Professional Documents
Culture Documents
PURCHASE REQUISITION
(Document No : A842-PDE-VV-PR-6041-0041)
Page 1 of 704
Click on the Document Title to go to that section of the document
Table of Contents
Document Number Rev. Document Title Page
Number
A842-PDE-VV-PR- 0 PURCHASE REQUISITION 6
6041-0041
A842-PDE-VV-PDS 0 ANY OTHER DOCUMENT 10
A842-79-41-PDE- 2 A842-79-41-PDE-11044 85
11044
A842-79-41-PDE- 2 A842-79-41-PDE-11045 86
11045
A842-79-41-PDE- 2 A842-79-41-PDE-11046 87
11046
A842-79-41-PDE- 2 A842-79-41-PDE-11084 88
11084
A842-79-41-PDE- 2 A842-79-41-PDE-11085 89
11085
A842-79-41-PDE- 2 A842-79-41-PDE-11086 90
11086
A842-PDE-80-43- 0 JOB SKETCHES 91
SK-0003
PDPP-SDR-0001 1 PDPP-SDR-0001 92
A842-PDE-80-43- A MIXER/AGITATOR DATASHEET 117
DS-XXXX
6-12-0001 5 General specification for pressure vessels. 119
6-12-0002 7 Supplementary specification for carbon steel vessels. 132
6-12-0006 5 Supplementary specification for austenitic stainless steel vessels. 139
6-12-0011 7 Standard specification for boiler quality carbon steel plates. 146
6-12-0014 5 Standard specification for weldable structural quality steel plates 153
for tanks and vessels
6-12-0020 7 Standard specification for stainless steel plates. 157
6-14-0003 5 Installation procedure for trays and tower internals. 162
6-14-0017 3 General specification for wire mesh demisters 178
6-81-0001 2 Standard specification for Positive Material Identification (PMI) at 184
Supplier's Works
6-81-0011 3 ITP for pressure vessels / columns carbon steel. 192
6-81-0014 3 ITP for stainless steel pressure vessels/ columns 199
6-81-0060 3 ITP for wire mesh demisters. 206
6-82-0001 6 Standard specification for health, safety & environment (HSE) 211
management at construction sites
6-78-0001 1 Specification for quality management system requirements from 298
bidders
6-78-0003 1 Specification for documentation requirement from suppliers 305
A842-000-79-41- 0 PROCESS SPECIFICATION-FREE NUMBER FORMAT 314
PLS-01
6-26-0001 3 Standard specification for mechanical agitators 358
7-12-0001 5 Vessel tolerances. 370
7-12-0002 5 SUPPORT FOR HORIZONTAL VESSEL 372
7-12-0004 6 Skirt base details. 373
7-12-0005 5 Skirt opening details. 374
7-12-0006 5 Angle leg support. 376
7-12-0007 5 Pipe leg support. 378
7-12-0008 5 Bracket support for vertical vessel. 379
7-12-0009 6 Manhole with hinged cover. 380
7-12-0010 6 Manhole with davit. 382
7-12-0011 5 Ladder rungs for manhole/demister. 384
7-12-0013 6 Nozzle reinforcement and projection. 385
Page 2 of 704
Click on the Document Title to go to that section of the document
Table of Contents
Document Number Rev. Document Title Page
Number
7-12-0015 5 Standard bolt hole orientation. 387
7-12-0017 5 Sight glasses for pressure vessels. 388
7-12-0018 5 Internal flanges. 390
7-12-0019 5 Vortex breakers. 391
7-12-0023 6 Pipe davit. 392
7-12-0024 7 Lifting lug top head type (for vertical vessels / columns). 395
7-12-0025 5 Fire proofing & insulation supports. 396
7-12-0026 5 Earthing lug. 398
7-12-0027 5 Name plate. 399
7-12-0028 5 Manufacturer name plate. 400
7-12-0029 5 Bracket for name plate. 401
7-12-0030 4 Name plate for small equipment. 402
7-12-0032 4 Supports for internal feed pipe. 403
7-12-0033 4 Hot insulation supports for horizontal vessel. 405
7-12-0036 4 Typical details of wire mesh demister and its supports (for vessels 406
and columns).
7-12-0038 0 Allowable nozzle loads 410
6-51-0064 1 Specification for energy efficient medium voltage induction motors 414
6-81-1032 5 ITP for MV motors 426
7-52-0001 4 Instrument connection on vessel, standpipes and tanks. 432
7-52-0002 4 Instrument connection on pipes. 436
7-52-0035 3 Thermowell. 439
7-52-0036 3 Thermocouple / RTD assembly with thermowell. 442
A842-000-16-51- A DRAWING 443
IS45
A842-000-16-51- A DRAWING 444
IS59
7-52-0481 4 Level gauge on vessel. 445
6-52-0052 3 Standard specification for instrumentation of package units. 446
7-52-0101 2 Instrument support single instrument 520
7-52-0041 3 Orifice plates and flanges dimensional details. 523
6-52-0032 4 Standard specification for electronic / pneumatic instruments. 537
A842-000-16-51-DS- A DATA SHEET 553
1001
A842-000-16-51-DS- A DATA SHEET 554
1101
A842-000-16-51-DS- A DATA SHEET 555
2601
A842-000-16-51-DS- A DATA SHEET 556
3201
A842-000-16-51-DS- A DATA SHEET 557
4001
A842-000-16-51-DS- A DATA SHEET 558
3701
A842-000-16-51-DS- A DATA SHEET 560
2501
A842-000-16-51-DS- A DATA SHEET 561
3401
A842-000-16-51-DS- A DATA SHEET 562
0201
Final Vendor List 0 VENDOR LIST 563
MR-6041(14) Rev 0
Page 3 of 704
Click on the Document Title to go to that section of the document
Table of Contents
Document Number Rev. Document Title Page
Number
7-52-0036 4 Thermocouple / RTD assembly with thermowell. 570
7-52-0481 5 Level gauge on vessel. 571
A842-79-41-PDE- 4 A842-79-41-PDE-11044 572
11044
A842-79-41-PDE- 4 A842-79-41-PDE-11084 573
11084
A842-PDE-16-50- 0 JOB SPECIFICATION FOR AGITATORS 574
SP-6042
A842-PDE-16-50- 0 VENDOR DATA REQUIREMENTS 577
VR-6041
A842-PDE-16-51-SL- 0 MANDATORY SPARE PARTS 580
6041/0041
A842-PDE-16-51- 0 JOB SPECIFICATIONS 582
SP-6041/0041
A842-PDE-16-51- A VENDOR DATA REQUIREMENTS 592
VDR-6041/0039
A842-PDE-85-41-VL- 0 VENDOR LIST 595
6041-41
PDPP-DS-A405 1 PDPP-DS-A405 602
PDPP-DS-A505 1 PDPP-DS-A505 603
PDPP-DS-V405 1 PDPP-DS-V405 604
PDPP-DS-V411 1 PDPP-DS-V411 607
PDPP-DS-V425 1 PDPP-DS-V425 610
PDPP-DS-V431 1 PDPP-DS-V431 614
PDPP-DS-V432 1 PDPP-DS-V432 617
PDPP-DS-V433 2 PDPP-DS-V433 620
PDPP-DS-V505 1 PDPP-DS-V505 622
PDPP-DS-V525 1 PDPP-DS-V525 625
PDPP-DS-V533 2 PDPP-DS-V533 629
PDPP-SDR-0001 2 PDPP-SDR-0001 631
A842-80-43-LL-6041- 0 PR LIST OF ATTACHMENTS 655
0041
A842-80-43-SS- 0 PR SCOPE OF WORK AND SUPPY 659
6041-0041
A842-80-43-TR- 0 PR INSTRUCTIONS TO VENDOR 665
6041-0041
A842-PDE-80-43- 0 VDR FOR VDR COMPILATION 678
VDR-6041
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 682
DS-3405
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 683
DS-3405A3
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 684
DS-3405A2
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 685
DS-3425
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 687
DS-3425A2
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 688
DS-3433
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 689
DS-3433A3
A842-PDE-80-43- 0 ENGINEERING DRAWINGS/SETTING PLAN 690
DS-3433A2
Page 4 of 704
Click on the Document Title to go to that section of the document
Table of Contents
Document Number Rev. Document Title Page
Number
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 691
DS-3432
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 692
DS-3432A3
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 693
DS-3432A2
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 694
DS-3431
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 695
DS-3431A2
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 696
DS-3505
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 697
DS-3505A3
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 698
DS-3505A2
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 699
DS-3525
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 702
DS-3525A2
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 703
DS-3411
A842-PDE-80-43- 0 MECHANICAL DATASHEETS 704
DS-3411A2
Page 5 of 704
PURCHASE REQUISITION (TOP SHEET)
ITEM DESCRIPTION: PRESSURE VESSEL -CS (UP TO 25 MM), PRESSURE VESSEL -SS (UP TO 25MM)
This drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced,
DOCUMENT NUMBER
( Always quote the Document Number given below as reference )
JOB NO. UNIT/ MAIN DOC. SR. NO. REV. DATE DIVN. DEPT.
AREA COST CODE
ORIGINATOR
Page 6 of 704
SR. NO. TAG NO./ DESCRIPTION QUANTITY
ITEM CODE/ [ ID. NO.]
01.00 Residual Design & Engineering of Vessels
This drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced,
Page 7 of 704
SR. NO. TAG NO./ DESCRIPTION QUANTITY
ITEM CODE/ [ ID. NO.]
instructions to vendor (refer note-1)
This drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced,
Unit rates for various items if any , shall be as included in the Commercial part
of the Purchase order.
Vendor to note that the numbers given in square '[]' and curly '{}' brackets are
not for their use and meant for store purpose only. Items shall be tagged as per
main equipment Tag No. only.
Page 8 of 704
LIST OF ATTACHMENTS
REVISION
This drawing, design and details given on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced,
GENERAL NOTES:
copied, exhibited or used, except in the limited way permitted by a written consent given by the lender to the borrower for the intended use. EIL-1641-515 Rev.1 A4-210x297.
Page 9 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V405-1
3 Project Name PDP Project
4 Item No. PDE-V-405 Job No. E029636001
5 Service Catalyst Mixing Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 2800 / 5100
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 896 - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
14 o
Temp. C 35 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 150 / - 50 (*1) - / - - / - Operating kg @
16 o
Temp. C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 31.4 - - ( ) Platform & Ladder
24 Operating m3 15.8 / 8.0 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 (X) Agitator (*3)
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 316 SS - - ( ) MH Balancer
30 Hopper 316 SS - - ( ) Internal Ladder
31 Nozzle 316 SS - -
32 Flange F316 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal, Basket, Mesh 316 SS - -
35 External C.S. - -
36 Leg,Saddle - - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Design press. of Hopper : F.W. + 150 mmWC(g)
42 (*2) Upper Part / Lower Part
43 (*3) As for the specification of agitator, refer to "PDPP-DS-A405".
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V405-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V405-3 Detail of Nozzle and Hopper
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 10 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V405-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-405 Service Catalyst Mixing Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from OSBL T1 2" 1 #150 SO-RF TG
57 N2 3" 1 #150 SO-RF Over Flow L1 3" 1 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from Upper Part L2 3" 1 #150 SO-RF LT
59 N4 2" 1 #150 SO-RF Liquid to Lower Part G1a,b 2" 2 #150 SO-RF LG
60 N5 2" 1 #150 SO-RF Liquid to P-405 G2a,b 2" 2 #150 SO-RF LG
61 N6(*3) 2" 1 #150 SO-RF LN Inlet
62 N7 2" 1 #150 SO-RF LN Inlet X1 (*1) 1 #150 SO-RF Agitator Mount
63 N8~9 2" 2 #150 SO-RF MXA Inlet
64 N10~11 2" 2 #150 SO-RF Spare (w/Cover) MH1~2 24" 2 #150 SO-RF Manhole (w/Cover)
65 N12 - 1 - PTSA Inlet
66 HH1 6" 1 #150 SO-RF Handhole (w/Cover)
67 V1 4" 1 #150 SO-RF VENT
68 V2(*3) 2" 1 #150 SO-RF VENT
69 D1~2 2" 2 #150 SO-RF DRAIN
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 11 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V405-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-405 Service Catalyst Mixing Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 12 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V411-1
3 Project Name PDP Project
4 Item No. PDE-V-411 Job No. E029636001
5 Service V-410 Receiver No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 3200 / 6700
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 857 / 977 - - WEIGHT
13 Operating Press. mmHg 200 - - Erection kg @
14 Temp. °C 31 - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 62.5 - - (X) Platform & Ladder (*1)
24 Operating m3 19.0 / 22.1 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side (X) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Scope of supply is finalized in detailed engineering stage.
42 (*2) Light Liquid Part / Decanting Part
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V411-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V411-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 13 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V411-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-411 Service V-410 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 6" 1 #150 SO-RF Liquid from E-412 T1 2" 1 #150 SO-RF TE
57 N2 2" 1 #150 SO-RF Liquid from E-413 L1a,b 2" 2 #150 SO-RF LT
58 N3 4" 1 #150 SO-RF Liquid to P-411A/B L2a,b 3" 2 #150 SO-RF LT
59 N4 4" 1 #150 SO-RF Liquid to P-412A/B G1a,b 2" 2 #150 SO-RF LG
60 N5 (*2) 1 #150 SO-RF Min. Flow(from P-411A/B) G2a,b 2" 2 #150 SO-RF LG
61 N6 (*2) 1 #150 SO-RF Min. Flow(from P-412A/B) P1 2" 1 #150 SO-RF PT
62 N7 2" 1 #150 SO-RF Equalization P2 2" 1 #150 SO-RF PG
63 N8 2" 1 #150 SO-RF LN Inlet
64 N9 2" 1 #150 SO-RF FCS Inlet MH1~2 24" 2 #150 SO-RF Manhole(w/Cover)
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 14 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V411-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-411 Service V-410 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 15 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V415-1
3 Project Name PDP Project
4 Item No. PDE-V-415 Job No. E029636001
5 Service Inhibitor Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 1900 / 5100
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 832 - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
14 o
Temp. C 35 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 150 / - 50 (*1) - / - - / - Operating kg @
16 o
Temp. C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 14.5 - - ( ) Platform & Ladder
24 Operating m3 6.4 / 5.1 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 (X) Agitator (*3)
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Hopper 304 SS - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal, Basket, Mesh 304 SS - -
35 External C.S. - -
36 Leg,Saddle - - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Design press. of Hopper : F.W. + 150 mmWC(g)
42 (*2) Upper Part / Lower Part
43 (*3) As for the specification of agitator, refer to "PDPP-DS-A415".
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V415-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V415-3 Detail of Nozzle and Hopper
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 16 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V415-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-415 Service Inhibitor Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from OSBL T1 2" 1 #150 SO-RF TG
57 N2 3" 1 #150 SO-RF Over Flow L1 3" 1 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from Upper Part L2 3" 1 #150 SO-RF LT
59 N4 2" 1 #150 SO-RF Liquid to Lower Part G1a,b 2" 2 #150 SO-RF LG
60 N5 2" 1 #150 SO-RF Liquid to P-415 G2a,b 2" 2 #150 SO-RF LG
61 N6(*3) 2" 1 #150 SO-RF LN Inlet
62 N7 2" 1 #150 SO-RF LN Inlet X1 (*1) 1 #150 SO-RF Agitator Mount
63 N8~9 2" 2 #150 SO-RF MXA Inlet
64 N10~11 2" 2 #150 SO-RF Spare (w/Cover) MH1~2 24" 2 #150 SO-RF Manhole (w/Cover)
65 N12 - 1 - Inhibitor Inlet
66 HH1 6" 1 #150 SO-RF Handhole (w/Cover)
67 V1 4" 1 #150 SO-RF VENT
68 V2(*3) 2" 1 #150 SO-RF VENT
69 D1~2 2" 2 #150 SO-RF DRAIN
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 17 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V415-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-415 Service Inhibitor Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 18 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V425-1
3 Project Name PDP Project
4 Item No. PDE-V-425 Job No. E029636001
5 Service Water Surge Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 2700 / 2700
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 863 / 977 - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
14 Temp. °C 32 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 150 / - 50 - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 15.5 - - (X) Platform & Ladder (*3)
24 Operating m3 0.4 / 11.8 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head - - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle - - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) It shall be verified that V2 is larger than V1.
42 V1 : sum of volume for pipes under 10m from grade connected from LZ-441, LZ-451 and E-443
43 V2 : volume between LIL and level at end of insert pipes
44 (*2) Light Liquid Part / Decanting Part
45 (*3) Scope of supply is finalized in detailed engineering stage.
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V425-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V425-3 Detail of nozzle
64 PDPP-DS-V425-4 Detail of Dam Baffle
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revised as per PDP review meeting
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 19 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V425-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-425 Service Water Surge Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from LZ-441 V1 3" 1 #150 SO-RF VENT
57 N2 2" 1 #150 SO-RF Liquid from LZ-451
58 N3 2" 1 #150 SO-RF Liquid from LZ-451 D1 2" 1 #150 SO-RF DRAIN
59 N4 2" 1 #150 SO-RF Liquid from V-471 D2 2" 1 #150 SO-RF DRAIN
60 N5 2" 1 #150 SO-RF Liquid from V-441
61 N6 2" 1 #150 SO-RF Liquid from LZ-416 L1a,b 2" 2 #150 SO-RF LT
62 N7 2" 1 #150 SO-RF Liquid from E-443 L2 3" 1 #150 SO-RF LT
63 N8 2" 1 #150 SO-RF Liquid from P-412A/B G1a.b 2" 2 #150 SO-RF LG
64 N9 2" 1 #150 SO-RF Liquid to P-424A/B G2a,b 2" 2 #150 SO-RF LG
65 N10 2" 1 #150 SO-RF Liquid to P-425A/B
66 N11 (*2) 1 #150 SO-RF Min. Flow (From P-424A/B) MH1 24" 1 #150 SO-RF Manhole(w/Cover)
67 N12 (*2) 1 #150 SO-RF Min. Flow (From P-425A/B)
68 N13 3" 1 #150 SO-RF Over Flow HH1 6" 1 #150 SO-RF Handhole(w/Cover)
69 N14 2" 1 #150 SO-RF FCS Inlet
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revised as per PDP review meeting
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 20 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V425-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-425 Service Water Surge Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revised as per PDP review meeting
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 21 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V425-4
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-425 Service Water Surge Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revised as per PDP review meeting
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 22 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V431-1
3 Project Name PDP Project
4 Item No. PDE-V-431 Job No. E029636001
5 Service V-440 Feed Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 3000 / 6000
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 884 - - WEIGHT
13 Operating Press. kg/cm2(g) ATM - - Erection kg @
14 o
Temp. C 35 - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / - - / - - / - Operating kg @
16 o
Temp. C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 49.7 - - (X) Platform & Ladder (*1)
24 Operating m3 25.0 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side (*2) Jacket Side Trace Side (X) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Scope of supply is finalized in detailed engineering stage.
42 (*2) All welding lines on the inner surface shall be smoothly finished by a grinder.
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V431-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V431-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 23 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V431-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-431 Service V-440 Feed Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 3" 1 #150 SO-RF Liquid from V-430 L1 3" 1 #150 SO-RF LT
57 N2 4" 1 #150 SO-RF Liquid to P-431A/B L2a,b 2" 2 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid to V-432 G1a,b 2" 2 #150 SO-RF LG
59 N4 2" 1 #150 SO-RF Liquid to V-432 G2a,b 2" 2 #150 SO-RF LG
60 N5 (*2) 1 #150 SO-RF Min. Flow
61 N6 3" 1 #150 SO-RF Equalization MH1 24" 1 #150 SO-RF Manhole (w/Cover)
62 N7 4" 1 #150 SO-RF Over Flow
63 N8 3" 1 #150 SO-RF Gas from V-420
64
65 V1 4" 1 #150 SO-RF VENT
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 24 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V431-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-431 Service V-440 Feed Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 25 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V432-1
3 Project Name PDP Project
4 Item No. PDE-V-432 Job No. E029636001
5 Service Oil Separator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 600 / 5250
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 884 - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
14 Temp. °C 35 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 150 / - 50 - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 1.5 - - ( ) Platform & Ladder
24 Operating m3 1.5 - - ( ) Lug for Attachment
25 Retention Time min. - - - (X) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V432-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V432-3 Detail of Baffle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 26 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V432-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-432 Service Oil Separator
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from V-420,V-430,V-431
57 N2 2" 1 #150 SO-RF Liquid to V-433
58 N3 2" 1 #150 SO-RF Liquid to LZ-611
59 N4 2" 1 #150 SO-RF FCS Inlet
60
61 V1 3" 1 #150 SO-RF VENT
62 D1 2" 1 #150 SO-RF DRAIN
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 27 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V432-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-432 Service Oil Separator
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 28 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V441-1
3 Project Name PDP Project
4 Item No. PDE-V-441 Job No. E029636001
5 Service V-440 Receiver No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 1600 / 3900
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 850 - - WEIGHT
13 Operating Press. mmHg 40 - - Erection kg @
14 Temp. °C 31 - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 9.1 - - (X) Platform & Ladder (*2)
24 Operating m3 4.6 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side (*1) Jacket Side Trace Side (X) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Scope of supply is finalized in detailed engineering stage.
42 (*2) All welding lines on the inner surface shall be smoothly finished by a grinder.
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V441-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V441-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 29 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V441-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-441 Service V-440 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 4" 1 #150 SO-RF Liquid from E-442 T1 2" 1 #150 SO-RF TE
57 N2 2" 1 #150 SO-RF Liquid from OSBL L1a 3" 1 #150 SO-RF LT
58 N3 3" 1 #150 SO-RF Liquid to P-441A/B L1b 3" 1 #150 SO-RF LT
59 N4 2" 1 #150 SO-RF Liquid to V-425 L2a,b 2" 2 #150 SO-RF LT
60 N5 (*2) 1 #150 SO-RF Min. Flow G1a,b 2" 2 #150 SO-RF LG
61 N6 2" 1 #150 SO-RF Equalization G2a,b 2" 2 #150 SO-RF LG
62 N7 2" 1 #150 SO-RF LN,FCS Inlet P1 2" 1 #150 SO-RF PT
63 P2 2" 1 #150 SO-RF PG
64
65 MH1 24" 1 #150 SO-RF Manhole (w/Cover)
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 30 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V441-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-441 Service V-440 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 31 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V451-1
3 Project Name PDP Project
4 Item No. PDE-V-451 Job No. E029636001
5 Service V-450 Receiver No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 1800 / 3700
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 887 - - WEIGHT
13 Operating Press. mmHg 12 - - Erection kg @
14 Temp. °C 30 - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 10.9 - - (X) Platform & Ladder (*1)
24 Operating m3 5.5 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side (*2) Jacket Side Trace Side (X) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Scope of supply is finalized in detailed engineering stage.
42 (*2) All welding lines on the inner surface shall be smoothly finished by a grinder.
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V451-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V451-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 32 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V451-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-451 Service V-450 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 8" 1 #150 SO-RF Liquid from E-452A/B T1 2" 1 #150 SO-RF TE
57 N2 2" 1 #150 SO-RF Liquid from E-453 L1a 1" 1 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from P-401A/B L1b 3" 1 #150 SO-RF LT
59 N4 6" 1 #150 SO-RF Liquid to P-451A/B G1a,b 1" 2 #150 SO-RF LG
60 N5 (*2) 1 #150 SO-RF Min. Flow P1 1" 1 #150 SO-RF PT
61 N6 2" 1 #150 SO-RF Equalization P2 1" 1 #150 SO-RF PG
62 N7 2" 1 #150 SO-RF LN,FCS Inlet
63 MH1 24" 1 #150 SO-RF Manhole (w/Cover)
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 33 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V451-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-451 Service V-450 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 34 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V455-1
3 Project Name PDP Project
4 Item No. PDE-V-455 Job No. E029636001
5 Service Inhibitor Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 1800 / 5100
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 891 - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
14 Temp. °C 30 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 150 / - 50 (*1) - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 13.0 - - ( ) Platform & Ladder
24 Operating m3 5.4 / 5.1 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 (X) Agitator (*4)
27 MATERIAL ( ) Demister
28 Section Shell Side (*3) Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Hopper 304 SS - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal, Basket, Mesh 304 SS - -
35 External C.S. - -
36 Leg,Saddle - - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Design press. of Hopper : F.W. + 150 mmWC(g)
42 (*2) Upper Part / Lower Part
43 (*3) All welding lines on the inner surface shall be smoothly finished by a grinder.
44 (*4) As for the specification of agitator, refer to "PDPP-DS-A455".
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V455-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V455-3 Detail of Nozzle and Hopper
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 35 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V455-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-455 Service Inhibitor Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from P-401A/B T1 2" 1 #150 SO-RF TG
57 N2 3" 1 #150 SO-RF Over Flow L1 3" 1 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from Upper Part L2 3" 1 #150 SO-RF LT
59 N4 2" 1 #150 SO-RF Liquid to Lower Part G1a,b 2" 2 #150 SO-RF LG
60 N5 2" 1 #150 SO-RF Liquid to P-455 G2a,b 2" 2 #150 SO-RF LG
61 N6(*3) 2" 1 #150 SO-RF MXA Inlet
62 N7 2" 1 #150 SO-RF MXA Inlet X1 (*1) 1 #150 SO-RF Agitator Mount
63 N8~9 2" 2 #150 SO-RF MXA Inlet
64 N10~11 2" 2 #150 SO-RF Spare (w/Cover) MH1~2 24" 2 #150 SO-RF Manhole (w/Cover)
65 N12 - 1 - Inhibitor Inlet
66 HH1 6" 1 #150 SO-RF Handhole (w/Cover)
67 V1 4" 1 #150 SO-RF VENT
68 V2(*3) 2" 1 #150 SO-RF VENT
69 D1~2 2" 2 #150 SO-RF DRAIN
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 36 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V455-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-455 Service Inhibitor Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 37 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V505-1
3 Project Name PDP Project
4 Item No. PDE-V-505 Job No. E029636001
5 Service Catalyst Mixing Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 1500 / 5100
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 937 - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
14 o
Temp. C 35 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 100 / - 50 (*1) - / - - / - Operating kg @
16 o
Temp. C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 9.0 - - ( ) Platform & Ladder
24 Operating m3 2.8 / 4.6 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 (X) Agitator (*3)
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 316 SS - - ( ) MH Balancer
30 Hopper 316 SS - - ( ) Internal Ladder
31 Nozzle 316 SS - -
32 Flange F316 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal, Basket, Mesh 316 SS - -
35 External C.S. - -
36 Leg,Saddle - - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Design press. of hopper : F.W. + 100 mmWC(g) / F.V.
42 (*2) Upper Part / Lower Part
43 (*3) As for the specification of agitator, refer to "PDPP-DS-A505".
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V505-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V505-3 Detail of Nozzle and Hopper
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 38 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V505-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-505 Service Catalyst Mixing Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from OSBL T1 2" 1 #150 SO-RF TG
57 N2 3" 1 #150 SO-RF Over Flow L1 3" 1 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from Upper Part L2 3" 1 #150 SO-RF LT
59 N4 2" 1 #150 SO-RF Liquid to Lower Part G1a,b 2" 2 #150 SO-RF LG
60 N5 2" 1 #150 SO-RF Liquid to P-505 G2a,b 2" 2 #150 SO-RF LG
61 N6~7 2" 2 #150 SO-RF MXA Inlet
62 N8~9 2" 2 #150 SO-RF Spare (w/Cover) X1 (*1) 1 #150 SO-RF Agitator Mount
63 N10 - 1 - PTSA Inlet
64 MH1~2 24" 2 #150 SO-RF Manhole (w/Cover)
65 V1 4" 1 #150 SO-RF VENT
66 V2(*3) 2" 1 #150 SO-RF VENT HH1 6" 1 #150 SO-RF Handhole (w/Cover)
67 D1~2 2" 2 #150 SO-RF DRAIN
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 39 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V505-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-505 Service Catalyst Mixing Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 40 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V511-1
3 Project Name PDP Project
4 Item No. PDE-V-511 Job No. E029636001
5 Service V-510 Receiver No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 2600 / 5700
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 (*1) - - WEIGHT
13 Operating Press. mmHg (*1) - - Erection kg @
14 Temp. °C 31 - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 34.9 - - (X) Platform & Ladder (*3)
24 Operating m3 10.7 / 12.0 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side (X) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Operating Condition:
42 Case BA HA
43 Fluid Density kg/m3 856/977 860/989
44 Operating Press. mmHg 200 105
45 (*2) Light Liquid Part / Decanting Part
46 (*3) Scope of supply is finalized in detailed engineering stage.
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V511-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V511-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 41 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V511-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-511 Service V-510 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating
56 N1 4" 1 #150 SO-RF Liquid from E-512 T1 2" 1 #150 SO-RF TE
57 N2 2" 1 #150 SO-RF Liquid from E-513 L1a,b 2" 2 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from P-503A/B L2a,b 2" 2 #150 SO-RF LT
59 N4 3" 1 #150 SO-RF Liquid to P-511A/B L3a,b 3" 2 #150 SO-RF LT
60 N5 3" 1 #150 SO-RF Liquid to P-512A/B G1a,b 2" 2 #150 SO-RF LG
61 N6 (*2) 1 #150 SO-RF Min. Flow(from P-511A/B) G2a,b 2" 2 #150 SO-RF LG
62 N7 (*2) 1 #150 SO-RF Min. Flow(from P-512A/B) P1 2" 1 #150 SO-RF PT
63 N8 2" 1 #150 SO-RF Equalization P2 2" 1 #150 SO-RF PG
64 N9 2" 1 #150 SO-RF LN Inlet
65 N10 2" 1 #150 SO-RF FCS Inlet MH1~2 24" 2 #150 SO-RF Manhole(w/Cover)
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 42 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V511-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-511 Service V-510 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 43 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V515-1
3 Project Name PDP Project
4 Item No. PDE-V-515 Job No. E029636001
5 Service Inhibitor Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 2300 / 5100
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 823 - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
14 o
Temp. C 35 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 100 / - 50 (*1) - / - - / - Operating kg @
16 o
Temp. C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 21.2 - - ( ) Platform & Ladder
24 Operating m3 10.5 / 5.8 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 (X) Agitator (*3)
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Hopper 304 SS - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal, Basket, Mesh 304 SS - -
35 External C.S. - -
36 Leg,Saddle - - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Design press. of hopper : F.W. + 100 mmWC(g) / F.V.
42 (*2) Upper Part / Lower Part
43 (*3) As for the specification of agitator, refer to "PDPP-DS-A515".
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V515-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V515-3 Detail of Nozzle and Hopper
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 44 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V515-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-515 Service Inhibitor Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from OSBL T1 2" 1 #150 SO-RF TG
57 N2 3" 1 #150 SO-RF Over Flow L1 3" 1 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from Upper Part L2 3" 1 #150 SO-RF LT
59 N4 2" 1 #150 SO-RF Liquid to Lower Part G1a,b 2" 2 #150 SO-RF LG
60 N5 2" 1 #150 SO-RF Liquid to P-515 G2a,b 2" 2 #150 SO-RF LG
61 N6~7 2" 2 #150 SO-RF MXA Inlet
62 N8~9 2" 2 #150 SO-RF Spare (w/Cover) X1 (*1) 1 #150 SO-RF Agitator Mount
63 N10 - 1 - Inhibitor Inlet
64 MH1~2 24" 2 #150 SO-RF Manhole (w/Cover)
65 V1 4" 1 #150 SO-RF VENT
66 V2(*3) 2" 1 #150 SO-RF VENT HH1 6" 1 #150 SO-RF Handhole (w/Cover)
67 D1~2 2" 2 #150 SO-RF DRAIN
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 45 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V515-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-515 Service Inhibitor Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 46 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V525-1
3 Project Name PDP Project
4 Item No. PDE-V-525 Job No. E029636001
5 Service Water Surge Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 2400 / 2400
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 (*1) - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
o
14 Temp. C (*1) - - Empty kg @
15 Design Press. mmWC(g) F.W. + 150 / - 50 - / - - / - Operating kg @
o
16 Temp. C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 10.9 - - (X) Platform & Ladder (*4)
24 Operating m3 0.4 / 8.4 (*3) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head - - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle - - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Operating Condition:
42 Case BA HA
43 Fluid Density kg/m3 862/978 852/982
44 Operating Temp. °C 31 37
45 (*2) It shall be verified that V2 is larger than V1.
46 V1 : sum of volume for pipes under 10m grade connected from LZ-541, LZ-551 and E-543.
47 V2 : volume between LIL and level at end of insert pipes
48 (*3) Light Liquid Part / Decanting Part
49 (*4) Scope of supply is finalized in detailed engineering stage.
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V525-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V525-3 Detail of nozzle
64 PDPP-DS-V525-4 Detail of Dam Baffle
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revised as per PDP review meeting
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 47 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V525-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-525 Service Water Surge Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from LZ-541 V1 3" 1 #150 SO-RF VENT
57 N2 2" 1 #150 SO-RF Liquid from LZ-541 D1 2" 1 #150 SO-RF DRAIN
58 N3 2" 1 #150 SO-RF Liquid from LZ-551 D2 2" 1 #150 SO-RF DRAIN
59 N4 2" 1 #150 SO-RF Liquid from LZ-551
60 N5 2" 1 #150 SO-RF Liquid from V-571 L1a,b 2" 2 #150 SO-RF LT
61 N6 2" 1 #150 SO-RF Liquid from E-543 L2a,b 2" 2 #150 SO-RF LT
62 N7 2" 1 #150 SO-RF Liquid from LZ-516 L3 3" 1 #150 SO-RF LT
63 N8 2" 1 #150 SO-RF Liquid from P-512A/B G1a.b 2" 2 #150 SO-RF LG
64 N9 2" 1 #150 SO-RF Liquid from V-541 G2a,b 2" 2 #150 SO-RF LG
65 N10 2" 1 #150 SO-RF Liquid to P-524
66 N11 2" 1 #150 SO-RF Liquid to P-525A/B MH1 24" 1 #150 SO-RF Manhole(w/Cover)
67 N12 (*2) 1 #150 SO-RF Min. Flow
68 N13 2" 1 #150 SO-RF Over Flow HH1 6" 1 #150 SO-RF Handhole(w/Cover)
69 N14 2" 1 #150 SO-RF FCS Inlet
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revised as per PDP review meeting
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 48 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V525-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-525 Service Water Surge Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revised as per PDP review meeting
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 49 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V525-4
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-525 Service Water Surge Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revised as per PDP review meeting
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 50 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V531-1
3 Project Name PDP Project
4 Item No. PDE-V-531 Job No. E029636001
5 Service V-540 Feed Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 2400 / 4900
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 884(BA) / 866(HA) - - WEIGHT
13 Operating Press. kg/cm2(g) ATM - - Erection kg @
14 Temp. °C 35 - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / - - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 25.9 - - (X) Platform & Ladder (*2)
24 Operating m3 13.0 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side (*1) Jacket Side Trace Side (X) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) All welding lines on the inner surface shall be smoothly finished by a grinder.
42 (*2) Scope of supply is finalized in detailed engineering stage.
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V531-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V531-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 51 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V531-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-531 Service V-540 Feed Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 3" 1 #150 SO-RF Liquid from V-530 L1 3" 1 #150 SO-RF LT
57 N2 3" 1 #150 SO-RF Liquid to P-531A/B L2a,b 2" 2 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid to V-532 L3a,b 2" 2 #150 SO-RF LT
59 N4 2" 1 #150 SO-RF Liquid to V-532 G1a,b 2" 2 #150 SO-RF LG
60 N5 (*2) 1 #150 SO-RF Min. Flow G2a,b 2" 2 #150 SO-RF LG
61 N6 3" 1 #150 SO-RF Equalization
62 N7 3" 1 #150 SO-RF Over Flow MH1 24" 1 #150 SO-RF Manhole (w/Cover)
63 N8 3" 1 #150 SO-RF Gas from V-520
64
65 V1 3" 1 #150 SO-RF VENT
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 52 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V531-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-531 Service V-540 Feed Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 53 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V532-1
3 Project Name PDP Project
4 Item No. PDE-V-532 Job No. E029636001
5 Service Oil Separator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 600 / 5250
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 884(BA) / 851(HA) - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
o
14 Temp. C 35 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 150 / - 50 - / - - / - Operating kg @
o
16 Temp. C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 1.5 - - ( ) Platform & Ladder
24 Operating m3 1.5 - - ( ) Lug for Attachment
25 Retention Time min. - - - (X) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 316 SS - - ( ) MH Balancer
30 Head 316 SS - - ( ) Internal Ladder
31 Nozzle 316 SS - -
32 Flange F316 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 316 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V532-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V532-3 Detail of Baffle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 54 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V532-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-532 Service Oil Separator
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from V-520,V-530,V-531
57 N2 2" 1 #150 SO-RF Liquid to V-533
58 N3 2" 1 #150 SO-RF Liquid to LZ-611
59 N4 2" 1 #150 SO-RF FCS Inlet
60
61 V1 3" 1 #150 SO-RF VENT
62 D1 2" 1 #150 SO-RF DRAIN
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 55 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V532-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-532 Service Oil Separator
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 56 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V533-1
3 Project Name PDP Project
4 Item No. PDE-V-533 Job No. E029636001
5 Service Scum Separator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 600 / 3200
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 884(BA) / 866(HA) - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
o
14 Temp. C 35 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 150 / - 50 - / - - / - Operating kg @
o
16 Temp. C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 0.9 - - ( ) Platform & Ladder
24 Operating m3 0.8 - - ( ) Lug for Attachment
25 Retention Time min. - - - (X) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 316 SS - - ( ) MH Balancer
30 Head 316 SS - - ( ) Internal Ladder
31 Nozzle 316 SS - -
32 Flange F316 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 316 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V533-2 Outline Sketch and List of Nozzle
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 57 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V533-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-533 Service Scum Separator
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from V-532
57 N2 2" 1 #150 SO-RF Liquid to P-533
58 N3 2" 1 #150 SO-RF Liquid to V-507
59 N4 2" 1 #150 SO-RF Over Flow
60 N5 2" 1 #150 SO-RF FCS Inlet
61
62 V1 3" 1 #150 SO-RF VENT
63 D1 2" 1 #150 SO-RF DRAIN
64
65 L1 3" 1 #150 SO-RF LT
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 58 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V541-1
3 Project Name PDP Project
4 Item No. PDE-V-541 Job No. E029636001
5 Service V-540 Receiver No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 1600 / 3200
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 839(BA) / 864(HA) - - WEIGHT
13 Operating Press. mmHg 25(BA) / 16(HA) - Erection kg @
14 Temp. °C 31 - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 7.7 - - (X) Platform & Ladder (*1)
24 Operating m3 3.9 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side (*2) Jacket Side Trace Side (X) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Scope of supply is finalized in detailed engineering stage.
42 (*2) All welding lines on the inner surface shall be smoothly finished by a grinder.
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V541-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V541-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 59 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V541-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-541 Service V-540 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 4" 1 #150 SO-RF Liquid from E-542 T1 2" 1 #150 SO-RF TE
57 N2 2" 1 #150 SO-RF Liquid from OSBL,P-503A/B L1a,b 3" 2 #150 SO-RF LT
58 N3 3" 1 #150 SO-RF Liquid to P-541A/B L2a,b 2" 2 #150 SO-RF LT
59 N4 3" 1 #150 SO-RF Liquid to V-525 L3a,b 2" 2 #150 SO-RF LT
60 N5 (*2) 1 #150 SO-RF Min. Flow G1a,b 2" 2 #150 SO-RF LG
61 N6 2" 1 #150 SO-RF Equalization G2a,b 2" 2 #150 SO-RF LG
62 N7 2" 1 #150 SO-RF LN,FCS Inlet P1 2" 1 #150 SO-RF PT
63 P2 2" 1 #150 SO-RF PG
64
65 MH1 24" 1 #150 SO-RF Manhole (w/Cover)
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 60 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V541-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-541 Service V-540 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 61 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V551-1
3 Project Name PDP Project
4 Item No. PDE-V-551 Job No. E029636001
5 Service V-550 Receiver No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 1500 / 3000
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 886(BA) / 877(HA) - - WEIGHT
13 Operating Press. mmHg 12(BA) / 7(HA) - - Erection kg @
14 Temp. °C 31(BA) / 30(HA) - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 6.2 - - (X) Platform & Ladder (*2)
24 Operating m3 3.1 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side (*1) Jacket Side Trace Side (X) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) All welding lines on the inner surface shall be smoothly finished by a grinder.
42 (*2) Scope of supply is finalized in detailed engineering stage.
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V551-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V551-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 62 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V551-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-551 Service V-550 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 6" 1 #150 SO-RF Liquid from E-552 T1 2" 1 #150 SO-RF TE
57 N2 2" 1 #150 SO-RF Liquid from E-553 L1a 1" 1 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from P-401A/B, L1b 3" 1 #150 SO-RF LT
59 P-501A/B G1a,b 1" 2 #150 SO-RF LG
60 N4 4" 1 #150 SO-RF Liquid to P-551A/B P1 1" 1 #150 SO-RF PT
61 N5 (*2) 1 #150 SO-RF Min. Flow P2 1" 1 #150 SO-RF PG
62 N6 2" 1 #150 SO-RF Equalization
63 N7 2" 1 #150 SO-RF LN,FCS Inlet MH1 24" 1 #150 SO-RF Manhole (w/Cover)
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 63 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V551-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-551 Service V-550 Receiver
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 64 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V555-1
3 Project Name PDP Project
4 Item No. PDE-V-555 Job No. E029636001
5 Service Inhibitor Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 1500 / 5100
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name P - -
12 Density kg/m3 880 - - WEIGHT
13 Operating Press. mmWC(g) ATM - - Erection kg @
14 o
Temp. C 30 - - Empty kg @
15 Design Press. mmWC(g) F.W. + 100 / - 50 (*1) - / - - / - Operating kg @
16 o
Temp. C 65 - -
17 Hydro.Test Press. mmWC(g) F.W. - - ACCESSORIES
18 Leak Test Press. mmWC(g) - - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 9.0 - - ( ) Platform & Ladder
24 Operating m3 3.3 / 4.1 (*2) - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 (X) Agitator (*4)
27 MATERIAL ( ) Demister
28 Section Shell Side (*3) Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Hopper 304 SS - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal, Basket, Mesh 304 SS - -
35 External C.S. - -
36 Leg,Saddle - - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Design press. of hopper : F.W. + 100 mmWC(g) / F.V.
42 (*2) Upper Part / Lower Part
43 (*3) All welding lines on the inner surface shall be smoothly finished by a grinder.
44 (*4) As for the specification of agitator, refer to "PDPP-DS-A555".
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V555-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V555-3 Detail of Nozzle and Hopper
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 65 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V555-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-555 Service Inhibitor Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 2" 1 #150 SO-RF Liquid from P-501A/B T1 2" 1 #150 SO-RF TG
57 N2 3" 1 #150 SO-RF Over Flow L1 3" 1 #150 SO-RF LT
58 N3 2" 1 #150 SO-RF Liquid from Upper Part L2 3" 1 #150 SO-RF LT
59 N4 2" 1 #150 SO-RF Liquid to Lower Part G1a,b 2" 2 #150 SO-RF LG
60 N5 2" 1 #150 SO-RF Liquid to P-555 G2a,b 2" 2 #150 SO-RF LG
61 N6~7 2" 2 #150 SO-RF MXA Inlet
62 N8~9 2" 2 #150 SO-RF Spare (w/Cover) X1 (*1) 1 #150 SO-RF Agitator Mount
63 N10 - 1 - Inhibitor Inlet
64 MH1~2 24" 2 #150 SO-RF Manhole (w/Cover)
65 V1 4" 1 #150 SO-RF VENT
66 V2(*3) 2" 1 #150 SO-RF VENT HH1 6" 1 #150 SO-RF Handhole (w/Cover)
67 D1~2 2" 2 #150 SO-RF DRAIN
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 66 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V555-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-555 Service Inhibitor Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 67 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V611-1
3 Project Name PDP Project
4 Item No. PDE-V-611 Job No. E029636001
5 Service No.1 Knock Out Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 900 / 1800
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name PVG - -
12 Density kg/m3 1.06 - - WEIGHT
13 Operating Press. mmHg 702 - - Erection kg @
14 Temp. °C AMB - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 1.3 - - ( ) Platform & Ladder
24 Operating m3 1.3 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL (X) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - (X) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V611-2 Outline Sketch and List of Nozzle
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 68 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V611-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-611 Service No.1 Knock Out Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 14" 1 #150 SO-RF PVG Inlet MH1 18" 1 #150 SO-RF Manhole (w/Cover)
57 N2 14" 1 #150 SO-RF PVG Outlet
58 N3 2" 1 #150 SO-RF Liquid to LZ-611
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 69 of 704
Page 70 of 704
Page 71 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V613-1
3 Project Name PDP Project
4 Item No. PDE-V-613 Job No. E029636001
5 Service No.1 ITY Knock Out Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 400 / 1200
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name PVG - -
12 Density kg/m3 1.06 - - WEIGHT
13 Operating Press. mmHg 702 - - Erection kg @
14 Temp. °C AMB - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 0.2 - - ( ) Platform & Ladder
24 Operating m3 0.2 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL (X) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V613-2 Outline Sketch and List of Nozzle
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 72 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V613-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-613 Service No.1 ITY Knock Out Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 6" 1 #150 SO-RF PVG Inlet
57 N2 6" 1 #150 SO-RF PVG Outlet
58 N3 2" 1 #150 SO-RF Liquid to LZ-613
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 73 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V614-1
3 Project Name PDP Project
4 Item No. PDE-V-614 Job No. E029636001
5 Service No.2 ITY Knock Out Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type VERTICAL Shell I.D. / Shell Length mm 600 / 1400
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name PVG - -
12 Density kg/m3 1.06 - - WEIGHT
13 Operating Press. mmHg 702 - - Erection kg @
14 Temp. °C AMB - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / F.V. - / - - / - Operating kg @
16 Temp. °C 65 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 0 (for S.S.) - - (X) Earth Plate
22 Insulation None - - ( ) Support for Insulation
23 Volume Full m3 0.5 - - ( ) Platform & Ladder
24 Operating m3 0.5 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL (X) Demister
28 Section Shell Side Jacket Side Trace Side ( ) Vortex Breaker
29 Shell 304 SS - - ( ) MH Balancer
30 Head 304 SS - - ( ) Internal Ladder
31 Nozzle 304 SS - -
32 Flange F304 SS - -
33 Gasket V#7010 or Eq. - -
34 Internal 304 SS - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V614-2 Outline Sketch and List of Nozzle
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 74 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V614-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-614 Service No.2 ITY Knock Out Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 8" 1 #150 SO-RF PVG Inlet
57 N2 8" 1 #150 SO-RF PVG Outlet
58 N3 2" 1 #150 SO-RF Liquid to LZ-613
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 75 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 DRUM DATA SHEET Doc. No. PDPP-DS-V751-1
3 Project Name PDP Project
4 Item No. PDE-V-751 Job No. E029636001
5 Service Condensate Drum No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code ASME Sec.VIII Div.1
8 Type HORIZONTAL Shell I.D. / Shell Length mm 2300 / 4000
9 DESIGN CONDITIONS PAINTING
10 Section Shell Side Jacket Side Trace Side ( ) Yes ( ) No (X) C.S. only
11 Fluid Name SCL,SCM - -
12 Density kg/m3 958 - - WEIGHT
13 Operating Press. kg/cm2(g) ATM - - Erection kg @
14 Temp. °C 100 - - Empty kg @
15 Design Press. kg/cm2(g) 3.5 / - - / - - / - Operating kg @
16 Temp. °C 115 - -
17 Hydro.Test Press. kg/cm2(g) By Code - - ACCESSORIES
18 Leak Test Press. kg/cm2(g) 3.5 - - (X) Name Plate with Saddle
19 Radiograph % By Code - - (X) Lifting Lug
20 Post Weld Heat Treatment By Code - - (X) Anchor(Set) Bolt & Nut
21 Corrosion Allowance mm 3.0 (for C.S.) - - ( ) Earth Plate
22 Insulation HOT - - (X) Support for Insulation
23 Volume Full m3 19.8 - - (X) Platform & Ladder (*1)
24 Operating m3 8.8 - - ( ) Lug for Attachment
25 Retention Time min. - - - ( ) Sight Glass
26 ( ) Agitator
27 MATERIAL ( ) Demister
28 Section Shell Side Jacket Side Trace Side (X) Vortex Breaker
29 Shell C.S. - - ( ) MH Balancer
30 Head C.S. - - (X) Internal Ladder
31 Nozzle C.S. - -
32 Flange C.S. - -
33 Gasket V#8596 or Eq. - -
34 Internal C.S. - -
35 External C.S. - -
36 Leg,Saddle C.S. - -
37
38 REMARKS
39
40 '@' Marks to be decided by Vendor.
41 (*1) Scope of supply is finalized in detailed engineering stage.
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61 LIST OF ATTACHED SHEETS
62 PDPP-DS-V751-2 Outline Sketch and List of Nozzle
63 PDPP-DS-V751-3 Detail of Nozzle
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 76 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V751-2
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-751 Service Condensate Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54 NOZZLE LIST
55 Mark Size Q'ty Rating Service Mark Size Q'ty Rating Service
56 N1 4" 1 #150 SO-RF SCM from PDE-400/500 T1 2" 1 #150 SO-RF TG
57 N2 6" 1 #150 SO-RF SCL from PDE-500 L1a,b 3" 2 #150 SO-RF LT
58 N3 8" 1 #150 SO-RF SCL from PDE-400 G1a,b 2" 2 #150 SO-RF LG
59 N4 2" 1 #150 SO-RF SCL from E-751
60 N5 6" 1 #150 SO-RF Over Flow MH1 24" 1 #150 SO-RF Manhole (w/Cover)
61 N6 (*1) 1 #150 SO-RF Min. Flow
62 N7 6" 1 #150 SO-RF WDM Inlet
63 N8 10" 1 #150 SO-RF Liquid to P-751A/B
64 N9 6" 1 #150 SO-RF Vapor to E-751
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 77 of 704
MITSUBISHI CHEMICAL CORPORATION
1 Doc. No. PDPP-DS-V751-3
2
DRUM DATA SHEET Project Name PDP Project
3 Job No. E029636001
4 Item No. PDE-V-751 Service Condensate Drum
5
6
7
8
CONFIDENTIAL
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 78 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 AGITATOR DATA SHEET Doc. No. PDPP-DS-A405
3 Project Name PDP Project
4 Item No. PDE-A-405 Job No. E029636001
5 Service V-405 Agitator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code -
8 Type Propeller No. of Stage 1
9 OPERATING CONDITION
10 Liquid Name P Operating in Empty Tank ( ) Yes (X) No
11 Liquid Volume / B.H.P.
12 Press.(Nor. / Des.) kg/cm2(g) ATM / F.W. + 150 / -50 mmWC(g) Min. m3 / kW /
13 Temp.(Nor. / Des.) °C 35 / 65 Nor. m3 / kW /
14 Mixing Time - Max. m3 / kW 15.8 / Min. 5.5
15 MIXING CONDITION VESSEL DESCRIPTION
16 Material for Mixing BUOH / PTSA Item No. V-405
17 Charge kg/Batch 14200 Doc. No. PDPP-DS-V405
18 Flow Rate kg/h - Type Vertical
19 Temp. °C 35 Size I.D. mm 2800
20 Viscosity mPa s 2.7 HLL-Btm mm 2380
21 Density kg/m3 896 Flange Size / Rating @ / #150 SO-RF
22 CONSTRUCTION VESSEL ARRANGEMENT SKETCH
23 Mfr. -
24 Entering (X) Top ( ) Btm ( ) Side
25 Impeller Type Propeller
26 No. of Stage 1
27 Diameter mm 650
28 No. of Blade 3
29 Speed rpm @
30 Rotation(View from Driver) ( ) CW ( ) CCW (X) @
31 Baffle No. of Baffle -
32 Dimension mm -
33 Spacing from Wall mm -
34 Draft Tube Length mm -
35 Diameter mm -
36 Coil ( ) Yes (X) No
37 Power Transmission ( ) Direct (X) Gear ( ) V-belt ( ) @
38 Shaft Seal Type (X) Packing ( ) Mech. ( )@
39 Sealing Fluid -
40 Temp./Press. °C / kg/cm2(g) - / -
41 Cooling Water
42 C.W. Jacket l/min. ( ) Yes ( ) No (X) @ /
43 Stuff. Box l/min. ( ) Yes ( ) No (X) @ /
44 Pedestal l/min. ( ) Yes ( ) No (X) @ /
45 Temp./Press. °C / kg/cm2(g) 26 / 7.5
46 MATERIAL
47 Impeller 316 SS Gasket V#7010 or Eq.
48 Shaft 316 SS O-Ring -
49 Shaft sleeve 316 SS Shaft Seal V#8132 or Eq.
50 Mounting Flange 316 SS
51 ACCESSORIES
52 (X) Coupling (X) Mounting Flange (X) Shaft Sleeve MOTOR
53 (X) Coupling Guard (X) Mounting Gasket (X) Gasket Supplied by @
54 ( ) Pressure Unit (X) Bolt & Nut (X) Special Tool (If need) Mounted by @
55 ( ) Auxiliary Piping (X) Reducer Mfr. @
56 PAINTING Type @
57 ( ) Yes ( ) No (X) C.S. only Rated Output / Amp. kW / A @ / @
58 Pole / Revolution P / rpm @ / @
59 WEIGHT Phase / Cycle / Volt P / Hz / V 3 / 50 / 415
60 Erection kg @ Exp.Proof Class (*2)
61 Empty kg @ Bearing @
62 Operating kg @ Lubricating @
63 REMARKS A-weighted sound pressure level
64 (equip. side 1m) dBA 85
65 '@' Marks to be decided by Vendor. REDUCER
66 (*1) Estimated mounting nozzle height is 150mm. Mfr. @
67 (*2) Refer to "HAZARDOUS AREA CLASSIFICATION PLAN" Type Gear
68 Reduction ratio @
69 Revolution In / Out rpm @
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 79 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 AGITATOR DATA SHEET Doc. No. PDPP-DS-A415
3 Project Name PDP Project
4 Item No. PDE-A-415 Job No. E029636001
5 Service V-415 Agitator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code -
8 Type Propeller No. of Stage 1
9 OPERATING CONDITION
10 Liquid Name P Operating in Empty Tank ( ) Yes (X) No
11 Liquid Volume / B.H.P.
12 Press.(Nor. / Des.) kg/cm2(g) ATM / F.W. + 150 / -50 mmWC(g) Min. m3 / kW /
13 Temp.(Nor. / Des.) °C 35 / 65 Nor. m3 / kW /
14 Mixing Time - Max. m3 / kW 6.4 / Min. 2.3
15 MIXING CONDITION VESSEL DESCRIPTION
16 Material for Mixing BUOH / HQ Item No. V-415
17 Charge kg/Batch 5360 Doc. No. PDPP-DS-V415
18 Flow Rate kg/h - Type Vertical
19 Temp. °C 35 Size I.D. mm 1900
20 Viscosity mPa s 2.3 HLL-Btm mm 2140
21 Density kg/m3 832 Flange Size / Rating @ / #150 SO-RF
22 CONSTRUCTION VESSEL ARRANGEMENT SKETCH
23 Mfr. -
24 Entering (X) Top ( ) Btm ( ) Side
25 Impeller Type Propeller
26 No. of Stage 1
27 Diameter mm 550
28 No. of Blade 3
29 Speed rpm @
30 Rotation(View from Driver) ( ) CW ( ) CCW (X) @
31 Baffle No. of Baffle -
32 Dimension mm -
33 Spacing from Wall mm -
34 Draft Tube Length mm -
35 Diameter mm -
36 Coil ( ) Yes (X) No
37 Power Transmission ( ) Direct (X) Gear ( ) V-belt ( ) @
38 Shaft Seal Type (X) Packing ( ) Mech. ( )@
39 Sealing Fluid -
40 Temp./Press. °C / kg/cm2(g) - / -
41 Cooling Water
42 C.W. Jacket l/min. ( ) Yes ( ) No (X) @ /
43 Stuff. Box l/min. ( ) Yes ( ) No (X) @ /
44 Pedestal l/min. ( ) Yes ( ) No (X) @ /
45 Temp./Press. °C / kg/cm2(g) 26 / 7.5
46 MATERIAL
47 Impeller 304 SS Gasket V#7010 or Eq.
48 Shaft 304 SS O-Ring -
49 Shaft sleeve 304 SS Shaft Seal V#8132 or Eq.
50 Mounting Flange 304 SS
51 ACCESSORIES
52 (X) Coupling (X) Mounting Flange (X) Shaft Sleeve MOTOR
53 (X) Coupling Guard (X) Mounting Gasket (X) Gasket Supplied by @
54 ( ) Pressure Unit (X) Bolt & Nut (X) Special Tool (If need) Mounted by @
55 ( ) Auxiliary Piping (X) Reducer Mfr. @
56 PAINTING Type @
57 ( ) Yes ( ) No (X) C.S. only Rated Output / Amp. kW / A @ / @
58 Pole / Revolution P / rpm @ / @
59 WEIGHT Phase / Cycle / Volt P / Hz / V 3 / 50 / 415
60 Erection kg @ Exp.Proof Class (*2)
61 Empty kg @ Bearing @
62 Operating kg @ Lubricating @
63 REMARKS A-weighted sound pressure level
64 (equip. side 1m) dBA 85
65 '@' Marks to be decided by Vendor. REDUCER
66 (*1) Estimated mounting nozzle height is 150mm. Mfr. @
67 (*2) Refer to "HAZARDOUS AREA CLASSIFICATION PLAN" Type Gear
68 Reduction ratio @
69 Revolution In / Out rpm @
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 80 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 AGITATOR DATA SHEET Doc. No. PDPP-DS-A455
3 Project Name PDP Project
4 Item No. PDE-A-455 Job No. E029636001
5 Service V-455 Agitator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code -
8 Type Propeller No. of Stage 1
9 OPERATING CONDITION
10 Liquid Name P Operating in Empty Tank ( ) Yes (X) No
11 Liquid Volume / B.H.P.
12 Press.(Nor. / Des.) kg/cm2(g) ATM / F.W. + 150 / -50 mmWC(g) Min. m3 / kW /
13 Temp.(Nor. / Des.) °C 30 / 65 Nor. m3 / kW /
14 Mixing Time - Max. m3 / kW 5.4 / Min. 1.9
15 MIXING CONDITION VESSEL DESCRIPTION
16 Material for Mixing BA / MQ Item No. V-455
17 Charge kg/Batch 4780 Doc. No. PDPP-DS-V455
18 Flow Rate kg/h - Type Vertical
19 Temp. °C 30 Size I.D. mm 1800
20 Viscosity mPa s 0.85 HLL-Btm mm 1980
21 Density kg/m3 891 Flange Size / Rating @ / #150 SO-RF
22 CONSTRUCTION VESSEL ARRANGEMENT SKETCH
23 Mfr. -
24 Entering (X) Top ( ) Btm ( ) Side
25 Impeller Type Propeller
26 No. of Stage 1
27 Diameter mm 550
28 No. of Blade 3
29 Speed rpm @
30 Rotation(View from Driver) ( ) CW ( ) CCW (X) @
31 Baffle No. of Baffle -
32 Dimension mm -
33 Spacing from Wall mm -
34 Draft Tube Length mm -
35 Diameter mm -
36 Coil ( ) Yes (X) No
37 Power Transmission ( ) Direct (X) Gear ( ) V-belt ( ) @
38 Shaft Seal Type (X) Packing ( ) Mech. ( )@
39 Sealing Fluid -
40 Temp./Press. °C / kg/cm2(g) - / -
41 Cooling Water
42 C.W. Jacket l/min. ( ) Yes ( ) No (X) @ /
43 Stuff. Box l/min. ( ) Yes ( ) No (X) @ /
44 Pedestal l/min. ( ) Yes ( ) No (X) @ /
45 Temp./Press. °C / kg/cm2(g) 26 / 7.5
46 MATERIAL
47 Impeller 304 SS Gasket V#7010 or Eq.
48 Shaft 304 SS O-Ring -
49 Shaft sleeve 304 SS Shaft Seal V#8132 or Eq.
50 Mounting Flange 304 SS
51 ACCESSORIES
52 (X) Coupling (X) Mounting Flange (X) Shaft Sleeve MOTOR
53 (X) Coupling Guard (X) Mounting Gasket (X) Gasket Supplied by @
54 ( ) Pressure Unit (X) Bolt & Nut (X) Special Tool (If need) Mounted by @
55 ( ) Auxiliary Piping (X) Reducer Mfr. @
56 PAINTING Type @
57 ( ) Yes ( ) No (X) C.S. only Rated Output / Amp. kW / A @ / @
58 Pole / Revolution P / rpm @ / @
59 WEIGHT Phase / Cycle / Volt P / Hz / V 3 / 50 / 415
60 Erection kg @ Exp.Proof Class (*2)
61 Empty kg @ Bearing @
62 Operating kg @ Lubricating @
63 REMARKS A-weighted sound pressure level
64 (equip. side 1m) dBA 85
65 '@' Marks to be decided by Vendor. REDUCER
66 (*1) Estimated mounting nozzle height is 150mm. Mfr. @
67 (*2) Refer to "HAZARDOUS AREA CLASSIFICATION PLAN" Type Gear
68 Reduction ratio @
69 Revolution In / Out rpm @
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 81 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 AGITATOR DATA SHEET Doc. No. PDPP-DS-A505
3 Project Name PDP Project
4 Item No. PDE-A-505 Job No. E029636001
5 Service V-505 Agitator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code -
8 Type Propeller No. of Stage 1
9 OPERATING CONDITION
10 Liquid Name P Operating in Empty Tank ( ) Yes (X) No
11 Liquid Volume / B.H.P.
12 Press.(Nor. / Des.) kg/cm2(g) ATM / F.W. + 100 / -50 mmWC(g) Min. m3 / kW /
13 Temp.(Nor. / Des.) °C 35 / 65 Nor. m3 / kW /
14 Mixing Time - Max. m3 / kW 2.8 / Min. 1.0
15 MIXING CONDITION VESSEL DESCRIPTION
16 Material for Mixing 2EHOH / PTSA Item No. V-505
17 Charge kg/Batch 2660 Doc. No. PDPP-DS-V505
18 Flow Rate kg/h - Type Vertical
19 Temp. °C 35 Size I.D. mm 1500
20 Viscosity mPa s 6.5 HLL-Btm mm 1500
21 Density kg/m3 937 Flange Size / Rating @ / #150 SO-RF
22 CONSTRUCTION VESSEL ARRANGEMENT SKETCH
23 Mfr. -
24 Entering (X) Top ( ) Btm ( ) Side
25 Impeller Type Propeller
26 No. of Stage 1
27 Diameter mm 450
28 No. of Blade 3
29 Speed rpm @
30 Rotation(View from Driver) ( ) CW ( ) CCW (X) @
31 Baffle No. of Baffle -
32 Dimension mm -
33 Spacing from Wall mm -
34 Draft Tube Length mm -
35 Diameter mm -
36 Coil ( ) Yes (X) No
37 Power Transmission ( ) Direct (X) Gear ( ) V-belt ( ) @
38 Shaft Seal Type (X) Packing ( ) Mech. ( )@
39 Sealing Fluid -
40 Temp./Press. °C / kg/cm2(g) - / -
41 Cooling Water
42 C.W. Jacket l/min. ( ) Yes ( ) No (X) @ /
43 Stuff. Box l/min. ( ) Yes ( ) No (X) @ /
44 Pedestal l/min. ( ) Yes ( ) No (X) @ /
45 Temp./Press. °C / kg/cm2(g) 26 / 7.5
46 MATERIAL
47 Impeller 316 SS Gasket V#7010 or Eq.
48 Shaft 316 SS O-Ring -
49 Shaft sleeve 316 SS Shaft Seal V#8132 or Eq.
50 Mounting Flange 316 SS
51 ACCESSORIES
52 (X) Coupling (X) Mounting Flange (X) Shaft Sleeve MOTOR
53 (X) Coupling Guard (X) Mounting Gasket (X) Gasket Supplied by @
54 ( ) Pressure Unit (X) Bolt & Nut (X) Special Tool (If need) Mounted by @
55 ( ) Auxiliary Piping (X) Reducer Mfr. @
56 PAINTING Type @
57 ( ) Yes ( ) No (X) C.S. only Rated Output / Amp. kW / A @ / @
58 Pole / Revolution P / rpm @ / @
59 WEIGHT Phase / Cycle / Volt P / Hz / V 3 / 50 / 415
60 Erection kg @ Exp.Proof Class (*2)
61 Empty kg @ Bearing @
62 Operating kg @ Lubricating @
63 REMARKS A-weighted sound pressure level
64 (equip. side 1m) dBA 85
65 '@' Marks to be decided by Vendor. REDUCER
66 (*1) Estimated mounting nozzle height is 150mm. Mfr. @
67 (*2) Refer to "HAZARDOUS AREA CLASSIFICATION PLAN" Type Gear
68 Reduction ratio @
69 Revolution In / Out rpm @
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 82 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 AGITATOR DATA SHEET Doc. No. PDPP-DS-A515
3 Project Name PDP Project
4 Item No. PDE-A-515 Job No. E029636001
5 Service V-515 Agitator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code -
8 Type Propeller No. of Stage 1
9 OPERATING CONDITION
10 Liquid Name P Operating in Empty Tank ( ) Yes (X) No
11 Liquid Volume / B.H.P.
12 Press.(Nor. / Des.) kg/cm2(g) ATM / F.W. + 100 / -50 mmWC(g) Min. m3 / kW /
13 Temp.(Nor. / Des.) °C 35 / 65 Nor. m3 / kW /
14 Mixing Time - Max. m3 / kW 10.5 / Min. 3.7
15 MIXING CONDITION VESSEL DESCRIPTION
16 Material for Mixing 2EHOH / NCR Item No. V-515
17 Charge kg/Batch 8680 Doc. No. PDPP-DS-V515
18 Flow Rate kg/h - Type Vertical
19 Temp. °C 35 Size I.D. mm 2300
20 Viscosity mPa s 5.4 HLL-Btm mm 2380
21 Density kg/m3 823 Flange Size / Rating @ / #150 SO-RF
22 CONSTRUCTION VESSEL ARRANGEMENT SKETCH
23 Mfr. -
24 Entering (X) Top ( ) Btm ( ) Side
25 Impeller Type Propeller
26 No. of Stage 1
27 Diameter mm 600
28 No. of Blade 3
29 Speed rpm @
30 Rotation(View from Driver) ( ) CW ( ) CCW (X) @
31 Baffle No. of Baffle -
32 Dimension mm -
33 Spacing from Wall mm -
34 Draft Tube Length mm -
35 Diameter mm -
36 Coil ( ) Yes (X) No
37 Power Transmission ( ) Direct (X) Gear ( ) V-belt ( ) @
38 Shaft Seal Type (X) Packing ( ) Mech. ( )@
39 Sealing Fluid -
40 Temp./Press. °C / kg/cm2(g) - / -
41 Cooling Water
42 C.W. Jacket l/min. ( ) Yes ( ) No (X) @ /
43 Stuff. Box l/min. ( ) Yes ( ) No (X) @ /
44 Pedestal l/min. ( ) Yes ( ) No (X) @ /
45 Temp./Press. °C / kg/cm2(g) 26 / 7.5
46 MATERIAL
47 Impeller 304 SS Gasket V#7010 or Eq.
48 Shaft 304 SS O-Ring -
49 Shaft sleeve 304 SS Shaft Seal V#8132 or Eq.
50 Mounting Flange 304 SS
51 ACCESSORIES
52 (X) Coupling (X) Mounting Flange (X) Shaft Sleeve MOTOR
53 (X) Coupling Guard (X) Mounting Gasket (X) Gasket Supplied by @
54 ( ) Pressure Unit (X) Bolt & Nut (X) Special Tool (If need) Mounted by @
55 ( ) Auxiliary Piping (X) Reducer Mfr. @
56 PAINTING Type @
57 ( ) Yes ( ) No (X) C.S. only Rated Output / Amp. kW / A @ / @
58 Pole / Revolution P / rpm @ / @
59 WEIGHT Phase / Cycle / Volt P / Hz / V 3 / 50 / 415
60 Erection kg @ Exp.Proof Class (*2)
61 Empty kg @ Bearing @
62 Operating kg @ Lubricating @
63 REMARKS A-weighted sound pressure level
64 (equip. side 1m) dBA 85
65 '@' Marks to be decided by Vendor. REDUCER
66 (*1) Estimated mounting nozzle height is 150mm. Mfr. @
67 (*2) Refer to "HAZARDOUS AREA CLASSIFICATION PLAN" Type Gear
68 Reduction ratio @
69 Revolution In / Out rpm @
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 83 of 704
MITSUBISHI CHEMICAL CORPORATION CONFIDENTIAL
1 Customer Bharat Petroleum Corporation Limited
2 AGITATOR DATA SHEET Doc. No. PDPP-DS-A555
3 Project Name PDP Project
4 Item No. PDE-A-555 Job No. E029636001
5 Service V-555 Agitator No. Req'd Working 1 Spare 0 Total 1
6 Regulation - Location ( ) Indoor (X) Outdoor
7 Code -
8 Type Propeller No. of Stage 1
9 OPERATING CONDITION
10 Liquid Name P Operating in Empty Tank ( ) Yes (X) No
11 Liquid Volume / B.H.P.
12 Press.(Nor. / Des.) kg/cm2(g) ATM / F.W. + 100 / -50 mmWC(g) Min. m3 / kW /
13 Temp.(Nor. / Des.) °C 30 / 65 Nor. m3 / kW /
14 Mixing Time - Max. m3 / kW 3.3 / Min. 1.1
15 MIXING CONDITION VESSEL DESCRIPTION
16 Material for Mixing HA / MQ Item No. V-555
17 Charge kg/Batch 2870 Doc. No. PDPP-DS-V555
18 Flow Rate kg/h - Type Vertical
19 Temp. °C 30 Size I.D. mm 1500
20 Viscosity mPa s 1.6 HLL-Btm mm 1740
21 Density kg/m3 880 Flange Size / Rating @ / #150 SO-RF
22 CONSTRUCTION VESSEL ARRANGEMENT SKETCH
23 Mfr. -
24 Entering (X) Top ( ) Btm ( ) Side
25 Impeller Type Propeller
26 No. of Stage 1
27 Diameter mm 500
28 No. of Blade 3
29 Speed rpm @
30 Rotation(View from Driver) ( ) CW ( ) CCW (X) @
31 Baffle No. of Baffle -
32 Dimension mm -
33 Spacing from Wall mm -
34 Draft Tube Length mm -
35 Diameter mm -
36 Coil ( ) Yes (X) No
37 Power Transmission ( ) Direct (X) Gear ( ) V-belt ( ) @
38 Shaft Seal Type (X) Packing ( ) Mech. ( )@
39 Sealing Fluid -
40 Temp./Press. °C / kg/cm2(g) - / -
41 Cooling Water
42 C.W. Jacket l/min. ( ) Yes ( ) No (X) @ /
43 Stuff. Box l/min. ( ) Yes ( ) No (X) @ /
44 Pedestal l/min. ( ) Yes ( ) No (X) @ /
45 Temp./Press. °C / kg/cm2(g) 26 / 7.5
46 MATERIAL
47 Impeller 304 SS Gasket V#7010 or Eq.
48 Shaft 304 SS O-Ring -
49 Shaft sleeve 304 SS Shaft Seal V#8132 or Eq.
50 Mounting Flange 304 SS
51 ACCESSORIES
52 (X) Coupling (X) Mounting Flange (X) Shaft Sleeve MOTOR
53 (X) Coupling Guard (X) Mounting Gasket (X) Gasket Supplied by @
54 ( ) Pressure Unit (X) Bolt & Nut (X) Special Tool (If need) Mounted by @
55 ( ) Auxiliary Piping (X) Reducer Mfr. @
56 PAINTING Type @
57 ( ) Yes ( ) No (X) C.S. only Rated Output / Amp. kW / A @ / @
58 Pole / Revolution P / rpm @ / @
59 WEIGHT Phase / Cycle / Volt P / Hz / V 3 / 50 / 415
60 Erection kg @ Exp.Proof Class (*2)
61 Empty kg @ Bearing @
62 Operating kg @ Lubricating @
63 REMARKS A-weighted sound pressure level
64 (equip. side 1m) dBA 85
65 '@' Marks to be decided by Vendor. REDUCER
66 (*1) Estimated mounting nozzle height is 150mm. Mfr. @
67 (*2) Refer to "HAZARDOUS AREA CLASSIFICATION PLAN" Type Gear
68 Reduction ratio @
69 Revolution In / Out rpm @
70
71 <1> 11 Mar. 2016 T.Tanaka M.Matsuyama J.Takahashi Revision up
72 <0> 17 Jan. 2016 T.Tanaka M.Matsuyama J.Takahashi Original
73 Rev. Date Prepared Checked Approved Description
Page 84 of 704
Page 85 of 704
Page 86 of 704
Page 87 of 704
Page 88 of 704
Page 89 of 704
Page 90 of 704
EQUIPMENT
DIVISION
Page 91 of 704
CHAPTER-5
CONFIDENTIAL
Page 92 of 704
MITSUBISHI CHEMICAL CORPORATION PDP Project
REVISION 1
11 Mar. 2016
CONTENTS
Page 2 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 93 of 704
MITSUBISHI CHEMICAL CORPORATION PDP Project
REVISION 1
11 Mar. 2016
Page 3 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 94 of 704
MITSUBISHI CHEMICAL CORPORATION PDP Project
REVISION 1
11 Mar. 2016
5.1.1 General
This document provides the information to achieve safe and stable operation of
Acrylate plant and shall be referred / accommodated in detailed engineering.
5.1.2.1 Polymerization
The polymerization of Acrylic Acid and Acrylate causes blockage in the equipment
and piping. To avoid the polymerization, countermeasures shown as below shall
be taken into account for the process equipment and piping which have possibility
to make polymerization.
- Stagnation of liquid shall be minimized
- Condensation shall be avoided
- Inhibitors and air shall be provided adequately to process liquid
- Contamination of foreign objects causing polymerization shall be avoided
5.1.2.2 Odor
Since Acrylic Acid and Acrylate have foul odor, countermeasures against leakage
shall be incorporated in the plant design.
5.1.3 Analysis
Acrylic Acid and Acrylate are easy to polymerize. Analysis itself is a point of vital
importance for stable operation with good product and polymerization prevention,
as the analysis result leads to the correct operation conditions. Analytical
requirements and information, such as “Chemicals to analyze”, “Sampling point”,
“Frequency of sampling”, “Analytical method for raw materials or stream products”
and so on, are referred to “Chapter 22 ANALYSIS EQUIPMENT INFORMATION”.
Page 4 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 95 of 704
MITSUBISHI CHEMICAL CORPORATION PDP Project
REVISION 1
11 Mar. 2016
5.2.1 General
This paragraph describes design requirement from process features which shall
be accommodated in detailed engineering stage.
5.2.2 Equipment
5.2.2.1 General
(1) For welding on internals and inner surfaces of equipment, double fillet welding or
full penetration and continuous butt welding shall be used without gaps. Socket
welds are not allowed for any of the equipment. After welding, be sure to
thoroughly finish and clean the welding lines to ensure that there are no adverse
affects on the product quality. All welding lines on the inner surfaces of equipment
must be smoothly finished by a grinder. Moreover, all welding lines that contact
the process fluid should be finished by acid-pickling and rinsed with fresh water
(e.g., boiler feed water) to remove particles and dust on the surfaces.
(2) All butt joints in the shell and head shall be welded by full penetration welding
without backing strip for process equipment. This requirement shall also apply to
the welded joints between the bodies and nozzles. Even a small gap may lead to
the accumulation of stagnant fluid and which may cause polymerization.
(3) Gap, crevice and/or groove on any joint of equipment shall not be provided to
prevent the stagnation of fluid has possibility of polymerization. For this purpose,
such as Bell-and-Spigot type joint or Tang-and-Groove flange shall not be applied.
Unless otherwise specified in PDP documents, Modified Male and Female type
flange (refer to Fig.-1 below) is preferable for equipment girth flanges or heat
exchanger channel head flanges with PTFE solid sheet gasket under the vacuum
condition.
Page 5 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 96 of 704
MITSUBISHI CHEMICAL CORPORATION PDP Project
REVISION 1
11 Mar. 2016
Gasket
Gasket
(4) Dead space (the part which has possibility of fluid stagnation) in equipment shall
not be allowed to prevent the polymerization. Any design changes in detailed
engineering stage leading to make dead space shall not be allowed without
permission of LICENSOR. This change includes, for instance, the addition of
nozzles or the change of instrument type, etc.
(5) Weep holes for internals and devices on equipment shall be provided for complete
drainage.
5.2.2.2 Reactor
Esterification Reactor
To prevent polymerization in the reactor, spray of process liquid with inhibitors
shall be provided for all inner surfaces in gas phase zone of the reactor including
agitator installation nozzles. Actual arrangement of spray nozzle location shall be
designed and finalized in detailed engineering stage according to process
requirements specified on the reactor data sheet.
5.2.2.3 Column
(1) Column and internals shall be designed so as to remove polymers easily which
might be formed and accumulated inside. Following structures are applied to the
design in detailed engineering stage;
Minimum dead space
Welding with smooth finished structure for not removable internal parts
Bolt and nut tighten structure for removable internal parts
Page 6 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 97 of 704
MITSUBISHI CHEMICAL CORPORATION PDP Project
REVISION 1
11 Mar. 2016
(2) The levelness of trays and trough-type distributors shall be as shown below.
Inside Tower Diameter (mm) Max Levelness (mm),(Note 1)
1500 and under 2
from 1501 up to 2500 3
from 2501 up to 4000 4
from 4001 up to 5000 5
Note 1: “Levelness” refers to the difference between the highest point and the
lowest point out of at least 5 equivalently spread points.
[ Type-A ] [ Type-B ]
Standard Type For 5 tubes
Page 7 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 98 of 704
MITSUBISHI CHEMICAL CORPORATION PDP Project
REVISION 1
11 Mar. 2016
5.2.2.5 Drum
Feed nozzles of liquid from overhead condenser and vent condenser to reflux
drum shall be connected to side of shell and lower than LLL (Low Liquid Level) as
shown in Fig.-3. Unless otherwise specified in P&ID or EQUIPMENT DATA
SHEET, inner pipe shall not be provided to prevent polymerization.
Fig.-3: Liquid Inlet Nozzle of Reflux Drum
From Condenser
Reflux Drum
5.2.2.6 Tank
(1) Tank roofs with butt welding or double fillet welding as shown in Fig.-4 below shall
be applied.
Fig.-4: Fillet Welding of Tank Roof
Page 8 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 99 of 704
MITSUBISHI CHEMICAL CORPORATION PDP Project
REVISION 1
11 Mar. 2016
(2) In order to eliminate dead space from tank inner surface, following construction
shown in Fig.-5 shall be applied.
Roof rafters shall be installed above roof (outside of tank)
Roof plate and shell plate shall be welded and smoothed
Fig.-5: Structure of Tank Roof
(3) Liquid circulation lines for the tank shall be installed to achieve good mixing for
minimizing temperature difference and inhibitors maldistribution at any part of tank
inside.
5.2.2.7 Pump
(1) Mechanical seal system
(a) Mechanical seal system for the process pumps might have leakage trouble by
polymerization of process liquid and crystallization of inhibitors in process liquid.
Hence, the most suitable mechanical seal system shall be selected for such fluid
properties. TANKEN SEAL SEIKO Co., Ltd. or John Crane are required as
mechanical seal Vendor because LICENSOR has many experiences applying
their mechanical seals for Acrylate process pumps.
(b) Following table gives reference specifications about mechanical seals for
process pumps in the existing and/or the past licensed plant.
