0) EO Reactor Spool Installation Schedule


Spool 제거 / 설치 작업 Start

Sr.No Activity Item No. Crane Requirement Duration 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 1-Aug 2-Aug 3-Aug 4-Aug 5-Aug 6-Aug 7-Aug 8-Aug 9-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug

1 Crane Assembly and TUV (300ton Crawler Crane) 6 days

2 Preparation the Ground for Ramp/Access/Position (for Crawler) 3 days

R-6110/
3 Scaffolding for Unbolting of Temporary Spool 2 days
R-6120

4 Setting(Counter Weight) of Mobile Crane R-6110 100ton Mobile Crane 0.5 day

4 Unbolting/Dismantling of Temporay Spool/Elbow Spool R-6110 100ton Mobile Crane 0.5 day

5 Erection/Bolting of Elbow Spool R-6110 100ton Mobile Crane 0.5 day

R-6110/
6 Erection of 16" Vent Line and Scaffolding for Holding of Pipe 300ton Crawler Crane 1 day
R-6120

R-6110/
7 Erection of Support for 16" Vent line (4 Locations) 1 day
R-6120
300ton Crawler
Erection/Bolting of 48" Reactor to Exchanger Spool
8 R-6110 Crane 1.5 days
(Incl. Scaffolding Dismantling for Holding Pipe)
100ton Mobile Crane
9 Shifting/Setting(Counter Weight) of Mobile Crane to R-6120 R-6120 100ton Mobile Crane 0.5 day

10 Unbolting/Dismantling of Temporay Spool/Elbow Spool R-6120 100ton Mobile Crane 0.5 day

11 Erection/Bolting of Elbow Spool R-6120 100ton Mobile Crane 0.5 day


300ton Crawler
Erection/Bolting of 48" Reactor to Exchanger Spool
12 R-6120 Crane 1.5 days
(Incl. Scaffolding Dismantling for Holding Pipe)
100ton Mobile Crane
13 Preparation for Removal of Bottom Spool R-6110 Chain Block Only 1 day

14 Removal/Erection/Alignment/Bolting of Bottom Spool R-6110 Chain Block Only 2 days

15 Preparation for Removal of Bottom Spool R-6120 Chain Block Only 1 day

16 Removal/Erection/Alignment/Bolting of Bottom Spool R-6120 Chain Block Only 2 days

R-6110/
17 Bolt Torquing and Inspection for Pipe Spools (Total 8 Spools) 7 days
R-6120

R-6110/
18 Manhole Closing (Total 8 Manhole) 1 day
R-6120

R-6110/
19 Scaffolding for Piping Insulation 6 days
R-6120

R-6110/
20 Piping Insulation
R-6120
▣ (Rev.1) EO Reactor Spool Installation Schedule
Crawler Crane Positioning Start

Duration (Day shift


Sr.No Activity Item No. Start Finish 25-Jul 26-Jul 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 1-Sep 2-Sep 3-Sep 4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep
Only)

1 Crane Assembly and TUV (300ton Crawler Crane) 8/24/2021 8/29/2021 5 days

2 Shifting of Crane to Lifting Location (300ton Crawler) 8/30/2021 8/30/2021 4 Hrs

3 Unbolting/Dismantling for Temporay Spool E-6111 8/30/2021 8/30/2021 4 Hrs

4 Dismantling of Scaffolding(Temp. Spool ↔ Elbow Connection Point) E-6111 8/31/2021 8/31/2021 4 Hrs

5 Unbolting/Dismantling for Temporay Spool E-6121 8/31/2021 8/31/2021 4 Hrs

6 Dismantling of Scaffolding(Temp. Spool ↔ Elbow Connection Point) E-6121 8/31/2021 8/31/2021 4 Hrs

7 Unbolting/Dismantling/Reinstallation of Elbow Spool E-6121 9/1/2021 9/2/2021 1 day

8 Unbolting/Dismantling/Reinstallation of Elbow Spool E-6111 9/2/2021 9/2/2021 1 day

Crane Position and Preparation Work (Incl. Dismantling of Scaffolding for


9 R-6110 9/4/2021 9/4/2021 1 day
holding the Pipe)

10 Erection/Bolting of 48" Reactor to Exchanger Spool R-6110 9/5/2021 9/5/2021 1 day

Crane Position and Preparation Work


11 R-6120 9/6/2021 9/6/2021 1 day
(Incl. Dismantling of Scaffolding for holding the Pipe)

12 Erection/Bolting of 48" Reactor to Exchanger Spool R-6120 9/7/2021 9/7/2021 1 day

R-6110/
13 Erection of 16" Vent Line and Scaffolding for Holding of Pipe 9/8/2021 9/8/2021 1 day
R-6120

R-6110/
14 Erection of Support for 16" Vent line (4 Locations) 9/9/2021 9/9/2021 1 day
R-6120

15 Shifting of Crane to Laydown and Disassembly 9/11/2021 9/15/2021 5 days

16 Preparation for Removal of Bottom Spool R-6110 9/2/2021 9/2/2021 1 day

17 Removal/Erection/Alignment/Bolting of Bottom Spool R-6110 9/4/2021 9/5/2021 2 days

18 Preparation for Removal of Bottom Spool R-6120 9/6/2021 9/6/2021 1 day

19 Removal/Erection/Alignment/Bolting of Bottom Spool R-6120 9/7/2021 9/8/2021 2 days

Reactor
20 Bolt Torquing and Inspection for Pipe Spools (Total 8 Spools) 9/4/2021 9/11/2021 7 days
Exchanger

R-6110/
21 Manhole Closing (Total 8 Manhole) 9/12/2021 9/13/2021 2 days
R-6120

R-6110/
22 Scaffolding for Piping Insulation
R-6120

R-6110/
23 Piping Insulation
R-6120
Reactor Top Spool / Vent Line (16")

Temporary Spool / Elbow Spool

Bottom Spool