCEPT PERSONEL CONCERNED”. .....................................4
4 RESPONSIBILITY...............................................................................................................5
7.2.1 Moving Separator Tank from lay down to site area. ...............................................8
7.2.5 Put the object on the surface of the work floor for stabilization ............................. 13
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 4 of 14
1 GENERAL
This procedure provides information about the erection of Separator Tank at REINJEKSI
FLUIDA PANAS BUMI UNIT-IV 20MW Project.
2 PURPOSE
This Procedure is to make sure that all people involve in the erection, assembly and
welding of Separator Tank activity understand and familiar to doing the work with quality
control system for getting quality result as per client specification and requirement,
drawing, standard and code.
3 GENERAL NOTE
3.1 Inspection
As per the works required inspection, carry out inspection under attendance of
Superintendent / Engineer and as surreally record is result.
3.2 Safety
3.2.1 A safety officer presents all times Safety Briefing.
3.2.2 Job Safety Assessment (JSA) must be carried out for all crane lifts and all other tasks
that have potential risk to personnel of equipment.
3.2.3 Install scaffolding where necessary to install bolt in trestles / support legs connection.
3.2.4 Pre lift study before any lifting activity.
3.2.5 Lift briefing and Safety briefing before any lift; assign responsibility to all personnel
involved. (Hand signals, Rigger to crane driver, etc.)
3.2.6 Insure all equipment required for installation is on hand and in position before lift i.e.
Chain blocks, Level blocks, Podgy, Drifts, Hammer, Spanners. Etc.
3.2.7 Tag lines must be used to control lift.
3.2.8 Ground conditions must be ready before activities.
3.2.9 Set up safety rope around lifting area of Separator Tank area and put notice board
entered “KEEP OFF EXCEPT PERSONEL CONCERNED”.
3.3 Lifting
All conditions adapted to the lifting procedure. Prior to commencement of lifting works,
assuredly carry out check of lifting equipment.
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 5 of 14
4 RESPONSIBILITY
5 BASIC REQUIREMENT
The Packing List should indicate the quantity of the material and equipment supplied and
its specification as described in the erection drawing. This will also indicate the size and
the total weight of the component and the method of storage. Also the packing number
and material coding is very essential.
5.4 Storage Area and Warehouse
Upon a thorough check on the drawing and the packing list, the quantity of materials and
equipment is already known, including the method of storing, the size of the storage area
and the warehouse can be identifies.
5.5 Resources
Identification of resources is integral part of planning and scheduling is the most essential
part of the basic requirement in undertaking REINJEKSI FLUIDA PANAS BUMI UNIT-IV
20MW Project in particular and in all jobs in general. Resources means, the materials,
labour and equipment needed to perform REINJEKSI FLUIDA PANAS BUMI UNIT-IV
20MW Project.
6 PREPARATION WORK
It is assumed in this procedure that before starting the erection of the Separator Tank, the
supporting structure were already erected and checked by others and clearance to proceed with
the Separator Tank System erection had been obtained.
The following sequences are for reference only. During actual field assembly, refer to lifting
procedure and erection drawing (Rigging plan).
7.1 Preparation
Make sure the job site in a safe condition for the installation work, in accordance with the
requirements of Health Safety Environment department.
Prepare equipment and materials that will be done.
All equipment in good condition. In accordance with the Safety Equipment Checklist.
All man power associated with lifting and installation job, certainly in good health.
Make sure if the main frame for support of Separator Tank in ready for supporting.
Make sure that if the rough terrain crane 75 ton in good condition. In accordance with the
results inspection crane safety checklist. This use for main crane for lifting.
Make sure that if the rough crane 45 ton in good condition. In accordance with the
results inspection crane safety checklist. This use for main crane for tailing.
Ensure the use of 20 millimetre thick steel plate to the floor where the position of out
rigger cranes for work.
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 8 of 14
Figure 1
These activities:
1. Separator Tanks were taken from the lay down to the job site using a low bed.
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 9 of 14
2. After arriving at work sites, Separator Tank will be derived from the low bed using Rough
terrain crane 75 tons and Rough terrain crane 45 tons.
3. Connected all sling to Separator Tank.
4. All connected must be safety, refer to Safety lifting checklist.
5. Lift Separator Tank until 1 meter up to low bed.
6. Low bed moves left the job site.
7. Separator Tank is placed on the work floor.
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 10 of 14
Figure 2
These activities:
1. Prepare a Rough terrain crane 75 tons out rigger cranes and Rough terrain crane 45
tons at the work site.
2. Make sure conditions are safe cranes for lifting jobs.
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 11 of 14
3. Crane placed on the safe radius for the appointment, in accordance with the crane load
chart provided by the factory cranes.
