Professional Documents
Culture Documents
AUTHORS
Summary
The electrical clearance (D) in Japan is calculated from the sum of Safety distance
(Ds) and Minimum air clearance required to prevent a disruptive discharge between
phase conductors and objects at earth potential during fast front or slow front
overvoltages (Del). Del is ‘clearance increment’ and depends on the system voltage.
This is the same idea as in foreign countries. The interpretation of the technical
standards (Ministerial Ordinance) for electrical appliances and materials (hereinafter
referred to as ‘Interpretation of Technical Standards’) stipulates a clearance value
that increases with rising voltage (hereinafter referred to as ‘clearance increment’).
The clearance increment varies depending on the safety distance and has been set
as 12 cm / 10 kV above 60 kV for other structures and trees, and 15 cm / 10 kV above
35 kV for buildings.
The clearance increments in other countries are generally set to about 6 cm / 10 kV,
so as the voltage rises, Japan's clearance is clearly larger than in other countries.
When the clearance was established in Japan in 1959, there were no 500 kV
overhead transmission lines (hereinafter referred to as ‘OHL’), and the clearance of
extra-high voltage OHL had not been suf ciently studied. Since then, the number of
OHL of 170 kV class and above has been increasing rapidly. It was thought that if
these clearances could be reviewed to be comparable to those in other countries, the
height of towers would be reduced and the area of tree trimming that interferes with
OHL would be reduced, leading to cost savings in the construction and maintenance
of OHL. Based on these circumstances, in order to explore the possibility of
reviewing the electrical clearance of EHV OHL in Japan, we conducted overseas
survey on the regulations of Germany, France, Canada, and the United States and
then not only the electrical clearance values but also basis for their setting were
investigated and compared to Japanese one. The overseas survey con rmed that
This amendment of the electrical clearance will reduce the height of 500 kV towers
by about 2 m, thereby reducing the cost of materials, transportation, and assembly of
the towers. In addition, by reviewing the electrical clearance from the conductor to
the tree, the area of trees to be cut down as obstacles can be reduced, especially
when the conductor swings sideways in the wind. Therefore, it will reduce not only
the compensation cost of new OHL, but also the maintenance cost of existing OHL.
This paper describes the results of the studies and investigations that formed the
basis for the rst revision of Japan's electrical clearances in 61 years, and the effects
of the regulatory changes on the design and cost of OHL.
KEYWORDS
1. Introduction
The interpretation of the technical standards (Ministerial Ordinance) for electrical
appliances and materials (hereinafter referred to as ‘Interpretation of Technical
Standards’) stipulates a clearance value that increases with rising voltage
(hereinafter referred to as ‘clearance increment’). The clearance increments vary
depending on the type of object approaching the conductor, with ‘other
structures*1 and trees’ set at 12 cm / 10 kV and ‘buildings’ at 15 cm / 10 kV. However,
in other countries, they are generally set at around 6 cm / 10 kV, and as the voltage
class increases, the deviation from the Japanese clearance becomes more
pronounced.
This standard value was set in 1959, but at that time, 500 kV overhead lines did not
exist and the clearance for EHV lines was not fully considered. Since 1959, the
number of EHV OHL above 170 kV has been increasing rapidly. Therefore, if this
clearance can be revised, the cost of construction and maintenance of OHL will be
reduced.
*1In Interpretation of Technical Standards, structures other than ’buildings, roads (except those
with infrequent vehicular and human traf c), pedestrian bridges, railroads, tracks, cableways,
overhead communication lines, low-voltage (600 V or less) or high-voltage (7,000 V or less)
overhead electric lines, low-voltage or high-voltage train lines, and other electric lines
exceeding 7,000 V’ are de ned as ‘other structures’.