Fluid BA / HA HE
Single Single
Type
Stationary Stationary
Seal face WC/WC WC/WC
Back metal Titan Hastelloy-C
Secondary seal O ring (Chemraz) Metal bellows
Page 9 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 10 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.2.3 Piping
(1) For welding of process piping, full penetration and continuous butt welding shall
be used. Socket welds are not allowed. Projection of weld metal into pipe bore
shall be minimized. Welding by GTAW (Gas Tungsten Arc Welding) for first layer
of all process piping is required except for the double welding. After welding, be
sure to thoroughly finish and clean the lines to ensure that there are no adverse
affects on the product quality.
Moreover, all piping welding lines of more than 20” diameter that contact the
process fluid shall be finished smoothly by a grinder and acid-pickling, and rinsed
with fresh water to remove particles and dust on the surface.
(2) Flange quantities in piping system shall be minimized for process line except for
flanges necessary for facilitate cleaning, maintenance and inspection.
(3) For process liquid lines, piping slopes shall be designed to ensure the complete
drainage of the process liquid from the drain nozzles. For gas and/or vapor lines,
“no pocket” piping layout shall be designed to ensure the complete drainage of
process liquid condensate from gas and/or vapor.
(4) “Min.” in the P&ID represents the constructive minimum distance requirement for
piping. The minimum distance construction of piping prevents polymerization by
reducing the stagnation in piping which might become a dead end. EPC
Contractor shall carefully comply with the minimum distance construction
specified on the P&ID in detailed engineering stage. As a best way, the fittings
such as flange (WN Flange or Stub-end for Lap joint) and tees should be welded
directly to construct minimum distance. When the adjustment of the distance
between them is necessary, the short pipe piece can be inserted under the above
mentioned purpose. In this case, the enough consideration for the practical
fabrication procedure shall be done. A target value of the “Min.” distance from
COP (Center of Pipe) to flange face is shown as follows.
Main Pipe Min. Distance
Size [mm]
1”or less Not more than 100
1_1/2”-4” Not more than 200
6” or above Not more than 300
(5) Liquid circulation lines shall be installed to pipe line between process area and
tank yard area for BA, HA and HE services to prevent blockage caused by
stagnation of liquid. Required specifications for these lines are as follows.
Page 11 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Min. Min.
FI
Page 12 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Fig.-6-III: Piping around Flow Meter (excluded area) and Control Valve
(7) All drain nozzles shall be straight line until drain valve.
(8) Length of forced circulation reboiler loop line and film evaporator bottom line shall
be shortened to reduce retention time because it affects process performance.
(9) Air Distributer for reboiler circulation line shown in P&ID shall be finalized in
detailed engineering stage referring to schematic drawing shown in “Chapter 16.8
PIPING PARTS INFORMATION”. Requirement (hole size and numbers) for each
nozzle is shown on P&ID.
(10) Strainer washing box for washing of strainer element shall be provided near
process pump strainer on Grade. Schematic drawing of strainer washing box are
referred to “Chapter 16.8 PIPING PARTS INFORMATION”. Actual location of
strainer washing box shall be decided in detailed engineering stage referring to
“Chapter 12. GENERAL PLOT PLAN” and “Chapter 13. EQUIPMENT PLOT
PLAN”.
5.2.4.1 General
This paragraph describes insulation and tracing requirements to prevent the
condensation of process fluids in equipment, piping, and instrument piping.
Installation required portion of tracing and/or insulation are shown in P&ID and/or
EQUIPMENT DATA SHEET individually in process requirement point of view.
Page 13 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
DATA SHEET.
(a) Selection of LLS or MS tracing system
These systems are to prevent condensing of process vapor (e.g. in distillation
column shell or inside of overhead lines) and/or increasing HE viscosity. Selection
either LLS tracing system or MS tracing system are specified in P&ID and
EQUIPMENT DATA SHEET in accordance with operating temperature of process
fluid.
(b) Thermal insulation slip
Thermal insulation slip (referring to Fig.-7 bellow) shall be installed between tracer
and process line to avoid local heating of process line.
Page 14 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
(3) In general, NPS 1/2 carbon steel tracing pipe is applied for all tracing systems,
however only in case carbon steel pipe is not possible to install relatively tangled
portion such as around instruments equipment, OD 10mm / ID 8mm tube can be
used as alternative.
(4) Tracing line specifications (tracer size and quantities) with respect to each
process line size and length are shown in following tables as LICENSOR’s past
experiences. Required tracing line quantities shall be verified and determined
according to site conditions considering with actual selected insulation
specifications in detailed engineering stage.
(a) Steam Tracing
Steam Tracing
Process Line (NPS)
(LLS,MS)
Steam Tracing
(6) Flanges and connections for tracers should be installed at the same place of
process lines’ flanges so as to facilitate piping / equipment maintenance. Also joint
of tracer is recommended to be placed outside of process line insulation.
5.2.5 Civil
Liquid Acrylic Acid (AA) and Solid or Solution of Para Toluene Sulfonic Acid
(PTSA) have corrosive property. Anticorrosive countermeasures for civil structure
are required to consider for the following places having chance of exposing to AA
or PTSA. (For example, Acid resistant concrete)
(a) Mandatory Place
Inside of WW Pit and Oil Pit
(b) Recommended Place
On the surfaces of concrete or civil structure around AA or PTSA handling
equipment (especially for pump base).
Inside of trench around AA or PTSA handling equipment
Corrosivities of AA and PTSA against structural materials are referred to following
table.
Page 16 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
liquid acrylic acid CH2CHCOOH yes 1 to 2 - Yes strong medium medium weak strong weak
Pala toluene
liquid sulfonic acid CH3C6H4SO3H yes 1 to 2 - yes strong strong medium medium strong strong
solution
Pala toluene
solid CH3C6H4SO3H yes 1 to 2 - yes strong strong medium medium strong strong
sulfonic acid
Page 17 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 18 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.3.1 General
This paragraph describes considerations and/or study items shall be performed in
detailed engineering stage referring to PDP. In general, descriptions in this
paragraph are not strongly related to process requirements, therefore this
paragraph does not contain the descriptions listed in the Paragraph 5.2 above.
Any design changes related to process requirements specified in PDP shall be
informed to LICENSOR for the review and the approval in case the design
changes are executed in detailed engineering stage.
5.3.4.2 Insulation
Insulation thickness is specified in Line List based on “Chapter 2. DESIGN
CRITERIA”, it shall be verified and finalized in detailed engineering stage
according to selected insulation material and/or LICENSEE’s standards.
Page 19 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 20 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.3.7 Equipment
5.3.7.1 General
In general, process requirements are specified in EQUIPMENT DATA SHEET of
PDP. However, specifications (such as dimension of parts, nozzle position, nozzle
orientation, etc.) other than specified in EQUIPMENT DATA SHEET shall be
decided in detailed engineering stage considering with its purpose or operability,
maintainability and etc. In case these specifications are to be decided by
LICENSEE or EPC Contractor, its relative position shall be kept as process
requirements described in the EQUIPMENT DATA SHEET of PDP.
5.3.7.2 Column
(1) Column diameter is specified as preliminary sizes, it shall be verified based on the
process requirements described in data sheet and shall be modified accordingly, if
necessary.
(2) Feed inlet nozzles and reboiler return nozzles shall be verified based on the
process requirements which is described in data sheet and shall be modified
based on vendor’s information in detailed engineering stage, if necessary.
(3) Tray plate shall be designed that tray plate is tighten with bolt, nut and washers so
as to set and remove easily.
Page 21 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.3.7.4 Tank
Design of “Air Foam Chambers” for all required tanks shall be executed in detailed
engineering stage.
5.3.7.5 Pump
(1) Pump head specified on data sheet is calculated based on the estimated piping
length and number of fittings etc., it shall be verified and finalized based on the
piping routing plan in detailed engineering stage. Design pressure for equipment
and instrument shall be modified according as final shut off pressure in detailed
engineering stage.
(2) Motor rated output specified on data sheet is preliminary figure, it shall be verified
and finalized based on the vendor’s information.
(3) Pump capacities (Minimum, Normal and Design) specified on data sheet do not
include any minimum flow rate, it shall be requested pump vendor to specify the
required minimum flow rate.
(4) Estimated system and size of cooling water lines and flushing lines for pump were
specified on P&ID. It shall be verified / finalized in detailed engineering stage.
5.3.7.7 Desuperheater
Minimum flow rates for desuperheater are based on PDE-400 operation assuming
PDE-500 is under switch operation. Minimum condition shall be finalized in
detailed engineering stage considering operation case.
Page 22 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.3.7.8 Hoist
Hoist is recommended to install in operability point of view. EPC Contractor shall
finalize specifications of hoist considering with shape of inhibitor paper bag,
Vendor’s information and final plot plan in detailed engineering stage.
Recommended location to install hoist is;
Above Inhibitor / PTSA drum (for lifting up of inhibitor paper bag)
5.3.8 Piping
(1) In general, mechanical design of piping shall be performed in accordance with
ASME B31.3.
(2) In detailed engineering stage, thermal stress analysis of piping should be
conducted which operating temperature shown in line list exceeds 100 deg.C. For
piping which the results of the analysis show excess in allowable stress or
moment and considered to have detrimental distortion, the piping systems shall
be designed so that they have adequate flexibility by installing expansion joints or
reinforcing equipment nozzles, etc.
(3) If low point drain nozzles other than specified in P&ID of PDP are found necessary
to install according to actual piping routing plan in detailed engineering stage, it
shall be added in consideration of complete drainage from the pipelines after the
shutdown operation.
(4) Equipotential bonding shall be provided considering the requirement of local
regulations, laws or LICENSEE’s standards in detailed engineering stage.
Page 23 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
(5) Details of Air Regulator for process vent gas line shown in P&ID shall be finalized
in detailed engineering stage referring to schematic drawing shown in “Chapter
16.8 PIPING PARTS INFORMATION”.
5.3.9 Instrument
(1) All pressure data on pump discharge line are specified based on estimated pump
head calculation, it shall be reviewed and finalized accordingly based on the
piping routing plan in detailed engineering stage.
(2) Elevation (static head) is not considered for the pressure data in the Instrument
List. The pressure data shall be finalized in detailed engineering stage considering
with its installed elevation.
(3) Minimum flow rates for PDE-700 are based on PDE-400 operation assuming
PDE-500 is under switch operation. Minimum condition shall be finalized in
detailed engineering stage considering operation case.
5.3.10 Electrical
Motor List
All motor outputs mentioned on motor list is estimated figures, it shall be reviewed
and finalized based on vendor’s information in detailed engineering stage.
5.3.11 Civil
(1) Base Level is assumed as EL +/- 0m and set as floor level of Process Area, Pipe
Rack and Intermediate Tank Yard Area in PDP. Actual altitude of each level shall
be decided in detailed engineering stage.
(2) Anti-vibration design for structure and for foundation of rotating equipment shall be
provided in accordance with the selected vendor’s information (dynamic load etc.).
5.3.12 Others
(1) Firefighting system
Firefighting system (including air foam chamber for tanks) shall be designed by
EPC Contractor in detailed engineering stage in accordance with applicable laws,
codes, local regulations, and/or LICENSEE’s standards.
Page 24 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
(b) Eye washer and safety shower should be installed nearby sample box and
strainer washing box for operator’s safety as recommendation of LICENSOR.
Refer to Attachment 1.
Page 25 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
SHEET 1 OF 2
6.1 PURPOSE :
6.2 OPERATION : FLOW RATE THROUGH VESSEL: (m3/hr)
6.3 BATCH OPERATION TIME : RETENSION TIME (HR):
6.4 CONTINOUS FLOW RATE REQUIRED WITHIN THE TANK (min.) m3/hr RATED : MAX. :
6.5 OPERATING PRESSURE (Kg/cm² g) : OPERT. TEMP(°C) : SOLIDS PRESENT : TYPE & SIZE:
6.6 FOAM TENDENCY : SOLUBILITY :
6.7 DEGREE OF AGITATION ABRASION :
6.8 CORROSIVE PRODUCTS SETTLING :
6.9 PROCESS LIMITATION (IF ANY) : NONE H.P. TIP SPEED SPACE TORQUE SEE NOTES
8.0 CONSTRUCTION
8.1 VESSEL : ITEM NO. : DRG. NO. SUPPLY BY OTHERS BY VENDOR LINING NO YES
8.2 VOLUME: DIA/SIDE (mm) : HEIGHT/LENGTH (mm) : THICKNESS (mm)
8.3 TOP : OPEN : CLOSED TYPE FLAT DISHED MIXER MOUNTING NOZZLE SIZE (mm DIA.):
8.4 BOTTOM : FLAT DISHED CONICAL DEPTH OF BOTTOM FROM WLF/TANGENT LINE (mm) :
8.5 BAFFLES : NO YES VENDOR TO SUGGEST TYPE NO. : SIZE(L x W x T)/DIA (mm)
8.6 BAFFLE SPACING FROM WALL (mm) : HEATING COILS PROVIDED : NO YES SIZE
8.7 LIQUID LEVEL (INCH FROM WELD/TANGENT LINE) : NORMAL : MIN. MAX.
8.8 MOUNTING SPACE FOR MIXER AVAILABLE AMPLE RESTRICTED (mm) ACTUALLY REQD. (mm)
8.9 MIXER : LOCATION SIDE ENTRY TOP ENTRY BOTTOM ENTRY PORTABLE MOTOR/GEARBOX MOUNTING: HORIZONTAL VERTICAL
8.10 MOUNTING : CLAMPED FLANGED MOUNTING ANGLE : INSTALLATION HEIGHT REQUIRED: mm
8.11 SHAFT SEAL : MECH SEAL STUFF. BOX LABYRINTH SEAL VAPOR SEAL
8.12 MAKE TYPE : CLASS SIZE :
8.13 MTRL. NO. OF RINGS : LANTERN RINGS YES NO
8.14 SHUT-OFF DEVICE WITH : (A) TANK FULL YES NO (B) UNDER PRESSURE YES NO
10.0 CHARACTERISTICS
X
NO. DATE REVISION BY CHK APP
This drawing and the design it covers are the property of ENGINEERS INDIA LIMITED. They are merely loaned and on the borrower's express agreement that they will not be reproduced, copied, loaned, exhibited, nor
used except in the limited way and private use permitted by any written consent given by the lender to the borrower. CONFIDENTIAL Property of ENGINEERS INDIA LTD. To be used or reproduced only with the written
permission of Engineers India Ltd.
FORMAT NO. 4-1646-0102 REV. 2 (20.12.2011) A4-210 X 297
SHEET 2 OF 2
11.0 PERFORMANCE
11.1 HORSE POWER ABSORBED : (A) WITH BAFFLE: (B) WITHOUT BAFFLES : POWER NO. USED
11.2 BASIS OF POWER CALCULATION :
11.3 EFEECT OPER. TIME : RECYCLE TIME TANK-TURN-OVER RATE :
11.4 CRITICAL SPEED OF MIXER (RPM) OPERATING SPEED AS PERCENTAGE OF CRITICAL SPEED :
11.5 SEAL FLUSHING : YES NO API PLAN SEAL COOLING (SEE NOTE-6): REQUIRED NOT REQUIRED
11.6 EFFECTIVE SPHERICAL RADIUS OF AGITATION : THEO : (mm)
11.7 GUARANTEE FURNISHED : MECHANICAL PERFORMANCE SMOOTH OPERATION
12.0 TESTING
13.0 MISCELLANEOUS
NOTES :
1 BIDDER SHALL FURNISH ALL RELEVANT DATA FOR EACH MIXER ALONG WITH THE BID AS PER VENDOR DATA REQUIREMENTS.
2 BIDDER TO CONFIRM IF DYNAMIC BALANCING TEST IS A REQUIREMENT FOR THIS ITEM
3 BIDDER TO FURNISH THE EXACT MATERIAL INDICATING DESIGNATION ETC. FOR ALL MATERIALS QUOTED
4 BIDDER TO FURNISH LIST OF TWO (2) YEARS OPERATION SPARES AND INDICATE IF COMMISIONING SPARES WILL BE REQUIRED.
5 CORROSION ALLOWANCE EQUAL TO SPECIFIED FOR VESSEL/TANK SHALL BE CONSIDERED FOR EACH EXPOSED SURFACE.
6 ALL INSTRUMENTS/EQUIPMENTS/ACCESSORIES REQUIRED FOR SEAL COOLING TO MEET BATTERY LIMIT CONDITIONS SHALL BE SUPPLIED BY VENDOR
7 REFERENCE DOCUMENTS:
X
NO. DATE REVISION BY CHK APP
This drawing and the design it covers are the property of ENGINEERS INDIA LIMITED. They are merely loaned and on the borrower's express agreement that they will not be reproduced, copied, loaned, exhibited, nor
used except in the limited way and private use permitted by any written consent given by the lender to the borrower. CONFIDENTIAL Property of ENGINEERS INDIA LTD. To be used or reproduced only with the written
permission of Engineers India Ltd.
FORMAT NO. 4-1646-0102 REV. 2 (20.12.2011) A4-210 X 297
f
REVISED AND RE-ISSUED AS STANDARD
5 29.10.2014 VDY IK/ SKM
SPECIFICATION
REVISED AND RE-ISSUED AS STANDARD
4 11.03.2010 AK SKM/HCN AKG ND
SPECIFICATION
REAFFIRMED AND RE-ISSUED AS
3 22.07.2004 AK KKG RKA SKG
STANDARD SPECIFICATION
Standards Standards
Committee Bureau
Rev. Prepared Checked
Date Purpose Convenor Chairman
No by by
Approved by
Abbreviations:
BB Bolting Bar
D/C Downcomer
M/W Manway
TSR Tray Support Ring
SLOTS Slots are provided for adjustments of the tray segments. Vessels are made
to manufacturing tolerances which are fully accounted for in Distillation
Tray design.
SPACINGS Spacings of loose beams or deck plates shown on drawings are TYPICAL
for perfectly round and sized vessels. The vessels may not be perfect, so
spacings will need to be ADJUSTED.
CONTENTS
1.0 INTRODUCTION 4
8.0 DISTRIBUTORS/REDISTRIBUTORS 12
13 .0 LEAK TESTING 16
14.0 REMOVAL OF LINSEED OIL COATING FROM CARBON STEEL TRAYS AND
INTERNALS 16
1.0 INTRODUCTION
Whether installation involves a small number of trays, tower internals or is a large complex
involving thousands of components, it is vital that care is taken to ensure efficient handling
and assembly of tray components.
This specification should be used only as a "General Guide". The work in each tower and for
each tray/tower internal should be carried out in accordance with General Arrangement
Drawings prepared for specific tray/tower internal.
An adequate number of components with installation spares, where applicable, are supplied
for every assembly. Significant time and Cost can be saved by efficient storage and usage of
such components.
2.1 Review the drawings provided for respective tray/tower internals. It is an important aid for
installation. The drawings show the relative position of each component and corresponding
item number. After all trays/tower internals are uncrated, identify each piece of the tray/tower
internal with the item number w.r.t. its location on the General Arrangement Drawing.
2.2 Ensure that protective oil coating is removed from carbon steel tray/tower internal parts prior
to initiating installation of trays and tower internals in the tower. (For suggested procedure
for removal of linseed oil coating, refer clause 14.0 of this specification).
2.3 Check levelness of tray support rings & various dimensions of bolting bar welded to the
tower to ensure that these are as per relevant drawings and within specified tolerances. In
case of any deviation observed, refer this to EIL-HMTD. Levelness of support ring and other
dimensions of bolting bar shall be recorded in Format attached in EIL Specification No. 6-
14-0016.
2.4 Trays
2.4.3 Fit and leak test seal pan below bottom tray, if provided.
2.4.7 Fit deck plates for bottom tray except man way deck plate. (However proper fitment of man
way decks plate shall be ensured).
2.4.9 Fit/install lattice girder/major beam, if required, for tray above bottom tray.
2.4.11 Fit beams and decks for tray above bottom tray except man way deck plate. (However proper
fitment of man way decks plate shall be ensured).
2.4.13 Remove all the foreign material and ensure that trays are clean and unobstructed for proper
performance.
2.5.3 Install (including welding and leak testing) vapour distributor/chimney tray/accumulator tray,
if any.
2.5.5 Pack the tower with random packings in accordance with EIL spec. 6-14-0011 titled
"Specification for Packing the Tower".
2.5.6 Install the bed limiter/hold down grid wherever specified in drawings, in case of random
packings
2.5.7 Install distributor/redistributor, Leak test pan/trough type distributor/redistributor and hydro
test spray header, if specified, on the drawings.
2.5.9 Repeat from paragraph 2.5.2 to 2.5.8 above, for the next bed.
2.5.10 Remove all the foreign material from respective tower internal. Ensure that the same are
clean and un-obstructed for proper performance.
3.1 Carefully place shims, as necessary, under major beams to bring top of beam exactly in level
with tray support ring (Refer sketch 3.1.1). Tack weld/bolt shims in position.
NOTE: Depth of stool is always designed to allow for minimum shim thickness of 3 mm
(although this may be taken up in vessel or tray manufacturing tolerances).
THICKNESS
et... OF CLAMP
BEAM
THICKNESS
y s
PROVIDE SHIMS
AS NECESSARY
3.2 Line-up down comer bolting bars, if fitted, on beam with downcomer bolting bars attached to
vessel wall. See sketch No. 3.2.1.
MAJOR BEAM
i) Level exit weir base (top) with top of support ring and/or support beam top
surface.
(b) Fit bottom downcomer sliding plate into position, position bottom of plate in
downcomer support bracket while fitting on tray below. Check clearance under
downcomer bottom edge. See Sketch No. 4.1.1.
HORIZONTAL SLOTS
IN BOLTING BAR D/C THICKNESS
EQUAL TO BEAM
TRAY DECK
END CLEARNCE TO BE IN
THICKNESS
SAME LEVEL
EXIT WEIR
— —F
TRAY DECK
FIT STANDARD TRAY
THICKNESS
EDGE CLAMP WHEN UNDER D/C CLEARANCE
BOLTING IS OMITTED
IN BOTTOM PIECE OF TOLERANCE ± 3
DOWNCOMER.
(a) Place shims, as necessary, under top downcomer section to bring exit weir base (top)
exactly in level with support ring and/or lattice girder/major beam (if provided) and
then bolt downcomer sections including exit weir securely. Tack weld/bolt shims in
position.
(b) Fit bottom-sliding plate of downcomer in position in downcomer support bracket, set
clearance under downcomer plate within plus or minus 1/8" (3mm). The clearance
obtained should be maintained as near constant across the width as possible (See
Sketch No. 4.2.1).
HORIZONTAL SLOTS
IN BOLTING BAR D/C THICKNESS
EQUAL TO BEAM
TRAY DECK
END CLEARNCE TO BE IN
THICKNESS
SAME LEVEL
EXIT WEIR
TRAY DECK
Fff STANDARD TRAY
THICKNESS
EDGE CLAMP WHEN UNDER D/C CLEARANCE
BOLTING IS OMI1TED
IN BOTTOM PIECE OF TOLERANCE ± 3
DOWNCOMER.
Unless otherwise specified on drawing, two washers (one on bolt head side & one on nut
side) shall be used for every bolt. The nut shall be provided towards the side accessible from
Tray man way. Lock nuts shall not be provided on clamp/bolting for Man way deck plate.
Nuts for supporting pipes (i.e. U clamps) shall be kept loose so as to have free
movement/expansion of the pipe.
Vent Tubes are standard feature in Three (3) / Four (4) pass trays.
(a) Fit one top section of center/off-center downcomer as in paragraph 4.1/4.2 and then
position tube as shown in Sketch 4.4.1.
(c) Place shims, as necessary, between vent tube flanges and tighten the bolts.
TOP D/C
VENT TUBE
SHIMS AS
NECESSARY
After downcomer sections have been fitted, position bracer panels and bolt securely.
Bolt loosely into position after down comer has been leveled and tightly secure. Weir top
edge then to be leveled upto desired height and bolts tightened securely. Unless otherwise
specified on the drawings, adjustable weirs to be set at mid point.
5.1 Measure distance across area of deck to be installed at 90° to run of minor beams. See Sketch
No. 5.1.1
5.2 Compare measurement taken in paragraph 5.1 with dimensions stated on tray General
Arrangement Drawings.
5.3 If comparison shows measured distance GREATER than shown on drawings, INCREASE 25
mm typical spacing difference - see Sketch No. 5.3.1.
25 mm NOMINAL GAP
TO BE OPENED OR CLOSED
(MAX 27mm, MIN 23mm)
5.4 If distance measured is SMALLER than shown on drawings, DECREASE 25mm typical
spacing between the deck plates to absorb the difference - EXCEPT at each side of man way
section, which must remain at 25 mm to allow man way clamps to operate properly. See
Sketch No. 5.3.1.
5.5 Position deck plates as required from paragraph 5.3 to 5.4 on support ring and/or down comer
top flange.
5.6 Position deck plates centrally along their length i.e. leave EQUAL clearance at each end.
NOTE: Edge clamps must be orientated correctly (see Sketch No. 5.6.1). Stud/pin of all tray
edge clamps are provided with screwdriver slot and center punch mark as aid in
installation and fitting of edge clamps properly. Slot shall be in radial direction,
while punch mark be towards center of the tower.
II II
II I
I
II II
5.7 Position man way plate in place to check that this can be put in position from top as well as
bottom of tray without fouling or interfering with man way beam clamp or adj acent tray deck
plate.
5.8 Remove man way plate and keep it on the tray or in downcomer area so that tray man ways
are accessible for inspection of trays.
5.9 Bubble cap trays, seal pans, draw off etc. shall be leak tested to ensure that drop in water
level does not exceed the specified limit mentioned in the drawing. In case the leakage
exceeds the allowable limit, consult EIL-HMTD.
5.11 Tray man way plate shall be clamped in position only after all the trays installed in the tower
have been inspected, tested and approved by competent authority.
6.1.1 Start installation with the short piece of decicing and work across the tower. When gasketing
is specified, place the gasket on the support ring. If a mid span is required, place gasket on
the mid span also. Install the support ring clamps in the deck sections; leave the clamps loose.
Place the deck section on the support ring. Place the minor beam against the edge of the deck.
Minor beams are not always required (see drawing). Install the adjacent deck section. Install
the bolting through the deck section and through the minor beams when provided. When
gasketing is required between the deck sections, the bolts should also go through the gasket.
Tighten the bolting. Continue this procedure until all deck sections are installed.
For some applications, liquid downcomer tubes are provided which hang below the deck
sections. The downcomer tubes may or may not be removable (check drawing provided).
6.1.2 When the tubes are removable they should be installed before the deck sections are installed
on the support ring.
6.1.3 For various applications, riser tubes with covers are provided (which may or may not be
removable). When the tubes or covers are removable, install the tubes with the gaskets and
bolting provided as the deck sections are being installed. When the gas riser tube covers are
removable, ensure that they are fastened firmly in place.
6.1.4 After all deck plates are installed; rotate clamps under support ring and tighten clamps.
Ensure that all gasketing is in proper position.
6.1.5 Remove all foreign material so that the support plate is clean and unobstructed for proper
performance.
6.2.1 Place the sections in position on top of the support ring starting with the shorter sections at
one side of the tower. Proceed across the tower. Make sure all sections are making proper
contact with the support ring. The sections shall be equally spaced so that the gap between
sections is uniform.
Ensure that at any location on the support plate, gap is not large enough for the random
packings to pass through.
6.2.2 When clamps are required, the clamps are to be assembled in position as the sections are set
in place. Tighten clamps after sections are properly positioned.
6.2.3 Remove all foreign material so that the support plate is clean and unobstructed for proper
performance.
7.1 After the Bed Limiter is uncrated, identify each section of the Bed Limiter with the tag
number. The tag numbers locate the relative position of the sections.
7.2 Install the packing in the tower upto the depth of the minor beams from the support ring, as
shown on the drawing provided.
7.3 Install the minor beams to the support ring as shown on the drawing in their correct
positions. Finish installing the tower packing such that packings level is same as the top of
the minor beams and support ring/support cleats.
7.4 Install the screened Bed Limiters sections. Some of the sections may require tray clamps (see
drawings). If tray clamps are required, install them in the sections before installing the
sections on the support ring/support cleats.
7.5 Bolt all the sections with the hardware provided, as shown on the drawings.
7.6 Ensure removal of all foreign materials so that the bed Limiter is clean and unobstructed for
proper performance.
7.7 Ensure that the packings do not fly from the gaps. If so, adjust/reduce the gap.
8.0 DISTRIBUTOR/REDISTRIBUTOR
8.1.1 Start installation with the short piece of deck and working across the tower. Place the gasket
on the support ring. Install the support ring clamps in the deck sections; leave the clamps
loose. Place the deck sections on the support ring. Place the minor beam, if provided, against
the edge of the deck. Gasketing is to be installed on both sides of the minor beam. Install the
bolting through the deck sections, gasketing and minor beams. Tighten the bolting. Continue
this procedure until all deck sections are installed.
8.1.2 Some applications require covers or hats over the gas riser area. Install the same.
8.1.3 When specified, the distributor shall be leak tested after installation.
8.1.4 Ensure that all foreign materials are removed so that the distributor/redistributor is clean and
unobstructed for proper performance
8.2.2 Install the tray clamps (wherever provided) loosely in the deck sections and the end closing
plates. If the plate is equipped with a center sump (see drawing), install the center sump first.
8.2.3 For some low-flow applications, gasketing is provided with the plate. If gasketing is required
(see drawing), place the gasket along with the support ring and sump top edges.
8.2.4 To install the main deck of the distributor/redistributor, begin by placing the short deck
section in its proper position on the support ring. Using the tag numbers as a guide, place the
adjacent deck section on the support ring. Bolt the deck sections together with the proper end
closing plates. If gasketing is provided with the plate, ensure providing gaskets in the joints
between the deck sections and the end closing plates. Tighten the bolting at these joints to
minimize leakage.
Some applications require covers or hats over the gas riser area. If covers are required, install
the same. Continue this, until the entire distributor/redistributor is installed.
8.2.5 After the plate is assembled on the support ring, rotate the tray clamps under the support ring
and tighten the clamps. Ensure gasketing (if required) is in proper position.
8.2.6 If parting box(es) are provided with the distributor, install the parting box brackets to the
parting box(es), then bolt this assembly in proper position on the distributor/redistributor.
8.2.7 Remove all foreign materials so that distributor/redistributor is clean and unobstructed to
ensure proper performance.
8.2.8 For some applications, distributors are provided with leveling screws. Level the troughs
wherever leveling screws are provided to bring within level as specified in the respective
drawings.
8.3.1 If mounting clips have not been previously welded to the tower wall this is to be done before
installing distributor. The drawing provided for the job will show the proper position of the
mounting clips. Layout and weld the clips in position.
8.3.2 Place the laterals in position resting on top of the bed limiter.
8.3.3 If the tower is larger than 1250 mm I D , support members are provided. When support
members are provided, they are to be installed next. Loosely bolt the support members to the
mounting clips. Lift laterals and loosely bolt laterals to support members.
8.3.4 Place the gasketing provided on top of the lateral flanges in the proper position.
8.3.5 Place header in position and loosely bolt header to clips. Then assemble bolting through
header, gasket and lateral flange. Be sure to keep gasket in proper position. Tighten lateral
flange bolting. Leave other bolting loose.
8.3.6 Install connecting pipe and flange gaskets to header and inlet nozzle. Tighten pipe flange
bolting.
8.3.8 Ensure to remove all foreign materials so that the distributor is clean and unobstructed for
proper performance.
8.4.2 If mounting clips have not been previously welded to the tower wall, this is to be done before
installing the distributor. The drawing provided for the job will show the proper position of
the mounting clips layout. Weld the clips in position.
8.4.3 Check to see that all the piping is clean and unobstructed inside.
8.4.4 Place the laterals in position resting on top of the bed limiter.
8.4.5 Place header in position and loosely bolt to wall clip. Assemble the bolting and gasket at the
inlet flange. Tighten inlet flange bolting.
8.4.6 Place the lateral pipes in position and loosely bolts to wall clips. Assemble the bolting and
gasket at the flange end. Tighten the flange bolting.
8.4.7 Secure the wall clip bolting as shown on the drawing provided.
8.4.8 Hydro tests the spray header, without spray nozzles, if specified on the drawings.
8.4.9 Assemble the spray nozzles to the header and lateral assembly as shown on the drawing
provided.
If the spray nozzles are threaded, it is recommended that an anti seize pipe thread compound
be used for installation.
If the spray nozzles are flanges, use gaskets and tighten the bolting securely.
8.4.10 The bolting provided at end of pipe (i.e. for U clamps) shall be kept loose so as to have free
movement/expansion of the pipe.
8.4.11 Check the spray pattern visually by running the pump with water. If spray pattern is
defective, replace the spray nozzle with spare spray nozzles supplied.
9.1 Review the drawing provided with the Flashing Feed Gallery plate.
9.2 Install the tray clamps loosely in the sections that go on the support ring.
9.3 For most applications, gasketing is required and is provided with the plate. When gasketing is
required, place the gasket along with the support ring.
9.4 Place the first section on the support ring and snug up the tray clamps enough to hold it in
place. Place the adjacent section on the support ring with a gasket between the two sections.
Bolt the two sections together. Install all the sections on the support ring in a similar manner.
Tighten the tray clamps and the bolting to ensure leak free operation.
In some instances, where a high gallery wall is required, more sections are provided which
need to be bolted on top of the first row of sections. If angle braces are provided, they are to
be bolted to the first row of sections. It is advisable to bolt them in place before the upper
sections are installed.
After all the sections are bolted tightly together and all the joints are gasketed, install all
bracing when required, as shown on the drawing provided. Attach wall clips as shown on the
drawing, when required.
Remove all foreign materials so that the Flashing Feed Gallery is clean and unobstructed to
ensure proper performance.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
10.2 Start installation with the short piece of decking and work across the tower.
10.3 Collector/Chimney/Accumulator trays may be provided with gaskets or may be of seal welded
construction to achieve leak tight joints.
10.4 In case trays are provided with gaskets, place the gasketing on the support Ring. Install the
support ring clamps in the deck sections and end closing plates. Leave the clamps loose.
Attach the proper end closing plate with gasket to each end of the deck sections by bolting
through the deck section, gaskets and end closing plate. Tighten the bolting. Continue this
procedure until all sections are installed.
10.5 After deck plates are installed, rotate clamps under support ring and tighten clamps. Ensure all
gasketing, when required, is in proper position.
10.6 In case of seal welding, welding to be completed after assembly of deck plates and before
building the riser height. After completion of floor level assembly and seal welding, leak test
the tray to locate deficiency of seal welding and ensure leak tightness.
Install next level of risers to build-up riser height, seal weld and leak test. Continue till tray
assembly, seal welding and leak testing is complete.
10.7 Place gas riser covers in position and bolt covers to gas riser using the bolting provided.
Tighten the bolts.
10.9 Remove all foreign materials so that collector is clean and unobstructed to ensure proper
performance.
Lattice girders, where utilized, will be of a special design to suit the job. Lattice girders are
normally provided to support Two trays/internale (i.e. top lip/flange of each primary member
supporting one tray/internal). Lattice girders are supplied in segments so as to enable
individual segment pass through the tower manhole, for final installation and welding inside
the tower.
Do not install tray, unless installation (including welding) of Lattice Girder is complete.
While tightening bolts & clamps, care should be exercised to apply proper force to avoid
deformation in clamps. A spanner with a lever arm of 200 mm (8 inch) maximum should be
employed so as to apply a torque of approximately 15 ft. Lbs. for tightening of bolts, studs &
clamps of M10 size; torque of 18-22 ft. Lbs. for tightening of bolting/clamps of M12 size and
torque of 24-36 ft. Lbs. for tightening of bolting/clamps of M16 size.
If filling the plate with water is not practical, spot leak testing should be done. Using a
small stream of water from a hose, pour water on the joints and see if leakage occurs.
The main joints to check are the joints at support ring. A small liquid pool will occur.
If leakage occurs loosen the bolting and reposition the gasketing to stop the leakage.
If leak testing cannot be done, all gaskets should be closely inspected to assure proper
gasket sealing. This can be done with a small diameter wire by probing the joint or by
light testing the joint. If holes/gaps are found, loosen joints and reposition gasket to
obtain proper sealing.
14.0 REMOVAL OF LINSEED OIL COATING FROM CARBON STEEL TRAYS AND
TOWER INTERNALS
14.2 Immerse Tray or Tower Internal component coated with linseed oil for about 10 minutes.
14.3 Remove the component, scrub with wire brush using sand followed with rinse in clean
potable water for 15 minutes.
After completion of Installation of each tray/tower internal, review the installation and report
the same in accordance with EIL specification for Review of Site Installation of Tower
internale (Specification No. 6-14-001 6).
*111-111-ti i cl i 1 kill
GENERAL SPECIFICATION
FOR WIRE MESH DEMISTERS
Abbreviations:
CONTENTS
1.0 SCOPE 4
2.0 REFERENCES 4
3.0 MATERIAL 4
5.0 SPARES 5
8.0 GUARANTEE 6
9.0 DOCUMENTATION 6
1.0 SCOPE
This specification covers the general requirements for design, fabrication, inspection and
supply of knitted wiremesh assemblies (Demisters) in duly packed condition.
The demister assembly(ies) shall consist of wiremesh pad, top and bottom holding grids,
major beams (if specified), bolting/clamps/tie rods/J-bolts/spacer pipes and any other
components which are essential to complete the demister assembly to be installed on supports
welded inside the vessel.
2.0 REFERENCES
(* Standard 7-12-0036 shall be used for reference only. Final design of demister supports shall
be as per vendor design standards/calculations and shall be submitted to EIL for review prior
to start of fabrication.)
3.0 MATERIAL
All the material used for fabrication & supply of Demister shall be new & of first quality and
shall be duly supported with material test certificates.
4.1 Basic details such as demister specification (surface area, voidage, and bulk density), material
of construction, supporting arrangement, manhole size etc. shall be as per drawings/
specification furnished by EIL.
4.2 In the General Arrangement drawing Demister Vendor shall indicate the following outside
dimensions (incase of square / rectangular demister) / diameter:
a) The oversized outside dimensions / diameter to take care of the tolerances/column ovality
defined in applicable Code / EIL Standard 7-12-0001/ drawings for snug fitment. These
dimensions / diameter shall be used for shop inspection of the demister mock up
assembly.
b) The final fit-up dimensions / diameter.
4.3 Demister assembly shall be designed for a net upward thrust of 100 kg/m2 (uniform) due to the
vapour loadings. The assembly should also be able to withstand a concentrated live load of 60
kg at mid point of any of the demister sub-assembly/component.
In addition to the above loading, demister shall be designed to withstand the additional
pressure surges, if specified.
4.4 All demister sub-assemblies shall be sized to facilitate installation inside the column/vessel
through the manhole. These shall rest on support ring/cleats welded inside vessel/column by
others.
4.5 Tentative details of the support rings/cleats, mid span beams (wherever required) grid details
& fixing arrangements shall be as given in the referenced documents listed in clause 2.0.
Vendor is advised to follow the same for the design/fabrication in their scope of work. Vendor
may, however, suggest any improvement in the design. Such suggestions will however be
reviewed/ approved by EIL/Client and can be followed by the vendor only on written
acceptance by EIL/Client.
4.6 All internal bolting shall be minimum M10 size and shall be compatible with Demister
material. All bolting shall be provided with locknuts.
4.7 Welding
All welding shall be done by metal arc welding. For welding on thinner gauge sheets TIG
welding is preferred. Welding wherever required, is to be done by qualified and approved
welders using the suitable fillers and fluxes recommended for materials used for the
fabrication.
5.0 SPARES
Fasteners - bolts, nuts, clamps, spacer pipes, - 10% (minimum 4 Nos. of each type/size)
J-bolts etc.
In addition to Constructional spares as indicated above, vendor shall also supply following
operational spares:
Fasteners - bolts, nuts, clamps, spacer pipes, - 10% (minimum 4 Nos. of each type/size)
J-bolts etc.
6.1 The material, fabrication and trial assembly shall be Inspected by the EIL/Client and/or their
AIA.
6.2 Complete demister assemblies (along with grids) and Beams etc. shall be assembled as floor
mock-up & shall be offered for final inspection. Assembly shall be checked for oversized
dimensions as per the approved drawing.
The individual components shall be marked with proper item/part number as given in the
drawings to facilitate identification at site. Demister shall be wrapped in polythene and
supplied in wooden cases for damage free transportation. For all other requirements refer EIL
Specification No. 6-14-0009.
8.0 GUARANTEE
Vendor shall guarantee the design, performance (i.e. separation efficiency, and pressure drop),
material, fabrication and workmanship for the demisters for the period as outlined in General
Purchase Conditions.
9.0 DOCUMENTATION
Documents/drawings shall be furnished as per the 'Vendor Data Requirement' enclosed with
requisition / feed document. All the drawings prepared by the vendor shall be on AUTOCAD.
Shop changes made by Vendor after approval of drawings under Code-1 by EIL and
deviations granted in deviation permits, if any, shall be marked in hard copy of drawings
which shall then be stamped 'As-built' by the vendor. These 'As-built' drawings shall be
reviewed and stamped by Authorised Inspector also. Vendor shall prepare scanned image files
of all marked-up 'As-built' drawings. Vendor shall also incorporate the above changes in the
native soft files of the drawings.
In addition, vendor shall also incorporate site changes, if any, based on mismatch observed at
site and resubmit the 'As-built' documents.
I
151fRiseA ENGINEERS FOR POSITIVE MATERIAL
si at efaleg INI NA LIMITED
/A “nul na. Lnden.,), IDENTIFICATION (PMI) AT
6 - 81 - 0001 Rev. 2
SUPPLIER'S WORKS Page I of 8
covingii 4
c 1T
STANDARD SPECIFICATION
FOR
POSITIVE MATERIAL
IDENTIFICATION
(PMI)
AT SUPPLIER'S WORKS
40D ., 15,
2 20.10.11 REVISED AND RE-ISSUED AKC DM
Abbreviations:
CONTENTS
1.0 SCOPE 4
2.0 REFERENCE DOCUMENTS 4
3.0 DEFINITIONS 4
4.0 PMI EXAMINATION 5
5.0 ACCEPTABLE METHODS FOR PMI 5
6.0 EXTENT OF PMI EXAMINATION 6
7.0 RECORDING AND DOCUMENTATION 7
8.0 MARKING 7
1.0 SCOPE
1.1 This specification applies to the requirements for Positive Material Identification (PMI) to be
performed at the Supplier's works on Metallic Materials procured either directly by the
Owner/EIL/ LSTK contractor or indirectly through the sub-Suppliers.
1.2 Any post order deviation from this specification must be approved by Owner/EIL in the
Deviation/ Waiver Permit format (No. 5-0000-0180-F1) enclosed with Material Requisition.
1.3 This specification covers the procedures and methodology to be adopted to assure that the
chemical composition of the material is consistent with the material specifications as specified
in purchase documents using 'Alloy Analyzer' at the time of final inspection before dispatch.
1.4 The scope of this specification shall include but shall not be limited to Positive Material
Identification (PMI) to be performed on Materials listed below:
1.5 All grades of material supplies including Stainless Steels shall be liable for PMI test at site. In
case of any defective materials being found at site, the Supplier shall be responsible to effect
replacement of such defective materials at project site without any delays to the satisfaction of
EIL site RCM (Resident Construction Manager).
2.1 API Recommended Practice 578 (First Edition, May 1999) - Material Verification Program for
New and Existing Alloy Piping Systems.
3.0 DEFINITIONS
3.1 Supplier: Any Supplier or Manufacturer on whom an order is placed for the supply of referred
items. This definition shall also include any sub-Supplier or manufacturer on whom a sub-order
is placed by the Supplier.
3.2 Inspection Lot: A group of items offered for inspection covered under same size, Heat and
Heat treatment lot.
3.3 Alloy Material: Any metallic material (including welding filler materials) that contains
alloying elements such as chromium, nickel, molybdenum or vanadium, which are intentionally
added to enhance mechanical or physical properties and/or corrosion resistance.
4.1 The Supplier shall submit a procedure of PMI to comply with the requirements of this
Specification Approval of PMI Procedure shall be obtained from Owner/EIL/TPIA prior to
commencing manufacture/ inspection of product.
4.2 PMI examination of materials is independent of any certification, markings or colour coding
that may exist and is aimed at verifying that the alloy used are as per specified grades.
4.3 The Supplier shall identify all incoming alloy materials and maintain full traceability of all alloy
materials, including all off-cuts. Transfer of identification marks shall be undertaken prior to
cutting to ensure maintenance of identification on off-cuts.
4.4 The Supplier shall ensure that all alloy materials are segregated and stored in separately
identified locations to prevent the mix up of materials of different alloy specifications or alloy
material with carbon steel. Non ferro-magnetic materials shall be segregated at all times from
ferro-magnetic materials.
5.1 The method used for PMI examination shall provide a quantitative determination of the alloying
elements like chromium, nickel, molybdenum or vanadium in Alloy Steel items.
5.2 Instruments or methods used for PMI examination shall be able to provide quantitative,
recordable, elemental composition results for positive identification of alloying elements
present.
5.3 The acceptable instruments for alloy analyzer shall be either "Portable X-Ray fluorescence" or
"Optical Emission" type each capable of verifying the percentage of alloy elements within
specified range.
5.4 Chemical spot testing, magnets, alloy sorters and other methods using eddy current or
triboelectric testing methods are not acceptable for PMI examination.
5.5 The PMI instrument used shall have the sensitivity to detect the alloying elements in the
specified range.
5.6 All PMI instruments shall have been serviced within a 6 month period of the time of use to
verify the suitability of batteries, sources etc., and the data of the last service shall be stated on
the PMI Report Form (Sample enclosed).
5.7 Each analyzer must be calibrated according to the manufacturer's specification at the beginning
and end of each shift. Instrument must be checked against known standard for each alloy type
to be inspected during the shift.
5.8 Certified samples, with full traceability, of a known alloy materials shall be available for use as
a random spot check on the instrument calibration.
5.9 The surfaces to be examined shall be prepared by light grinding or abrasive paper and solvent
cleaner. Evidence of Arc burn resulting from examination shall be removed by light grinding or
abrasive paper. No permanent marks, which are injurious to the usage of product in service, are
acceptable.
5.10 Alloy Steel ring type joint Gaskets shall be inspected by using portable X-Ray fluorescence
instrument.
5.11 Testing shall be done as per the procedures outlined by the manufactures of alloy analyzer
being used. Modification of these procedures if any must be approved by Owner/EIL.
5.12 The persons performing PMI shall demonstrate their capabilities to the satisfaction of
Owner/EIL/TPIA visiting engineer. If the Supplier has qualified operator on their rolls, he may
perform the examination. Otherwise PMI examination shall be sub-contracted to an independent
testing agency approved by EIL.
5.13 Whenever material is identified as not meeting requirements by the visiting engineer a rejection
note shall be issued.
Following sampling plans shall be applicable for PMI examination of various items.
Note:
For Welded Pipes and Fittings, PMI shall be performed on Base Metal as well as
weldments.
Whenever any sample drawn to PMI test on the basis of percentage selection in B & C
above, fails to meet specification requirements, 100% of items of lot shall be tested for
PMI.
The results of PMI examination shall be recorded in a Report Format as enclosed with this
specification.
8.0 MARKING
8.1 All alloy materials tested by PMI shall be identified using either of the following methods by
indicating "PMI OK"
Material Specification/Grade
Element Cr Mo Ni V
Specified Range
Actual observations
Instrument Type / ID
kVilIP—
t'
Convenor Chairman
Rev. Prepared Checked Standards Committee Standards Bureau
Date Purpose
No. by by
Approved by
Abbreviations:
Members:
1.0 SCOPE
This Inspection and test plan covers the minimum testing requirements of Pressure vessels/ Columns carbon steel
SCOPE OF INSPECTION
SL QUANTUM
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO. OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
1.0 Procedures
SCOPE OF INSPECTION
SL QUANTUM
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO. OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
SCOPE OF INSPECTION
SL QUANTUM
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO. OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
Inspection
Test coupon as applicable 100% H H W
report
Visual & dimensional (min.
100% Inspection
thickness, profile, ovality etc ) H H H
report
inspection
100% Batch test
3.5 Welding consumable Chemical & mechanical properties W R R
certificates
Visual & dimensional inspection,
Inspection
weld edge, root gap, offset, 100% - W
Weld edge preparation & set check list
3.6 alignment, cleanliness etc
up of pressure parts
NDT of weld edges as applicable
for cracks, laminations or 100% NDT Reports - W R
segregations
Intermediate inspection of Inspection
3.7 Visual/ inter pass temperature 100% - W -
welds report
4.0 Final inspection
Visual and dimensional Visual/ dimensions, completeness
inspection (internals & of assembly and weld visual for Inspection
4.1 100% - H H
externals) including welds reinforcement, undercuts, Surface report
(before PWHT as applicable) defects, etc.
SCOPE OF INSPECTION
SL QUANTUM
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO. OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
Each Inspection
4.2 PMI (AS/SS components) Chemical check W R
component report
5.0 Painting
SCOPE OF INSPECTION
SL QUANTUM
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO. OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
Visual inspection (after surface
preparation and final painting for Inspection
5.1 Final painting 100% - H
workmanship, uniformity) DFT report
check
6.0 Documentation and IC
Legend: H- Hold (Do not proceed without approval), P-Perform, RW - Random Witness (As specified or 10% ( min.1 no. of each size and type of Bulk item)),
R-Review, W-Witness (Give due notice, work may proceed after scheduled date).
1. This document describes the generic test requirements. Any additional test or Inspection scope if specified in contract documents shall also be
applicable.
(Unless otherwise agreed upon)
2. Acceptance Norms for all the activities shall be as per PO/PR/STANDARDS referred there in /Job Specification /Approved Documents.
Convenor Chairman
Rev. Prepared Checked Standards Committee Standards Bureau
Date Purpose
No. by by
Approved by
Abbreviations:
Members:
1.0 SCOPE
This Inspection and Test Plan covers the minimum testing requirements of Pressure vessels/ Columns stainless steel
SCOPE OF INSPECTION
QUANTUM
SL NO. STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
1.0 Procedures
Hydro test ,heat treatment, NDT,
Procedure
1.1 hot forming, and other Documented procedures. 100% - H R
Documents
Procedures
Procedure R-Existing
1.2 WPS/ PQR /WPQ Documented procedures. 100% - H
documents W-New
SCOPE OF INSPECTION
QUANTUM
SL NO. STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
3.0 In process inspection
Review of test certificates, markings
Materials identification for visual & dimensional inspection, Material
3.1 100% - H H
plates, pipes (pressure parts) identity correlation & transfer of clearance record
identity
Material identification for
Review of test certificates, markings Material
3.2 forgings, fittings, fasteners, 100% H R
identity correlation . clearance record
gaskets (pressure parts)
Non pressure parts (including Material test
3.3 Review of test certificates 100% W R R
internals, supports etc.) certificate
NDT report/RT
NDT of weld seam as applicable 100% W W R
films
DPT (dished ends and tori cone) for
100% Inspection
cracks on inside & outside surfaces in W W R
report
knuckle zone and edges.
Solution Annealing as applicable 100% HT chart W W R
Inspection of formed components As per
3.4 Hardness check as applicable Inspection report W W R
(Cold or hot formed) requirement
SCOPE OF INSPECTION
QUANTUM
SL NO. STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
Chemical & mechanical properties 100% Batch test
3.5 Welding consumable W R R
including IGC certificates
Visual & dimensional inspection, weld
Inspection
Insp
edge, root gap, offset, alignment, 100% W R
check list
3.6 Weld edge preparation & set up cleanliness etc
of pressure parts
DPT of weld edges as applicable for Inspection
100% - W R
cracks, laminations or segregations check list
3.7 Intermediate Inspection of Welds Visual/ DPT for weld root 100% Inspection report W R
Each
Inspection
4.2 PMI Chemical check component - W RW
report
and weld
SCOPE OF INSPECTION
QUANTUM
SL NO. STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
PWHT as applicable 100% HT chart W R
SCOPE OF INSPECTION
QUANTUM
SL NO. STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
Legend: H- Hold (Do not proceed without approval), P-Perform, RW - Random Witness (As specified or 10% ( min.1 no. of each size and type of Bulk item)), R-Review,
W-Witness (Give due notice, work may proceed after scheduled date).
CD
3
's7)
cn
o.
o.
3
<D
0.) W
6' o
<n 3
3 P,
• 3
C)
O
NJ
rsi
rsi
O
cn
cn
cn
NOIIVIN3IN31d1All dadcmnsst
z
O
O
cn
cn
Cl3f1SSI-3dCINV CI3SIA3d
0
O
O
O
cn
C131-1SSI-32!CINVCI3SIA3d
G)
sllaismaa HSMAI allas.
MVIEd CINV1\louDadsm
C
rn
£'Aall0900-18-9
STANDARD SPECIFICATION No.
XIVId
• ▪ • •
•
•0
• •
• ••
r1-1 t=inn
H ) (") z rri
HH ■-3
H
:suogulnammy
tw co
:3dODS
.
,
w)
C/)
Quantumof
....•
-
.......
.....•
15-
'...7
—
.-t.
.—2•
g
0
..,z,
c
CP:
ro
e%
Procedures
DocumentedProcedures
NDTProcedure(as Procedure
z
.-.
C
—
-■
■
applicable) documents
WeldingProcedures
WPS,PQR,WPQ(as WPS/PQR/ W-New,
z
—
.--,
i•-)
Qualification
applicable) WPQRecords R- Existing
Materials inspection
0
IN
z
z
--,
t‘..)
0
rn
Cro
a.
Scopeof Inspection
f!I
.n
>
Quantumof
~.•
ci)
Characteristics
cA
'.--
...,-
r>
5:'
frCI
»...
Check Sub Supplier Supplier EIL/TPIA
O
Inprocessinspection
c.,. )
Materials identification
Reviewof testcertificates
(Wires,plates, fasteners
markings. visual & Material
with locknuts,washers,
c>
c>
_.
,--
clearance
t.,)
dimensional inspection
.
clamps,gaskets, foilsetc.
identification,correlation record
includingsupport
etc.
members)
Visual inspection for
reinforcement,undercuts,
o
o
,-,
c>
i..)
NDT Report
1,-)
Inspectionof Welds
.
surface defectsetc.
1. 2. 3. 4. 5.
O
Final inspection
Trialassemblyof
IndividualDemisteralong
Dimensions,Ovality,
withgridandsupport Inspection
--
Straightness,Camberand 100%
.
beams inamanner Report
completenessof assembly.
comparablewith actual
installation.
Visual
Dimensions
FinalInspection Inspection
7:1
o
c>
c>
i.)
Flange finish
Report
MatchMarking
Bulk density
£"^aH 0900-18-9
.1.•
5"
cn
ro
r>
(fel
Check Sub Supplier Supplier EIL/TPIA
Asper
PMI(For AS/SS Inspection
Chemical check purchase
4.
L.)
i
components) report
siecification
O
Picklingandpassivation
f,,
Pickling&Passivation( Inspection
o
c>
Visual inspection
,--
,-,,,
i
asapplicable) report
z:,
Documentation
O'N
Reviewof inspection
Compilationofstage
z
(-)
4
o
H
c>
.--,
documents & Issueof
..-
C'■
inspectionreports
MTC
Inspection
z
z
,.)
.-.
c>
Issueof IC(asapplicable) InspectionCertificate
cr,
iN.)
Certificate
0.
0:,
'zrs
CD e,
0
■—•
c5
CD
• et,
CD
CD
0
CD
(I)
• 0
(/)
-cs
CD
o
z
cn (-)
o
CD
vc
=
el>
0.
o
‘-z
(1)
CD
7,3
O
co
Cn
CD
CD
•
•
:(ameoudde sv ) S3IO N
6 26/02/2014
REVISED & UPDATED SM J RKD SC
Standards Standards
Comm ittee Bureau
Rev Date Purpose Prepared by Checked by Convenor Chairman
Approved by
Abbreviations:
CONTENTS
CLAUSE TITLE PAGE NO.
1.0 Scope 5
2.0 References 5
3.0 Requirement of Health, Safety and Environment (HSE) Management 5
System to be complied by Bidders
3.1 Management Responsibility 5
3.1.1 HSE Policy & Objective 5
3.1.2 Management System 5
3.1.3 Indemnification 6
3.1.4 Deployment & Qualification of Safety 6
Personnel
3.1.5 Implementation, Inspection & Monitoring 7
3.1.6 Behavior Based Safety 8
3.1.7 Awareness 9
3.1.8 Fire prevention & First-Aid 9
3.1.9 Documentation 9
3.1.10 Audit 10
3.1.11 Meetings 10
3.1.12 Intoxicating drinks & drugs and smoking 11
3.1.13 Penalty 11
3.1.14 Accident/Incident investigation 14
3.2 House Keeping 14
3.3 HSE Measures 15
3.3.1 Construction Hazards 15
3.3.2 Accessibility 16
3.3.3 Personal Protective Equipments (PPEs) 16
1.0 SCOPE
This specification establishes the Health, Safety and Environment (HSE) management
requirement to be complied by Contractors/Vendors including their sub-contractors/sub vendors
during construction.
This specification is not intended to replace the necessary professional judgment needed to
design & implement an effective HSE system for construction activities and the contractor is
expected to fulfill HSE requirements in this specification as a minimum. It is expected that
contractor shall implement best HSE practices beyond whatever are mentioned in this
specification.
2.0 REFERENCES
The Contractor should have a documented HSE policy duly & objectives to demonstrate
commitment of their organization to ensure health, safety and environment aspects in their line
of operations.
HSE Policy of the contractor shall be made available to Owner / EIL at the place of execution of
specific contract works, as a valid document.
The HSE management system of the Contractor shall cover the HSE requirements &
commitments to fulfill them, including but not limited to what are specified under clause 1.0
and 2.0 above. The Contractor shall obtain the approval of its site specific HSE Plan from EIL /
Owner prior to commencement of any site works. Corporate as well as Site management of the
Contractor shall ensure compliance of their HSE Plan at work sites in its entirety & in true
spirit.
3.1.3 Indemnification
Contractor shall indemnify & hold harmless, Owner/EIL & their representatives, free from any
and all liabilities arising out of non-fulfillment of HSE requirements or its consequences.
The Contractor shall designate/deploy various categories of HSE personnel at site as indicated
below in sufficient number. In no case, deployment of safety Supervisor / Safety Steward shall
substitute deployment of Safety Officer / Safety Engr what is indicated in relevant statute of
BOCW Act i.e deployment of safety officer/Safety Engineer is compulsory at project site. The
Safety supervisors, Safety stewards etc. would facilitate the HSE tasks at grass root level for
construction sites and shall assist Safety Officer / Engineers.
a) Safety Steward
As a minimum, he shall preferably possess School leaving Certificate (of Class XII with
Physics & Chemistry etc.) and trained in fire-fighting as well as in safety/occupational
health related subjects, with minimum two year of practical experience in construction
work environment and preferably have adequate knowledge of the language spoken by
majority of the workers at the construction site.
b) Safety Supervisor
(i) Recognized degree in any branch of Engg. or Tech. or Architecture with practical
experience of working in a building or other construction work in supervisory
capacity for a period of not less than two years, or possessing recognized diploma in
any branch of Engg. or Tech with practical experience of building or other
construction work in supervisory capacity for a period of not less than five years.
(ii) Recognized degree or diploma in Industrial safety with one paper in Construction
Safety
(iii) Preferably have adequate knowledge of the language spoken by majority of the
workers at the construction site.
Alternately
(i) Person possessing Graduation Degree in Science with Physics & Chemistry and
degree or diploma in Industrial Safety (from any Indian institutes recognized by
AICTE or State Council of Tech. Education of any Indian State) with practical
experience of working in a building, plant or other construction works (as Safety
Officer, in line with Indian Factories Act, 1958) for a period of not less than five
years, may be considered as Safety Officer, in case Owner/Client of the project
agrees for /approves the same.
d) HSE In-Charge
In case there is more than one Safety Officer at any project construction site, one of them,
who is senior most by experience (in HSE discipline), may be designated as HSE In-
Charge. Duties & responsibilities of such person shall be commensurate with that of
relevant statute and primarily to coordinate with top management of Client and contractors.
In case the statutory requirements i.e. State or Central Acts and / or Rules as applicable like
the Building and Other Construction Workers’ Regulation of Employment and Conditions
of Service- Act,1996 or State Rules (wherever notified), the Factories Act, 1948 or Rules
(wherever notified), etc. are more stringent than above clarifications, the same shall be
followed.
Contractors shall ensure physical availability of safety personnel at the place of specific
work location, where Hot Work Permit is required / granted. No work shall be started at
any of the project sites until above safety personnel & concerned Site Engineer of
Contractor are physically deployed at site. The Contractor shall submit a HSE organogram
clearly indicating the lines of responsibility and reporting system and elaborate the
responsibilities of safety personnel in their HSE Plan.
The Contractor shall verify & authenticate credentials of such safety personnel and furnish
Bio-Data/ Resume/ Curriculum Vitae of the safety personnel as above for EIL/Owner’s
approval, at least 1 month before the mobilization. The Contractor, whenever required,
shall arrange submission of original testimonials/certificates of their Safety personnel, to
EIL/Owner (for verification/scrutiny, etc.)
Imposition / Realization of penalty shall not absolve the Contractor from his/her
responsibility of deploying competent safety officer at site.
Adequate planning and deployment of safety personnel shall be ensured by the Contractor
so that field activities do not get affected because of non-deployment of competent &
qualified safety people in appropriate numbers.
The Contractor shall be fully responsible for planning, reporting, implementing and
monitoring all HSE requirements and compliance of all laws & statutory requirements.
The Contractor shall also ensure that the HSE requirements are clearly understood &
implemented conscientiously by their site personnel at all levels at site.
The Contractor shall ensure physical presence of their field engineers / supervisors, during
the continuation of their contract works / site activities including all material transportation
activities. Physical absence of experienced field engineers / supervisors of Contractor at
critical work spot during the course of work, may invite severe penalization as per the
discretion of EIC, including halting / stoppage of work.
Contractor shall furnish their annual Inspection Plan, with regard to project issues /subjects,
frequency and performers to EIL/Owner.
The Contractor shall regularly review inspection report internally and implement all
practical steps / actions for improving the status continuously.
The Contractor shall ensure important safety checks right from beginning of works at every
work site locations and to this effect format No: HSE-10 “Daily Safety Check List” shall
be prepared by field engineer & duly checked by safety personnel for conformance.
The Contractor shall carry out inspection to identify various unsafe conditions of work
sites/machinery/equipments as well as unsafe acts on the part of
workmen/supervisor/engineer while carrying out different project related works.
Adequate records for all inspections shall be maintained by the Contractor and the same
shall be furnished to EIL/Owner, whenever sought.
The Contractor shall not carry-out work by engaging single worker anywhere without any
supervisor anytime during day or night.
To demonstrate involvement/commitment of site management of Contractor, at least one
Safety Walk through in a month shall be carried out by Contractor’s head of site (along
with his area manager/field engineers) and a report shall be furnished to EIL/Owner as per
format No: HSE-1” Safety walk through report” followed by compliance for unsatisfactory
remarks.
As a general practice lifting tools/tackles, machinery, accessories etc. shall be inspected,
tested and examined by competent people (approved by concerned State authorities) before
being used at site and also at periodical interval (e.g. during replacement,extension,
modification, elongation/reduction of machine/parts, etc.) as per relevant statutes. Hydra,
cranes, lifting machinery, mobile equipments / machinery / vehicles, etc. shall be inspected
regularly by only competent / experienced personnel at site and requisite records for such
inspections shall be maintained by every contractor. Contractor shall also maintain records
of maintenance of all other site machinery (e.g. generators, rectifiers, compressors, cutters,
etc.) & portable tools/equipments being used at project related works (e.g. drills, abrasive
wheels, punches, chisels, spanners, etc.). The Contractor shall not make use of arbitrarily
fabricated ‘derricks’ at project site for lifting / lowering of construction materials.
Site facilities /temporary. installations, e.g. batching plant, cement godown, DG-room,
temporary electrical panels/distribution boards, shot-blasting booth, fabrication yards, etc.
and site welfare facilities, like labour colonies, canteen/pantry, rest-shelters, motor
cycle/bicycle-shed, site washing facilities, First-aid centers, urinals/toilets, etc. should be
periodically inspected by Contractor (preferably utilizing HR/Admn. personnel to inspect
site welfare facilities) and records to be maintained.
The HSE committee of contractor shall observe individual’s behavior for safe practices
adapted for utilization/execution of work for following as a minimum:-
- PPE
- Tools & equipment
- Hazard Identification & control
- House keeping
- Confined space entry
- Hot works
- Excavation
- Loading & unloading
- Work At height
- Stacking & storage
- Ergonomics
- Procedures
The Contractor shall promote and develop awareness on Health, Safety and Environment
protection among all personnel working for the Contractor.
Regular awareness programs and fabrication shop / work site meetings at least on monthly
basis shall be arranged on HSE activities to cover hazards/risks involved in various
operations during construction.
Contractor to motivate & encourage the workmen & supervisory staff by issuing /
awarding them with tokens/ gifts/ mementos/ monetary incentives / certificates, etc.
Contractor shall assess & recognize the behavioral change of its site engineers / supervisors
periodically and constantly motivate / encourage them to implement HSE practices at
project works
3.1.8 Fire prevention & First-Aid
The Contractor shall arrange suitable First-aid measures such as First Aid Box (Refer
Appendix-B for details), trained personnel/nurse (male) to administer First Aid, stand-by
Ambulance vehicle and
The Contractor shall arrange installation of fire protection measures such as adequate
number of steel buckets with sand & water and adequate number of appropriate portable
fire extinguishers (Refer Appendix-C for details) to the satisfaction of EIL/Owner.
The Contractor shall deploy trained supervisory personnel / field engineers to cater to any
emergency situation.
In case the number of workers exceeds 500, the Contractor shall position an Ambulance /
vehicle and nurse on round the clock basis very close to the worksite.
The Contractor shall arrange FIRE DRILL at each site at least once in three months,
involving site workmen and site supervisory personnel & engineers. The Contractor shall
maintain adequate record of such fire drills at project site
3.1.9 Documentation
The Contractor shall evolve a comprehensive, planned and documented system covering the
following as a minimum for implementation and monitoring of the HSE requirements and the
same shall be submitted for approval by owner/EIL.
- HSE Organogram
- Site specific HSE Plan
- Safety Procedures, forms and Checklist. Indicative list of HSE procedures is attached as
Appendix :H
- Inspections and Test Plan
- Risk Assessment & Job Safety Analysis for critical works.
The monitoring for implementation shall be done by regular inspections and compliance of
the observations thereof. The Contractor shall get similar HSE requirements implemented
at his sub-contractor(s) work site/office. However, compliance of HSE requirements shall
be the responsibility of the Contractor. Any review/approval by EIL/Owner shall not
absolve contractor of his responsibility/liability in relation to fulfilling all HSE
requirements.
3.1.10 Audit
The Contractor shall submit an Audit Plan to EIL/Owner indicating the type of audits and
covering following as minimum:
Internal HSE audits regularly at least on quarterly basis by engaging internal qualified
auditors (viz safety officers/Construction personnel having 5 years experience in
construction safety and Lead Auditor Course :OSHA 18001certification).
External HSE audits regularly at least on every six months by engaging qualified external
auditors (viz safety officers/Construction personnel having 10 years experience in
construction safety and Lead Auditor Course :OSHA 18001certification).
All HSE shortfalls/ non-conformances on HSE matters brought out during review/audit, shall be
resolved forthwith ( generally within a week) by Contractor & compliance report shall be
submitted to EIL/Owner.
In addition to above audits by contractor, the contractor’s work shall be subjected to HSE audit
by EIL/Owner at any point of time during the pendency of contract. The CONTRACTOR shall
take all actions required to comply with the findings of the Audit Report and issue regular
Compliance Reports for the same to OWNER/ EIL till all the findings of the Audit Report are
fully complied.
Failure to carry-out HSE Audits & its compliance (internal & external) by Contractor, shall
invite penalization.
3.1.11 Meetings
The Contractor shall ensure participation of his top most executive at site (viz. Resident
Construction Manager / Resident Engineer / Project Manager / Site-in-Charge) in Safety
Committee / HSE Committee meetings arranged by EIL/Owner usually on monthly basis
or as and when called for. In case Contractor’s top most executive at site is not in a
position to attend such meeting, he shall inform EIL/Owner in writing before the
commencement of such meeting indicating reasons of his absence and nominate his
representative – failure to do so may invite very stringent penalization against the specific
Contractor, as deemed fit in Contract. The obligation of compliance of any observations
during the meeting shall be always time bound. The Contractor shall always assist
EIL/Owner to achieve the targets set by them on HSE management during the project
implementation.
In addition, the Contractor shall also arrange internal HSE meetings chaired by his top most
executive at site on weekly basis and maintain records. Such internal HSE meetings shall
essentially be attended by field engineers / supervisors (& not by safety personnel only) of
the Contractor and its associates. Records of such internal HSE meetings shall be
maintained by the Contractor for review by EIL/Owner or for any HSE Audits.
The time frame for such HSE meeting shall be religiously maintained by one and all.
The Contractor shall ensure that his staff members & workers (permanent as well casual)
shall not be in a state of intoxication during working hours and shall abide by any law
relating to consumption & possession of intoxicating drinks or drugs in force.
The Contractor shall not allow any workman to commence any work at any locations of
project activity who is/are influenced / effected with the intake of alcohol, drugs or any
other intoxicating items being consumed prior to start of work or working day.
Awareness about local laws on this issue shall form part of the Induction Training and
compulsory work-site discipline.
The Contractor shall ensure that all personnel working for him comply with “No-Smoking”
requirements of the Owner as notified from time to time. Cigarettes, lighters, auto ignition
tools or appliances as well as intoxicating drugs, dry tobacco powder, etc. shall not be
allowed inside the project / plant complex.
Smoking shall be permitted only inside smoking booths exclusively designated &
authorized by the Owner/EIL.
3.1.13 Penalty
The Contractor shall adhere consistently to all provisions of HSE requirements. In case of non-
compliances and also for repeated failure in implementation of any of the HSE provisions,
EIL/Owner may impose stoppage of work without any cost & time implication to the Owner
and/or impose a suitable penalty.
2.0% (Two percent) of the contract value for Item Rate or Composite contracts with an overall
ceiling of 1, 00, 00, 000 (Rupees One crore)
0.5% (Zero decimal five percent) of the contract value for LSTK, OBE, EPC, EPCC or Package
contracts with an overall ceiling of 10, 00.00.000 (Rupees ten crores)
This penalty shall be in addition to all other penalties specified elsewhere in the contract. The
decision of imposing stop-work-instruction and imposition of penalty shall rest with
EIL/Owner. The same shall be binding on the Contractor. Imposition of penalty does not make
the Contractor eligible to continue the work in unsafe manner.
The amount of penalty applicable for the Contractor on different types of HSE violations is
specified below:
Sl.
Violation of HSE norms Penalty Amount
No.
1. For not using personal protective equipment Rs 500/- per day/ Item / Person.
(Helmet, Shoes, Goggles, Gloves, Full body harness,
Face shield, Boiler suit, etc.)
2. Working without Work Permit/Clearance Rs 20000/- per occasion
3 Execution of work without deployment of requisite Rs. 5000/- per violation per day
field engineer / supervisor at work spot
4. Unsafe electrical practices (not installing ELCB, Rs 10000/- per item per day.
using poor joints of cables, using naked wire without
top plug into socket, laying wire/cables on the roads,
electrical jobs by incompetent person, etc.)
5. Working at height without full body harness, using Rs. 10000/- per case per day.
non-standard/ rejected scaffolding and not arranging
fall protection arrangement as required, like hand-
rails, life-lines, Safety Nets etc.
6. Unsafe handling of compressed gas cylinders (No Rs 500/- per item per day.
trolley, jubilee clips double gauge regulator, and not
keeping cylinders vertical during storage/handling,
not using safety cap of cylinder).
7. Use of domestic LPG for cutting purpose / not using Rs. 3000/- per occasion.
flash back arresters on both the hoses/tubes on both
ends.
8. No fencing/barricading of excavated areas / Rs. 3000/- per occasion.
trenches.
9. Not providing shoring/strutting/proper slope and not Rs.5, 000/- per occasion.
keeping the excavated earth at least 1.5M away from
excavated area.
10. Non display of scaffold tags, caution boards, list of Rs.1000/- per occasion per day
hospitals, emergency services available at work
locations.
11. Traffic rules violations like over speeding of Rs. 2000/- per occasion per day
vehicles, rash driving, talking on mobile phones
during vehicle driving, wrong parking, not using seat
belts, vehicles not fitted with reverse horn / warning
alarms / flicker lamps during foggy weather.
12. Absence of Contractor’s RCM/SIC or his Rs10000/- per meeting.
nominated representative (prior approval must be
taken for each meeting for nomination) from site
HSE meetings whenever called by EIL/Owner &
failure to nominate his immediate deputy (in the site-
organogram) for such HSE meetings.
13. Failure to maintain HSE records by Contractor Rs 10000/- per month.
Safety personnel, in line with approved HSE
Plan/Procedures/Contract specifications..
14. Failure to conduct daily site safety inspection (by Rs.10000/- per occasion.
Contractor’s safety engineers/safety officers),
internal HSE meeting, internal HSE
Awareness/Motivation Program, Site HSE Training
and HSE audit at predefined frequencies (as
approved in HSE Plan).
Sl.
Violation of HSE norms Penalty Amount
No.
th
15. Failure to submit the monthly HSE report by 5 of Rs. 10000/- per occasion and Rs.
subsequent month to Project’s Engineer-in-Charge / 1000/- per day of further delay.
Owner
16. Poor House Keeping Rs. 5000/- per occasion per subject
17. Failure to report & follow up accident (including Rs. 20000/- per occasion
Near Miss) reporting system within specific time-
frame.
18. Degradation of environment (not confining toxic Rs10000/- per occasion
spills, spilling oil/lubricants onto ground)
19. Not medically examining the workers before Rs 5000/- per occasion per worker
allowing them to work at height / to work in
confined space / to work in shot-blasting / to work
for painting / to work in bitumen or asphalt works,
not providing ear muffs while allowing them to work
in noise polluted areas, made them to work in air
polluted areas without respiratory protective devices,
etc.
20. Violation of any other safety condition as per job Rs. 5000/- per occasion
HSE plan / work permit and HSE conditions of
contract (e.g. using crowbar on cable trenches,
improper welding booth, not keeping fire
extinguisher ready at hot work site, unsafe rigging
practices, non-availability of First-Aid box at site,
not using hood with respiratory devices by blaster
for shot//grit blasting, etc.)
21. Failure to carry-out Safety audit in time (internal & Rs. 20,000/- per occasion
external), close-out of identified shortfalls of
Observations of Safety Aspects(OSA),etc
22. Carrying out sand blasting instead of grit/shot Rs. 50,000/- per day
blasting
23. Failure to deploy adequately qualified and Rs. 10000/- per day per Officer
competent Safety Officer
24. Utilization of hydra/ back-hoe loader for material Rs 25,000/- per occasion
shifting or any other unauthorized /unsafe lifting
works
25. Any incident / accident at project site has been Rs 10,00,000/-per occasion
caused because of willful negligence or gross
violation of safety measures / provisions on the part
of the Contractor or any of its sub-agencies
26. Any violation not covered above To be decided by EIL/Owner.
The Contractor shall make his field engineers/supervisors fully aware of the fact that they
keep track with the site workmen for their behavior and compliance of various HSE
requirements. Safety lapses / defects of project construction site shall be attributable to the
concerned job supervisor / engineer of the Contractor, (who remains directly responsible
for safely executing field works). For repeated HSE violations, concerned job supervisor /
engineer shall be reprimanded or appropriate action, as deemed fit, shall be initiated (with
an information to EIL & Owner) by the concerned Contractor.
Contractor shall initiate verbal warning shall be given to the worker/employee during his first
HSE violation. A written warning shall be issued on second violation and specific training shall
be arranged / provided by the Contractor to enhance HSE awareness/skill including feedback on
the mistakes/ flaws. Any further violation of HSE stipulations by the erring individuals shall
call for his forthright debar from the specific construction site. A record of warnings for each
worker/employee shall be maintained by the Contractor, like by punching their cards / Gate
passes or by displaying their names at the Project entry gate. Warnings, penalizations,
appreciations etc. shall be discussed in HSE Committee meetings by site Head of the
Contractor.
The Contractor shall ensure that a high degree of house keeping is maintained and shall ensure
inter alia; the followings:
a) All surplus earth and debris are removed/disposed off from the working areas to designated
location(s).
b) Unused/surplus cables, steel items and steel scrap lying scattered at different places within
the working areas are removed to identify location(s).
c) All wooden scrap, empty wooden cable drums and other combustible packing materials,
shall be removed from work place to identified location(s).
d) Roads shall be kept clear and materials like pipes, steel, sand, boulders, concrete, chips and
bricks etc shall not be allowed on the roads to obstruct free movement of men &
machineries.
e) Fabricated steel structural, pipes & piping materials shall be stacked properly for erection.
f) Water logging on roads shall not be allowed.
g) No parking of trucks/trolleys, cranes and trailers etc shall be allowed on roads, which may
obstruct the traffic movement.
h) Utmost care shall be taken to ensure over all cleanliness and proper upkeep of the working
areas.
i) Trucks carrying sand, earth and pulverized materials etc. shall be covered while moving
within the plant area/ or these materials shall be transported with top surface wet.
j) The contractor shall ensure that the atmosphere in plant area and on roads is free from
particulate matter like dust, sand, etc. by keeping the top surface wet for ease in breathing.
k) At least two exits for any unit area shall be assured at all times – same arrangement is
preferable for digging pits / trench excavation / elevated work platforms / confined spaces
etc.
l) Welding cables and the power cable must be segregated and properly stored and used .The
same shall be laid away from the area of movement and shall be free from obstruction.
m) Schedule for upkeep/cleaning of site to be firmed up and implemented on regular basis
The Contractor shall carry-out regular checks (minimum one per fortnight) as per format No:
HSE-11 for maintaining high standard of housekeeping and maintain records for the same.
The Contractor shall ensure identification of all Occupational Health, Safety & Environmental
hazards in the type of work he is going to undertake and enlist mitigation measures. Contractor
shall carry out Job Safety Analysis (JSA)/Risk Analysis specifically for high risk jobs/crtical
jobs like
a) Working at height (+2.0 Mts height) for cold (incl. colour washing, painting, insulation
etc.) & hot works.
b) Work in confined space,
c) Deep excavations & trench cutting (depth > 2.0 mts.)
d) Operation & Maintenance of Batching Plant.
e) Shuttering / concreting (in single or multiple pour) for columns, parapets & roofs.
f) Erection & maintenance of Tower Crane.
g) Erection of structural steel members / roof-trusses / pipes at height more than 2.0 Mts. with
or without crane.
h) Erection of pipes (full length or fabricated) at height more than 2.0 Mts. height with Crane
of 100T capacity.
i) All lifts using 100T Crane plus mechanical pulling.
j) All lifts using two cranes in unison (Tandem Lifting).
k) Any lift exceeding 80% capacity of the lifting equipments (hydra, crane etc.).
l) Laying of pipes (isolated or fabricated) in deep narrow trenches – manually or
mechanically.
m) Maintenance of crane / extension or reduction of crane-boom on roads or in yards.
n) Erection of any item at >2.0 Mts. height using 100T crane or of higher capacity
o) Hydrostatic test of pipes, vessels & columns and water-flushing.
p) Radiography jobs (in-plant & open field)
q) Work in Live Electrical installations / circuits
r) Handling of explosives & Blasting operations
s) Demolishing / dismantling activities
t) Welding / gas cutting jobs at height (+2.0 Mts.)
u) Lifting / placing roof-girders at height (+2.0 Mts.)
v) Lifting & laying of metallic / non-metallic sheet over roof/structures.
w) Lifting of pipes, gratings, equipments/vessels at heights (+2.0 Mts) with & without using
cranes
x) Calibration of equipment, instruments and functional tests at yards / work-sites.
y) Operability test of Pump, Motors (after coupling) & Compressors.
z) Cold or Hot works inside Confined Space.
aa) Transportation & shifting of ODC consignments into project areas.
bb) Working in “charged/Live” elect. Panels
cc) Stress Relieving works (Electrically or by Gas-burners).
dd) Pneumatic Tests
ee) Card board blasting
ff) Chemical cleaning
and take feedback from EIL/Owner. The necessary HSE measures devised shall be put in to
place, prior to start of an activity & also shall be maintained during the course of works, by the
Contractor. Copies of such JSAs shall be kept available at work sites by the Contractor to enable
all concerned carrying out checks / verification.