4. Separator Tank connected to the crane by a sling and Shackle.
Figure 3
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 12 of 14
These activities:
1. Lift the Separator Tank until 1 meter up to the level before.
2. Rough terrain crane 45 tons stop lifting.
3. Rough terrain crane 75 tons is continued to lift.
Figure 4
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 13 of 14
These activities:
1. Continue tailings so that the Separator Tank is in the position of 90 degrees.
7.2.5 Put the object on the surface of the work floor for stabilization
Figure 5
These activities
1. Lift the object up to 1 meter above the drift in Separator Tank support.
Method Of
Work-
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 14 of 14
CHAPTER 2
Job Safety
Assessment
Procedure
Document Number
Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002
Separator Tank Page 2 of 10
TABLE OF CONTENT
1 GENERAL ...........................................................................................................................3
2 DEFINITIONS .....................................................................................................................3
3 RESPONSIBILITIES ...........................................................................................................4
5 NOTICE ............................................................................................................................ 10
Job Safety
Assessment
Procedure
Document Number
Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002
Separator Tank Page 3 of 10
1 GENERAL
This document applies to all employees and Contractors of Gaka Karya Engineering, and
full compliance is required by 17 July 2011, in the erection of Separator Tank at
REINJEKSI FLUIDA PANAS BUMI UNIT-IV 20MW Project.
2 DEFINITIONS
Task A segment of work that requires a set of specific and distinct actions,
which has a definable goal or outcome.
Job A specific task that is performed in a particular location. A job’s hazards
are a combination of the task hazards and the work area hazards.
Minor Job A task of negligible risk (typically a single step) that is planned to be
performed in a work area such that it:
does not involve moving off a walkway,
is within handrails,
does not have the potential to make contact with moving parts or
hazardous substances (i.e. no additional PPE),
does not require isolations, and
Does not require additional support equipment (e.g. ladder,
scaffolding, harness).
For example:
Opening or closing a Valve.
Visual inspection of equipment.
Lubrication.
Plant cleaning, where no isolation is required.
Non-intrusive condition monitoring etc.
JSA Job Safety Analysis is a structured risk assessment used for tasks of
substantial size; ideally developed by those conducting the work.
TBRA Team Based Risk Assessment. A risk assessment structured that is
used for complex and high hazard situations on work.
Standard Procedure A document, which contains detailed instruction regarding a
particular task (routine or non-routine) and will over time, come to
Job Safety
Assessment
Procedure
Document Number
Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002
Separator Tank Page 4 of 10
contain a risk assessment document (where there is any risk other than
negligible). The types of Standard Procedures include:
Standard Operating Procedure held in Document Management
System.
Standard Maintenance Procedure / PM’s / Work Orders that are
used on a scheduled or as needed basis.
A personal safety check, completed by an individual, and which identifies hazards and
encourages review of risks before carrying out a task.
3 RESPONSIBILITIES
3.1 MANAGERS
Managers shall ensure compliance with this guide manual within their area of
responsibility
3.2 SUPERVISORS
Supervisors shall:
1. Ensure their personnel are competent in basic risk assessments and comply with
the requirements of this guide manual.
2. Ensure all tasks are risk assessed in accordance with this guide manual.
3. Authorise JSA’s that are used to create or revise Standard Procedures.
3.3 RESPONSIBLE OFFICER
The Responsible Officer (RO) shall:
1. Ensure Contractors have an adequate risk assessment in accordance with this
guide manual.
2. Review and endorse (by signature) all JSA’s, Standard Procedure or other generic
risk assessments to be used. This task-based risk document is then supplemented
by risk assessing the hazards associated with the work environment just prior to the
work by:
a. updating the JSA
b. working under a new Work Permit
3.4 PERMIT AUTHORISER
The Permit Authoriser shall:
Job Safety
Assessment
Procedure
Document Number
Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002
Separator Tank Page 5 of 10
1. Ensure risk assessment for the task is adequate before authorizing the Work
Permit.
2. Understand the hazards and controls that have been put in place to minimize the
risk of incidents.
3. Discuss additional area specific hazards and controls with the Permit Holder as
identified on the new Work Permit or ensure that these are identified by “Take 5”
or revised JSA.
3.5 PERMIT HOLDER
The Permit Holder shall:
1. Ensure the appropriate level of risk assessment for the type of job is completed.
2. Walk through the work area escorted by an operational person if they are not
familiar with the hazards and layout.
3. Ensure all hazard controls are maintained during the task and personnel working
on the task follow the requirements of all the risk management documentation:
Standard Procedures (SOP’s, PM’s, Work Orders), JSA, Work Permit
3.6 TEAM MEMBERS (WORKERS PERFORMING THE TASK)
The Team Members shall:
1. Participate in developing risk assessment or read, review and include any
additional risk controls to existing JSA / Standard Procedure / Work Permit.
2. Understand the hazards and controls that have been put in place to minimize the
risk of incidents and their responsibility in maintaining those hazard controls.
3. Where a JSA risk assessment is used, write the date, their name and sign onto the
document before commencing the task every day / shift they are on that task to
indicate their acceptance to work in line with the risk assessments on the job.
3.7 SAFETY ADVISOR AND TRAINING IMPROVEMENT COORDINATOR
The Safety Advisor and Training Improvement Coordinator shall:
1. Provide support to all aspects of the risk assessment process.
2. Audit risk assessments in their area of responsibility to ensure compliance with
this guide manual.
3. Facilitate JSA’s is being absorbed into Standard Procedures.
4. Deliver Basic Risk Assessment training sessions.
5. Approve use of a contractor’s own format of risk assessment (Safety Advisor and
Shift Supervisors only).