The safety distance (Ds) was calculated from model cases in each country, and there
was no signi cant difference between Japan and other countries for buildings and
other structures. On the other hand, the clearance increment (Del) is 6.4 cm / 10 kV
in the United States and Canada, 6.2 cm / 10 kV in Germany (average of 35 kV or
more), and 7.5 cm / 10 kV in France, so the clearance increment in Japan is
remarkably large. As a result of this, the divergence from Japan's clearance becomes
striking as the voltage class grows larger (Figure 1 and 2).
*5 ‘The minimum insulation gap’ is de ned as the air gap that does not cause ashover for the
assumed switching surge and short-time overvoltage.
*6 ‘The standard insulation gap’ is de ned as the air gap that allows lightning-induced ashover
to occur between the arc horns and not between the wires and the tower.
*7Figures 1 and 2 are taken from Figures 3.1 and 3.3 in Electrical clearance for extra high
voltage overhead transmission lines exceeding 170 kV, JESC E2012 (2013), (in Japanese) [13]
36 0.35
52 0.60
72.5 0.70
100 0.90
123 1.00
145 1.20
170 1.30
245 1.70
300 2.10
420 2.80
525 3.50
L=1.115 x Z+0.021
Where,
L: Standard insulation gap (m), Z: Arcing horn gap (m)
In the new standard, a clearance exceeding the standard insulation gap has been
assured, and there is no potential for ashovers to other objects (Table 3, Figure 8
and 9).
187 1.53 (100%) 3.44 (225%) 5.22 (341%) 3.56 (233%) 5.40 (353%)
220 2.36 (100%) 3.62 (153%) 5.40 (229%) 3.92 (166%) 5.85 (248%)
275 3.03 (100%) 3.98 (131%) 5.76 (190%) 4.64 (153%) 6.60 (218%)
500 4.82 (100%) 5.30 (110%) 7.08 (147%) 7.28 (151%) 10.05 (209%)
Figure 10 - Reduction effect of EHV overhead transmission line towers passing through mountainous
areas
7.2. Effect of reducing the area of trees that are cut down
as obstacles to conductor
The expected reduction in the area of tree falling on conductors due to the
amendment of electrical clearance is described as follows. The reduction ratio in the
area of tree trimming, determined from the required clearance when the conductor
swings 60 degrees and sideways in high winds, is 3.8 % for overhead transmission
lines of 170 kV and above, which can be reduce the compensation cost (see Figure
11) [13]. This is not a temporary compensation at the time of OHL construction, but
lasts as long as the facility exists, so this economic effect is also signi cant.
8. Conclusions
As in Japan, the electrical clearance in other countries is calculated based on the
standard clearance value plus the clearance increment per 10 kV, but since the
Japanese clearance increment used to be larger than in other countries, there was a
maximum divergence of about 3 m in 500 kV. The Japanese electrical clearance was
amended for the rst time in 61 years on February 25, 2020 after many years of
study and recent overseas surveys. This will reduce the height of 500 kV towers by
about 2 m, which will reduce the material and assembly costs of the towers and
reduce the area of trees to be cut down as obstacles. It will not only reduce the cost of
constructing new OHL, but also the cost of maintaining the existing one, which will
have a signi cant economic impact.
References
1. Technical Standards for Electrical Facility in Japan (in Japanese)
2. National Electrical Safety Code (NESC) C2 (2017)
3. National Bureau of Standards Handbook H43
4. CSA standard C22.3 No.1-15 Overhead Systems (CSA)
5. EN 50341-1 Overhead electrical lines exceeding AC 1 kV - Part 1: General
requirements - Common speci cations
6. EN 50341-2-4 Overhead electrical lines exceeding AC 1 kV - Part 2-4: National
Normative Aspects (NNA) for GERMANY
7. VDE 0210-1 Overhead electrical lines exceeding AC 1 kV Part 1: General
requirements – Common speci cations
8. EN 50341-2-8 Overhead electrical lines exceeding AC 1 kV - Part 2-8: National
Normative Aspects (NNA) for France
9. UTE C11-001 Conditions techniques auxquelles doivent satisfaire les
distributions d'énergie électrique - Arrêté technique