A list of typical construction hazards along with their effects & preventive measures is given in
Appendix-E.
3.3.2 Accessibility
The Contractor shall provide safe means of access(in sufficient numbers) & efficient exit to
any working place including provisions of suitable and sufficient scaffolding at various
stages during all operations of the work for the safety of his workmen and EIL/Owner.
The Contractor shall implement use of all measures including use of “life line”, “fall-
arresters”, “retractable fall arresters” , “safety nets” etc. during the course of using all safe
accesses & exits, so that in no case any individual remains at risk of slip & fall during their
travel.
The access to operating plant / project complex shall be strictly regulated. Any person or
vehicle entering such complex shall undergo identification check, as per the procedures in
force / requirement of EIL/Owner.
Accessibility to ‘confined space’ shall be governed by specific system / regulation, as
established at project site.
The Contractor shall ensure that all their staff, workers and visitors including their sub-
contractor(s) have been issued (records to be kept) & wear appropriate PPEs like nape strap
type safety helmets preferably with head & sweat band with ¾” cotton chin strap
(made of industrial HDPE), safety shoes with steel toe cap and antiskid sole, full body
harness (CЄ marked and conforming to EN361), protective goggles, gloves, ear muffs,
respiratory protective devices, etc. All these gadgets shall conform to applicable IS
Specifications/CE or other applicable international standards. The Contractor shall
implement a regular regime of inspecting physical conditions of the PPEs being issued /
used by the workmen of their own & also its sub-agencies and the damaged / unserviceable
PPEs shall be replaced forthwith.
Owner/EIL may issue a comprehensive color scheme for helmets to be used by various
agencies. The Contractor shall follow the scheme issued by the owner/EIL and shall choose
any colour other than white (for Owner) or blue (for EIL) All HSE personnel shall
preferably wear dark green band on their helmet so that workmen can approach them for
guidance during emergencies. HSE personnel shall preferably wear such dresses with
fluorescent stripes, which are noticeable during night, when light falls on them.
For shot blasting, the usage of protective face shield and helmets, gauntlet and protective
clothing is mandatory. Such protective clothing should conform relevant IS Specification.
For off-shore jobs/contracts, contractor shall provide PPEs (new) of all types to EIL &
Owner's personnel, at his (contractor's) cost. All personnel shall wear life jacket at all time.
Contractor shall ensure procurement & usage of following safety equipments/ accessories
(conforming to applicable IS mark / CE standard) by their staff, workmen & visitors
including their subcontractors all through the span of project construction / pre-
commissioning/ Commissioning:-‘
a. PPEs (Helmet, Spectacle, Ear-muff, Face shield, Hand gloves, Safety Shoes, Gum
boot)
b. Barricading tape / warning signs
c. Rechargeable Safety torch (flame-proof)
d. Safety nets (with tie-chords)
e. Fall arresters
f. Portable ladders (varying lengths)
g. Life-lines (steel wire-rope, dia not less than 8.0 mm)
h. Full body harness (double lanyard)
i. Lanyard
j. Karabiner
k. Retractable fall arresters (various length)
l. Portable fire extinguishers (DCP type) – 5 kg capacity
m. Portable Multi Gas detector
n. Sound level meter
o. Digital Lux meter
p. Fire hoses & flow nozzles
q. Fire blankets / Fire retardant cloth (with eyelets)
The Contractor shall issue permit for working (PFW) at height after verifying and
certifying the checkpoints as specified in the attached permit (Format No. HSE-6). He
shall also undertake to ensure compliance to the conditions of the permit during the
currency of the permit including adherence of personal protective equipments. Contractor’s
Safety Officer shall verify compliance status of the items of permit document after
implementation of action is completed by Contractor’s execution / field engineers at work
site. Job Safety Analysis (JSA) for specific works at height duly commented by
EIL/Owner, shall be kept attached with particular Permit for Work (PFW) at site for ready
reference & follow-up.
Such PFW shall be initially issued for one single shift or expected duration of normal work
and extended further for balance duration, if required. EIL/Owner can devise block-permit
system at any specific area, in consultation with project specific HSE Committee to specify
the time-period of validity of such PFW or its renewal. This permit shall be applicable in
areas where specific clearance from Owner’s operation Deptt. /Safety Deptt. is not
required. EIL / Owner’s field Engineers/Safety Officers/Area Coordinators may verify and
counter sign this permit (as an evidence of verification) during the execution of the job.
All personnel shall be medically examined & certified by registered doctor, confirming
their ‘medical fitness for working at height. The fitness examination shall be done once in
six months.
In case work is undertaken without taking sufficient precautions as given in the permit, EIL
/Owner Engineers may exercise their authority to cancel such permit and stop the work till
satisfactory compliance/rectification is arranged made. Contractors are expected to
maintain a register for issuance of permit and extensions thereof including preserving the
used permits for verification during audits etc.
The Contractor shall arrange (at his cost) and ensure use of Fall Arrester Systems by his
workers. Fall arresters are to be used while climbing/descending tall structures or vessels /
columns etc. These arresters should lock automatically against the anchorage line,
restricting free fall of the user. The device is to be provided with a double security opening
system to ensure safe attachment or release of the user at any point of rope. In order to
avoid shock, the system should be capable of keeping the person in vertical position in case
of a fall.
The Contractor shall ensure that Full body harnesses conforming EN361 and having
authorized CЄ marking is used by all personnel while working at height. The lanyards and
life lines should have enough tensile strength to take the load of the worker in case of a fall.
One end of the lanyard shall be firmly tied with the harnesses and the other end with life
line. The harness should be capable of keeping the workman vertical in case of a fall,
enabling him to rescue himself.
The Contractor shall provide Roof Top Walk Ladders for carrying out activities on sloping
roofs in order to reduce the chances of slippages and falls.
The Contractor shall ensure that a proper Safety Net System is used wherever the hazard of
fall from height is present. The safety net, preferably a knotted one with mesh ropes
conforming to IS 5175/ ISO 1140 shall have a border rope & tie cord of minimum 12mm
dia. The Safety Net shall be located not more than 6.0 meters below the working surface
extending on either side up to sufficient margin to arrest fall of persons working at different
heights.
In case of accidental fall of person on such Safety Net, the bottom most portion of Safety
Net should not touch any structure, object or ground.
The Contractor shall ensure positive isolation while working at different levels like in the
pipe rack areas. The working platforms with toe boards & hand rails shall be sufficiently
strong & shall have sufficient space to hold the workmen and tools & tackles including the
equipments required for executing the job. Such working platforms shall have mid-rails, to
enable people work safely in sitting posture.
Suitable scaffoldings shall be provided to workmen for all works that cannot be safely done
from the ground or from solid construction except such short period work that can be safely
done using ladders or certified (by 3rd party competent person) man-basket. When a ladder
is used, an extra workman shall always be engaged for holding the ladder.
The Contractor shall ensure that the scaffolds used during construction activities shall be
strong enough to take the designed load. Main Contractor shall always furnish duly
approved construction-design details of scaffold & SWL (from competent designers) free
of charge, before they are being installed / constructed at site. Owner/EIL reserves the right
to ask the Contractor to submit certification and or design calculations from his Head office
/ Design/ Engineering expert regarding load carrying capacity of the scaffoldings.
All electrical installations/ connections shall be carried out as per the provisions of latest
revision of following codes/standards, in addition to the requirements of Statutory
Authorities and IE/applicable international rules & regulations:
- OISD STD 173 : Fire prevention & protection system for electrical installations
- SP 30 (BIS) : National Electric Code
a. Shall make Single Line Diagram (SLD) for providing connection to each equipments &
machinery and the same (duly approved by EIL/Owner) shall be pasted on the front face of
DBs (distribution boards) or JBs (Junction boxes) at every site. ( A typical Switch Board
Sketch is attached as Appendix -G )
b. Ensure that electrical systems and equipment including tools & tackles used during
construction phase are properly selected, installed, used and maintained as per provisions
of the latest revision of the Indian Electrical/ applicable international regulations.
c. Shall deploy qualified & licensed electricians for proper & safe installation and for regular
inspection of construction power distribution system/points including their earthing. A
copy of the license shall be submitted to EIL / Owner for records. Availability of at least
one competent (ITI qualified) / licensed electrician (by State Elec. authorities) shall be
ensured at site round the clock to attend to the normal/emergency jobs.
d. All switchboards / welding machines shall be kept in well-ventilated & covered shed/ with
rain shed protection. The shed shall be elevated from the existing ground level to avoid
water logging inside the shed . Installation of electrical switch board must be done taking
care of the prevention of shock and safety of machine.
e. No flammable materials shall be used for constructing the shed. Also flammable materials
shall not be stored in and around electrical equipment / switchboard. Adequate clearances
and operational space shall be provided around the equipment.
f. Fire extinguishers and insulating mats shall be provided in all power distribution centers.
g. Temporary electrical equipment shall not be employed in hazardous area without obtaining
safety permit.
i. All temporary installations shall be tested before energizing, to ensure proper earthing,
bonding, suitability of protection system, adequacy of feeders/cables etc.
k. Multilingual (Hindi, English and local language) caution boards, shock treatment charts and
instruction plate containing location of isolation point for incoming supply, name &
telephone No. of contact person in emergency shall be provided in substations and near all
distribution boards / local panels.
m. Regular inspection of all installations at least once in a month. (Ref. Format HSE-12).
3.3.6.2 The following features shall also be ensured for all electrical installations during construction
phase by the contractor:
Each installation shall have a main switch with a protective device, installed in an
enclosure adjacent to the metering point. The operating height of the main switch shall not
exceed 1.5 M. The main switch shall be connected to the point of supply by means of
armoured cable.
The outgoing feeders shall be double or triple pole switches with fuses / MCBs. Loads in a
three phase circuit shall be balanced as far as possible and load on neutral should not
exceed 20% of load in the phase.
The installation shall be adequately protected against overload, short circuit and earth
leakage by the use of suitable protective devices. Fuses wherever used shall be HRC type.
Use of rewirable fuses shall be strictly prohibited. The earth leakage device shall have an
operating current not exceeding 30 mA.
All connections to the hand tools / welding receptacles shall be taken through proper
switches, sockets and plugs.
All single phase sockets shall be minimum 3 pin type only. All unused sockets shall be
provided with socket caps.
Only 3 core (P+N+E) overall sheathed flexible cables with minimum conductor size of 1.5
mm2 copper shall be used for all single phase hand tools.
Only metallic distribution boxes with double earthing shall be used at site. No wooden
boxes shall be used.
All power cables shall be terminated with compression type cable glands. Tinned copper
lugs shall be used for multi-strand wires / cables.
Minimum depth of cable trench shall be 750 mm for MV & control cables and 900 mm for
HV cables. These cables shall be laid over a sand layer and covered with sand, brick & soil
for ensuring mechanical protection. Cables shall not be laid in waterlogged area as far as
practicable. Cable route markers shall be provided at every 25 M of buried trench route.
When laid above ground, cables shall be properly cleated or supported on rigid poles of at
least 2.1 M high. Minimum head clearance of 6 meters shall be provided at road crossings.
Under ground road crossings for cables shall be avoided to the extent feasible. In any case
no under ground power cable shall be allowed to cross the roads without pipe sleeve.
All cable joints shall be done with proper jointing kit. No taped/ temporary joints shall be
used.
All cables and wire rope used for earth connections shall be terminated through tinned
copper lugs.
In case of local earthing, earth electrodes shall be buried near the supply point and earth
continuity wire shall be connected to local earth plate for further distribution to various
appliances. All insulated wires for earth connection shall have insulation of green colour.
Separate core shall be provided for neutral. Earth / Structures shall not be used as a neutral
in any case.
ON/OFF position of all switches shall be clearly designated / painted for easy isolation in
emergency.
Contractor shall ensure that flash back arrestors conforming to BS: 6158 or equivalent are
installed on all gas cylinders as well as at the torch end of the gas hose, while in use.
All cylinders shall be mounted on trolleys and provided with a closing key. Empty &
filled-up gas cylinders shall be stored separately with TAG, protecting them from direct
sun or rain. Minimum 2 nos. of Portable DCP type fire extinguishers (10 kg) shall be
maintained at the gas cylinder stores. Stacking & storing of compressed gas cylinders shall
be arranged away from DG set, hot works, Elect. Panels / Elec. boards, etc
The burner and the hose placed downstream of pressure reducer shall be equipped with
Flash Back Arrester/Non Return Valve device.
The hoses for acetylene and oxygen cylinders must be of different colours. Their
connections to cylinders and burners shall be made with a safety collar.
At end of work, the cylinders in use shall be closed and hoses depressurized.
Cutting of metals using gases, other than oxygen & acetylene, shall require written
concurrence from Owner.
All welding machines shall have effective earthing at least at distinctly isolated two points.
In order to help maintain good housekeeping, and to reduce fire hazard, live electrode bits
shall be contained safely and shall not be thrown directly on the ground.
The hoses of Acetylene and Oxygen shall be kept free from entanglement & away from
common pathways / walkways and preferably be hanged overhead in such a manner which
can avoid contact with cranes, hydra or other mobile construction machinery.
Hot spatters shall be contained / restricted appropriately (by making use of effective fire-
retardant cloth/fabric) and their flying-off as well as chance of contact with near-by
flammable materials shall be stopped.
The Contractor shall arrange adequate systems & practices for accumulation / collection of
metal & other scraps and remnant electrodes and their safe disposal at regular interval so as
to maintain the fabrication and other areas satisfactorily clean & tidy.
All gas cylinders must have a cylinder cap on at all times when not in use.
The Contractor shall assign to his workmen, tasks commensurate with their qualification,
experience and state of health.
All lifting tools, tackles, equipment, accessories including cranes shall be tested
periodically by statutory/competent authority for their condition and load carrying capacity.
Valid test & fitness certificates from the applicable authority shall be submitted to
Owner/EIL for their review/acceptance before the lifting tools, tackles, equipment,
accessories and cranes are used.
The contractor shall not be allowed to use defective equipment or tools not adhering to
safety norms.
Contractor shall arrange non-sparking tools for project construction works in operating
plant areas / hydrocarbon prone areas.
Wherever required the Contractor shall make use of Elevated Work Platforms (EWP) or
Aerial Work Platforms (mobile or stationary) to avoid ergonomical risks and workmen
shall be debarred to board such elevated platform during the course of their shifting /
transportation.
Contractor shall ensure installation of Safe Load Indicator (SLI) on all cranes (while in use)
to minimize overloading risk. SLI shall have capability to continuously monitor and
display the load on the hook, and automatically compare it with the rated crane capacity at
the operating condition of the crane. The system shall also provide visual and audible
warnings at set capacity levels to alert the operator in case of violations.
The contractor shall be responsible for safe operations of different equipments mobilized
and used by him at the workplace like transport vehicles, engines, cranes, mobile ladders,
scaffoldings, work tools, etc.
The Contractor shall arrange periodical training for the operators of hydra, crane,
excavator, mobile machinery, etc. at site by utilizing services from renowned
manufacturers
The contractor shall identify all operations that can adversely affect the health of its
workers and issue & implement mitigation measures.
For surface cleaning operations, sand blasting shall not be permitted even if not explicitly
stated elsewhere in the contract.
To eliminate radiation hazard, Tungsten electrodes used for Gas Tungsten Arc Welding
shall not contain Thorium.
Workmen shall be made aware of correct methods for lifting, carrying, pushing & pulling
of heavy loads. Wherever possible, manual handling shall be replaced by mechanical lifting
equipments.
For jobs like drilling/demolishing/dismantling where noise pollution exceeds the specified
limit of 85 decibels, ear muffs shall be provided to the workers.
To avoid work related upper limb disorders (WRULD) and backaches, Display Screen
Equipments' workplace stations shall be carefully designed & used with proper sitting
postures. Power driven hand-held tools shall be maintained in good working condition to
minimize their vibrating effects and personnel using these tools shall be taught how to
operate them safely & how to maintain good blood circulation in hands.
The Contractor shall arrange health check up (by registered medical practitioner) for all the
workers at the time of induction. Health check may have to be repeated if the nature of duty
assigned to him is changed necessitating health check or doubt arises about his wellness.
EIL/Owner reserves the right to ask the contractor to submit medical test reports. Regular
health check-ups are mandatory for the workers assigned with Welding, Radiography,
Blasting, Painting, Heavy Lift and Height (>2m) jobs. All the health check-ups shall be
conducted by registered Medical practitioner and records are to be maintained by the
Contractor.
The Contractor shall ensure vaccination of all the workers including their families, during
the course of entire project span.
Hazardous, inflammable and/or toxic materials such as solvent coating, thinners, anti-
termite solutions, water proofing materials shall be stored in appropriate containers
preferably with lids having spillage catchment trays and shall be stored in a good ventilated
area. These containers shall be labeled with the name of the materials highlighting the
hazards associated with its use and necessary precautions to be taken. Respective MSDS
(Material Safety Data Sheet) shall be made available at site & may be referred whenever
problem arises.
Where contact or exposure of hazardous materials are likely to exceed the specified limit or
otherwise have harmful effects, appropriate personal protective equipments such as gloves,
goggles/face-shields, aprons, chemical resistant clothing, respirator, etc. shall be used.
The work place shall be checked prior to start of activities to identify the location, type and
condition of any asbestos materials which could be disturbed during the work. In case
asbestos material is detected, usage of appropriate PPEs by all personnel shall be ensured
and the matter shall be reported immediately to EIL/ Owner.
The contractor shall establish a regular cleaning and basic housekeeping programme that covers
all aspects of the workplace to help minimize the risk of slips, trips & falls. The contractor shall
take positive measures like keeping the work area tidy, storing waste in suitable containers &
harmful items separately, keeping passages, stairways, entrances & exits especially emergency
ones clear, cleaning up spillages immediately and replacing damaged carpet/ floor tiles, mats &
rugs at once to avoid slips, trips & falls.
All personnel exposed to physical agents such as ionizing & non-ionizing radiation,
including ultraviolet rays or similar other physical agents shall be provided with adequate
shielding or protection commensurate with the type of exposure involved.
For Open Field Radiography works , requirements of Bhabha Atomic Research Centre
(BARC)/ Atomic Energy Regulatory Board (AERB) shall be followed.
The Contractor shall implement an effective system of control (as described in the AERB
regulations) at site for handling radiography-sources & for avoiding its misuse & theft.
The contractor shall generate the Format No: HSE-8 “Permit for radiation work” before
start of work.
In case the radiography work has to be carried out at day time, suitable methodology to be
used so that other works, people are not affected.
Blasting operations shall be carried out as per latest Explosive Rules (Indian / International)
with prior permission. The Contractor shall obtain license from Chief Controller of
Explosives (CCoE) for collection, transportation, storage of explosives as well as for
carrying out blasting operations.
The Contractor shall prepare exclusive method statement (in cognizance with statutory
requirements) for diffusing unfired explosives, if any, at project site before carrying out
actual task. Nowhere blasting shall be carried out by the Contractor or its agency without
the involvement of competent supervisor and licensed blaster / shot blaster.
The contractor shall adhere to safe demolishing/ dismantling practices at all stages of work
to guard against unsafe working practices.
The contractor shall disconnect service lines (power, gas supply, water, etc.)/ make
alternate arrangements prior to start of work and restore them, if required as directed by
EIL/ Owner at no extra cost.
Before carrying out any demolition/ dismantling work, the contractor shall take prior
approval of EIL/Owner and generate the Format No.HSE-9. For revamp jobs in operating
plants where location of underground utilities is not known with certainty, the contractor
shall depute an experienced engineer for supervision and shall make adequate arrangements
for Fire fighting & First-Aid during the execution of these activities.
The Contractor shall arrange approved Job Safety Analysis (JSA) / Method Statement for
the specific demolition / dismantling task and corresponding action plan commensurate
with hazards / risks associated therein. In no case any activity related to demolition /
dismantling shall be carried out by the Contractor without engaging own supervision / field
engineer.
The Contractor shall ensure adequately planned road transport safety management system.
The vehicles shall be fitted with reverse warning alarms & flashing lights / fog-lights and
usage of seat belts shall be ensured.
The Contractor shall also ensure a separate pedestrian route for safety of the workers and
comply with all traffic rules & regulations, including maintaining speed limit of 20 kmph
or indicated by owner for all types of vehicles / mobile machinery. The maximum
allowable speed shall be adhered to.
In case of an alert or emergency, the Contractor must arrange clearance of all the routes,
roads, access. The Contractor shall deploy sufficient number of traffic controllers at project
site routes / roads/ accesses, to alert reversing movement of vehicles & machinery as well
as pedestrians.
Dumpers, Tippers, etc. shall not be allowed to carry workers within the plant area and also
to & from the labour colony to & from project sites.
Hydras shall only be allowed for handling the materials at fabrication/ storage yards and in
no case shall be allowed to transport the materials over project / plant roads.
The Contractor shall not deploy any such mobile machinery / equipments, which do not
have competent operator and / or experienced banks-man / signal-man. Such machinery /
equipments shall have effective limit-switches, reverse-alarm, front & rear-end lights etc.
and shall be maintained in good working order.
The Contractor shall not carry-out maintenance of vehicles / mobile machinery occupying
space on project / plant roads and shall always arrange close supervision for such works.
For pipeline jobs, the contractor shall submit a comprehensive plan covering transportation,
loading / unloading of pipes, movement of side booms, movement of vehicles on the ROW,
etc.
Contractor’s shall arrange /install visible road signs, diversion boards, caution boards, etc
on project roads for safe movement of men and machinery.
Contractor shall, at the minimum, ensure the following facilities at work sites:
A crèche at site where 10 or more female workers are having children below the age of 6
years.
Adequately ventilated / illuminated rooms at labour camps & its hygienic up-keeping.
Reasonable canteen facilities at site and in labour camps at appropriate location depending
upon site conditions. Contractor shall make use of “industrial” variety of LPG cylinder &
satisfactory illumination at the canteens. Necessary arrangement for efficient disposal of
wastes from canteens & urinals /toilets shall also be made and regular review shall be made
to maintain the ambience satisfactorily hygienic & shall also comply with all applicable
statutory requirements.
Adequately lighted & ventilated Rest rooms at site (separate for male workers and female
workers).
Urinals, Toilets, drinking water, washing facilities, adequate lighting at site and labour
camps, commensurate with applicable Laws / Legislation.
Contractor shall ensure proper storage and utilization methodology of materials that are
detrimental to the environment. Where required, Contractor shall ensure that only the
environment friendly materials are selected and emphasize on recycling of waste materials,
such as metals, plastics, glass, paper, oil & solvents. The waste that cannot be minimized,
reused or recovered shall be stored and disposed of safely. In no way, toxic spills shall be
allowed to percolate into the ground. The contractor shall not use the empty areas for dumping
the wastes.
The contractor shall strive to conserve energy and water wherever feasible.
The contractor shall ensure dust free environment at workplace by sprinkling water on the
ground at frequent intervals. The air quality parameters for dust, poisonous gases, toxic releases,
harmful radiations, etc. shall be checked by the contractor on daily basis and whenever need
arises.
The contractor shall not be allowed to discharge chemicals, oil, silt, sewage, sullage and other
waste materials directly into the controlled waters like surface drains, streams, rivers, ponds. A
discharge plan suggesting the methods of treating the waste before discharging shall be
submitted to EIL/Owner for approval.
For pipeline jobs, top soil shall be stacked separately while making ROW through fields. This
fertile soil shall be placed back on top after backfilling.
For offshore construction barges, arrangements shall be made for safe disposal of human, food
& other wastes and applicable laws in this regard shall be followed.
All persons deployed at site shall be knowledgeable of and comply with the environmental laws,
rules & regulations relating to the hazardous materials, substances and wastes. Contractor shall
not dump, release or otherwise discharge or disposes off any such materials without the express
authorization of EIL/Owner. An indicative list of Statutory Acts & Rules relating to HSE is
given under Appendix-D.
Contractor shall take appropriate measures to protect workers from severe storms, rain, solar
radiations, poisonous gases, dust, etc. by ensuring proper usage of PPEs like Sun glasses, Sun
screen lotions, respirators, dust masks, etc. and rearranging/ planning the construction activities
to suit the weather conditions. Effective arrangement (without creating inconvenience to project
facilities & permanent installations) for protecting workmen from hailstorm, drizzle in the form
of temporary shelter shall be made at site.
3.3.20 Communication
All persons deployed at the work site shall have access to effective means of communication so
that any untoward incident can be reported immediately and assistance sought by them.
All health & safety information shall be communicated in a simple & clear language easily
understood by the local workforce.
a. Quality Policy
b. HSE Policy contents
c. Environment Policy
d. HSE Objectives
e. Safety Cardinal Rules
f. HSE Target – reached or missed
g. Praises & Warnings to personnel for HSE Management
h. Safety Walk Through Reports and safety defects / shortfalls (by management)
i. HSE Audit results
j. Revised Statutory Health & Safety provisions, if any
k. H & S publicity
l. Suggestions
a. Complaints
b. Compliances on safety defects / shortfalls
c. Suggestions
d. Proposals for changes & improvements
e. HSE Reports (including near-miss reports)
The contractor shall generate a work permit (Format No. HSE -7) before entering a confined
space. People, who are permitted to enter into confined space, must be medically examined &
certified by registered doctor, confirming their ‘medical fitness for working in confined space’.
All necessary precautions mentioned therein shall be adhered to. An attendant shall be
positioned outside a confined space for extending help during an emergency. All appropriate
PPEs and air quality parameters shall be checked before entering a confined space. It shall be
ensured that the piping of the equipment which has to be opened is pressure- free by checking
that blinds are in place, vents are open and volume is drained. Inside confined space works, only
electrical facilities / installations of 24V shall be permitted. Contactor shall ensure usage of safe
& suitable arrangement of oxygen supply for individual workmen (during the course of work in
confined space), if oxygen concentration is found to be less than 19.5% (v/v) there.
The contractor shall submit detailed rigging studies plan for EIL/ Owner approval prior to
lifting equipment which cannot be erected with a crane of approx. 100 MT capacity due to
constraints of its dimensions, location of foundation height, approach & weight.
Contractor shall generate the format no:HSE-15 “Permit for heavy lift/critical erection”
Prior to actual lifting activities, contractor shall check the validity of the crane inspection
certificate issued by statutory/ competent authority. This requirement shall also apply to all
rigging equipments utilized for the job.
The contractor shall, at all times, be responsible for all rigging activities.
The Contractor shall ensure medical fitness of all workmen who are engaged / involved in
erection of equipments, vessels etc. and such fitness checks shall be carried-out every six
months interval with the help of a registered medical practitioner & record shall be
maintained
Adequate safety measures such as positive barricading, usage of appropriate PPEs, permit
to work, etc. shall be taken during all heavy or critical lifts.
For lifting any material (irrespective of shape, size or volume), at any height, it is always
advisable to prepare a Plan of Erection (PoE) taking into consideration hazards & risks
associated therein – this can enable people to put their own experiences of various natures
& side-by-side establish a practical method for risk-free erection / lifts. The contractor shall
prepare PoE & shall document the same, when risks are identified as “medium” or “high”
and the same shall be approved by its competent / qualified engineer.
The contractor shall measure an activity in both leading & trailing indicators for statistical and
performance measurement. The activities pertaining to key performance indicators are covered
in Monthly HSE Report (Format No. HSE-5). The contractor shall try to achieve a statistically
fair record and strive for its continual improvement.
- Number of Safety Inductions carried-out at site (for workmen & staff members)
- Number of HSE inspections carried out
- Number of “Safety Walk Through” carried-out by site-head.
- Number of HSE shortfalls / lapses identified per contractor & closed-out in time.
- Number of Safety Meetings conducted (in-house / with contractors)
- Number of HSE Audits made (internal & external) vis-à-vis non conformances raised
- Number of HSE Awareness / Motivational program conducted by contractors
- Number of HSE Trainings conducted at site for supervisors & workmen
- Study of Near miss case reported
- Encouragements / Awards / Recognitions to workmen, job supervisors & field engineers.
- Suggestions for improvement
- Calculation of HSE statistics viz frequency rate, severity rate, LTA free manhours,etc
- Analysis of incidents / accidents (nature, severity, types etc.)
- Study of Incident / Accident with respect to :-
Variety
Period of the year / project span
Timings of the incident / accident
Age profile of victims
Body parts involved
Penalty levied for causing incident / accident
Contractor shall take appropriate measures and necessary work permits/clearances if work is to
be done in or around marshy areas, river crossings, mountains, monuments, etc. The Contractor
shall make right assessment and take all necessary action for developing work areas to make
them safe & suitable for crane operations or other vehicular movement before carrying out any
project related activity / operation. Contractor shall take all necessary actions to make the
surroundings of its site establishments (site office, stores, lay-down area etc.) work-worthy
safe and secure.
Contractor shall ensure that boats and other means used for transportation, surveying &
investigation works shall be certified seaworthy by a recognized classification society. It shall
be equipped with all life saving devices like life jackets, adequate fire protection arrangements
and shall posses communication facilities like cellular phones, wireless, walkie-talkie. All
divers used for seabed surveys, underwater inspections shall have required authorized license,
suitable life saving kit. Number of hours of work by divers shall be limited as per regulations.
EIL/ Owner shall have the right to inspect the boat and scrutinize documents in this regard.
3.3.26 Excavation
The Contractor shall obtain permission from competent authorities prior to excavation wherever
required.
The Contractor shall locate the position of buried utilities (water line, cable route, etc.) by
referring to project / plant drawing / in consultation with EIL/Owner. The Contractor shall start
digging manually to locate the exact position of buried utilities & thereafter use mechanical
means.
The Contractor shall keep soil heaps at least 1.5 M away from edge or a distance equal to depth
of pit (whichever is more)
The Contractor shall maintain sufficient “angle of repose” during excavation – shall also
provide slope or suitable bench as decided by EIL / Owner.
The Contractor shall arrange “battering” or “benching” wherever required for preventing
collapse of edge of excavations.
The Contractor shall identify & arrange de-watering pump or well-point system to prevent earth
collapse due to heavy rain / influx of underground water.
The Contractor shall arrange protective fencing / barricading with warning signal around
excavated pits, trenches, etc. along with minimum 2 (two) entries, exits / escape ladders.
The Contractor must avoid “underpinning” / under-cutting to prevent collapse of chunk of earth
during excavation
The Contractor shall use “stoppers” to prevent over-run of vehicle wheels at the edge of
excavated pits / trenches.
The Contractor shall arrange strengthening of “shoring” & “strutting” proactively to avoid
collapse of earth / edges due to vehicular movement in close proximity of excavated areas / pits
/ trenches, etc.
Contractor shall conduct daily TBT with workers prior to start of work and shall maintain
proper record of the meeting. A suggested format is given below. The TBT is to be conducted
by the immediate supervisor of the workers
The Contractor shall conduct TBT before start of every morning or evening shift or night shift
activities, for alerting the workers on specific hazards and their appropriate dos & don’ts. The
Contractor shall provide sufficient rests to the site workmen and their foremen to avert fatigue
& thereby endangering their lives during the course of site works.
Remarks, in any
The above record can be kept in local language, which workers can read. These records shall be
made available to EIL/ Owner whenever demanded.
Initial induction of workers into Construction oriented activities and appraising them about
the methodology of works and how to carry-out safely and the same should not be inter
mixed with Tool Box Talks or HSE Training. In this regard careful action should be made
& maintained for imparting HSE induction to every individual, irrespective of his
task/designation/level of employment, whereas, HSE Training should be imparted to
specific person/group of people who are to carry-out that specific task more than once – for
example, Riggers must be trained for working at heights, welders must be trained for work
in confined space, fitters/carpenters, mesons must be trained for work at heights, etc.
Contractor shall conduct Safety induction programme on HSE for all his workers and
maintain records. The Gate Pass shall be issued only to those workers who successfully
qualify the Safety induction programme.
The Contractor shall brief the visitors about the HSE precautions which are required to be
taken before their proceeding to site and make necessary arrangements to issue appropriate
PPEs like Aprons, hard hats, ear-plugs, goggles & safety shoes etc., to his visitors. The
Contractor shall always maintain relevant acknowledgement from visitor on providing him
brief information on HSE actions.
Contractor shall ensure that all his personnel possess appropriate training to carry out the
assigned job safely. The training should be imparted in a language understood by them and
should specifically be trained about
The Contractor shall make regular program for conducting Safety Training on various
topics related to various activities & their safe-guarding utilizing experienced persons /
outside agency / faculty. A program for Safety Training (indicative list as per Appendix –F)
shall be furnished by the Contractor in its HSE Plan .
For offshore and jetty jobs, contractor shall ensure that all personnel deployed have
undergone a structured sea survival training including use of lifeboats, basket landing, use
of radio communication etc. from an agency acceptable to Owner/EIL.
As a minimum, the contractor shall ensure adherence to following safety requirements while
working in or in the close vicinity of an operating plant:
a) Contractor shall obtain permits for Hot work, Cold work, Excavation and Confined Space
from Owner in the prescribed format.
b) The contractor shall monitor record and compile list of his workers entering the operational
plant/unit each day and ensure & record their return after completing the job.
c) Contractor’s workers and staff members shall use designated entrances and proceed by
designated routes to work areas only assigned to them. The workers shall not be allowed to
enter units' area, tanks area, pump rooms, etc. without work authorization permit.
d) Work activities shall be planned in such a way so as to minimize the disruption of other
activities being carried out in an operational plant/unit and activities of other contractors.
e) The contractor shall submit a list of all chemicals/toxic substances that are intended to be
used at site and shall take prior approval of the Owner.
f) Specific training on working in a hydrocarbon plant shall be imparted to the work force and
mock drills shall be carried out for Rescue operations/First-Aid measures.
h) Care shall be taken to prevent hitting underground facilities such as electrical cables,
hydrocarbon piping during execution of work.
j) Emergency evacuation plan shall be worked out and all workmen shall be apprised about
evacuation routes. Mock drill operations may also be conducted.
k) Flammable gas test shall be conducted prior to any hot work using appropriate measuring
instruments. Sewers, drains, vents or any other gas escaping points shall be covered with
flame retardant tarpaulin.
l) Respiratory devices shall be kept handy while working in confined zones where there is a
danger of inhalation of poisonous gases. Constant monitoring of presence of Gas/
Hydrocarbon shall be done.
m) Clearance shall be obtained from all parties before starting hot tapping, patchwork on live
lines and work on corroded tank roof.
o) Welding spatters shall be contained properly and in no case shall be allowed to fall on the
ground containing oil. Similar care shall be taken during cutting operations.
p) The vehicles, cranes, engines, etc. shall be fitted with spark arresters on the exhaust pipe
and got it approved from Safety Department of the Owner.
q) Plant air should not be used to clean any part of the body or clothing or use to blow off dirt
on the floor.
r) Gas detectors should be installed in gas leakage prone areas as per requirement of Owner's
plant operation personnel.
s) Experienced full time safety personnel shall be exclusively deployed to monitor safety
aspects in running plants.
The contractor shall develop a method of check & balance through self assessment &
enhancement techniques and shall explore the opportunities for continual improvement in the
HSE system.
The contractor shall encourage his workforce to promote HSE efforts at workplace by way of
organizing workshops/seminars/training programmes, celebrating HSE awareness weeks &
National Safety Day, conducting quizzes & essay competitions, distributing pamphlets, posters
& material on HSE, providing incentives for maintaining good HSE practices and granting
incentives / bonus for completing the job without any lost time accident.
3.9 Lock Out and Tag Out (LOTO) for isolation of energy source
Contractor shall follow the LOTO/Isolation procedure of owner for all energy source
isolations installed/under purview by /of owner ie. “Brown field”
For all the other energy source (not under purview of client/owner) i.e “Green field”
Contractor shall develop a system to ensure the isolation of equipments, pipelines, Vessel,
electrical panels from the energy source covering following as minimum:-
Only on confirmation of above the contractor will remove their lock and tag from the
isolation points and give instructions for energizing the same. Only the person carrying out
the task shall himself carry the key for the lock in /Lock out.
The Contractor shall submit a comprehensive Health, Safety and Environment Plan or
programme for approval by EIL/Owner prior to start of work. The Contractor shall participate in
the pre-start meeting with EIL/Owner to finalize HSE Plans which shall including the
following:
Contractor shall implement approved Health, Safety and Environment management programme
including but not limited to as brought out under para 3.0. Contractor shall also ensure:
to arrange workmen compensation insurance, registration under ESI Act, third party
liability insurance, registration under BOCW Act, etc, as applicable.
to arrange all HSE permits before start of activities (as applicable), like permits for hot
work, working at heights (Refer Format No. HSE-6), confined space (Refer Format No.
HSE-7), Radiation Work Permit (Refer Format No. HSE-8), Demolishing/ Dismantling
Work Permit (Refer Format No. HSE-9),Permit for erection/modification & dismantling of
scaffolding(Refer Format No:HSE-14), Permit for heavy lift/critical erection (Refer Format
No:HSE-15) ,Permit for energy Isolation & De-isolation” (HSE-16) ,storage of chemical /
explosive materials & its use and implement all precautions mentioned therein. In this
regard, requirements of Oil industry Safety Directorate Standard No. Std -105 "Work
Permit Systems” shall be complied with while working in existing Oil or Gas processing
plants. List of the persons involved shall be maintained as annexure to the work permit
issued for a particular activity.
to submit, timely, the completed checklist on HSE activities in Format No.HSE-1, Monthly
HSE report in Format No.HSE-5 (use of web based package (www.eil.co.in/conthse) is
compulsory wherever the facility is available else a hard copy is to be submitted), accident/
incident reports, investigation reports etc. as per EIL/Owner requirements. Compliance of
instructions on HSE shall be done by Contractor and informed urgently to EIL/Owner.
that his top most executive at site attends all the Safety Committee/HSE meetings arranged
by EIL/Owner and carries out safety walk through regularly. Only in case of his absence
from site that a second senior most person shall be nominated by him, in advance, and
communicated to EIL/Owner for performing the above tasks.
display at site office and at prominent locations HSE Policy, caution boards, list of
hospitals, emergency services available, safety signs like Men at work, Speed Limits,
Hazardous Area, various do’s & don’ts, etc.
identify, assess, analyze & mitigate the construction hazards & incorporate relevant control
measures before actually executing site works. (HIRAC = Hazard Identification, Risk
Analysis and Control).
carryout audits/inspection (internal & external) at his works as well as sub contractor works
as per approved HSE plan/procedure/programme & submit the compliance reports of
identified shortfalls for EIL/Owner review.
arranging HSE training for site workmen (of his own & sub contractors) through internal or
external faculty at periodical intervals.
assistance & cooperate during HSE audits by EIL/Owner or any other 3rd party and submit
compliance report.
generate & submit of HSE records/report as per this specification.
carry-out all dismantling activities safely, with prior approval of EIL/Owner representative.
The Contractor shall ensure that “Hot works” and painting works do not continue at the
same place / location at project site for which chance or probability of “fire” incident
exists.
The contractor shall review the HSE management system of the sub-contractors in line with the
requirements given in this specification. The contractor shall be held responsible for the
shortcomings observed in the HSE management system of the sub-contractor(s) during
execution of the job.
5.0 RECORDS
At the minimum, the contractor shall maintain/ submit HSE records in the following reporting
formats/:
APPENDIX-A
(Sheet 1 of 2)
A. IS CODES ON HSE
SP: 53 Safety code for the use, Care and protection of hand operated tools.
IS: 838 Code of practice for safety & health requirements in electric and gas welding
and cutting operations
IS: 1179 Eye & Face precautions during welding, equipment etc.
IS: 1860 Safety requirements for use, care and protection of abrasive grinding wheels.
IS: 1989 (Pt -II) Leather safety boots and shoes
IS: 2925 Industrial Safety Helmets
IS: 3016 Code of practice for fire safety precautions in welding & cutting operation.
IS: 3043 Code of practice for earthing
IS: 3764 Code of safety for excavation work
IS: 3786 Methods for computation of frequency and severity rates for industrial injuries
and classification of industrial accidents
IS: 3696 Safety Code of scaffolds and ladders
IS: 4083 Recommendations on stacking and storage of construction materials and
components at site
IS: 4770 Rubber gloves for electrical purposes
IS: 5121 Safety code for piling and other deep foundations
IS: 5216 (Pt-I) Recommendations on Safety procedures and practices in electrical works
IS: 5557 Industrial and Safety rubber lined boots
IS: 5983 Eye protectors
IS: 6519 Selection, care and repair of Safety footwear
IS: 6994 (Pt-I) Industrial Safety Gloves (Leather & Cotton Gloves)
IS: 7293 Safety Code for working with construction Machinery
IS: 8519 Guide for selection of industrial safety equipment for body protection
IS: 9167 Ear protectors
IS: 11006 Flash back arrestor (Flame arrestor)
IS: 11016 General and safety requirements for machine tools and their operation
IS: 11057 Specification for Industrial safety nets
IS: 11226 Leather safety footwear having direct moulded rubber sole
IS: 11972 Code of practice for safety precaution to be taken when entering a sewerage
system
IS: 13367 Code of practice-safe use of cranes
IS: 13416 Recommendations for preventive measures against hazards at working place
APPENDIX-A
(Sheet 2 of 2)
Safe handling of compressed: P-1 (Compressed Gas Association Gases in cylinders 1235
Jefferson Davis Highway,
Arlington VA 22202 - USA)
Lanyard : EN-354
APPENDIX-B
DETAILS OF FIRST AID BOX
------------------------------------------------------------------------------------------------------------------------
SL. DESCRIPTION QUANTITY
NO.
------------------------------------------------------------------------------------------------------------------------
1. Small size Roller Bandages, 1 Inch Wide (Finger Dressing small) 6 Pcs.
2. Medium size Roller Bandages, 2 Inches Wide (Hand & Foot Dressing) 6 Pcs.
3. Large size Roller Bandages, 4 Inches Wide (Body Dressing Large) 6 Pcs.
4. Large size Burn Dressing (Burn Dressing Large) 4 Pkts.
5. Cotton Wool (20 gms packing) 4 Pkts.
6. Antiseptic Solution Dettol (100 ml.) or Savlon 1 Bottle
7. Mercurochrome Solution (100 ml.) 2% in water 1 Bottle
8. Ammonia Solution (20 ml.) 1 Bottle
9. A Pair of Scissors 1 Piece
10. Adhesive Plaster (1.25 cm X 5 m) 1 Spool
11. Eye pads in Separate Sealed Pkt. 4 pcs.
12. Tourniqut 1 No.
13. Safety Pins 1 Dozen
14. Tinc. Iodine/ Betadin (100 ml.) 1 Bottle
15. Polythene Wash cup for washing eyes 1 No.
16. Potassium Permanganate (20 gms.) 1 Pkt.
17. Tinc. Benzoine (100 ml.) 1 Bottle
18. Triangular Bandages 2 Nos.
19. Band Aid Dressing 5 Pcs.
20. Iodex/Moov (25 gms.) 1 Bottle
21. Tongue Depressor 1 No.
22. Boric Acid Powder (20 gms.) 2 Pkt.
23. Sodium Bicarbonate (20 gms.) 1 Pkt.
24. Dressing Powder (Nebasulf) (10 gms.) 1 Bottle
25. Medicinal Glass 1 No.
26. Duster 1 No.
27. Booklet (English & Local Language) 1 No. each
28. Soap 1 No.
29. Toothache Solution 1 No.
30. Vicks (22 gms.) 1 Bottle
31. Forceps 1 No.
32. Note Book 1 No.
33. Splints 4 Nos.
34. Lock 1 Piece
35. Life Saving/Emergency/Over-the counter Drugs As decided at site
-----------------------------------------------------------------------------------------------------------------
Box size: 14" x 12" x 4"
-----------------------------------------------------------------------------------------------------------------
Note : The medicines prescribed above are only indicative. Equivalent medicines can also be used.
A prescription, in this regard, shall be required from a qualified Physician.
APPENDIX-C
Fire
Extinguisher
Multi purpose
Fire Water Foam CO2 Dry Powder
(ABC)
Inflammable liquids
like alcohol, diesel,
petrol, edible oils,
bitumen
Originated from
gases like LPG,
CNG, H2
Electrical fires
: NOT TO BE USED
Note: Fire extinguishing equipment must be checked at least once a year and after every use by an
authorized person. The equipment must have an inspection label on which the next inspection date is
given. Type of extinguisher shall clearly be marked on it.
APPENDIX-D
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
(A) Falling into pit Personal injury Provide guard rails/ barricade with warning
EXCAVATION signal
Provide at least two entries/ exits.
Pit Excavation Provide escape ladders.
upto 3.0m Earth Collapse Suffocation/ Provide suitable size of shoring and strutting, if
Breathlessness required.
Buried Keep soil heaps away from the edge equivalent to
1.5m or depth of pit whichever is more.
Don't allow vehicles to operate too close to
excavated areas. Maintain at least 2m distance
from edge of cut.
Maintain sufficient angle of repose. Provide
slope not less than 1:1 and suitable bench of 0.5m
width at every 1.5m depth of excavation in all
soils except hard rock.
Battering/benching the sides.
Contact with Electrocution Obtain permission from competent authorities,
buried electric Explosion prior to excavation, if required.
cables Locate the position of buried utilities by referring
Gas/ Oil to plant drawings.
Start digging manually to locate the exact
Pipelines position of buried utilities and thereafter use
mechanical means.
Pit Excavation Same as above Can cause Prevent ingress of water
beyond 3.0m plus drowning situation Provide ring buoys
Flooding due to Identify and provide suitable size dewatering
excessive rain/ pump or well point system
underground
water
Digging in the Building/Structure Obtain prior approval of excavation method from
vicinity of may collapse local authorities.
existing Building/ Loss of health & Use under-pining method
Structure wealth Construct retaining wall side by side.
Movement of May cause cave-in Barricade the excavated area with proper lighting
vehicles/ or slides. arrangements
equipments close Persons may get Maintain at least 2m distance from edge of cut
to the edge of cut. buried. and use stop blocks to prevent over-run
Strengthen shoring and strutting
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Narrow deep Same as above May cause severe Battering/benching of sides
excavations for plus injuries or prove Provide escape ladders
pipelines, etc. Frequent cave-in fatal
or slides
Flooding due to May arise drowning Same as above plus
Hydro- static situation Bail out accumulated water
testing Maintain adequate ventilation.
Rock by Improper May prove fatal Ensure proper storage, handling & carrying of
excavation handling of explosives by trained personnel.
blasting explosives Comply with the applicable explosive acts &
rules.
Uncontrolled May cause severe Allow only authorized persons to perform
explosion injuries or prove blasting operations.
fatal Smoking and open flames are to be strictly
prohibited
Scattering of Can hurt people Use PPE like goggles, face mask, helmets etc.
stone pieces in
atmosphere
Rock excavation Entrapping of May cause severe Barricade the area with red flags and blow siren
by blasting persons/ animals. injuries or prove before blasting.
(Contd) fatal
Misfire May explode Do not return to site for at least 20 minutes or
suddenly unless announced safe by designated person.
Piling Work Failure of pile- Can hurt people Inspect Piling rigs and pulley blocks before the
driving beginning of each shift.
equipment
Noise pollution Can cause deafness Use personal protective equipments like ear
and psychological plugs, muffs, etc.
imbalance.
Extruding Can hurt people Barricade the area and install sign boards
rods/casing Provide first-aid
Working in the Can cause Keep sufficient distance from Live-Electricity as
vicinity of 'Live- electrocution/ per IS code.
Electricity' Asphyxiation Shut off the supply, if possible
Provide artificial/rescue breathing to the injured
(B) Air pollution by May affect Wear respirators or cover mouth and nose with
CONCRETING cement Respiratory System wet cloth.
Handling of Hands may get Use gloves & other PPE.
ingredients injured
Protruding Feet may get Use Provide platform above reinforcement for
reinforcement injured movement of workers.
rods.
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Earthing of Can cause Ensure earthing of equipments and proper
electrical electrocution/ functioning of electrical circuit before
mixers, asphyxiation commencement of work.
vibrators, etc.
not done.
Falling of Persons may get Use hard hats
materials from injured Remove surplus material immediately from work
height place.
Ensure lighting arrangements during night hours
Continuous Cause tiredness of Insist on shift pattern
pouring by same workers and may Provide adequate rest to workers between
gang lead to accident. subsequent pours.
Revolving of Parts of body or Allow only mixers with hopper
concrete mixer/ clothes may get Provide safety cages around moving motors
vibrators entrapped. Ensure proper mechanical locking of vibrator
Super-structure Same as above Shuttering/props Avoid excessive stacking on shuttering material
plus may collapse and Check the design and strength of shuttering
Deflection in prove fatal material before commencement of work
props or Rectify immediately the deflection noted during
shuttering concreting.
material
Passage to work Improperly tied and Ensure the stability and strength of passage
place designed before commencement of work.
props/planks may Do not overload and stand under the passage.
collapse
(C) Curtailment and Persons may get Use PPE like gloves, shoes, helmets, etc.
REINFOR- binding of rods injured Avoid usage of shift tools
CEMENT Carrying of rods Workers may get Provide suitable pads on shoulders and use safety
for short injured their hands gloves.
distances/at and shoulders. Tie up rods in easily liftable bundles
heights Ensure proper staging.
Checking of Rods may cut or Use measuring devices like tape, measuring rods,
clear distance/ injure the fingers etc.
cover with hands
Hitting projected Persons may get Use safety shoes and avoid standing
rods and injured and fell unnecessarily on cantilever rods
standing on down Avoid wearing of loose clothes
cantilever rods.
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Falling of material May prove fatal Use helmets
from height Provide safety nets
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
(E) Ionizing Radiations may react Ensure Safety regulations as per BARC/AERB
RADIOGRAPHY radiation with the skin and can before commencement of job.
cause cancer, skin Cordon off the area and install Radiation warning
irritation, dermatitis, symbols
etc. Restrict the entry of unauthorized persons
Wear appropriate PPE and film badges issued by
BARC/AERB
Transpor-tation Same as above Never touch or handle radiography source with
and Storage of hands
Radiog-raphy Store radiography source inside a pit in an
source exclusive isolated storage room with lock and
key arrangement. The pit should be approved by
BARC/AERB.
Radiography source should never be carried
either in passenger bus or in a passenger
compartment of trains.
BARC/AERB has to be informed before source
movement.
Permission from Director General of Civil
Aviation is required for booking radio isotopes
with airlines.
Loss of Radio Same as above Try to locate with the help of Survey Meter.
isotope Inform BARC/AERB (*)
(F) ELECTRICAL Short circuiting Can cause Use rubberized hand gloves and other PPE
INSTALLATION Electrocution or Fire Don't lay wires under carpets, mats or door ways.
AND USAGE Allow only licensed electricians to perform on
electrical facilities
Use one socket for one appliance
Ensure usage of only fully insulated wires or
cables
Don't place bare wire ends in a socket
Ensure earthing of machineries and equipments
Do not use damaged cords and avoid temporary
connections
Use spark-proof/flame proof type field
distribution boxes.
TYPE OF EFFECT OF
ACTIVITY
HAZARD HAZARD
PREVENTIVE MEASURES
Do not allow open/bare connections
Provide all connections through ELCB
Protect electrical cables/equipment's from water
and naked flames
Check all connections before energizing
Overloading of Bursting of system Display voltage and current ratings prominently
Electrical can occur which with 'Danger' signs.
System leads to fire Ensure approved cable size, voltage grade and
type
Switch off the electrical utilities when not in use
Do not allow unauthorized connections.
Ensure proper grid wise distribution of Power
Improper laying Can cause Do not lay unarmoured cable directly on ground,
of overhead and electrocution and wall, roof of trees
underground prove fatal Maintain at least 3m distance from HT cables
transmission All temporary cables should be laid at least 750
lines/cables mm below ground on 100 mm fine sand
overlying by brick soling
Provide proper sleeves at crossings/ inter-
sections
Provide cable route markers indicating the type
and depth of cables at intervals not exceeding
30m and at the diversions/termination
(G) FIRE Small fires can Cause burn injuries In case a fire breaks out, press fire alarm system
PREVENTION become big ones and may prove fatal and shout "Fire, Fire"
AND and may spread Keep buckets full of sand & water/ fire
PROTECTION to the extinguishing equipment near hazardous
surrounding locations
areas Confine smoking to 'Smoking Zones' only.
Train people for using specific type of fire
fighting equipments under different classes of fire
Keep fire doors/shutters, passages and exit doors
unobstructed
Maintain good housekeeping and first-aid boxes
(for details refer Appendix-B)
Don't obstruct assess to Fire extinguishers.
Do not use elevators for evacuation during fire.
Maintain lightening arrestors for elevated
structures
Stop all electrical motors with internal
combustion
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Move the vehicles from dangerous locations
Remove the load hanging from the crane booms
Remain out of the danger areas.
Improper It may not Ensure usage of correct fire extinguisher meant
selection of Fire extinguish the fire for the specified fire (for details refer Appendix-
extinguisher C).
Do not attempt to extinguish Oil and electric
fires with water. Use foam cylinders/CO2/sand
or earth.
Improper storage Same as above Maintain safe distance of flammable substances
of highly from source of ignition
inflammable Restrict the distribution of flammable materials
substances to only min. necessary amount
Construct specifically designed fuel storage
facilities
Keep chemicals in cool and dry place away from
heat. Ensure adequate ventilation
Before welding operation, remove or shield the
flammable material properly
Store flammable materials in stable racks,
correctly labeled preferably with catchment
trays.
Wipe off the spills immediately
Short circuiting Same as above Don't lay wires under carpets, mats or door ways
of electrical Can cause Use one socket for one appliance.
system Electrocution Use only fully insulated wires or cables
Do not allow open/bare connections
Provide all connections through ELCB
Ensure earthing of machineries and equipments
(H) Crossing the Personal injury Obey speed limits and traffic rules strictly
VEHICULAR Speed Limits Always expect the unexpected and be a
MOVEMENT (Rash driving) defensive driver
Use seat belts/helmets
Blow horn at intersections and during
overtaking operations.
Maintain the vehicle in good condition
Do not overtake on curves, bridges and slopes
Adverse weather Same as Above Read the road ahead and ride to the left
condition Keep the wind screen and lights clean
Do not turn at speed.
Recognize the hazard, understand the defense
and act correctly in time.
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Consuming Same as above Alcohol and driving do not mix well. Either
alcohol before choose alcohol or driving.
and during the If you have a choice between hitting a fixed
driving object or an on-coming vehicle, hit the fixed
operation object
Quit the steering at once and become a passenger.
Otherwise take sufficient rest and then drive.
Do not force the driver to drive fast and round the
clock.
Do not day dream while driving
Falling objects/ May prove fatal Ensure effective braking system, adequate
Mechanical visibility for the drives, reverse warning alarm..
failure Proper maintenance of the vehicle as per
manufacturer instructions
(I) PROOF Bursting of May cause injury Prepare test procedure & obtain EIL/owner's
TESTING piping and prove fatal approval
(HYDROSTATI Collapse of Provide separate gauge for pressurizing pump
C /PNEUMATIC tanks and piping/equipment
TESTING) Tanks flying off Check the calibration status of all pressure
gauges, dead weight testers and temperature
recorders
Take dial readings at suitable defined intervals
and ensure most of them fall between 40-60% of
the gauge scale range
Provide safety relief valve (set at pressure
slightly higher than test pressure) while testing
with air/ nitrogen
Ensure necessary precautions, stepwise increase
in pressure, tightening of bolts/nuts, grouting, etc.
before and during testing
Keep the vents open before opening any valve
while draining out of water used for hydro-testing
of tanks.
Pneumatic testing involves the hazard of released
energy stored in compressed gas. Specific care
must therefore be taken to minimize the chance
of brittle failure during a pneumatic leak test.
Test temperature is important in this regard and
must be considered when the designer chooses
the material of construction.
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
A pressure relief device shall be provided, having
a set pressure not higher than the test pressure
plus the lesser of 345 KPa (50 psi) or 10% of the
test pressure.
The gas used as test fluid, if not air, shall be
nonflammable and nontoxic.
(J) Person can fall May sustain severe Provide guard rails/barricade at the work place
WORKING AT down injuries or prove Use PPE like full body harness, life line, helmets,
HEIGHTS fatal safety shoes, etc.
Obtain a permit before starting the work at height
above 3 meters
Fall arrest and safety nets, etc. must be installed
Provide adequate working space (min. 0.6 m)
Tie/weld working platform with fixed support
Use roof top walk ladder while working on a
slopping roofs
Avoid movement on beams
May hit the Keep the work place neat and clean
scrap/material Remove the scrap immediately
stacked at the
ground or in
between
Material can fall May hit the workers Same as above plus
down working at lower Do not throw or drop materials or equipment
levels and prove from height. I.e. do not bomb materials
fatal All tools to be carried in a tool-kit
Bag or on working uniform
Remove scrap from the planks
Ensure wearing of helmet by the workers
working at lower levels
(K) CONFINED Suffocation/ Unconsciousness, Use respiratory devices, if reqd.
SPACES drowning death Avoid over crowding inside a confined space
Provide Exhaust fans for ventilation
Do not wear loose clothes, neck ties, etc
Fulfill conditions of the permit
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Check for presence of hydrocarbons, O2 level
Obtain work permit before entering a confined
space
Ensure that the connected piping of the
equipment which is to be opened is pressure
free, fluid has been drained, vents are open and
piping is positively isolated by a blind flange
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Overloading of Same as above Safe lifting capacity of derricks and winches
lifting written on them shall be got verified
equipments The max. safe working load shall be marked on
all lifting equipments
Check the weight of columns and other heavy
items painted on them and accordingly decide
about the crane capacity, boom and angle of
erection
Allow only trained operators and riggers during
crane operation.
Overhead Can cause Do not allow boom or other parts of crane to
electrical wires electrocution and come within 3m reach of overhead HT cables
fire Hook and load being lifted shall preferably
remain in full visibility of crane operators.
(M) Person can fall Person May sustain Provide guard rails for working at height
SCAFFOLDI down severe injuries and Face ladder while climbing and use both hands.
NG, prove fatal Ladders shall extend about 1m above landing for
FORMWOR easy access and tying up purpose
K Do not place ladders against movable objects and
AND maintain base at 1/4 unit of the working length of
LADDERS the ladder.
Suspended scaffolds shall not be less than 500
mm wide and tied properly with ropes
No loose planks shall be allowed
Use PPE, like helmets, safety shoes,etc
Failure of Same as above Inspect visually all scaffolding materials for
scaffolding stability and anchoring with permanent
material structures.
Design scaffolding for max. load carrying
capacity.
Scaffolding planks shall not be less than 50X250
mm full thickness lumber or equivalent. These
shall be cleated or secured and must extend over
the end supports by at least 150mm and not more
than 300mm
Don't overload the scaffolds
Do not splice short ladders to make a longer one.
Vertical ladders shall not exceed 6m.
Material can Persons working at Remove excess material and scrap immediately
fall down lower level gets Carry the tools in a tool-kit bag only
injured Provide safety nets
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
(N) Personal Can cause injury or Do not take rest inside rooms built for welding
STRUCTUR negligence and casualty machines or electrical distribution system.
AL WORKS danger of fall Avoid walking on beams at height
Wear helmet with chin strap and full body
harness while working at height.
Use hand gloves and goggles during grinding
operations
Cover or mark the sharp and projected edges
Do not stand within the operating radius of
cranes
Lifting/ slipping Same as above Do not stand under the lifted load
of material Stack properly all the materials. Avoid slippage
during handling
Control longer pieces lifted up by cranes from
both ends
Remove loose materials from height
Ensure tightening of all nuts & bolts
(O) Erection/ Can cause injury Do not stand under the lifted load
PIPELINE lowering failure Do not allow any person to come within the
WORKS radii of the side boom handling pipes
Check the load carrying capacity of the lifting
tools & tackles
Use safe Load Indicators
Use appropriate PPEs
Other Same as above Wear gum boots in marshy areas
Allow only one person to perform signaling
operations while lowering of pipes
Provide night caps on pipes
Provide end covers on pipes for stoppage of pigs
while testing/ cleaning operations
(P) Pollution in Can cause personal Ensure the blasting is done in enclosed shed.
GRIT neighboring injury Keep safe distance while blasting operations.
BLASTING area, hit by grits Wear positive pressure blast hood or helmet
and high with view –window, ear-muff/plug, gloves,
pressure air overall or leather coat /apron, rubber shoes.
APPENDIX-F
1. The Law & Safety – Statutory Requirement / Applicable statutes / Duties of employer / employee
2. Policy & Administration – Why HSE? / Duties & Responsibilities of Safety Personnel at project
site / Effect of incentive on accident prevention
3. HSE & Supervision – Duties of Supervisor / HSE integrated supervision / Who should be held
responsible for site accidents?
4. Safety Budget / Cost of Accidents – Direct costs / Indirect costs
5. Hazard Identification / Type of hazards / HIRAC
6. Behavioural Safety & Motivation
7. Housekeeping – Storage / Stacking / Handling of materials / Hydra handling
8. Occupational Health in Construction sector
9. Personal Protective Equipments – Respiratory & Non- respiratory
10. Electricity & Safety – ELCB / Fuse / Powered tools / Project illumination
11. Handling of Compressed Gas – Transportation / Storage / FBAs / Fire prevention
12. Machine Safety – Machine guarding / Maintenance
13. Transportation – Hazards & risks in transp. of materials / ODC consignments
14. Cranes & Other Lifting machinery – Legal requirements vis-à-vis essential safety requirements.
15. Communication – HSE Induction / TBTs / Safety Committee / Safety meeting / Safety
propaganda / Publicity.
16. Excavation – Risks & Dangers / Safety measures
17. Working at Heights – Use of ladder / Work on roofs / Scaffolds / Double harness lanyards / Life-
line / Fall arrester / Safety Nets / Floor openings
18. Hazards in Welding & important safety precautions
19. Gas Cutting – Hazards & safety measures
20. Fire prevention & fire protection
APPENDIX - G
CONSTRUCTION POWER BOARD( typ)
APPENDIX-H
e) Other
2. PERSONNEL PROTECTIVE EQUIPMENT
a) Goggles; Shields
b) Face protection
Hearing protection
Foot protection
e) Hand protection
i) Other
3. EXCAVATIONS/OPENINGS
c) Excavations barricaded
e) Other
Non
SL. Satisafctory
ITEM satisfactory/ Remarks Action
NO. / Yes
No
4. WELDING & GAS CUTTING
g) Other
d) Adequate shoring
e) Adequate access
h) Other
6. LADDERS
b) Top of landing
c) Properly secured
e) Other
Non
SL. Satisafctory
ITEM satisfactory Remarks Action
NO. / Yes
/No
7. HOISTS, CRANES AND DERRICKS
h) Qualified operators
i) Other
a) Proper instruction
b) Safety devices
c) Proper cords
e) Other
c) Licensed drivers
d) Other
Non
SL. Satisafctory
ITEM satisfactory Remarks Action
NO. / Yes
/No
10. TEMPORARY FACILITIES
e) General neatness
g) Other
12. ELECTRICAL
Non
SL. Satisafctory
ITEM satisfactory Remarks Action
NO. / Yes
/No
14. HANDLING AND STORAGE OF
MATERIALS
a) Safely stored or stacked
b) Passageways clear / free from obstructions
c) Fire fighting facility in place
15. FLAMMABLE GASES AND LIQUIDS
a) Containers clearly identified / protected from
fire
b) Safe storage & transportation arrangement
made
c) Fire extinguishers positioned nearby
d) Facilities kept away from electric spark, hot
spatters & ignition source.
16. WORKING AT HEIGHT
a) Approved Erection plan and work permit in
place
b) Safe access, Safe work platform & Safety
nets provided
c) Life lines, Fall arrester, Full body harness
and with double lanyards used;
d) Health Check record available for workers
going up?
e) Protective handrails arranged around floor
openings
17. CONFINED SPACE
a) Work Permit obtained from requisite
authority
b) Test for toxic gas and sufficient availability
of oxygen conducted & status
c) Supervisor present at site & at least one
person outside the confined space for
monitoring deputed
d) Availability of safe means of entry, exit and
ventilation (register for entry & exit
maintained)
e) Fire extinguisher and first-aid facility
ensured
f) Lighting provision made by using 24V Lamp
g) Proper usage of PPEs ensured
18. RADIOGRAPHY
a) Proper storage and handling of source as per
BARC/ AERB guidelines (authorized
radiographer available)
b) Work permit obtained
Non
SL. Satisafctory
ITEM satisfactory Remarks Action
NO. / Yes
/No
c) Cordoning of the area done
d) Use of appropriate PPE's ensured
e) HSE training to workers/supervisors
imparted during the fortnight (indicate topic)
f) Minimum occupancy of workplace ensured
(To be submitted by Contractor after every Incident / Accident within 24 hours to EIL/ Owner)
Non-disabling injury (Non- Hospitalized but resumed duty before end of 48 hrs
LTA)
Disabling injury (other LTA) Hospitalized & failed to resume duty within next 48 hrs
Fatal (LTA): Death / Expiry
First Aid case (non LTA) Resume duty after first aid
Qualification
No formal education Non-Matriculate Matriculate
Graduate Post- grad Other/specify
Job Experience
NIL Less than 2 yrs 2-5 yrs
5-10 yrs 11-15 yrs 15 years and above
What exactly the victim was doing just before the incident / accident? ....................................
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
Nature of injury:
Bruise or Contusion Abrasion (superficial wound) Sprains or strains
Cut or Laceration Puncture or Open wound Burn
Inhalation of toxic or Absorption Amputation
Poisonous fumes or gases
Fracture Other/specify
Accident type:
Struck against Struck by Fall from Elevation
Fall on same level caught in caught under
caught in between Rubbed or abraded Contact with (Electricity)
_____________________________________________________________________________
Intimation to local authorities (Dist Collector / Local Police Station / ESI authority): Yes / No / NA.
If yes, to whom ………………………………………………………………………………………..
To : Owner
: RCM/Site-in-charge EIL (3 copies)
Non-disabling injury (Non- Hospitalized but resumed duty before end of 48 hrs
LTA)
Disabling injury (other LTA) Hospitalized & failed to resume duty within next 48 hrs
Fatal (LTA): Death / Expiry
First Aid case (non LTA) Resume duty after first aid
Qualification
No formal education Non-Matriculate Matriculate
Graduate Post- grad Other/specify
Job Experience
NIL Less than 2 yrs 2-5 yrs
5-10 yrs 11-15 yrs 15 years and above
What exactly the victim was doing just before the incident / accident? ....................................
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
Particular of tools & tackles being used and condition of the same after incident/accident:
…………………………………………………………………………….........................................
………………………………………………………………………………………………………
Description of Incident/Accident (How the incident was caused):
……………………………………………………………………………………….
……………………………………………………………………………………………………………
……………………………………………………………………………………………………………
Nature of injury:
Bruise or Contusion Abrasion (superficial wound) Sprains or strains
Cut or Laceration Puncture or Open wound Burn
Inhalation of toxic or Absorption Amputation
Poisonous fumes or gases
Fracture Other/specify
Name & Designation of person who provided First-Aid to the victim: ---------------------------------------
Name & Telephone number of Hospital where the victim was treated_________________________
Mode of transport used for transporting victim – Ambulance / Private car / Tempo / Truck / Others
In case of FATAL incident, indicate clearly the BOCW Registration No. of the victim
/Company……………………………………………………………………………………………
Comments of Medical Practitioner, who treated / attended the victim/injured (attached / described
here)_____________________________________________________________________
What actions are taken for investigation of the incident, please indicate clearly – (Video film /
Photography / Measurements taken etc……………………………………………………………..)
Basic cause
Root cause
Others(specify)
Was the victim performing relevant tasks for which he was engaged /employed? Yes / No
Was the Supervisor present on work-site during the incident? Yes / No
Have the causes of incident rightly identified? Yes / No
Cause of Accident was_____________________________________________________________
Remedial measures recommended by Safety Officer of Contractor for avoiding similar incident in
future
: ………………………………
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
……………………………………………………………………………………………………………
………………………………………………………………………………………………………...
Intimation to local authorities (Dist Collector / Local Police Station / ESI authority): Yes / No / NA.
If yes, to whom ………………………………………………………………………………………..
_____________________________________________________________________________
To : Owner
: RCM// Site-in-charge of EIL (3 copies)
Divisional Head (Constn) through RCM
Project Manager EIL, through RCM
__________________________________________________________________________________
Incident reported by :
Location :
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
To : Owner
: RCM/Site-in-charge EIL (3 copies)
Above items have been checked & compliance has been found in place. Hence work is permitted to
start / continue at the above-mentioned location. Work shall not start till identified lapses are rectified.
Permit Closure :
(A) Entry was closed stopped will continue on ...
Remarks, if any:
Project : Sr.No. :
Name of the work : Date :
Name of site contractor : Job No. :
Location of work :
Source strength :
The following items have been checked &compliance shall be ensured during currency of the
permit:
Permission is granted.
Permit is valid from ___________ AM/PM ____________ Date to ___________ AM/PM _________
Date
The following items have been checked &compliance shall be ensured during currency of the
permit:
Permission is granted.
Name :
Date :
Completion report :
CONTRACTOR’s NAME
Project : Sr.No. :
Name of the work : Date :
Name of contractor : Job No. :
Description of Job decided to perform : -
Inspected by Verification By
Contractor Engineer Contractor Safety Officer
Sl Satisafctory/ Non
No.
Subjects of Review Remarks Action
Yes satisfactory/No
21. Captions / Posters / Slogans on various safety
instructions are displayed legibly in local
language
22. Cable trenches are water-free or regular
arrangement for taking out accumulated water
exists.
23. Windows of rooms / offices are regularly
cleaned
24. Facilities for cycle sheds, drinking water,
washing, rest-rooms etc. are maintained in tidy
manner.
25. Toilet, Urinals, Canteen / kitchen / pantry etc.
are maintained & free from obnoxious smell.
26. Construction tools / tackles are stored
systematically - the items are tagged / tested /
certified by competent third party.
27. Sufficient numbers of Dust-bins / Waste-bins
found at site and are regularly emptied.
Inspected by Verification By
Contractor Engineer Contractor Safety Officer
SL
SUBJECTS OBSERVATION (YES /NO) ACTION TAKEN
NO
Switchboards installed properly are in order and
1
protected from rain & water-logging.
Adequate illumination provided for switchboard
2 operation during night hours & the lamps are protected
from direct human contact.
Voltage ratings, DANGER signs, Shock-Treatment-
3
Chart displayed in the installation / booth
Fire extinguisher (DCP or CO2) & Sand Bucket kept in
4
close vicinity of Switchboards
Valid License & Competent Electrician / Wireman
5 available & name/ license no. displayed at booth /
installation.
General housekeeping in & around booth / installation
6
found in order.
7 Cable-route-markers for U/G cables provided.
Monthly inspection report of Electrical hand tools
8
available in booth / installation.
9 Insulated Mat provided in front of Elec. Panels.
10 Rubber hand gloves available/ used by Electricians
Availability of CAUTION boards for shutdown & / or
11
repairing works.
All incoming & outgoing feeders have proper MCCB /
12
HRC fuses / Switches.
Switchboards “earthed” at two distinctly isolated
13
locations.
Switchboards have adequate operating space at the front
14
face & at the rear face too.
15 All connections provided through 30mA ELCB.
16 Testing records of all ELCBs available at site
17 Only industrial type plugs & sockets are used.
Temporary connections are 3-core double insulated &
18 free from cuts & joints and 3rd core is earthed at both
ends
Socket boards are properly mounted on stand &
19
protected from water ingress.
Electrical equipments operating above 250V have two
20
earthing / double earthing.
All incoming / outgoing cables are properly glanded &
21
terminated with “lugs”.
22 Switch-boards are of industrial variety / type.
Sketch for installation / connection (SLD) made &
23
pasted & other safety labels/display boards
24 Labeling of incoming / outgoing feeders made.
25 All hand lamps are protected from direct contact.
26 All electrical cable / joints are in safe condition
Inspected by Verification By
Contractor Engineer Contractor Safety Officer
(Sheet 2 of 2)
Sl. Actions
Description Yes No N. A
No taken
Whether provision is made to arrange duck ladder, crawling board for
29
working on fragile roof?
Whether scaffold has been inspected by qualified civil engineers prior to
30
their use?
Whether the scaffolding has been designed for the load to be borne by the
31
same?
Whether the erection and dismantling of the scaffolding is being done by
32
trained persons and under adequate supervision?
Whether safety net with proper working arrangement and life-line has
33
been provided?
Whether TAGS (Green for acceptable and Red for incomplete/unsafe
34
scaffolds) are used on scaffolds?
Whether sufficient illumination is provided in and around the scaffold
35
and access?
Whether emergency rescue / response arrangements are made in place
36
Inspected by Verification By
Contractor Engineer Contractor Safety Officer
This permit for work shall be available at specific work location all the time.
After completion of work, permit shall be returned to safety cell of main contractor, without fail.
This Permit shall be issued maximum upto (Monday to Sunday).
Additional Precautions, if any
…………………………………………………………………………………………………………………
ACCORD OF PERMISSION (to be ticked) - YES ( ) / NO ( )
Inspected by Verification By
Contractor Engineer Contractor Safety Officer]
Everyday Site working conditions & performance of workmen shall be assessed / checked by Contractor
Site Engr. and Safety Officer shall verify the same .
Project : Sr.No. :
Name of the work : Date :
Name of contractor : Job No. :
Nature of activities : Duration: From………To…………
Location of work : Name /Type of crane :
Equipment/Structure to be erected: Wt. of equipment/ structure to be erected :
SL. COMPLIANCE STATUS
Description of Item
NO. Remarks
Yes No Not applicable
1) Is the crane type suitable for lift or as per erection
procedure?
2) Is the crane have the correct number of counterweights
fitted?
3) Availability of Load Certification of crane from
authorized agency.
4) Is the load chart of crane available in carne cabin/or with
Crane operator?
5) Is the device to check the Wind speed in crane is working?
Is the safety features in crane are working?
6) Availability of Load certification of slings and other
accessories from authorized agency
7) Availability of Licensee/certificate for crane operator from
authorized agency.
8) Availability of approved JSA for the subject activities.
9) Availability of approved erection/rigging procedures.
10) Availability of temporary gratings/ platforms for critical
lifting(as applicable)
11) Tool Box conducted before erection?
12) Has the area been cordoned off?
13) Are the authorized persons during erection are identified?
14) Does each person identified for erection understand their
roles and responsibilities?
15) Is the ground on which crane will rest or outrigger support
are correct?
16) Is hard stand requirement (if any) complied?
17) Is the communication system (viz walkie talkies,etc are
working properly?
18) If more than one crane is lifting the load, is an
Intermediate rigger will supervise the lift?
19) If there is other obstruction within the operating radius of
the crane, have correct precautions been taken to prevent
collision?
20)
All the persons are wearing the requisite PPE?
Project : Sr.No. :
Name of the work : Date :
Name of contractor : Job No. :
ENERGY ISOLATION PERMIT
Clearance required from:…..Hrs ………Date To …. ..Hrs ….Date
Name of equipment/ energy source etc ………………………………………………………………….
Nature of job to be done: ……………………………………………………………………………….
Area………………………….Location:…………………………………………………………………..
Name & Signature of Site Engr Name & Signature of Safety Officer
Contractor (Initiator) Contractor (Issuing authority)
NOTES: -
1. Slopes or benches for excavation beyond 2.0M depth shall be designed & approved by Contractor’s site
head.
2. Excavated earth to be kept at least 1.5M away from edges
3. Safety helmets, Safety shoes or gum-boots, gloves, goggles, Face shield, Safety Harness shall be essential
PPEs.
4. Permit shall be made in duplicate and original shall be available at site of work.
5. Permit shall be issued for maximum one week only (Monday to Sunday)
6. After completion of works, permit shall be closed & preserved for record purpose
Issuing authority
Initiator (site Review by EIL /
Sl. Validity period Working Time (Safety Officer
Engr. of Main Owner (Remarks
No. From ____To ____ From _____To _____ of Main
Contractor) with date
Contractor)
1.
2.
3.
4.
5.
6.
7.
BIDDERS Page 1 of 7
QMS QMS
1 12.03.15 General Revision Standards Standards MPJ SC
Committee Committee
QMS QMS
0 04.06.09 Issued as Standard Specification Standards Standards SCT ND
Committee Committee
Standards Standards
Committee Bureau
Rev. Checked
Date Purpose Prepared by Convener Chairman
No by
Approved by
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Abbreviations:
CV Curriculum Vitae
ISO International Organization for Standardization
MR Material Requisition
PO Purchase Order
PR Purchase Requisition
QA Quality Assurance
QMS Quality Management System
CONTENTS
1.0 SCOPE
2.0 DEFINITIONS
2.1 Bidder
For the purpose of this specification, the word "BIDDER" means the person(s), firm,
company or organization who is under the process of being contracted by EIL /
Owner for delivery of some products (including service). The word is considered
synonymous to supplier, contractor or vendor.
2.3 Owner
Owner means the owner of the project for which services / products are being
purchased and includes their representatives, successors and assignees.
Unless otherwise agreed with EIL / Owner, the BIDDER proposed quality system
shall fully satisfy all relevant requirements of ISO 9001 "Quality Management
Systems — Requirements." Evidence of compliance shall be current certificate of
quality system registration to ISO 9001 or a recent compliance audit recommending
registration from a certification agency. The quality system shall provide the
planned and systematic control of all quality related activities for execution of
contract. Implementation of the system shall be in accordance with BIDDER'S
Quality Manual and PROJECT specific Quality Plan.
5.2 BIDDER shall identify all specified or implied statutory and regulatory requirements
and communicate the same to all concerned in his organization and his sub
contractor's organization for compliance.
5.3 BIDDER shall deploy competent and trained personnel for various activities for
fulfillment of PO / contract. BIDDER shall arrange adequate infrastructure and work
environment to ensure that the specification and quality of the deliverable are
maintained.
5.4 BIDDER shall do the quality planning for all activities involved in delivery of order.
The quality planning shall cover as minimum the following:
Resources
Product / deliverable characteristics to be controlled.
Process characteristics to ensure the identified product characteristics are
realized
Identification of any measurement requirements, acceptance criteria
Records to be generated
Need for any documented procedure
The quality planning shall result into the quality assurance plan, inspection and test
plans (ITPs) and job procedures for the project activities in the scope of bidder.
These documents shall be submitted to EIL/Owner for review/approval, before
commencement of work.
5.6 BIDDER shall plan and carry production and service provision under controlled
conditions. Controlled conditions shall include, as applicable
5.7 BIDDER shall validate any processes for production and service provision where
resulting output cannot be verified by subsequent monitoring and measurement.
This includes any process where deficiencies become apparent only after the
product is in use or service has been delivered.
5.8 BIDDER shall establish a system for identification and traceability of product /
deliverable throughout product realization. Product status with respect to inspection
and testing requirements shall be identified.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
5.9 BIDDER shall identify, verify, protect and safeguard EIL / Owner property (material /
document) provided for use or incorporation into the product. If any Owner / EIL
property is lost, damaged or otherwise found to be unsuitable for use, this shall be
reported to the EIL / Owner.