Job Safety
Assessment
Procedure
Document Number
Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002
Separator Tank Page 6 of 10
Step 2
Using the JSA worksheet, break down the job into logical steps and in
the correct sequence that the work will be carried out
Step 3
Identify all the hazards in each step
Step 4
Develop Hazard Controls required
Step 5
Measure the Residual Risk
Step 6
Sign JSA Acknowledgement Sheet
Step 7
Review and Update the JSA
Step 8
File the JSA
Job Safety
Assessment
Procedure
Document Number
Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002
Separator Tank Page 7 of 10
DESCRIPTION
CONSEQUENCE
Injury / Illness Environment
Insignificant Minor Injury / Illness Little or no environmental impact
Minor Medical Treatment Injury / Illness Small and/or localized impact
Moderate Restricted Duties Injury / Illness Substantial environmental impact
Major Lost Time Injury / Illness Serious environmental impact
Fatality or Permanent Disability Injury / Widespread environmental
Catastrophic
Illness impact
Table 1 – JSA Risk Assessment: Consequence, Likelihood and Risk Ranking Definitions
b. The risk ranking is then used to determine those risks that have an
“acceptable” level of risk i.e. are controlled.
c. An Extreme risk outcome is not acceptable and the job cannot commence.
Risk rank scores of Extreme require additional risk reduction strategies to
be implemented. Risk rank scores of High need to be highlighted to both
the workers in the team and the Permit Authorizer.
d. Responsible Officers shall be made aware of any High risk work planned
by the Contractors.
e. Potential work that results in an Extreme risk ranking shall not go ahead.
Additional hazard controls need to be implemented. If these are not known
to those planning to undertake the work, an additional risk assessment tool
is required, such as Team Based Risk Assessment. The Business Unit
Manager (or their designate) shall authorize the outcome of the TBRA as it
relates to the planned work.
The only exception to this is confined space activities where JSA’s shall be
retained for 5 years as required under legislation.
As a business decision, once the JSA has been used on the task, the JSA is to be
retained as a controlled document in CSBP’s Document Management System for
future reference. Refer to Section 10: JSA’s and Standard Procedures for further
details
5 NOTICE
The other things which not be coverage and included in this regulation will be added and
described in the other documents.
SAFE WORK METHOD STATEMENT
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 1 of 8
CHAPTER 3
SAFE WORK METHOD STATEMENT
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 2 of 8
Prepared by:
HaGun
Gunawan
Hg
Gunawan, H
HaGun Gunawan
Date safe work method prepared: 17 July 2011 Date work to be commenced:
SAFE WORK METHOD STATEMENT
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 3 of 8
Personnel qualification & experience required: Engineering details/certificates authority approval required:
Crane Operators, Riggers, Protection Officer, Supervisors, Labourers Lifting Assembly to be fully certified. Anti Drop valves to be fitted to
excavator.
RISK
POTENTIAL RANKING HAZARD CONTROLS WHO WILL
ITEM WHAT ARE THE BASIC STEPS HAZARDS 1 (H), 2 ENSURE THAT
(What controls can be put in place to prevent an injury/illness)
(What may cause an (M), OR 3 THIS IS DONE
N.B. Control measures must not raise or create an increased risk
injury/illness to occur)
(L)
Plant in unsafe
condition All work group to be made aware of scope of
1 Daily Pre-Start Safety Brief All personal
causing slips works
trips, falls
Electro
3 Start up plant Plant Operators
conduction
Ensure that Live Overhead Traction Obtain Isolation & “C” Form before Green Card
4 Wires at Stable Swamp Creek have commencing work. Holder.
been isolated Supervisor
Fall from
10 Remove lifting chains from Separator Ensure dogman is wearing safety harness Gaka Personnel
Separator
Tank attached to static line on Separator Tank.
Tank
11 Repeat steps 7-9 until all 2 Separator Gaka Personnel
SAFE WORK METHOD STATEMENT
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 8 of 8
Limb injuries
Ensure good manual handling techniques
13 Move temporary fencing back to from poor Foreman S2K
are employed and communicated to all
original position manual
workers
handling
RISK MANAGEMENT SAFE WORK
METHOD STATEMENT (SWMS)
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 1 of 7
CHAPTER 4
RISK MANAGEMENT SAFE WORK
METHOD STATEMENT (SWMS)
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 2 of 7
RESORCES:
Equipment Used:
Trades Involved: Riggers. Crane Operators Relevant certificates of competency and General Induction certificate. Pink card.
Maintenance checks: Current lifting chain test certificates, all crane log books to be up to date.
Materials used: Rigging equipment, Appropriate warning signs & Barricade tape. Relevant tag line.
Relevant Personnel Protection Equipment required: Hard hats. Steel caped safety boots, Harness with double lanyard, eye and sun protection. High
vies clothing or vests, Gloves.
