You are on page 1of 3

Version 1.

MANAGEMENT OF CHANGE REQUEST FORM

Name of Person or Group Requesting Change: ________________________________ Date: _________

Summary Description of Change:

Reason(s) for Change:

Change is: permanent


temporary Duration of change: __________________

Signature of Requestor: _________________________________

Yes N/A
Attachment checklist: Updated Process Flow Sheet, if changed
Current Process Flow Sheet
Updated JSA pages, if changed
Current JSA pages
Updated Engineering documentation pages, if changed
Current Engineering documentation pages
Safety Evaluation Checklist (req’d. – see below)
Version 1.0

Management of Change Request Form

PROCESS CHANGE REQUEST


APPROVAL FORM

Type of Change: Major – Requires review by entire team and faculty adviser
Minor – Requires review by team only

Description of Change as Approved:

Approved Duration of Change: ___________________________

Signatures of Approval
Faculty Adviser: _____________________________________________ Date: ______________

Review Team Member: ____________________________________________ Date: ______________

Review Team Member: ____________________________________________ Date: ______________

Review Team Member: ____________________________________________ Date: ______________

Review Team Member: ____________________________________________ Date: ______________

Review Team Member: ____________________________________________ Date: ______________

Review Team Member: ____________________________________________ Date: ______________

Attach minutes and pertinent notes from review team meetings and place in permanent file.
Version 1.0

Management of Change Request Form

SAFETY EVALUATION CHECKLIST


Complete this safety evaluation checklist, noting any conditions that apply to the proposed change. Attach a
more detailed description of the change, if necessary, along with all supporting materials.

Changes in Process Conditions/Materials: Changes in Facilities:


temperature ventilation
pressure lighting
flow utility services
level building modifications/renovations
composition
chemical Changes in Safety Equipment:
toxicity containment
flash point guarding
reaction conditions fire protection
biohazard fire detection
use of regulated materials safety equipment location
use of lasers/ change in class of lasers safety equipment type
personal protective equipment
Changes in Operating Conditions/ Procedures: grounding/bonding
startup
normal operations Changes in Control Systems/ Elements:
abnormal operations programming change
shut down controller action
emergency shut down control valve trim/sizing
maintenance procedures instrument/transmitter
lock-out sensing element
tagging graphically displayed information
system response to alarm
Changes in Process Equipment:
size or capacity Changes in Environmental Conditions:
materials of construction discharge air quality
seals and gasket materials discharge water quality
piping/ valving solid waste
electrical system
max./min. working pressure
max./min. working temperature
equipment guarding
thermal insulation/insulation coverings
filters
support structures