5.10 BIDDER shall ensure the conformity of product / deliverable during internal
processing and delivery to the intended destination. Requirements mentioned in the
tender shall be adhered to.
5.11 BIDDER shall establish system to ensure that inspection and testing activities are
carried out in line with requirements. Where necessary, measuring equipments
shall be calibrated at specified frequency, against national or international
measurement standards; where no such standard exists, the basis used for
calibration shall be recorded. The measuring equipments shall be protected from
damage during handling, maintenance and storage.
5.12 BIDDER shall ensure effective monitoring, using suitable methods, of the processes
involved in production and other related processes for delivery of the scope of
contract.
5.13 BIDDER shall monitor and measure the characteristics of the product/deliverable to
verify that product requirement has been met. The inspection (stage as well as
final) by BIDDER and EIL / Owner personnel shall be carried out strictly as per the
ITPs forming part of the contract. Product release or service delivery shall not
proceed until the planned arrangements have been satisfactorily completed, unless
otherwise approved by relevant authority and where applicable by Owner / EIL.
5.14 BIDDER shall establish and maintain a documented procedure to ensure that the
product which does not conform to requirements is identified and controlled to
prevent its unintended use or delivery
5.16 All deficiencies noticed and reported by EIL / Owner shall be analyzed by the
BIDDER and appropriate corrective and preventive actions shall be implemented.
BIDDER shall intimate EIL / Owner of all such corrective and preventive action
implemented by him.
5.17 BIDDER should follow the standards, specifications and approved drawings.
Concessions/Deviations shall be allowed only in case of unavoidable circumstances.
In such situations Concession/deviation request must be made by the BIDDER
through online system of EIL eDMS. URL of EIL eDMS is
http://edocx.eil . co . in/vportal.
5.19 All project records shall be carefully kept, maintained and protected for any damage
or loss until the project completion, then handed over to EIL / Owner as per contract
requirement (Refer Specification Nos. 6-78-0002 - Specification for Documentation
Requirements from Contractors and 6-78-0003 - Specification for Documentation
Requirements from Suppliers), or disposed as per relevant project procedure.
6.0 AUDITS
BIDDER shall plan and carry out the QMS audit for the job. Quality audit programme
shall cover design, procurement, construction management and commissioning as
applicable including activities carried out by sub-vendors and sub-contractors. This
shall be additional to the certification body surveillance audits carried out under
BIDDER'S own ISO 9001 certification scheme.
The audit programmes and audit reports shall be available with bidder for scrutiny
by EIL / Owner. EIL or Owner's representative reserves the right to attend, as a
witness, any audit conducted during the execution of the WORKS.
In addition to above EIL, Owner and third party appointed by EIL/Owner may also
perform Quality and Technical compliance audits. BIDDER shall provide assistance
and access to their systems and sub-contractor / vendor systems as required for this
purpose. Any deficiencies noted shall be immediately rectified by BIDDER.
BIDDER shall submit following QMS documents immediately after award of work
(Within one week) for record / review by EIL / Owner.
Organization chart (for complete organization structure and for the project)
Project Quality Plan/Quality Assurance Plan
Job specific Inspection Test Plans, if not attached with PR
Job Procedures
Inspection/Test Formats
Quality Manual
Certificate of approval for compliance to ISO: 9001 standard
Procedure for Control of Non-conforming Product
Procedure for Control of Documents
Sample audit report of the QMS internal and external audits conducted during
last one year
Customer satisfaction reports from at least 2 customers, during the last one
year
Project QMS audit report
Technical audit reports for the project
Corrective action report on the audits
C)(415----2
QMS QMS
1 12.03.15 General Revision Standards Standards SC
Committee Committee
QMS QMS
0 04.06.09 Issued as Standard Specification Standards Standards SCT ND
Committee Committee
Standards Standards
Comm ifte Bureau
Rev. Prepared Checked
Date Purpose Convener Chairman
No by by
Approved by
Abbreviations:
CONTENTS
Clause Title Page
No.
1.0 SCOPE 4
2.0 DEFINITIONS 4
3.0 REFERENCE DOCUMENTS 4
4.0 DOCUMENTATION REQUIREMENTS 4
Attachments
Format for completeness of Final Documentation Format No. 3-78-0004
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
1.0 SCOPE
This specification establishes the Documentation Requirements from Suppliers.
All documents/data against the PO / PR / MR shall be developed and submitted to
EIL/Owner by the suppliers for review / records, in line with this specification.
2.0 DEFINITIONS
2.1 Supplier
For the purpose of this specification, the word "SUPPLIER" means the person(s),
firm, company or organization who is under the process of being contracted by EIL /
Owner for delivery of some products (including service). The word is considered
synonymous to bidder, contractor or vendor.
2.2 Owner
Owner means the owner of the project for which services / products are being
purchased and includes their representatives, successors and assignees.
4.1.1 The Supplier shall submit the documents and data against the PO/PR/MR as per the
list given in respective PO/PR/MR.
4.1.2 Review of the supplier drawings by EIL would be only to review the compatibility with
basic designs and concepts and in no way absolve the supplier of his
responsibility/contractual obligation to comply with PR requirements, applicable
codes, specifications and statutory rules/regulations. Any error/deficiency noticed
during any stage of manufacturing/execution/installation shall be promptly corrected
by the supplier without any time and cost implications, irrespective of comments on
the same were received from EIL during the drawing review stage or not.
4.2.1 All Documents shall be in ENGLISH language and in M.K.S System of units.
4.2.2 Before forwarding the drawings and documents, contractor shall ensure that the
following information are properly mentioned in each drawing:
Purchase Requisition Number
Name of Equipment / Package
Equipment / Package Tag No.
Name of Project
Client
Drawing / Document Title
Drawing / Document No.
Drawing / Document Revision No. and Date
Supplier shall create and submit Document Control Index (DCI) for review based on
PO/PR/MR along with schedule date of submission of each drawing/document on EIL
eDMS. The DCI shall be specific with regard to drawing/document no. and the exact
title. Proper sequencing of the drawings/documents should be ensured in schedule
date of submission.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
http://edocx.eil.co.in/vportal
After placement of order supplier shall assign a Project Manager for that order. The
details are to be filled online through the portal. The details include e-mail address,
mailing address, telephone nos., fax nos. and name of Project Manager. All the system
generated emails pertaining to that order shall be sent to the assigned Project
Manager.
Supplier shall submit monthly progress report and updated procurement, engineering
and manufacturing status (schedule vs. actual) every month, beginning within 2 weeks
from FOA/LOA. In case of exigencies, EIL/Owner can ask for report submission as
required on weekly/fortnightly/adhoc basis depending upon supply status and supplier
shall furnish such reports promptly without any price implication. Format for progress
report shall be submitted by the Supplier during kick off meeting or within one week of
receiving FOA/LOA, whichever is earlier.
Note: Non fulfilling above requirement shall result into appropriate penalty or with-
holding of payment as per conditions of PO/PR/MR.
Weight : 32 MT
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL—AIL rights reserved
In addition to hard copies, Supplier shall submit electronic file (CD-ROM) covering soft
copies of all the final drawings and documents, all text documents prepared on
computer, scanned images of all important documents (not available as soft files), all
relevant catalogues, manuals available as soft files (editable copies of drawings/text
documents, while for catalogues/manuals/proprietary information and data, PDF files
can be furnished).
All the above documents shall also be uploaded on the EIL eDMS portal.
4.6.5 Completeness of Final Documentation
Supplier shall get the completeness of final documentation verified by EIUTPIA and
attach the Format for Completeness of Final Documentation (Format No. 3-78-0004)
duly signed by EIL Inspector or TPIA as applicable to the document folder.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Name of Supplier/Contractor
Customer
Project
EIL's Job No.
Purchase Order No./
Contract No.
Tag. No.
Supplier's/ Contractor's
Works Order No.
Certified that the Engineering Documents/ Manufacturing & Test Certificates submitted by the
supplier are complete in accordance with the Vendor Data Requirements of Purchase
Requisition.
Signature Signature
Date Date
Name Name
Designation Designation
Department Department
Supplier/Contractor EIL/TPIA
arTilittl/APPROVED
gTffTeR/ Sig
eilegiltk
tvi . ...........
.....
4/ Name: ......... .. . ......
..................
f4-41--/ Date: ..... ••••••• .... ......
Format No. 3-78-0004, Rev. 1/ 12.03.2015 Copyright EIL — All rights reserved
Rev.
Date Purpose Prepared by Reviewed by Approved by
No
Abbreviations:
AS : Alloy Steel
CS : Carbon Steel
DFT : Dry Film Thickness
DM : De-mineralized
GI : Galvanized Iron
ID : Internal Diameter
IRN : Inspection Release Note
LTCS : Low Temperature Carbon Steel
MS : Mild Steel
NB : Nominal Bore
OD : Outside Diameter
RCC : Reinforced Cement Concrete
SS : Stainless Steel
WFT : Wet Film Thickness
CONTENTS
1.0 General…………………………………………………………………………………. 4
2.0 Scope…………………………………………………………………………………… 4
3.0 Reference Codes & Standards……………………………………………………….... 6
4.0 Equipment……………………………………………………………………………… 7
5.0 Surface Preparation, Shop Primer, Coating Application & Repair and 7
Documentation..
6.0 Paint Materials………………………………………………………………………….. 15
7.0 Coating Systems selection criteria……………………………………………………... 19
8.0 Coating System for Gratings, Rolling & Stationery Ladders, Spiral Stairways and
Hand Rails in All Location……………………………………………………………... 21
9.0 Coating System for Offsite Area (Inland Plants)………………………………………. 22
10.0 Coating System For Unit Areas as well as DM, CPP, Cooling Tower of Inland Plants
and for All Areas (Unit, Offsite, DM, CPP, etc.) of Coastal Plants……………………. 23
11.0 Coating System for Effluent Treatment Plant (ETP)…………………………………... 25
12.0 External Coating Systems for Uninsulated Carbon Steel and Low Alloy Steel Storage
Tanks (For All Plant Locations, Coastal or Inland) - All Process Units & Off-Sites …. 26
13.0 Internal Coating Systems for Carbon Steel and Low Alloy Storage Tanks - All
Process Units & Off-Sites……………………………………………………………… 28
14.0 Coating Systems for External Side of Underground Carbon Steel Plant Piping and
Underground Vessels…………………………………………………………………... 30
15.0 Coating Under Insulation (Coastal Or Inland Plants). All Units Areas & Off-Sites…… 31
16.0 Coating System for Carbon Steel Components of Coolers / Condensers (Internal
Protection) for Fresh Water Service……………………………………………………. 32
17.0 Coating System (Internal Protection) for Galvanized or Non Ferrous or Stainless
Steel/ Duplex Stainless Steel Components of Coolers/ Condensers for Fresh Water
Service….......................................................................................................................... 32
18.0 Storage………………………………………………………………………………….. 32
19.0 Paint colour code for piping and equipment ……...…………………………………… 32
20.0 Recommended paint color code ………………...……………………………………. 35
21.0 Painting for civil defense requirements………………………………………………… 40
22.0 Selection of paint materials …………………………………...……………………….. 41
23.0 Quality Control, Inspection and Testing ………………………………………………. 42
24.0 Guarantee……………………………………………………………………………….. 46
1.0 GENERAL
1.1 This technical specification shall be applicable for the work covered by the contract, and
without prejudice to the provisions of various international codes of practice, standard
specifications etc. It is understood that contractor shall carry out the work in all respects with
the best quality of materials and workmanship and in accordance with the best engineering
practice and instructions of Engineer-In-Charge.
1.2 Wherever it is stated in the specification that a specific material is to be supplied or a specific
work is to be done, it shall be deemed that the same shall be supplied or carried out by the
contractor.
Any deviation from this standard without written deviation permit from appropriate
authority will result in rejection of job.
1.3 This specification covers the requirement for protective coating for new construction.
2.0 SCOPE
2.1 Scope of work covered in the specification shall include, without being limited to the
following.
2.1.1 This specification defines the requirements for surface preparation, selection and application
of primers and paints on external surfaces of equipment, vessels, machinery, piping, ducts,
steel structures, external & internal protection of storage tanks for all services and chimneys
if any. The items listed in the heading of tables of paint systems is indicative only, however,
the contractor is fully responsible for carrying out all the necessary painting, coating and
lining on external and internal surfaces as per the tender requirement.
2.2.1 The following surfaces and materials shall require shop, pre-erection and field painting
All uninsulated Carbon Steel & Alloy Steel equipments like vessels, Columns, storage
Tanks, Exchangers if any, parts of boilers etc.
All uninsulated carbon steel and low alloy plant and related piping, fittings and valves
(including painting of identification marks), furnace ducts and stacks.
All insulated parts of vessels, boilers, chimneys, stacks, piping and steam piping and if
any other insulated items present.
All structural steel work, pipe, structural steel supports, walkways, handrails, ladders,
platforms etc.
Flare lines, external surfaces of MS chimney with or without refractory lining and
internal surfaces of MS chimney without refractory lining. (If present)
Supply of all primers, paints and all other materials required for painting (other than
Owner supplied materials)
Painting under insulation for carbon steel, alloy steels and stainless steel as specified.
Repair work of damaged pre-erection/ fabrication and shop primer and weld joints in the
field/site before and after erection as required.
All CS Piping, equipments, storage tanks and internal surfaces of RCC tanks in ETP
plant.
Quality control, testing and inspection during all stages of work (surface preparation,
application of coating and testing of furnished coating).
2.2.2 The following surfaces and materials shall not require painting in general. However, if there
is any specific requirement by the OWNER/LICENSOR, the same shall be painted as per the
relevant and applicable specifications.
2.3 Documents
2.3.1 The contractor shall perform the work in accordance with the following documents issued to
him for execution of work.
2.4 Unless otherwise instructed, final paint coating (i.e., application of field primer,
wherever required, intermediate and top coats) on pre-erection/ shop primed
equipments shall be applied at site, only after all welding, testing on systems are
completed as well as after completion of steam purging wherever required.
2.5 Changes and deviations required for any specific job due to clients requirement or otherwise
shall be referred to EIL for deviation permit.
3.1 Without prejudice to the provision of Clause 1.1 above and the detailed specifications of the
contract, latest editions of the following codes and standards are applicable for the work
covered by this contract.
The latest editions of any of the following standards shall be followed for surface
preparation:
3.2.1 ISO 8501-1 / SIS-05 59 00: ISO standard for Preparation of steel substrates before
application of paints and related products. This standard contains photographs of the various
standards on four different degrees of rusted steel and as such is preferable for inspection
purpose by the Engineer-In-Charge.
3.2.2 Steel Structures Painting Council, U.S.A. (Surface Preparation Specifications (SSPC-SP).
3.2.4 Various International Standards equivalent to Swedish Standard for surface preparations are
given in Table-I.
3.3 The contractor shall arrange, at his own cost, to keep a set of latest edition of above standards
and codes at site.
3.4 The paint manufacturer's instructions shall be followed as far as practicable at all times for
best results. Particular attention shall be paid to the following:
b. Surface preparation prior to painting shall be followed as per Table 8.0 to 16.0 of
this standard shall be followed.
4.0 EQUIPMENT
4.1 All tools, brushes, rollers, spray guns, blast material, hand power tools for cleaning and all
equipments, scaffolding materials, shot & grit blasting equipments & air compressors etc.
required to be used shall be suitable for the work and all in good order and shall be arranged
by the contractor at site and in sufficient quantity. The manufacturer’s test certificates / data
sheets for all the above items shall be reviewed by Engineer-in-charge at site before start of
work.
4.2 Mechanical mixer shall be used for paint mixing operations in case of two pack systems
except that the Engineer-In-Charge may allow the hand mixing of small quantities at his
discretion in case of specific requirement for touch up work only.
5.1 General
5.1.1 In order to achieve the maximum durability, one or more of following methods of surface
preparation shall be followed, depending on condition of surface to be painted and as
instructed by Engineer-In-Charge. Adhesion of the paint film to surface depends largely on
the degree of cleanliness of the metal surface. Proper surface preparation contributes more to
the success of the paint protective system.
5.1.2 Mill scale, rust, rust scale and foreign matter shall be removed fully to ensure that a clean and
dry surface is obtained. Unless otherwise specified, surface preparation shall be done as per
provisions of relevant tables given elsewhere in this specification. The minimum acceptable
standard, in case of thermally sprayed metal coatings, in case of mechanical or power tool
cleaning it shall be St. 3 or equivalent. In case of blast cleaning it shall be Sa 2-1/2 as per
Swedish Standard SIS-055900 (latest edition) or SSPC-SP or ISO 8501-01.Blast cleaning
shall be Sa 3 as per Swedish Standard in case thermally sprayed metal coatings.
Before surface preparation by blast cleaning, the surface shall be degreased by aromatic
solvent to remove all grease, oil etc.
5.1.3 Irrespective of whether external or internal surface to be coated, blast cleaning shall not be
performed where dust can contaminate surfaces undergoing such cleaning or during humid
weather conditions having humidity exceed 85%. In case of internal coating of storage tanks,
dehumidifier shall be used, to control humidity level below 60%. Dehumidifier should
depress the dew point of air in the enclosed space, sufficient enough so as to maintain it 3⁰C
below the metal substrate temperature during centre period of blasting and coating
application. During the interval time between application of primer coat and subsequent
intermediate and top coats or between blast cleaning completion and start of application of
Dehumidifier should be able to maintain grain drop (moisture removal) at the rate of 25
grains per pound of air per hour. Dehumidifier should have capacity of at least 2 air changes
per hour of the enclosed space. All necessary psychometric data should be collected by
contractor for the given site conditions before starting operation of dehumidifier to ensure
that desired values of dew point, moisture content in enclosed scope is achieved.
Dehumidification to be maintained round the clock for surface preparation and painting till
the total coating application is over.
Dehumidifier shall not be stopped under any condition till the entire blasted surface is primed
to the satisfaction of the technical representative of the paint manufacturer interested with
quality assurance for the work. In case the dehumidifier breaks down in middle of the job, the
same shall be replaced at the risk and the cost of the contractor and the entire unfinished
work shall be repeated.
5.1.4 The Engineer in-charge shall have the right to disallow usage of dehumidifier if the
performance is not meeting the specified requirements. Under such circumstances the
contractor shall remove the equipment and replace the same with another equipment to
provide satisfactory results without any additional cost to the owner.
5.1.5 Irrespective of the method of surface preparation, the first coat of primer must be applied by
airless spray/ air assisted conventional spray if recommended by the paint manufacturer on
dry surface. This should be done immediately and in any case within 4 hours of cleaning of
surface. However, at times of unfavorable weather conditions, the Engineer-In-Charge shall
have the liberty to control the time period, at his sole discretion and/or to insist on re-
cleaning, as may be required, before primer application is taken up. In general, during
unfavorable weather conditions, blasting and painting shall be avoided as far as practicable.
5.1.6 The external surface of R.C.C. chimney to be painted shall be dry and clean. Any loose
particle of sand, cement, aggregate etc. shall be removed by scrubbing with soft wire brush.
Acid etching with 10-15% HCL solution for about 15 minutes shall be carried and surface
must be thoroughly washed with water to remove acid & loose particles and then dried
completely before application of paint.
The surfaces shall be blast cleaned using one of the abrasives like angular chilled cast iron or
steel grit, copper slag or Nickel slag, A12O3 particles at pressure of 7kg/cm2 at an appropriate
distance and angle depending of nozzle size maintaining constant velocity and pressure.
Chilled cast iron or steel shall be in the form of shot or grit of size in the range of G16 – G42
conforming to SSPC AB1 and S250 grade size of steel shots (maximum) to obtain a desired
surface profile of 35-50 microns trough to peak. For all other abrasives, size shall be in the
range of G16 – G24. The combination of steel grits and shots shall be normally in the ratio of
3:1. The quality of abrasives shall be free from contaminants and impurities and shall meet
the requirements of SSPC AB1. Compressed air shall be free from moisture and oil. The
blasting nozzles should be venturi style with tungsten carbide or boron carbide as the
materials for liners. Nozzles orifice may vary from 3/16” to ¾”. On completion of blasting
operation, the blasted surface shall be clean and free from any scale or rust and must show a
grey white metallic luster. Primer/first coat of paint shall be applied within 4 hours of surface
preparation. Blast cleaning shall not be done outdoors in bad weather without adequate
protection or when there is dew on the metal, which is to be cleaned. Surface profile shall be
uniform to provide good key to the paint adhesion (i.e. 35 to 50 microns). If possible
vacuum collector shall be installed for collecting the abrasives and recycling.
Power tool cleaning shall be done by mechanical striking tools, chipping hammers, grinding
wheels or rotating steel wire- brushes. Excessive burnish of surface shall be avoided as it can
reduce paint adhesion. On completion of cleaning, the detached rust mill scale etc. shall be
removed by clean rags and /or washed by water or steam and thoroughly dried with
compressed air jet before application of paint.
For equipments on which application of total protective coating (Primer + Intermediate + top
coat) is carried out at shop, compatibility of finish coat with primer should be checked with
paint manufacturer. If the shop coat is in satisfactory condition showing no major defect upon
arrival at site, the shop coat shall not be removed.
5.4 Shop coated equipments (coated with Primer & finishing coat) should not be repainted unless
paint is damaged. Repair shall be carried out as per Table 7.2 of paint systems depending
upon compatibility of paint.
5.5 Shop primed equipment and surfaces will only be 'spot cleaned' in damaged areas by means
of power tool brush cleaning or hand tool cleaning and then spot primed before applying one
coat of field primer unless otherwise specified. If shop primer is not compatible with field
primer then shop coated primer should be completely removed before application of selected
paint system for particular environment.
5.6 For Package units/equipment, shop primer should be as per the paint system given in this
specification. However, manufacturer’s standard can be followed after review.
As mentioned in section 2.4, all coating application at field (field primer, intermediate and
top coat) on equipments, structures, piping, etc, shall be carried out only after its erection and
all welding, testing, steam purging (wherever carried out) have been completed.
All paint coatings shall be applied by airless spray excepting at the following special
cases where application can be carried out by brush subject to suitability of the
application of the paint product by brush.
- Spot repair
- Stripe coating on edges
- Small bore parts not suitable for spray application.
Irregular surfaces such as sharp edges, welds, small brackets, and interstices may stripe
coated to ensure specified DFT is achieved. Paint manufacturer recommendation
should be followed before deciding for brush application.
5.7.1 Surface shall not be coated in rain, wind or in environment where injurious airborne elements
exists, when the steel surface temperature is less than 5oF above dew point when the relative
humidity is greater than 85% or when the temperature is below 40oF and when the
ambient/substrate temp is below the paint manufacturer’s recommended temperature of
application and curing. De-humidifier equipment shall be used to control RH and Dew point.
The paint application shall not be done when the wind speed exceeds 20km per hour.
5.7.2 Blast cleaned surface shall be coated with one complete application of primer as soon as
practicable but in no case later than 4 hrs the same day.
5.7.3 To the maximum extent practicable, each coat of material shall be applied as a continuous
film uniform thickness free of probes. Any spots or areas missed in application shall be
recoated and permitted to dry before the next coat is applied. Applied paint should have the
desired wet film thickness.
5.7.4 Each coat shall be in proper state of cure or dryness before the application of succeeding
coat. Material shall be considered dry for recoating when an additional coat can be applied
without the development of any detrimental film irregularities, such as lifting or loss of
adhesion of the under coat. Manufacturer instruction shall be followed for inter coat interval.
5.7.5 When the successive coat of the same colour have been specified, alternate coat shall be
tinted, when practical, sufficiently to produce enough contrast to indicate complete coverage
of the surface. The tinting material shall be compatible with the material and not detrimental
to its service life and shall be recommended by the original paint manufacturer.
5.7.6 Airless spray application shall be in accordance with the following procedure: as per steel
structure paint Manual Vol.1 & Vol.2 by SSPC, USA, Air less spray relies on hydraulic
pressure rather than air atomization to produce the desired spray. An air compressor or
electric motor is sued to operate a pump to produce pressures of 1000 to 6000 psi. paint is
delivered to the spray gun at this pressure through a single hose within the gun, a single paint
stream is divided into separate streams, which are forced through a small orifice resulting in
automization of paint without the use of air. This results in more rapid coverage with less
over spray. Airless spray usually is faster, cleaner, more economical and easier to use than
conventional air spray.
Airless spray equipment is mounted on wheels, and paint is aspirated in a hose that sucks
paint from any container, including drums. The unit shall have in built agitator that keep the
paint uniformly mixed during the spraying. The unit shall consist of in built strainer. Usually
very small quantity of thinning is required before spray. In case of high build epoxy coating
(two pack). 30:1 pump ratio and 0.020-0.023” tip size will provide a good spray pattern.
Ideally fluid hoses should not be less than 3/8” ID and not longer than 50 ft to obtain
optimum results.
a. Brushes shall be of a style and quality that will enable proper application of paint.
b. Round or oval brushes are most suitable for rivets, bolts, irregular surface, and
rough or pitted steel. Wide flat brushes are suitable for large flat areas, but they
shall not have width over five inches.
5.7.8 For each coat the painter should know the WFT corresponding to the specified DFT and
standardize the paint application technique to achieve the desired WFT. This has to be
ensured in the qualification trial.
5.8.1 No coat shall be applied until the preceding coat has dried. The material shall be considered
dry for re-coating when another coat can be applied without the development of any film
irregularities such as lifting or loss of adhesion of undercoats. Drying time of the applied coat
should not exceed maximum specified for it as a first coat; if it exceeds the paint material has
possibly deteriorated or maxing is faulty.
5.8.2 No paint shall be force dried under conditions which will cause chalking, wrinkling,
blistering formation of pores, or detrimentally affect the conditions of the paint.
5.8.3 No drier shall be added to paint on the job unless specifically called for in the manufacturer’s
specification for the paint.
5.8.4 Paint shall be protected from rain, condensation, contamination, snow and freezing until dry
to the fullest extent practicable.
5.9.1 Where pre erection shop primer has been damaged at isolated localized spots during handling
and transportation, or after erection / welding, the repair of damaged coating of pre-erection /
pre-fabrication or shop primer shall be done as given below and as per the Table 7.2 of this
specification.
5.9.2 Repair of damaged inorganic zinc silicate pre-erection / pre-fabrication or shop primer
(F9) after erection / welding in the design temperature of -90oC to 400oC and damaged
silicone aluminium (F-12) pre-erection / pre-fabrication or shop primer after erection /
welding for design temperature range of 401 – 550 °C.
Surface Preparation: Quickly remove the primer from damaged area by mechanical scraping
and emery paper conforming to SSPC-SP-3 to expose the white metal. Blast clean the
surface, if possible. Feather the primed surface over the intact adjacent surface surrounding
the damaged area by emery paper.
Primer coating: One coat of F-9 shall be applied wherever damage was observed on pre-
erection / pre fabrication or shop primer of inorganic zinc silicate coating (F-9). Similarly
one coat of F-12 shall be applied wherever damage observed on pre-erection / pre-
fabrication shop primer of silicone aluminium (F-12).
5.9.3 Wherever if damaged areas are found extensive and spread over large areas, then entire pre-
erection / pre-fabrication or shop primer shall be removed by blasting to achieve SSPC-SP-
10 then entire blasted surface shall be primed again with F-9 or F-12 as applicable for the
intended design temp. (See note under table 7.2).
5.10.1 Shop priming/pre-erection priming with F9 or F12 shall be done only on blasted surface
(SSPC-SP-10)
5.10.2 Shop priming / pre-erection priming with F9 or F12 shall be done only with airless spray.
The paint system to be applied for a specific job shall be arrived at sequentially as given
below:
- Identify the environment from area classification details and chose the appropriate table.
- Identify the specific field paint system and surface preparation requirement from the above
identified table and temperature range.
- Identify the shop priming requirement from Table 7.1 based on compatibility of the above
paint system.
- Identify the need of repair of shop primer and execute as per Table 7.2.
5.11.1 A written quality plan with procedure for qualification trials and for the actual work
including test and inspection plan & procedure for approval before start of work.
5.11.2 Daily progress report with details of weather conditions, particular of applications, no of
coats and type of materials applied, anomalies, progress of work versus program.
5.11.3 Results of measurement of temperatures relative humidity, surface profile, film thickness,
holiday detection, adhesion tests with signature of appropriate authority.
5.11.4 Particulars of surface preparation and paint application during trials and during the work.
The coating applicator must maintain a job record consisting of all the information as per
5.11.2 -5.11.7 above as well as the approved procedure of work (5.11.1 above). The job
record consisting of information as required in accordance to 5.11.2 – 5.11.7 shall be entered
on daily basis and should be daily signed by Engineer-in-charge.
VARIOUS INTERNATIONAL
Sl. STANDARDS (EQUIVALENT)
DESCRIPTION REMARKS
No. ISO 8501-1/ SSPC-SP, NACE,
SIS-05 59 00 USA USA
Manual or hand tool
cleaning
VARIOUS INTERNATIONAL
Sl. STANDARDS (EQUIVALENT)
DESCRIPTION REMARKS
No. ISO 8501-1/ SSPC-SP, NACE,
SIS-05 59 00 USA USA
Commercial Blast For steel required to
be painted with
Blast cleaning until at least conventional paints
two-third of each element of for exposure to
3.3 SA 2 SSPC-SP-6 NO.3
surface area is free of all mildly corrosive
visible residues with desired atmosphere for longer
surface profile. life of the paint
systems.
Brush-off Blast
Paint manufacturers shall furnish the characteristics of all paints materials on original printed
literature, along with the test certificate for all specified characteristics given in this
specification. All the paint materials shall be of first quality and conform to the following
general characteristics as per the tables 6.1, 6.2, 6.3 and 6.4.
PAINT MATERIALS
PAINT MATERIALS
Sl.
DESCRIPTION F-2 F-3 F-6A/B F-6C F-7
No
Acrylic Chlorinated High build coal
Epoxy-High Build Solvent less
1 Technical name Polyurethane rubber based tar epoxy
coating epoxy coating
finish paint finish paint coating.
Single pack F-6A Two-pack
Two pack, Two pack
plasticised Aromatic amine
cured with polyamide
Two-pack chlorinated cured epoxy resin
Amine cured epoxy
aliphatic rubber based medium suitably
Type and Adduct; resin blended
2 isocynate medium with pigmented.
composition catalyzed with coaltar
cured acrylic chemical and F-6B: polyamide
epoxy resin medium,
finish paint. weather cured epoxy resin
suitably suitably
resistant medium suitably
pigmented pigmented
pigments. pigmented
3 Volume Solids % 40 ± 3 38±2 60±3 99±1 65±3
DFT (Dry Film
4 thickness) per coat in 30-40µ 30-40 100-125µ 200-500 100-125µ
microns
Theoritical covering
5 capacity in 11-15 11-15 5-6 2-3 5.2-6.5
M2/coat/litre
Weight per liter in
6 1.15±0.03 1.15±0.03 1.42±0.03 1.40±0.03 1.40±0.03
kgs/litre
7 Touch dry at 30oC 30 minutes 30 minutes. 3 hrs. 3 hrs. 4 hrs.
Hard dry at 30oC
16 hrs
(max) 48 hrs
8 hrs
8 Full cure at 30oC (for 8 hrs 16 hrs
5 days
immersion/ high 5 days
temperature service)
Over-coating interval Min.12 hrs. Min.: Min.: Overnight Min.: 8 hrs. Min.: 24 hrs
9
at 30 oC Overnight Max.: 5 days Max.: 48 hrs. Max.: 5 days.
Pot life (approx.) at
6-8 hrs. Not
10 30oC for two 4-6 hrs 30 minutes 4-6 hrs.
applicable
component paints
Temperature 120oC(Dry
o o
Resistance 80 C 60 C service), 125oC
80oC
11 (minimum) Dry service Immersion 50oC Immersion
Dry service
min service (Immersion service
service)
PAINT MATERIALS
Sl.
DESCRIPTION F-8 F-9 F-11 F-12
No
Self priming type Heat resistant
Heat resistant
surface tolerant synthetic medium
silicone
high build epoxy Inorganic zinc based two pack
1 Technical name Aluminium paint
coating (complete silicate coating Aluminium paint
suitable up to
rust control suitable up to
500oC dry temp.
coating). 250oC dry temp.
A two pack air
Two pack epoxy drying self curing
resin based solvent based
Heat resistant
suitable inorganic zinc Single pack
synthetic medium
pigmented and silicate coating with silicone resin
based two pack
2 Type & composition capable of minimum 80% zinc based medium
Aluminium paint
adhering to content on dry film. with Aluminium
suitable up to
manually The final cure of flakes.
250oC.
prepared surface the dry film shall
and old coating. pass the MEK rub
test.
3 Volume Solids % 78±3 60±3 38±0.03 20±2
DFT (Dry Film
4 thickness) per coat in 100-125 65-75µ 15-20µ 15-20µ
microns
Theoritical covering
5 capacity in M2/coat/ 6.0-7.2 8-9 10-12 8-10
litre
Weight per liter in
6 1.41±0.03 2.3±0.03 0.95±0.03 1.00±0.03
kgs/litre
Touch dry at 30oC
7 3 hrs. 30 minutes. 3 hrs. 30 minutes.
(maximum)
Hard dry at 30oC
(maximum) 24 hrs 12 12 hrs 24 hrs
8 Full cure 30oC (for
immersion /high 5days NA NA NA
temperature service)
Min.: 12 hrs .at
9 Over-coating interval Min.: 10 hrs Min. 24 hrs Min.: 24 hrs
20oC & 50 % RH
Pot life at 30oC for two
10 90 minutes. 4-6 hrs. Not applicable Not applicable
component paints
Temperature 80 oC 400 oC 250oC 500oC
11
Resistance (minimum) Dry service Dry service Dry service Dry service
PAINT MATERIALS
Sl.
DESCRIPTION F-14 F-15 F-16 F-17
No
Ambient temperature
curing Poly Siloxane
Two-component Two component
coating/High build
Epoxy phenolic solvent free type
cold applied inorganic
coating cured with high build epoxy
copolymer based
Polyamine cured Polyamine adduct phenolic/novalac
1 Technical name aluminium coating
coal tar epoxy hardener system epoxy phenolic
suitable for under
(primer + coating cured with
insulation coating of
intermediate coat Polyamine adduct
CS and SS piping for
+ finish paint) hardener system
high temperature
service.
Two pack ambient Two component
Specially
temperature curing solvent free type
formulated Suitable for high
epoxy phenolic high build epoxy
polyamine cured temperature service
coating system phenolic/novalac
2 Type & composition coal tar epoxy and under insulation
suitable for epoxy phenolic
suitable for coating for CS, alloy
application under coating cured with
application under steel and SS
insulation of Polyamine adduct
insulation
CS/SS piping hardener system
3 Volume Solids % 70±3 70±3 60±2 98-100
DFT (Dry Film
4 thickness) per coat in 100-125 75-100 75-100 125- 150
microns
Theoritical covering
5 capacity in M2/coat/ 5-8 4-5 7.0- 9.0 6.5 - 8
litre
Weight per liter in
6 1.45±0.03 1.65±0.03 1.3 1.7
kgs/litre (mix paint)
Touch dry at 30oC
7 4 hrs 3 hrs 1 hr 2 hrs
(maximum)
Hard dry at 30oC
(maximum) 24 hrs 24 hrs 16 hrs 24 hrs
8 Full cure 30oC (for
immersion /high 168 hrs (7 days) 168 hrs (7 days) - 168 hrs (7 days)
temp. service)
Over-coating interval Min. 6 hrs Min. 36 hrs Min.16 hrs Min. 16 hrs
9
Max.5 days Max.21 days Max. Not applicable Max.21 days
Pot life at 30oC for
10 two component 4 hrs 4-6 hrs 1 hr 1 hr
paints
Temperature -45oC to 150oC
-45oC to 125oC
Resistance under insulation & Up to 6000C -45oC to 150oC for
11 under insulation
immersion (Note: 5) immersion service
And immersion
1 Covering capacity and DFT depends on method of application. Covering capacity specified above is theoretical. Allowing
the losses during application, min specified DFT should be maintained.
2. All primers and finish coats should be cold cured and air drying unless otherwise specified.
3 All paints shall be applied in accordance with manufacturer's instructions for surface preparation, intervals, curing and
application. The surface preparation, quality and workmanship should be ensured. In case of conflict between this
specification and manufacturer’s recommendation, the same shall be clarified through EIL.
4 Technical data sheets for all paints shall be supplied at the time of submission of quotations.
5 F-16: Ambient temperature curing poly siloxane Coating or high build cold applied inorganic co-polymer based
aluminium coating. Inert polymeric matrix paint product with applicable temperature range of -180 to 650deg C is also
comes under this category
The coating system (External) should be selected based on the Plant location as given below:
- For all UNITs, DM, CPP & Cooling Tower etc: Table 10.0 to be followed
- For offsite area, UNITs, DM, CPP & Cooling Tower etc.: Table 10.0 to be
followed
c) For external surface of above ground tanks, table 12.0 to be followed for all locations
(Inland or coastal)
Notes:
2. Primers & Finish paints covered in Tables 8.0 to 17.0 are listed in Table 7.1.
TABLE 7.1: LIST OF PRIMERS & FINISH COATS COVERED IN TABLE NOS. 8 to 18.0
PRIMERS
P-2 Chlorinated rubber zinc Phosphate Primer
P-4 Etch Primer/Wash Primer
P-6 Two component Epoxy Zinc Phosphate Primer cured with polyamine hardener
Single pack, cold galvanizing compounds containing minimum 92% electrolytic zinc in dry film.
P-7
make ZINGA, LOCKTITE (of HENKEL) or ZRC
F-9 Two component Inorganic Zinc Silicate coating
Total DFT
Sl. Surface
Design Temp. in oC Coating System in Microns Remarks
No. Preparation
(min.)
NOTES:
1 The application and repair of pre-erection/pre-fabrication or Shop Primer given in above tables
shall be done for all the items to be painted. In case the damages of primer are severe and spread
over large area, entire primer shall be removed by blasting to achieve SSPC-SP-10 and surfaces
to be primed again with F-9 or F-12 as applicable.
TABLE 8.0 COATING SYSTEM FOR GI HAND RAILS & GI ITEMS WHICH REQUIRE
COLOUR CODING- All locations
Design
Sl. Total DFT
Temp. in Coating System
No. o in Microns (min.)
C
Hot Dip Galvanizing * to 80-85 microns (600-610
80 microns of finish coat
gm/m2)as per IS 4759, 2629, 4736, 2633 +
8.1 Up to 60 (excluding the thickness of
1 coat of P-6 @ 40µ DFT/coat + 1 coat of F-2 @ 40
galvanizing )
microns DFT/coat
NOTES:
2 Repair of the damaged area of galvanized coatings due to welding during erection shall be
carried out as per recommended practice IS 11759 using cold galvanizing spray process.
Organic Paint systems are not acceptable for repair.
3 After repair of damaged galvanized coating by Cold Galvanized, the repaired area shall be top
coated with paint system as given in Table 8.0 above (i.e., 1 coat of P-6 @ 40µ DFT/coat + 1
coat of F-2 @ 40µ DFT/coat).
* Flare line within unit or offsite areas shall be coated as per Clause 10.3 of Table 10.0, having
finish coat of 2 coats of F-12.
NOTES:
1 The list of items given in the heading of the above table is not exhaustive. There may be more
items for a particular contract where these specifications are used. The Contractor is fully
responsible for completing painting including prefabrication primer for all the items supplied
and fabricated through his scope of work as per tender document.
2 If the Pre-erection/Pre-fabrication & Shop Primer has already been completed, the same shall not
be repeated again in the field. In case the damages of primer are severe and spread over large
areas, the engineer-in-charge may decide & advise re-blasting and priming again. Repair of pre-
fabrication/pre-erection primer, if required, shall be done as per Table 7.2.
3 In case of Paint systems as per Sl. Nos. 9.5 and 9.6, the color bands shall be applied over the
Aluminum paint as per the Color coding requirement for specific service of piping given in
Clause 19.0.
4 All coating system including surface preparation, primer, and finish coat for piping shall be done
at field only.
TABLE 10.0 COATING SYSTEMS FOR UNIT AREAS AS WELL AS DM, CPP,
COOLING TOWER OF INLAND PLANTS AND FOR ALL AREAS (UNIT,
OFFSITE, DM, CPP, etc.) OF COASTAL PLANTS
For external surfaces of un-insulated and above ground (atmospheric exposure) structures, piping,
vessels, equipments, external surface of MS chimney/stacks, RCC chimney, internal surface of MS
chimney without refractory lining, towers, columns, pumps, compressors, blowers etc. of carbon steel,
LTCS & low alloy steels (note-1)
SSPC-SP-10; a) No over-
10.1 -90 to -15 1coat of F-9 @ None None 65-75 coating to be
65-75µ DFT/coat done on
F-9 as it will
2 coats of F-6B lead to mud
@ 100 µ cracking.
DFT/coat + 1
SSPC-SP-10; 1 coat of P-6
coat of F-2 @ b) F-12 shall
10.2 -14 to 80 1coat of F-9 @ @ 40 µ 345-355
40µ DFT/coat; be ambient
65-75µ DFT/coat DFT/coat
(2x100 + 40= temperature
240) curing type
c) Finish coat
including
2 coats of F-12 primer
SSPC-SP-10; @ 20µ compatible
10.3 81 to 400 1coat of F-9 @ None DFT/coat 105-115 with finish
65-75µ DFT/coat 2x20=40 coat (i.e. field
primer) shall
be applied at
site only.
Finish
2 coats of F-12 coating is not
SSPC-SP-10; permitted at
@ 20µ
10.4 401 to 550 1coat of F-12 @ None 60 equipment
DFT/coat;
20µ DFT/coat manufacture
(2x20=40)
shop.
NOTES:
1. The list of items given in the heading of the above table is not exhaustive. There may be more
items for a particular contract where these specifications are used. The Contractor is fully
responsible for completing painting including prefabrication primer for all the items supplied
and fabricated through his scope of work as per tender document.
2. If the Pre-erection/Pre-fabrication & Shop Primer has already been completed, the same shall not
be repeated again in the field. In case the damages of primer are severe and spread over large
areas, the engineer-in-charge may decide & advise re-blasting and priming again. Repair of pre-
fabrication/pre-erection primer, if required, shall be done as per Table 7.2.
3. For external surface of MS chimney with or without refractory lining and for internal surface
without refractory lining, paint system as per 10.3 above shall be followed.
4. For external surface of RCC Chimney, 2 coats of F-6B @ 100µ DFT/coat to obtain total DFT of
200 µ shall be applied after proper surface preparation as per guidelines in 5.1.6.
5. In case of paint systems as per Sl. Nos. 10.3 and 10.4, the colour bands shall be applied over the
Aluminum paint as per the Color coding requirement for specific service of piping given in
Clause 19.0.
6. All coating system including surface preparation, primer, finish coat for piping shall be done at
site/field only.
NOTES
1. The paint /coating manufacturers shall provide their Quality control test certificate of coating
materials (F-6A) for immersion service of the exposed effluent given in 11.2.
Total
Surface Coating system (Field)
DFT
Sl. Design Temp. Preparation (see note 1 below) in Remarks
No. in oC (Field)
Microns
Primer Finish Coat (min.)
All external surfaces of shell, wind girders, appurtenances, roof tops of all above ground tank including top
12.1
side of external and internal floating roof and associated external structural works.
F-6 should
2 coats of F-6B @
1coat of F-9 @ 65-75µ be suitable
100µ DFT /coat + 1
SSPC-SP-10 DFT/coat + 1coat of P-6 for
12.1.1 -14 to 80 coat of F-2 @ 40µ 345-355
@ 40µ DFT/ coat ; occasional
DFT/ coat;
water
immersion
12.2 External surfaces of bottom plate (soil side) for all storage tanks.
F-7 should
be suitable
for
SSPC-SP-10 1 coat of F-9 @ 3 coats of F-7@ 100µ immersion
12.2.1 -14 to 80 365-375
65-75µ DFT/ coat DFT/coat (3x100=300) service of
the
products
given
1 coat of F-15 primer @
80µ DFT/ coat + 1 coat
SSPC-SP-10 1 coat of F-15 finish
12.2.2 81 to 150 of F-15 intermediate 240 -
coat @ 80µ DFT/ coat
coat @ 80µ DFT/coat ;
(80+80=160)
1 coat of F-16 @ 125 µ 1 coat of F-16 @ 125 µ
12.2.3 151 to 550 SSPC-SP-10 250 -
DFT /coat DFT /coat
12.3 For underside of the bottom plate (in case tank is not lifted during PWHT) (see Note 2c)
For CS Products
SSPC SP-6 from
Commercial JOTUN or
Blast HI-TEMP
2 coats of inert
-180 to 650 1 coat of inert polymeric coatings or
12.3.1 polymeric matrix 350-400
For SS matrix coating @ 125 µ SK
coating @ 125 µ
SSPC SP-1 FORMULA
with non- TIONS are
chloride recommend
solvent ed.
NOTES
1. All paint coating application including primer for tankage shall be carried out at field after
erection and completion of all welding.
TABLE 13.0 INTERNAL COATING SYSTEMS FOR CARBON STEEL AND LOW ALLOY
STORAGE TANKS & VESSELS
Amercoat
3 coats of vinyl
23 or
chloride co-polymer
13.6. equivalen
All SSPC-SP-10 None AMERCOAT 23 @ 225
1 t suitable
75µ /Coat;
for the
(3x75=225)
service
13.7 Inside pontoon and inside of double deck of all floating roofs
13.7. 1 coat of F-8 @ 100µ 1 coat of F-8 @ 100µ
-14 to 80 SSPC-SP-3 200 -
1 DFT/coat DFT/coat
WET SLOPS, AMINE solutions, SOUR WATER , WATER DRAW OFF
13.8
All internal surfaces, accessories and roof structures of Cone and Dome roof tanks
1 coat of F-15
intermediate coat @
13.8. 1 coat of F-15 primer @ 80µ DFT/coat + 1 coat
-14 to 90 SSPC-SP-10 240 -
1 80µ DFT/ coat of F-15 finish coat @
80µ DFT/ coat;
(80+80=160)
VACUUM RESIDUE, FUEL OIL , DRY SLOP, BITUMEN AND OTHER HIGH TEMPERATURE
HYDROCARBON LIQUIDS
13.9 Underside of floating roof, internal surface of cone roof, bottom plate, inside of bare shell – including
wetted and non wetted surfaces, oil side surfaces of deck plates, oil side surfaces of pontoons, roof
structures, structural steel and ladders
1 coat of F-17
intermediate coat @
13.9. 1 coat of F-17 primer 125µ DFT/coat + 1 coat
Up to 150oC SSPC-SP-10 375 Note:3
1 @ 125µ DFT/ coat of F-17 finish coat
@125µ DFT/ coat;
(125+125=250)
ALKALIS UP TO 50 % CONCENTRATION
13.10
All internal surfaces, accessories and roof structures of Cone and Dome roof tanks
2 Coats of F-6 A @
13.10 1 coat of F-15 primer @
Up to 60oC SSPC-SP-10 100µ DFT/coat; 280-100 -
.1 80µ DFT/ coat
(2x100=200)
NOTES
1. All paint coating application including primer shall be carried out after erection and completion
of all welding work at site.
2. F-6A should be suitable and resistant for immersion service for the respective Hydrocarbons.
3. This system can be used where maximum operating temperature is below 150oC and design
temperature is up to 200oC. Cases of operating temperature > 150oC are not covered in this spec,
such cases shall be covered in separate job specifications.
4 F-6 A shall be suitable for drinking water service and should have competent authority
certification.
1 Primer & Field painting including priming shall be in accordance with applicable
SOR/MR/PRs.
15.2 Stainless Steel, Alloy Steel, Alloy-20 Piping, Vessels &Equipments (Note:2)
1 coat of F-15
Sweep blasting/Light Blast clean
intermediate coat @
as per grade Sa-1.0, of Swedish
80µ DFT/coat + 1 coat
15.2.1 -30 to 125 Standards SIS-05-5900 (Latest) None 240
of F-15 finish coat @
(15-25µ surface profile)
80µ DFT/coat;
1 coat of F-15@ 80 µ DFT/coat
(80+80=160)
SSPC-SP-10
Inert polymeric matrix coating*@
125µ DFT/coat 2 coats of Inert polymer
for SS sweep blasting/Light Blast matrix coating* @
15.2.3 500-650 --- 375
clean as per grade Sa-1.0, of 125µ DFT/coat
Swedish Standards SIS-05-5900
(Latest)
(15-25µ surface profile)
15.3 Cyclic service of CS, LTCS, SS, & Alloy Steels
SSPC-SP-10
Inert polymeric matrix coating*@
125µ DFT/coat 2 coats of Inert polymer
for SS sweep blasting/Light Blast matrix coating* @
-180 to 650 none 250
clean as per grade Sa-1.0, of 125µ DFT/coat
Swedish Standards SIS-05-5900
(Latest)
(15-25µ surface profile)
NOTES
1. The blast cleaning abrasives for SS and Alloy steel surfaces shall be SS grits/shots or Aluminium oxide
grits/shots.
2. For piping with cyclic temperature of -45 to125 deg.C Sr.No 15.2.1 is applicable.
3. Application of Primer, field paint & repair shall be in accordance with applicable SOR/MR/PRs.
18.0 STORAGE
18.1 All paints and painting materials shall be stored only in rooms to be arranged by contractor
and approved by Engineer-in-charge for the purpose. All necessary precautions shall be
taken to prevent fire. The storage building shall preferably be separate from adjacent
building. A signboard bearing the word “PAINT STORAGE – NO NAKED LIGHT –
HIGHLY INFLAMABLE” shall be clearly displayed outside. Manufacturer’s
recommendation shall be followed for storage of paint materials.
This specification covers the requirement of colour scheme for the identification of the
contents of the pipelines carrying fluids, storage tanks and equipment in refineries. The
following colour coding system has been made based on BPCL-KR input document
19.1 IDENTIFICATION
The system of colour coding consists of a ground colour and secondary colour bands
superimposed over the ground colour. The ground colour identifies the basic nature of the
service and secondary colour band over the ground colour distinguishes the particular service.
The ground colour shall be applied over the entire length of the un-insulated pipes. For
insulated lines ground colour shall be provided as per specified length and interval to identify
the basic nature of service and secondary colour bands to be painted on these specified length
to identify the particular service. Above colour code is applicable for both unit and offsite
pipelines.
The following ground colour designation for identification of basis classification of various
important services shall be followed.
Secondary colours: The narrow bands presenting the secondary colour which identifies the
specific service may be applied by painting or preferably by use of adhesive plastic tapes of
the specific colour.
19.2.1 The following specifications of colour bands shall be followed for identifying the piping
contents, size and location of bands & letters. The bandwidth and size of letters in legends will
depend to some extent upon the pipe diameter. Either white or black letters are selected to
provide maximum contrast to the band colour. Bands usually are 100 mm wide and regardless
of band width, are spaced 50 mm apart when two bands are employed.
Contrast shall be provided between color field and legend for readability. Use of letters
standard style, in sizes, 1/2inch (13mm) and larger, is recommended. See above table for
specific size recommendations. For identification of materials in pipes of less than ¾ inch
(19mm) in diameter, and for valve and fitting identification, the use of permanently legible tag
is recommended.
In addition, ground colour as per specified length should be provided on insulated piping for
easy identification of nature of fluid, on which the colour bands should be painted for
identification of each service. The length of the ground colour should be 3 times the width of
normal bands or 2 meters, whichever is suitable depending on the length of the pipe.
Arrows shall be used to indicate direction of flow. Where flow can be in both directions,
arrows in both directions shall be displayed.
Positive identification of the contents of a piping system shall be by lettered legend, giving the
name of the contents in full or abbreviated form. Contents shall be identified by a legend with
sufficient additional details such as temperature, pressure, etc as are necessary to identify the
hazard. Legends shall be brief, informative, pointed and simple of greatest effectiveness.
Legends shall be applied close to valves or flanges and adjacent to changes in direction,
branches and where pipes pass through walls or floors, where it enters and emerges from road,
culvert and walkway overpasses, unit battery limits and at every 50m intervals on straight pipe
runs sufficient for identification. Identification may be accomplished by stencilling, the use of
tape, or markers. In any situation, the number and location of identification markers shall be
based on the particular piping system.
The letters will be in black on pipes painted with light shade colours and white on pipes
painted with dark shade colours to give good contrast.
Only writing of service name shall be done on stainless steel lines. Precautions should be taken
while painting by using low chloride content painting to avoid any damage to the stainless
steel pipes. It is preferable to use adhesive plastic tapes to protect stainless steel pipes.
Visibility:
Attention shall be given to visibility with reference to pipe markings. Where pipelines are
located above or below the normal line of vision, the lettering shall be placed below or above
the horizontal centreline of the pipe.
Size of letters stencilled / written for equipment shall be as given below:
In addition, the contents of the pipe and/or direction of flow may be further indicated by
arrows and legend. If a hazard is involved it must be identified clearly by legend.
Colour bands: The location and size of bands, as recommended, when used, shall be
applied to the pipe.
For alloy steel / stainless steel pipes and fittings in stores / fabrication yard, colour band
(Minimum ½” wide) should be applied along the complete length of pipe, bends / tees, side-
covered surface (on thickness) of flanges as well as valves as per the metallurgy.
When the piping layout creates or occurs in a limited area of inaccessibility or of extreme
complexity, such segments of layouts may require substitute techniques shall be limited to
such segments and shall not deviate from the concept of identification as defined above.
The specification for application of the complete Piping identification colour code, including
base and bands colours, are presented in the below table.
11 Crude Sweet 1 Light brown ground colour with 1 yellow band in centre
12 Crude Sour 1 Light brown ground colour with 1 orange band in centre
13 VGO / HCU Feed 1 Oxide red ground colour with 1 steel grey band in centre
14 OHCU Bottom / FCCU Feed 1 Oxide red ground colour with 2 steel grey band in centre
6. GRATING GALVANSIED
8. HAND RAILINGS
- HANDRAIL, MIDDLE RAIL, TOE PLATE SIGNAL RED
- VERTICAL POST BLACK
20.1 Equipment number shall be stencilled in black or white on each vessel, column, equipment &
machinery (insulated or uninsulated) after painting. Line number in black or white shall be
stencilled on all the pipe lines of more than one location as directed by Engineer-In-Charge;
Size of letter printed shall be as below:
21.2 Two coats of selected finishing paint as per defense requirement shall be applied in a
particular pattern as per 20.3 and as per the instructions of Engineer-In-Charge.
21.3.1 Disruptive painting for camouflaging shall be done in three colours in the ratio of 5:3:2 (all
matte finish).
21.3.4 The patches should be continuous where two surfaces meet at an angle.
Contractor shall submit MAR (Material Approval Request) along with datasheets, MSDS,
relevant information and Test results as indicated below including test results of long term
tests for all paint products against system indicated for approval.
The contractor shall be fully responsible for the quality of the paints meeting technical
requirements of the products as per approved datasheets. Along with the delivery of the paint
products, the contractor shall furnish batch wise test report from the manufacturer.
Once the paint material is supplied to site, In addition to the quality control system as
specified in section 13.0, for each product, the supplier shall organize random sampling and
testing in a third party laboratory as per discretion of the Engineer-in-charge. Failing to meet
the specified quality requirements may cause rejection of the paint products.
23.1 All painting materials including primers and thinners brought to site by contractor for
application shall be procured directly from manufactures as per specifications and shall be
accompanied by manufacturer's test certificates. Paint formulations without certificates are not
acceptable (see section 12.0).
The painting work shall be subject to inspection by Engineer-In-Charge at all times. In
particular, following stage-wise inspection will be performed and contractor shall offer the
work for inspection and approval of every stage before proceeding with the next stage. The
record of inspection shall be maintained in the registers. Stages of inspection are as follows:
The steel substrate after degreasing as per SSPC-SP 1 shall be tested as per following
procedure to validate absence of oil and grease contamination.
a) Visual inspection - Continue degreasing until all visible signs of contamination are
removed.
b) Conduct a solvent evaporation test by applying several drops or a small splash of
residue-free tri-chloromethane on the suspect area especially pitting, crevice corrosion
areas or depressed areas. An evaporation ring formation is indicative of oil and grease
contamination.
Continue degreasing and inspection till test is passed.
- Tests for surface finish of blasted surface shall be done by visual inspection using SSPC-
VIS1. Clear cellophane tape test as per ISO 8502-3 shall be used to confirm absence of
dust on blasted surface. Checks shall be done on each component at least once per 200
m2 of blasted surface and minimum of 3 checks per shift.
- Test for presence of soluble salt as per method ISO 8502-9. Maximum allowable salt
content shall be considered 20 mg/m2 (2 mg/cm2). Checks shall be done on each
component at least once per 200 m2 of blasted surface and minimum of 3 checks per
shift. In case salt exceeds specified limit, the contaminated surface shall be cleaned by
method as per Annexure-C of IS 12944-4 (water cleaning). After cleaning surface shall
be retested for salt after drying.
The angular profile depth measurement shall be done by profile tape as per method
NACE Standard RP 0287 or ASTM D 4417 method B (Profile depth gauge micrometer).
Spot measurement shall be carried out every 15m2 of blasted surface. At each spot three
measurements shall be taken over an area of 10 cm2 and average of measurements to be
recorded and reported.
If profile is <65 microns blasting shall continue till greater than 65 microns depth profile
is achieved.
Blasting Media (For every fresh batch of media and one random test during blasting)
Blasting Media shall be visually inspected for absence of contamination and debris using
10 X magnification.
a) Inspection for the absence of oil contamination shall be conducted using following
procedure:
- Fill the bottle with potable water, cap and shake the bottle.
- Inspect water for oil film/slick. If present, the blasting media is not to be used.
Test for Blasting Air (Once Daily before start of blasting and once at random during
blasting)
The air for blasting shall be free from moisture and oil. The compressor air shall be
checked for oil and water contamination per ASTM D 4285.
In addition to above, record should include type of shop primer already applied on equipment
e.g. zinc silicate, or zinc rich epoxy, or zinc phosphate.
Any defect noticed during the various stages of inspection shall be rectified by the contractor
to the entire satisfaction of Engineer-In-Charge before proceeding further. Irrespective of the
inspection, repair and approval at intermediate stages of work, contractor shall be responsible
for making good any defects found during final inspection/guarantee period/defect liability
period as defined in general condition of contract. Dry film thickness (DFT) shall be checked
and recorded after application of each coat and extra coat of paint should be applied to make-
up the DFT specified without any extra cost to owner, the extra coat should have prior
approval of Engineer-in-charge.
After surface preparation, the primer should be applied to cover the crevices, corners, sharp
edges etc. in the presence of inspector nominated by Engineer-In-Charge.
The shades of successive coats should be slightly different in colour in order to ensure
application of individual coats, the thickness of each coat and complete coverage should be
checked as per provision of this specification. This should be approved by Engineer-In-
Charge before application of successive coats.
The contractor shall provide standard thickness measurement instrument with appropriate
range(s) for measuring.
Dry film thickness of each coat, surface profile, gauge for checking of surface profile in case
of sand blasting. Holiday detectors and pinhole detector & protector whenever required for
checking in case of immersion conditions.
Prior to application of paints on surfaces of chimneys, the thickness of the individual coat
shall be checked by application of each coat of same paint on M.S.test panel. The thickness of
paint on test panels shall be determined by using gauge such as 'Elko meter'. The thickness of
each coat shall be checked as per provision of this specification. This shall be approved by
Engineer-In-Charge before application of paints on surface of chimney.
At the discretion of Engineer-In-Charge, the paint manufacturer must provide the expert
technical service at site as and when required. This service should be free of cost and without
any obligation to the owner, as it would be in the interest of the manufacturer to ensure that
both surface preparation and application are carried out as per their recommendations. The
contractor is responsible to arrange the same.
1) Coating DFT measurement shall be as per ISO 2808. Type II electromagnetic gauges
should be used for ferrous substrates. DFT gauge calibration, number of measurement
shall be as per SSPC-DA 2. Measured DFT shall be within + 10% of the dry film
thickness, specified in the specifications.
2) Adhesion of the primer to the steel substrate and intercoat adhesion of the subsequent
coat(s) after curing for at least a week after application of the topcoat shall be examined by
a knife test in accordance with ASTM D 6677. For the knife test, if the rating is better than
8, the adhesion is considered acceptable. The adhesion is destructive and tested areas shall
be repaired afterward using the spot repair procedure. Alternatively, the applicator may
perform the adhesion test on a steel panel coated using the same surface preparation and
coating application procedure as the work piece. Adhesion testing shall be carried out for
each component at least once per 200 m2 (2000 ft2) of coated surface.
3) Holiday testing shall be conducted in accordance with NACE SP 0188. For immersion
services, 100% of coated area shall be inspected for holidays. For atmospheric exposure,
10% of coated area which must include weld seams, corners and edges to be holiday
tested. Voltage at which test is to be carried out will depend upon DFT of coating being
tested and shall be as per NACE SP 0188. Any holiday is unacceptable and should be
marked and repaired immediately.
The contractor shall arrange for spot checking of paint materials for Specific gravity, glow
time (ford cup) and spreading rate.
A final inspection shall be conducted prior to the acceptance of the work. The coating
contractor and the facility owner shall both be present and they shall sign an agreed inspection
report. Such reports shall include:
General
- Names of the coating contractor and the responsible personnel
- Dates when work was performed
Coating Materials
- Information on coating materials being applied
- Condition of coating materials received
Environmental Conditions
- Weather and ambient conditions
- Coating periods
Surface Preparation
- Condition of surface before preparation
- Tools and methods used to prepare surface
- Condition of surface after preparation
Coating Application
- Equipment used
- Mixing procedure prior to application
- Coating application techniques used
Testing
- Type and calibration of inspection instruments used
- Type of quality control tests performed, and results
24.0 GUARANTEE
The contractor shall guarantee that the chemical and physical properties of paint materials used
are in accordance with the specifications contained herein/to be provided during execution of
work.
L-
O
—U-
r
REF. PLANE
ir4
SPECIAL NOTES
CUMULATIVE TOLERANCES ON CONSECUTIVE DIMENSIONS SHALL BE LIMITED BY OVERALL DIMENSIONAL TOLERANCES.
ALL TOLERANCES ARE FROM REFERENCE PLANE UNLESS OTHERWISE INDICATED.
INTERFERENCE BETWEEN INTERNAL AND EXTERNAL PARTS OR ANY RESTRICTION TO THE INTENDED FUNCTION OF ANY
PART SHALL BE KEPT IN VIEW WHERE TOLERANCES ARE CUMULATIVE.
SPECIFIC TOLERANCES FOR ANY PART SHOWN ON EIL DRAWING SHALL BE GIVEN PREFERENCE TO THOSE GIVEN
IN THIS STANDARD.
UNUSUALLY LARGE OR COMPLEX VESSELS MAY BE EXECUTED AS PER FABRICATOR'S STANDARD WHEN THE TOLERANCES
AS SHOWN ARE UNREASONABLE. IN SUCH INSTANCES FABRICATOR'S TOLERANCES & UMITS MUST BE SUBMITTED
FOR APPROVAL.
E. VESSEL UPTO AND INCLUDING 750 mm NOMINAL DIAMETER SHALL HAVE CARTRIDGE TYPE TRAY. FOLLOWING
TOLERANCES ON DIAMETER SHALL APPLY THROUGHOUT ITS LENGTH.
VESSEL NOMINAL DIAMETER TOLERANCE
500 mm AND UNDER VESSEL I.D. + 1 mm
501 mm TO 750 mm VESSEL I.D. ± 3 mm A
TYPE - A
IUD 1000
1200
950
1100
700
800
330
375
820
960
B
B
12.3
19.4
85
130
HOLE FOR 1400 1250 900 465 1150 B 19.7 140
SLIDING SUPPORT
1600 1450 1000 370 1300 C 23.3 165
1800 1600 1100 410 1450 C 39.1 260
D/18 2000 1750 1200 445 1600 C 43.5 290
O 9R
■ 2200 1950 1300 495 1800 D 49.1 295
i 110 111 2400 2150 1450 545 2000 D 53.5 390
ki iii
__.
..1 2600 2300 1550 585 2150 D 52.9 440
11 1
Li Li
N- II It
1 0
2800
3000
2500
2670
1650
1750
620
670
2300
2500
E
E
52.7
64.9
475
600
I- EARTHING 3200 2800 1850 710 2600 E 63.8 620
I 250
L
26 0 HOLES FOR 3400 3000 1950 760 2800 E 64.9 630
30 M 20 BOLTS
111111 3600 3200 2050 830 3000 E 60.5 725
TYPE - B
DUD ,
3800
4000
3350
3550
2150
2250
845
895
3150
3300
E
E
61.0
60.6
745
820
HOLE FOR
SLIDING SUPPORT
TYPE t1 t2 L3 t3
D/18 A 10 10 170 12
B 10 12 250 12
110 C 12 16 300 16
D 16 20 350 20
2-60 VENT
HOLE (TYP.) E 20 20 400 20
(REF. NOTE-5)
I L 1 I L1 I Li 140
EARTHING
I 250
L2
I 30 0 HOLES FOR
30 M 24 BOLTS
PARALLEL TO VESSEL
TYPE - C. D. E AXIS (TYP)
HOLE FOR
SLIDING SUPPORT
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
VESSEL DIAMETER 'D' REFERS TO THE OUTER DIAMETER OF THE SHELL.
FOR INTERMEDIATE DIAMETERS TAKE THE IMMEDIATE NEAREST DIAMETER SUPPORT.
WELDING SHALL BE DONE ALL AROUND AND SHALL BE CONTINUOUS FILLET WELD. WELD SIZE SHALL
BE 6 mm FOR VESSELS UPTO 1400 mm DIA. AND 8 mm FOR VESSELS ABOVE 1400 mm DIA.
PROVIDE 2 NO. 60 VENT HOLES IN SADDLE WRAPPER PLATE. THESE HOLES SHALL BE PROVIDED DIAGONALLY
OPPOSITE AND BE LEFT UNPLUGED AND SHALL BE FILLED WITH HARD GREASE ONLY.
WHERE EARTHING LUG CANNOT BE PUT AT AN ELEVATION OF 400 mm ABOVE THE SADDLE BASE PLATE
IT SHALL BE LOCATED AS HIGH AS POSSIBLE.
EARTHING LUGS ARE NOT TO BE PAINTED OR GALVANIZED.
DETAIL, DIMENSIONS AND NOTES IN ENGINEERING DRAWING TAKE PRECEDENCE OVER THOSE SHOWN HERE.
MATERIALS SHALL BE AS PER ENGINEERING DRAWING.
EARTHING LUG SHALL BE AS PER STANDARD 7-12-0026
CHAIR CAP
NOTCH GUSSET TO WASHER WELD AT SITE
CLEAR WELD CONTINUOUS RING
NOTCH GUSSET TO
CLEAR WELD
EARTHING LUG
ir
// BOLT 0
+ 3mm
H 20
//
W
n A K
AK +V BOLT 0
-17
I-
II BOLT 0
+ 12mm
L + 12mm
(ALL DIMENSIONS AND DETAILS ARE
BCD BCD SAME AS SHOWN FOR TYPE-2
BCD EXCEPT CONTINUOUS RING)
BOLT 0 + 12mm
[WIDE SLOT RADIUS
+ 6mm
TYPE-1 TYPE-2 SLOT DETAIL TYPE-3
(SEE NOTE-6) (FOR CONTINUOUS RING ONLY)
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
BOLT CIRCLE DIAMETER ( BCD ), NUMBER AND SIZE OF THE BOLTS SHALL BE AS PER ENGINEERING DRAWING.
* 3. DIMENSIONS t1, t2, t3 AND 'I: ARE TO BE CHECKED IN EVERY CASE.
IN CASE OF ANY CONFLICT THE ENGINEERING DRAWING SHALL GOVERN.
NUMBER OF BOLTS USED IS TO BE A MULTIPLE OF 4 AND BOLTS SHALL STRADDLE VESSEL NORTH—SOUTH
CENTRE LINE IN PLAN.
USE CONTINUOUS RING ( CHAIR CAP ) IF DISTANCE BETWEEN CONSECUTIVE BOLTS IS LESS THAN 400 mm.
CIRCULAR WASHER SHALL BE SHIPPED LOOSE AND WELDED AT SITE AFTER ANCHOR BOLTS ARE IN POSITION.
♦ 8. PREFERRED DIMENSION 'A'
EARTHING LUG SHALL BE LOCATED BETWEEN THE ANCHOR BOLTS AND SHALL BE AS PER STANDARD 7-12-0026.
WHEN THE ANCHOR CHAIR CAP IS NOT CONTINUOUS, THE BASE PLATE SHALL BE SUITABLY STIFFENED USING
REMOVABLE STRUCTURAL SECTIONS (BEAM/SPIDER) AT SITE DURING ERECTION.
t*/
6 30.06.2011 REAFFIRMED AND REISSUED AS STANDARD POREL RKT M/SC DM
5 08.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
Page 373 of 704
.C110Eet/IINGNEEI6
dliturletuleGNIFINDIA
oimmumwommose
UMITED
(A Govt. of Indio Undertaking)
SKIRT OPENING DETAILS 7-12-0005 Rev. 5
Page 1 of 2
N
PAD ALL AROUND
SEE NOTE-7
SKIRT
INSIDE 100NB SCH. 40
40 PIPE VENI
SKIRT
EQUISPACED INSIDE
BASE PLATE
SKIRT
80x6THK. PLATE
INSIDE
cv II 2mm(TENTATIVE)
CHECK FOR PIPE
THERMAL EXPANSION.
MALLER OF tx+2
OR 14mm (FOR PIPE
SSEE NOTE-6)
OR INSULATED PIPE+10
SEE NOTE-10
2-120 HANDLE
3-50 PINS-15 LG
EQUISPACED
VIEW—Q
VIEW—P
NOTES (HOT TYPE VESSEL) (COLD TYPE VESSEL)
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
ACCESS OPENING SHALL BE LOCATED BETWEEN ANCHOR BOLTS WHEREVER POSSIBLE.
ACCESS OPENING IS NOT TO BE BLOCKED BY BOTTOM HEAD.
SKIRT DIAMETER ACCESS OPENING DIA.(D) NO. OF ACCESS OPENING
UP TO 1000 400 1
OVER 1000 UPTO 1500 450 1
OVER 1500 UPTO 3000 500 1
OVER 3000 500 2
SKIRT DIAMETER NO. OF VENT HOLES
UP TO 1000 2
OVER 1000 UPTO 2000 3
OVER 2000 4
MINIMUM SIZE OF PIPE SLEEVE IS 150NB SCH 40. USE SCH 40 UPTO 250NB PIPE SLEEVE. FOR 300NB AND
ABOVE, PIPE SLEEVE SHALL BE FABRICATED FROM PLATE.
ALL OPENINGS 300 DIA. AND ABOVE SHALL BE PROVIDE WITH REINFORCEMENT PADS ON INNER SURFACE OF SKIRT.
IN CASE OF CONFUCT ENGINEERING DRAWING SHALL GOVERN.
IN FLARED SKIRT, OPENING DETAIL IS SAME AS THAT FOR CYLINDRICAL SKIRT.
WOODEN BLOCK SHALL BE FIXED TO SLEEVE WITH TWO NO. OF WOOD SCREWS.
ACCESS OPENING/PIPE OPENING/VENT SHALL BE OF SAME MATERIAL AS THAT OF SKIRT.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
* 13. PROJECTION OF SLEEVE/NECK SHALL BE GREATEST OF (30+INSULATION THK.), (30+FIRE PROOFING) & 50mm.
14. CENTER LINE OF ACCESS OPENING SHALL BE 850 MM (MINIMUM) ABOVE BOTTOM BASE RING FOR ANCHOR
BOLTS OF SIZE M45 & BELOW AND 1100 MM (MINIMUM) FOR ANCHOR BOLTS OF SIZE ABOVE M45. IF ANCHOR
CHAIR HEIGHT IS MORE THAN THAT OF GIVEN IN STANDARD. LOCATION OF ACCESS OPENING SHALL BE ESTABLISHED
SUITABLY.
1
5 23.05.2011 REAFFIRMED AND REISSUED AS STANDARD POREL RKT
PAD AS PER
ENGINEERING DRAWING
6 THK. COVER
PLATE
REF. TABLE ON
SHT. 2 OF 2 HOLE DIA.= BOLT DIA.
NOTCH TO + 6mm
CLEAR WELD
WELD UNE
TANGENT UN
B.C.D.=VESSEL 0/D-50
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
THIS STD. IS APPLICABLE FOR VESSEL DIAMETER UPTO AND INCLUDING 2000mm, MAXIMUM SHELL THICKNESS OF 20mm
AND MAXIMUM LENGTH (T.L. TO T.L.) OF 3000mm VESSELS BEYOND ABOVE RANGE REQUIRE SPECIAL CONSIDERATION.
3. FOR CALCULATION, FOLLOWINGS PARAMETERS HAVE BEEN CONSIDERED.
WIND PRESSURE 200 Kg/me
SHAPE FACTOR 0.7
BASIC SEISMIC CO—EFFICENT (a0 ) 0.08
SOIL FOUNDATION SYSTEM FACTOR (p) 1.5
IMPORTANCE FACTOR (I) 2.0
EMPTY WEIGHT WITH WIND LOADING OR HYDROSTATIC WEIGHT WITH SEISMIC LOADING.
4. HEIGHT AND NUMBER OF LEG SUPPORTS AND SIZE OF ANCHOR BOLTS SHALL BE AS PER ENGINEERING DRAWING.
MINIMUM BOLT SIZE SHALL BE M 20.
MAXIMUM INSULATION THICKNESS CONSIDERED IS 150 mm.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
MATERIALS SHALL BE AS PER ENGINEERING DRAWING.
EARTHING LUG SHALL BE AS PER STANDARD 7-12-0026.
800 4 ISA 100x100x10 ISA 130x130x8 ISA 130x130x12 200x200x16 THK. 45 3150
1000 4 ISA 100x100x12 ISA 130x130x10 ISA 150x150x12 230x230x16 THK. 45 4600
1250 4 ISA 110x110x15 ISA 150x150x10 ISA 150x150x12 230x230x16 THK. 45 6750
1600 4 ISA 130x130x15 ISA 150x150x15 ISA 150x150x18 230x230x16 THK. 60 9500
1750 4 ISA 150x150x12 ISA 150x150x18 ISA 200x200x12 300x300x16 THK. 60 12700
2000 4 ISA 150x150x18 ISA 200x200x12 ISA 200x200x15 300x300x20 THK. 75 16400
NOTES
FOR A VESSEL WITH MAXIMUM SUPPORT LEG HEIGHT OF 1500mm, FOLLOWING ALTERNATIVE
LEG SIZES MAY BE USED :—
ISA 65x65x8 WITH HYDROSTATIC WEIGHT UPTO 500 Kg.
ISA 80x80x8 WITH HYDROSTATIC WEIGHT 501 Kg. TO 1000 Kg.
Y
NOTCH TO WELD UNE
CLEAR WELD
TANGENT UNE
S./
O
0
0_
to
NOTES
w ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
FOR DESIGN OF SUPPORT, FOLLOWINGS PARAMETERS HAVE BEEN CONSIDERED.
WIND PRESSURE 200 Kg/m2
SHAPE FACTOR 0.7
BASIC SEISMIC CO—EFFICENT (a0) 0.08
SOIL FOUNDATION SYSTEM FACTOR ( /3 ) 1.5
IMPORTANCE FACTOR (I) 2.0
EMPTY WEIGHT WITH WIND LOADING OR HYDROSTATIC WEIGHT
WITH SEISMIC LOADING.
HEIGHT AND NUMBER OF LEG SUPPORTS AND SIZE OF ANCHOR BOLTS
HOLE DIA = BOLT DIA +
SHALL BE AS PER ENGINEERING DRAWING.
MINIMUM BOLT SIZE SHALL BE M 20.
6rnn\ 91-11-E MAXIMUM INSULATION THICKNESS CONSIDERED IS 150 mm.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
MATERIALS SHALL BE AS PER ENGINEERING DRAWING.
EARTHING LUG SHALL BE AS PER STANDARD 7-12-0026.
SUITABLE PAD FOR SS VESSEL SHALL BE PROVIDED.
0--64
5 30.06.2011 REAFFIRMED AND REISSUED AS STANDARD POREL KT KM/SC DM
4 08.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Format No. 8-00-0001-F4 Rev.O Copyright EIL - All rights reserved
Page 378 of 704
BRACKET SUPPORT FOR STANDARD No.
orfr
ftemm uyirrED
ENGNEERs
IA Govt. of India Undertaking) VERTICAL VESSEL
7-12-0008 Rev. 5
Page 1 of 1
•
REFER NOTE-3
(SEE ENGINEERING
DRAWING)
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
NUMBER OF BRACKETS SHALL BE FOUR PER VESSEL
PAD THICKNESS SHALL BE AS PER ENGINEERING DRAWING.
FOR VESSELS UPTO 800 mm DIA. REFER ENGINEERING DRAWING.
5. IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
'6. DISTANCE 'X' IS TO BE FINALISED CONSIDERING INSULATION THICKNESS, BOLT SIZE AND ERECTION
REQUIREMENT AND SHALL BE KEPT MINIMUM.
7. EARTHING LUG SHALL BE AS PER STANDARD 7-12-0026.
SS HINGE
BAR
MIN 3 THK. WASHER
80 C' 4 GAP
BLIND
M16 FLANGE
80 SS COTTER PIN
WITH 3THK. WASHER
1-3mm NPT
-J 120 0
TELL—TALE HOLE U-
N
I-
0
1 110 0
M16
0
20 0 ROD
SEE NOTE-2
slue
HANDGRIP DETAIL OF JACK SCREW
di 0
BLIND FLANGE
SLOPE TO FIT
PERIPHERY OF
W.N. OR S.O. MANHOLE FLG.
FLANGE R
W.N. OR S.O.
II d10
R
FLANGE
MIA9111
BLIND FLANGE
NOMINAL G t d R d1 L
FLANGE RATING
BORE
400 298 28 35 55 36 42
450 318 28 35 55 36 42
CLASS 150
500 348 28 35 55 36 42
600 406 28 35 55 36 42
400 324 28 35 55 36 42
450 355 28 35 55 36 42
CLASS 300
500 386 30 35 55 36 42
600 458 30 35 55 36 42
400 342 32 40 55 41 47
450 372 32 40 60 41 47
CLASS 600
500 406 36 40 60 41 47
600 470 36 40 75 41 47
400 352 32 40 60 41 47
450 394 32 40 65 41 47
CLASS 900
500 428 40 40 70 41 47
600 520 40 40 90 41 47
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
WELD HINGE TABS AFTER TIGHTENING THE COVER WITH GASKET IN PLACE
AND MAINTAIN A LOOSE FIT OF HINGE BAR IN HINGE TABS.
BCD OF JACK SCREWS IS TO BE SUITABLY CHANGED IF MANHOLE
STUDS INTERFERE WITH JACK SCREWS.
IF SQUARE RODS ARE USED FOR HANDLES, THEIR EDGES SHALL BE ROUNDED OFF.
IN CASE OF CONFLICT, ENGINEERING DRAWING SHALL GOVERN.
ALL FILLET WELDS SHALL BE 6mm MINIMUM.
TELLTALE HOLE SHALL NOT BE PLUGED AND SHALL BE FILLED WITH
HARD GREASE ONLY.
THE MATERIAL OF COMPONENTS SHALL GENERALLY BE IS : 2062 UNLESS
OTHERWISE SPECIFIED ON ENGINEERING DRAWING. FOR LOW TEMPERATURE
SERVICES AND SERVICES ABOVE 425*C THE HINGE TABS AND HANDLE SHALL
BE OF SAME MATERIAL AS THAT OF SHELL.
20 0 x 25 LG. SNAP
HEAD RIVET
1
1
6R 15
1NO. 60
DRAIN HOLE
DETAIL 'X'
TELL TALE HOLE
BUND
FLANGE
IM16
jk4j6;.11?l''-
6 30.06.2011 REAFFIRMED AND REISSUED AS STANDARD POREL KM/SC DM
5 11.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
Page 382 of 704
Olar
STANDARD No.