LIST THE RELEVANT OHS ACT and REGULATIONS: LIST THE RELEVANT CODES OF PRACTICE APPLICABLE TO YOUR WORK:
CONSEQUENCE
PROBABILITY
Steps (where practical in associated with each we currently have in high add additional
RANKING
sequence) step. place to address the controls and nominate
Examine each to find identified hazard for each Person/s
possibilities that could job step Responsible.
lead to an incident Conduct a risk
involving injury. assessment utilising the
Equipment damage or attached Matrix
environmental harm.
Toolbox meeting and Not understanding the job in Ensure all personnel involved All work to carry out by Gaka personnel
signing of JSA in relation hand in the unloading and qualified personnel.
to the unloading and positioning of Separator Tank No unauthorised personnel
positioning of Separator understand procedure and permitted in the work area.
Tank units. sign SWMS Gaka personnel to clearly
Boom configuration identify all potential
Weight of load being underground and over
lifted Separator Tank head hazards and services
units. in relation to work and
Radius required: 8m. access areas of crawler
Boom length: 33.5m. cranes and relevant
Rough terrain crane 75 transport.
SWL @ 12m 39.9t
Note; weight of lifting
hook, lifting equipment
and spreader to be in
overall weight.
RISK MANAGEMENT SAFE WORK
METHOD STATEMENT (SWMS)
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 4 of 7
Use of relevant PPE Equipment failure Personnel Ensure that all personnel are PPE required; eye Gaka personnel
equipment and up to date injury crushing and pinch trained and competent in the protection, safety boots,
Pink card points. Back strain, Muscular relevant use of PPE. sun protection, hard hats,
injuries, and falling objects. Ensure all relevant PPE and harness with double
equipment is used at all times. layer high vis vests and
Harnesses are to be worn and cover all.
lanyards attached at heights All personnel working on
greater than 2m or in the ground and round plant or
event of no edge protection or machinery are to wear
risk of falling exists. high vis clothing or vests.
All personnel to comply
with Pink card induction
requirements.
Ensure that all GAKA
personnel are conversant
with GAKA safe working
policies
Establish exclusion zone. Falling objects and protection All loads to be contained No unauthorised access Gaka personnel
of site personnel and public. within exclusion zone Gaka to will be permitted into areas
notify of required exclusion during the rigging and de-
zone and notify site personnel rigging of the rough terrain
of work activity. crane 75.
Exclusions zones to be
barricaded of using If access is required during
appropriate signage & the lifting of units, Gaka
barricading tape to ensure an personnel are to be
exclusion zone is set. notified of access.
All loads are to be slung
and directed by a qualified
rigger or Dogman.
RISK MANAGEMENT SAFE WORK
METHOD STATEMENT (SWMS)
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 5 of 7
Manual handling Back strain, Muscular injuries Seek assistance if required, Ensure that all Gaka Gaka personnel
use correct manual handling personnel are conversant
techniques. with Gaka safe working
policies.
Organize communication Communications Failure to All two way radios to be Riggers to carry or have Gaka personnel
understand directions tested before starting. access to fresh battery
when required, whistle to
be used in the event of
radio failure.
Establish rough terrain crane Ground failure, Structural Crane to be set up as per An audible wind speed Gaka personnel
75 at required radius from failure, and personnel injury. manufactures specifications. indicator is installed to
centre of rift on head stocks. indicate if wind speed is
Riggers to observe position of too great to continue lifts
boom at all times when safely, Operator to monitor
working in close proximity to conditions and to notify
overhead obstructions. relevant supervisors.
Crane counters weight radius Impact of counter weight Check swing radius and Gaka personnel to clearly
and clearance. resulting in load swing or sling clearances. identify all potential
breakage and catastrophic underground and over
load fall. head hazards and services
in relation to work and
Ground conditions. Crane base tracks sink Ground compaction report to access areas of crawler
resulting in uneven lift, load be supplied before the setting cranes and relevant
shift and excess boom stress up of crawler crane, use steel transport.
and collapses. ground pads under crane
tracks.
RISK MANAGEMENT SAFE WORK
METHOD STATEMENT (SWMS)
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 6 of 7
Check all lifting gear and Mechanical Failure, Personal All lifting equipment must be Any lifting equipment that Gaka personnel
relevant equipment on rough injury, sling breaks, load checked and tagged current. has been supplied by other
terrain crane 75 required for drops, and boom collapses. Any faults must be reported parties is to be compatible
lift being performed immediately to site supervisor. for required lifts and to be
All loads are to slung and of Australian Standards
directed by a qualified rigger and have required test
or dogman certificates.
Attach lifting equipment to Structural failure, personnel Ensure all personnel involved All loads are to be slung Gaka personnel
required lift as per injury, and inclement weather in the lifting of the Separator and directed by a qualified
manufactures specified lifting conditions. Load Falls from Tank understand the rigger.
points on Separator Tank. height. procedure and sign SWMS.
All work to be carried out
Harnesses are to be worn and by qualified personnel.
Lugs on units not suitable to lanyards attached at heights
take the weight of the load on greater than 2m or in the No unauthorised personnel
the lift being performed. event of no edge protection or permitted in the work area
risk of falling exists. or access onto crane.
