1.0 OBJECTIVE:
To lay down a Procedure to effectively use of Effluent Treatment Plant (ETP).

2.0 SCOPE:

This SOP is applicable for the 50 KLD Effluent Treatment Plant at ………………….

3.0 RESPONSIBILITY:

Executive/Officer- Engineering

4.0 ACCOUNTABILITY:

Department Head:-Approval, Ensure Training and Implementation of this SOPs.

5.0 DEFINITION:

NA

6.0 PROCEDURE:

6.1 Starting Procedure.

6.1.1 Switch “ON” the Air Blower.


--- Prepared By Checked By Approved By
Officer/Executive Department Head Head Quality Assurance
Name

Signature

Date

FORMAT No.:………………………….
PHARMA SCHOLARS
ENGINEERING DEPARTMENT

STANDARD OPERATING PROCEDURE

Restricted Circulation
Department: Engineering
TITLE : SOP FOR EFFLUENT TREATMENT PLANT (ETP)
SOP No. Revision No.
Effective Date Supersedes No.
Review Date Page No. 2 of 7

6.1.2 Add 05 Kg Lime once time, in Lime chemical dosing tank.


6.1.3 Mix Lime about15 minutes in Lime chemical dosing tank with raw water 200 Ltrs by a hand
stirrer. .
6.1.4 Add 05 Kg potash Alum once time in to the Alum chemical dosing tank and mix with 200 Ltrs
raw water.
6.1.5 Add 50 gm Polyelectrolyte once time into polyelectrolyte chemical dosing tank and mix 100
Ltrs. raw water.
6.1.6 All chemical dosing depend upon the effluent pH and effluent quantity. Initially chemical
Preparation 0f 5000 Ltrs effluent
6.1.7 Switch ‘ON’ the effluent transfer pump
6.1.8 Open the valves of chemical dosing tanks.
6.1.9 Allow to transfer the effluent through chemical reactor (Reaction Chamber, Flocculation
Chamber), Primary tube settler. Sludge is passed through sludge drying bed-1& 2 and collected
into sludge storage tank.
6.1.10 Allow to transfer the effluent Bio Reactors I & II from tube settler I
6.1.11 Allow to transfer the effluent tube settler I from Bio reactor II.
6.1.12 Allow to transfer the effluent filter feed tank with sodium hypochlorite dosing.
6.1.13 Allow to settle the effluent about 45 minutes in filter feed tank and switch on the Filter feed
pump it is passed through dual media filter and active carbon filter and micron housing filters

6.1.14 Take the sample and send to the QC department and received the report.

--- Prepared By Checked By Approved By


Officer/Executive Department Head Head Quality Assurance
Name

Signature

Date

FORMAT No.:………………………….
PHARMA SCHOLARS
ENGINEERING DEPARTMENT

STANDARD OPERATING PROCEDURE

Restricted Circulation
Department: Engineering
TITLE : SOP FOR EFFLUENT TREATMENT PLANT (ETP)
SOP No. Revision No.
Effective Date Supersedes No.
Review Date Page No. 3 of 7

6.1.15 Allow to go the effluent to clear water Re-use in gardening.


6.1.16 Check the clear water pH is 7.5.

6.2 Stopping Procedure

6.2.1 If effluent is not found in full quantity the process should be stop.

7.0 ABBREVIATIONS:

No. Number
SOP Standard Operating Procedure
EN Engineering

8.0 ANNEXURES:

ANNEXURE No. TITLE OF ANNEXURE FORMAT No.


Operation Log Book of ETP
Annexure-I F01-00
Hazardous Waste Management of Sludge
Annexure-II F02-00
ETP Water Daily Analysis Report
Annexure-III F03-00

9.0 DISTRIBUTION:
• Master Copy Quality Assurance Department.
• Controlled Copy No. 01 Engineering Department.
10.0 REFERENCES:

--- Prepared By Checked By Approved By


Officer/Executive Department Head Head Quality Assurance
Name

Signature

Date

FORMAT No.:………………………….
PHARMA SCHOLARS
ENGINEERING DEPARTMENT

STANDARD OPERATING PROCEDURE

Restricted Circulation
Department: Engineering
TITLE : SOP FOR EFFLUENT TREATMENT PLANT (ETP)
SOP No. Revision No.
Effective Date Supersedes No.
Review Date Page No. 4 of 7

In-House

11.0 REVISION HISTORY:


Revision Change Details of Reason of Changes Effective Done By
No. Control No. Changes Date
00 Not Applicable Not Applicable New SOP

--- Prepared By Checked By Approved By


Officer/Executive Department Head Head Quality Assurance
Name

Signature

Date

FORMAT No.:………………………….
PHARMA SCHOLARS
ENGINEERING DEPARTMENT

STANDARD OPERATING PROCEDURE

Restricted Circulation

Department: Engineering
TITLE : SOP FOR EFFLUENT TREATMENT PLANT (ETP)
SOP No. SOP/EN/032 Revision No. 00
Effective Date Supersedes No. Nil
Review Date Page No. 5 of 7

ANNEXURE-1

PHARMA SCHOLARS
ENGINNERING
OPERATION LOG BOOK OF ETP

DATED TIME FLOW/DAY CHEMICALS PH NO.OF QTY. DRY NO.OF OPERATOR


START STOP LIME ALUM POLY INITIAL FINAL DMF OF WT.OF CLEANINGOF SIGNATURE
ELECTROLYTE BACK SLUDGE SLUDGE SLUDGE
WASH DRYING BEDS

Format No.:……………….

--- Prepared By Checked By Approved By


Officer/Executive Department Head Head Quality Assurance
Name
Signature
Date
FORMAT No………………………
PHARMA SCHOALRS
STANDARD OPERATING PROCEDURE

Department: Engineering
TITLE : SOP FOR EFFLUENT TREATMENT PLANT (ETP)
SOP No. Revision No.
Effective Date Supersedes No.
Review Date Page No. 6 of 7

ANNEXURE-II

PHARMA SCHOLARS
ENGINNERING
HAZARADOUS WASTE MANAGEMENT OF SLUDGE

DATE DESCRIPTION NATURE COLLECTION QTY.OF SLUDGE OPERATOR REMARK


ETP SIGNATURE
SLUDGE

Format No.:…………………..

--- Prepared By Checked By Approved By


Officer/Executive Department Head Head Quality Assurance
Name
Signature
Date

FORMAT No.: SOP/QA/001/F01-00


PHARMA SCHOALRS
STANDARD OPERATING PROCEDURE

Department: Engineering
TITLE : SOP FOR EFFLUENT TREATMENT PLANT (ETP)
SOP No. Revision No.
Effective Date Supersedes No.
Review Date Page No. 7 of 7

PHARMA SCHOLARS

ENGINNERING
ETP WATER DAILY ANALYSIS REPORT

ANNEXURE-III

Date pH (without Treatment) pH (after Treatment Limit T.S.S. Limit NMT 100 Signature (Done By) Checked By
6.0 – 8.5) mg/liter

Format No.:……………………..