ENGINEERS MANHOLE WITH DAVIT
geINIDIA LIAM 7-12-0010 Rev. 6
/A Govt. of India Undertaking)
Page 2 of 2
8
260 350
(320)
40R NP4,
10V
ti DETAIL OF HAND GRIP
HAND GRIP
141"
0
I
— 1°N
N 20 0 x 25 LG. SNAP
250 HEAD RIVET
// PIPE 'A'
il \\
// \\
\\\
1/ \\ \ I I
/ \\ I I 0
II 1111 I I
— 30 VENT
\ 11 II
I I // ) 0
\\ // F—R
\ \ s.
\\
\\
\\
.■...--
1
1
//
ii
//
//
Y
------_ --------------
1 15
3N0.—M16 SS JACK SCREWS
ON BOLT CIRCLE DIAMETER 1NO. 60 )
(SEE NOTE-3) DRAIN HOLE
DETAIL 'Y'
1 N0.-3mm NPT
TELL TALE HOLE
TOP OF DEMISTER
•!6!;!.9.■!VAtt;!..!..!■!•:•!.!•!..!•:•!..!•!....!•!•:•!•:•!..!•:•!
UM
DETAIL-X
HORIZONTAL VESSEL
V)
Z
7
CC TOP LADDER RUNGS EQUISPACED AT BOTH LEVELS O
o 2-NOS. FOR DIA. < 1000. 1=1
a"'
0
4-NOS. FOR 1000 < DIA. < 2000 I
cJ p) 1-
¢< 6-NOS. FOR 2000 < DIA. < 3000 0 W
—I I—
8-NOS. FOR DIA. > 3000 °
%.D
V) _j
HANDGRIP 175 175
350+1/2 MANHOL DIA. CU
MANHOLE
II
`1,
e) DETAIL-X
200
r DETAIL-X
F
175 175
HANDGRIP
NOTES
1. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
A 2. VARIATION IN SPACING BETWEEN LADDER RUNGS IS PERMITTED
IN CASE OF INTERFERENCE WITH SOME NOZZLE OR INTERNALS.
HOWEVER THE SPACING OF RUNGS SHALL BE EQUAL.
SQUARE RODS MAY BE USED FOR HANDGRIP / LADDER RUNGS.
IF FABRICATED FROM PLATE THE EDGES ARE TO BE ROUNDED OFF.
MATERIAL SHALL BE AS PER ENGINEERING DRAWING.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
ORIENTATION OF LADDER RUNGS SHALL BE SAME AS OF MANHOLE.
7. DIMENSIONS SHOWN IN BRACKETS ARE FOR STAINLESS STEEL MATERIAL. r
du
5 30.06.2011 REAFFIRMED AND REISSUED AS STANDARD POREL T AKM/SC DM
4 11.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose by
Convenor Chairman
No. by Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
0
1
5-
1-30 NPT TELLTALE HOLE
(REFER NOTE-7)
O
F—
NOTES
1. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
2. IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
C) 3. WIDTH IS MINIMUM AND SHALL BE CHECKED AGAINST CODE REQUIREMENT. CHECK REINFORCEMENT REQUIREMENT FOR
ALL EXTERNAL PIPING LOADING ALSO.
4. NOZZLE PROJECTIONS ARE BASED ON INSULATION THICKNESS EQUAL TO 75mm. FOR INSULATION THICKNESS
GREATER THAN 75mm, THE NOZZLE PROJECTION IS 'A' + [INSULATION THICKNESS(mm)-75].
5. PROJECTION 'A' FOR SELF—REINFORCED NOZZLE SHALL BE BASED ON DESIGN OF REINFORCEMENT SUBJECT TO
MINIMUM REQUIREMENTS AS PER THIS STD.
6. EXTEND PAD LOCALLY FOR MANHOLE DAVIT SUPPORT, IF REQUIRED.
7. EXTERNAL REINFORCING PADS SHALL HAVE A MINIMUM OF 1 NO. TELL—TALE HOLE EXCEPT THAT PADS FOR
NOZZLES GREATER THAN 10"NB(250NB) SHALL HAVE MINIMUM TWO NOS. TELL—TALE HOLES AND NOZZLES IN
EXCESS OF 36"NB (900NB) SHALL HAVE 4 NOS. TELL—TALE HOLES. PAD INSTALLED IN SECTIONS SHALL HAVE
ATLEAST ONE TELL—TALE HOLE PER SECTION. TELL—TALE HOLES ON REINFORCEMENT PADS SHALL BE
EQUALLY SPACED IN CIRCUMFERENTIAL DIRECTION OF PAD.
8. TELL—TALE HOLE SHALL NOT BE PLUGGED AND SHALL BE FILLED WITH HARD GREASE ONLY, AFTER
HYDROTEST/PNEUMATIC TEST OF EQUIPMENT.
9. o) FOR COLUMNS & VERTICAL VESSELS, PROJECTION OF NOZZLE ON TOP HEAD SHALL BE 400mm MINIMUM FROM
OUTSIDE.
b) FOR HORIZONTAL VESSELS, PROJECTION OF NOZZLES ON TOP SIDE OF SHELL SHALL BE 300mm MINIMUM FROM
OUTSIDE.
10. PROJECTIONS ARE BASED ON ASME 816.5 FLANGES FOR UPTO AND INCLUDING 24"NB NOZZLES AND ASME 816.47
SERIES 'B' FLANGES FOR NOZZLE SIZES ABOVE 24"NB.
.1 1
Page 1 of 1
HORIZONTAL VESSEL
(ELEVATION)
q_
VERTICAL VESSEL
(PLAN)
NOTES
ANY DEVIATION FROM THIS ARRANGEMENT WILL BE INDICATED IN ENGINEERING DRAWING.
BOLT HOLES TO STRADDLE CENTRE LINES INDICATED ( BY q. ) ABOVE.
I NO.-3mm NPT
TELL—TALE HOLE GLASS
tfl
15
GLASS
1 N0.-3mm NPT
TELL—TALE HOLE
39R
1110.-3mm NPT
TELL-TAIL
HOLE
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
TYPE OF SIGHT GLASS SHALL BE TOUGHENED BOROSILICATE AND SHALL BE TESTED
AS PER IS : 5428 / BS 3463.
FOR APPLICATION OUTSIDE THE LIMITS SPECIFIED ON THE STANDARDS, MANUFACTURER'S
PROVEN DESIGN FOR THE COMPLETE SIGHT GLASS ASSEMBLY SHALL BE USED.
UNLESS OTHERWISE SPECIFIED, GASKET MATERIAL SHALL BE COMPRESSED ARAMIDE GASKET OR
COMPRESSED FIBRE ASBESTOS—FREE GASKET.
THE INDICATED SIGHT GLASS THICKNESSES ARE MINIMUM. NEGATIVE TOLERANCE IS NOT PERMITTED.
REFER ENGINEERING DRAWING FOR TYPE AND MATERIAL OF NOZZLE COMPONENTS.
GLASS AND SEAT FACE SHALL BE POLISHED PERFECTLY.
9. PROVIDE GASKET ON EITHER SIDE OF SIGHT GLASS.
O.D.
B.C.D.
18 DIA. HOLES
FOR M16 BOLTS
THICKNESS OF
NOMINAL NUMBER FLANGE t
PIPE SIZE I.D. B.C.D. O.D.
OF BOLTS CARBON S. STEEL
(mm)
STEEL OR MONEL
40 51 110 160 4 16 10
50 63 120 170 4 16 10
80 92 150 200 4 16 10
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
* 3. FILLET SIZE IN BRACKET ARE FOR STAINLESS STEEL / MONEL.
FULL FACED GASKETS SHALL BE USED.
DIMENSIONS EXCEPT THICKNESS FOR INTERNAL FLANGES OF SIZE 25NB OR LESS SHALL BE AS PER
ASME 816.5 CLASS 150. FLANGE THICKNESS AND FACING SHALL BE EQUIVALENT TO 4 NB LANGE
COVERED IN THIS STANDARD. 2 14-4
5 30.07.2011 REAFFIRMED AND REISSUED AS STANDARD POREL AK / SC '' DM
4 11.09.2006 REAFFIRMED AND REISSUED AS STANDARD POREL DNN AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
Page 390 of 704
STANDARD No.
BsICNEERS
WA LIMITS) VORTEX BREAKERS 7-12-0019 Rev. 5
Man VIRINVINOMPINI (A Govt. of Indio Undertaking)
Page 1 of 1
to
4=1
w
0 50
z
50 FOR NOZZLES UPTO 250 NB
AND 80 FOR NOZZLES ABOVE
250 NB
TYPE — 1A TYPE — 2A
FOR NOZZLE NB 100
3D0
TYPE — 1B TYPE — 2B
FOR NOZZLE NB < 100
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
3.a) FOR ALLOY LINED VESSELS, THE BAFFLE MATERIAL SHALL BE SAME AS ALLOY LINING.
b) FOR CONCRETE LINED VESSELS, THE BAFFLE MATERIAL SHALL BE ALLOY AS SPECIFIED
IN ENGINEERING DRAWING.
REFER ENGINEERING DRAWING FOR DIMENSION 'B'.
DENOTES NOMINAL BORE SIZE OF SUBJECT NOZZLE.
W
L_
r=• ANGLE SIZE 'SI X IX TAPPED HOLE
o a- Z WITH M16 BOLT
In co
L. 0
N mw
ANGLE SIZE 'S'
DETAIL IN TOP BRACKET
SHT. 2 aq
TOP OF PLATFORM
I
HAND
RAILING
z
TAPPED HOLE 1
WITH M16 DOLT 8
PIPE cu
SIZE 'D' 1 DETAIL-70 0
DETAIL — W
, TOP OF
I PLATFORM
1.--1)DAVIT SUPPORT
HAND RAILING
4Q N
(TYPE-1) (TYPE-2)
65
DEVIT FOR TOP DEVIT FOR SIDE TO SUIT
MOUNTED PLATFORM MOUNTED PLATFORM PIPE O/D.
8-180 HOLES
A (MAX) B CAPACITY PIPE SIZE ANGLE SIZE R1 R2 r t EQUISPACED
Cm) (rim) Ckgs.) D S
500 100NBxSCH.160 75x75x6 75 60 10 20
1000 1000 150NBxSCH.80 100x100x8 110 60 12 25 160 LOCKING
I'2—
PIN
(Ci
500 150NBxSCH.80 100x100x8 110 60 10 20
2000 1000 200NBxSCH.80 150x150x10 140 60 12 25
0
0 LOCKING PLATE
:: 500 200NBxSCH.80 150x150x10 140 60 10 20
/.
3000 1000 200NBxSCH.160 150x150x12 140 60 12 25 DETAIL—X DETAIL—Y
R1
D (NB) D1
100 120
150 175
POSITIONING 200 225
PLATE
DETAIL—Z (DAVIT EYE)
DETAIL—K
DETAIL—P
4---
6 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL KM / SC DM
5 12.10.2006 REAFFIRMED AND REISSUED AS STANDARD POREL RKG AKM VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by
Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
—
EXTENSION ANGLE
DETAIL- —-
CHAIN
(MIN. 350 LG.)
REF, LEVEL
ISMC 100
ELEVATION
50 (TYP)
PLATFORM (NOTE-8
N\
DETAIL — Q
80
25NB SCH.80 INS. THK.
PIPE SLEEVE +300
030x10 THK.
PLAN (TOP BRACKET)
020 TURNING
12 THK.
REF. AXIS
in
170
17 60 15 25 10 20 17
to
2 CAPACITY KGS
NAME PLATE
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
NAME PLATE
MATERIAL STAINLESS STEEL 2mm THICK.
NAME PLATE IS TO BE TACK WELDED TO THE DAVIT PIPE.
THE LETTERS AND NUMBERS SHALL HAVE RAISED POLISHED FACE.
BACKGROUND SHALL BE BLACK.
DIMENSION 'A' SHALL BE SUCH THAT THE DAVIT EYE EXTENDS PREFERABLY BY 900 mm OUTSIDE PLATFORM.
REFER ENGINEERING DRAWING FOR DIMENSIONS A, B, C, E, CAPACITY OF DAVIT AND INSULATION THICKNESS.
THE DAVIT USED SHALL CLEAR HANDRAIL OF THE EQUIPMENT.
MATERIAL OF PIPE SHALL BE A-53 / IS:1978 OR EQUIVALENT AND STRUCTURAL PARTS SHALL BE IS:2062 GR.B
OR EQUIVALENT.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
FOR THIN WALLED EQUIPMENT, DESIGNER SHALL ANALYSE THE STIFFNESS OF SHELL AT THE BRACKET LOCATIONS.
DETAIL DIMENSIONS AND NOTES IN ENGINEERING DRAWING TAKE PRECEDENCE OVER THOSE SHOWN HERE.
LOCKING PLATE (DETAIL —Y), LOCKING PIN (DETAIL —X) WITH CHAIN, POSITIONING PLATE (DETAIL —K), DEFLECTOR
CONE (DETAIL—P) AND LOCKING SUPPORT CHANNEL (DETAIL —Q) SHALL BE SUPPLIED LOOSE BY FABRICATOR AND
WELDED AT SITE BY MECHANICAL CONTRACTOR.
ALL FILLET WELDS SHALL BE 6 mm MINIMUM.
FOR LOW TEMPERATURE SERVICE, BRACKET DETAILS SHALL BE AS PER EIL STD. 7-12-0034
13. IN CASE DIMENSIONS 'B' IS BEYOND THIS STANDARD, IT IS RECOMMENDED TO INSTALL PIPE DAVIT
ON STRUCTURAL PLATFORM.
t-/
-1(j491Ak.
6 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL KT KM / SC
DM
SECTION XX
BOTTOM OF BRACE TO TOP OF LUG F 200 230 300 400 500 600
BOTTOM OF BRACE TO T.L OF HEAD E SEE NOTE 2
T.L. OF VESSEL TO BOTTOM OF LUG B 200 230 280 350 400 480
C 30 40 50 70 90 100
TOP OF LUG TO Q OF HOLE J 90 90 115 150 180 230
K 30 40 50 70 80 100
NO. OF LUGS 2 2 2 2 2 2
NOTES
1. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
*2. DIMENSION 'E' IS TO BE DETERMINED BY THE SHAPE OF HEAD IN CONJUNCTION WITH DIMENSION 'K'.
DETAIL, DIMENSIONS AND NOTES GIVEN IN ENGINEERING DRAWING TAKE PRECEDENCE OVER THOSE SHOWN HERE.
FOR THIN WALLED EQUIPMENTS, DESIGNER SHALL ANALYSE THE STIFFENESS OF SHELL AT THE LIFTING LUG LOCATION.
IF PADS ARE USED ON STAINLESS STEEL EQUIPMENTS THE SIZE OF FILLET WELD BETWEEN SHELL AND STAINLESS
STEEL PAD SHALL BE ANALYSED.
MATERIAL SHALL BE COMPATIBLE WITH HEAD MATERIAL.
FOR INTERMEDIATE ERECTION WEIGHT, NEXT HIGHER SIZE OF LIFTING LUG SHALL BE USED.
LIFTING LUG SHALL BE MACHINED TO COVER OFFSET BETWEEN OUTER DIAMETERS OF SHELL AND HEAD.
N W.L o b
T.L
5 X COLD INSULATION
THICKNESS ( MIN 600MM)
a_
7
1=-J b
M12 SQUARE NUTS TACK WELD
ON INSIDE AND OUTSIDE OF PIPE G
SKIRT ‘111SUPPORT
SKIRT ON 450 TRIANGULAR PITCH
FOR FIRE PROOFING (SEE DETAIL-Y) ANGLE LEG
(REFER NOTE-8) SUPPORT
DETAIL—Y
SECTION 'C—C'
M6 X 25 LG G.I. BOLTS w 0
BETWEEN TWO CLEATS (TYP) w
AND NUTS. to z
AIR POCKET
6 THK. FLAT (FOR VESSEL TEMP.
10
ABOVE 400T)
3 THK.
ASBESTOS SHEET
10 THK. PLATE
VESSEL PART
tr.)
N
14 DIA. HOLE
(FOR M12 BOLT)
75 25
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
ALL EQUIPMENTS SHALL BE PROVIDED WITH TWO(2) EARTHING
LUGS, UNLESS OTHERWISE STATED.
3.(a) EARTHING LUGS SHALL BE LOCATED DIAMETRICALLY OPPOSITE ON
NORTH—SOUTH CENTER LINE ON SKIRT SUPPORTED EQUIPMENTS,
ON ANY TWO(2) LEGS OF THREE(3) LEG SUPPORTED VERTICAL VESSEL,
ON DIAMETRICALLY OPPOSITE LEGS OF FOUR(4) LEG SUPPORTED
VERTICAL VESSEL AND ON EACH SADDLE OF HORIZOTAL VESSEL.
TWO(2) EATHING LUGS ARE TO BE LOCATED ON EACH SADDLE OF
HORIZONTAL VESSEL OF LENGTH GREATER THAN 20 METERS.
FOR SPHERE, TOTAL 4 — NOS. OF EARTHING LUGS SHALL BE PROVIDED
PREFERABLY ON DIAMETRICALLY OPPOSITE AND EQUALLY SPACED LEGS.
(SPHERES ARE USUALLY PROVIDED WITH LEGS IN NUMBERS WHICH ARE
MULTIPLE OF 4 FOR THE SYMMETRY)
DO NOT WELD EARTHING LUG ON PRESSURE PART.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
6. MATERIAL OF CONSTRUCTION SHALL BE CARBON STEEL.
"CE
co
1
6 .. z 1-
Li,
I- u_
<
1- Y 0 E
0
<
E
—.1 csj
ce Zt
w
N m 1— L,_
o
w o
cc I _1
w 1— 1—
w Ww
I- 0 Y i—
o T I- 0 v)
a
w 0 IX V)
tr) L.LI CO U)
La 0 w
_1 __I Ix _I
D o C.)
1
Li -4Z
1—
cr)
E CD 6 C■1
°)
E < o LL.
Lo 1-- 1 o
Z a co w — N Li,
_1 CD CO
w _J 1
w < _1 N _1
< 2 J _1
V) < 0 <
(/) I CC I
Z 0 V-) < (1)
0 Z 0
U) o Lu WW..
1-- Z
<
0 ,- n
W
w ix
0 CL
V 0_
m
E cr
Y L.L1 L.Li LO
(/) _1
_I C<C) <
2 1- 1 . 1L "i
MI < CO Z O Z
0
Z .— C■I ri 4 6 tO
/ 11. , ^
4.0 0
2/Vvt'4
KT
5 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL 44.4) AKM / SC DM
4 12.10.2006 REAFFIRMED AND REISSUED AS STANDARD POREL RKG AKM VC
STANDARD No.
15iffazle ENGINEERS
e...111E1f5teg INDIA LIMI TED MANUFACTURER NAME PLATE 7-12-0028 Rev. 5
(llETI FIUME 115r3911771) (A Govt. of Indio Undertaking)
Page 1 of 1
I-
fY
CO
)-
W
_1
m
1.5
L...; V)
C.) o
Q 0_
Li_
I-
o o Li
w Z I—
=
La 5
Zi cc o_
0 Li)
a. = La
0
co
i a
M
—7"
Z I-
La La
I- VI 1..J La.
I- IX 0
fi)IX C E
t,_ ix
-J N
taJ
in 0 0 a u.
i—
W La 0
W 0
CZ CD I J
La I—
i— La
X - Lai La
1
I- -I
x
< I- 6 (n
'-
0
V)
0 0
w
< 0
ct)mw
Lai IX 0
-I ILI _i J
Z 0
= ix le
• I-Li
ce
0 z
LL 4'1
0 I 1-
E m -1 le a) V)
E 0 m .()
4 " L.
Z
z ,, 1.-
< m
0
1 o
N W
V) __I co
,_ m
La le ..„ I
IX 0
Q 0 i —I
< -J N _1
_1
_1 vi 4I 0 ..t
V1 m I cc Z
Z 0 in ..t v)
= ..:
v, Z o
Li) ce = Lai Z 1-61
Z Lai 0 I-
5 < I-
w
m
i— ce
1- 0 0_
1—
0 0_
5 L i
ICW
X
La La
2
Cl)-J
-J J () 4 < 2 Lu
ll- 41
I- < < CO Z IX Z
0
Z Csi Iii 4 ui (IS
,/0/49-4-1"/ 5/44-k
5 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL RKT AKM / SC DM
4 12.10.2006 REAFFIRMED AND REISSUED AS STANDARD POREL RKG AKM VC
0
—J
V)
10 R
BRACKET
NAME PLATE
0
r-
4-
N
EIL NAME PLATE
o 0:
+
N
0
N
0
MANUFACTURER NAME PLATE
<TYP
2V •
200
230
NOTES
I. ALL DIMENSIONS ARE IN inn UNLESS OTHERWISE STATED.
2, BRACKET MATERIAL SHALL BE SAME AS SHELL MATERIAL.
1"1' 0
125
M IS NAME OF MANUFACTURER
DESIGNED BY I I OWNER I
cs,
ITEM NO. I I JOB NO. I rs,
, P.O. NO. I I YEAR OF FABRICATION I
(.1
D in CODES I INSPECTED BY I ,
IN N. I
DESIGN PRESSURE I I DESIGN TEMPERATURE I
CORROSION ALLOW. I I RADIOGRAPHY I
cs,
TEST PRESSURE I I EMPTY WEIGHT I
rs,
4,st- I
4" DATE OF TEST I
el
5R
4.50 HOLE 2
28 26 28
BRACKET
NAME /
PLATE
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE SPECIFIED.
ALL LETTERS, BLOCKS AND BORDERS SHALL BE RAISED POLISHED FACE.
BACKGROUND SHALL BE BLACK.
NAME PLATE SHALL BE TACK—WELDED TO THE BRACKET. WHERE NOT POSSIBLE
IT MAY BE RIVETTED.
NAME PLATE SHALL BE OF STAINLESS STEEL OF 2mm THICK.
BRACKET MATERIAL SHALL BE SAME AS SHELL MATERIAL.
4
3
31.08.2011
12.10.2006
REAFFIRMED AND REISSUED AS STANDARD
REAFFIRMED AND REISSUED AS STANDARD
POREL
POREL
A41
KT
RKG
A.D‘>)
kAAr914/1"/
KM / SC
AKM
DM
VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
Page 402 of 704
SUPPORTS STANDARD No.
laftetitErsiGINEaS
dgar faMegvir INDIA UMIT1ED FOR 7-12-0032 Rev. 4
INET! meow =mom) to Govt. of India Undertaking)
INTERNAL FEED PIPE Page 1 of 2
SEE
VESSEL DRG. 00
TYPE—IA
100
VENT HOLE
(6+2xC.A.)
50 TO 75 THK. MIN. FLAT
AS PER
PIPE SIZE
I I '• 25 R
£
TYPE-1
INTERNAL FEED PIPE FOR HORIZONTAL VESSEL
SPARGER/FEED PIPE SUPPORT
NOTE TYPE—IA IS APPLICABLE FOR LARGE THERMAL EXPANSION (AIR / GAS SERVICE)
(6+2xC.A.)
THK. MIN. FLAT
TYPE-2
INTERNAL SPLASH FEED PIPE FOR HORIZONTAL VESSEL
65
15 0 HOLE IN PIPE CLEAT (6+2xC.A.)
& 30 LONGx15 WIDE SLOTTED THK. MIN. FLAT
HOLE IN SHELL CLEAT
SUPPORT CLEAT
FOR VERTICAL VESSEL
TYPICAL DETAIL OF BOLTING CLEATS
3MM
CLEARANCE
REINFORCEMENT PAD
(NOTE-6)
TYPE—A
(FOR PIPES UPTO 250NB)
TS
20 MIN. D (NB) 50
SHELL
11
II
REINFORCEMENT PAD L
(NOTE-6)
10 N•F
0.5G
If)
TYPE—B
(FOR PIPES ABOVE 250NB)
T
PIPE N.B. BOLT SIZE E F G
D CA=O CA=1.5 CA=3 CA=5 CA=7
50 — 80 M 12 6 10 12 16 20 60 40 60
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
IN CASE OF CONFLICT VESSEL ENGG. DRAWING SHALL GOVERN.
MATERIAL OF CLEATS SHALL BE AS PER VESSEL ENGG. DRAWING.
ALL FILLET WELDS TO BE ALL AROUND & SIZE OF WELDS ARE (6+1xC.A.) MINIMUM UNLESS OTHERWISE STATED.
ALL INTERNAL BOLTS SHALL BE MIN. M 12 SIZE AND OF STAINLESS STEEL WITH DOUBLE NUTS.
REINFORCING PAD SHALL BE LARGER BY 50mm ALL AROUND THAN BRACKET CLEATS. NO PAD IS REQUIRED FOR
VESSELS WITH WALL THICKNESS GREATER THAN 25mm.
)?•./
4 31.08.2011 REAFFIRMED AND REISSUED AS STANDARD POREL K 4/KM / SC DM
* 600
INSULATION 8 THK. LOOSE FLAT
THK. (S) * 8 THK. LOOSE 60 HOLES
FLAT RING *
eli 3—I AI
100
15
—I IF(TYR) I
loco
ti
II KT#
REQUIRED
FOR VESSEL
HAVING
FOR VESSEL HAVING DIAMETER DIAMETER
SEE DETAIL -Z ABOVE >2000
ABOVE 600 PROVIDE 30x6 THK.
CLEAT WITH HEIGHT EQUAL TO
INSULATION THICKNESS AT 600
CIRCULAR PITCH 100 LOOSE GALVANIZED
RING (TYP.)
6 0 HOLE
/AT 600 PITCH `B' 'B' 2NO. 6 DIA. HOLES
' I VESSEL PER SEGMENT
tINSIDE
Li
10 T.L FOR DETAIL-X
'A'
10
8 THK. RING IN
3 SEGMENTS
8 THK. T-CLEAT AT VIEW—`A'
1000 SPACING
(MIN. 3 PER RING-
FOR DETAIL-X ONLY) DETAIL—'Z' (PLAN)
DETAIL—'X'/ DETAIL—'Y'
(SEE NOTE-6)
0 I.D.
V1
1OR LOWER
GRATING
LOWER 0
120 HOLE GRATING
0 IN CLAMP 15NB SCH.40s
M10 BOLT PIPE SLEEVE
SUPPORT WELDED WITH
30 WITH NUTS
RING GRID I
90 M10 BOLT 30 0
0
DETAIL-V 60 SUPPORT
(REMOVABLE THROUGH BOTTOM) VIEW - tV1' 122
RING
DETAIL-W
* SEE GENERAL NOTE-4
(REMOVABLE THROUGH TOP)
TYPE-A
0 I.D.
UPPER
GRATING
C•1
50 t 50
0 11 ' Zl'
NOTCH
25X25
11 P,- A/11A
_I IBM=
!II!
1 411
14 30
4
14.
WELD
NOTCH 25 90
25X25
VENT HOLE 01250
(MIN. 4NOS.) DETAIL-Z
M 2 BOLT RETAINER PLATE
(MIN.) IN SEGMENTS
50 tl
50 r 50_
DETAIL- X DETAIL-Y
(REMOVABLE THROUGH BOTTOM) (REMOVABLE THROUGH TOP)
VENT HOLE 120 HOLE
DETAIL IN CLAMP
M10 BOLTS
FOR C 200 NO GUSSETS ARE READ.
TYPE-B WITH NUTS
FOR C > 200 MINIMUM 4 GUSSETS SHALL BE PROVIDED.
01250 (MIN. 4 NOS.)
40 WIDE x
SECTION X—X
TYPE—C
NOTES
1. THIS TYPE IS APPLICABLE FOR VESSELS WITH REMOVABLE COVERS.
2. GRATING FRAME AND HOLD DOWN BARS TO BE MADE FROM 25 X 6 THK. PLATE.
11
150
(
11211211114FAIPIWIIIIII%
111•30
1
4101. 1a1111111111
TABLE-1 TABLE-2
GENERAL NOTES
1. ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
2. DEMISTER TYPE AND MATERIAL SHALL BE AS PER VESSEL DRAWING.
3. ALL INTERNAL BOLTS SHALL BE STAINLESS STEEL, OTHER MATERIALS SHALL BE
AS PER VESSEL DRAWING.
4. WIDTH AND LENGTH OF EACH DEMISTER PIECE SHALL BE DECIDED BY VENDOR.
HOWEVER THE WIDTH OF EACH PIECE SHALL BE SUCH THAT THE SAME CAN PASS THROUGH
THE MANHOLE. THE LENGTH OF EACH PIECE SHALL NOT EXCEED 2.5 M.
5. ANY DETAIL SHOWN IN VESSEL DRAWING SHALL BE GIVEN PREFERENCE
TO THAT OF STANDARD.
6. WIDTH OF SUPPORTING RING SHALL BE DECIDED BY VENDOR BASED ON LOADING
7. DEMISTER PAD SHALL BE SUPPLIED SUITABLY OVER SIZED FOR SNUG' FITTING.
4 01.10.2013 REVISED AND REISSUED AS STANDARD GCPA., SC
K
3 27.01.2009 REAFFIRMED AND REISSUED AS STANDARD VPR RKG AKM SKG
MC
FL
NOTES: —
1. THIS STANDARD COVERS ALLOWABLE NOZZLE LOADS FOR PRESSURE VESSELS & COLUMNS ONLY.
2. EACH PROCESS NOZZLE OF VESSELS SHALL BE ANALYZED FOR THE LOADS PROVIDED IN THIS
STANDARD.
3. THESE LOADS SHALL BE CONSIDERED TO BE ACTING SIMULTANEOUSLY WITH INTERNAL/EXTERNAL
DESIGN PRESSURE. ALLOWABLE STRESS SHALL BE AS PER APPLICABLE DESIGN CODE.
4. STRESS CALCULATIONS SHALL BE CARRIED OUT AS PER WRC BULLETIN N0. 107/297. WRC 107
SHALL BE USED FOR NOZZLES ON DISHED ENDS AND WRC 297 SHALL BE USED FOR NOZZLES
ON CYLINDRICAL SHELL.
5. IN CASE OF FAILURE DUE TO WRC, FEM ANALYSIS / PD 5500 ANALYSIS CAN BE CARRIED
OUT TO ESTABLISH THE ADEQUACY OF PROVIDED CONFIGURATION.
NOZZLE MT ML MC
FA FL FC
SIZES
(Kgf) (Kgf) (Kgf) (Kgf—m) (Kgf—m) (Kgf—m)
(DN)
50 135 200 200 50 40 30
80 202 300 300 112 90 67
100 270 400 400 200 160 120
150 405 600 600 450 360 270
200 540 800 800 800 640 480
250 675 1000 1000 1250 1000 750
300 810 1200 1200 1800 1440 1080
350 945 1400 1400 2450 1960 1470
400 1080 1600 1600 3200 2560 1920
450 1215 1800 1800 4050 3240 2430
500 1350 2000 2000 5000 4000 3000
600 1620 2400 2400 7200 5760 4320
650 1755 2600 2600 8450 6760 5070
700 1890 2800 2800 9800 7840 5880
750 2025 3000 3000 11250 9000 6750
800 2160 3200 3200 12800 10240 7680
850 2295 3400 3400 14450 11560 8670
900 2430 3600 3600 16200 12960 9720
950 2565 3800 3800 18050 14440 10830
1000 2700 4000 4000 20000 16000 12000
1050 2835 4200 4200 22050 17640 13230
1100 2970 4400 4400 24200 19360 14520
1150 3105 4600 4600 26450 21160 15870
1200 3240 4800 4800 28800 23040 17280
1250 3375 5000 5000 31250 25000 18750
1300 3510 5200 5200 33800 27040 20280
1350 3645 5400 5400 36450 29160 21870
1400 3780 5600 5600 39200 31360 23520
1450 3915 5800 5800 42050 33640 25230
1500 4050 6000 6000 45000 36000 27000
NOZZLE
FA FL FC MT ML MC
SIZES
(Kgf) (Kgf) (Kgf) (Kgf—m) (Kgf—m) (Kgf—m)
(DN)
50 168 250 250 62 50 37
80 253 375 375 140 112 84
100 337 500 500 250 200 150
150 506 750 750 562 450 337
200 675 1000 1000 1000 800 600
250 843 1250 1250 1562 1250 937
300 1012 1500 1500 2250 1800 1350
350 1181 1750 1750 3062 2450 1837
400 1350 2000 2000 4000 3200 2400
450 1518 2250 2250 5062 4050 3037
500 1687 2500 2500 6250 5000 3750
600 2025 3000 3000 9000 7200 5400
650 2193 3250 3250 10562 8450 6337
700 2362 3500 3500 12250 9800 7350
750 2531 3750 3750 14062 11250 8437
800 2700 4000 4000 16000 12800 9600
850 2868 4250 4250 18062 14450 10837
900 3037 4500 4500 20250 16200 12150
950 3206 4750 4750 22562 18050 13537
1000 3375 5000 5000 25000 20000 15000
1050 3543 5250 5250 27562 22050 16537
1100 3712 5500 5500 30250 24200 18150
1150 3881 5750 5750 33062 26450 19837
1200 4050 6000 6000 36000 28800 21600
1250 4218 6250 6250 39062 31250 23437
1300 4387 6500 6500 42250 33800 25350
1350 4556 6750 6750 45562 36450 27337
1400 4725 7000 7000 49000 39200 29400
1450 4893 7250 7250 52562 42050 31537
1500 5062 7500 7500 56250 45000 33750
NOZZLE MT ML MC
FA FL FC
SIZES
(Kgf) (Kgf) (Kgf) (Kgf—m) (Kgf—m) (Kgf—m)
(DN)
50 135 200 200 50 40 20
d»71E. -gurg
Wf"kil 11
fqw
SPECIFICATION
FOR
ENERGY EFFICIENT
MEDIUM VOLTAGE
INDUCTION MOTORS
Abbreviations:
AL Aluminium
BASEEFA British Approvals Service for Electrical Equipment in Flammable Atmospheres
BIS Bureau of Indian Standards
BS British Standards
CEA Central Electricity Authority
CIMFR Central Institute of Mines and Fuel Research
CPRI Central power research institute
CT Current Transformer
CU Copper
DGMS Directorate General of Mines Safety
DOL Direct On Line
EIL Engineers India Limited
ERTL Electronics Regional test laboratory
FM Factory Mutual
FRP Fiber Reinforced Plastic
IEC International Electro-technical Commission
IEEE Institute of Electrical & Electronics Engineers
IP Ingress Protection
IS Indian Standard
JEC Japanese Electro-technical Committee
KLPL Karandikar laboratories Pvt. Ltd.
LCIE Laboratoire Central des Industries Electriques
NEMA National Electrical Manufacturers Association
PESO Petroleum and Explosive Safety Organisation
PO Purchase Order
PVC Poly Vinyl Chloride
RPM Revolutions per Minute
UL Underwriter's Laboratories
VFD Variable Frequency Drive
VDE Verband Deutscher Elektrotechniker
CONTENTS
1.0 SCOPE 4
5.0 PERFORMANCE 6
9.0 PAINTING 10
11.0 CERTIFICATION 11
1.0 SCOPE
This specification covers the design, manufacture, testing, packing and supply of energy
efficient-High efficiency (IE2) three phase medium voltage squirrel cage induction motors.
2.1 The squirrel cage induction motors and their components shall comply with the latest editions of
following standards issued by BIS (Bureau of Indian Standards) unless otherwise specified:
2.2 In case of imported motors, standards of the country of origin shall be applicable if these
standards are equivalent or stringent than the applicable Indian Standards.
2.3 The motors shall also conform to the provisions of CEA regulations and other statutory
regulations currently in force in the country.
2.4 In case Indian Standards are not available, standards issued by IEC/ BS/ VDE/ IEEE/
JEC/NEMA or equivalent agency shall be applicable.
2.5 In case of any conflict between requirements specified in various applicable documents, the
most stringent one shall prevail. However, owner's decision in this regard shall be final and
binding.
3.1 The offered equipment shall be brand new with state of the art technology and proven field track
record. No prototype equipment shall be offered.
3.2 Vendor shall ensure availability of spare parts and maintenance support services for the offered
equipment at least for 10 years from the date of supply.
3.3 Vendor shall give a notice of at least one year to the end user of equipment and EIL before
phasing out the product/spares to ensure the end user for placement of order for spares and
services.
Motors shall be suitable for operating satisfactorily in humid and corrosive atmosphere found in
refineries, petrochemical, fertilizer and metallurgical plants. Service conditions shall be as
specified in the motor data sheet. If not specifically mentioned therein, a design ambient
temperature of 40 ° C and an altitude not exceeding 1000 meters above mean sea Level shall be
taken into consideration.
Unless otherwise agreed, motors shall be designed for continuous operation at rated output
under the following conditions:
a) The terminal voltage differing from its rated value by not more than + 6 % or
b) The frequency differing from its rated value by not more the + 3 % or
c) Any combination of (a) and (b)
4.3 Starting
withstand time under hot conditions at 75% & 100% voltages, shall be minimum 1.4
times the starting time at the corresponding voltage.
d) Unless otherwise specified, all motors shall be suitable for starting under specified load
conditions with 75 % of the rated voltage at the motor terminals.
e) Motors shall be designed to allow the minimum number of consecutive starts indicated
in Table below:
Motors shall be suitable for either direction of rotation. In case unidirectional fan is provided for
motors, direction of rotation for which the motor is designed shall be permanently indicated by
means of an arrow. Directional arrow should be manufactured from corrosion resistant material.
When a motor is provided with bi-directional fans, a double-headed arrow should be provided.
Normally, clockwise rotation is desired as observed from the driving (coupling) end, when the
terminals UVW are connected to a power supply giving a terminal phase sequence in the order
UVW. Counter-clockwise rotation of the motor shall be obtained by connecting the power
supply to terminals so that the phase sequence corresponds to the reversed alphabetical
sequence of the terminal letters. Ample space shall be provided at the terminal box for
interchanging any two external leads for obtaining the reverse phase sequence.
5.0 PERFORMANCE
5.1 Motors shall be rated for continuous duty (Si), unless otherwise specified.
5.2 Unless specified, the starting current (as % rated current) shall be limited to maximum 600-
700% (based on number of poles and KW rating) as per IS 12615:2011, subject to IS tolerance
5.3 In particular cases, when the starting current is to be limited, care shall be taken such that the
design values of torque meets the load requirement while at the same time complying to clause
4.3 above of this specification. Unless otherwise specified the minimum pull-up torque of
motors, at rated voltage & frequency shall be minimum 50% of the rated full load torque.
5.4 In particular cases, when the starting with reduced voltage is specified, care shall be taken such
that the design values of torque meets the load requirement while at the same time complying to
clause 4.3 above of this specification.
5.5 Starting torque and minimum torque of the motor shall be compatible with the speed torque
curve of the driven equipment under specified starting and operating conditions.
In case where characteristics of driven equipment are not available while selecting the motor,
minimum starting torque shall be 110% of rated value for motors up to 75 kW and shall be 90%
of rated value for motors above 75 kW.
5.6 The breakdown torque at the rated voltage shall be not less than 175% of the rated load torque
with no negative tolerance. Unless otherwise agreed, the breakdown torque shall not exceed
300% of the rated load torque.
In case of motors driving equipment with pulsating loads (e.g. reciprocating compressors,
crushers, ball mills) the minimum value of pull out torque at 75% of the rated voltage shall be
more than the peak value of pulsating torque and the current pulsation shall be limited to 40%.
5.7 Motors fed by variable frequency drive shall additionally meet the following requirements.
5.7.1 The motors shall be suitable for the current wave forms produced by the power supply including
harmonics generated by the drive. The necessary coordination by motor manufacturers with
drive manufacturers regarding harmonics generated by VFD shall be taken care and
incorporated in motor design suitably.
5.7.2 The motors shall be designed to operate continuously at any speed over the range as per process
requirement with minimum range as 10-100% of rated speed or as specified in data sheet. The
characteristics shall be baked on the application — in terms of constant torque / variable torque as
per the driven equipment. Additional cooling fan shall be provided if required to limit the
temperature rise to specified limits, alternatively option of applying suitable de-rating may be
considered.
5.7.3 The motors shall withstand torque pulsation resulting from harmonics generated by the solid
state power supply.
5.7.4 The motors required to be transferred to DOL bypass mode shall be rated for specified
variations in line voltage and frequency.
5.8 The minimum values for performance characteristics of these motors shall be as given in the
tables 1, 2 & 3 of IS 12615-2011 for 1E2 motors, subjected to tolerance as per IS/IEC. Motor
meant for application with VFD, the efficiency value can be one class lower as per IS.
6.1 Windings
6.1.1 Unless otherwise specified, motors shall be provided with class 'B' insulation as a minimum. In
case of motors with class 'F' insulation, the permissible temperature rise above the specified
ambient temperature shall be limited to those specified in the applicable Indian standards for
class 'B' insulation.
6.1.2 The winding shall be tropicalised. The windings shall preferably be vacuum impregnated.
Alternately the windings shall be suitably varnished, baked and treated with epoxy gel for
operating satisfactorily in humid and corrosive atmospheres.
6.1.3 Windings shall be adequately braced to prevent any relative movement during operation. In this
respect, particular care shall be taken for the stator windings for direct-on-line starting squirrel
cage motors. Insulation shall be provided between coils of different phases that lie together.
Core laminations must be capable of withstanding burnout for rewind at 350 °C without damage
or loosening.
6.1.4 In case of motors driving equipment with pulsating loads, special care shall be taken for the
joints of rotor bars and end rings to avoid premature failures due to induced fatigue stresses.
6.1.5 The windings shall be connected in delta. However, for motors rated 2.2 kW and below, star
connection may be accepted. In case of motors with star-delta starting, the motor windings shall
be fully insulated for delta connection.
6.1.6 The ends of the windings shall be brought out into a terminal box. These shall be terminated by
means of terminals mounted on an insulating base made of non-hygroscopic and non-flammable
material.
6.1.7 All motors shall be provided with six terminals and suitable links to connect them in star or in
delta except for motors rated up to and including 2.2 kW which may be accepted with three
terminals.
6.2.1 Unless otherwise agreed, the terminal box shall be located on the right hand side as viewed from
the driving (coupling) end. The terminal box shall have side cable entry from non-driving end.
However, as a special case, terminal box located on top may also be accepted, particularly for
hazardous area motors, in case manufacturer has only top mounted terminal box design which is
duly tested/certified by CIMFR and approved by PESO for installation in hazardous area. The
terminal box design shall allow rotation in steps of 90 ° C to facilitate cable entry from any
direction at site.
6.2.2 Terminal box cover shall be provided with handles to facilitate easy removal. However, for
terminal box covers weighing less than 5 kg., terminal box covers without handles can be
accepted.
6.2.3 The terminal box shall be provided entries for suitable cable glands corresponding to the size of
the specified cable. Crimp type tinned Copper lugs and nickel-plated brass (or aluminum if
specifically required), double compression type cable glands shall be supplied along with the
motors for the specified cable sizes for power and space heater cables.
6.2.4 For flameproof motors, terminal box can be provided in increased safety `Exe' execution.
6.2.5 The terminals, cable lugs, terminal box, cable entries and cable glands shall be suitable for the
maximum cables sizes as specified below for 2 pole, 4 pole or 6 pole motors:
6.2.6 Cable sizes for motors having synchronous speeds 750 RPM and below shall be as agreed
between the purchaser and manufacturer.
6.3.1 The minimum degree of motor enclosures including terminal boxes and bearing housing shall
be IP-55 as per IS.
6.3.2 Motors for outdoor use shall be suitable for installation and satisfactory operation without any
protective shelter or canopy. Motor casing shall be provided with a suitable drain for removal of
condensed moisture except in case of flameproof motors (Type Ex d/Exde).
6.3.3 A11 internal and external metallic parts, which may come into contact with cooling air, shall be
of corrosion resistant material or appropriately treated to resist the corrosive agents, which may
be present in the atmosphere. Screws and bolts shall be of rust proof material or protected
against corrosion.
6.3.4 Unless otherwise agreed, motors shall have standard frame sizes (min.) for various output
ratings as stipulated in IS.
6.4.1 Motors shall have grease lubricated ball or roller bearings. In all cases, the bearings shall be
chosen to provide a minimum L-10 rating life of 5 years, (40, 000 hours) at rated operating
conditions
(The L-10 rating life is the number of hours at constant speed that 90% of a group of identical
bearings will complete or exceed before the first evidence of failure).
6.4.2 The bearings shall be adequate to absorb axial thrust produced by the motor itself or due to shaft
expansion. Motors designed to handle external thrust from the driven equipment shall be
supplied with a thrust bearing at the non-driving end.
6.4.3 In cases such as pumps for hot liquids where the driven equipment operates at high
temperatures, bearings shall be cooled by a shaft-mounted fan. This shall ensure efficient
ventilation of the bearing and disperse the heat transmitted from the driven equipment by
conduction or convection.
6.4.4 Bearings shall be capable of grease injection from outside without removal of covers with
motors in the running conditions. The bearing boxes shall be provided with necessary features
to prevent Loss of grease or entry of dust / moisture e.g. labyrinth seal/ oil seal/ V seal. Where
grease nipples are provided, these shall be associated, where necessary, with appropriately
located relief devices, which ensure passage of grease through the bearings.
6.4.5 Pre-lubricated sealed bearings may be considered provided a full guarantee is given for 4 to 5
years of trouble-free service without the necessity of re-lubrication.
All motors shall be self ventilated, fan cooled. Fans shall be corrosion resistant or appropriately
protected. They shall be suitable for motor rotation in either direction without affecting the
performance of the motor. If this is not possible for large outputs, it shall be possible to reverse
the fan without affecting the balancing of the motor.
For motors operating in hazardous area, the fans shall be of an anti-static non-sparking material.
6.6 Rotor
The rotor shall be of squirrel cage type, dynamically balanced to provide a low vibration Level
and long service life for the bearings. Die cast aluminum rotors for motors in hazardous areas
may be accepted provided the same are type tested and approved by competent authorities.
Motors shall be provided with a single shaft extension with key-way and full key. Motor shaft
shall be sized to withstand 10 times the rated design torque.
A11 motors weighing more than 30 kg. shall be provided with lifting hooks of adequate capacity.
Two earth terminals located preferably on diametrically opposite sides shall be provided for
each motor. Necessary nuts and spring washers shall be provided for earth connection.
All motors rated 30 kW and above shall be provided with 240 V anti-condensation heaters,
sized and located so as to prevent condensation of moisture during shutdown periods.
For motors with heaters installed in hazardous atmospheres (Zone - 1 or Zone - 2), such heaters
shall conform to the provisions of applicable Indian Standards and temperature classification
specified in the motor data sheet.
The heater leads shall be brought out, preferably, to a separate terminal box which shall be of
the same specification and grade of protection as the main terminal box.
A warning label with indelible red inscription shall be provided on the motor to indicate that the
heater supply shall be isolated before carrying out any work on the motor.
In addition to the motor rating plate, a separate number plate for motor tag number shall be
fixed in a readily visible position. This number shall be as per the motor data sheets.
The first actual critical speed of stiff rotors shall not be lower than 120 % of the synchronous
speed. For flexible rotors this shall be between 60 % and 80 % of the synchronous speed; the
second actual critical speed shall be above 120 % of the synchronous speed.
9.0 PAINTING
A11 metal surfaces shall undergo manufacturer's standard cleaning /painting cycle. After
preparation of the under surface, the equipment shall be painted with two coats of epoxy based
final paint. Color shade of final paint shall be 632 of IS: 5/ RAL-7035. All unpainted steel parts
shall be suitably treated to prevent rust formation. If these parts are moving elements, then these
shall be greased.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
10.1 All tests shall be carried out at manufacturer's shop under his care and expense.
10.2 The manufacturer shall submit all internal test records of the tests carried out by him on the
bought-out items, motor sub-assembly and complete motor assembly.
10.3 The manufacturer shall carry out the following routine and acceptance tests as per applicable
Standards/ITP on all the motors.
a) Visual check (Nameplate, terminal box location, terminal type, clearance, size, entries,
space adequacy & gland size, direction of rotation etc.)
b) Dimension check (shaft height etc.)
c) Cable glands, cable lugs size and no. of entries in terminal box.
d) Winding resistance
e) No load test & measurement of voltage, speed, current, power input
f) Measurement of starting torque, starting current, full load torque, breakdown torque
g) Reduced voltage starting & running
h) Insulation resistance before and after high voltage test
i) High voltage
i) Vibration
10.4 The manufacturer shall submit the following type test certificates (one sample from each
type/rating):
a) Full load test & measurement of voltage, current, power slip, power factor, bearing,
noise
b) Efficiency & pf at 100%, 75% and 50% load
c) Temperature rise test
d) Momentary overload test
e) Vibration
f) Noise Level
g) Over speed
h) Measurement of starting torque, starting current, full load torque.
10.5 For VFD fed motors, all tests as specified in the VFD specification shall be followed in addition
to the above.
11.0 CERTIFICATION
The motors and associated equipment shall have test certificates issued by recognised
independent test house (CIMFR/ CPRI/ ERTL/ BASEEFA/ LCIE/ UL/ FM/ KLPL or
equivalent). All indigenous motors shall conform to Indian standards and shall be certified by
recognised testing agencies. A11 motors (indigenous & imported) shall also have valid statutory
approvals (e.g. PESO, DGMS etc). as applicable for the specified location. All indigenous
fiameproof motors shall have valid BIS license and marking as required by statutory authorities.
A11 the equipment shall be divided into several sections for protection and ease of handling
during transportation. The equipment shall be properly packed for transportation by ship/rail or
trailer. The equipment shall be wrapped in polythene sheets before being placed in crates/cases
to prevent damage to the finish. Crates/cases shall have skid bottom for handling. Special
notations such as `Fragile', `This nide up', `Center of gravity', Weighe, `Owner's particulars',
`PO Nos.' etc. shall be clearly marked on the package together with other details as per purchase
order.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL - All rights reserved
The equipment may be stored outdoors for long periods before installation. The packing shall
be completely suitable for outdoor storage in areas with heavy rains/high ambient temperature,
unless otherwise agreed.
c-)
CD
6 CD
CD
CD
0.)
3
0.
0.
so.
o.) (4)
0 a
a
A
7
p anssl -e p ue pes! Aa8 L OOZ Z 117Z
0
7
CD
panssl -e p ue p es! Aej L. OZ10 . 91.
(f)
C)
0
CD
0
N
CD
CD
CD
0
0
p a nssi -e p ue p asha){ 41. 0Z *6040
-I
<
0
m
1—
m
E
E
>
9- nab Z£01.- 1. 8- 9
1-
>
Z
m
-n >
C)
—z
gl)
u)
m
0
ON NO LLVOI3133dSOINONVIS
-
• • • • • -
•
4
eD cd >
, .)
- (m.:Inn(-) to
t-`71 E E-)" (") "id --3 "ri rd 5 rd n 46;4 > ci)
.0 4(7- r.;
(") --] H Emi rri ,t cA
toaq qy
co
co
,7z2, El
rd
e►
g rTi
►
r) '-r1
r) >
:su o
O
ml
0. A9 21 L3 - 1. 000-00-8'oN
ADZ
t--' pj' = ,.,. = = = t., *T1 "r1 -7-1 cri rz, trdinnnno::i>to> r=r-r,
mi- -I —
..-0- • -AD0
a- •-•- - . w
rn
PvelIP31A1•11A1
Inspection Standards Committee
• tri
= = = -t = o 4 '6' . (I) (I H 1.,0 c4 6. = •- mh co -0 cD
rn, ig. ((i)-) (.7. P■ a
t , -, -4 0 ,, =4
= .. = 0
-, 5 0
., 0,
-, c, H -• =. , L,-
•-•• -I crq H a y — CD — .-- • AD
cn 0 .- • , C./)
2 = v9 Q- c4D ,..1.) CA
cn •-••- '-•) = 0
/2„, 7.... CM e,
-0 0 c--t
0 0 m ,--,' ("") CD
. ct 4. 6 . "d -4 a, ,....3 Gig PD) rri P '1
= 0 = CD 5. , 4
CM Fi . = i,-7. C"'' AD z-CD-) .
AD E' m-
cn 5- • 5 5' ,
= Crg
c, Fir (.1)
.... cf):1•- 0
n FD . Crg =
.Z'. "
-t
O P cr CD
5, oP v) rrl
(-) co Fr
o -1
AD FD s3- 0
fm,
0 - ,
-'•
co ,? 7dF- c- l .
CD 7' cn C'"
C AD
co - •
AD m
5' ..0)
0 ■=r
=-• 0
m cn
co 13
0
E -4
5
o z
- 0 2
cr • I p3
?-17 0
m
m
• Cn
0 -I
C4 -0
r" .0 .0 r" ■mmi r) < P:J Er,I CD rl C7 '71 cp 'd
'17 n 7d 0 H
0 4 Cn
4
5>"
0 CD CD C1/
=
=
CL .1
■—t- ■—• .
■-1
cn .-t 0 •-t-
4- CI: P.4- 0 0 -8
ca. CZ
cD a t. rD
. 0 Po ca,
t/D 1 -.. < .... = CD _
0 ,ty m n - < IDD CL 0 !ZI
t--4 = co
b-• ; CP4 u "
.--, 1 . = IDD - AD —
(-) = CD c" D' F. , , . 9. cn
F--> . , — -0 ‘< 0 =
CD mt 0 •-t-
• CD AD m co an =` X ■-r
4-3 0 ='' 4-1 = AD TZ
Jam) asegoind
md S
• E., ?„? r- (44. v, F;
o AD ■-• '0 0 -- Cr ismD- DI. CD
= -0 0 CD ..1. •.:.1.• '7 i
1'0014 03B I ELI O1T 01\1
C<- PD `I = 0 G0 0
-,. ■ -• • cl,
O 0 :R. • = cD 01-. 0 w < CD
rd 0 AD O. CM CD = m CD
1AI
cD C./) 0
■- •• Z Au
'< '0 2 > .-'---h 1
co C "• = CD
peaH uogons ong!sod Tax
= AD En m cfp uct o 0
CD ■-- • 0
co pa
e-+
co k.. -
(-)
=
o •-,. '-< = -I
AD 5 a. CR
Pp 0)
O a = tCD
= CD
N N.)
-• 0
O 0
0)
g•neu Z£0 - b8-9
0
'ONNOLLVO I3103d S ONVONVIS
D
0
m
z
5
cn
--1
I-
--1
z
m
—I
z
z
cn
c-)
>
-
9-A81:1 Z£0V L8-9
-1 O
-n
>x
0
Cn
X
0
g
0
m
—i
v
_
E
E
m
I—
"0
Oa
a)
0
0
n)
(.0
Fa
0
This InspectionandTest Plancovers theminimumtesting & inspecti onrequi rementsof threephasemediumvoltagesquirrel cage inducti onmotors .
n
4
ril
O
-i
m
n
g
g
z
i=1
,
PO/PR & Standardsreferred therei n/ Job specifications/Approved doc uments .
simawallm Oni 1S11 (my NOLLD IJSKI
SCOPlEOF INSPECTION
SL QUANTUM
STAGE/ ACTIVITY CHARACTERISTICS RE CORD SUB
NO. OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
7::::+
I■A
Proced ures
1
1
1
1
1
2.0 Material I nspection
RawMaterial :
Body(castingor fabrication), Material Test
Chemical ,Physicalproperti es, finish
=
100% Certificates /
IN)
asperrelevant standard
Insulationmaterial,Bearings,Terminals, Testrecords
Cable boxes, Cableglands,etc .
N"--:'
W
MotorAssembly
,
■
e
balancing,Terminal boxmountingand
I
SL
4.0
_4,
NO.
Q
4
2-,
0
.-,
0PzJ
.5-,
'-'•
0
Fi nal Inspecti on
Motor(Type Tests)
0(,)
r7
V)
,.....'
STAGE/ ACTIVITY
• • • • • • • • • •
< Z 5 a 7v r''' 5 < Z R n '8 e-9 S Cr •
. . ..... :-, p ,• ,..4_ (70" CD (:)
<
64 • 6-Q- • c..) == a ci-.) -= -,-
--1 = =" — 0 Cr ■er ..C) ai Z
SW '-'" '-'• f-F AD 0 CL CD ■-• • ::0 ...-. po
C - =° A) -
...7..
7'•
L.,. < = C)
F4 CPP
0 5-
0 < a CL Cr,.CqD P
01. b- onv) = 00 °'0''
2
,,— ,—, ... CM =
50% load
=
Vibration
PO c4 (71) r-t. $'3)7' 5 co ‘-‹ co cc) ,-F =
a Fp' ,-, < 0 0
Noise Level
XI " = c4 r) R° - 5. co
q CfQ co 0 ,--, 7.0 a ? Fo- V) CL s:__., c/D ‘?
CD CD cr Pr 0 CD P .--, •
,- Al " = ..- N ■-1- ,----,
Temp Risetest
= cn .-- • • ' cA) lo CD Z
Ej F)
(i) trq H
R) (i)
i:1" = o CD
c/) ,__) = $1)
.--r = C/) (4 n = CD , a p
= tt •
o ,-, = frw'o /o .-I co ,---, (/) ,...r. rD
co fa) q (c)
CD CA . N.. =1
cD • P 'ICI
MI = = - y) - -
., / ES.
co trc 5 cm P tz) (4 ;Cs F.D4'
B', • 0 A) (c) =)
Momentaryoverload test
.'" "
1:1) '17 ci) =. ''''• '0 co
co
" = o co gi (91 • crg . co"
CHARACTERISTICS
•-1 C) 0
`.' "1 0
•
'CS 3 .....
.Q) c,
C)
-,SI)
,-+ 0
p n c::"
5- g. -ti
CfQ
QUANTUM
CT'
OF CHECK
c , 5
• • • •
-, ts
co co CD
" ioc,co
00 0 g
o '"-.
-t 6
o 5.
0- ta. =
vt = v, ,.
RECORD
F'D 0
et
...,-
v)
-,
t t
SUB
SUPPLIER I
X
SUPPLIER
C/) C/)
9- "t au ZEOL- L13- 9
,
t....) CD (4.) CD
co
R° z R° z
'ON N OLLVO IJ133d SaavaN vis
4=, 2, - 4. 2,
o
EIL/TPIA
o
pa ' esai sp.1 6!-I II V - 113I4 6p Ado0
SCOPlEOF INSPEC'LION
Z
0
I 0Z
>
-1
Cl)
D
0 z
-rri
Cl)
E '6
9. nati Z£0 1.- 1. 8- 9
r' -n
>
Ci)
O
C)
•
E
•m
<
th
cn
0
—
SCOP1 TION
SL QUANTUM
STAGE/ACTIVITY CHARACTERISTICS RECORD SUB
NO. OF CHECK SUPPLIER EIL/TPIA
SUPPLIER
Overspeed
Measurement of Starting Torque ,
Startingcurrent , full Load Torque ,
Pull outtorque byJEC *
5.0 Painting
Visual
Suitableprotectiontoprevent entry Packing li st/
of foreignmaterial . 100% Supplier' s
Paintingand Packing
—
v,
1
1
Properpackingtoprevent any Records
damage duringtransportationand
storage .
6.0 Documentationand IC
• • • • • • • • • • •
Reviewof Internal Test Reports
Testcertificate fromrecognized
testing laboratory forarea
'—:
or—t-
CD
FD
0 "10
cn
CA
Conn=
classification.
ta.
"
BIScertificate for FLPmotorsand
011
.--' •
0
rD
accessori esasapplicable .
x
x
0
c)
r-t-
Documentationand IC
—
cp,
i
'..'
PESO approved certificates for
Fij •
e-... --..
motorsand accessori esas
CO
pa o
=
■.-i• `—'
rA
applicable .
F.).
-•
:It
CD
cD
0
Degree of protectionof enclosure
IC issuance
Final data
Compilationof Inspectionreports, folder/
x
Final Documentsubmi ssion 100%
01
i,....)
1
drawings,etc .asper VDR / PR Completeness
certifi cate
IsJ
CD
O H CrtD
4
0 C
CD rn
0 CD H c4
"1:23
. 0
C (7) o
CD
co • CD
(74 rD O_
0 co
a a. CD
°
cn (4 O g
;7)
$11 CD
0 'CS
C • "
CD
CD "CS pa
co o ,:•-•"'
co C 0
CD
CD e-•
a.
0 • pC1
C CD
a
cn <
;I) —•
co
fao CD
0 • PZI
C
co 's
CL
co 7t
(/)
AD AD
CD
0 CD cl
• 0
CD
-o
C)
C
co CD
C
(4
0 0
Cr -0
co
`CI
C)
(1)
0
-C
CD CD
0 0
AD
0
0 CD
C
C)
"CI
0
C
'1
IDD
co C)
0
0 C)
C C
CD
co
C C
c/)
(4
C
0
cr
co
$1,
-0 CD
CD
0
C-
g•n et! ZE O6- 68- 9
C
- Samplesmust includemi n .1Noofeachtype),
"ON N OLLVOl d103 dS 421VONV1S
CD
lD
0 co
7' 03
• c
3
O3
("
7 u)
• 0
o.
a
• al
0 o.
o a.
co
co
z
io
01
-•
C-
z
C)
O
0
031198132iaNVC13S1A321
m
m
zz
cn
cn
Cl)
-o
cn
cn
cn
m
m
0
m
0
0
0
0
z
z
z
C
z
z
z
z
ti'net' 6000-ZS-L S)INVI aNv S3dIdaNVIS"I3SS3A NO NO1103NNO0 INMAIMILSNI
.oN altIVCINVIS
4" 3"
.oN aavaNvis
3" 2" 3" 2"
O
O
UNCLADDED EQUIPMENTS CLADDED EQUIPMENTS
INSTRUMENT
F'
EXTERNAL DISPLACER LEVEL INSTRUMENT ON EQUIPMENT 2" FLGD. 2" FLGD. 3" FLGD. FLGD. 2" FLGD.
,—
EXTERNAL DISPLACER LEVEL INSTRUMENT ON STANDPIPE 2" FLGD. 2" FLGD. 2" FLGD. FLGD. 2" FLGD.
N
EXTERNAL GUIDED WAVE LEVEL INSTRUMENT ON EQUIPMENT 2" FLGD. 2" FLGD. FLGD. 3" FLGD. 2" FLGD.
,4
EXTERNAL GUIDED WAVE LEVEL INSTRUMENT ONSTANDPIPE 2" FLGD. 2" FLGD. FLGD. 2" FLGD. 2" FLGD.
EXTERNAL MAGNETIC LEVEL INSTRUMENT/ GAUGEON 2" FLGD. 2" FLGD. FLGD. 3" FLGD. 2" FLGD.
EQUIPMENT
4" 3"
EXTERNAL MAGNETICLEVEL INSTRUMENT/ GAUGE ON 2" FLGD. 2" FLGD. FLGD. 2" FLGD. 2" FLGD.
STANDPIPE
CA
EXTERNAL BALL FLOAT LEVEL INSTRUMENT ON VESSEL 1 2" FLGD. 2" FLGD. 3" FLGD. 3" FLGD.
-.4
C4
4t
* 1
CA
V1
4t
o.r
0.
INTERNAL DISPLACER / FLOAT LEVELINSTRUMENTS 4" FLGD 4" FLGD 4" FLGD.
I
INTERNAL GUIDED WAVE LEVEL INSTRUMENT ON EQUIPMENT 4" FLGD. 4" FLGD. 4" FLGD.
I
MAGNETIC LEVEL INSTRUMENT/ GAUGE(INTERNAL -TOP FLGD. FLGD. 4" FLGD.
I
MOUNTED)
C/1
n
P
C4
xJ
4k
qt
.:
'
VI
'.
cA
P
SPECIAL LEVEL INSTRUMENT ON EQUIPMENT (CAPACITANCE 2" FLGD. 3" FLGD. 2" FLGD.
1:.
'
PROBE/ULTRASONIC PROBE/R.F.PROBE)
"
1/4 " SCRD.
4 t
C7
2 " FLGD. 3" FLGD. 3" FLGD.
to
01
r)
P
e.
xJ
:
CA
CA
4t
D.
',
CA
4k
>::'
cA
(NOTE-1)
4" FLGD. FLGD.
EXTENDED DIAPHRAGM SEAL D.P. INSTR/ GAUGE ON VESSEL
1 4" FLGD.(NOTE-1)
0•AaH L3 1000 008coN lewio pemasei sp4 61.1 11V—113146p4d00
O
O
6
4:■
CD
UNCLADDED EQUIPMENTS CLADDED EQUIPMENTS
oP
2 ci)
INSTRUMENT
TYPE OF INSTRUMENTS
EQUIPMENT/STANDPIPE FIRST BLOCK EQUIPMENT/STANDPI CONNECTION
FIRST BLOCK VALVE
CONNECTION VALVE PE CONNECTION
r)
Z
.1
-<
Ch
d
•—•
CI)
:4:,
DIP TUBE LEVEL INSTRUMENT 6 " FLGD. 6" FLGD. %" SW (BY INST)
7
;:.:`,
i..,7`
t,)
z
.:
;:s.,,-
d
0
P
SF.
C.4
._,
(—)
CI
TANK LEVEL INSTRUMENT (MECHANICAL) 11/2" FLGD (BY
■
1
INST)
t,..)
,—.
TANK LEVEL INSTRUMENT (SERVO) ON ATMOSPHERIC TANKS 6" FLGD. 6" FLGD
1
r..)
N.)
.
t
(CLEAN SERVICE)
:I"
t•-.)
TANK LEVEL INSTRUMENT (RADAR) ON ATMOSPHERIC TANK 24" FLGD. 24" FLGD.
■
i
(VISCOUS SERVICE)
t,..)
TANK LEVEL INSTRUMENT (RADAR) FOR PRESSURISED 8" FLGD. 8" FLGD. 8" FLGD.
J
1
EQUIPMENTS
9,
1,-)
TANK LEVEL INSTRUMENT- CAPACITANCE / ULTRASONIC/ RF 2" FLGD. 3" FLGD. 2" FLGD.
I
TYPE ON ATMOSPHERIC TANKS/PRESSURISED EQUIPMENTS
t•-1,
7-4
.
',1
c,
9°
2
t,
N.)
lt
--11
..e
4,L
1:0
i-i
t:C
CJ
PRESSURE INSTRUMENT/ GAUGE ON VESSEL 3" FLGD. " SCRD
l'j
''''
_
..I'C'
<
I.)
c.,
C)
>:....
....,
7t
CA
C4
4t
4t
PRESSURE INSTRUMENT/ GAUGE ON STANDPIPE %" SCRD
!'''
C/1
ZF:
C)
,...)
...
d
CHEMICAL SEAL PRESSURE INSTRUMENT/ GAUGE ON VESSEL 2 " FLGD 2 " FLGD 3" FLGD. 3" FLGD.
:-"
l...7
DIAPHRAGM SEAL PRESSURE INSTRUMENT /GAUGE ON VESSEL 2 " FLGD 2 " FLGD 3" FLGD. 3" FLGD. FLGD.
tr.,
!‘"J
I
t
FLGD
.L.,
l....,
MULTI-POINT TEMPERATURE ELEMENTS FOR TANKS 3"FLGD. 3" FLGD. 3" FLGD
I
1
L
..4..
LA.>
I
o
o
l...J
.tit
.
t
■
ALL FLANGES/SW RATING SHALL BE AS PER PIPING SPECIFICATION UNLESS PROJECT SPECIFICATION REQUIRES MIN . 300#.
IN CASE OF DIRECT MOUNTED FLANGED INSTRUMENTS AND WHERE FLANGEDTYPE FIRST ISOLATION VALVE ARE PROVIDED, BOLTING AND GASKETSSHALL BE IN PIPINGSCOPE.
INSTALLATION OFSTLL WELL OF TANK LEVEL INSTRUMENTS (SERVO, MECHANICALAND MULTIPOINT TEMPERATURE ELEMENT) ON TANKS ARE IN TANK VENDOR SCOPE.
cm
FOR ANY OTHER INSTRUMENTS NOT REFERED ABOVE THE CO ECTION DETAILS SHALL BE AS PER PROJECT REQUIREMENT.
It
CD
a
CD
m
cr m
P `)
0.
c
a SD gu
0 w
7 0
= coa
C a
O
CO
7
7:1
O
C1311SSI3NCINVCI3SIA31:1
0
2
z z
NJ
agnssial ONVCl3SIA321
O
zz
C)
W
0311SSI32i aNYCI3SIA3e1
0
45.•
V
m
m
-a
-o
Cl)
C)
C)
cn
0
0
0
C
z
z
z
z
ti"AON Z000-ZS-L S3cIld NONOIIO3NNOO
'oN ativaNVIS
0 00 rn J. 1,1
11
113131AI MOTH
Cb
t21
31770N/121111N3A
C
..... .-
1":! :',,.: w 2,,'
. uo .,■'
;7;7 ;.1'7
. .11 :37:
on on -1 CA .1 "Irl LO
-ri r) n r- n
n
r r- p0
r- . r- .
CD CD X CD 70 CD CD 70
C7 C7 C7 C7 u 0 C7
'A" FLGD
P P * * • * *
A" SCRD*
PROCESS
CONNECTION
...
2" FLGD.
::37
,
." ,■'0 1:".- . 1
''-!
''. W ';',7
, 7
3 3
on C4 n1 cn "< -in. nn GO
r) (-) r- n 2 r- . r- . n
r- Pc C) 7o ,,, 70
CD C7 0 CJ 0 --3 C)
VALVE
C)
'A" FLGD
* * • * ...-, 0
'A" SCRD*
.- .-
;:r. ;;F: w ,":3: u'.3 w w
,',7, Z.7
.. .3: 1
LO Ln n1 LO hl nn nn
nn "T1 n r) ,-. r) r- . , , t-
r-
c) r"
C 70 ,
0 x 4
C C) C)
2" FLGD
P P :.- P C7 C7
'A" SCRD
T
'A" SCRD
C) P
WHERE PIPINGCLASS RECOMMENDS
CONNECTION
FIRST BLOCKINSTRUMENTS
SCRDCONNECTION ..
-- -.
3 4, .":,:f.3 Qa ;.„.:' ;;;.7
. 3
7.7
;:',7 ::...7 .3 l'.̀
.
'
.
I. Go Go ' on " Ln „ 3 1
r-
P, p ,1 -,1 r) (-, -1
r- il (::J c E E P:, El
c) c
P P 1..- P 0 u a • P„ u
__
2" FLGD.
t! ...! :37
LO C4 vu ...‹ . 3 3 l'' ,;,Z
!..,',.
r- 1` P2 2 P P. P. cc on a
C) aa 65 0 tr- cn C 0 C C
Y2" SW
%" BW
VALVE
P -3 0 CI c
'A" FLGD
P l'
-'i C
INSTRUMENT CONNECTION ON PIPES
... ...
;.. .c ..;‹ ^': ;;;Z, W. ,,;.r w w w ua La ;')..7.
cn cn -n un -n .-1 .:1 .11 ce,
n (..) r- () r- r- r- r a ()
r- r" 7s pD3 C) xi C) C) C) C) C) 20
2" FLGD
0 C) C7 C7 C7 C7 :7 0 C7 C) V Z7
'A" SCRD
'A" SCRD
'A" SCRD
C7 P
'ING CLASS RECOMMENDS
CONNECTION
FIRST BLOCK INSTRUMENTS
BW # CONNECTION
..- --
:;"‹ 1",
! .
"3:,
'
. (J'i '33! w Is: ;:37 ;:',,.'
3 ;73'-
,
t137, 1 „ 3 :
nn ,, .., nn nn
-n n1 'f=";
r r r r r r =" c4
c)
c) c c
r0
c c o c) i,-i x c)
2" FLGD.
0
'A" FLGD
Puuoc) *uu
'" SCRD*
P P
PROCESS
'A" SCRD**
CONNECTION
'
c
'A" FLGD
A" FLGD
c :.--, C7 .-.- C7 C7 0 0 C) C7
'A" FLGD
p
CD
CD
NJ
0
- --
." ;.',.7. ;.,u. ;.;,-, L'..! t'f< '"i. w L., 3.,..t L..) ::;.7
.
„ nn C n1 ni=1 -.6 h6 -.6 ,,
h,
.noN Z000-Z9-L
r c) C) c c C) C) x
.1
2" FLGD
c-) C7 p C7 ? C7 Z7 C7 C7 p
'A" SCRD
'A" SCRD
'A" SCRD
0 P
CONNECTI
VALVE
'0 Oa -4 ON to 41. Lo t,
..) --
C
lewiod
(.01 4:a. L.)
<5>
ORIFICE
(FLGD ) <5>
+ + * 4t * "Iv . .; > "11
FLOW METER
FLOW METER
ORIFICE (DIA-
THERMOWELL
* X'-'-rO
PHGRAMSEAL)
+
SEAL PRESSURE
rrI '-3 CM'X
c4 .,„
cn > E.-;) "il >
DIAPHGRAM SEAL
/A V
FLOWMETER ++
TYPEOF
INSTRUMENTS <5>
c:r"rn ; Z cs O,
XJ .-< C, CD
# 009 <
INSTRUMENTS
0'AO/AL3-1000-00-8
#009
7r ii 0 --] CA m = -1 ' -7.,. 12 -4 xt 4k
AVERAGINGPITOT TUBE
DIAPHGRAM(CHEMICAL)
_PRESSUREINSTRUMENTS
PRESSUREINSTRUMENTS
rZ,..,-1:1 cliF5S2c4=
3" FLGD
3" FLGD.
3" FLGD.
'A" SCRD*
PROCESS
*
3/4" SCRD**
%"SW/BW#
c) ,_ n(-) 24=z 0 a
IT' ,...., .n C: r- m , -1 > H
r- crl
CONNECTION
cA
cn (4 0 -cl H
m= m m
-orri c zz, r- aa Ca
-tlz HcA P'' 0
VALVE
3" FLGD 6a
3" FLGD.
3/4" SCRD*
*
3/4"SW/BW#
OH P V V
FIRST BLOCK
(4,
(BY INST)
z r-n1 0
CLADDED PIPES
(n r- Z (4
Y>rcxr) 4c4Mm -
r q m >n -3 ,;;Z: 7. t...,.■
m M2Z"-j= cn ^ri
cn xJ -000 m
n ,-ri r) r
c ...›....,
(4. r- XI 0
—3 C.) 0
WHERE PIPING CLASS SPECIFIES
3" FLGD
3" FLGD
3" FLGD
3 " FLGD
'A" SCRD
V2" SCRD
,-,
SCRD.
>2=-7
'A" SCRD.
-t, z o m2 P P 5?
r
CONNECTION
poz,
INSTRUMENTS
F i
0, cA rn - r)
U 700H H
-to ,r
‹ c4 > -
c,, m z g
a c ,.-
cr X 0 t-r1 C/)
H rri til0H I ' 0
Xi 0 ..n > P:J
C
3" FLGD
3" FLGD
3" FLGD
o
3" FLGD
3" FLGD
3" FLGD
3" FLGD
> .:J'
'A" SCRD*
...
PROCESS
K C c., ct' h
tri 0
rri H (4
:c
Z --
CONNECTION
H cn cn >
0 t-
r r-
> :',..'
.-3
1A
o 5' r
: vi
O . . .
?:' z v)
= < `-0 oa
VALVE
3"FLGD
3" FLGD
m
3/4" FLGD
a
1 1/4"FLGD
'A" SW/BW
'A" SW/BW
CD 7y
' " SW/BW
r
FIRST BLOCK
<
(BY INST)
rrl rn
< c
S3dId NO NO1133NNO3IN3IN I11:11SNI
rn
CI =
,...,
r r1 ....
CEMENT LINED PIPES
X w0 C: ,.."7 .■
's7. .,7
rrl PO > ..,z :. .1
(n C) r- Cl) CA cn . .
H <n (-) n n
e P zJ zi
5 c
3" FLGD
3" FLGD
3" FLGD
WHERE PIPING CLASSSPECIFIES
'A" SCRD
0 0
3" FLGD+
ti, c 0
0, p c
INSTRUMENTS
.< CO .-
'-'
K 0 n1
m-i K
r) 2 m
z
x --
0 !
-3 „Z .1:
1A
-1
.11
z P r,
F--)' 0 r” c)
> 0 c)
1" FLGD
1" FLGD
3" FLGD
3" FLGD
0
3" FLGD.
r- 0
PROCESS
0
' " FLGD
C)
n >
CONNECTION CONNECTION
o c.)
z t-1-1
X H
ul
n u, --.
H = "r1
O > . '
,
1 ' t-'
?c1 r- r
r-
VALVE
C
1" FLGD
1" FLGD
3" FLGD
I" FLGD
0
3" FLGD.
cc
(BY INST)
1 'A" FLGD
m 0
FIRST BLOCK
2 up
rn
-0 Ca
za 0
2 Ca
C)
..;Z
n
-nau Z000-Z9-L
0 -,1 C . .
C)
.oN auvaNvis
-c, r- x
C)
3" FLGD
WHERE PIPINGCLASS SPECIFIES
3" FLGD
'"SCRD
'A" SCRD
3" FLGD.
'A" SCRD
3" FLGD+
C C
INSTRUMENTS
Page 1 of 3
cZ 34 mm CHAIN
ct• 1/2"NPT r_
ID 11 mm
BORE TO BE CONCENTRIC
WITH 0.D. WITHIN 10% OF
WALL THICKNESS
18 mm
(1)
0 34 mm CHAIN
r_ 00 I's 1.0z"
q 1/2"NPT
•
•
••
Min
4!)
N
FOR OW TERMINATION PLUG WITH CHAIN
(ONLY FOR TEST THERMOWELL) 45 mm
ABM
6R
FULL PENETRATION WELD
NO WELD MATERIAL
PROJECTION BEYOND RF
OD 21 mm
z
ID 7 mm
BORE TO BE CONCENTRIC
WRH O.D. WRMIN 10% OF
WALL THICKNESS
JO 16 mm
0 34 mm
45 mm
WELD
BORE TO BE CONCENTRIC
WITH O.D. WITHIN 10% OF
WALL THICKNESS
BAR STOCK
0 18 mm
NOTES:-
DP TEST SHALL BE CARRIED OUT FOR ALL WELD JOINTS.
TYPE OF FLANGE SHALL BE RTJ FOR RATING (AS PER ASME CLASS) >
3 21-03-12 REVISED & REISSUED e‘anoj R JMS
2 21-08-08 REVISED & REISSUED MN TGM PM VJN
Rev. Prepared Checked Stds. Committee Stds. Bureau
No. Date Purpose Convenor Chairman
by by
Approved by
Format No. 8-00-0301-F4 Rev.O Copyright EIL • AI rights reserved
1/2" NPT
(NOTE-1)
CHAIN
UNION 1/2" NPT
(NOTE-2)
THERMOWELL
P - BY PIPING
I- BY INSTRUMENTATION
V- BY INSTRUMENT VENDOR
LIST OF ITEMS
CODE DESCRIPTION SIZE ENDS QTY. UNIT CODE DESCRIPTION SIZE ENDS QTY. UNIT
7 NIPPLE 1/2" TH X PL 4 No
48 FLANGE 2" X 3/4" FL X TH (Rod) 2 Ne
51 CAP 1/2" TH 2 Ne
210 GATE VALVE 1/2" SW 2 Ne
n 44,..
12-10-11 Revised and Reissued Mano /J
3 07-08-06 Reaffirmed and Reissued MN TGM PM VJN
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by Approved by
Format No. 8-00-0001-F4 Rev.O Copyright EIL - All rights reserved
Ogar0154'dg
.
ala_it4 ENGINEERS
INDIA LIMITED
STANDARD SPECIFICATION FOR
INSTRUMENTATION OF
PACKAGE UNITS
STANDARD SPECIFICATION No.