In the event of any deviation Stop all work activities Hold a toolbox meeting record To be authorised by Gaka Gaka personnel
from this Safe Work Method and adjust SWMS variations safety representative
Statement
RISK MANAGEMENT SAFE WORK
METHOD STATEMENT (SWMS)
Rev. : A
Document Number 17 July 2011
INSTALLING SEPARATOR TANK
GKE-HG-RIG-0002 Page 7 of 7
THIS SWYIS HAS BEEN DEVELOPED THROUGH CONSULTATIONS WITH LCR EMPLOYEES AND HAS BEEN READ AND UNDERSTOOD
THEN SIGNED BY ALL EMPLOYEES INVOLVED WITH THIS ACTIVITY
RIGGING DEPARTMENT
THINK SAFE
DO SAFELY
SAFETY FIRST
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
RIGGING DEPARTMENT
ANALYZE AND PLANED ACTIVITY FOR
LIFTING AND ERECTION WORK
START
DATA MATERIAL
1. DIMENSION
2. WEIGHT
REFERENCE
1. RIGGING BOOK
2. EQUIP. MANUAL
3. B30.24-2003 Safety Standard
4. B30.21-2005 manually lever operated hoist
5. Australian Standard, AS 3569--1989, Wire ropes
6. Australian Standard, AS 2759--1985, Wire ropes
7. NAVFAC P-307, June 2003
8. Construction Industry Crane Safety Summit, 2009
Yes
NEED DUO CRANE
No TAILING DESIGN
MONO CRANE
Risk
JOB SAFETY ANALISYS
Safe
RIGGING PLAN
ACTION
CONTROL
Final Inspection by No
GKE & IKPT
Yes
Prepare Final Report for ApprovaL
Handover
FINISH
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
RIGGING PROCEDURE
01. OBJECTIVE
Rigging Study of INSTALL Separator
03. REFERENCE
1. PT GAKA KARYA ENGINEERING RIGGING DEPARTMENT REFERENCE
04. EQUIPMENT
No Equipment Qty Capacities Remark
01 MOBILE CRANE 1 unit 75 ton New
02 MOBILE CRANE 1 unit 30 ton New
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
SEPARATOR INSTALLATION
PREPARING ACTIVITY IN SITE LAY DOWN ACTIVITY
START
Cleaning Separator
Inspection Quality No
by QC & Safety
Yes
Connected all Sling
for Lifting
Lifting Separator
by RawLer Crane
ERECTION ACTIVITY
to Target Elevation
From ELev. 0.000
FINISH
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
ER
ET
M
,5
=4
R
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
ER
ET
M
,5
=4
R
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
ER
ET
M
,5
=4
R
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
ER
ET
M
,5
=4
R
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
ER
ET
M
,5
=4
R
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
TILING CRANE
CRANE MOBILE
CRANE TYPE Terex RT230
CAPACITIES 30 ton
DIMENSIONS IN MILLIMETERS
APPROVED. BY
PREPARED BY PT. GAKA KARYA ENGINEERING
PT IKPT
H GUNAWAN
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 1 of 10
CHAPTER 6
Rigging Tools
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 2 of 10
TABLE OF CONTENT
3 POLYESTER ROUND SLINGS & FLAT WEB SLINGS QUALITY AUSTRALIAN MADE ....6
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 3 of 10
http://www.activelifting.com.au/liftingEquipment/slingsWireRope.htm
METHOD
OF
LOADING
2.8
11 1.5 1.1 0.74 2.8 2.7 2.6 2.1 1.5 2.7 2.6 2.1 1.5 5.4 5.1 4.1
3.5
12 1.8 1.3 0.88 3.4 3.1 3.0 2.5 1.8 3.1 3.0 2.5 1.8 6.5 6.1 4.9
4.1
13 2.1 1.5 1.0 3.9 3.8 3.6 2.9 2.1 3.8 3.6 2.9 2.1 7.6 7.1 5.9
4.8
14 2.4 1.8 1.2 4.6 4.4 4.2 3.4 2.4 4.4 4.2 3.4 2.4 8.8 8.2 6.7
6.2
16 3.1 2.3 1.6 4.9 5.7 5.4 4.4 3.1 5.7 5.4 4.4 3.1 11.5 10.7 8.8
7.9
18 4.0 3.0 2.0 7.6 7.3 6.8 5.6 4.0 7.3 6.8 5.6 4.0 14.5 13.7 11.2
9.8
20 4.9 3.7 2.4 9.4 9.0 8.4 6.9 4.9 9.0 8.4 6.9 4.9 18.0 16.9 13.9
11.8
22 5.9 4.4 3.0 11.4 10.8 10.2 8.3 5.9 10.8 10.2 8.3 5.9 21.9 20.5 16.7
14.1
24 7.0 5.3 3.5 13.6 12.9 12.2 9.9 7.0 12.9 12.2 9.9 7.0 25.9 24.3 19.9
16.5
26 8.3 6.2 4.1 15.9 15.3 14.3 11.6 8.3 15.3 14.3 11.6 8.3 30.5 28.6 23.4
19.2
28 9.6 7.2 4.8 18.4 17.7 16.6 13.5 9.6 17.7 16.6 13.5 9.6 35.4 33.2 27.1
25.1
32 12.5 9.4 6.3 24.1 23.1 22.0 17.6 12.5 23.1 22.0 17.6 12.5 46.3 43.3 35.4
31.7
36 15.8 11.9 7.9 30.6 33.1 27.0 22.0 15.8 33.1 27.0 22.0 15.8 58.6 54.9 44.8
39.0
40 19.6 14.7 9.8 37.7 36.1 34.0 28.0 19.6 36.1 34.0 28.0 19.6 72.2 67.7 55.3
47.3
44 24.0 17.7 11.8 45.7 43.7 41.0 33.0 24.0 43.7 41.0 33.0 24.0 87.4 81.9 66.9
56.5
48 28 21.0 14.0 54.6 52.2 49.0 40.0 28.0 52.2 49.0 40.0 28.0 104.4 97.8 79.9
66.1
52 33.0 25.0 16.6 63.8 61.1 57.0 47.0 33.0 61.1 57.0 47.0 33.0 122.2 114.6 93.6
76.6
56 38.0 29.0 19.2 74.0 70.8 66.0 54.0 38.0 70.8 66.0 54.0 38.0 141.6 132.6 108.3
88.0
60 44.0 33.0 22.0 84.8 81.2 76.0 62.0 44.0 81.2 76.0 62.0 44.0 161.5 152.3 124.4
Rigging Tools
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 4 of 10
http://www.activelifting.com.au/liftingEquipment/shackles.htm
Material: body and pin high tensile steel, quenched and tempered.
