Professional Documents
Culture Documents
Sr.No Activity Item No. Crane Requirement Duration 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 1-Aug 2-Aug 3-Aug 4-Aug 5-Aug 6-Aug 7-Aug 8-Aug 9-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug
R-6110/
3 Scaffolding for Unbolting of Temporary Spool 2 days
R-6120
4 Setting(Counter Weight) of Mobile Crane R-6110 100ton Mobile Crane 0.5 day
4 Unbolting/Dismantling of Temporay Spool/Elbow Spool R-6110 100ton Mobile Crane 0.5 day
R-6110/
6 Erection of 16" Vent Line and Scaffolding for Holding of Pipe 300ton Crawler Crane 1 day
R-6120
R-6110/
7 Erection of Support for 16" Vent line (4 Locations) 1 day
R-6120
300ton Crawler
Erection/Bolting of 48" Reactor to Exchanger Spool
8 R-6110 Crane 1.5 days
(Incl. Scaffolding Dismantling for Holding Pipe)
100ton Mobile Crane
9 Shifting/Setting(Counter Weight) of Mobile Crane to R-6120 R-6120 100ton Mobile Crane 0.5 day
10 Unbolting/Dismantling of Temporay Spool/Elbow Spool R-6120 100ton Mobile Crane 0.5 day
15 Preparation for Removal of Bottom Spool R-6120 Chain Block Only 1 day
R-6110/
17 Bolt Torquing and Inspection for Pipe Spools (Total 8 Spools) 7 days
R-6120
R-6110/
18 Manhole Closing (Total 8 Manhole) 1 day
R-6120
R-6110/
19 Scaffolding for Piping Insulation 6 days
R-6120
R-6110/
20 Piping Insulation
R-6120
▣ (Rev.1) EO Reactor Spool Installation Schedule
Crawler Crane Positioning Start
1 Crane Assembly and TUV (300ton Crawler Crane) 8/24/2021 8/29/2021 5 days
4 Dismantling of Scaffolding(Temp. Spool ↔ Elbow Connection Point) E-6111 8/31/2021 8/31/2021 4 Hrs
6 Dismantling of Scaffolding(Temp. Spool ↔ Elbow Connection Point) E-6121 8/31/2021 8/31/2021 4 Hrs
R-6110/
13 Erection of 16" Vent Line and Scaffolding for Holding of Pipe 9/8/2021 9/8/2021 1 day
R-6120
R-6110/
14 Erection of Support for 16" Vent line (4 Locations) 9/9/2021 9/9/2021 1 day
R-6120
Reactor
20 Bolt Torquing and Inspection for Pipe Spools (Total 8 Spools) 9/4/2021 9/11/2021 7 days
Exchanger
R-6110/
21 Manhole Closing (Total 8 Manhole) 9/12/2021 9/13/2021 2 days
R-6120
R-6110/
22 Scaffolding for Piping Insulation
R-6120
R-6110/
23 Piping Insulation
R-6120
Reactor Top Spool / Vent Line (16")
Bottom Spool