6-52-0052 Rev. 3
,A Govt of Indla Undertaking) Page 1 of 58
Ada fry
*o-t-§al21mm ITFTW fq fff -kmRT
Abbreviations:
Members : Mr S Bhowal
Mr M Nandi
Mr R K Gupta
Ms Rima Kundu
Mr S Mahesh Kumar
Ms. N.P.Guha (Proj.)
CONTENTS
1.0 GENERAL 6
2.0 DESIGN PHILOSOPHY 12
3.0 SPARES PHILOSOPHY 19
4.0 GENERAL SPECIFICATION OF INSTRUMENTS 20
5.0 LIST OF DOCUMENTS ATTACHED 46
ANNEXURES:
PART I
GENERAL SPECIFICATION OF
INSTRUMENTATION
1.0 GENERAL
1.1 Scope
1.1.1 This specification together with the attachments covers the design and engineering of
instruments, control systems, accessories and materials, along with special test equipments,
where the supply is part of a package being supplied by vendor. This specification is general
and all instruments/systems included may not be required for the proposed package. The
scope shall be as defined in the scope of supply of Instrumentation.
1.1.2 The detailed scope of work, specific job requirements, exclusions, deviations, additions etc.
if any, will be indicated in Scope of Supply of Instrumentation and Job Specification of
Instrumentation included in the material requisition.
1.1.3 This specification provides only the qualitative specifications of commonly used
instruments. Specifications of Instruments not covered in this specification shall be
submitted by vendor for review by Purchaser.
1.1.4 Vendor shall be fully responsible for design, material selection, sizing and selection of the
proper instruments for their system. The compliance to this specification does not absolve
the vendor of the responsibility towards contractual obligations with regards to
completeness, proper selection, satisfactory operation and easy maintenance of the unit.
1.1.5 All items, as offered, shall be field proven and should have completed trouble free
satisfactory operation for a period of minimum 6 months on the bid due date in the similar
application with the process conditions similar to those as specified in the purchaser's data
sheets. Items with proto-type design or items not meeting provenness criteria specified
above shall not be offered
1.1.6 In the event of any conflict between this specifications, data sheets, related standards, codes
etc., the vendor shall refer the matter to the purchaser for clarification and only after
obtaining the same should proceed with the manufacturing/engineering of the item in
question. DCS/ PLC is not included in this specification. Vendor shall refer specifications
attached separately in case DCS/ PLC is included in scope of supply.
1.2 Bids
1.2.1 Vendor shall provide the following information along with their offer:
1.2.2 Vendor shall clearly define the operational philosophy proposed, which shall be in line with
requirements specified in the job specification. Vendor shall also clearly indicate the
provision of control panels and control systems required for the package along with offer.
1.2.3 Documents like Instrument list and typical specifications and any other details if submitted
by vendor in their bid, shall not be reviewed and shall be retained for records only. All such
details shall be submitted by vendor only after the finalisation of P&ID (Piping and
Instrument Diagram) during detail engineering. No implication shall be admissible on the
Format No. 8-00-0001-F1 Rev. 0 Copyright EL — All rights reserved
basis of these documents and vendor shall be responsible for completeness and correctness
of the same with respect to Purchase Requisition/Tender.
1.2.4 Vendor's offer, catalogues, drawings, instrument manuals etc. shall be in English.
1.3.1 Design and terminology shall comply, as a minimum, with the latest edition of following
codes, standard practices and publications, unless otherwise specified:
AGA American Gas Association, Gas Measurement Committee
Report No.3 Orifice Metering of Natural Gas and Other Related
Hydrocarbon Fluids — Concentric, Square-Edged Orifice
Meters
Report No.7 - Measurement of Natural Gas by Turbine Meter
ISO 5167 Measurement of fluid flow by means of orifice plates, nozzles and venturi
tubes inserted in circular cross-section conduits
NFPA-496 National Fire Protection Association - Purged and pressurised enclosures for
electrical equipment
1.4.1 Detailed drawings, data and catalogues required from the vendor shall be as per Vendor
Data Requirement attached elsewhere in the Material Requisition / Tender.
1.4.2 The minimum requirements expected from the various documents listed in Vendor Data
Requirement shall be as follows:
This document lists out all drawings and documents prepared and/or submitted by vendor to
purchaser after placement of order through vendor portal. Following information shall be
available in this document:
Name and number of each drawing and document listed.
Expected and Actual date of submission to purchaser.
c) Review category of the documents
1.4.2.2 Instrument Index
Instrument Index lists out all instruments appearing on the P&ID without any exception. It
is a basic instrument document which is necessary for the smooth execution of a job and is
also a reference document after the completion of job. Instrument Index shall be prepared in
EIL Format. In case, any other format is used, it must contain all information as listed in
this format as a minimum.
This document shall list out all instrument items and accessories including control system
along with the name of the sub-vendors from whom vendor is likely to procure these items.
Instrument Sub-vendor shall meet the enlistment conditions of Ell, approval at the time of
placing the order on sub-vendor for the Project Approved Vendor List. The EIL approval
conditions are available with the Sub-Vendors. Vendor shall follow the approval
requirement.
For Instruments / items not covered in the vendor list, Vendor shall get approval from
purchaser/ owner for the vendors proposed, prior to the placement of order. In such cases the
sub-vendors suggested shall be manufacturer of repute and it shall meet the provenness
criteria specified in this document.
Instrument sizing calculations provide information regarding sizing (as per standards
specified else-where in this document), type, selection and other related information.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Following sizing calculations shall be applicable, in general, duly approved by the authority
indicated in Vendor's Standard Quality Plan;
This document lists out the following information regarding utilities required by the vendor;
List of utilities required i.e. Power (UPS, Non UPS), Instrument air, Cooling water,
steam for tracing, Nitrogen etc.
Location and estimated/actual requirement at each location. The requirement shall be
listed as minimum/normal/maximum.
Incase of AC power, the In-rush current with duration and power factor shall also be
indicated for each location.
In case of cooling requirement of any instrument/equipment, vendor shall provide the
detail of pressure/flow requirement with location.
1.4.2.6 Nozzle Elevation for Level Instruments
Nozzle elevation for level Instruments represent the nozzle elevation, nozzle sizes and
rating, requirement of stand-pipes, type of level instrument etc. for all the vessels, columns,
exchangers and tanks.
Purchase Requisition shall contain following information as a minimum but updated in line
with the finally accepted offer of the successful vendor including:-
Functional Schematics details out the functionality of all the loops shown on the P&ID
including their correlation. The schematic shows all the hardware necessary to configure a
loop including their physical location, their interconnection and important software blocks as
applicable to make a loop complete. Similar loops may be combined under the same
functional schematic.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Logic diagram is a logic representation of process interlock and shutdown system and details
out the functionality, in a schematic form, as either process cause and effect table shown on
the P&ID or in a separate write-up. The schematic shall be prepared based on ISA S5.2 — A
Binary Logic Diagrams for Process Operations and shall show the physical location of
Input/output devices, their interconnection with functional blocks, bench status of all
electrical devices etc. The schematic shall also be supplemented with operational
requirements like startup and process bypasses, reset and shut down push buttons, selector
switches, status lamp etc.
The FF segment drawing provides the complete segment design details indicating all the
devices of a segment, the Tag names, device control/monitoring functional requirements,
spur length, FF Junction box barriers connectivity, termination details, location of JB etc.
Each loop shall have a separate Instrument Loop drawing which shall show each component
from field device to final receiver including physical location; initiating device, its terminal
number; junction box with its terminal number; cable number with pair number/polarity;
receiver instrument terminals/cabinet terminals; system functional blocks of loop in
simplified manner (without configuration details).
Control room layout drawing shall show the location of control panels, system cabinets,
marshalling racks and other auxiliary cabinets, consoles with monitors, hard wired consoles,
printers, non-system panels/cabinets including panels/cabinets for packages, LEL panel, fire
alarms panels or any other equipment required to be installed in control room. The layout
shall be prepared on control room architectural drawing and shall also show layout of
equipment in engineering room/computer room etc.
This drawing shall show the arrangement of panel mounted instruments like indicating
instruments, alarm annunicator, indicating lamps, push buttons/switches etc. including their
approximate sizes and their mounting locations.
This document indicates the physical assignment of various I/O modules and their respective
channels to various physical inputs and outputs.
Instrument duct/tray trench drawing shows the routing of main instrument duct/tray trench in
the unit/plant. The drawing shall be prepared on plot-plan/ Equipment layout and shall show
the size, cross-section at various locations, general notes, symbols, reference drawings and
the control room entry.
Instrument Location Plans shall show the location of instruments, location of tapping points,
location of local panels, junction boxes, main cable trenches, instrument air distribution
scheme etc. These drawings are prepared on equipment layout drawings in 1:50 or 1:100
scale depending on density of instruments.
The instrument cable schedule shall show all instrument and power cables required for
complete instrumentation. The document shall show tag number, cable number, type, length
and size of cables, type of junction box, identity of local panel, control room panel/cabinet
location etc. The document shall also show the size of terminals considered for power
junction boxes and the dimensions of cable considered by the contractor.
The cable schedule document shall include all single & multi pair cables indicating
terminations of instruments, field junction boxes and respective termination in satellite rack
room cabinets. The instrument cable schedule shall be prepared on ElL format.
1.4.2.20 3D Modelling:
Whenever 3D modeling is included in package vendor's scope, it shall include the following
instrumentation items as a minimum:
2.1 Instrumentation shall be complete in every respect in accordance with latest approved
P&IDs for the safe, efficient and easy operation, start up and shut down of the plant.
2.2 All instruments and equipments shall be suitable for use in a hot, humid and tropical
industrial climate in which corrosive gases and/or chemicals may be present. As a
minimum, all instruments and enclosures in field shall be metallic construction, dust proof
and weatherproof to IP-65 as per IS/IEC-60529 and secure against the ingress of fumes,
dampness, insects and vermin. All external surfaces shall be suitably treated to provide
protection against corrosive plant atmosphere.
2.3 The design of electronic instruments shall be in compliance with the electromagnetic
compatibility requirements as per IEC 61000-4 'Electromagnetic compatibility for Industrial
Process measurement and Control equipment.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Contractor shall be responsible for obtaining all statutory approvals, as applicable, for
all instruments and control systems.
For all flame proof equipments manufactured locally (indigenously), the testing
shall be carried out by any of the approved test house like Central Institute of
Mining & Fuel research (CIMFR)/ Electronics Regional Testing Laboratory
(ERTL) etc. The equipment shall in addition bear the valid approval from
Petroleum and Explosives Safety Organisation (PESO)/ Chief Controller of
Explosives (CCE), Nagpur and a valid BIS license.
iii) For all intrinsically safe equipment manufactured locally (indigenously), the
testing shall be carried out by any of the approved test house like Central Institute
of Mining & Fuel research(CIMFR)/ Electronics Regional Testing
Laboratory(ERTL) etc. The equipment shall in addition bear the valid approval
from Petroleum and Explosives Safety Organisation (PESO)/ Chief Controller of
Explosives (CCE), Nagpur.
c) Approvals other than above shall neither be offered nor will these be acceptable.
2.6 Following units of measurement shall be applicable, unless indicated specifically otherwise:
Flow Liquid M3/11
Steam kg/h
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
2.8 Ranges for instruments shall be selected in general, such that in normal process operation
the indication is between 35% to 65% of the range i.e. middle 30% of the full working
range.
2.9 Field mounted direct actuated Flow and Temperature switches shall not be used. Instead,
transmitters shall be used along with flow element/temperature element. Process switches
shall not be considered unless its use is unavoidable and the same shall be subject to
purchaser's approval. In case switch has been considered, same shall be provided with
sealed micro switch contacts rated for the specified application. Also contacts shall be SPDT
type unless otherwise specified. Contacts used in intrinsically safe applications shall be
suitable for the application.
All intrinsic safety barriers shall be active type isolating barriers only, with three port
isolation.
Barriers must be selected based on entity concept. Cable parameters shall also be
considered while matching entity parameters.
Each instrument in the hazardous area and the intrinsic safe barrier shall be certified for
intrinsic safety by any statutory authority.
Each input and output in a loop shall have separate barrier. No barrier shall be shared
between two loops or input/outputs.
Any device required to be connected to any intrinsically safe loop in the hazardous side
permanently or temporarily shall also be certified intrinsically safe.
Configuration tools whenever required for any intrinsically safe item, which forms part
of the intrinsically safe item, shall also be certified intrinsically safe.
2.11 Power Supplies and their Distribution
a) Power supply shall be made available at the following voltage levels, unless otherwise
specified:
0 For Instruments, Control Systems, 240V AC/110V AC
Analyzers
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Solenoid Valves, Relays, lamps 24V DC/110V DC ±10%/
240 AC/ 110 V AC UPS
Input interrogation voltage 24V DC/110V DC ±10%
0
Panel/cabinets lighting 240V AC Non-UPS ± 10%
In case 24 V DC is required for Input interrogation, relays and lamps, any other vendor
supplied instruments/ electronics), same shall be considered by the vendor using dual
redundant power packs (110 V AC to 24 V DC converter). 24 V DC feeders shall not be
provided by Purchaser unless indicated specifically in the job specifications.
All instruments, control systems (PLC and DCS) and analyser system shall be able to
operate at the following UPS specification:
d) Instrument power circuits shall be individually protected and isolated from fault with
the help of fuses and DPST switches. Power supply to the individual instrument shall
be disconnected with the help of DPST switch and protected with the help of fuses.
Miniature circuit breakers (MCB's) may be selected in place of switch fuse unit in case
protection is provided for overload protection.
Alarms shall be provided to give audible and visual warning of any process and
machine malfunction in the package.
All trips shall have a pre-trip warning alarm in addition to alarm at the trip condition.
Package alarms including pre-trip warning alarms and trip alarms (shutdown alarms)
shall be annunciated on the local panel as per approved P&ID.
Rotating equipments shall have the status indication provided on the local panel as per
approved P&ID.
e) 'Fail-safe' type with normally closed alarm contacts shall be used.
2.13 All line or equipment mounted instruments like control valves, pressure relief valves,
thermo-wells, orifice flanges, level instruments etc., installed on pipes and vessels under
IBR shall be certified by IBR or their authorized representative.
2.14 Location of process connections shall be from the side or from the top of the process
equipment but not from the bottom. This requirement is applicable to both pipes and vessels.
The location of lower side connection for level measurement when necessary shall be
extended inside the equipment with the approval of purchaser to prevent plugging due to dirt
or other suspended solids. In addition, the connections shall be short, vertical or horizontal
and without any pockets.
2.15 Material of construction of instruments shall be as per the material selection chart, attached
as Annexure I of this specification, as a minimum. However vendor is responsible to ensure
that the selected material is consistent with temperature, pressure, corrosion conditions and
other process requirements.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
2.16.1.1 The field transmitters in all conventional loops shall be smart type only unless specified
otherwise. Field transmitters for flow, pressure, temperature, differential pressure and level
applications shall be yoke mounted type unless specified otherwise. Meter electronics used
for flow measurement etc. shall include all the associated items like pre-amplifier, converter,
transmitter, integrator, integral output meter etc.
2.16.1.2 Field transmitter shall be intrinsically safe and meter electronics shall be intrinsically safe, in
general. In case, intrinsically safe is not available from the approved vendor list enclosed
with this MR/tender, flameproof enclosure is acceptable. In case sensor/ pick up coil is
intrinsically safe, suitable barrier shall be provided and installed in flameproof enclosure.
2.16.1.3 These transmitters shall be 2 wire systems having 4 - 20 mA DC output with superimposed
digital signal having simultaneous analog and digital communication with HART
communication protocol, unless otherwise specified.
2.16.1.4 The transmitter shall be microprocessor based and it shall incorporate a non-volatile memory
which shall store complete configuration data of transmitter and sensor characterization. All
necessary signal conversions, including conversion to produce output with the required
protocol shall be carried out in the transmitter electronics. The configuration data of the
instruments shall be stored in a non-volatile memory such that this remains unchanged
because of power fluctuations or power off condition. In case vendor standard instrument
has battery backed RAM, vendor to ensure that battery drain alarm is provided as diagnostic
maintenance message.
2.16.1.5 Transmitter shall also run complete diagnostic subroutines and shall provide diagnostic
alarm messages for sensor as well as transmitter healthiness. In the event of detection
failure, the output shall be driven to a predefined value, which shall be field configurable.
2.16.1.6 Universal hand held configurator / terminal for the configuration and maintenance of
instruments with HART output shall be provided for all HART based smart instruments.
2.16.2.2 Field bus based transmitter/ devices shall meet the following requirements;
All instruments must satisfy the requirements of the fieldbus registration laboratory
with applicable checkmark like foundation field bus, profibus etc as specified in Job
Specification.
All instruments shall be polarity in-sensitive. Also transmitter shall be LAS capability.
Line plugging detection facility shall be provided, whenever specified in data sheet.
All instruments shall have Analog Input (AI) block and Proportional, Integration and
Differential (PID) control block, as a minimum.
All instruments must be interoperable and shall have valid interoperability test
clearance like ITK latest version for foundation field bus or equivalent for profibus PA,
as applicable.
The field bus instruments shall support peer to peer communication with two wire
communication and bus powered supply.
All instruments shall support EDDL or FDT/DTM requirements.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Internal software shall be configured by the vendor including the following information
such as serial number, Device Tag (Tag Number) and Process description
All instruments shall be capable of supporting incremental Device descriptor (DD) for
extra functionality and for software revisions in device memory.
Soft copy of the Device Descriptor (DD) files for configuring the FF device parameters
and common file format (CFF) files for integrating the device into the system shall be
provided by the bidder for offline configuration by System vendor immediately after
despatch.
Fieldbus based field indicator shall be able to indicate all signals available in the
fieldbus segment, selectively.
2.16.2.3 The fieldbus / devices provided shall be able to communicate with latest universal fieldbus
communicator.
2.16.3 Accuracy of transmitters (Pressure & Differential pressure), smart as well as fieldbus based
shall be as follows:
The accuracy is defined as the combined effect of repeatability, linearity and hysteresis.
2.16.4 Transmitter shall update the output at least 8 times a second unless otherwise specified.
For transmitter range of 760 mm WC and above, the response time shall be equal to or
better than 500 milliseconds.
For transmitter range below 760mm WC, the response shall be equal to or better than 1
second.
The response time of the transmitter shall be considered as the sum of dead time and 63.2%
step response time of the transmitter.
2.16.5 Unless specified otherwise, the over-range/static pressure protection of the transmitter shall
be as follows;
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
<N1> However if the Over range/ static pressure value specified above is less than the
maximum/ design pressure of service conditions, offered instrument shall be suitable for the
maximum/ design pressure.
2.16.6 Diaphragm seal DP transmitters in flow measurement with a DP of less than 250 mmWC
shall be avoided and alternate type of flow meters shall be provided for such cases suitable to
the process condition.
2.16.7 All transmitters shall have vent and drain facility and the same shall be provided with metallic
plugs. All the cable entries shall also be provided with metallic plugs.
2.17.1 The connections of instruments installed on vessels, tanks, standpipes and piping shall be as
per following EIL Standards.
2.17.3 Electrical cable entry connection shall be 1/2" NPT (F)/ 3/4"NPT (F) as per the cable size.
Suitable cable gland shall be used.
2.17.4 End connections shall meet the following, unless, otherwise specified:
2.18.1 Air supply at pressure specified elsewhere shall be made available to the vendor at the
battery limit for distribution to the instruments.
2.18.2 Pneumatic Instruments shall operate on air supply of 1.4 kg/cm2g and shall have
transmission and output signal of 0.2 to 1.0 kg/cm2g.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
2.18.3 Instrument air quality shall be as per ISA- S 7.0.01and free from corrosive, hazardous and
toxic contaminants.
2.19.1 Wherever applicable, instrument junction boxes shall be provided as interface between
purchaser and vendor. Marshalling details between purchaser-vendor cabling shall be shown
with corresponding junction box termination number allocated against appropriate
purchaser's/vendor's instrument tag number in the format provided by purchaser.
All signals from package skid/battery limit to purchaser's control room shall be terminated
in the junctions boxes located at the battery limit. Separate junction boxes shall be used for
the following type of signals:
Where signals as indicated in Clause 2.19.2 is less in number and do not justify
separate junction boxes, all such signals may be routed via local control panel.
All such signals shall be terminated on separate terminal strips in the local control
panel. The terminal strips shall be segregated as per Clause 2.19.2.
c) Intrinsically safe barriers for all such signals, wherever required, shall be provided.
The above shall only be considered with prior approval from purchaser.
Unless specified otherwise, the following mandatory spares shall be provided by vendor.
Mandatory spares shall be ware-house spares and shall be supplied as loose items.
3.1.1.1 Higher of 10% or minimum one of each type (range, type, material and rating ) of complete
instruments for commonly used instruments such as transmitter, gauges, temperature
elements, switches, probes.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
3.1.1.2 For Control valve one set of packing and bonnet gasket with tag, one set of stem seal o-ring
for each actuator and piston o-ring additionally for each piston actuated valve, line bolting
(set of studs and nut) and set of gasket with each tag no.
Vendor shall be responsible to supply all spares which are found necessary to replace while
performing pre-commissioning and commissioning activities and this includes system
oriented items (hardware / software).
Vendor shall supply consumable spares for six months of normal operation.
3.1.4.1 For Control system, installed spare module of higher of 10% or minimum one of
input/output modules (including termination panels, if applicable) to enhance the system
functional requirements of control system.
A minimum of 20% spare windows with alarm modules shall be provided in alarm
annunciator.
A minimum of 20% spare status lamps / switches / pushbuttons / terminals or one no of
each type, whichever is higher, shall be provided.
For pneumatic panels, 10% spare instrument air header branch lines and 15% spare
bulkheads and tapping points shall be provided in each panel.
Control panels shall have additional spare-space as per clause 4.2.8 of this specification.
Vendor shall supply a list of recommended spare parts for each instrument and system
required for two (2) years of normal operation. These spares shall be quoted separately.
4.1.1 Alarm Annunciator shall either be solid state type or microprocessor based programmable
type with plug in modules and integral power supply. Window display shall be back lighted
incandescent lamps or cluster LED type integral power supply. For window display with
back lighted incandescent lamps two numbers of incandescent lamps of minimum 5 watt
each shall be provided for each window. For cluster type LED display, the number of
LED's in the cluster matrix windows shall be sufficient to provide illumination level of at
least 150 lumens. The circuit shall be designed in such a way that removal/failure of one
lamp or LED from a window/ cluster shall not hamper functioning of that particular
window/display. The annunciator lamps shall be replaceable from the front of the enclosure
panel. In general, dedicated alarm logic module shall be used for each alarm input.
However, when micro processor based alarm Annunciator is offered failure of one
microprocessor shall not affect more than four alarm windows.
Intrinsically safe annunciator circuit, when used, shall have power supply unit in a safe area.
Annunciator alarm sequence shall be as per F3A of ISA.
The design of the alarm annunciator system shall be such that transient alarms of less than
330 milliseconds duration shall be automatically rejected.
4.2.1 All panels shall be supplied in pre-tubed/pre-wired condition and shall be completely tested
at manufacturer's works prior to dispatch.
4.2.2 Panels shall be free standing type. Panels with instruments mounted on the front shall be
fabricated from 3 mm thick cold rolled steel sheet. If the same is not available, 4 mm thick
hot rolled steel sheet shall be used. All other panels shall be fabricated from 2mm thick cold
rolled steel sheet. Angle iron framework shall use a minimum section of 50 x 50 x 4 mm
angle. Panel painting procedure shall include blast cleaning, grinding, chemical cleaning,
surface finishing by suitable filler and two coats of high grade lacquer with wet blasting
wherever required. Two coats of paint in the panel colour shall be provided for non-glossy
high satin finish. Final coat shall be given after assembly at site.
Unless otherwise specified, exterior/interior portion of all panels and closed cabinets shall
have a colour as per RAL-7035. Channel base shall be of black colour.
4.2.3 Panel shall be enclosed cubicle type with each section of typically 2100 mm high, 1200 mm
wide and 800 mm deep mounted on 100 mm channel base.
4.2.4 Enclosed cubicle panels shall have removable hinged doors for easy maintenance and
accessibility of the instruments. Doors shall be double leaved type with handle and shall be
provided with lock and key. Adequate illumination shall be provided inside the panel. All
light fittings shall be suitable for 240 V, 50 Hz AC. Power supply greater than 240 V shall
also not enter the control panel.
4.2.5 All cable entries to the panel shall be from panel bottom only using cable glands of adequate
size. Cable gland plate thickness shall be a minimum of 3 mm cold rolled cold annealed
(CRCA) as a minimum. All unused cable entries must be plugged.
4.2.6 Space heater shall be provided where condensation is expected. The space heater provided
shall be with temperature cut off and manual control.
4.2.7 The design of panel shall incorporate provision for expansion by installing adequate spare
capacity. Each panel shall be designed to accommodate the following additional equipment,
as a minimum:
4.2.10 All lamps, status as well as alarm, shall be provided with lamp test facility. One single lamp
test push button shall be used for each panel. Logic for lamp test shall not be implemented
through relay logic in the panel.
Status Lamps
On/Open/Permissive Green
Off/Close/Emergency Red
Alarms
Normal/Pre-trip alarms Amber
Shutdown alarms Red
e) Push/Pull buttons
On/Open Green
Off/Close Red
Emergency shut-down (ESD) Red
(Push-button with cover/
Mushroom push button)
4.2.12 Panel Piping and Tubing
4.2.12.1 The instrument air header shall be adequately sized with 1/2" branches, SS packless isolation
valves and shall be complete with suitable dual filter-cum-air reducing station.
4.2.12.2 Panel tubing from the bulk head to the panel instruments and instrument air supply to the
panel instruments shall be of 6 mm x lmm thick SS 316L tubing.
4.2.12.3 The tubing shall be laid in plastic slotted ducts. Panel air header and tube fittings shall be of
SS 316.
4.2.13.1 Open terminals shall generally be avoided. Terminal strips shall preferably be mounted in an
enclosure. Fused terminal may be used wherever necessary. All terminals shall be of
mechanical screw clamp/screwless type with pressure plates as per the job specification.
Self-insulating crimping wire lugs shall be used for all terminations on terminal blocks,
whereas forked tongue type or lug with eyehole type shall be used for termination on
screwed terminals such as on relays, push buttons, lamp etc. Terminal blocks shall be rated
for 600 V.
4.2.13.2 A minimum of 1 mm multi stranded PVC insulated copper conductor shall be used in
2
general. All wiring shall be laid in the PVC troughs. No trough shall be more than 70%
full.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
4.2.13.4 Extension cables/wires shall be used for all thermocouple inputs. These wires shall be
routed in separate troughs/wire-ways.
4.2.13.5 All intrinsically safe wires shall be routed in separate wire ways from non-intrinsically safe
and power wiring. Intrinsically safe wiring and terminals shall be light blue in colour and
shall be separated from non-intrinsically safe terminals atleast by 50 mm.
4.2.13.6 All incoming power feeders shall be terminated on separate terminals suitable for the
incoming feeder size. These shall be located at the bottom of the panel and shall be suitably
covered for protection against accidental shorting and for human safety.
4.2.13.7 Power supply shall be made available at one point. Further power distribution network shall
be designed such that a single power fault in any instrument branch system shall not cause a
trip of the entire system. Each consumer shall be provided with a separate switch and fuse
for isolation and protection of the system.
4.2.14 Electrical Wiring
All the cabinets, consoles and panels shall be completely wired. Interconnections shall
preferably be done with the help of pre-tracked cables. Vendor may follow their standard
wiring practices, however the requirements specified herein must be complied.
All wiring shall conform to API RP 552- Transmission Systems. Different signal level
cables shall be routed with separation distances as recommended by code.
All wiring inside racks, cabinets, and back of the panels shall be housed in covered,
non-flammable plastic raceways arranged to permit easy assembly to various
instruments for maintenance, adjustments, repair and removal.
All wiring in the raceways shall be properly clamped. All incoming cable shall be
terminated by vendor at marshalling rack with cable glanding including supply of
cable glands. Total wiring cross-sectional area shall not exceed 50% of the raceway
cross sectional area.
Separate wiring raceways shall be used for power supply wiring, DC and low level
signal wiring, and intrinsically safe wiring. Parallel runs of AC and DC wiring closer
than 300mm shall be avoided.
Vendor can alternately offer prefabricated cables for interconnection between
different cabinets and panels.
Wire termination shall be done using self-insulating crimping lugs. More than two
wires shall not be terminated on one side of single terminal. The use of shorting links
for looping shall not be done.
The spring material for all terminals shall be chrome nickel spring steel of high tensile
strength and of excellent corrosion resistance. All terminal / terminal blocks shall be
DIN Rail mounted type and shall be easily removable. The size of the terminal blocks
/ terminals of different types shall be consistent and identical.
All terminal blocks shall be mounted on suitable anodised metallic or plastic stand-
off.
f) Terminal strips shall be arranged group-wise for incoming and outgoing cables
separately. Terminal blocks for intrinsically safe wiring shall be separate. 20% spare
terminals shall be provided, as a minimum, preferably in each terminal strip.
4.2.16 Following design philosophy shall be followed while deciding the internal layout of panels,
as a minimum;
4.3.1 Local control panel for the package units shall be installed within the battery limit of the
package considering operational and maintenance requirements and accessibility. In case of
skid mounted packages, panel shall be located away from the skid.
In case local control panel is housed outdoor i.e. not in a local control room, it shall be
designed to meet IP-55 requirements. In addition, panel must be provided with a rain cum
sun shade/canopy.
4.3.2 Local control panel/panels shall be totally enclosed cubicles. Panel sizing shall be carried
out based on equipment being installed keeping in view the maintenance clearances and
easiness of operation. Although the panel dimensions shall be guided by the actual
requirements, typical dimensions shall be 2100 mm height x 1200 mm width x 1000 mm
depth. In any case, vendor shall not proceed with panel manufacturing before getting prior
approval from the purchaser.
4.3.3 Local control panels located in the hazardous area shall either be purged type or flame proof
Ex'd' or weather proof with Ex'd' components such as lamps, push buttons, switches etc. as
specified in job specification. In case pressurized panels are specified the same shall be
purged and pressurized as per NFPA 496 requirements to render space within the panel non
hazardous. For panels located in IEC Zone 2, hazardous area type Z purging shall be used
with a purge fail alarm in main control room. In case, panels are located in Zone 1, the
power shall be cut off on perssurisation failure as per x-purge requirements of NFPA-496.
An alarm shall be provided on local panel and a contact shall be provided for remote
annunciation, whenever the panel pressurization falls below 2.5 mm of H2O. A protective
device to protect the panel from over pressure must be provided.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
4.3.4 Panel pressurisation with start-up panel purging scheme shall be fully automatic however it
shall be started manually from a push button. Solenoid valves and differential pressure
switch required for panel purging shall be flameproof, however other items like relays,
switches/pushbuttons, timers etc. shall be located in a flameproof housing. Other items like
valves, restriction orifice plates, dual filter regulators, pressure gauges, rotameters etc
required for pressurization shall also be located in the non-pressurized section of the panel.
4.3.5 It shall be possible to switch off incoming power to panel from panel front. All such power
on/off switches shall be flameproof type.
In addition, all those devices and terminals, which cannot be powered off from on/off
switches shall also be located inside flameproof enclosures.
4.3.6 All hinges, screws and other non-painted metallic parts shall be of stainless steel material.
4.3.7 All other requirements as specified in clause 4.2 of this specification shall also be applicable
for local control panels.
4.3.8 Whenever weatherproof local panel is provided by vendor for classified area, the Alarm
Annunciator shall be intrinsically safe and push button, lamps; selector switches shall be
flame-proof "Exd" type mounted on LCP. IS Barriers/ relays for IS alarm annunciator shall
be supplied by vendor along with IS annunciator and potential free non-flameproof contact
for the same shall be considered from the PLC / DCS/ control systems. The IS power supply
module for alarm annunciator shall be installed in a flameproof box in local panel by bidder.
For Lamps, wet contact shall be considered from the PLC/ control system and the lamp test
logic shall be realised in PLC/ control system. The Power supply distribution box inside the
Local Panel shall also be flame-proof "Exd'. IS PCs for display of loop powered indicators
shall be used in weather-proof local panels in case no. of tag local display more than Five
tags. The same IS PC can also be used for local display of vibration and temperature
monitoring system parameters at field instead of separate display unit at field. For 5 or less
number of tags for local indication, normal IS loop powered indicators shall be provided on
weather proof local panel.
Intrinsically Safe (IS) type with minimum 15" Display (Remote interactive PC terminal) unit
certified suitable for the hazardous area shall be mounted on the panel front of local control
panel of the package, wherever IS PC is considered. All local control panel mounted field
remote output indicators, wherever required as per approved P&IDs, shall be displayed in
this remote PC. Single serial interface (RS 485 with Modbus RTU protocol) corresponding
to these signals from control system shall be considered and vendor's scope shall include all
necessary converters, power supply module, connectors at both ends along with serial
communication cables for connecting to serial interface cards.
The PC terminal shall be equipped with necessary keyboard suitable for specified hazardous
area.
4.4.1 Local gauge board shall be used to install skid-mounted instruments like pressure gauges,
temperature gauges and transmitters.
4.4.2 Location of local gauge boards, when provided, shall be decided to allow easy access at the
rear and front for all instruments and accessories for maintenance and operation.
4.4.3 Gauge board shall be constructed from 3 mm stainless steel sheet with other necessary SS
supporting structure.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
4.4.4 Local gauge board shall be supplied with all instruments installed and completely in
tubed/wired condition before shipment.
4.4.5 All pressure transmitters and gauges shall be provided with block and bleed valves securely
fastened. Identification tags shall be securely fastened for easy identification. Wherever local
temperature indicator is required with temperature transmitter, Loop powered indicator shall
be provided.
4.5.1 Thermowells
All temperature elements shall be provided with thermowells fabricated out of bar stock
of minimum SS 316 material as per EIL Standard 7-52-0035. The base of the
thermowells shall be chosen to fit the instrument without air gap for minimizing
measurement lag.
Built-up thermowells shall be used in low pressure and low velocity services like in
fired heaters and also where thermowell immersion lengths greater than 500 mm are
required.
Any pipe line less than 4" nominal bore shall be blown to 4" size to install thermowell.
e) Thermowell flange and well material shall be as per material selection chart.
0 The vibration analysis shall be carried out as per PTC 19.3 TW:2010 (latest version)
and corrective measures shall be taken as necessary.
Local temperature gauges shall be in general bimetallic type. The temperature bulb
shall be of stainless steel construction. The gauge connection shall be all angles
adjustable. Gas filled type shall be used when measuring range is beyond the limits of
Bimetallic gauge or thermowell length exceeds 550 mm or in applications involving
excessive vibrations. Mercury filled type temperature gauge shall not be used.
All local temperature gauges shall have 150 mm dial size. The bulb size shall be
selected to suit the thermowell.
Temperature gauges shall have accuracy of ±1% URV (upper range value).
e) Bimetallic type dial thermometers shall be avoided where excessive vibrations are
enoniinterett, clich ac reriprnrating rnmpreccor clicrharr Only filled type with
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
capillary extension shall be used in such cases. Capillary tubing shall be a minimum of
304 SS with stainless steel flexible armouring, and PVC covering over armour. Filled
type gauges shall be manufactured as per relevant SAMA class.
f) Thermometer stem adjustable gland with union connection and bushing shall be
suitable for 1/2" NPTF connection.
Thermocouple assemblies shall be furnished with weatherproof screw type heads as per
EIL Standard 7-52-0036.
Thermocouples shall be as per IEC-60584-2 and shall have a wire size of 18 AWG for
single and 20 AWG for duplex thermocouples. These shall be magnesium oxide (MgO)
filled grounded type, unless necessary otherwise. The type of thermocouple shall be
selected based on temperature. The selection of type shall be as per following
guidelines:
RTD (Resistance Temperature Detecter) shall be platinum element 3 wire type with
100 ohms resistance at 0°C calibrated as per 1EC 60751. RTD shall be used within a
temperature range of -200 to 650°C. Three-wire system shall be adopted in connecting
the element.
0 RTD shall be used where accuracies of the order of 0.25% or better and smaller
measuring spans are required.
g) Duplex element sensors shall be supplied. Two separate cable entries shall be provided
with plugs.
The Temperature transmitters with RTD shall have an accuracy of 0.075% of URV as a
minimum for range above 350° C, 0.15% of URV for temperature range 350° C to 150°
C and 0.25% for calibrated range below 150° C.
The Temperature transmitters with cold junction compensation for thermocouple shall
have an accuracy of 0.25% of URV as a minimum for range above 350° C, 0.5% of
URV for temperature range between 350° C to 150° C and 0.75% for calibrated range
below 150° C.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
4.5.5 Burn out protection must be provided with temperature transmitters. Upscale or downscale
protection shall be decided based on its application to ensure fail-safe operation.
Pressure gauge dial shall be white with black figures. The dial face shall be marked
with pressure element material. Pointers shall have micrometer adjustment.
Pressure gauges shall be weatherproof with dial size of 150 mm and shall have features
like over range protection (at least 130% of max. operating pressure) and blowout
discs. Glass shall be shatter proof. Pressure gauge sensing element shall be of SS 316
and movement of SS 304, as a minimum.
Over range protector and pulsation dampener, whenever used, shall be of SS 304, as a
minimum. Pulsation damepner shall be used for all pulsating services. It shall be
floating pin type, externally mounted and externally adjustable.
Pressure gauges with range 0-100 kg/cm 2g and more shall have safety type solid front
case.
Ranges shall be so specified that the gauge normally operates in the middle third of the
scale and shall conform to IS-3624 standard dials, wherever possible.
Diaphragm seals shall be furnished where plugging of the element may occur or where
suitable material is not available in highly corrosive services. When chemical seals are
required, they shall be of the clean out type with flushing connection.
Where vibrations and pressure fluctuations are expected, glycerin filled type and
snubber shall be used.
k) Receiver pressure gauges for local transmitter output indication shall have 100 mm dial
with stainless steel element and 1/4" NPTM connection.
1) The pressure element shall be bourdon, diaphragm or bellows depending upon process
condition. Single diaphragm type Differential pressure gauges shall not be considered,
Instead double diaphragm type or bellows shall be considered.
All transmitters shall have an integral output meter. Remote mounted meters may be
provided if required in addition.
c) Diaphragm seal element with capillary shall be used for congealing, corrosive and
highly viscous services.
Process switches shall not be considered unless its use is unavoidable and the same
shall be subject to purchaser's approval
Pressure switches shall have either diaphragm or bellow type of process element with
SS 316 material of construction as a minimum. Switch type shall be sealed micro-type
with contact rating suitable for specific application. Also contacts shall be SPDT type
unless otherwise specified. Contacts used in intrinsically safe applications shall be
suitable as per the process condition.
Pressure switches shall be blind type with 1/2 NPTF process connection and shall be
operative in full-specified range. The switch differential shall be selected as per
operating conditions.
All gauge glasses shall be steel armoured reflex or transparent type with body and cover
material of forged carbon steel as a minimum and shall have tempered borosilicate glass
with asbestos or other suitable gasket. Transparent type of gauges shall be provided
with integral illuminators operating at 240 V 50 H z supply and shall be suitable for
electrical area classification specified. All gauge glasses must have a rating equal to or
more than the vessel design pressure and temperature.
Reflex type will be used for clean and colourless liquids, except liquids level interface.
For low temperature, low boiling point service, large chamber type will be used.
Transparent type will be used on acid, caustic, dirty or viscous, coloured liquids and
liquid interface. Transparent type with Mica or Kel-F shields shall be used for treated
water, boiler and condensate services, and for corrosive liquids, which will attack glass.
Tubular gauge glasses shall, in general, not be used in Hydrocarbon/hazardous services.
They may be used for non-hazardous services at ambient temperature and low pressures
(less than 10 kg/cm2g operating).
Large chamber gauges with frost shields shall be provided for cold services below 0° C.
Heating jacket shall be provided for viscous liquids with 1/2" flanged connection.
All gauges shall have top and bottom chamber connections, unless otherwise specified.
However side-side chamber connection is acceptable where nozzle installation is a
constraint. In addition each gauge shall be provided with ball check valves and pipe
union.
e) The visible range of level gauge shall be selected to cover the complete operating level
as well as measuring range of the other level instruments provided for the same
purpose. In general, the visible length and C to C distance of the top and bottom level
gauges shall be selected from the following:
220 470
470 720
720 970
980 1230
1230 1480
1490 1740
For side-side level gauge C to C distance shall be 10 mm less than visible length.
0 For level gauging in very viscous, corrosive liquids, liquids with crystals and high
pressure service, float operated magnetic gauges with 2" (50 mm) flanged end
connections, shall be used. C to C length of single magnetic level gauge shall not be
more than 2500mm.
Guided Wave Radar type instruments with external cage and side-side connections
shall normally be used for level and for interface level measurement upto 2400 mm.
Differential pressure transmitter shall be used for level measurement above 2400 mm,
for services requiring purge or where liquid might boil in external portion.
Differential Pressure transmitters for use on corrosive or fouling service shall generally
be diaphragm wafer with extended filled capillary type. Flush or extended diaphragm
type differential pressure transmitter shall be considered for special applications only.
Diaphragm material shall normally be stainless steel or any other special alloy.
e) For sump levels, Guided wave radar or non- contact type radar level instrument shall be
used depending on the application within accuracy ± 3mm.
0 Generally for top mounted level transmitters, internal guided wave radar type
instruments shall be used for level measurement upto 3000mm. Above that non-contact
type radar shall be used.
4.7.3 Other Special types of level instruments like ultrasonic, hydrostatic, nucleonic, capacitance,
conductivity type shall be used as necessitated by application requirements.
4.7.4 For high pressure steam drum application at least one number conductivity type (Hydrastep
or equivalent) level instrument shall be provided. Also level gauges shall be of bi-color type
for such application.
a) Each tank shall be provided with minimum 2 types of tank level instruments operating
on different principles like one servo and other one radar (Antenna) type.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Radar type transmitter shall be provided with ±3 mm accuracy for storage tanks and ±1
mm for custody transfer. Whenever ±3.0 mm accuracy is required, process connection
on vessel/ tank/ equipment for non-contact radar gauge can be 4" with 4" Carbon Steel
/ Stainless Steel (depending on the pipe schedule requirement) still well. However
wherever ±1.0 mm accuracy is required (e.g. in custody application), process
connection on vessel/ tank/ equipment for non-contact radar gauge shall be 8" with 8"
Carbon Steel / Stainless Steel (depending on the pipe schedule requirement) still well.
For viscous service, nozzle connection shall be 24".
Servo type instruments shall have 6" process connection with 6" diameter still well,
with accuracy ±3 mm for storage tanks and ±1 mm for custody transfer. Raising or
lowering of displacer for calibration shall be possible on-line with the design of still-
well.
The wetted material like float, displacer, tape, wire etc. shall generally be 316 SS.
The accessories for servo-controlled level gauge shall include isolation ball valves for
pressurized tanks and calibration/maintenance chamber for all tanks. Each calibration
chamber shall be provided with a viewable window of blast proof glass. The
calibration chamber can be either integral to the instrument or separate. Whenever
calibration chamber is separate i.e. not integral to the tank level instrument, the material
of construction of calibration chamber shall be stainless steel. The calibration chamber
shall also permit insertion / removal of displacer for maintenance without removing the
instruments.
f) Servo and Radar type instruments shall be capable of providing serial output as per
vendor standard protocol or field bus protocol as per IEC-61158 in addition to analog
4-20 mA DC current output. These instruments shall also be capable of accepting input
from multi element tank temperature sensors (thermocouple/ RTD), water cut probes
and transmit the same as a part of serial signal from the transmitter. Multi-element tank
temperature sensors when used shall be provided with 3" stillwell and 3" process
connection.
In-line flow instruments shall have a direction of flow indication clearly marked and easily
visible in the final installed position.
Flow switches shall not be used without prior approval from the purchaser.
a) Flow measurement shall normally be carried out by using thin square edged concentric
orifice plate mounted between a pair of weld neck flanges of minimum 300 pounds
ANSI rating for line size 2" and above. Flange taps shall be used for line sizes upto 14"
while D-D/2 taps shall be used for line sizes more than 14". The material of the orifice
plates shall be normally 316 SS, as a minimum.
Quadrant edge or quarter circle orifice plates shall be used for highly viscous liquids
and for pipe Reynold number below 10,000.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Conical entrance type of orifice plates shall preferably be used for very highly viscous
liquids upto throat Reynolds number of 250. These plates shall be fabricated as per
Flow Measurement Hand Book by RW Miller.
Vent and Drain holes shall be provided for bore dia above 25.4 mm.
b) Sizing of orifice plate shall be carried out in accordance with ISO-5167 (Latest
Edition). For orifice plates not covered in ISO 5167, sizing methods shall be ASME
MFC-14M (latest Edition) or AGA Report No. 3 or 'Flow measurement-Engineering
Handbook' by RW Miller.
Honed metering runs or integral orifice type transmitter shall be used in line size with
1.5" (40 mm) nominal diameter or below.
Upstream and downstream straight length shall be provided based on maximum d/D
ratio of 0.75, in general. Where it is difficult to meet this requirement, the actual d/D
ratio can be considered for reducing the straight length as permitted by the codes. Flow
straighteners are to be considered, where straight runs are difficult to achieve otherwise.
f) Meter taps shall be horizontal for liquids, condensible vapours and steam. The taps
shall be on top for gas, non-condensible vapour, or liquids which boil at or below the
maximum design ambient temperature at operating pressure. Where piping clearances
are a factor, taps may be located upto 45 degree below the horizontal center line for
condensible vapour and liquid. The taps may be located upto 60 degree from vertical
for gas, non-condensible vapour and steam.
4.9.2 Venturi Flowmeters
Venturi shall be designed and constructed as per ISO 5167-4 (Latest Edition) or ASME
MFC-3M.
The Venturi Flow element shall be classical, machined, non truncated type.
c) Impulse piping connection for venturi tubes shall be provided with 1/2" NPTF
connection, unless otherwise specified in the data sheet.
Venturi tube shall be provided with Annular chamber / Piezo-metric Ring. Material of
construction of Annular chamber / Piezo-metric Ring shall be same as material of
Venturi tube.
Flow calibration for those Venturi tubes, which are necessitated due to their installations
outside the limits as defined in ISO 5167 for D (Pipe Inside Diameter), beta and
Reynolds numbers shall be considered in the base quote
Averaging pitot tube in general shall not be considered unless specifically required by the
purchaser. Averaging pitot tube shall meet the following requirements:
a) The flow sensor shall be continuous averaging velocity head producing type of pitot
tube with four or more equal averaging pitot tube sensing ports or continuous slots to
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
suit line velocity profile. The sensor shall also incorporate a rear port for the
measurement of line static pressure.
Averaging pitot tube shall be of 3" flanged connection with isolation ball valve.
The insert retract mechanism shall be provided to allow on line removal and insertion
of the average Pitot tube under maximum pressure and flow condition.
Vibration analysis for each averaging pitot tube element shall be done for the indicated
flow condition to ensure that the averaging pitot tube is of sufficient thickness and
strength to withstand the vibration effects created due to Karman vortex shedding in the
fluid stream.
The free end of the averaging Pitot tube shall be pressure supported at the pipe wall.
However, for the large pipe sizes and where vibration analysis recommends the
requirement of end support, the end support/weld cap support shall be provided.
f) The offered averaging pitot tubes shall have ±1% accuracy of actual value and
repeatability of ±0.1% of actual value.
Variable area flow meters or rotameters shall be provided as per the P&ID or where
rangeability in flow precludes the use of an orifice. Variable area flow meters shall be as per
ISA-RP 16.1, 16.2, 16.3, 16.4, 16.5 and 16.6. Metal tube rotameters shall be used for all
fluids. External devices for indicating or transmitting shall be magnetically coupled to the
float or extension.
Glass tube rotameters shall not be used unless it is necessitated for low range or for low
pressure utility services for local indication and where line size is 1-1/2" (40mm) or less
with the approval of purchaser.
Reducer shall be considered, in case the size of the flowmeter is less than the line size.
Flow meter shall be of in-line mounting design and shall be of flanged body
construction with stainless steel as minimum material of construction.
The mass flow meter shall be provided with the external flow tube housing. In all
such cases, the flow tube housing shall have provision to monitor housing pressure
continuously.
The meter electronics shall be protected against transients induced by lighting and
power supply surges. Transient protection electronics shall preferably be provided in
the terminal block.
e) Flow meter electronics shall be microprocessor based and shall include pre-amplifier,
converter, transmitter electronics and integral output meter. The indication on the
output meter shall be digital with engineering units.
0 The mass flow meter shall be capable of computing field density and shall incorporate
temperature sensor flow fluid temperature measurement. Whenever required, the flow
meter electronics shall have capabi lity to compute vnliimPtri, flow rates.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
The meter electronics shall be protected against transients induced by lightning and
power supply surges. Transient protection electronics shall preferably be provided in
the terminal block. The transient protection shall meet the requirements specified in
IEC-60587.
Unless specified otherwise in the job specification, the performance requirements for
the mass flow meter shall be as follows:
Flow meter accuracy: + 0.2% of mass flow rate for liquid service.
± 0.5% of mass flow rate for gas / vapour
service.
Flow meter repeatability: ± 0.1% of mass flow rate for liquid service.
± 0.25% of mass flow rate for gas / vapour
service.
The performance requirements specified above excludes the effect of zero stability of
the flow meter on these parameters.
Flow accuracy shall be maintained between the minimum and maximum flow. Where
only normal flow is specified, the maximum and minimum flows considered for the
purpose of sizing shall be:
Maximum flow = 1.4 times the normal flow
Minimum flow = 0.4 times the normal flow
When only maximum flow is specified minimum flow shall be considered as 0.2
times the maximum flow for sizing the meter.
The maximum pressure drop at meter maximum shall not exceed the allowable
pressure drop across the meter specified in the data sheet.
The meter shall be selected such that both accuracy and allowable pressure differential
across the meter are complied.
4.9.6 Ultrasonic flowmeter
4.9.8 Vortex meter shall be considered where high rangeability is the prime requirement.
4.9.9 Differential Pressure type flow transmitter shall meet all the requirements specified in clause
2.16.
4.9.10 Wedge flow meter shall be considered in slurry services or where powder deposits may form.
However, Diaphragm seal type DP transmitter shall be provided along with wedge flow
meter duly calibrated with both sensor and the transmitter.
4.10.1 Control valves shall normally be globe type. Other valve types like butterfly, ball, rotary
plug, angle or 3way etc., shall be selected as per service and process requirements.
4.10.2 Control valve sizing shall be carried out as per ISA S75-01. The valve shall permit upto
150% of normal flow or 110% of maximum flow, whichever is higher. In general, control
valves shall be sized so that the valve opening is as noted below:
4.10.4 Minimum control valve body size shall be 1" in general. Reduced trims can also be
considered.
4.10.5 For globe valves trim characteristics shall be equal percentage type unless required
otherwise. Control valve plugs shall be heavy top guided for single seated valves. Cage
guiding may be used in clean applications.
4.10.6 Anti-cavitation trim shall be selected wherever cavitation is expected in the valve. For
flashing services and hardened trim shall be used and anti-cavitation trim shall not be
provided.
4.10.7 Noise from control valve during operation shall be limited to OSHA specified level or
better. The maximum allowable noise is 85 dBA SPL (Sound Pressure Level). Source
treatment for noise may be performed by using special trims like low noise trims, in case
noise exceeds the specified level. Other methods based on merit are also permissible.
4.10.8 Valve seat leakage shall be minimum class IV as per ANSI/FCI 70.2 unless tight shutoff
requirement is required as per the P&ID.
4.10.9 Flanged bolted type gland packing boxes shall be used. Packing shall normally be PTFE on
liquid and gas service up to 200°C (design). Graphite/grafoil shall be used above
200°C(design) temperature. Asbestos based packing material shall not be used.
4.10.10 Bellows seal shall be used where it is required to isolate the packing from the process fluid
or where no leakage to atmosphere can be tolerated like toxic, explosive and precious fluids.
4.10.11 Material used for trim shall be minimum SS 316, with guide bushing of hardened stainless
steel like 440 C, 17-4 PH. For higher pressure drops (more than 10 kg/cm 2) or erosive and
slurry services and in general for all steam services, flashing and cavitating services, plug
and seat shall be stellited.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Special cases may require 17-4 PH seat ring and 440 C solid plugs or other materials like
Hastelloy, Monel etc.
4.10.12 Valve actuator shall be pneumatic spring opposed diaphragm type, in general. Piston type
actuators may be used for very high shut off pressure requirements. Additional equipment
including volume bottle necessary to meet fail safe condition shall also be included in case
double acting piston type actuator is selected. In either case, actuator shall be able to
withstand maximum shut-off pressure (1.5 times of design pressure) with the minimum
instrument air pressure specified.
4.10.13 Whenever limit switches are specified as inductive proximity type, these shall meet
NAMUR (DIN-19234) requirements.
4.10.14 Solenoid valves, wherever used, shall be universal and continuous rated type with class H
coil insulation. These shall be SS body as a minimum.
4.10.15 Self-actuating regulators for flow, pressure and temperature shall be used where loads are
constant and requirements of precision and accurate controls are not stringent.
4.10.16 The actuator shall be painted as below:
Items like air volume tanks etc., supplied as an accessory along with the actuators, shall be
painted as per corresponding actuator.
Whenever flangeless on-off valve body design is specified, following shall apply:
Wafer type or lug type body design for butterfly type on-off valves body size up to
6 inches.
Lug type body design for butterfly type of on-off valve body size more than 6
inches.
4.11.2 For on-off valves with fire safe design, flanged body construction shall only be acceptable.
4.11.3 For all services where full port valves are specified, following shall apply:
Port size shall be equal to line size for rating up to ASME Class 1500.
Port size shall not be less than one size than the line size for rating ASME Class
2500 and above.
4.11.4 For steam jacketed valves, the body and port size shall be one size lower than the on-off
valve end connections.
4.11.5 On-off valve body, bonnet, bottom flange, line flanges and other pressure containing
assemblies shall be of the same material of construction as specified for valve body.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
The valve design shall ensure valve seat and body protection against thermal expansion
of the entrapped fluid when the on-off valve is fully close.
For size up to 4" and rating up to ASME Class 300, the on-off valve shall have floating
ball design. For ratings ASME Class 600 and above, floating ball is acceptable for
sizes less than 2". For higher sizes trunion mounted ball design shall be provided.
4.11.7 Rotary type on-off valves like Ball valves, butterfly valves etc. shall have blow out proof
shaft guiding design.
4.11.8 Guide bushing shall be of a sufficiently hard material to resist side thrust on the plug or
shaft.
4.11.9 Vendor shall be responsible for trim design and selection of the on-off valve. However, it
must meet the following minimum requirements:
Vendor shall select proper material pairs, surface finish, hardness and clearances to
avoid galling.
For all on-off valves including 3-way type of valves, stem and plug shall be
detachable and shall be attached together by suitable threaded design secured with
a pin to avoid plug rotation during operation.
4.11.10 Trim material and actuator colour shall be as specified for the control valve.
4.11.11 Leakage class of on-off valves shall be as specified in data sheet, where no class is
specified it shall be Class IV.
4.11.12 For on-off valves specified with Class VI / bubble tight (as per API) leakage class,
vendor shall select the soft seat (elastomer) material suitable for the process conditions
i.e., shut off pressure, maximum temperature and process fluid. Metal seated on-off
valves meeting the leakage class shall also be acceptable.
4.11.13 For application in vacuum service, vendor to provide inverted packing design suitable for
vacuum service. For pressure-cum-vacuum service, the on-off valve shall have dual
packing design suitable for the application. Dual packing design shall also be provided
for on-off valves in toxic service, with a facility to connect inert fluid between the
packings.
4.11.14 Valve actuator shall be designed to move the valve to the failure position as specified.
For failure position specified as 'fail-locked', vendor shall provide air reservoir with all
required accessories to meet the fail lock position of the valve.
4.11.15 Whenever double acting springless type of actuator is unavoidable, all accessories like
pilot valves, booster relays, non-return valve, pressure gauge, volume tank etc. shall be
provided to ensure desired action on air failure.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
4.11.16 The volume tank shall be of carbon steel construction and sized as per ASME Section
VIII with design pressure of 10kg/cm2g as a minimum. Each volume bottle shall be sized
for a minimum of 3 valve strokes
4.11.17 The actuator casings and diaphragms shall be designed for minimum twice the maximum
pneumatic operating pressure of the on-off valve.
4.11.18 Vendor shall be fully responsible for sizing and selection of correct actuator, while sizing
the actuator vendor shall consider minimum actuator thrust equal to two times (2) the
total force induced by shut off condition and the force required to overcome packing
friction.
4.11.19 Wherever the valves are indicated as fire safe, they shall be tested for fire safe as per BS
6755 (Part-2) when the valves are supplied with metal-to-metal seats and shall be tested
as per API 607 latest edition when the valves are provided with soft seats.
4.11.20 Wherever fire safe actuator and controls have been asked for, actuators and all
accessories such as solenoid valves, air volume bottles etc. shall meet the fire proof
requirement to ensure normal valve operation even during and after exposure to fire.
Vendor shall clearly define the schemes they propose to achieve the above requirements
and ensure that the proposed schemes shall meet the requirement in terms of type of
exposure and exposure time of the testing procedure given in BS 6755/API 607.
4.11.21 Vendor shall furnish type test certificate duly witnessed by third party inspection agency
like M/S LRIS,BV,DNV,TUV etc. for fire safe testing of valve, actuator and controls for
the offered models.
Digital smart positioners or field bus type of positioners with diagnostic capabilities shall be
provided as per job specific requirement. These shall meet the following minimum
requirements:
The positioner sensor and sensing mechanism shall be rugged and shall not be affected
by the line/valve vibration. The performance of the positioners shall be immune to
above vibration.
The positioner's output and input range shall be field adjustable without any hardware
modification. The output from the positioners shall be available for both single acting
as well as double acting actuator.
Control valve's operating signatures in the form of hard copy and soft copy for each
control valve provided with smart positioners shall be supplied. The necessary software
for advanced control valve diagnostics like seat ring condition, gland packing condition,
actuator leakage etc. shall also be included.
Fieldbus positioner shall have the capability to perform functions like PID etc.
4.13.1.1 All pressure relieving devices shall be designed in accordance with ASME code for 'Boilers
and Pressure Vessels', API-521 and Indian Boiler Regulations. The pressure relief valve
sizing shall be as per API 520. For mixed phase fluids, sizing shall be as per Leung-Omega
method (or Diers) sizing shall be followed. The orifice sizing, area and designation, valve
size and rating shall be as per API RP 526.
4.13.1.2 Pressure relief valves shall be full nozzle full lift type except for thermal relief valves.
4.13.1.3 Conventional valves shall be specified for constant back pressure while bellows seal type
valves shall be specified for variable back pressure. Pilot operated pressure relief valves
shall be used when Back pressure is greater than 50% of set pressure or when the difference
between operating pressure and set pressure is within 10% of the set pressure.
4.13.1.4 Lifting lever shall be specified for steam, air or water above 65 degree service. Open bonnet
shall be used for steam service.
4.13.1.5 The percentage accumulation in case of pressure relief valves/safety valves shall be as
follows:
Steam Service
Liquid for thermal Relief 25/ 10% (as per Process requirement)
4.13.1.6 3/4" x 1" threaded (NPT) modified nozzle type valves with typically 0.38 cm 2 orifice size
shall be specified for thermal relief. However, if discharge is connected to flare or with
variable back pressure more than 10% of set pressure, 1D2 flanged valves as per API-526
as a minimum to be provided.
4.13.1.7 The body material shall, as a minimum, be as per piping specifications. Nozzle and disc
material shall be SS 316 as a minimum with machined stainless steel guide and spindle.
Whenever semi nozzle designs are unavoidable, body material shall be atleast same as
nozzle and disc material.
4.13.1.8 The spring material of pressure relief valves shall be as follows unless otherwise necessary
because of process conditions;
4.13.1.10 Where permissible, screwed connections shall be used on sizes 3/4" and below.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
4.13.2.1 Rupture discs shall be reverse buckling type, in general and shall be supplied in pre-torqued
holder assembly, which shall fit inside the inner diameter of the bolt circle of standard
flanges. Disc material shall be compatible with the vessel contents and shall be consistent
with the bursting requirements. Inconel discs shall be used above 100°C if compatible with
the process fluid.
4.13.2.2 When rupture disc is used upstream of a pressure relief valve, a pressure gauge shall be
provided on the downstream of the disc to indicate any rupture of the disc in addition to an
excess flow check valve. In addition combination capacity factor of 0.9 shall be used for
sizing unless the combination has been tested and approved for any other combination
capacity factor.
4.13.2.3 The bursting tolerance of the rupture disc shall be 5% of the specified bursting pressure or
less, unless otherwise specified.
4.13.2.4 Vendor shall consider 5 nos. rupture discs (1 for testing + 1 for installation + 3 nos. spare) of
the same specifications.
4.14.1 Interlock and Shutdown System shall be an independent system with its own dedicated
primary element except for orifice flow measurement. For orifice flow element, separate set
of tapping for each flow transmitter for shut down / interlock shall be considered.
4.14.2 The system shall be designed fail safe and shall meet the following requirements, as a
minimum:
All initiating contacts shall be close (except limit switches for which contact shall close
when the limit reaches) under normal conditions and shall open under abnormal
conditions.
All relays and solenoid valves shall be energised under normal conditions and shall de-
energize under abnormal conditions.
c) If desired, because of operational or maintenance requirements, adequate trip by-pass
facilities are to be provided with warning lights to indicate that the trip has been
bypassed. Trip bypass alarms shall be provided in local as well as in remote location.
All such by-pass switches shall be key-operated type.
4.14.3 Each shutdown circuit and solenoid valve shall be provided with a switch-fuse unit
separately.
a) Vendor shall be fully responsible for the complete design of Anti surge/performance
control system (ASC) including selection of type of flow element, controller Algorithm,
type of explosion protection, type and operating timings of final control element. Vendor
shall guarantee the performance of machine with the offered ASC system. Wherever
required, ASC system shall be designed in such a way that it is capable of correcting the
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
compressor operating point so as to avoid surge in order to protect machine from possible
damage, to minimize process upsets and to minimize recirculation.
ASC system shall typically consist of but not limited to flow element, flow transmitter,
differential pressure transmitter, ASC controller, control valve and other accessories as
felt necessary by the vendor.
Vendor shall supply all the hardware and software related to the operation and safety of
the equipment. This shall include but not limited to the following;
Design and operation of surge control loop scheme based on offered equipment
performance.
The ASC shall be a dedicated single loop controller on proprietary Hardware Platform or
single/multi loop controllers of common hardware platform such as PLC. The single loop
controller shall be dedicated controller for each Anti-surge or Performance control
application/Tag. Dedicated panel mounted facia shall be provided. The ASC system
when provided on common hardware platform shall be with redundant configuration as
minimum viz-dual processor, dual input/output, redundant communication & dual power
supply system. The multiloop controller/system shall be dedicated for Anti-
surge/Performance applications/Tags of each machine/each machine tag. Unless specified
otherwise dedicated panel facia for each application shall be provided to mount on
hardwired console in control room
It should be able to accept 4-20 mA signal from field or from HIC at purchaser DCS or
at LCP as a manual override to anti-surge control system with bump less transfer.
0 Auto-manual operation with bump less transfer shall be provided.
The controller response time (total time to read input, processing time and output) shall
be as per the machine dynamics and safety and shall be of the order of max. 40-milisec.
Any faster response required based on machine dynamics shall be considered by
vendor. The input sampling interval shall be as per machine dynamics within the
controller response time as above. The processor cycle time shall be considered to meet
the overall response time.
The ASC shall be field proven, specific to the make of machine and for the similar
application in hydrocarbon industries. Vendor shall provide the proven track record for
the offered ASC meeting the above.
The algorithm developed by vendor shall be specific for given application, surge
control, performance, load sharing etc. and shall be field proven for the compressor
make.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Anti surge controller shall not be used for performing any other machine related inter
locks/logics.
p) The ASC system vendor shall be fully responsible for the sizing and selection of the anti-
surge valve. Vendor to provide the sizing calculations duly vetted by ASC system
manufacturer.
Machine Monitoring system shall be provided for continuous monitoring and indication of
machine parameters like vibration & axial displacement, bearing and winding temperature,
key-phasor etc.
4.15.2.1 Vibration and displacement monitoring system shall be as per API-670. The extent and type
of monitoring shall be as defined elsewhere. However, vendor shall furnish any additional
requirements for monitoring deemed essential by them with reasons. Two probes at 90
degree apart for each location shall be provided and connected to same dual channel monitor
for vibration monitoring.
4.15.2.2 The machine monitoring system shall be provided with preferably built in intrinsically safe
barrier and shall be duly mounted in separate panel. However, separate terminal blocks shall
be provided for terminating the field cables for maintenance purpose. Direct cable
termination on modules shall not be considered.
4.15.2.3 For MMS the display unit shall be provided at local control panel with necessary statutory
certification. Alternatively purged enclosure is also acceptable with necessary certification.
4.15.2.4 The sensing probe shall be accessible for adjustment, repair and replacement without
dismantling the machine.
4.15.2.5 Vendor shall provide hardwired Voted contact output of each parameter for Pre trip and trip
alarms for alarms/ interlock in purchaser's control system. The alarms/trips of the channels
within each monitor/ Module can be grouped together and common pre-trip alarm and
common trip contact for each monitor/ Module shall be provided. 4-20 mA signals from
Vibration & Temperature Monitoring System racks to DCS system are not required
separately, unless specified and vendor to ensure that all the parameters are available
through serial interface. For multi racks, vendor shall provide common serial interface
through multi drop link.
4.15.2.6 In addition to this, it shall be provided with necessary hardware (communication gateway
module) including the cable for serial data communication from monitoring system to
purchaser's DCS for machine monitoring through purchaser's DCS via redundant serial
data interface. This serial link shall be RS 422 / RS 485 with MODBUS RTU protocol.
Vendor shall furnish all details like pin configuration and tag number wise MODBUS
address mapping list etc. for smooth interfacing of this communication link with DCS.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Vendor shall also provide necessary hardware and software for providing raw data to
conditioning monitoring system for each rack.
4.15.2.7 Vendor shall also supply one common laptop based configuration unit for the package unit
with required configuration software (refer clause 4.17) and hardware for configuration of
MMS system including the serial communication cable required between configuration unit
(laptop) & MMS monitors.
Key phasor system shall be provided by vendor for performing analysis of vibration signals
to determine machine malfunctions. It shall consist of a proximity probe and transmitter,
extension cable etc. and other accessories to make the system complete. Vendor shall
provide necessary reference on the shaft to determine one-per-turn occurrence.
Monitors shall be four channel types and shall meet the following specifications as a
minimum:
Continuous channel monitoring with each channel input from one probe. Readout
scale shall read higher of the sensors.
Each channel shall have two independent alarm levels one for pre trip alarm and one
for each trip and that can be set continuously over measurement range. Two relay
contacts for each pre-trip alarm and trip alarm per channel shall be provided.
LED lamps on monitor front for each channel to indicate pre-trip alarm, trip-alarm and
circuit fault conditions.
e) Selector switches on monitor front to read vibration/ displacement pre-trip alarm and
trip set points for each channel shall be provided.
a) Sensor shall be three wires RTD element of platinum having 100 ohms resistance at
0°C.
The temperature sensor, cables, terminal heads, junction boxes etc. shall be capable of
withstanding the mechanical vibration and environment of a rotating machinery
atmosphere.
Continuous six channel monitoring with each channel input from each RTD.
Read out scale shall read higher of the six temperatures.
Each channel shall have two independent alarm levels one for pre-trip alarm and
one for trip alarm and that can be set continuously over measurement range.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Selector switches on monitor front, to read temperature, pre-trip alarm and trip set
points for each channel shall be provided.
Analog output 4-20 mA DC isolated signals shall be provided for each channel
for remote indication, if specified.
4.15.2.11 Wherever MMS is not specified, vendor shall provide suitable transmitter for all the
vibration and axial displacement, temperature, key phasor to provide 4-20mA signal to
purchaser's control system.
4.15.3.1 Digital microprocessor based system mounted in standalone cabinet and located in rack room
shall be provided. Fault tolerant triple modular redundant (TMR) system shall be supplied
unless otherwise specified in Job Specification.
4.15.3.2 HMI for operator interface shall be supplied loose with all mounting accessories for mounting
this HMI in purchaser's hardwired console in general. This shall include all basic features of
governor to enable operator to do all control and monitoring operations from console itself
4.15.3.3 This shall include features like assignable speed range, adjustable speed set point, remote
speed set point input, digital speed indication, adjustable speed ramp, override for testing the
external over speed trip system etc.
4.15.3.4 It should be able to accept 4-20 mA signal from HIC at purchaser's DCS or LCP as a manual
override to governor and pass on the same, after a bump less auto / manual selection and
local / remote selector switches configured in speed governor (shall be possible through
HMI) to governor valve as manual control.
4.15.3.5 Vendor shall provide all hardware & software in the system (including the cable for serial
data communication from system to purchaser's DCS) for serial communication link for all
data transfer from governor to purchaser's DCS. This serial link shall be RS 422 / RS 485
with MODBUS RTU protocol, vendor shall furnish all details like pin configuration and tag
number wise MODBUS address mapping list etc. For smooth interfacing of this
communication link with DCS.
4.15.4.1 If accumulators are used with nitrogen for lube oil dampening at the desired pressure to meet
the system requirement the following instrumentation with the accumulator to be provided
by vendor:
Accumulator shall have charge kit with isolation valves and connection hoses.
Standard nitrogen cylinders available in India are at pressure of 140 kg/cm 2g with
standard connection sizes. Vendor shall provide the complete regulator system with
protection for charging nitrogen from nitrogen cylinder to accumulator at the desired
pressure. Regulator shall be suitable for the inlet pressure variation of 140 to 150
kg/cm2g while charging with suitable inlet connection to match the Nitrogen cylinder
connection. Regulator system shall have pressure indicator, regulator, relief valve,
needle valve etc. as a minimum. Material of construction shall be stainless steel.
4.15.5 The compressor loading-unloading scheme for reciprocating compressors shall be provided
as per the minimum requirements specified in the job specifications. Manual as well as
automatic schemes shall be provided.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
4.15.6 Emergency switch shall be provided in the local panel/local. All such switches shall have a
protective cover to avoid inadvertent shutdown.
4.15.7 Vendor shall provide the following common alarms for purchaser:
4.16.1 All system cabinets, marshalling racks and hardwired consoles shall be free standing and
enclosed cubicles type. All these items shall have bottom cable entry.
4.16.2 Cabinets shall be fabricated from cold rolled steel sheet (CRCA) of minimum 2.0mm
thickness suitably reinforced to prevent warping and buckling. Doors shall be fabricated out
of 1.6 mm thick CRCA sheet. Cabinets having modular construction and with basic frame
structure of heavy duty aluminium shall also be acceptable.
4.16.3 Cabinet/Console finish shall include sand blasting, grinding, chemical cleaning, surface
finishing by suitable filler and two coats of high-grade lacquer with sanding between coats.
Two coats of paint in the cabinet colour and a final coat after assembly at site, shall be given
for non-glossy high satin finish.
4.16.4 In order to remove dissipated heat effectively vent louvers backed by wire fly screen shall be
provided. Further, ventilation fans shall be provided wherever required. High temperature
annunciation shall be provided on operator console.
4.16.5 Illumination shall be provided for all cabinets by fluorescent lamps, which shall be operated
by door switch.
4.16.6 All cabinets/racks/consoles shall be adequately sized to avoid any congestion. Wiring shall
be done as per guidelines provided in clause 4.2.14 of this specification.
4.16.7 The height and colour of the cabinets shall be inline with other equipments being installed in
the control room.
PART II
ENGINEERS
INSTRUMENTATION OF 6-52-0052 Rev. 3
Oar 1#112,1 eiecnte ,,o++1,
INDIA LIMITED
A Go„ of India Undellaktng) PACKAGE UNITS Page 48 of 58
1.2 Clause 1.1 above broadly covers the items required for any typical plant, however vendor
shall supply all necessary items to make the installation and commissioning work complete
in all respect, irrespective of whether these have been explicitly included in their scope or
not.
1.3 Salient feature and minimum requirement for some of the main installation materials is
being described in the following paragraphs. For items for which no specification has been
provided, vendor may follow their own specifications and prevailing international standards.
1.4 Cables
1.4.1 All cables shall have PVC insulated primary insulation of cable shall be 85°C Polyvinyle
Chloride type as per IS-5831 and inner and outer sheath of cable shall be flame retardant
made of extruded PVC Type ST-2 at 90°C as per IS-5831. Oxygen index of PVC shall be
over 30% at 27 °C+2 °C and temperature index shall be over 250°C. However, Polyethylene
(PE) insulation shall be provided in IIC area classification.
1.4.2 In general cables shall be flame retardant as per standard IEC 60332 Part 3 Cat.A. However,
cables with fire-safe valves shall be fire resistant also as per the following.
1.4.2.1 The insulation grade shall be 650 V/1100 V as a minimum and shall meet insulation
resistance, voltage and spark test requirements as per BS-5308 Part-II.
1.4.2.2 All cables shall be twisted and armoured. Armour over inner jacket shall be of galvanised
steel wire/flat as per IS-1554 part I.
1.4.3 For signal and control cables, inner jacket colour shall be black. Outer jacket colour shall be
light blue for intrinsically safe application and black for others. For thermocouple extension
cables the inner and outer jacket colour shall be as per IEC.
1.4.4 Maximum DC resistance of the conductor of the completed cable shall not exceed the
following:
1.4.6 L/R ratio of adjacent cores shall not exceed 40 [tH/Q for cables with 1.5 mm 2 conductor and
25 p,H / Q for cables with 0.5 mm 2 conductor.
1.4.7 The drain wire resistance including shield shall not exceed 30 ohms/km.
1.4.8 A pair of communication wire shall be provided for multipair/multitraid cables. Each wire
shall be 0.5 mm2 of plain annealed single or multi-strand copper conductor with 0.4 mm
thick 85°C PVC insulation. Insulation shall be green and red colour coded.
1.4.10 Running length of the cable shall be printed on the outer sheath at least at every 5 metre
interval.
Single pair shielded signal/alarm cables shall be used between field instruments and
junction boxes/local control panels.
Multipair individually and overall shielded signal/alarm cables shall be used between
junction boxes/local control panels and control room, in general.
The single pair and triad cables shall be of 1 5 mm 2 conductor size made of electrolytic
copper conductor of 7 strands with each strand of 0.53 mm diameter, multipair cables
with 0.5 mm2 conductor size shall have 16 strands of annealed electrolytic grade copper
conductor with each strand of 0.2 mm diameter, multi triad cable or multi pair cable
with 1 5 mm2 conductor shall have 7 strands with each strand of 0.53 mm diameter, as
per the job specification.
Shield shall be aluminium backed mylar/polyester tape bonded together with the
metallic side down helically applied with either side having 25% overlap and 100%
coverage. The minimum shield thickness shall be 0.05 mm in case of single pair/traid
and 0.075 mm incase of multipair/triad cable.
Drain wire shall be provided for individual pair and overall shield which shall be 0.5
mm2 multi stranded bare tinned annealed copper conductor. The drain wire shall be in
continuous contact with aluminium side of the shield.
All multi pair cables shall have 6 pair/12 pairs only while multitriad cable shall have 6
triads/8 triads only.
1.4.12 Control Cables
Single pair control cables shall be used between field mounted solenoid valves and
junction boxes/local control panels and shall meet the requirements specified in para
1.4.11 above.
Multipair control cables shall be used between junction boxes/local control panel and
control room mounted devices in general. These cables shall have only overall
shielding.
c) These control cables shall have 1.5 sq mm conductor size with 7 stranded conductors of
annealed electrolytic grade copper, with each strand of 0.53 mm diameter.
1.4.13 Fieldbus Cables
Fieldbus cables shall be 16AWG (1.31 mm 2) for trunk and 18 AWG (0.82mm 2 ) for
spur twisted in pair individually and overall shielded with aluminium mylar tape with
drain wire and armoured. Other parameters shall be as per Type A defined in IEC-
61158-2.
Fieldbus cables shall be single pair or two pairs.
Field bus cable shall be field proven for FF applications.
Fieldbus cable shall comply with H1 cable test specification FF 844.
e) Outer jacket color shall be orange with 3 longitudinal blue stripes for spur cables and
black stripes for trunk cables.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
a) All power supply cables shall be as per IS-1554 Part I and shall have copper/aluminium
conductors depending on conductor size. Minimum conductor size shall be 2.5 mm2 of
copper conductor. For higher sizes (above 16 mm2), aluminium conductor can be
considered. All these cables shall be PVC insulated and armoured.
1.4.18 Any other special cable required for instruments shall also be supplied as per the
requirement. Vendor shall ensure that these cables are armoured type and shall meet all other
requirements specified in para 1.4.1 through 1.4.10, as applicable.
1.5 Cable Glands
Vendor shall supply all cable glands required for glanding the above mentioned cables
at field instrument side, local control panel side, junction boxes side and at control room
side.
All cables glands shall be of nickel-plated brass and shall be double compression type
suitable for armoured cables.
Flame proof glands wherever required shall be supplied with Ex (d) certification.
PVC Cable shrouds shall be provided with all the cable glands.
1.6 Junction Boxes (Non-Fieldbus loops)
Vendor shall supply junction boxes as per the cables selected, wherever required. These
shall be of die cast aluminium alloy (min. LM-6) body and shall be weather proof to
IP65 as a minimum.
These boxes shall have terminals suitable for minimum 4.0 mm 2 cable termination
mounted on rails. 20% spare terminals shall be supplied in each junction box.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Flame proof junction boxes shall be used in explosion proof/ flame-proof instruments
circuits and supplied with Ex (d) certification. All such boxes shall be weatherproof
also.
e) Each junction box shall have a minimum 12 numbers of entries with 20% or 2 Nos. as
spare entries for branch cable and minimum 2 numbers of entries for multipair cable
with 1 No. spare. All entries shall be provided with suitable plugs.
0 Suitable 3-way power junction box shall be considered for higher size of incomer
power cable, which is not matching with the terminals provided in the control panel.
1.7.1 For Fieldbus segment, junction box shall be used for mounting the wiring/ terminal blocks to
terminate the trunk and spurs in the fieldbus networks.
Unless otherwise specified, vendor must use the following type of terminal blocks:
1.7.4 Surge protectors on the field side shall be provided whenever specifically mentioned in job
specification either within the FFJB or along with the instrument.
1.7.5 Sufficient spacing shall be provided inside the Junction Boxes for mounting of field barrier
assemblies, termination and routing of Trunk/ Spur cables to the barrier/Megablocks,
sufficient space shall be provided for installing terminator etc. inside the Junction Box.
1.7.6 For spur and trunk cables, 20 % addition cable entries must be provided. Unused entries
shall be plugged.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
1.7.7 Each junction box shall be provided with sufficient entries with weatherproof, flameproof
plugs, as required. Trunk and spur entries shall be from the bottom.
Vendor shall supply instrument valves (miniature type) and valve manifolds wherever
required.
The hydrostatic test pressure for instrument miniature valves shall be 153 Kg/cm2g for
pipe class upto 600 and whereas for Instrument air lines, it shall be 41 Kg/cm2g. All
valves and manifolds shall be forged type only.
c) Valve body and trim material shall be 316 SS unless otherwise specified. Superior trim
material shall be selected as required by process conditions. Packing material in general
shall be of PTFE.
1.9 Impulse Piping/Tubing
Vendor shall supply 1/2" OD x 0.065" thick ASTM A 269 TP 316 L stainless steel
seamless tubes as a minimum for impulse lines.
Where the pressure (operating) exceeds 70kg/cm2g or if piping is specified as impulse
line, seamless pipes of size '/2" NB of required thickness shall be supplied with material
as per piping class.