Safety factor: 6 times W.L.L. = minimum breaking strength.
Generally conforms to AS 2741
Anchor Shackle with Chain Shackle with Safety Anchor Shackle Safety Chain Shackle
screw pin bow screw pin Dee bolt type bow bolt type Dee
INSIDE LENGTH
INSIDE WIDTH APPROX. WEIGHT
WORKING LOAD LIMIT DIA BOW DIA PIN CHAIN ANCHOR
WIDTH OF BOW EACH
TYPE TYPE
D d a C C 2r in kgs
0.33 5 6 10 22 16 0.02 -
0.5 6 8 12 29 20 0.06 0.07
0.75 8 10 13.5 27 32 21 0.11 0.13
1 10 11 16 31 36 26 0.15 0.17
1.5 11 13 18 37 43 29 0.21 0.25
2 13 16 22 43 51 32 0.37 0.44
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 5 of 10
Grade S Shackles are used in lifting applications as removable links to connect wire rope
chain and other fittings.
Screw Pin Shackles are mainly used for non permanent applications.
Bolt type Shackles are used preferably for long term or permanent applications and in
circumstances where the pin of the shackle may rotate during loading.
Dee Shackles are used mainly in a one-leg system while bow shackles are used in multi-
leg systems.
Rigging Tools
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 6 of 10
3 POLYESTER ROUND SLINGS & FLAT WEB SLINGS QUALITY AUSTRALIAN MADE
http://www.activelifting.com.au/liftingEquipment/polyesterRoundSlings.htm
CODE MM CODE MM KG KG KG KG KG
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 7 of 10
http://www.activelifting.com.au/liftingEquipment/3GindustrialChainBlock5tonne.htm
The latest range of colour coded 3G Industrial Chain Blocks from Active Lifting offer you a new
system of identification for hoisting and lifting that makes choosing the correct capacity block
much easier and safer.
This is particularly important when working in harsh or muddy environments where rated
capacity 'ID' plates on this type of equipment can become obscured or severely damaged.
Our 3G Industrial Chain Blocks are ideally suited to applications in the mining, construction,
engineering and logging industries.
The colors in this range have been matched to those used for synthetic lifting slings to ensure a
standardizing of colors for lifting products in the capacity needed to be used.
Features:
The 3G Industrial Chain Block has improved design features to ensure full protection of
the vital gears, shafts and bearings.
The side covers are made from reinforced heavy duty steel.
The load chain is calibrated alloy Grade T(80) material which guarantees safety when
lifting loads, and the chain is marked according to AS1418.2.
The industrial strength bearings ensure minimum lifting effort even under full load.
Hand chain is supplied electro-galvanised (silver) finish.
Superior Weston type friction braking system with high strength twin pawls for additional
safety.
Roller chain guides top and bottom to help eliminate tangling and jamming of the load
chain, ensuring trouble-free service.
Revised design ball bearing retention system on top and bottom hooks to ensure a safe
coupling. Both hooks swivel and are complete with safety catches.
Rigging Tools
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 8 of 10
Traceability of each 3G Chain Block is by means of an individual serial number, which co-
relates directly to the test certificate.
Each 3G Chain Block is individually tested to its rated capacity and is supplied with a test
certificate.
'ID' plates and rivets are supplied in stainless steel material in order to avoid dangerous
sparking.
Yellow plastic Safety and Warning cylinder supplied with all Chain Blocks.
A comprehensive range of spare parts are available, complete with full repair facilities
and re-testing to NATA specifications.
Complies with AS1418.2
Standard Lift 3m
Falls of Chain 2
Clearance Dimensions
A (Headroom) 620
B (Width) 240
C (Depth) 178
D (Diameter) 218
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 9 of 10
http://www.activelifting.com.au/liftingEquipment/ModelSB900-GchainLeverBlock9tonne.htm
This high capacity Active Lifting Chain Lever Block is an extremely efficient, versatile and
portable hand operated hoisting unit which has been designed for tensioning, securing, pulling,
towing and lifting. Active Lifting Chain Lever Blocks have a wide application in industries such as
mining, shipbuilding, construction, engineering and logging.
Features:
The Chain Lever Block is made of steel: Mechanism and gears are enclosed in a robust
steel compact shell.
The load chain is made of high resistance, alloy steel Grade T(80), black finish, heat
treated and calibrated.
Weather protected automatic Weston brake that works with load pressure and a sprocket
wheel that incorporates twin pawls for added safety.
All gears and shafts run on roller bearings.
The short arm lever and the particular gear ratio allows minimum effort to raise
maximum load with maximum security.
Freewheeling gear system, giving greater ease of operation.
Top and bottom hooks swivel and come complete with safety catches.
Traceability of each 3G Industrial Chain Lever Block is by means of an individual serial
number, which is stamped on the identification side plate - this number relates directly to
a test certificate.
Every Chain Lever Block is operationally tested to its rated capacity and comes with a
test certificate.
'ID' plates and rivets are supplied in stainless steel material in order to avoid dangerous
sparking.
Rigging Tools
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 10 of 10
A comprehensive range of spare parts are available, complete with full repair facilities
and re-testing to NATA specifications.
Complies with AS1418.2
A 200
B 122
Dimensions mm C 338
67
E 53
Net Weight kg 45
Critical Lift
Worksheet
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 1 of 6
CHAPTER 7
Critical Lift
Worksheet
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 2 of 6
TABLE OF CONTENT
Title: Date:
Description:
Jobsite Address:
Notes:
Notes:
Notes:
Counterweigh: Description:
Jib:
Hook Block:
Shackle Capacity
Notes:
Title: Date:
Critical Lift
Worksheet
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 5 of 6
Notes: Notes:
Pre-Lift Checklist
Communication Method:
Other Considerations:
Critical Lift
Worksheet
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 6 of 6
Signatures
Engineer:
Supervisor:
Operator:
Client:
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 1 of 21
CHAPTER 8
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 2 of 21
TABLE OF CONTENT
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 3 of 21
Commencement
Date: Completion Date:
Task Description
Rough terrain crane 75 used to lift of Separator Tank to position while installing.
Load Description
Dimensions:
Centre of Gravity:
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 4 of 21
Personnel
Name Classification Cart Number
Crane Operator
Rigger
Cranes
Unit Make Capacity Plan Inspect Proposed Boom Jib Hook Max Load
No Reg Date CWT Length Length Riving SWL Share
No.
Transport
Unit No. Prime Trailer Reg No. Inspect Max Load Proposed
Mover Date Cap Load
Other:
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 5 of 21
Chains
Lift Point Diameter Length SWL Inspected Load Share Details
No
Slings
Lift Point Diameter Length SWL Inspected Load Share Details
No
Shackles
Lift Point No Size SWL Inspected Load Share Details
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 6 of 21
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 7 of 21
5 Rigging/Slinging –Diagram
Sketch the Load and mark: Nominated Lift Points, Weight at each Lift Point, Centre of Gravity,
Load Sharing Calculation, and Rigging Arrangement.
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 8 of 21
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 9 of 21
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 10 of 21
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 11 of 21
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 12 of 21
Item Checked
Cranes standing and working area is level. compacted and suitable for assembly
Adequate and suitable area identified to unload, assemble, handle and store the load
All overhead obstructions, power wires, structures etc, identified and controlled
All underground obstructions, pipes drains, manholes etc, identified and controlled
Scaffold, ladders, access platforms, to all work areas identified and prepared
Clearances for tail swing, boom operation and load movement are confirmed
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 13 of 21
Item Checked
Personnel
On arrival at site all personnel are briefed and delegated particular tasks
The site area is cleared of all persons and equipment not involved
Barricades, signage warning devices installed
Access to work areas installed - P.P.E.
Control measures applied to hazardous areas or situations
CRANES
Crane/s positioned in accordance with plan, radius and S.W.L. confirmed
Outrigger packing positioned, outrigger beams extended, outrigger jacks extended
Crane jacked level, locking pins and devices fitted, as per crane manual
Boom assembled or extended to required length, pins, wedges, safety devices etc., fitted
Counterweight fitted, hooks revved, bolts, pins, wedges, safety devices etc. fitted
Boom erected, brakes, pawls, lock outs, weigh gauges, etc. tested
Tail swing and boom clearances confirmed, communications system tested
LOAD
Item is positioned or assembled, supported and brace, in a safe stable manner
Rigging/Slinging is fitted, protection for gear installed as per plan
Load is lifted clear of ground, slinging checked, outriggers checked
Observance for hazards is made, confirmation to proceed is given
Load is lifted and placed in final position and safely secure
Rigging / Slinging equipment disconnected and lowered to ground
MOVE OUT
All equipment is safely dis-assembled, stowed loaded and tied on transport
Cranes are prepared for travel in accordance with manuals and permits
Inspection made to ensure no hazards remain as a result of activity
All personnel and equipment depart from site in a safe. orderly manner
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 14 of 21
8 Main Specification
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 15 of 21
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 16 of 21
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 17 of 21
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 18 of 21
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 19 of 21
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 20 of 21
Lift Study
Document Number
Installing Rev. : A
GKE-HG-RIG-0002
Separator Tank 17 July 2011
Page 21 of 21
ITEM Checked
Are all surface encumbrances that may create a hazard re-moved or supported?