Seamless tubes shall have a hardness of max 80 RB as typical.
Steam tracing shall be 10 mm OD copper tubes of electrolytic grade copper.
e) Instrument air tubing shall be 6 mm SS316L.
Vendor shall supply flareless compression type of tube fitting and of three piece
construction.
The fitting/ferrule hardness shall not be less than RB 90 so as to ensure a minimum
hardness difference of 5 to 10 between tube and fittings. The fitting/ferrule shall be of
SS316 material.
Socket-weld type forged pipe fittings of suitable material and rating shall be supplied
for pipe fittings as per Piping Material Specification. The minimum rating shall be 3000
Lbs. Weld neck fittings shall be used where socket weld type are not allowed by piping
class.
Brass fittings, wherever used as per job specification, shall be suitable for use on
copper tubes conforming to ASTM B68 /B68M hardness not exceeding RB 50. All
fitting parts shall be manufactured from Brass as per IS-319 bar stock or equivalent and
shall be nickel plated.
e) All threaded fittings shall have NPT threads as per ANSI/ASME B 1.20.1 only.
Vendor shall supply 6mm OD x 1mm thick SS316L tube for pneumatic signal tubes.
Vendor shall avoid use of intermediate connections and shall estimate single length for
each instrument location.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL - All rights reserved
=
Ogar Rift
ENGINEERS
INDIA LIMITED
STANDARD SPECIFICATION FOR
INSTRUMENTATION OF
STANDARD SPECIFICATION No.
6-52-0052 Rev. 3
PACKAGE UNITS Page 53 of 58
Seamless galvanised, inside and outside, carbon steel pipes used for instrument air
distribution shall be as per IS 1239 class Heavy. In view of difficulty in bending such
pipes, elbows shall be used wherever bending is expected or A106 Gr B pipe shall be
supplied.
Galvanised forged screwed carbon steel screwed fittings of 2000 lbs rating fittings shall
be used.
c) Isolation valves on instrument air service shall be packless gland type full bore ball
valves. .
Instrument air filter regulator of suitable size, range and capacity shall be supplied for
each pneumatic instrument.
The body of the filter shall be anodised aluminium.
c) The filter shall have 5 micron sintered bronze filter element and shall be provided with
manual drain and 2" nominal size pressure gauge.
All cables on the main pipe rack shall be laid in cable duct. Cable ducts shall be of
galvanised mild steel with SS bolts and shall be fabricated as per 'Duct Fabrication-
bolted Construction Details' standard No. 7-52-0254.
All branch cables/tubes shall run on cable trays.
These cable trays shall be made out of galvanised mild steel sheets of 2.5 mm
thickness. Ladder trays shall be of galvanised mild steel. 50 mm x 50 mm x 6mm thick
angle shall be used as a minimum.
The width shall be so selected that 50% of tray space is available for future use.
Suitable SS wire cable clamps shall be supplied for binding the cables/tubes at every
500 mm. Nuts/Bolts used for cable trays fixing shall be SS.
FRP cable trays shall be provided when specified.
1.15 Instrument Support/Structural Steel
a) Vendor shall supply instrument stands, stanchions and other structural steel material
required for supporting the cable trays, impulse lines and instruments.
2.0 INSTALLATION
2.1 Vendor shall be completely responsible for installation of all instruments within their battery
limit, in line with the installation standards (typical) furnished alongwith package
specification.
2.2 Whenever installation is beyond the scope of vendor/contractor, purchaser shall install the
instruments as per the details/documents/drawings provided by the vendor/contractor.
However, in such a case it must be ensured that complete installation materials shall be
supplied.
2.3 All direct mounted instruments like thermocouples, thermowells, temperature gauges,
pressure gauges, pressure switches etc. shall be installed in such a way that they have good
readability and accessibility.
2.4 The capillary of all capillary type instruments shall be supported properly and shall be
protected against mechanical damage.
2.5 All pressure/differential pressure instruments shall be provided with block and bleed/ by-
pass, drain/vent valves etc as per the installation standards, and shall have accessibility.
2.6 All primary piping/tubing (impulse lines) shall have a slope of 1 in 12 on the horizontal run.
2.7 All welding shall be carried out as per the relevant codes with proper electrodes. Any testing
(non destructive) like DP test and radiography on root weld and final weld shall be carried
out as applicable. All consumables shall be part of vendor's scope of supply. Any pre/post
weld treatment as required by the relevant codes shall be carried out.
2.10 Instrument drain/vent connections shall be piped to safe area like oily water sewer or above
pipe racks to avoid accumulation of hazardous fluid in the plant atmosphere.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
2.11 Steam tracing wherever required shall be carried out by 10 mm OD x 1 mm thick coper
tubes and condensate traps shall be provided to collect all the condensate and shall be piped
to the nearest pipe drain funnels.
2.12 All tubes/cables shall be properly laid on cable trays, which shall be supported at regular
intervals.
2.13 Separate routing or physical separation shall be maintained between signal, shut down and
power cables.
2.14 Wherever intrinsically safe system cabling is employed, the minimum separation of 150 mm
shall be adhered between IS (intrinsically safe) and non- IS signal cables.
2.15 The cases of instruments shall be earthed by earthing wire to the nearest earth bus bar for
safety reasons.
2.16 In case the cables are to be buried or laid in concrete trench the same shall be carried out by
vendor. In case civil work is carried out by purchaser, requirement of trenches shall be
provided with prior intimation to client.
2.17 Painting of angle trays, instrument supports and all structural supports shall be painted as
under :-
a) The surface to be painted shall be thoroughly cleaned with brush and sand paper to
remove all scales. After cleaning, one coat of red oxide zinc chromate primer shall be
given conforming to IS-2074 and allowed to dry. One coat of final paint shall be
applied.
Second and final coats of paint of final colour shall be given before handing over the
plant/ commissioning.
2.18 Installation of Systems ( MMS, Analysers etc.)
2.18.1 The system as applicable shall be installed by the system vendor who would be responsible
for installation and termination of interconnecting cables in the system racks/cabinets. All
interconnecting cables shall be identified and the individual cores/wires shall be properly
identified using ferrules. Direct-cross ferruling method shall be used for identification.
2.18.2 All system communication cables shall be laid in covered GI (galvanised iron) trays away
from power cables. Prefabricated cables shall be avoided for interconnection if these are to
be routed out side the cabinets. If unavoidable these should be laid in covered GI trays.
2.18.3 All panels/cabinets shall be properly leveled and secured firmly with the base supporting
structure. However, the consoles and printer stands need not be secured to base structure.
2.18.4 Grounding
Each cabinet, console and other equipment supplied as a part of system shall have
earthling lugs which shall be secured to the 'AC mains earthing bus'.
All circuit grounds, shields and drain wires shall be connected to the 'system ground'
bus which is isolated from 'AC mains earth'. This bus shall typically be 25 mm wide
and 6 mm thick of copper.
The total resistance of system ground shall be less than 5 ohms unless otherwise
recommended by system manufacturer.
c) Safety barriers, if used, shall be secured to 'Safety ground' which shall have typically
ground resistance of less than 1 ohm. The bus shall be designed considering a fault level
of 0.5 A at 250V r.m.s. per barrier.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
2.18.5 All other installation guidelines as recommended by system manufacturer shall be followed.
3.1 All impulse lines shall be tested hydrostatically at 1.5 times the design pressure / maximum
operating pressure. Ensure that instrument and vessel/piping is isolated during this test.
3.2 In case of special instruments/items where hydrotesting is not permitted due to service
conditions, the impulse lines testing shall be carried out by using air or nitrogen.
3.3 After pressure testing, all these impulse lines shall be drained and dried with dry air for 15
minutes to remove any traces of moisture, oil and dust.
3.4 Instrument air lines shall be duly tested for any leak after pressurising and isolating the main
root valve by soap solution and bubbler unit. After isolation, the rate of fall in pressure shall
be less than 1 kPa for every 4.4 metre (1 psi for each 100 feet) of tubing for a test period of 2
minutes.
3.5 All instrument cables shall be tested for continuity and insulation. While meggering the
cables for insulation testing, ensure that all instruments and barriers are isolated at both ends.
The megger testing at site is not required to be carried out for the field bus cables and
thermocouple extension cables. However, for field bus cables and thermocouple extension
cables, the loop resistance and capacitance shall be checked by the contractor before and
after the completion of cable laying.
3.6 All instruments supplied by the vendor shall be calibrated using proper test equipment.
3.7 All instruments shall be calibrated for 0%, 25%, 50%, 75%, 100% and vice versa.
3.11 All displacer type level transmitters shall be calibrated with water or suitable fluids and
corrected for specific gravity.
3.12 All alarm and trip switches shall be calibrated over the entire range, finally set and checked
for alarm/trip points and reset points as per the alarm/trip set point schedule. After setting,
these shall be sealed.
3.13 All control valves, prior to stroke checking, shall be externally cleaned thoroughly. The full
stroke of valve shall be checked for opening and closing. Any adjustment required for
obtaining full stroke and reducing hysteresis shall be carried out. The hysteresis shall not be
more than 1% URV (upper range value) with positioners and 5% URV without positioners.
3.14 Solenoid valve shall be checked functionally for its operation and also compatibility with
respect to barrier.
3.15 Safety valves and relief valves shall be set/ tested by using dry air/nitrogen. Leakage if any
shall be removed by proper lapping of seat and disc.
3.16 All electronic/pneumatic receiver instruments shall be calibrated as per the manufacturer's
instructions. Controllers shall be aligned properly.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
3.17 All special instruments like analyzer shall be checked and calibrated as per manufacturer's
instructions. Prior to testing, all analyzer sample lines shall be thoroughly cleaned by carbon
tetra chloride or any other cleaning liquid. After cleaning, these lines shall be thoroughly
purged with dry nitrogen.
3.19 The accuracy of overall loop shall be within 1% for electronic and 1.5% for pneumatic
loops.
3.20 After performing the calibration of all instruments, the entire loop shall be checked for
proper operation.
3.21 The entire shutdown scheme shall be simulated from the process trip switches/ control
system and the scheme shall be tested for its proper operation prior to start up of the unit.
3.22 If no instrument air is available vendor shall provide necessary nitrogen cylinders with
suitable regulators to carry out the above activity.
3.23.1 All the system functions shall be checked thoroughly for proper functioning. These shall
include but not limited to the following tests:
3.24.1 Loop checking shall be carried out by vendor, which shall include proper functioning and
interconnection of all items in the loop.
3.24.2 All input signals shall be generated in the field and corresponding reading shall be checked
at all corresponding displays.
All the outputs shall be checked in the field, by physical verification of valve stroke or
operation of solenoid valve/pick-up of electrical contactor.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
3.24.3 After loop checking is completed, vendor shall connect back any terminals and connections
removed during loop checking.
3.24.4 For fieldbus loops the segment verification shall be carried out by DCS vendor. Any field
side modifications required shall be carried out by vendor.
4.0 COMMISSIONING
4.1 This activity shall be carried out in a systematic manner so as to avoid any accident to plant
and operating personnel.
4.2 During the plant start up all the instruments calibration, controller alignment, trip point
settings shall be trimmed so as to meet the operation requirements.
4.3 Prior to guarantee run of any package unit, the vital instruments as required by vendor have
to be recalibrated and the results recorded.
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
1.0 GENERAL
1.1 Material selection chart defines the base material requirements for major instrument
items. The materials have been specified as per 'piping class' in which these
instruments are installed. Additional requirements like stelliting etc. shall be selected
based on process conditions.
1.3 For all instruments in sour service requiring NACE as per Piping class, all materials
of construction shall meet the requirements specified in NACE MR 01-03 latest
edition. In addition, any other requirements if specified in respective piping class,
shall also be complied.
1.4 Impulse pipe material shall be as per the corresponding piping class. However, for
Impulse tubing material shall be 316L SS, as a minimum. Better material shall be
selected wherever required.
1.5 This gives details of selection criteria for most of the common EIL Piping Classes.
However, variations may exist from these in jobs and also new piping classes may
arise. In those circumstances, the material selection shall be based on the relevant job
piping classes and evaluation of actual requirements.
1.6 For testing requirement like Radiography, IBR, NACE, Hydrogen testing, Post weld
heat treatment, etc shall be followed as per piping material specification for the
respective piping class.
fiPzrekgi:—
:h ENGINEERS Annexure I to
iaReg INDIA LIMI1B D MATERIAL SELECTION CHART STANDARD SPECIFICATION NO.
14917A 2120,1,61JAMI, una,isonsi
in Govt Of InOta
6 -52 -0052 Rev3
Page 2 of 5
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL — All rights reserved
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL - All rights reserved
A1K, A2K, A22K, A3K, B 1K, B2K, A182 GrF304 SS 316 A312 GrTP304
D2K
B25K A182 GrF304L SS 316L A312 GrTP304L
AIN, BIN, B6N, A26N*, D26N* A182 GrF316L SS 316L A312 GrTP316L
Format No. 8-00-0001-F1 Rev. 0 Copyright EIL - All rights reserved
PRESSURE, DIFFERENTIAL
LEVEL GAUGE PRESSURE AND VACUUM
SL. GAUGE
PIPING CLASS
NO Sensing
Cock Cock Diaphragm
Chamber Element
Body Trim
/ Socket
Al A, A3A , A6A, A8A,A10A, A105 A105 SS 316 SS 316 SS 316
A14A, A19A, A22A, B IA, B6A,
B9A, B13A, B19A, B21A, D1A,
D9A, D19A, E1A, F1A,A5A,
BSA, D5A, F5A
Al 6A, A23A, A26A, A68A, A105* A105* SS SS 316* SS 316L*
B16A, B23A, B24A, B26A, 316L*
B68A, D23A, D26A
A2A, B2A, D2A, E2A, F2A A105 A105 SS 316 SS 316 SS 316
Notes:
* Material shall be hardness controlled and shall comply with NACE MR-0103 latest edition.
For Hydrogen service wetted part material for switches, transmitters shall be SS 316L gold
plated, base material Hastelloy shall be avoided
ANNEXURE-Il
,.. 73
o •-; 6
a
,..., i Z a.
'-' Z
a.
1/..
i "6 '4 Ca
1: - z 5
cn `,..4
00 =
°
=1
F
e
26
ea T.
3 7.
7
2 wl
X
CD
o 5
g a - 6
...: es Z
3 ea
-.?
0
6
E z
o a
c.:,
;..,
-,-
rn -at
g co) 6
as Z
es
CI
0 .
.2i
o.
6
z
72
z ,..C
o6 a>
fig g .
.5-.4 .sto.
t.T.7
o
o
to
0.
i
0
3
6,
6e
oz
a
E-•
n
2
2...
2 :
512
00
F
>, .>
m r: _J
.c eL
I-- .0
0
ci 5 Cr
Lu
1— >, i--.—
m `i) z
LI
as 0
ee
Z
z € E C..)
(I) 0
w =
u., 4-
Lu
z -c
Z a-
ill E
4- X
0 11'
>, -,i,,,
C. 03
CD
0.
0 -..
).- 0
0- C
0
m .15
r e_.
_13
TAG NUMBER AL AH ALL AHH REMARKS
a) x
0 Q)
a
CO -6
1- 0
0 C
> 0
0 0
0 n
-0
•-• W
'O.
c 0
O) 0
"f7) -6
0 0
-0 z0
-o 12
c 1-2
0 a.
w
o) ,--
c_ q,
30 .c)
I-4.•
0 0
C
03 •-
..C- = U3
I- i LI-
N
cr)
1. a-
a)
E 1'
0
w
L Q)
v0
>n .>
CO .
0.. ......-.I
-C
I
-.. 0 0
W°
LLI
8
I– >, I—
0
J3
=
Q0 0
0 C.)
Z-
—= E
(.1) a)
I:t .0
W".-
4.1
Z .0
Z.-.5 4-•
Z CI-
LLI CD
,._ X
0 g)
>, Z
L._ (0
ID=
0.
0 4-•
L. 0
CL c
CD 15 4,
-C 4,
..... :a TAG NUMBER AL AH ALL AHH REMARKS
o LE
L- X
0 Q)
CO .6
I- 0
C
>0
00
0 -
75.
C
0,
.(a) -6
a>
0
o
-0
c2
0 cl.
a)
0) i-
c0
R _a
o
I_ .....
-o o
c
to
:-E F In
I– i c,-
>
In
k'
cS
;
'I'
g "'
z es. 0 ..
z
is 2 7,
t !
g t, Le 7-
0 ...,
s
Ei °
5 s .5
i& 1
,'1":/-
ti ..
i
mm
I
‘-,
te &
P
3
o
n
3
m 9
3 k ,1E
0 x.
L' • °
5 .3-
a
. o
ti g
,
tij
i'
.
2
.
r ?.
i
1 fc
is g 0
-e.:-..
4',
3
z
g g
,
5
t
I 2 g
c. F 0 ,_
a
i i2 z z
z 1U 2
aa 0 ui =
3 Z. .7.- z 1— x
5 il
a u,
t,- ti 8
03g
. 4 — —
. .-
i1t z z
„,
5 5
0. 0
E,
..4
CI
w
1--
—
-J _
< I
— –I
I 0W
" ZO
0
IX Ill
LLI Z
W
Z
(.9
ui 2- z
a_ w
>-
I-
a.
0
0
_,
1
Z E
. E
'-•:-''
o i, t ,,,
o r . V=
. E
9
--i
* X
1 :
E > -0 20
—0 & 0
,-,
3r z CD-, z ••••
1 ;91 P p p 3
zir 1 —
13 --I
1 t 3
0)
11; K 3
q11 a
F, a 2
(I g
11 _ e M ,
Z fa .
I 1 la 0 .r) 2
is I fi @ 0 (7-7 a
- o
a ZT CI f- =
P a
F13 §xg
6 =
gE
* =o:
z FT 2
z 0
0 70
CD ..o
Z
3
a)
R- S.'
CA 9-
Page 515 of 704
0
1-
LU
z Z
— °cc
co
< 1..
0
LL
LL
ch
U
0
U
-J
a_
co
o •
2 z0
Oo re
lc <o.
z6
<C .1-
D a..)
......
20
ce
8
.
2 re ci
8 0 2
1.- 0
0 ct
Lu
1—
0
re
a.
W
0
Lu
-n
re
Co
M CO
0 ....
ct
1.1 _
W
W
w re
11/ co
m 0 <I a
< < ui 0 0 0
m
u a o z 0 w
z 0 0 (X 0
<
2
LLI a
0 Z ° (3j CI.
t=
< 9 <
M ix
F- i ,--
Ill I- W
Gz
III -J 0 -I
2 2.c) m
I- Z
co 0 MZ M
<0 i-ii1 .:t
ga 0 2. -, -, 0 0
I I 1
a-1 n4 m el . ..-1 ni m V' •• IN rfl .1.
ii 8g
1g1
.i.
E
ci2 dc
LI
II-
z ?
.....
1/1
-J
z us
0 -J
P. m
a <
— 2 0
Z6 o m
.13
9
w
Ø
0 0
1--
23= a> ui
_1
_,O m
<
l-
V
c.) z
0
2 P..
re 0 0
0 z
co — --'
0 w o c:3,
us I— ct 0 < us
0 < 1_ us I— so
0 z -J 2 au
pl W
CID o o
-,
O
I-
m
a
0
o
m
u..
La,
oi-
0
o
0
o
2
u
.
0
,„
Fa'<
. m
-) .2
a. M I- I-
- 0
0
J
IX
55
_l
Z
13
Z
0 a <4
,_ 14
z C.,
_< E
I i'
L
w
<4
Z
I—I
d A
1-1- 0
-1
1....1
CI
co
0
x 0
cn
›- ,-1
....
U
g
Z
0
I—I
I— I
0
0_
I—I
IX
U
i
V)
LA
1=1 M
64
U
I—I
l_D
0
_J
1 1
_J
.
as
Ni
P. C.)
z
)-
(n 0
cn _1
m ,:t g
1- ra
a i
1- ix
ce, o U
LA ,z
U 0
> 6
w O LA
V i
1=1 ci
z z
o 0
LD
Z a
1-- 9 O0
<
D
I—
6I-
0
< .=.)6 W6
>u
IX -J
W<
o E
0
Z 1 1
Pi
CE
B
d g
Ø
Z z
ea
0
Q
F-
Lez-v
ort x SOS-Ii91 — 113
JO M OIJOGI 914 01 Jopuoi oto dq uomb IUDSUOD IJONIJM AUD poqmwied ion 91DA/Jd pUD ADM mum otn UI visoxo pawl lou 'pommqxo 'pouooi 'po!doo 'p000poicloi oq ;ou
tog logy luouJooJBo 1190JdX9 9-19/A0JJOU ayl pUD pouool AIMMILLI 9JD 941 " alunn VION1 SH33NION3 APodcud eta JD 9.19A00 ufqoop Dip puo buunuP ;NI
0
z
.e 2
"6 .4,1
e
E ••
z
0 U
0 § 0
O
`6'
z0
ro
.<
toas
E
0.
0
0
o
S2
2t
z
E.
00
es.
0
00 0
Cl)
dz
1;'
6.
"5 0 0
pi Z
0
E
a
LL
2" PIPE
300
WEL HOLES FOR U-BOLTS
ANGLE
50X50X6
REFER
DE AMP"
WELD WEEP HOLE(TYP.)
(TYP.) REFER NOTE-3
6mm THK. 8 SHT. 3 OF 3
6 mm THICK
1751 MS-PLATE
STIFFNER PLATE SIDE VIEW FRONT V EW
DETAIL'?"
TYPE 11-1 TYPE 11-2
Ai iA i 1 iA
2" PIPE 2" PIPE
M12 M12
CLINCH ANCHOR BOLTS BOLTS & NUTS
(QTY. 04 NOS.) (CITY. 04 NOS.)
ISmC 100
II il
F.FLOOR PLTF. GRATING • All WELD TO PLTF. MEMBER
.. ••im., ..I. ......m.m..
•
lialir
MS PLATE MS PLATE
_____Ep. *V 6mm THK. --rp- t / 6mm THK.
a cr•
0 0 in c0 — Tir
in c0 — fiD — tv .—
I
__...4y
14 DIA HOLES 114 DIA HOLES
180 (4 NOS.)
180 (4 NOS.)
250 250
II
r PIPE
2" PIPE
STANCHION\\'‘ r M12
SUPPORT a ANCHOR BOLTS a
a a
STRIPS (WELD) .-
(50Lx25Wx6T) (QTY. 04 NOS.)
. ..■
G. LEVEL ., G. LEVEL 1/1111111
4 • - et"
• LI
. • '
300
6
WEEP HOLE
M12
CINCH ANCHOR BOLTS
QUAINTITY 04 NOS.
MS PLATE
6mm THK. CONCRETE COLUMN
COLUMN DETAIL
WITH ANGLE INSERT
(BY STRUCTURAL)
CONCRETE COLUMN
6mm THK. (WITH ANGLE INSERT)
FRONT VIEW SIDE VIEW
COLUMN DETAIL
WITH INSERT PLATE
(BY STRUCTURAL)
CONCRETE COLUMN
(WITH INSERT PLATE)
j2" PIP
WEEP HOLE
111
WELD TYP
WELD(TYP.)
2" PIPE
WEEP HOLE
WELD TY WELD TYP
0 U-BOLT ASSY.
U-BOLT ASSY. 0 REFER NOTE-4
0 REFER NOTE-4
03
N
WELD TYP
STIFFNER PLATE
(6 THK.) ,;?.
14 DIA HOLES 300
(4 NOS.) 4" MIN. PIPE SIZE 250 WEEP HOLE
NOTE:- WELD TY
DIMENSIONS • & PIPE CLAMPS SIZES SHALL BE
AS PER PIPE DIMENSIONS. 4 . MIN PIPE SIZE
VIEW-AA
FRONT VIEW SIDE VIEW
(HORIZONTAL PIPE)
NOTES:- 1. ALL DIMENSIONS ARE IN M.M. UNLESS OTHERWISE SPECIFIED.
2 PIPE MATERIAL SHALL BE IS:1239 HEAVY GRADE AS A MINIMUM.
3.6 mm DIA WEEP HOLE SHALL BE PROVIDED AT LOW POINT.
U-BOLT ASSEMBLY SHALL BE OF MINIMUM M12 SIZE WITH NUTS AND SPRING WASHERS.
ALL WELD SHALL BE 3mm FILLET WELD FULL STRENGTH.
ADD 50mm WHERE-EVER FIRE INSULATION IS PROVIDED
BOLT SHALL BE TURNED FROM M.S. ROUNDS CONFIRMING TO IS : 432 GRADE 1
8. NUTS AND WASHERS SHALL CONFIRM TO IS : 1363 AND IS : 3138.
2 14-11-11 Revised & Reissued 4■1^>Manoj oriRG /JMS DM
1 01-09-06 Reaffirmed and Reissued MN TGM PM VC
Prepared Checked Stds. Committee Stds. Bureau
Rev.
Date Purpose Convenor Chairman
No. by by Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
DETAILS Page 1 of 14
W
SEE DETAIL - Y SEE DETAIL - X
U,
m"
INLET FACE
WELDED AND
SMOOTH
GROUND 45° ± 2° SMOOTHED
WHEN REQD.
GLOSSED
V (DRAIN)
IF REQD.
A SECTION Z-Z
INLET
d
DETAIL - X
NB
0
ASME CLASS- - - RF
DETAILS Page 2 of 14
INLET FACE
WELDED AND
SMOOTH GROUND
45° ± 2° SMOOTHED
WHEN REQD.
ALTERNATE VENT
LOCATION SHARP EDGE MUST NOT
G (VENT)
REFLECT LIGHT WHEN
IF REQD. VIEWED WITHOUT
MAGNIFICATION
SECTION Z-Z
E- (D-) - 0.01 D
INLET
d
NB DETAIL - X
ASME CLASS- - - RF
DETAILS Page 3 of 14
INLET FACE
WELDED AND
SMOOTH GROUND
SMOOTHED
G (VENT)
IF REQD. 45° ± 2°
WHEN REQD. SHARP EDGE MUST NOT
REFLECT LIGHT WHEN
VIEWED WITHOUT
MAGNIFICATION
GLOSSED
SECTION Z-Z
F = 0.98D
DETAIL - X
DETAILS Page 4 of 14
C
(NOTE-2)
SEE DETAIL - Y SEE DETAIL - X
INLET FACE
WELDED AND
SMOOTH GROUND
SMOOTHED
2 mm
SEE DEATIL - A
INSIDE RADIUS
OF PIPE LESS
1 mm (3/64")
0
0
0
A SECTION Z-Z
F = 1.5d BUT NOT GREATER THAN INTERNAL PIPE DIA "D"
INLET RADIUS - r
(TOLERANCE
MATL- - - - 0.01 r)
d DETAIL - Y
DETAIL - X
NB
ASME CLASS- - - RF TAG NO.- - - -
EQUAL TO r
DETAIL - A
I--I(NOTE-3)
SEE DETAIL - Y SEE DETAIL - X
WELDED AND
SMOOTH GROUND
2 mm
f
INSIDE RADIUS
OF PIPE LESS
1 mm (3/64")
SECTION Z-Z
INLET
MATL- - - -
d
DETAIL - X DETAIL - Y
NB
TAG NO.- - - -
ASME CLASS- - - RF
0.084d ± 0.003d
0.021d ± 0.003d
0.105d MAX
0.1 D MAX
CONICAL ENTRANCE ORIFICE PLATE
DETAIL - A
NOTES :-
DIMENSIONS A,B,C ARE SAME AS FOR SQUARE EDGE ORIFICE PLATES.
DIMENSION-d SHALL NOT BE LESS THAN 0.25" AND NOT GREATER THAN 0.316D.
3. DIMENSION- W SHALL BE GENERALLY SAME AS FOR SQUARE EDGE ORIFICE PLATES AND
SHALL NECESSARILY CONFORM TO FOLLOWING;
W SHALL NOT EXCEED 0.1D WHERE D IS THE INTERNAL DIAMETER OF STREAM PI LINE. /2i13,4_
NB RATING T T
+0 +0
125 250 900 1500 2500 W TOLER. - 0.25 W TOLER. - 0.25
400 600
mm (") 150 300
25 (1) 66.7 73.0 73.0 73.0 79.4 79.4 85.7 3.18 0.51 6.35
40 (11/2) 85.7 95.3 95.3 95.3 98.4 98.4 117.5 3.18 +0.12 0.76 6.35
50 (2) 104.8 111.1 111.1 111.1 142.9 142.9 146.1 3.18 0.79 6.35
80 (3) 136.5 149.2 149.2 149.2 168.3 174.6 196.9 3.18 -0.25 0.79 6.35
100 (4) 174.6 181.0 177.8 193.7 206.4 209.6 235.0 3.18 1.59 9.52
150 (6) 222.3 250.8 247.7 266.7 288.9 282.6 317.5 3.18 1.59 9.52 ± 0.25
200 (8) 279.4 308.0 304.8 320.7 358.8 352.4 387.4 3.18 3.18 12.7
250 (10) 339.7 362.0 358.8 400.1 435.0 435.0 476.3 6.35 SEE 3.18 12.7 SEE
419.1 457.2 498.5 520.7 549.3 6.35 NO2TE 3.18 12.7 NOTE
300 (12) 409.6 422.3
350 (14) 450.8 485.8 482.6 492.1 520.7 577.9 6.35 ± 0.25 3.18 12.7
400 (16) 514.4 539.8 536.6 565.2 574.7 641.4 6.35 6.35 12.7
450 (18) 549.3 596.9 593.7 612.8 638.2 704.9 6.35 6.35 12.7
500 (20) 606.4 654.1 647.7 682.6 698.5 755.7 6.35 6.35 12.7
550 (22) 660.4 704.9 701.7 733.4 6.35 6.35 12.7
600 (24) 717.6 774.7 768.4 790.6 838.2 901.7 6.35 6.35 12.7
-0 C ±0.4
B + 10
RATING RATING R
NB
125 250 125 10600 TO
400 600 900 1500 2500 400 25 00
mm (") 150 300
25 (1) 100 (D-G)
(D2 G)
40 (1 1/2) 100 R-
88 88 88 30
(2) 100 114
80 (3)
100 (4) 114 127
100
150 (6) 88 100 100
127 158
200 (8) 40
114
250 (10) 140 165
114
300 (12) 177
350 (14) 114 114
127 152
400 (16)
450 (18) 100 50
140 177
500 (20) 127 127 127
550 (22) 144
600 (24) 40 140 140 165 203
d G
LEGEND:-
<d TOLER.
FROM I TO TOLER. D - INTERNAL DIAMETER OF THE PIPE
FROM TO ± 0.05
<6.350 0.007 NB - NOMINAL BORE.
< 25.400 - -
6.350 9.525 0.013 d - ORIFICE BORE DIAMETER.
25.400 88.900 2.38
9.526 12.700 0.015 DIMENSIONS IN mm UNLESS OTHERWISE
88.901 104.775 3.18 SPECIFIED.
12.701 15.875 0.020
104.776 127.000 3.97
15.876 19.050 0.023 NOTE:-
127.001 152.400 4.76
19.051 22.225 0.025 FOR BIDIRECTIONAL FLOW BEVELLING SHALL NOT BE
152.401 171.450 5.56
22.226 25.400 0.030 PROVIDED.
171.451 190.500 6.35
25.401 31.750 0.036 VALUES OF T SHOWN IN THIS STANDARD ARE
190.501 212.725 7.14
31.751 38.100 0.043 VALID FOR THE CORRESPONDING W AND d/D
212.726 234.950 7.94
38,101 44.450 0.051 (6) BETWEEN 0.25 AND 0.70 INCL WHEN THE
234.951 254.000 8.73
44.451 127.000 0.064 VALUES ARE NOT SHOWN AND FOR B < 0.25
254.001 276.225 9.53 AND 6 > 0.70, T SHALL BE CALCULATED EVERY
> 127.000 0.0005
xd 276.226 295.275 10.32 TIME AND SHALL NOT BE HIGHER THAN THE
295.276 317.500 11.11 SMALLER OF THE VALUES RESULTING FROM
317.501 336.550 11.91 THE FOLLOWING RATIOS :-
> 336.550 - 12.70 d D D-d
ORIFICE PLATE DIMENSIONS 8 50 8
3 30-05-11 REVISED & REISSUED Manoj G 4 3/JMS DM
2 11-08-06 REVISED & REISSUED MN TGM PM VJN
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
Page 528 of 704
ORIFICE PLATES AND FLANGES STANDARD No.
0 el ENGINEERS
ligar lapeg
Wren eleakeandTIM)
INDIA LIMITED
IA Govt of India Undertaking)
DIMENSIONAL 7-52-0041 Rev. 3
DETAILS Page 7 of 14
SECTION A-A
112" NPT
OR AS SPECIFIED
B 25.4 MINUS
SEAT MACHINED
FOR NUT SUPPORT
Ct -
7° MAX
10±1°
7° MAX
37.5' ± 2.5° 37.5° ± 2.5 °
Cr)
co _t___.
1
—I I-- 0.25" MIN.
0.06"± 0.03 " 0.06" ± 0.03 "
DETAILS Page 8 of 14
1-
=
(..7 0)
o
0
o
Lo
cf)
0)
o
CD
o ce)
‘-.
o co
To-
Cal 1.0 N a- I.0 0 N 177)
LTJ -Ne CO ..- .- N Tr N-
0,/ b O o 0 0 b b zq Z4 0 0
4.)
co ) Zo 0 co r F17
r,
6 24 N .4- Pt V' CD CD r- t, N. N- N- N- ti
co CO co co
.-- .- CD CD CD co Tr CD C.) C.7 .- ..-. ,- co
D
6
a-
o 6
N
6
N
6
N
O
N
Co
N
CO
N
Cri
C•)
C6
C.)
6
C.)
6
C.)
6
C,1
N.:
Tr
cNi
in
CO co co co CD co Tr a) U) in .- .-
,.,..
,_
,...- Cq Co)
cr cfi Cei C.i ai CNi 06 6
N N-
Ci
cv N N N N V) ro C.) 4 4 4 COD
..., in
N. Is N- N. a) .- N N Tr '4". 4 CO co.
in N N N csi Lci C) csi cNi Lci co Co
C) oi — 1— — N N N N N (7)
cr N- Is Cr) Ce) CI el cn .- N N v. Nt v. co C)
CNi N TI Ni Ti 4 Co 6 N N in vi 6
C7)
4
C.)
N N N N N
N CO Cr). N- N Is CD CD N Ps CD a- CD Tr
.c oi cfi Lei 6 .- N i ci Cr) N.: 0 Cr)
;1.-- Cr)
ce)
c)
1—
co
a—
CO
a—
V)
N N
N
siF)
Cf)
.-- co
Tr 3 o
CD
CD
CD N-
co
N. CO
IL i_ (/)
0 _j 111
-I co o o v 4 Tr v
O0 0 Tr
N
,_ N
a-
CD
a- a- N N N N N N
Z CO 2 .4.
CO CO CO
0 (° Ce CO CO CD
,_
CD
,_ co CD Co (0 cc! cc? co CD co
. 1f— a— 1— 1— V— 1— a— N— a-
,-
0 N C) C) 0) q CO 07 '4" N
re CO N 6 a; M a- N 6 C.) 4 N
6 CNi
IS
N
N.:
1.0 CD N ,- CD C.) op ;7 a)
in N.
ti a) s- .- iv- N Vi C.) Tr in in CD CD
.- ,_ r- ..- ,_ ,_ CI co CO 0. N L I) U) N- C)
0 6 CO 6 CD 6 6 N: 6 IS 6 CM cci ai
Cr) C.) C.) in v.) C r) ■Tr Tr in g in co co co co
C.) 0 Cf7 0 a) N v. 0) Nt Co r.- co o CO
Y a) mi N: 6
co
6
O
6
co
6
C.)
1...
CO
0
It)
cl:
a-
.- CO to C■i
Tr
N
CD N N CO
CO .- .— — N N 01 co Tr in CD co N- CD
O CD .- co 0 to 0 U) N. N N- N n- N Tr
0 4
-N-
.--
Co
,-
6
CD
,--
0N
ai
3
N
N-
Z".'")
c7.
CI
4
mr
ct
O
N
ill
g
Co
N:
CO
,t--
v.. 4
N.
N-
CO
cf)
co
Ti
7;
Co — Tr v r.-- 1--. to co v cr v. I`
0. 0) N: CD CO o 6 ' vi N Cr) t•-.: .--
X oi a-
cl-
,-
0
N
CD
N CD)
N
N.
V)
N CD C.7
tli COO ,
`.
N-
N
CD NI- Nt
V) .4. N .- C) CD .(t. N 0 co co
< Co C.) Cl) a) 4 co ai M co Ito C C) N: co CO 6
M CG 0 CD co is N to 0 Co 0 Co O
Cf) cr co CC — '— N N CO C., ct NP Co I.0 co
__
..., ..-. ...... ..-.. .....
s
03 2`-'
LC) ...-.
,-
.._. a- CV C.) cl- CD CO a- a- a- N N N
..-.•
ZE
W E o 0 0 0 0 0 0 0 0 0 0
() 10 0 0 0 0 in o in o in o in o L17 0
Z N Tr in CD ,-. .- N N cv V) Tr ct Lf) I1) CD
u_ (9
z
, o
co
2
I-
DETAILS Page 9 of 14
I-
S 11) CV a) 1.11 0 rs. CD
0 01) co 0
N CV 4- 01 4- N CV U) 0) CV
LT.I -Ne CO .-
ID
.- CV mr CO .- N V) 4- to co ti a)
o b b o rn o b o z.Ni a
co C ,) ZD 0 C1 N N ii) in O
N
co
ZNI
co
Nt Nt Zr CO co r,
CO
r- r-- r-- r-- r- r- r,-
.4- -- co co co - ..- ,_ .- - O a) a) a) 0)
ai ai O O cii CO OD CO CD CD N N N N Ni
a- CV CI 01 01 C1 01 01 C1 4- 4 .4. 4 v.
cr co. CO co co in - N— N— N— a—
...-
CO CO CD CO CO
z.„-i 6 CO
(.7;
CNI
(c)
N co 4 4
v
4
4
4
-4- 4- ONr
a;
4 4 O.4.
a;
-4-
N. N- N- .- .- r r .-• ,- r• .- r r
.-•• co u3 N N 4 • r• ‘- • • r 1-
D) ai ,- c7, N C; CV C71 C741 C71 N CV
CV CO C.1 N- co U) 0 0) r-- N CV 0) CV 01 CV
cNi C1 a- 6 4 .- U)i M 4 ai c(O 6 6 O O
-c 0 CO co a- N- co CO CV a)
II( CO
Cv)
.- 4,- .-- N 01 11' U)
1.‘7 U) (M
O O I-- a) co
r- r-- r,- r• r- r- r- r,-, r,- r•-•
2 Tr 4 v- co oi cNi cNi oi cNi oi oi oi cNi oi c.i
cth (6 Co a) r r r r r r r 1—
LI— CO
I- LLI
-1 -.1
d 0 0 ,4. CV
,.. CV_
, CD 0 0 0 0 1' 4- V'
-4- CO CO co CV CV CV CV N CV CV
Z CO 1
co a) ..- co o ,_ co .- C) a) N
CO 0 co.
Y o? 4 N- C C) U) C•41 ai a; N- C1 0) N: c6
cc; N CO CM v• Z.73 CO CV 0 3 CV N- co
co a— a— N— Z.N—1 CV V) Cr -4- U) CO CO N- rs. co
0 CD s- co ,- CD a- 0 0) C1 CO 0 a) 0 CO
0 1; U) U) ai C') U) C) CO CO C) U) cei oi ci cri
CV U) CO 0 r- u-) 0 U) 0 Co 4- .- r-- co
.- .- .- CV CV 01 Z:7- U) U) up co r- CO co a)
co V' (t) ..- C) .- CD. CO a- CID CO co
cp a) .- N.: N N CO cNi O .- U) C C) c
CD N:
X „: ,-- co co
CA
co 66 .- %- CV
N
N.
CV A 0
.4- -4-
a)
-4- U)
0
CO co ;.7.
< co
cei
01
CO
co
O
a)
<36
co
4
'cot.
co
CV
cri
.-
a-
C')
N-
CS)
M
CV
CD
U)
U)
't
CO
0
N
N-
U)
0
CO
O
CO
CO
U)
co
a;
O
01 cr co co ,-. .- N CV 0) 01 4- -4- co co co
511 0
Z 0
17-- 0
CD
cl\/\
3 30-05-11 REVISED & REISSUED Manoj P/JMS DM
2 11-08-06 REVISED & REISSUED MN TGM PM VJN
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Format No. 8-00-0001-F4 Rev.O Copyright EIL - All rights reserved
I— N-
l
=
(.9 C))
i ...sc
CV
..—
CO
,--
CD
CV CO ..-
LC)
CO
,
1—
0
a)
,-
N.
N-
csi
10
A
a—
4
LO
3
c.;
N.
N-
CV
co
a)
c,..o
CD CD CO CD CO
,_ 0) a) a) 0) a co CD CO
M
cci CO CO N csi cNi csi N N. N: N.:
CO
CV
CC)
CV CV
CO
CV CO CO 4 4 4 ,cr 4 4 4 Tr
O) a) a) a) to ..- (o OD CD CD
1
CD CD CD CO
a- c.i c.i csi c‘i cci ...- oi ai ai oi oi
co CO co co CO 4 v v v 4 4 to to
N. N- N- 0) CV CV CV CV CV CV nt
- NI: aci cl
a)
N- N.: cl 4 4 4 4 4 r- :
V.
N- r-
a— CV CV CV CV CV CI CV CV CV
07 ,- .— l— CV CV o CD CO CO CD cc. cc'
0) 0) ai 01 Ca.) cci cc; CC) CO CD .-
, r CV CV CV CV CV CV CV CO) CO
U- CO
0 I— WJ 0 0 0 0
—1 —
ci 0 0 ,t, CV CV co CV 0 0 CV CV CV
Z 03 =
4 CD CD CO .— a— a— CV CV
0 V. v. 4 v. v. v. v. '4' v. V: v. v. v. Tr
CO CO CD CD CO CD co CD CO CO CO CO co CO
0 CV 0) CD 0) W CD CD V. CV a--
cc 03 CV a— N: Is: tri O) CO .. C 0) CO 4 0)
ci CO Cai CV to CD CD CO CO CD
to N.- a) ,L- .- c71 CV CO CO CT 4 to to co
4 co .4 - ,- - CO to co q rs-
.- v. cc cc
to
CV
cci
CV
to
CV
In
CV Z:;) CO
O
CO
O
CO
cd
CO
,- 4
4
a
to 3 (D
co
O o rs. ,- co to 4 ,- co 0 0. to
0
>- to
co
co
Lc;
0)
cci
0
e—
CO
O
,—
ci
CV
,—
cCD
4
n—
CO
CD
e—
a
O)
N—
(6
O
CV
,-
N
c .i
CV
CV
LO
CO
CV
3
CV
c ci
O)
CV
0 C a—
W. to to to co 0? CD CV N. a— CO Co 4 CO
o z; a> (ci at
4 4 4 4
a
in CO rs-
Lci
CO it
0)
Ili
a)
Or
a— .—
(O 0 a— LO 0 to N- a) Nr CO 0 CD CO Is
.-- ' to ci iri N- ri CA CO CD CD to CA T-
Y
CV CD 0) CO (7) D CO LO CO art
CV CO act CO LO CO CD r- C)
a) a) 4 co v.
CV CO 0) CO .— 9 .- CO v.
0 ci ti to r N 10- cri (c; CA 4
..,.--:
- 1
mr
a—
N.
a—
v-- 71. O)
CV CO
t.0
at
0
CD (?)
0
N.
CO
Is-
U)
CO
0
.--
N Cs/
CO 0 CO 0 LC) CO a— 0) 0 CV CO CO
V. C7) azi N: CO CO CO cci ai a cc; in cNi 0)
X
CV ai o
„-. CV (C) CO 0)
7:";
to 0 CD CV Nr
ts...
to co co
,- .- CV CV CO act LC) LC)
5
co v. CV a— CY) co N. CV 0 CO
< to CO to
o. 0)
Ti co oi ri ri 6 CO N.: cci ai
CO O O CODo r
t` 1.0 0 u, 0 o 2
to co
CV
CO NI- CO CO ,— "" c7, CV CO CO cr 4
........ s,—.
.. cc.. 0. cs. 6, 4- tY
co
Z
—
•.•■•••
E
—
.,..,
—
in
.-
..
CV
■ ••••■
CO
..
ci- CD CO
. r. N
■—
••••
,—
,...., .4—
. ...
r
■—
.......
CV
.......
CV
•••
W E 0 o 0 0 0 0 0 0 0 0
0 to 0 0 0 o to o
° to o to o to o
Z CV ad' LC) co , ,-- CV CV CO CO 4 Nt. to CD
Z 0
—J
I= 0
0,
3a1
3 30-05-11 REVISED & REISSUED Manoj 4/JMS DM
DETAILS Page 11 of 14
I- 4 C)
= 0 co 0 CO CD co N acr
C.0 0 N 00 0) CD to 0 v.)
Ti -SC N CD 0')
LC)
U) CO g N at I,- 0 4 co
a-
cn
N CO
1- a- e- a-
o‘i b b 6 0 0 b b b b b
6 rN ro
N nt
lb
NI-
to
4 co
- Co
t--
b
CD
a
0,
Fs-
P,- r-
r r cp
r--
f?
1--
Co Co CO CO CO CO CD CO
CD CO CD CV) Cc) a- 0) C) C) CO 4 4 4 4
CO CO cri Ch 6 N N N N.: N N N N
05
N N N C.) CY) el 4 4 4 4 co up up co
cr C) C) C) up co r co CD CD CD CO Cc) CO Cr)
c.i
M
cNi
M
cNi
V)
c6
C.)
CO
co
6
4
6
4
oi
4 3 6
co
d
CD
ci
0
d
CO
.a CO 4 M cd N C) Ch 4 M 6 ci cti o
r
r 4
s- co
a-
N
N
Is.
N A
ce)
4
c,)
U)
N
CO
g
CO
CD
Is-
ci)
CO
N
0)
a-
e-
N. N- ti N- N- r-- N. N- N. rs-
w 2 Nr
CC
4 v. in
CA
csi
r oi
r cNi
1- N
r cNi
r c‘i cNi csi cNi c.i
c6 co ■
LL Cl)
IY 0 F-- w
_1 _i N CD CO CO CD CD CO
N N .- a- r .- a-
ci o O az)- CO CO CO e- a- - `-
w Z CO X .4.
0 act v. 4 v. v. 4 v. v. 4 V v. 4 't 4
cc co ai co up c6 co co co co co 6 up co
a
w CO N e-
0 N 0
LO
CO
oi
a)
c6
C:?. CO 0
a
4
c7
N
4
a-
N
In CC
O M N N
: Is:
0 CO N CO
N
CO Cc) CO C)
to N.. 0 1- .- .ICZI N Cc) Ca") 7:1 4 to in co
>- 6
00 cti 6 N. 0) 6 Co 4 r•- ci N cNi
a 6 6 o
., N co
,- N. co co co a- co CO
co 0) ,— %— N N N 01 M Ce) ;7-
w
CO N N. v. 0) CD
0
0 0 iq 0 CV 0) 4 4 6 6 N cCC) N 6
4 4 4 6 6 6 r ce) v.) in co U) o
4 4 0 CO OD CD a- 1- a- a- e- r N
CD 0 ,- N 0 f•••• CO 0 CO Is CO
E CI In q
z 4 6 ri N: ci
Y ...- ui .4: 4 ,-
N CO o :Tr a- o cOO
N i.--- el o r-- 6)
o
.— ,-- N N Cc) V' 0 CO N- N- Co C)
at
Is- Is- co co
z
N CO 0) N Co N .— Nr 0'1 CO
U) 6 N- 6 CO ‘-. c6 c.i M C) U) 4 CO
0 N- ,-- co I N- N .- X .---
4 CD CO 4
0
,- ,- N M CI V' 0 CO N- CO 0)
zw
(7)
X
act
Cq
In
0
0
CO
co
0
a-
Nr-
M
Ca,
a.-
C)
r
CO
CO
N
N
.-
N
0)
N
CO
CO
CO
V)
CO
6
0
Tr
CO
u
0)
cr
0
N
0
co
CO
CO
a>
co
er.
a-
CO
0
N
0
N-
co v. N a- 0 CO act N 0 CD
< CO C.) LO 0 cl: co ai cr.; ri 6 6 N.: 6 cri
M CCD 6 6 co N- N 0 0 LC) 0 0
c,f) Ti- co co .- 4-- ii N Cf) VI act cr uo co
i ,,,_ „...
Lc? .•••■ iff.„), ..... a. .......
...,
. .
.. N
qr. a
CO
. a ..4..
co— --- — ....... ....., ....., ..-..) vv.. '-. %— ' s— CNI CNI
ZE
o o
w
C.1
E co 0 0 0 0
o o
co o
o to o
o uop o
o uP
o
o o
o
Z N NI• In CO ,_ ,_ N N Cf) co 4 4 0 CO
u. 9.
.-
I=
0
0 ►
g -L° A .._
DETAILS Page 12 of 14
5- 609.6 mm ± 1.59
0 > 609.6 mm ± 3.18 "
NB <
- 125 + 2.38
- 0.79
A
NB _> 150 + 3.96
- 0.79
NB < 250
_ ± 1.59
(10)
Y
NB > 300 ± 3.18
(12)
K ± 1.59
DRILLING
CENTRES BETWEEN HOLES ± 0.79
FOR G = 1.6 mm ± 0.79
R
FOR G = 6.4 mm ± 0.40
ECCENTRICITY BETWEEN K AND R DIAMETERS ± 0.79
ECCENTRICITY BETWEEN K AND D DIAMETERS ± 0.79
ECCENTRICITY BETWEEN R AND D DIAMETERS ± 0.79 *
150 ± 0.12 *
NB <
- (6)
+ 0.12
0.
200 8250 *
NB - 0.25
(8 &10)
+ 0.12
300 *
D NB - 0.38
(12)
450 + 0.12 *
NB . ?. - 0.76
(18)
TOLERANCES ON I'
L-LENGTH mm < 305 310 TO 455 >455
-o -0 -0
TOLERANCE mm + 1.6 + 3.2 + 6.4
DETAILS Page 14 of 14
250
G mm H R
D mm (Inches) F
MAX. MIN. mm mm
9.5 (3/8) 14.3 20.2 19.0 6.4 0.8
11.1 (7/16) 15.9 22.5 21.0 7.5 0.8
12.7 (1/2) 19.1 26.9 25.3 8.3 0.8
15.9 (5/8) 23.8 33.7 31.6 10.7 1.6
19.1 (3/4) 28.6 40.4 37.9 12.7 1.6
22.2 (7/8) 33.3 47.1 44.2 15.1 1.6
25.4 (1) 38.1 53.9 50.6 16.7 2.4
28.6 (1 1/8) 42.9 60.6 56.9 19.1 2.4
31.8 (11/4) 47.6 67.4 63.2 21.4 2.4
38.1 (11/2) 57.2 80.8 75.8 25.4 2.4
t\'` I l• japc(A4r-
3 30-05-11 REVISED & REISSUED Manoj ir• G /JMS DM
2 11-08-06 REVISED & REISSUED MN TGM PM VJN
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Format No. 8-00-0001-F4 Rev.0 Copyright EIL - All rights reserved
Abbreviations:
FF Fieldbus Foundation
WC Water Column
6-52-0032 Rev.4
(Men .FleTerFM1,19.
i^ INSTRUMENTS
A Gort of India Undedaking)
Page 3 of 14
CONTENTS
1.0 GENERAL 4
5.0 SHIPPING 14
6.0 REJECTION 14
ANNEXURES:
ANNEXURE - 1: STUD - BOLTS AND NUTS MATERIAL REQUIREMENT
ANNEXURE - 2: GASKET MATERIAL REQUIREMENT
1.0 GENERAL
1.1 Scope
1.1.1 This specification, together with the data sheets attached herewith describes the requirements
for the design, materials, nameplate marking, inspection, testing and shipping of
electronic/pneumatic instruments.
1.1.2 The related standards referred to herein and mentioned below shall be of the latest edition
prior to the date of the purchaser's enquiry:-
ASME American Society of Mechanical Engineers
1.20.1 Pipe Threads General Purpose (Inch)
16.5 Pipe Flanges and Flanged Fittings
16.20 Metallic Gaskets for Pipe Flanges,Ring Joint, Spiral wound
and Jacketed.
EN European Standards
10204 Inspection Documents For Metallic Products
IS/IEC Indian Standards/ International Electrotechnical Commission
IS/IEC 60079 Electrical Apparatus for Explosive Gas Atmospheres.
IS/IEC 60529 Degree of Protection Provided by Enclosures (IP Code).
IEC 61000-4 Electromagnetic Compatibility (EMC) for Industrial
Process Measurement and Control Equipment
IEC 61158 Fieldbus Standard for use in Industrial Control System
IEC 61158-2 Physical Layer Specification and service definition for
Fieldbus
IEC 61508 Functional Safety of Electrical/Electronic/Programmable
Electronic Safety related Systems.
IEC 61511 Functional safety instrumented system for the process
industry sector
IEC 61804 Function blocks (FB) for process control — Electronic
Device Description
IEC 61518 Mating dimensions between differential pressure (type)
measuring instruments and flanged-onshut-off devices up
to 413 bar (41,3 MPa)
ISA International Society of Automation
S 7.3 Quality Standard for Instrument Air
S 50.1 Compatibility of Analog Signals for Electronic Industrial
Process Instruments.
ITK Interoperability Test Kit (latest version)
1.1.3 In the event of any conflict between this standard specification, job specification/data sheets,
statutory regulations, related standards, codes etc. the following order of priority shall govern:
Statutory Regulations
responsibility for the selected materials for their compatibility with the process
fluid and its operating conditions.
b) Selection of suitable sealant liquid for diaphragm seal instruments compatible with
the process fluid and its operating temperature.
1.2 Bids
1.2.1 Vendor's quotation shall be strictly as per the bidding instructions to the vendor attached
with the material requisition.
1.2.2 Whenever a detailed technical offer is required, vendor's quotation shall include the
following:
Compliance to the specifications.
Whenever the requirement of a detailed specification sheet for electronic/pneumatic
instruments is specifically indicated, a detailed specification sheet for each item
shall be furnished, which shall provide information regarding type, material of
construction, performance specification, model number etc. of the offered
electronic / pneumatic instruments. The material specification and the units of
measurement for various parts in vendor's specification sheets shall be to the same
standards as those indicated in purchaser's data sheets.
c) Proven references for each offered model number inline with clause 1.2.3 of this
specification.
d) A copy of approval from local statutory authority, as applicable such as Petroleum
& Explosives Safety Organisation (PESO) / Chief Controller of Explosives (CCE),
Nagpur or Director General of Mines Safety (DGMS) in India, for the electronic
instruments installed in electrically hazardous area along with:
Test certificate from recognised test house like Central Institute of Mining
and Fuel Research (CIMFR) / Electronics Regional Testing Laboratory
(ERTL) etc. for flameproof enclosure/intrinsic safety, as specified in the data
sheet, as per relevant standard for all Indian manufactured equipments or for
items requiring Director General of Mines Safety DGMS approval.
Certificate of conformity from agencies like Laboratorie Central Des
Industries Electriques (LCIE), British Approval Service for Electrical
Equipment in Flammable Atmospheres (Baseefa), Factory
Mutual (FM), Physikalisch-Technische Bundesanstalt (PTB) , Canadian
Standards Association (CSA), Underwriters Laboratories (UL) etc. for
compliance to ATEX directives or other equivalent standards for all
equipments manufactured outside India.
e) Deviations on technical requirements shall not be entertained. In case vendor has
any valid technical reason, they must include a list of deviations tag number wise,
summing up all the deviations from the purchaser's data sheets and other technical
specifications along with the technical reasons for each of these deviations.
Catalogues giving detailed technical specifications, model decoding details and
other related information for each type of electronic/pneumatic instruments covered
in the bid. Information shall include, but not limited to product certifications,
dimensional drawings, Transient Protection, range limits, power supply, Current
draw, vibration effect, power supply effect, Electromagnetic compatibility. For
Field bus instruments, Field bus parameters like available standard function
blocks/Advanced function blocks and their execution time for each block, Device
type, number of link objects, virtual communication Relationships, Basic and
advanced diagnostic features, transmitter failure mode, physical profile type etc.
1.2.3 All items, as offered, shall be field proven and should have completed trouble free
satisfactory operation for a period of minimum 4000 hours on the bid due date in the similar
application with the process conditions similar to those as specified in the purchaser's data
sheets. Items with proto-type design or items not meeting provenness criteria specified
above shall not be offered.
1.2.4 Wherever specified vendor must furnish certified values of failure rates, probability of
failure on demand (PFD) and test intervals for offered items for Safety Integrity Level (SIL)
analysis.
1.2.5 All documentation submitted by the vendor including their quotation, catalogues, drawings,
installation, operation and maintenance manuals, etc shall be in English language only.
1.2.6 Vendor shall also quote for the following:
Universal hand held configurator / terminal for the configuration and maintenance
of instruments with HART output.
Field bus configurator with hardware and software for configuration and
maintenance of field bus devices and also to perform diagnostics and trouble
shooting of fieldbus segments wherever specified.
Two-year operational spares for each model of instruments offered in the bid,
which shall include sensor, electronic module, local indicator, o-ring/gasket set etc.
based on vendor's recommendations.
Any special tool other than those covered under 1.2.6 (a) and (b). In case any
special tools are needed for maintenance of offered instruments, vendor must
certify in their offer.
1.3 Drawing and Data
1.3.1 Detailed drawings, data, catalogues and manuals required from the vendor are indicated by
the purchaser in vendor data requirement sheets. The required number of prints and soft
copies should be dispatched to the address mentioned, adhering to the time limits indicated.
1.3.2 Final documentation consisting of design data, installation manual, operation and
maintenance manual, etc submitted by the vendor after placement of purchase order shall
include the following, as a minimum;
Specification sheet for each electronic/pneumatic instrument and their accessories.
Certified drawing for each instrument, which shall provide dimensional detail,
internal construction and part list, material of construction etc.
Calculations for integral orifice
Copy of type test certificates.
Copy of the test certificates of all the tests indicated in clause 4.0 of this specification.
Installation procedure for electronic/pneumatic instrument and its accessories.
Calibration, Configuration and Maintenance procedures including replacement of
its internal parts.
Device Descriptor (DD) Files for configuring the device parameters (Soft Copy)
i) Common File Format (CFF) files for integrating the device into the system (Soft
Copy).
2.1.2 The range of instruments shall be selected by vendor based on the set range indicated in the
purchaser's data sheet. Where no set range is indicated, vendor may select the same as per
the following guidelines;
The set range shall be 1.1 times the maximum process value or 1.4 times the
operating process value whichever is higher rounded to the nearest ten.
The set range shall preferably be in the middle third of the selected instrument
range.
2.1.3 Measuring element in vacuum service shall have under range protection down to full
vacuum, without undergoing a change in calibration or permanent set.
2.1.4 Unless otherwise specified, diaphragm seal instrument shall meet the following requirements;
Instruments shall have its diaphragm seal (flanged type) integral with the
instrument. In case wafer type diaphragm seal is provided, it shall be supplied with
companion flange.
When purchaser data sheets specify wafer seal type of instrument, vendor shall
include supply of studs, nuts and gasket as per the materials specified in the
purchaser's data sheet. Refer Annexure — 1 attached with this specification for stud
— bolts, nuts and gasket material requirement.
c) The sealant shall be an inert liquid, compatible with the process fluid and process
temperature indicated in the purchaser's data sheets. In general, sealant shall be;
DC 704 or equivalent for all diaphragm seal instruments except for oxygen
and chlorine.
Flouro-lube or equivalent for all diaphragm seal instruments in oxygen and
chlorine.
d) The requirement of spacer ring shall be as specified in purchaser's data sheet. The
material of construction of spacer ring shall be 316 Stainless Steel, as a minimum
unless otherwise specified in the purchaser's data sheets.
e) The span of the offered model shall be selected to ensure zero elevation/zero
suppression equal to the head created by the fill fluid for the specified capillary
length in the data sheet.
2.1.5 Wherever purchaser data sheet specifies integral flow transmitter, vendor shall supply
complete assembly consisting of integral orifice, upstream and downstream meter runs with
end flanges, meeting the following requirements:
Three nos. of integral orifice plates shall be supplied i.e. one is installed and two
are spares.
Unless otherwise specified, material of construction shall be 316 Stainless Steel for
integral orifice and meter run with flanges.
2.1.6 The instrument enclosure shall be suitable for the area classification indicated in the
purchaser's data sheets. Unless otherwise specified, the enclosure shall meet the following
standards;
Weatherproof housing IP-65 to IS/IEC-60529.
Flameproof housing Flameproof/ Ex (d) as per IS/IEC-60079
Flameproof housing shall also be made weatherproof.
2.1.7 Unless otherwise mentioned, end connection details shall be as below:-
Threaded end connections shall be to NPT as per ASME B 1.20.1.
Flanged end connections shall be as per ASME B 16.5.
Grooves of ring type joint flanges shall be octagonal as per ASME B16.20.
Flanged face finish shall be as per ANSI B 16.5. The face finish shall be as
follows:
125 AARH : 125 to 250 microinch AARH
63 AARH 32 to 63 microinch AARH
2.1.8 All electronic / pneumatic instruments in oxygen and chlorine service shall be thoroughly
degreased using reagents like trichloro-ethylene or carbon tetrachloride. End connection
shall be blinded / plugged after the degreasing process in order to avoid entrance of grease or
oil particles.
2.1.9 Electronic Instruments
2.1.9.1 All instruments shall be of state-of-the-art technology and shall be in compliance with the
electromagnetic compatibility requirements specified in IEC-61000-4 standard.
2.1.9.2 Plug-in circuit boards shall be designed and manufactured such that reverse insertion or
insertion of the wrong card is prevented.
2.1.9.3 Electronic instruments shall generally operate on nominal voltage of 24 V DC and shall be
protected against short circuit and reverse voltage. Transmission and output signal shall
generally be 4 to 20 mA DC for analog and smart transmitters. The display of integral output
meter shall be in engineering units for pressure, differential pressure, flow & Temperature
and 100% linear for level.
2.1.9.4 Electronic transmitters with two-wire system shall be suitable for delivering rated current to
an external loop resistance of at least 600ohm when powered with 24 V DC.
2.1.9.5 Terminals for electrical connections shall be clearly identified, and polarity shall be
permanently marked.
2.1.9.6 Peak to peak ripple and total noise level in the analog output signal shall not exceed 0.25%
of the maximum signal.
2.1.9.7 Electrical cable entries shall have internal 'A" NPT threads.
2.1.9.8 Zero elevation/zero suppression shall be equal to minimum of 100% of the span of the
offered transmitter.
2.1.10 Pneumatic Instruments.
2.1.10.1 All pneumatic connections shall be 1/4" NPT, unless otherwise specified.
2.1.10.2 All threaded connections shall be internal, unless otherwise specified.
2.1.10.3 The process input connections and pneumatic output and air supply connections etc. shall be
permanently stamped on the body at a suitable place.
2.1.10.4 Unless otherwise specified, pneumatic instruments shall operate on air supply of 1.4 kg/cm2g
and shall have transmission and output signal of 0.2 to 1.0 kg/cm2g.
2.1.10.5 Instrument air quality shall be as per ISA-S7.3 and shall be free from all corrosive,
hazardous, flammable and toxic contaminants.
2.2 Transmitters
2.2.1 Pneumatic Transmitters
2.2.1.1 Pneumatic blind transmitters shall be of the force-balance type and pneumatic indicating
transmitters of the motion balance type.
2.2.1.2 Transmitters shall have an accuracy of 0.5 % of span.
2.2.1.3 Transmitters shall be supplied with external zero and span adjustments.
2.2.2 Electronic Analog Transmitters
2.2.2.1 Electronic transmitters shall be of the two-wire DC current regulating type. They shall be
provided with integral output indicator. When specified, field mounted external output
meters shall be provided.
2.2.2.2 Electronic analog transmitters shall have an accuracy oft 0.25 % of span.
2.2.2.3 Transmitters shall be supplied with external zero and span adjustments. Flameproof
transmitters shall also have their calibration adjustment from outside, without any need to
remove the cover.
2.2.2.4 Unless otherwise specified, the electronic transmitters shall be certified intrinsically safe.
2.2.3 Smart and Field bus based Transmitters
2.2.3.1 Smart and field bus based transmitters shall be two wire microprocessor based type. These
shall have a non-volatile memory, storing, complete sensor characterisation and
configuration data of the transmitter. All necessary signal conversions and output generation
with the required protocol shall be carried out in the transmitter electronics. Integral output
meter with LCD display shall be provided for all transmitters.
2.2.3.2 Transmitter shall also run complete diagnostic subroutines and shall provide diagnostic
alarm messages for sensor as well as transmitter healthiness. Field bus based transmitter in
addition shall have facility to detect plugged impulse lines, whenever specifically indicated
in purchaser's data sheets. In the event of detection failure, the output shall be driven to a
predefined value, which shall be field configurable.
2.2.3.3 The transmitters with field bus connectivity shall have built in control algorithm like
proportional, proportional-integral and proportional-integral-differential.
2.2.3.4 Whenever specifically indicated in purchaser's data sheets, the meter electronics shall be
provided with in-built lightning and power supply surges. The transient protection shall
meet the requirements specified in IEC-61000-4.
2.2.3.5 The configurational data of the instruments shall be stored in a non-volatile memory such
that this remains unchanged because of power fluctuations or power off condition. In case
vendor standard instrument has battery backed RAM, vendor to ensure that battery drain
alarm is provided as diagnostic maintenance message.
2.2.3.6 Accuracy of transmitters, smart as well as field bus based, shall be as follows:
Type of Transmitter Range of Transmitter Accuracy
Direct 760 mm WC and above Equal to or better than +0.075%
Direct Less than 760 mm WC Equal to or better than ±0.15%
Diaphragm seal 500 mm WC and above Equal to or better than ±0.25%
Diaphragm seal Less than 500 mm WC Equal to or better than ±0.5%
The accuracy is defined as the combined effect of repeatability, linearity and hysteresis.
2.2.3.7 The stability of the transmitters shall be equal to or better than ±0.1% of span for a period of
minimum 6 months, as a minimum.
2.2.3.8 Transmitter shall update the output at least 8 times a second unless otherwise specified.
2.2.3.9 Unless specified otherwise in purchaser's specification, transmitter response time shall be as
follows:
For transmitter range of 760 mm WC and above, the response time shall be equal to
or better than 500 milliseconds.
For transmitter range below 760mm WC, the response shall be equal to or better
than I second.
The response time of the transmitter shall be considered as the sum of dead time and 63.2%
step response time of the transmitter.
2.2.3.10 Unless specified otherwise, the over-range/static pressure protection of the transmitter shall
be as follows:
OVERRANGE / STATIC PRESSURE (*)
Range of Transmitter 0 Pressure Transmitter Differential Pressure Transmitter
Kg/Cm2 Kg/Cm2
0 <®<250 mmWC 20 20
250 < 0 < 1000 mmWC 45 52
1000 < 0 < 5000 45 70
mmWC
5000 < 0 < 10000 45 160
mmWC
1 < ® < 10 Kg/cm2 52 160
10 < 0 < 100 Kg/cm2 160 210
® > 100 Kg/cm2 210 210
(*) However, if the overange/static pressure valve specified above is less than the
maximum/design pressure of service conditions specified in the datasheets, offered
instrument shall be suitable for the maximum/design pressure as per datasheet.
2.2.3.11 In the transmitter, the 'WRITE' option shall be protected through password.
2.2.3.12 Temperature transmitters shall meet the following requirements as a minimum:
Temperature transmitter shall be universal type and shall be able to accept input
from resistance temperature detector (RTD) or thermocouple (T/C) of any type and
range.
Temperature transmitters shall be freely programmable i.e. element type and range
shall be programmable without any change in hardware / software.
Temperature transmitter shall be remote mounted type, in general Head mounted
transmitters shall be supplied when specifically indicated in purchaser's data
sheets.
The accuracy of the temperature transmitter with RTD element shall be as follows:
For temperature range above 350° C, the accuracy shall be equal to or better
than +0.075% of range.
For temperature range with ranges between 350° C to 150° C, the accuracy
shall be equal to or better than 10.15% of range.
For temperature range below 150° C, the accuracy shall be equal to or better
than +0.25% of range.
e) The accuracy of temperature transmitter with cold junction compensation for
Thermocouple element shall be as follows;
For temperature above 350° C, accuracy shall be +0.25% of range.
For temperature between 150°C to 350°C. accuracy shall be ±0.5% of range.
For temperature below 150°C, accuracy shall be +0.75% of range.
2.2.3.13 When HART protocol is specified, the following features must be ensured;
It shall allow multi masters (two for example, primary and secondary) for
configuration, calibration, diagnostics and maintenance. The primary could be the
control system or host computer and the secondary could be the hand-held
communicator.
It shall be capable of implementing universal commands from either of these
locations.
2.2.3.14 In addition to the requirements specified above, field bus based transmitter shall meet the
following requirements;
All instruments must satisfy the requirements of the field bus registration
laboratory with applicable checkmark like foundation field bus, profibus
NutZerorganisation e.v (PNO), or as specified in the purchaser's data sheets.
All instruments shall be polarity insensitive. Also transmitter shall be LAS capable
and provided with line plugging detection, whenever specified in data sheet.
All instruments shall have one no. of Analog Input (AI) block and One no. of
Proportional, Integration and Differential (PID) control block, as a minimum.
All instruments must be interoperable and shall have valid interoperability test
clearance like ITK latest version for foundation field bus or equivalent for profibus
PA, as applicable.
e) The field bus instruments shall support peer to peer communication.
The field bus instruments in hazardous area shall be certified as per entity concept
or shall be FISCO approved as per the requirements specified in the purchaser's
specification.
All instruments shall support EDDL or FDT/DTM requirements, as specified in
data sheets.
Internal Software shall be configured by the vendor including the following
information.
- Serial Number
Device Tag (Tag No.)
- Process Description
i) All instruments shall be capable of supporting incremental Device Descriptor (DD)
for extra functionality and/or software revisions in Device Memory.
2.3 Receivers
2.3.1 Pneumatic/electrical cables shall be such that they permit the instrument internals to be
drawn from its normal mounting position without affecting operation. Pneumatic connection
points shall seal automatically upon disconnection.
2.3.2 Electronic receivers shall be suitable for standard voltage inputs of 0.25 to 1.25 V, 1 to 5 V,
0 to 10 V dc. Any voltage receiver shall not alter the voltage drop across the conditioning
resistor by more than ±0.1% of input range of maximum input voltage.
2.3.3 Recorder pens shall be easily replaceable.
2.3.4 Each recorder shall be supplied with chart-rolls and ink for six months continuous operation.
2.4 Controllers
2.4.1 Automatic control stations including dedicated cascade control stations shall have switches
to transfer control from automatic to manual mode and vice-versa. The transfer shall be
procedure less and shall not produce any bump in the process under control during such a
transfer, the output signal shall not change by more than I% of span.
2.4.2 Cascade control stations shall have a switch to select local or remote set point.
2.4.3 The control settings of the controller shall be readily adjustable from the front.
2.4.4 Controller action shall be easily reversible.
2.4.5 Pneumatic automatic controller shall be easily removable, without disturbing the manual
control mechanism.
2.4.6 Electronic controller shall be easily removable, with the aid of a service station.
2.4.7 Local mounted pneumatic controllers shall be supplied with gauges for air supply pressure
and control signal. The gauges shall be integral with the instrument.
2.5 Accessories
2.5.1 Field Universal Communicator:
2.5.1.1 It shall be possible to perform routine configuration, calibration, display process variable,
diagnostics etc. from a hand held portable communicator, which can be connected at any
location in the transmitter loop. It shall be possible to perform all the above functions on-line
and the loop function shall remain unaffected.
2.5.1.2 There should be no interruption on the output while communicating with the transmitter.
2.5.1.3 Field communicator shall meet the following requirements:
Hand Held communicator shall be universal type and shall be compatible with all
make and models of HART transmitters and Smart positioners, with all engineering
capability like calibration, diagnostics, configuration, inhibition of HART signal,
etc. Similarly Field bus Hand Held communicator shall also be universal type and
shall be suitable for all make and models of FF transmitters and Positioner.
It shall be possible to connect the communicator at any of the following locations
for purpose of digital communication;
Marshalling cabinet serving the transmitter, in safe area.
Junction box serving the transmitter, in hazardous area.
iii) Directly at the transmitter, in hazardous area.
Plug-in type connections shall be provided with field communicator. Necessary
interconnection accessories shall be supplied by the vendor.
Offered communicator shall be dust-proof, certified intrinsically safe and suitable
for outdoor location. Carrying case shall be supplied with each communicator.
When specified in data sheets, the software shall also be capable of configuring
other makes of transmitters.
e) They shall be battery powered with replaceable and rechargeable batteries, suitable
for recharging with 240 V, 50 Hz . In case vendor's standard design does not make
use of rechargeable batteries, then vendor to provide 2 sets of spare batteries.
2.5.2 Remote output meter
2.5.2.1 Remote output meter shall be electronic with LCD display. The display shall be in actual
engineering units.
2.5.2.2 The indicator electronics shall be able to perform square root extraction for flow
measurement
2.5.2.3 Offered indicators shall be certified Intrinsically safe/FISCO, when used in hazardous area
as specified in Data sheet.
2.5.2.4 This Field Bus based field indicator shall be 2 wire segment powered and shall be able to
indicate minimum of 8 signals available in the fieldbus segment, selectively.
2.5.3 Yoke mounted instruments shall be supplied with universal mounting bracket , U-bolt and
nuts suitable for mounting the instruments on a 50 mm (nominal bore) pipe stanchion
(horizontal or vertical)
2.5.4 Air set
Air set, where provided, shall be a combination air filter regulator set with 5-micron filter
cartridge. It shall have a 50 mm diameter pressure gauge to indicate the regulated pressure.
Each air set shall be supplied with mounting bracket and bolts with nuts for surface mounting.
2.5.5 Battery charger
Battery charger shall be supplied with all necessary accessories and shall be suitable for
240V ±10%, 50Hz±3Hz, unless otherwise specified.
3.0 NAMEPLATE
3.1 Each flush panel mounted instrument shall have the following information identified in the
front:-
Tag number as per purchaser's data sheet.
Reading coefficient, if any
c) Pen colour, tag number-wise in the case of recorders.
Each flush panel mounted instrument shall have a back nameplate permanently fixed to it at
a visible place reporting the following information:
Instrument tag number.
Manufacturer's serial number or model number.
c) Manufacturer's name/trade mark.
3.2 Surface mounted instruments shall be provided with only one nameplate.
Local mounted instruments shall have a stainless steel nameplate attached firmly to it at a
visible place, furnishing the following information:
Tag number as per purchaser's data sheets.
Manufacturer's serial number and /or model number
Manufacturer's name/trade mark.
Body material.
Measuring element material.
Range of measurement.
j) Area classification in which the equipment can be used, this shall be to the same
code as per purchaser's data sheets.
5.0 SHIPPING
5.1 All threaded and flanged openings shall be suitably protected to prevent entry of foreign
material.
5.2 Instruments shall be supplied individually, in suitably sealed packing.
5.3 Proper care shall be taken in shipping instruments with diaphragm seals to ensure safety of
the diaphragm seals, extensions, capillaries, where specified.
5.4 All pneumatic / electronic instruments in oxygen and chlorine service shall be separately
packed along with a certificate indicating 'CERTIFIED FOR OXYGEN / CHLORINE
SERVICE', as applicable.
5.5 Proper care shall be taken in shipping instrument accessories clearly indicating the
instrument tag numbers.
6.0 REJECTION
6.1 Vendor shall prepare their offer strictly as per clause 1.2 of this specification and shall attach
only those documents and information, which are specifically indicated in the material
requisition.
6.2 Any offer not conforming to the above requirements, shall be summarily rejected.
3 MB, AID, A4F, A4G, BIB, BID, B5D, AI-193 Gr. B16
BIE, B3F, B4F, B4G, DIB, D2B, DID, A-194 GR. 4
D2D, D5D, D5E, F2D
8. Pressure Element- Bourdon Tube 16. Over Range Protection- 130% of the range or maximum
pressure whichever is higher
9. Element Material- * SS 316 17. Blow Out Protection- Required
NOTES:- This data sheet is indicative only indicating minimum requirement, vendor to develop the detail data sheet during detail engg.
FILE: REQUISITION NO :
NOTES:- This data sheet is indicative only indicating minimum requirement, vendor to develop the detail data sheet during detail engg.
* BY VENDOR
** AS PER INSTUMENTATION JOB SPECIFICATION
FILE: REQUISITION NO :
NOTES:- This data sheet is indicative only indicating minimum requirement, vendor to develop the detail data sheet during detail engg.
FILE: REQUISITION NO :
FILE- REQUISITION NO :
NOTES:- This data sheet is indicative only indicating minimum requirement, vendor to develop the detail data sheet during detail engg.
* Vendor to specify / confirm.
1. `U' length shall be 280 mm for 4" to 6" line, 320 mm for 8" & above size lines and 400 mm for Vessels. Lines less than 4" size shall be blown to 4".
FILE: REQUISITION NO :
l engg
APPD
REV
09000200828c4e2e_A4.xls,Sheet1
A
agreement that they will
Certification 53 Others
54 Manufacturer
Others 55 Model Number
Note: This data sheet is indicative only indicating the minimum requirement, package vendor to develop detail data sheet for
the required instrument.
FILE- REQUISITION NO :
FILE- REQUISITION NO :
VENDOR LIST
PROJECTS
(MR-6041)
THERMOWELLS – 15HD
8. 7 T232 TECHNOINSTRUMENTS
9. 8 T095 TEMP-TECH
11 S524 SIEMENSAG
GENERAL NOTES
1.0 CONTRACTOR shall necessarily procure all the material / equipment forming permanent part of the
unit / plant from OWNER / PMC approved vendors only. This shall include sub-ordered items /
components also. The “Approved Vendors” shall be item specific.
2.0 OWNER / PMC approved vendor list for the various items is enclosed in this section.
3.0 CONTRACTOR may procure material from any of OWNER / PMC approved vendors. However,
current validity, holiday status and range of approval as per EIL enlistment letter, workload,
stability and solvency need to be verified by the CONTRACTOR with vendor before placement of
order. CONTRACTOR is also required to ensure that equipment qualification criteria, specified
elsewhere in the bid document, are also simultaneously met.
4.0 Vendors on OWNER / PMC holiday list shall not be considered for ordering. CONTRACTOR shall
comply with this requirement without any time or cost implication to the OWNER. If a vendor is put
on OWNER / PMC’s holiday list subsequent to CONTRACTOR placing an order, it shall be
CONTRACTOR’s responsibility to ensure quality work and timely supply from the vendor.
5.0 For items not covered in the above list, the CONTRACTOR shall approach OWNER/PMC for that
list or the vendors list shall be approved by OWNER / PMC prior to placement of order by
CONTRACTOR. CONTRACTOR shall list down the proposed suppliers / vendors for such items
and submit the same for OWNER / PMC’s review / approval along with necessary documents /
credentials. “Approval status” documents / credentials to be furnished by the vendors in such
cases shall solely be the responsibility of the CONTRACTOR. OWNER / PMC’s decision on
above shall be final and non negotiable. Non –acceptance of a particular proposed vendor due to
any reasons whatsoever shall not be a cause of schedule and cost implication.
6.0 CONTRACTOR shall make an independent assessment of capability of all the vendors for timely
deliveries of material/ equipment. Any delays in deliveries by vendor(s) shall not be a cause of
schedule and cost implication.