Have all underground utility installation been located?
Are employees exposed to vehicular traffic wearing warning vests made of reflector
zed or high visibility material?
Is a warning system such as barricades, hand or mechanical signals or stop logs
used when mobile equipment approaches the edge of the excavation?
Is there Settlement (Low spots) in the ground?
Are there Cracks in the ground?
Is there Erosion in the ground?
Are there Alternative Cover (armoured rock, concrete, etc.) in the ground?
Whether the soil has a horizontal surface?
CHAPTER 9
Crane Lift
Study
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 2 of 15
TABLE OF CONTENT
Crane Lift
Study
Document Number Installing Rev. : A
17 July 2011
GKE-HG-RIG-0002 Separator Tank Page 3 of 15
3 ACTUAL CONDITION
CHAPTER 10
General Scaffolding
Safety Checklist
Document Number Installing Rev. : A
TABLE OF CONTENT
1 Documentation: ...................................................................................................................3
3 Foundation: .........................................................................................................................3
8 Ties: ....................................................................................................................................5
10 Platforms (general):.............................................................................................................6
12 Bracing:...............................................................................................................................7
13 Access: ...............................................................................................................................7
1 Documentation:
Has steel wire mesh/ shade cloth or containment sheeting been provided
where members of the public exposed to a risk of falling materials from the
scaffolding
Has steel wire mesh/ shade cloth or containment sheeting been provided
where workers are exposed to a risk of falling materials from the scaffolding
System in place to inspect the scaffolding after trades have used it e.g. form
workers, concreters, bricklayers, tillers
2 Supporting structure:
3 Foundation:
Base plates used are a minimum 100mm x 100mm and 6mm thick
If on soft ground are sole boards being used to distribute the load evenly
General Scaffolding
Safety Checklist
Document Number Installing Rev. : A
Are the sole boards continuous and where ever possible support 2
standards. and a minimum 220mm wide
Has the scaffolding been designed for wind loading where signage is being
tied to the scaffolding
7 Mixed components:
8 Ties:
System in place to monitor ties as other trades progress e.g. form workers,
bricklaying, tillers etc
0
Have 90 fittings been used (swivel fittings not to be used)
rd
Are ties provided as per AS 1576 - Vertical = every 4m Horizontal = 3 bay
rd
< 15m Every 3 - -
standard
nd rd
15m – 30m Every 2 Every 3 -
standard standard
nd rd
> 30m Every standard Every 2 Every 3
standard standard
Do the ties obstruct access along the full length of the working and access
platforms
9 Temporary ladders:
10 Platforms (general):
Is the duty of the scaffolding suitable for the task i.e. heavy, medium or light
Is the scaffold width appropriate for the duty e.g. heavy duty 5 planks
Are signs erected on the bays indicating duty of the bay/s (i.e. scaffold tag)
Are any of the platform bays being used to stack/store materials e.g. bricks,
F. Work
Does the weight of these material exceed the rated WLL per platform bay
Is there any materiel etc being stacked/stored above the height of the
General Scaffolding
Safety Checklist
Document Number Installing Rev. : A
Are openings at working platform level covered and secured e.g. plywood
(17mm), planks
11 Temporary stairways:
12 Bracing:
Has face bracing been provided i.e. longitudinal at no more than 3 bays
apart, unless otherwise specified
Has been provided at the end of the scaffolding i.e. transverse bracing
Hop up brackets:
If hop up brackets are 500mm above or below the working platform has
adequate fall prevention been provided
13 Access:
Is the access along the working platform - minimum 450mm wide for
persons and tools only (2 planks)
Is the access along the working platform - minimum 675mm wide for
persons and materials (3 planks)
Are incomplete scaffolding platforms etc blocked off and or signs used
Is there suitable access to and from the working platform e.g. from the
building to the scaffold
General Scaffolding
Safety Checklist
Document Number Installing Rev. : A
Is there safe access between working platform during use, erection and
dismantling
14 Edge protection:
Is edge protection provided where a person or object could fall (2m or) more
Where guardrails and toe boards (150mm) only are being used is a
suitable infill such as brick guards or infill panels being used
Are guardrails erected between 900mm and 1100mm above the platform
Where brick guards are being used is the mesh aperture no > 50mm x
50mm
Where the gap between scaffolding and supporting structure is > 225mm
has edge protection been provided
Do the trades on site using the scaffolding alter the scaffolding themselves
Are the trades on site that are using the scaffolding aware that any
alterations to the scaffolding are to be done by a scaffolder.