8.0 List of vendors appearing anywhere else in the contract document in case of duplication of the
items at two or more places shall not be considered by CONTRACTOR and shall be superseded
by the vendor list enclosed herewith.
9.0 It is understood that should the name of vendor be changed due to change in their company or
corporate share holding. OWNER may accept such vendors under its new name with prior
approval.
Any such approval shall however, not absolve the CONTRACTOR from any of his obligations
under the contract; neither shall any such approval signify nominations or instruction to use such a
vendor. All approved vendors are deemed to have been freely chosen by the CONTRACTOR at
his own risk.
10.0 The approved vendors list for fabricated equipment (Vessels, Column, Heat Exchangers, Ejectors
etc.) is for fabrication alone. Where mechanical design of the equipment is included in
CONTRACTORS’S scope, CONTRACTOR shall either himself or through his Detailed
Engineering sub-contractor be responsible for designing and obtaining approval/ review of
Mechanical design calculations as per codes/specifications specified elsewhere in the Bid/
Contractor document from OWNER / PMC.
1/2" NPT
(NOTE-1)
CHAIN
UNION 1/2" NPT
(NOTE-2)
THERMOWELL
11 'RN
3--
4 24.10.16 Reaffirmed & Reissued Manoj RG
3 19-07-11 Revised & Reissued Manoj RG RP/JMS DM
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Format No R-O0-0001-F4 Rev () Convrinht Fit - All rinhts rastarvarl
P - BY PIPING
I- BY INSTRUMENTATION
V - BY INSTRUMENT VENDOR
LIST OF ITEMS
CODE DESCRIPTION SIZE ENDS QTY. UNIT CODE DESCRIPTION SIZE ENDS QTY. UNIT
7 NIPPLE 1/2" THXPL 4 Ne
-// ..
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
1.0 GENERAL
1.1 The specification defines the basic requirements of the electrical works/supply in vendor’s scope for the
Agitators of pressure vessel for Acrylates Unit of Propylene Derivative Petrochemical Project, Kochi of
M/s BPCL-KR. This job specification shall be read in conjunction with EIL standard specifications, data
sheets and documents attached with the Purchase Requisition. In case of any conflict amongst various
documents enclosed with PR, the most stringent requirement shall govern and Owner/EIL decision in
this regards shall be final.
1.2 The equipment shall conform to this specification, enclosed data sheets and standard specifications.
2.0 SCOPE
Vendor's scope of supply shall include but not be limited to the following for Agitators of pressure
vessels. Anything required over and above that is specified, for safe and satisfactory operation of the
package shall be included by the vendor in his scope without any cost /time implications to purchaser:
Sr. Description Specified by Remarks
No. Purchaser
(Yes/No)
1 Electric Motor for Agitators Yes
2 Double compression flame proof & weather proof cable Yes
glands and tinned copper lugs for equipments supplied by
vendor.
3 Spares & Tools/Tackles
3.1 Commissioning spares as recommended by the equipment Yes
manufacturer.
3.2 For two years operation and maintenance spares for electrical Yes
items refer elsewhere in PR/PO.
3.3 Special tools and tackles required, if any, for erection, site Yes
assembly and maintenance of motors as recommended by
the equipment manufacturer.
4. Inspection & testing as per the applicable standard Yes
specification & inspection test plan attached with the PR for
electrical items.
5. All data & drawings as per Vendor data requirements, data Yes
sheets, specifications and referenced codes and standards.
3.0 EXCLUSIONS
The following works / item are excluded from the scope of the Vendor:
3.1 Supply of 415V feeders for DOL starters for Agitator motors.
3.2 Supply, laying and termination of power, control & space heater cables from Substation to field.
3.3 All cable trays / trenches for owner’s cables.
3.4 Earthing outside package battery limit.
4.0 UTILIZATION VOLTAGE
Utilization voltage for motors, anti-condensation heaters based on their ratings shall be as listed below:
a.) Motors rated upto 160kW : 415V ± 10%, 50Hz ± 3%
b.) Anti-condensation heaters : 240V ± 10%, 50Hz ± 3%
5.0 SPECIAL REQUIREMENTS
5.1 MV motors (<1100V) shall conform to EIL Specification 6-51-0064 and MV Motor data sheet attached
elsewhere with the PR.
5.2 The enclosure type / area classification requirement for motors and their auxiliaries shall be as listed
below:
S. No. Tag No. Item Description Enclosure Type Area Classification
1. PDE-AM-405 V-405 Agitator Ex-d/ Ex-de Zone-2, IIA/IIB, T3
2. PDE- AM-505 V-505 Agitator Ex-d/ Ex-de Zone-2, IIA/IIB, T3
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
5.3 Motors having enclosure protection Ex-d/Ex-de shall meet the requirements of IS/IEC 60079-1.
5.4 All motors shall be provided with fabricated GI canopy.
5.5 Exact cable sizes of power and control cables shall be finalised during detailed engineering. Provisions,
as required in Vendor’s equipment for termination of the same, shall be made accordingly without any
cost & time implications to Owner. Cable sizes indicated under clause 6.2.5 of specification 6-51-0064
is only for guidance/estimation.
5.6 Vendor to note that the MV motors (415V and upto 160kW) supplied shall be of Energy efficient (IE2)
type as per IS 12615 (2011) or equivalent IEC codes.
5.7 Type test certificate from the authorized agency of country of origin for all hazardous area electrical
equipment/items shall be provided by vendor.
5.8 All electrical equipment for use in hazardous areas shall be certified by CIMFR, PTB, Baseefa, UL, FM
or equivalent independent testing Agency for the service and the area in which it can be used. All the
equipment indigenous and imported shall have a valid statutory approval of CCOE/PESO and copies of
the same (CCOE/PESO) shall be furnished during detailed engineering stage which is mandatory as
per local rules/regulations.
5.9 Cable glands to be supplied with the motor shall meet all the requirement of IS/IEC-60079-0. For motors
and outdoor equipment, double compression type Nickel plated brass FLP/weatherproof cable glands
shall be supplied.
5.10 All lugs to be supplied shall be heavy duty, crimping type and made of copper.
6.0 MAKES OF EQUIPMENT AND COMPONENTS
6.1 List of approved vendors for Electrical equipment/components is as mentioned elsewhere in the Master
Vendor List, attached in the PR.
6.2 In case of imported equipment, the contractor shall furnish the reference list of customers and shall
ensure that type test certificates for similar type of equipment are available, which is essential for
technical acceptability. Additional makes of imported items shall be subject to Owner/EIL’s approval
during detailed engineering.
6.3 Vendor may procure material from any of the listed vendors. However current validity and range of
approval as per EIL enlistment letter, workload, stability and solvency need to be verified by the vendor
before placement of order.
7.0 Variation /Clarification against the standard specification for MV motor 6-51-0064, shall be as per the
MOU agreed with EIL by respective motor manufacturer. No further deviations to PR requirements shall
be entertained.
8.0 LIST OF ATTACHMENTS
S. No. Title Document No. Rev.
1. Data Sheet – MV Motors (415V) A842-PDE-16-50-DS-0501 A
2. Vendor Data Requirement (Electrical) A842-PDE-16-50-VR-6041 0
3. Specification for Energy efficient MV
6-51-0064 1
Induction Motors
4. Inspection & Test Plan for MV Motors 6-81-1032 5
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
The following drawings/documents marked " " shall be furnished by the bidder.
MV MOTOR
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
1. Schedule of Vendor Documents
2. Data Sheets (Duly filled-in)
3. Dimensional/Assembly Drawings : GA Drawing To be furnished along
with motor data sheet
For motors < 75kW as single document in
vendor portal
4. Dimensional/Assembly Drawings : Installation To be furnished along
with motor data sheet
Plan/Mounting Details as single document in
vendor portal
5. Dimensional/Assembly Drawings : Terminal To be furnished along
with motor data sheet
Box Arrangement as single document in
vendor portal
6. Dimensional/Assembly Drawings : Name Plate To be furnished along
with motor data sheet
Drawing as single document in
vendor portal
7. Performance Curves : Speed Torque Curves To be furnished along
with motor data sheet
as single document in
vendor portal
8. Performance Curves : Speed-Current/Time To be furnished along
with motor data sheet
Curves as single document in
vendor portal
9. Performance Curves : Thermal Withstand To be furnished along
with motor data sheet
Curves (Hot & Cold) as single document in
vendor portal
10. Performance Curves : P.f. & Efficiency Curves To be furnished along
with motor data sheet
as single document in
vendor portal
11. Inspection & Test Plan (ITP) -For review by Refer Note-'*'
Inspection Dept.
12. Test Records
13. Type Test Certificates for similar equipment
14. List of Commissioning Spares
15. List of Maintenance Spares
16. List of Special Tools & Tackles
17. Data Books/ Manuals : Installation Manual
18. Data Books/ Manuals : Operating/ Maintenance
Manual
19. Data Books/ Manuals : Catalogues/ Brochures
20. Equipment storage procedure at site
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
21. Statutory approval certificate of CCOE/PESO
Notes :
1. "TICK" denotes applicability.
2. Post order, drawing / document review shall commence only after approval of Document Control Index (DCI).
3. All post order documents shall be submitted / approved through EIL eDMS portal.
4. Final documentation shall be submitted in hard copy (Six prints) and soft ( two CDs/DVDs ) in addition to
submission through EIL eDMS.
5. Refer - 6-78-0001: Specification for quality management system from Bidders.
6. Refer - 6-78-0003: Specification for documentation requirement from Suppliers.
7. All drawings & documents shall be submitted in A4 or A3 paper sizes. Documents in higher paper size shall
be submitted in exceptional circumstances or as indicated in the MR/Tender.
8. Post order- The schedule of drawing / data submission shall be mutually agreed between EIL & the bidder /
contractor / supplier during finalization of Document Control Index (DCI).
9. Bill of Material shall form part of the respective drawing.
10. '*' indicates the following:
a. Equipments whose ITP is attached with Contract -ITP for respective equipment shall be followed. Therefore,
no ITP is to be furnished for review for those equipments.
b. Equipments whose ITP is not attached with Contract-Manufacturer's ITP shall be submitted by Packager/
Vendor/Contractor to respective Regional Procurement Office (RPO) near to manufacturer's works for approval
by EIL Inspection.
11. All technical details and documents furnished with bids shall be treated as data for engineering. These shall
however be subject to Purchasers review after order placement and bidder shall comply to MR/Tender
requirements without any cost & time implication to EIL/Owner.
12. "*" indicates submission of documents to Inspection Agency.
MANDATORY SPARES
INSTRUMENTATION
The vendor shall note the following and furnish the quotation for Mandatory Spares accordingly:
1. Mandatory spares shall consist of the Spares as listed below.
2. The word ‘Set’ means the quantity required for full replacement of that part in one machine.
3. The Vendor shall supply all the mandatory spares as defined below & as applicable to the proposed
design of the equipment. In case, any spare which is listed in the checklist but not applicable due to
specific construction/design of the equipment, the same shall be highlighted as ‘Not Applicable’
against that spare supported with proper technical explanation.’
4. Spare part shall be identical in all respects to the parts fitted on the main equipment, including
dimensions, material of construction, testing and heat treatment.
5. Vendor shall note that, only the mandatory spares (Rotating, Instrumentation, Electrical, and Static
Equipment & Piping) as specified below shall be included in the base price. No other spares of any
type shall be included in this list of mandatory spares.
6. If any additional spare is included, the same will not be taken cognizance of.
If vendor wishes to quote for any spare over and above those specified below, the same shall be
quoted as part of the Two years normal operation spares.
7. Vendor shall furnish the following checklist of mandatory spares, duly filled in, separately for each
equipment Item included in the inquiry, in his proposal.
Quoted
S. No. Part Description Quantity Required
Yes/No
1 FIELD INSTRUMENTS (as applicable)
10% (Subject to min. of 2 Nos) of each model,
1.1 Pressure Gauges range, material of construction and rating,
whichever is higher.
10% (Subject to min. of 2 No) of each model,
1.2 Draft Gauges range, material of construction and rating,
whichever is higher.
5% (Subject to min. of 1 No) of each model,
Temperature Gauges
1.3 range, material of construction and rating,
whichever is higher.
A) For transparent gauges, 10% of illuminators
1.4 Level Gauges
with holder and reflector and 50% of bulbs
B) In case of magnetic type level gauges, 10% of
bi-color rollers for each gauge to be provided in
addition to above.
Variable Area 5% or minimum one no. float & set of Packing for
1.8 Flowmeter each type, size, rating and material, whichever is
(Rotameters) higher. Spare glass of enclosure/indicating box
A) Repair kit consisting of (orifice, plug, spring,
Pressure control Valve
1.9 gasket, diaphragm, O-ring for each type, size &
(Self actuating valve)
rating of the valve.
B) Minimum 1 no of each type/ size, rating etc. of
Trim set consisting of seat, seat ring / seal ring,
plug with stem, cage (wherever applicable),
packing material for each valve to be provided as
spare.
NOTES:
1. The word ‘TYPE’ means the Make, Model no., Type, Range, Size/ Length, Rating, Material as
applicable.
2. Wherever % age is identified, Vendor shall supply next rounded figure.
3. The terminology used under ‘Part Description’ is the commonly used name of the part and may
vary from manufacturer to manufacturer.
4. The above list indicates Predefined Mandatory spares excluding the Commissioning spares,
Consumables and installed engineering spares for system-oriented items. The Commissioning
spares and Consumables shall also be part of Vendor scope of supply. The installed engineering
spares for system oriented items like Sub-package PLC, Dedicated control systems, Local Control
Panels etc.(As applicable) shall be as per specification given elsewhere.
5. Mandatory spares shall also be applicable for instrumentation items of sub-packages as per
mandatory spares philosophy.
(INSTRUMENTATION)
FOR
AGITATORS
ACRYLATE UNIT
PDPP, BPCL-KOCHI
A842-PDE-VV-PR-6041/0041
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
1.0 GENERAL
1.1 The purpose of this specification is to define general requirements and philosophy of
instrumentation for Agitators package..
1.2 This specification along with standards and relevant part of this requisition covers the
design, engineering, supply and testing of Instrumentation system with all accessories and
materials, required for Agitators package.
1.3 If there is any conflict between this specification, data sheets, related standard, code etc.
Vendor shall refer the matter to owner/consultant for clarification and only after obtaining
the same should proceed further.
2.1 Vendor's scope of instrumentation supply and work shall include the followings as a
minimum:
a) Supply and installation of all instruments (as applicable) as required for smooth and
satisfactory operation of Package.
b) Design and detailed engineering including residual engineering of instrumentation
and controls of the package based on P&IDs (to be developed by Vendor) and other
technical requirements described in various documents attached with the PR. This
shall include detailed engineering including preparation of engineering drawings/
documents, specification data sheets, sizing, selection of materials.
c) Piping and all other erection material including all fittings, mounting accessories,
instruments supports (2" yoke type) required for erection of instruments, under
Vendor's scope of supply, as per list of applicable installation standards (shall be
given to successful Vendor after order).
d) Supply and installation of all cables between instruments and Local Control Panel (if
applicable) supplied by Vendor.
e) Cable glands/plug shall be duly installed with the instruments.
f) Submission of documents shall be as per VDR.
g) One number potential free contact for stop & one number for running indication shall
be made available by the vendor for further use by purchaser. The isolated potential
free contact shall be suitable for 2A rating @ 24V DC for further interrogation/ usage
by the Purchaser.
3.1 All electronic field transmitters shall be suitable for intrinsic safe circuit and shall be
certified suitable for Zone-2 Gr IIA/B T3 hazardous area classification by statutory body.
All the instruments shall also be dust proof. Additionally instruments shall be certified by
CCE/ PESO India, irrespective of the origin of the instrument..
3.3 In place of process switches Foundation Field bus transmitters shall be provided for seal
plan for Agitators. Vendor shall provide the alarm set values during detail engineering. FF
Transmitter shall be bus powered type and shall have interoperability test clearance
complying ITK (latest revision). FF transmitter shall also have capability to become device
link master whenever required. It shall be compatible with EDDL (Electronic Device
Description Language) as per IEC 61804, latest revision or FDT/DTM requirements.
Foundation Fieldbus type transmitters shall be used in high powered trunk concept with
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
intrinsically safe Field barrier. Hence the intrinsically safe (entity concept) parameters of
the transmitters shall match with the entity parameters of field barriers.
3.4 All field instruments/transmitters shall be provided with dual cable entries. Unused entry
shall be plugged using suitable metallic plug. All cable entries shall be 1/2" NPT (F) size
and shall be fitted with double compression type nickel-plated brass cable glands with
Slipper type PVC sleeves (cable shrouds) and suitable for hazardous area classification as
indicated elsewhere in the bid package.
3.5 All the instruments shall be supplied from EIL / purchaser's approved vendors only. Vendor
shall furnish proposed sub-vendor list for EIL / purchaser's approval. It shall be approved
by EIL / purchaser during detail engineering after order. Vendor shall take prior approval of
make and specification of all instrument items before placement of order on sub-vendor.
3.6 Pressure rating of thermowell for temperature element/ temperature gauge, self-actuated
pressure control valve body and flanges shall be minimum 300# rating or as per respective
piping specification whichever is higher.
3.7 Instrument connection on vessel, standpipes and tanks shall be as per Doc no. 7-52-0001
and instrument connection on pipes shall be as per Doc no. 7-52-0002. The minimum
rating of all instrument nozzles on the vessels shall be 300#
3.7 All instruments shall have internal terminal block, anti-vibration type for cable termination.
Flying leads are not acceptable.
3.8 S.S. tag plates shall be provided for all the instruments.
3.9 Prefabricated FRP canopy shall be used for field electronic instruments,. Canopy for
transmitters shall cover TOP and all 4 SIDES with transparent door on the front.
FRP canopy shall have Acrylic window & mounting bracket plate material shall be SS304.
Color of the canopy shall be Light grey
3.10 Typical (skeleton / blank) instrument data sheets for each type of instruments are enclosed
with the requisition. The ‘.isf’ files for the same shall be furnished by Purchaser during
detailed engineering. Vendor shall furnish filled in data sheet for each tag after sizing,
range selection, material selection etc. These data sheets shall be reviewed and approved
by EIL / purchaser after placement of order. Proper selection of instruments, materials etc.
shall be Vendor's responsibility. Any necessary change required later for meeting the
specification shall be done by the Vendor. While filling the instruments data sheets, the
following shall be taken care:
a) All the relevant data shall be filled in. If any point is not applicable then N/A shall be
indicated.
b) Make and model number of the supplied instruments shall be indicated with model
decoding details for supplied instrument, without model no, data sheet shall not be
reviewed.
c) Vendor seal with signature shall be provided and pump vendor shall ensure the
correctness of the process data.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
a) For liquid measurement , Guided Wave Radar is not acceptable if process fluid is
Acrylate since there is chance of polymerization in presence of acrylate.
a) Level Gauges shall be steel armoured Magnetic type or Transparent type with body
material of SS 316 as a minimum or better corresponding to seal pot material and
tempered borosilicate glass. In case Transparent type gauge is being provided ,
illuminator to be provided for the same.
b) Level Gauge shall be supplied with off-set type quick closing ball check valve (Gauge
Glass and cock type) with carbon steel body and SS 316 trim as a minimum.
c) Level gauge shall be hydrostatically tested up to 72 Kg/cm2 (as a minimum) or up to
hydrostatic test pressure of seal pot, whichever is higher. Hydro test certificates shall
be furnished.
d) Vessel (Seal Pot) connection for level gauge shall be 3/4" NPT (F) with primary
isolation valve and 3/4" spherical union.
e) Studs and bolt material shall be ASTM A193 Gr. B7 and ASTM A194 Gr. 2H
respectively.
a) Pressure gauge dial shall be 6” white of non-rusting material with black figures.
Pressure gauge shall have solid front for operating pressure exceeding 60 Kg/cm2g.
b) Pressure gauge shall have 1/2" NPT (M) bottom connection.
c) Pressure gauge shall be provided with features like screwed bezel, externally
adjustable zero, over range protection and blow out disc.
d) Sensing element (bourdon tube) shall be of SS 316 and movement of SS 304, as a
minimum. Case material for pressure gauges shall be SS 304
e) Pressure gauge shall have an accuracy of ± 1% of URV (Upper Range Value) and
range shall be so selected that gauge normally operates in middle third of the range.
f) Pressure gauge shall be suitable for maximum pressure or 130% of the range
whichever is higher, without any calibration drift.
3.14 Transmitter
a) All open & closed loops shall be Foundation Fieldbus type while all interlock analog
signals shall be conventional SMART type. In case some special instruments not
available as FF Type, SMART instruments is also acceptable with Purchaser
approval. For SMART instruments details ,refer 6-52-0032 & 6-52-0052 attached
with this PR.
b) FF type Transmitters used in the seal plan shall be as per clause 3.3 above and shall
be suitable for the specified area class.
e) Threaded end connections shall be to NPT as per ANSI B 1.20.1. Flanged end
connections shall be as per ANSI B 16.5
a) Pressure Relief Valve shall meet the limiting relief valve requirements as defined in
API RP-520 (Part-I & II) and in API-526.
b) Pressure Relief Valve shall be full nozzle full lift type and Thermal Relief Valve shall
be modified nozzle type.
c) Percentage Accumulation shall be 10% for Pressure Relief Valve and 25% for
Thermal Relief Valve.
d) Body material shall be Carbon Steel as a minimum. Nozzle and disc material shall be
SS 316 as a minimum with machined SS guide and spindle.
e) Spring material shall be selected as per operating conditions. Normally it shall be
Cadmium/Nickel/Zinc/Aluminium plated Carbon Steel.
f) Pressure Relief Valve shall have flanged connections for sizes 1" and above and
shall have screwed connection for sizes 3/4" and below. Thermal Relief Valve shall
have screwed connection with 0.38 cm2 orifice size and inlet outlet shall be of 3/4"
NPT(M) X 1" NPT(F) sizes.
g) Pressure relief valve type shall be vendor’s responsibility suitable for the system.
a) Body material shall be Carbon Steel as a minimum. Trim material shall be Stainless
Steel as a minimum. Actuator shall be diaphragm type and diaphragm material shall
be Stainless Steel as a minimum.
b) All pressure parts shall be designed to withstand maximum shut off pressure.
c) Hardening of trim (includes plug and seat joint, orifice and plug contour) like stelliting
etc. shall be considered for pressure drops greater than 10 Kg/cm2g.
d) Valve shall have flanged connections for sizes 1" and above and shall have screwed
connection for sizes 3/4" and below.
Orifice plate shall be concentric square edged type of minimum of SS316 material and
flanges shall be min. carbon steel of minimum 300# rating. The sizing of Orifice shall be as
per ISO 5167. Dimensional detail shall be as per 7-52-0041.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
a) The temperature gauges shall be bimetallic type and shall be provided with 1½"
flanged (min. 300# rating) thermo well with ½" NPT (F) connection for temperature
gauges on process lines.
b) All temperature elements shall be RTD (Pt-100) for temp range (-200) to 650 DegC
and Duplex type. All temperature signals shall be provided with field remote mounted
(not head mounted) type temperature transmitter. Thermo wells shall be fabricated
out of bar stock.
c) Temperature gauges shall have accuracy of ± 1 % of URV (Upper Range Value).
d) Thermo well and flanges of Thermo well shall be minimum of SS-316 or better to suit
the service conditions. Minimum 300# rating shall be considered for thermowell.
e) Case material for temperature gauges shall be SS 304.
f) Temperature transmitter shall be provided for all temperature elements for both open
and closed loops except where signals are connected to vibration and temperature
machine monitoring system and shall be remote field mounted.
g) Temperature transmitters shall be provided with dual compartment.
a) Rotameter shall be of metal tube type. Transmitter shall be FF type as per clause 3.3
above. In case FF type transmitters are not available from any manufacturer, 4-20 mA
SMART output transmitters with HART protocol are acceptable.
b) The material for tube & float shall be SS 316 as a minimum.
c) The packing material shall be PTFE if the liquid temperature is below 230° C. For
temperatures above 230° C, packing shall be of GRAFOIL.
d) Rotameter shall have an accuracy of minimum ± 2% FSD.
(a) For Non-congealing Hydrocarbon services as well as utility services (except steam
which shall be closed coupled with 5 valve manifold), standard bought out Pre-
fabricated (with 5 valve manifold for flow and 2 valve manifold for PT) & pretested hook-
up for all flow (dP) transmitters, Pressure transmitters shall be used. These hook-ups
shall be basically close coupled instrument hookup integral type complete with
instrument root valve, equalizing valves, oval flange adaptors, vent, drain pre-tested and
pre-engineered ready for installation. All drain connections of pre-fabricated & pre-
tested hook-up for pressure transmitters shall be provided with connector, tube and
tubing cap for remote draining.
(b) 2 valve integral manifold along piping standard shall be considered for Local Pressure
gauges.
(c) Separate Vent/Drain valves are not required when 5 valve manifolds / pre-fabricated
and pre-tested hook ups are used for DP type flow transmitters
(d) Remote Instrument Installation shall be used for Level and Differential Pressure
Transmitters (DPTs) with hybrid standard (i.e. complete piping with tubing at the end).
Vent / drain valves shall be gate valve and isolation valve shall be globe valve.
(e) For pre-fabricated and pre-tested hook-up, first isolation valves shall be part of hook-up
and it shall be miniature type quarter turn ball valve with minimum 1500 # rating with
metal seated/ soft seated as per process pressure/ temperature condition. For all other
installation, the first isolation valves of piping shall also be quarter turn ball valves.
(f) The material of construction for the complete assembly of pre-fabricated hook-up shall
be SS 316 as a minimum unless more stringent materials are required as per process
conditions and PMS.
(g) Field transmitter supports should be properly clamped to the pipe for pre-fabricated
hook-up, wherever required. No air gap shall be kept between support clamp and pipe.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
(h) Vendor shall follow EIL installation standard for instrument hook-ups. The same shall be
provided to the successful vendor during detailed engineering.
(i) For seal oil, lube oil services tubing installation for instrument is also acceptable.
All instruments mounted on steam traced lines shall also have their installation steam traced.
Local panels shall be used only for startup and normal critical operations. Unless
otherwise indicated in the package, following points shall be kept in mind while engineering
the local panels:
Weatherproof local panel shall be provided by Vendor for classified area, wherein
the Alarm Annunciator shall be intrinsically safe and push button, lamps; selector switches
shall be flame-proof “Exd” type mounted on LCP. Barriers for IS alarm annunciator shall be
supplied by Vendor along with IS annunciator and Purchaser will provide potential free
contact for the same. The IS power supply module for alarm annunciator shall be installed
in a flameproof box in local panel. For Lamps, Purchaser will provide wet contact. The
Power supply distribution box inside the Local Panel shall also be flame-proof “Exd’. IS
PCs for display of loop powered indicators shall be used in weather-proof local panels in
case no. of tag local display more than 5 tags. The same IS PC can also be used for local
display of Vibration and Temperature monitoring system parameters at field instead of
separate display unit at field. Separate Local Panel shall be required for each Pump. Local
panel shall be located in field near the Pump.
Electronic Components / system located at local panel shall be suitable for combined
effect of outdoor ambient/climatic conditions and current carrying for installation in LCP.
Vendor shall confirm with catalogue / document mentioning ambient temperature rating of
Vendors supplied Electronic Components / system suitable for installation in local panel or
else Vendor shall supply necessary cooling arrangement.
.
Power supply (110 V AC (UPS ± 10%, 50Hz ± 3%) and / 240V AC 50Hz. 50Hz ±3%)
shall be given at one place near each panel in the field by Purchaser. Further
distribution shall be by Vendor. Vendor shall indicate the power consumption for 110
VAC (UPS) and 240 VAC for package, along with the bid proposal
b. Any Instrument loose supplied items are to be packed separately instead of packing the
same with other mechanical items while shipping to site. Markings shall be provided for
such packing as “Instrument Items – Loose Supply”
c. The package vendor shall generate and submit all instrument specifications, datasheets
using Intergraph Smart Plant Instrumentation (SPI) 2009.Purchaser shall provide blank
".isf files" (SPI) during detailed engineering for each instrument tag to vendor for filling
the same using “external editor”. Vendor shall prepare instrument datasheets using the
same only and submit pdf outputs for review/records and after finalisation, the final ".isf
file" shall be submitted for migrating the data into purchaser’s main SPI database.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
d. Small nut/bolts, used for fixing of instrument items in addition to cable trays, shall also be
stainless steel.
e. All drain connections of pre-fabricated & pre-tested hook-up for pressure transmitters
shall be provided with connector, tube and tubing cap for remote draining.
f. The Fieldbus devices configuration shall be provided by Vendor in the form of soft file
(CD) as part of VDR during detailed engineering. For all the Fieldbus instruments
supplied under the package, vendor to provide all the necessary data of field instruments
required for FF DCS engineering like Device Tag, Device type, Device revision, Device
address, DD file revision, CFF revision etc as actually configured in the supplied
instruments in the format given in the PR.
4.1 Instrumentation symbol shall follow latest edition of ISA standard S 5.1.
4.2 All vendor-supplied instruments shall have Tag No. as per the format indicated below.
Numerical no. for all the instruments shall be unique i.e. without any repetition of tag no.
for same type of instrument.
5.0 INSPECTION:
All instruments shall be inspected by owner / consultant for calibration and proper
operation prior to dispatch.
10% subject to minimum 1 no. of each type of applicable supplied Instruments. The word
‘TYPE’ means the make, Model No., Type, range, Size / length, rating, material as
applicable.
The installed engineering spares for system oriented items like Local Control Panels
etc.(As applicable) shall be as per specification given elsewhere
7.1 Vendor shall supply Instrumentation commissioning Spares required as per vendors
recommendation for successful commissioning of the supplied Package.
7.2 Deleted.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
7.3 Vendor shall note that in case any additional spare is required during erection and
commissioning over and above the recommended spares, the same shall be supplied by
vendor without any implications. Also, if any spares are consumed during commissioning
from mandatory spares, the same shall be replenished by vendor.
8.0 Deleted.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
ATTACHMENTS:
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
The following drawings/documents marked " " shall be furnished by the bidder.
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
1. Drawing and Document Schedule
2. Utility & Power Requirements
3. Spare part list for 2 years operation
4. Spare part list for Mandatory Spares
5. Instrument Index Note-19
Notes :
1. "TICK" denotes applicability.
2. Review Only for Critical items like Control valves, On-off valves, Pressure Safety Valve, self actuated control
valves . Others are for Records only.
3. Any other document/drawing not listed above but required to carryout the engineering and for integration of
other equipment packages sub-ordered by contractor shall also be prepared and furnished to Client / EIL.
4. Vendor to note that the system engineering documents are required for further engineering and site work.
These documents shall be, positively, provided as per mutually agreed schedule after order.
5. Post order, drawing / document review shall commence only after approval of Document Control Index (DCI).
6. Vendor shall prepare & submit the as built drawings / documents after commissioning. All the
drawings/documents listed shall be converted into âAs Builtâ after commissioning of Project. âAs Builtâ shall
include documents generated by Contractor & documents generated/ submitted by various Sub-vendors.
7. All instrument document/drawing shall be submitted after issue of P&IDs. The submission of document /
drawing is sequenced in such a way that submitted document /drawing is neither dependent nor changed due
to drawing / document yet to be submitted. Document/ drawing submission schedule shall be made accordingly.
8. Vendor shall furnish Hazardous area certificates for all instruments & equipments located in hazardous area.
Statutory certificates shall be obtained from authorities like PESO (Petroleum Explosive Safety Organizer) /
16. Post order- The schedule of drawing / data submission shall be mutually agreed between EIL & the bidder /
contractor / supplier during finalization of Document Control Index (DCI).
17. Final documentation shall be submitted in hard copy (Six prints) and soft ( two CDs/DVDs ) in addition to
submission through EIL eDMS.
18. Bill of material shall be prepared based on the EIL installation standards being used with contractor¿s item
codes for installation material items.
19. The package contractor shall generate and submit all instrument datasheets, Cable Schedule, instrument
index and loop wiring diagram using Intergraph Smart Plant Instrumentation (SPI) 2009
20. Bidder shall generate these documents in the formats which shall be provided by purchaser during detailed
engineering.
21. Documents other than those identified for review by Client/ EIL shall be submitted for record.
22. Bidder shall furnish filled in data sheet for each tag after sizing, range selection, material selection etc. with
make and model nos. These data sheets shall be reviewed / retained for records by purchaser after placement
of order. Proper selection of instruments, materials etc. shall be bidder's responsibility. Any necessary change
required later for meeting the specification shall be done by the bidder without any price or delivery implications.
While filling the instruments data sheets, the following shall be taken care:
i) All the relevant data shall be filled in. If any point is not applicable then N/A shall be indicated.
ii) Make and model number of the offered instruments shall be indicated with model decoding details for offered
instrument, without model no, data sheet shall not be reviewed
iii) Vendor seal with signature shall be provided and bidder shall ensure the correctness of the process data.
iv) Instruments tag numbers /data sheet numbers shall be indicated
VENDOR LIST
PROJECTS
(MR-6041)
THERMOWELLS – 15HD
8. 7 T232 TECHNOINSTRUMENTS
9. 8 T095 TEMP-TECH
GENERAL NOTES
1.0 CONTRACTOR shall necessarily procure all the material / equipment forming permanent part of the
unit / plant from OWNER / PMC approved vendors only. This shall include sub-ordered items /
components also. The “Approved Vendors” shall be item specific.
2.0 OWNER / PMC approved vendor list for the various items is enclosed in this section.
3.0 CONTRACTOR may procure material from any of OWNER / PMC approved vendors. However,
current validity, holiday status and range of approval as per EIL enlistment letter, workload,
stability and solvency need to be verified by the CONTRACTOR with vendor before placement of
order. CONTRACTOR is also required to ensure that equipment qualification criteria, specified
elsewhere in the bid document, are also simultaneously met.
4.0 Vendors on OWNER / PMC holiday list shall not be considered for ordering. CONTRACTOR shall
comply with this requirement without any time or cost implication to the OWNER. If a vendor is put
on OWNER / PMC’s holiday list subsequent to CONTRACTOR placing an order, it shall be
CONTRACTOR’s responsibility to ensure quality work and timely supply from the vendor.
5.0 For items not covered in the above list, the CONTRACTOR shall approach OWNER/PMC for that
list or the vendors list shall be approved by OWNER / PMC prior to placement of order by
Format No. EIL-1641-1924 Rev.1 Copyright EIL – All rights reserved
4
6.0 CONTRACTOR shall make an independent assessment of capability of all the vendors for timely
deliveries of material/ equipment. Any delays in deliveries by vendor(s) shall not be a cause of
schedule and cost implication.
7.0 At any stage of the project, if it comes to the notice of OWNER / PMC that CONTRACTOR has
procured material / equipment, intentionally or unintentionally whatsoever, from an unapproved
vendor and/or items not falling in approved range of vendor(s), the same shall be rejected fortwith
and CONTRACTOR shall be liable to replace such material / plant / machinery without any
schedule and cost implication to the OWNER.
8.0 List of vendors appearing anywhere else in the contract document in case of duplication of the
items at two or more places shall not be considered by CONTRACTOR and shall be superseded
by the vendor list enclosed herewith.
9.0 It is understood that should the name of vendor be changed due to change in their company or
corporate share holding. OWNER may accept such vendors under its new name with prior
approval.
Any such approval shall however, not absolve the CONTRACTOR from any of his obligations
under the contract; neither shall any such approval signify nominations or instruction to use such a
vendor. All approved vendors are deemed to have been freely chosen by the CONTRACTOR at
his own risk.
10.0 The approved vendors list for fabricated equipment (Vessels, Column, Heat Exchangers, Ejectors
etc.) is for fabrication alone. Where mechanical design of the equipment is included in
CONTRACTORS’S scope, CONTRACTOR shall either himself or through his Detailed
Engineering sub-contractor be responsible for designing and obtaining approval/ review of
Mechanical design calculations as per codes/specifications specified elsewhere in the Bid/
Contractor document from OWNER / PMC.
CONFIDENTIAL
CONTENTS
Page 2 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 3 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.1.1 General
This document provides the information to achieve safe and stable operation of
Acrylate plant and shall be referred / accommodated in detailed engineering.
5.1.2.1 Polymerization
The polymerization of Acrylic Acid and Acrylate causes blockage in the equipment
and piping. To avoid the polymerization, countermeasures shown as below shall
be taken into account for the process equipment and piping which have possibility
to make polymerization.
- Stagnation of liquid shall be minimized
- Condensation shall be avoided
- Inhibitors and air shall be provided adequately to process liquid
- Contamination of foreign objects causing polymerization shall be avoided
5.1.2.2 Odor
Since Acrylic Acid and Acrylate have foul odor, countermeasures against leakage
shall be incorporated in the plant design.
5.1.3 Analysis
Acrylic Acid and Acrylate are easy to polymerize. Analysis itself is a point of vital
importance for stable operation with good product and polymerization prevention,
as the analysis result leads to the correct operation conditions. Analytical
requirements and information, such as “Chemicals to analyze”, “Sampling point”,
“Frequency of sampling”, “Analytical method for raw materials or stream products”
and so on, are referred to “Chapter 22 ANALYSIS EQUIPMENT INFORMATION”.
Page 4 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.2.1 General
This paragraph describes design requirement from process features which shall
be accommodated in detailed engineering stage.
5.2.2 Equipment
5.2.2.1 General
(1) For welding on internals and inner surfaces of equipment, double fillet welding or
full penetration and continuous butt welding shall be used without gaps. Socket
welds are not allowed for any of the equipment. After welding, be sure to
thoroughly finish and clean the welding lines to ensure that there are no adverse
affects on the product quality. All welding lines on the inner surfaces of equipment
must be smoothly finished by a grinder. Moreover, all welding lines that contact
the process fluid should be finished by acid-pickling and rinsed with fresh water
(e.g., boiler feed water) to remove particles and dust on the surfaces.
(2) All butt joints in the shell and head shall be welded by full penetration welding
without backing strip for process equipment. This requirement shall also apply to
the welded joints between the bodies and nozzles. Even a small gap may lead to
the accumulation of stagnant fluid and which may cause polymerization.
(3) Gap, crevice and/or groove on any joint of equipment shall not be provided to
prevent the stagnation of fluid has possibility of polymerization. For this purpose,
such as Bell-and-Spigot type joint or Tang-and-Groove flange shall not be applied.
Unless otherwise specified in PDP documents, Modified Male and Female type
flange (refer to Fig.-1 below) is preferable for equipment girth flanges or heat
exchanger channel head flanges with PTFE solid sheet gasket under the vacuum
condition.
Page 5 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Gasket
Gasket
(4) Dead space (the part which has possibility of fluid stagnation) in equipment shall
not be allowed to prevent the polymerization. Any design changes in detailed
engineering stage leading to make dead space shall not be allowed without
permission of LICENSOR. This change includes, for instance, the addition of
nozzles or the change of instrument type, etc.
(5) Weep holes for internals and devices on equipment shall be provided for complete
drainage.
5.2.2.2 Reactor
Esterification Reactor
To prevent polymerization in the reactor, spray of process liquid with inhibitors
shall be provided for all inner surfaces in gas phase zone of the reactor including
agitator installation nozzles. Actual arrangement of spray nozzle location shall be
designed and finalized in detailed engineering stage according to process
requirements specified on the reactor data sheet.
5.2.2.3 Column
(1) Column and internals shall be designed so as to remove polymers easily which
might be formed and accumulated inside. Following structures are applied to the
design in detailed engineering stage;
Minimum dead space
Welding with smooth finished structure for not removable internal parts
Bolt and nut tighten structure for removable internal parts
Page 6 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
(2) The levelness of trays and trough-type distributors shall be as shown below.
Inside Tower Diameter (mm) Max Levelness (mm),(Note 1)
1500 and under 2
from 1501 up to 2500 3
from 2501 up to 4000 4
from 4001 up to 5000 5
Note 1: “Levelness” refers to the difference between the highest point and the
lowest point out of at least 5 equivalently spread points.
[ Type-A ] [ Type-B ]
Standard Type For 5 tubes
Page 7 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.2.2.5 Drum
Feed nozzles of liquid from overhead condenser and vent condenser to reflux
drum shall be connected to side of shell and lower than LLL (Low Liquid Level) as
shown in Fig.-3. Unless otherwise specified in P&ID or EQUIPMENT DATA
SHEET, inner pipe shall not be provided to prevent polymerization.
Fig.-3: Liquid Inlet Nozzle of Reflux Drum
From Condenser
Reflux Drum
5.2.2.6 Tank
(1) Tank roofs with butt welding or double fillet welding as shown in Fig.-4 below shall
be applied.
Fig.-4: Fillet Welding of Tank Roof
Page 8 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
(2) In order to eliminate dead space from tank inner surface, following construction
shown in Fig.-5 shall be applied.
Roof rafters shall be installed above roof (outside of tank)
Roof plate and shell plate shall be welded and smoothed
Fig.-5: Structure of Tank Roof
(3) Liquid circulation lines for the tank shall be installed to achieve good mixing for
minimizing temperature difference and inhibitors maldistribution at any part of tank
inside.
5.2.2.7 Pump
(1) Mechanical seal system
(a) Mechanical seal system for the process pumps might have leakage trouble by
polymerization of process liquid and crystallization of inhibitors in process liquid.
Hence, the most suitable mechanical seal system shall be selected for such fluid
properties. TANKEN SEAL SEIKO Co., Ltd. or John Crane are required as
mechanical seal Vendor because LICENSOR has many experiences applying
their mechanical seals for Acrylate process pumps.
(b) Following table gives reference specifications about mechanical seals for
process pumps in the existing and/or the past licensed plant.
Fluid BA / HA HE
Single Single
Type
Stationary Stationary
Seal face WC/WC WC/WC
Back metal Titan Hastelloy-C
Secondary seal O ring (Chemraz) Metal bellows
Page 9 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 10 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.2.3 Piping
(1) For welding of process piping, full penetration and continuous butt welding shall
be used. Socket welds are not allowed. Projection of weld metal into pipe bore
shall be minimized. Welding by GTAW (Gas Tungsten Arc Welding) for first layer
of all process piping is required except for the double welding. After welding, be
sure to thoroughly finish and clean the lines to ensure that there are no adverse
affects on the product quality.
Moreover, all piping welding lines of more than 20” diameter that contact the
process fluid shall be finished smoothly by a grinder and acid-pickling, and rinsed
with fresh water to remove particles and dust on the surface.
(2) Flange quantities in piping system shall be minimized for process line except for
flanges necessary for facilitate cleaning, maintenance and inspection.
(3) For process liquid lines, piping slopes shall be designed to ensure the complete
drainage of the process liquid from the drain nozzles. For gas and/or vapor lines,
“no pocket” piping layout shall be designed to ensure the complete drainage of
process liquid condensate from gas and/or vapor.
(4) “Min.” in the P&ID represents the constructive minimum distance requirement for
piping. The minimum distance construction of piping prevents polymerization by
reducing the stagnation in piping which might become a dead end. EPC
Contractor shall carefully comply with the minimum distance construction
specified on the P&ID in detailed engineering stage. As a best way, the fittings
such as flange (WN Flange or Stub-end for Lap joint) and tees should be welded
directly to construct minimum distance. When the adjustment of the distance
between them is necessary, the short pipe piece can be inserted under the above
mentioned purpose. In this case, the enough consideration for the practical
fabrication procedure shall be done. A target value of the “Min.” distance from
COP (Center of Pipe) to flange face is shown as follows.
Main Pipe Min. Distance
Size [mm]
1”or less Not more than 100
1_1/2”-4” Not more than 200
6” or above Not more than 300
(5) Liquid circulation lines shall be installed to pipe line between process area and
tank yard area for BA, HA and HE services to prevent blockage caused by
stagnation of liquid. Required specifications for these lines are as follows.
Page 11 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Min. Min.
FI
Page 12 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Fig.-6-III: Piping around Flow Meter (excluded area) and Control Valve
(7) All drain nozzles shall be straight line until drain valve.
(8) Length of forced circulation reboiler loop line and film evaporator bottom line shall
be shortened to reduce retention time because it affects process performance.
(9) Air Distributer for reboiler circulation line shown in P&ID shall be finalized in
detailed engineering stage referring to schematic drawing shown in “Chapter 16.8
PIPING PARTS INFORMATION”. Requirement (hole size and numbers) for each
nozzle is shown on P&ID.
(10) Strainer washing box for washing of strainer element shall be provided near
process pump strainer on Grade. Schematic drawing of strainer washing box are
referred to “Chapter 16.8 PIPING PARTS INFORMATION”. Actual location of
strainer washing box shall be decided in detailed engineering stage referring to
“Chapter 12. GENERAL PLOT PLAN” and “Chapter 13. EQUIPMENT PLOT
PLAN”.
5.2.4.1 General
This paragraph describes insulation and tracing requirements to prevent the
condensation of process fluids in equipment, piping, and instrument piping.
Installation required portion of tracing and/or insulation are shown in P&ID and/or
EQUIPMENT DATA SHEET individually in process requirement point of view.
Page 13 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
DATA SHEET.
(a) Selection of LLS or MS tracing system
These systems are to prevent condensing of process vapor (e.g. in distillation
column shell or inside of overhead lines) and/or increasing HE viscosity. Selection
either LLS tracing system or MS tracing system are specified in P&ID and
EQUIPMENT DATA SHEET in accordance with operating temperature of process
fluid.
(b) Thermal insulation slip
Thermal insulation slip (referring to Fig.-7 bellow) shall be installed between tracer
and process line to avoid local heating of process line.
Page 14 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
(3) In general, NPS 1/2 carbon steel tracing pipe is applied for all tracing systems,
however only in case carbon steel pipe is not possible to install relatively tangled
portion such as around instruments equipment, OD 10mm / ID 8mm tube can be
used as alternative.
(4) Tracing line specifications (tracer size and quantities) with respect to each
process line size and length are shown in following tables as LICENSOR’s past
experiences. Required tracing line quantities shall be verified and determined
according to site conditions considering with actual selected insulation
specifications in detailed engineering stage.
(a) Steam Tracing
Steam Tracing
Process Line (NPS)
(LLS,MS)
Steam Tracing
(6) Flanges and connections for tracers should be installed at the same place of
process lines’ flanges so as to facilitate piping / equipment maintenance. Also joint
of tracer is recommended to be placed outside of process line insulation.
5.2.5 Civil
Liquid Acrylic Acid (AA) and Solid or Solution of Para Toluene Sulfonic Acid
(PTSA) have corrosive property. Anticorrosive countermeasures for civil structure
are required to consider for the following places having chance of exposing to AA
or PTSA. (For example, Acid resistant concrete)
(a) Mandatory Place
Inside of WW Pit and Oil Pit
(b) Recommended Place
On the surfaces of concrete or civil structure around AA or PTSA handling
equipment (especially for pump base).
Inside of trench around AA or PTSA handling equipment
Corrosivities of AA and PTSA against structural materials are referred to following
table.
Page 16 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
liquid acrylic acid CH2CHCOOH yes 1 to 2 - Yes strong medium medium weak strong weak
Pala toluene
liquid sulfonic acid CH3C6H4SO3H yes 1 to 2 - yes strong strong medium medium strong strong
solution
Pala toluene
solid CH3C6H4SO3H yes 1 to 2 - yes strong strong medium medium strong strong
sulfonic acid
Page 17 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.3.1 General
This paragraph describes considerations and/or study items shall be performed in
detailed engineering stage referring to PDP. In general, descriptions in this
paragraph are not strongly related to process requirements, therefore this
paragraph does not contain the descriptions listed in the Paragraph 5.2 above.
Any design changes related to process requirements specified in PDP shall be
informed to LICENSOR for the review and the approval in case the design
changes are executed in detailed engineering stage.
5.3.4.2 Insulation
Insulation thickness is specified in Line List based on “Chapter 2. DESIGN
CRITERIA”, it shall be verified and finalized in detailed engineering stage
according to selected insulation material and/or LICENSEE’s standards.
Page 19 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
Page 20 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.3.7 Equipment
5.3.7.1 General
In general, process requirements are specified in EQUIPMENT DATA SHEET of
PDP. However, specifications (such as dimension of parts, nozzle position, nozzle
orientation, etc.) other than specified in EQUIPMENT DATA SHEET shall be
decided in detailed engineering stage considering with its purpose or operability,
maintainability and etc. In case these specifications are to be decided by
LICENSEE or EPC Contractor, its relative position shall be kept as process
requirements described in the EQUIPMENT DATA SHEET of PDP.
5.3.7.2 Column
(1) Column diameter is specified as preliminary sizes, it shall be verified based on the
process requirements described in data sheet and shall be modified accordingly, if
necessary.
(2) Feed inlet nozzles and reboiler return nozzles shall be verified based on the
process requirements which is described in data sheet and shall be modified
based on vendor’s information in detailed engineering stage, if necessary.
(3) Tray plate shall be designed that tray plate is tighten with bolt, nut and washers so
as to set and remove easily.
Page 21 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.3.7.4 Tank
Design of “Air Foam Chambers” for all required tanks shall be executed in detailed
engineering stage.
5.3.7.5 Pump
(1) Pump head specified on data sheet is calculated based on the estimated piping
length and number of fittings etc., it shall be verified and finalized based on the
piping routing plan in detailed engineering stage. Design pressure for equipment
and instrument shall be modified according as final shut off pressure in detailed
engineering stage.
(2) Motor rated output specified on data sheet is preliminary figure, it shall be verified
and finalized based on the vendor’s information.
(3) Pump capacities (Minimum, Normal and Design) specified on data sheet do not
include any minimum flow rate, it shall be requested pump vendor to specify the
required minimum flow rate.
(4) Estimated system and size of cooling water lines and flushing lines for pump were
specified on P&ID. It shall be verified / finalized in detailed engineering stage.
5.3.7.7 Desuperheater
Minimum flow rates for desuperheater are based on PDE-400 operation assuming
PDE-500 is under switch operation. Minimum condition shall be finalized in
detailed engineering stage considering operation case.
Page 22 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
5.3.7.8 Hoist
Hoist is recommended to install in operability point of view. EPC Contractor shall
finalize specifications of hoist considering with shape of inhibitor paper bag,
Vendor’s information and final plot plan in detailed engineering stage.
Recommended location to install hoist is;
Above Inhibitor / PTSA drum (for lifting up of inhibitor paper bag)
5.3.8 Piping
(1) In general, mechanical design of piping shall be performed in accordance with
ASME B31.3.
(2) In detailed engineering stage, thermal stress analysis of piping should be
conducted which operating temperature shown in line list exceeds 100 deg.C. For
piping which the results of the analysis show excess in allowable stress or
moment and considered to have detrimental distortion, the piping systems shall
be designed so that they have adequate flexibility by installing expansion joints or
reinforcing equipment nozzles, etc.
(3) If low point drain nozzles other than specified in P&ID of PDP are found necessary
to install according to actual piping routing plan in detailed engineering stage, it
shall be added in consideration of complete drainage from the pipelines after the
shutdown operation.
(4) Equipotential bonding shall be provided considering the requirement of local
regulations, laws or LICENSEE’s standards in detailed engineering stage.
Page 23 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
(5) Details of Air Regulator for process vent gas line shown in P&ID shall be finalized
in detailed engineering stage referring to schematic drawing shown in “Chapter
16.8 PIPING PARTS INFORMATION”.
5.3.9 Instrument
(1) All pressure data on pump discharge line are specified based on estimated pump
head calculation, it shall be reviewed and finalized accordingly based on the
piping routing plan in detailed engineering stage.
(2) Elevation (static head) is not considered for the pressure data in the Instrument
List. The pressure data shall be finalized in detailed engineering stage considering
with its installed elevation.
(3) Minimum flow rates for PDE-700 are based on PDE-400 operation assuming
PDE-500 is under switch operation. Minimum condition shall be finalized in
detailed engineering stage considering operation case.
5.3.10 Electrical
Motor List
All motor outputs mentioned on motor list is estimated figures, it shall be reviewed
and finalized based on vendor’s information in detailed engineering stage.
5.3.11 Civil
(1) Base Level is assumed as EL +/- 0m and set as floor level of Process Area, Pipe
Rack and Intermediate Tank Yard Area in PDP. Actual altitude of each level shall
be decided in detailed engineering stage.
(2) Anti-vibration design for structure and for foundation of rotating equipment shall be
provided in accordance with the selected vendor’s information (dynamic load etc.).
5.3.12 Others
(1) Firefighting system
Firefighting system (including air foam chamber for tanks) shall be designed by
EPC Contractor in detailed engineering stage in accordance with applicable laws,
codes, local regulations, and/or LICENSEE’s standards.
Page 24 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
(b) Eye washer and safety shower should be installed nearby sample box and
strainer washing box for operator’s safety as recommendation of LICENSOR.
Refer to Attachment 1.
Page 25 of 25
CHAPTER-5 CONFIDENTIAL
SPECIAL DESIGN REQUIREMENT
LIST OF APPLICABLE
SPECIFICATIONS & STANDARDS
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
SCOPE OF SUPPLY
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
SCOPE OF SUPPLY
1. Owner
[ ] Shell
[ ] Skirt
[ ] Manhole neck, nozzle neck 300 NB and above in carbon steel and 125 NB and
above in stainless steel
[ ] Renforcement pad
[ ] Wrapper plate
[ ] Internal piping
[ ] Insulation support
[ ] Lifting lugs
[ ] Baffle
[ ] Demister support
[ ] Pipe fitting
[ ] Gasket
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
[ ] Brick lining
[ ] Refractory lining
[ ] Tower packing & associated internals including distributor, feed pipes, support grid /
plates, retaining grid / bed limiters, etc. associated with packing
[ ] Thermowells
[ ] Refractory lining
2. VENDOR
[X] Shell
[X] Manhole neck, nozzle neck 300 NB and above in carbon steel and 125 NB and
above in stainless steel & 200 NB and above in clad steel
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
[ ] Tray Support Ring/ Chimney tray support/ Packing support ring/ Bolting Bar/ Seal
Pan/ Tray Downcomer welded to the equipment
2.2 Structural steel section and plate conforming to IS: 226/IS: 2062 Gr.B / SA-283 Gr.C for
[ ] Shell
[ ] Internals
[ ] Flat cover
[ ] Manway flange/cover
[ ] Section for stiffeners
[ ] Structural sections for platform, ladders, hand railing, grating etc as per SOR
attached with requisition
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
[X] Studs/bolts and nuts for manway / handholes / internal flanges / nozzles with blind
flange/shell flange, including jack bolts for manways, and shell flanges
[X] Gasket for manway/internal flange /shell flange/ nozzles shown with blind
flanges/companion flanges
[X] Agitator assembly with ancillaries including assembly & disassembly tools for
mechanical seal and any special tools & tackles for agitator assembly
[X] Associated piping works, instrumentations works and electrical works for Agitators.
(Refer P&ID No. A842-79-41-PDE-11044, A842-79-41-PDE-11045, A842-79-41-
PDE-11046, A842-79-41-PDE-11084, A842-79-41-PDE-11085 & A842-79-41-PDE-
11086 for scope)
[X] Internal piping and supports, Plate type flanges, pipe fittings
[X] Seamless nozzle necks 250 NB & below in Carbon Steel, 100NB & below in
Stainless Steel & 150 NB & below for weld overlayed nozzle
[ ] Spray nozzle
[ ] Internal packing
[X] All other metallic and non-metallic parts, consumables and gases not covered under
1 and 2 but required to complete fabricated equipments including inspection, testing
and supply of equipments as per this requisition
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
[X] Mandatory spares –10% of fasteners (min 2 nos. in each size) and two sets of
gaskets for each nozzle shown with blind/companion flange
[X] Commissioning spares –10% of fasteners (min 2 nos. in each size) and two sets of
gaskets for each nozzle shown with blind/companion flange
[X] Supply of Electrical items as per Job Spec Doc. No. A842-PDE-16-50-SP-6041
[X] Supply of all items related to instrumentation items Doc. No. A842-PDE-16-51-SP-
6041) for agitator assembly
[X] Accessories for Agitators. (Refer PDS No. PDPP-DS-A405, PDPP-DS-A415, PDPP-
DS-A455, PDPP-DS-A505, PDPP-DS-A515 & PDPP-DS-A555 for scope)
[] LWN Nozzles
[ ] Supply of all materials, fabrication of all platforms, ladders, cage ladders and other
structural works, supply, fabrication of hot dipped electro forged galvanized grating
and its installation as per Schedule of rates
[X] Supply & application of all primer (pre-erection) & finish painting of all equipments at
vendor’s works/shop as per Job specification A842-000-79-41-PLS-01
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
INSTRUCTIONS TO VENDOR
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
INSTRUCTIONS TO BIDDERS
1. Bidder to note that no correspondence shall be entered into or entertained after the bid
submission. Bids shall be evaluated based on the details submitted by the bidder. In
view of the same bidder in his own interest is advised not to submit any deviation.
3. No technical details of any nature shall be included in the offer. If the offer contains any
technical deviations or clarifications or stipulates any unsolicited technical specifications
(even if in line with the MR requirements), the offer is liable for rejection.
4. The submission of prices by the bidder shall be construed to mean that he has
confirmed compliance with all technical specifications of the corresponding item(s).
(B) Bidders to note that a prebid meeting shall be held in which bidders can seek any
clarifications/confirmation if required. Bidder to ensure that this conference is attended
by both technical and commercial personnel of the Bidder who should have thoroughly
scrutinized the MR before hand so that all issues are finally resolved in this meeting.
Technical Instructions
1. The shape of dished end/toricone, profile of conical reducer, knuckle radius, cone angle
and overall height shall be as per engineering drawing. Minimum thickness of shell, cone
and dished end shall be achieved taking into account thinning and scaling etc.
2. Dished ends and hot formed pressure parts shall have 10% or 2mm (whichever is
higher) allowance for scaling and thinning, in order to achieve minimum thickness
specified on the drawing.
b. For low temperature equipment and hot formed parts, number of production
coupons and the tests thereon shall be as per requisition.
4. Post weld heat treatment and all non destructive testing like radiography, ultrasonic
testing, magnetic particle/dye penetrant examination etc. shall be conducted as per
requisition.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
7. Pickling and passivation of internal / external surfaces of stainless steel and internal /
external surface of SS internals shall be carried out as per ASTM A-380.
8. For IBR vessels complete design of equipment as per IBR, approval of drawings,
documents, stagewise inspection and final certification of the equipment by Inspectorate
of Boilers shall be included in Bidder’s scope.
10. The main equipment shall not be subcontracted, however the bought out items/
components can be sub-ordered or sub-contracted to EIL approved vendors/sub-
contractors only.
11. Demister shall be procured from EIL approved vendors only listed in annexure - I to this
specification.
12. Agitators shall be procured from EIL approved vendors only (listed in Annexure-II to this
document) based on their capability of enlistment with EIL.
13. Hoppers for Hastelloy metallurgy (item no. PDE-V-405 & PDE-V-505) shall be procured
from EIL approved vendors only (listed in Annexure-III to this document) based on their
capability of enlistment with EIL
14. Wherever vacuum stiffening rings are provided, same shall be used as insulation
supports also (refer sketch no. A842-PDE-80-43-SK-0003). Additional insulation
supports shall be EIL standard.
15. Vacuum stiffening rings shall not be welded to shell until all fouling with respect to piping
and structural cleats are resolved.
16. Fabricator to supply template for checking the orientation of anchor bolts on foundation
and to ensure matching of base plate that is drilled in advance. The schedule of supply
of template at site shall be 8 weeks from LOI.
17. Gaskets used for hydrotesting of equipment shall be of the same specification as service
gaskets and the fabricator shall supply new gaskets for manholes and nozzles with blind
/companion flanges apart from spares. Gaskets used for hydrotest shall not be used for
actual hook up.
18. Gaskets shall be as per data sheet, in case a equivalent gasket are being used; Gasket
catalogue indicating make / type / m & y value shall be furnished for approval by
Licensor. Vendor to furnish gasket drawing in separate A4 sheet (AUTOCAD Format).
19. While transporting completed equipment, fabricator shall provide suitable type and no. of
supports so that no deformation of any part of the equipment takes place.
20. Fabricator shall exercise utmost care during loading/unloading of equipment so that no
damage to any part of the equipment occurs. Suitable type and no. of supports shall be
provided for supporting the equipment.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
i) The equipment having length more than 20 m and / or forming ‘Gross vehicle
weight (Weight of equipment and the weight of vehicle clubbed together) more
than 32 MT shall be transported by Hydraulic axles only with compliance to all
statutory norms of authorities concerned.
ii) Prime mover of the Vehicle to have GPS tracking system to monitor the
movement of consignment.
iii) The required operational password shall be provided to EIL/Owner, to enable all
concerned to monitor movement en-route
22. Erection weight given in equipment data sheet is approximate. Vendor shall calculate the
actual equipment weight and furnish calculation. Erection weight furnished in vendor
drawing shall be based on fabricator’s calculation. Calculation of Centre of Gravity (C.G.)
of the equipment shall also be done by vendor and marked on the equipment & in the
fabrication GA drawing.
23. When spot radiography is specified the extent of radiography defined in Clause
5.4.2 of EIL specification 6-12-0001 Rev. 5 shall be replaced as follows:
24. Refer Spec 6-26-0001 Rev 3 attached with MR. Following modifications to this
specification shall be noted. However, final guarantee of agitator as per Cl. 7 of 6-26-
0001 lies with Bidder :
Clause Modification
2.1.5 The intent of this clause is to remove agitator without dismantling Vessel.
2.4.1(ii) Rigid type coupling without spacer is also acceptable subject to using slotted
coupling to obtain proper assembly.
2.4.3 Snug fit Rigid coupling is acceptable and Material shall be selected based on
vendor’s standard which shall be suitable for process conditions.
2.6.2(b) As an alternative to the requirements mentioned; Agitators can be designed for
full cold jamming condition
2.6.2(d) Maximum dynamic shaft deflection shall be limited to 0.15mm in place of 0.07mm.
Mechanical seals shall be designed for a maximum deflection of 0.5mm in normal
operating conditions and 1mm in extreme conditions.
2.6.2(e) Shaft runout of “1.0mm per meter” indicated in this clause may be read as
“1.0mm per meter on each side”
2.7.4 Dynamic balancing of agitators are required for units having rpm of 300 and
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
above.
2.8.3 For Mechanical seal, Agitator manufacturer may recommend the seal
manufacturer based on their experience. However final responsibility of
performance guarantee lies with Agitator supplier.
General Instructions
1. Inspection requirements are as mentioned hereunder. All materials including those used
for internals shall be procured with stage-wise inspection. Stage wise and final
inspection of equipments and its components shall be carried out by following:
Stagewise & final inspection of the equipment including all components and internals shall
be carried out by third party inspection agency. Quoted price shall include for the same.
EIL shall be inspection agency for equipments and its indigenous components. Incase
internals/forging/plates etc. are procured from abroad, the inspection shall be carried out by
third party inspection agency. Quoted price shall include for the same. Charges for EIL
inspection to be borne by the OWNER.
2. Raw material procurement may proceed prior to approval of vendor drawings on the
basis of Purchase Requisition. However for plates & nozzles where there is no Hold in
size, thickness, etc, material procurement shall be initiated by successful vendor based
on MR drawings immediately after placement of order.
3. Shell rolling/welding and dished - head fabrication shall commence without awaiting
fabrication drawing approval.
Inspection shall be carried out in accordance with Purchase Requisition documents till
approved fabrication drawings are available.
4. Material for shell, dished ends and skirt shall be considered as major raw material
wherever identification of major raw material is one of the payment milestones.
5. Purchase requisition shall be issued within two weeks of Fax of intent (FOI). Final nozzle
sizes (without any holds) shall be issued alongwith purchase requisition or latest within
two months of Fax of intent (FOI).
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
6. Nozzle orientation of the equipment shall be issued latest by mid of contractual delivery
period reckoned from date of issue of Fax of Intent (FOI).
7. Pipe support/structural clip details shall be issued latest by three months before
contractual delivery date.
8. Minimum course width shall be 1 metre. Maximum no. of longitudinal seams shall be as
follows:
( a) vessels upto 2 metre diameter : 1 seam
( b) vessels from 2 metre upto 4 metre dia. : 2 seam
( c) vessels from 4 metre upto 6 metre dia. : 3 seam
In any case, distance between two longitudinal seams shall not be less than 3 meter.
9. If any discrepancy is found during design and fabrication stages, the fabricator shall
inform EIL immediately and shall obtain necessary clarification/approval before
proceeding with that portion of the job any further.
EIL's review of fabricator's drawings and documents must not be considered as a check
and shall not relieve the fabricator of his responsibilities to supply equipment as per
requisition. Fabricator shall remain responsible for conflicts between his
drawings/documents and EIL drawings/documents.
10. English language and metric units shall be used in all documents. Drawings shall be
prepared in prescribed sizes as standardized by bureau of Indian standards (BIS) and
shall be preferably in the sizes such as 210 x 297, 297 x 420, 420 x 597, 597 x 841, 841
x 1189 mm.
11. All fabricator's drawings submitted to EIL shall be based on purchase requisition and
shall bear reference number and revision of the corresponding EIL drawings. In addition,
it shall indicate item number, client's name, project name, fabricator's name, purchase
order number, purchase requisition number, drawing number, revision number etc. all in
the lower right hand corner. All revisions shall be clearly marked by encircling with
revision marks.
13. Vendor shall submit a list of those drawings, which are to be submitted for review
to EIL along with the submission dates for each drawing within 15 days of
placement of FOI. A soft copy of this index shall also be provided in the format
provided. Vendor shall strictly adhere to this drawing submission schedule.
Updated vendor drawing / document submission schedule shall be forwarded
along with each submission. This shall be submitted in soft copy also.
14. All drawings shall be thoroughly checked and duly signed by fabricator. Unchecked
drawings and drawings without revisions clearly marked shall be returned without
review. Successive review of the same fabricator's drawing shall apply only to EIL's
latest data sheet/comments on the previous revision. Drawings and documents returned
to fabricator for revision shall be resubmitted preferably within ten days of receipt. In
case of items like demisters & agitators, sub-vendor’s drawing shall be reviewed and
duly signed by vessel fabricator before submission to EIL
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
15. Dimensions of all flanges shall be as per ANSI B16.5 for nozzle sizes 24"NB and below
and as per ANSI B16.47 Series B for sizes greater than 24"NB unless otherwise stated.
Stage-I
- General arrangement drawing indicating design data, fabricated equipment's
weight, general notes, nozzle schedule, detail of shell, heads, skirt/supporting
arrangement, main weld seams, nozzle orientation plan, cutting layout (in case of
free issue material) etc.
- Bill of material for each item showing part size, quantity, material specification,
scope of supply and weight etc.
Stage-II
- Detail of internals such as tray, tray support ring, support beam, inlet weir and
bolting bar.
- Detail of external clips for ladder, platform, pipe support, insulation, fire proofing,
pipe davit, lifting trunnion, tailing lugs, lifting lugs etc.
- Bill of material for each item showing part size, quantity, material specification,
scope of supply and weight etc.
- In case of owner's free issue plate material, fabricator shall submit plate cutting
diagram for EIL's approval.
17. After receipt of order, fabricator shall submit to EIL, the planning of fabrication which
shall indicate the details and scheduled date of:
- Sub orders.
- Purchase of materials such as plates, pipes, forged flanges, bolting, gaskets, etc.
- Start of fabrication of dished ends and shell, welding of shell and heads.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
18. All drawings shall be drawn in AUTOCAD R-14 or above.No hand drawn drawings shall
be accepted. All residual calculations shall be computerized.
19. Documents and letters shall be furnished in electronic format. The software used shall
be as follows.
20. In case of owner's free issue plate material, fabricator shall tabulate each plate detail as
per following table:
Fabricator shall be allowed 2% burnout losses against the material consumed in case of
pressure vessels and 1% in case of storage tanks and spheres unless otherwise specified. In
general purchase conditions.all offcuts of width 800mm and perimeter 2400mm in carbon
steel materials and 150mm width and perimeter 1500mm in stainless steel materials shall be
returned to owner, unless otherwise specified. Returnable offcuts shall have original plate
markings transferred and duly stamped by inspector. All other non returnable scrap shall be
sold by fabricator on the basis of owner's instructions and approval.
21. Words “fabricator”, “vendor”, “contractor” appearing any where in the MR/Specifications/
Standards etc. shall be read as “bidder”.
22. Bidder to note that interference of nozzles with circumferential seams is not acceptable.
Vendor to take suitable care to avoid fouling of external/internal attachments with shell
seams.
23. Vendor shall note that the vendor drawing for the following standard components (as
applicable) shall not be reviewed by EIL. It shall be solely vendor's responsibility to
ensure the correctness of these drawings as per EIL Standards and Drawings. If any
discrepancy / mistake is found at a later date the vendor shall rectify the same at his
time and cost.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
- Pipe support cleats and ladder and platform cleats (Fouling of external support
cleats (if any), shall be highlighted to EIL along with shell development drawing
and suggestion for resolution)
However all these above listed drawing shall be submitted in a separate drawing for
information to EIL ensuring adherence to all the respective EIL Standards and Drawings.
Clarifications (if any) shall be obtained by Vendor from EIL before fabrication.
24. Standard Inspection and test plans are attached with requisition for guidance. Vendor
shall submit inspection test plans for the approval of visiting inspection engineer.
Inspection shall take care of all the requirements of specifications. Inspection engineer
has the authority to modify the plan depending on the criticality of the item.
However in event of conflict it shall be the duty of the Vendor to bring it to EIL’s
attention for resolution and resolve it before proceeding with the manufacture.
EIL’s comments shall be final and binding on vendor without any cost and
delivery implications.
27. Equipment tag number shall be engraved/welded on all components (if equipment is
being sent in parts) and on all spares. If spares are small enough or if welding/engraving
will damage the spares, metallic tag shall be provided with equipment tag number. If
welding/engraving on equipment can result in damages, equipment tag number shall be
painted on the equipment or its part (minimum three locations). Color coding of spares
as per PFI (Pipe Fabrication Institute) Standard ES-22 shall be done.
28. All drawings / documents of Agitator and vessels with agitator submitted shall be
reviewed by Licensor also. Consolidated comments (including Licensor comments) shall
be furnished within 06-08 weeks after receipt of documents / drawings. Vendor shall
incorporate all these comments without any time and cost implications.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Annexure-II
Vendor list for Agitators:
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Annexure-III
Vendor list for Hoppers (Hastelloy):
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
The following drawings/documents marked " " shall be furnished by the bidder.
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
1. GENERAL ARRANGEMENT DRAWING
INDICATING DESIGN DATA FABRICATED
EQUIPMENT WEIGHT, GENERAL NOTES,
NOZZLE SCHEDULE, DETAIL OF SHELL,
HEADS, SUPPORTING ARRANGEMENT,
MAIN WELD SEAMS, NOZZLE ORIENTATION
PLAN, CUTTING LAYOUT ETC.
2. DETAIL OF NOZZLES, MANHOLES,
ACCESSORIES, AGITATOR ASSEMBLY &
MOUNTING ETC
3. DETAILS OF DEMISTER.
4. DETAILS OF PACKING SUPPORT,
DEMISTER SUPPORTS, GRATINGS, AND
GRATING SUPPORTS.
5. DETAIL OF INTERNAL DISTRIBUTOR.
6. DETAIL OF EXTERNAL CLIPS SUCH AS
LADDER, PLATFORM, PIPE SUPPORT.
7. DETAIL OF INSULATION, FIRE PROOFING
8. DETAIL OF PIPE DAVIT
9. DETAIL OF LIFTING LUG,TRUNION AND
TAILING LUG ETC.
10. CERTIFIED 'AS BUILT' DRAWINGS
INCORPORATING ACTUAL DIMENSIONS
AND MATERIAL USED, DULY CERTIFIED BY
THE INSPECTOR
11. DATA FOLDER AS PER SPECIFICATION
12. INSPECTION AND TESTING PLAN @
13. WELDING PROCEDURES AND
QUALIFICATION TEST REPORTS @
14. DESTRUCTIVE AND NON-DESTRUCTIVE
TEST REPORTS @
15. MATERIAL TEST CERTIFICATES @
16. RADIOGRAPHIC EXAMINATION REPORTS
WITH FILMS @
17. HEAT TREATMENT PROCEDURE AND TIME
TEMPERATURE CHARTS @
18. CODE CERTIFICATES (INCLUDING
INSPECTION CERTIFICATE, HYDROSTATIC
TEST CERTIFICATE, LOCAL CODE
REQUIREMENTS, RUBBING OF CODE
STAMP AND NAME PLATE ETC.) @
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
19. PACKING AND FORWARDING
INSTRUCTIONS @
20. ASSEMBLY AND INSTALLATION DETAIL
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
1. GENERAL ARRANGEMENT DRAWING
INDICATING DESIGN DATA FABRICATED
EQUIPMENT WEIGHT, GENERAL NOTES,
NOZZLE SCHEDULE, DETAIL OF SHELL,
HEADS, SUPPORTING ARRANGEMENT,
MAIN WELD SEAMS, NOZZLE ORIENTATION
PLAN, CUTTING LAYOUT ETC.
2. DETAIL OF NOZZLES, MANHOLES,
ACCESSORIES, AGITATOR ASSEMBLY &
MOUNTING ETC
3. MECHANICAL DESIGN CALCULATIONS OF
AGITATOR
4. AGITATOR GA DWG, DETAIL DRGS
CATALOGUE ETC.
5. DETAIL OF INTERNALS SUCH AS BASKET
6. DETAIL OF INTERNAL DISTRIBUTOR.
7. DETAIL OF INSULATION, FIRE PROOFING
8. DETAIL OF PIPE DAVIT
9. DETAIL OF LIFTING LUG,TRUNION AND
TAILING LUG ETC.
10. CERTIFIED 'AS BUILT' DRAWINGS
INCORPORATING ACTUAL DIMENSIONS
AND MATERIAL USED, DULY CERTIFIED BY
THE INSPECTOR
11. DATA FOLDER AS PER SPECIFICATION
12. INSPECTION AND TESTING PLAN @
13. WELDING PROCEDURES AND
QUALIFICATION TEST REPORTS @
14. MATERIAL TEST CERTIFICATES @
15. RADIOGRAPHIC EXAMINATION REPORTS
WITH FILMS @
16. HEAT TREATMENT PROCEDURE AND TIME
TEMPERATURE CHARTS @
17. CODE CERTIFICATES (INCLUDING
INSPECTION CERTIFICATE, HYDROSTATIC
TEST CERTIFICATE, LOCAL CODE
REQUIREMENTS, RUBBING OF CODE
STAMP AND NAME PLATE ETC.) @
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
18. PACKING AND FORWARDING
INSTRUCTIONS @
19. ASSEMBLY AND INSTALLATION DETAIL
20. FILLED IN MIXER/AGITATOR DATASHEET
Notes :
1. "TICK" denotes applicability.
2. Post order, drawing / document review shall commence only after approval of Document Control Index (DCI).
3. All post order documents shall be submitted / approved through EIL eDMS portal.
4. Final documentation shall be submitted in hard copy (Six prints) and soft ( two CDs/DVDs ) in addition to
submission through EIL eDMS.
5. Refer - 6-78-0001: Specification for quality management system from Bidders.
6. Refer - 6-78-0003: Specification for documentation requirement from Suppliers.
7. All drawings & documents shall be submitted in A4 or A3 paper sizes. Documents in higher paper size shall
be submitted in exceptional circumstances or as indicated in the MR/Tender.
8. Post order- The schedule of drawing / data submission shall be mutually agreed between EIL & the bidder /
contractor / supplier during finalization of Document Control Index (DCI).
9. Bill of Material shall form part of the respective drawing.
10. Also refer other department's VDR :-
11. Electrical
12. Instrumentation
13. "@"- These document shall be reviewed by EILs regional procurement office (RPO) pertaining to vendors
region. Vendor shall submit this document in hard copy to RPO-EIL for review.
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SECTION VIII DIV.-1 LATEST EDITION,PRACTICE
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm2g) ATM
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR AUSTENTIC SS VESSELS 6-12-0006 DESIGN PRESSURE (NOTE-27) (mmWCg) INT. F.W. +150 EXT. (-) 50
X1 1
200
12 THK. 150 SO RF 400 -
AGITATOR MOUNT+ AGITATIOR SUPPLIED BY VENDOR.
X BRACKET FOR NAME PLATE 7-12-0029 SUPPORT BASE SA 240 GR.316
(HOLD) ASSEMBLY + GASKET+BOLT 23 THE THICKNESS INDICATING IN THE ENGG. DATA SHEETS ARE THE MINIMUM TO BE NAME PLATE FOR SMALL EQUIPMENT 7-12-0030 INTERNAL PARTS (WELDED) SA 312 TP316 / SA 240 GR.316
MANHOLE + B.F. + DAVIT PROVIDED. VENDOR TO CHECK/VERIFY THE WHOLE DESIGN OF THE VESSEL AND DETAILS OF FORGED NOZZLES 7-12-0031 INTERNAL PARTS (BOLTED) SA 312 TP316 / SA 240 GR.316
MH1 1 600 6 THK. 150 SO RF 1660 255xT NOZZLE SIZE "X1" BASED ON PROCESS DATA SHEETS AND ACTUAL
+ GASKET + BOLT
DETAILS/PARAMETERS OF THE AGITATOR. ONLY UPWARD INCREASE IN THE X SUPPORTS FOR INTERNAL FEED PIPE 7-12-0032 CLIPS & ATTACHMENTS DIRECTLY WELDED
SA 240 GR.316
MANHOLE + B.F. + DAVIT HOT INSULATION SUPPORT FOR HORIZONTAL VESSEL 7-12-0033 (EXTERNAL)
MH2 1 600 6 THK. 150 SO RF 1660 255xT THICKNESS IS PERMISSIBLE.
+ GASKET + BOLT BIDDER TO QUOTE ACCORDINGLY KEEPING THIS ASPECT IN CONSIDERATION. NO PIPE DAVIT SUPPORT FOR COLD INS. VESSELS 7-12-0034 CLIPS & ATTACHMENTS WELDED OVER PAD
IS 2062 GR.E 250 QUALITY B
HANDHOLE + B.F. + DAVIT PRICE IMPLICATION AT LATER SHALL BE ALLOWED ON THIS ACCOUNT. TYP. DETAILS OF WIRE MESH DEMISTER SUPPORTS 7-12-0036 (EXTERNAL)
HH1 1 150 6 THK. 150 SO RF 400 -
+ GASKET + BOLT (NOTE-26) 24 FINAL LOAD AND FOUNDATION LOADING DATA TO BE CONFIRMED BY THE VENDOR. S.R NOZZLE NECK 7-12-0037 WRAPPER PLATE -
25 PIPE FITTINGS SHALL BE THE SAME SIZE AND THICKNESS AS THE ATTACHED PIPE. X ALLOWABLE NOZZLE LOADS 7-12-0038 DEMISTER/GRID -
26 HANDHOLE NOZZLE SHALL BE LOCATED JUST ABOVE VENT PIPE. PAD FOR EXTERNAL ATTACHMENT SA 240 GR.316
27 DESIGN PRESSURE OF HOPPER IS FW+150MM WC(g). LIFTING LUG SA 240 GR.316
28 VENDOR TO DESIGN LIFTING LUG FOR ERECTION OF COMPLETE EQUIPMENT WITH CURB ANGLE SA 240 GR.316
AGITATOR CONSIDERING AN IMPACT FACTOR OF 2.0. WIRE MESH SS 316
'T' DENOTES CORRESPONDING SHELL/DISH END/SKIRT NOMINAL THICKNESS.
29 LOCATION OF NIPPLE SHALL BE SUCH THAT OPERATOR CAN STAB BOTTOM OF HOPPER
WITH BAR THROUGH SAFETY BAR. HOPPER
30 MINIMUM THICKNESSES OF INTERNAL SHALL BE 6THK. IF NOT SPECIFIED. TOP PLATE SA 240 GR.316
31 DESIGN LOAD FOR BASKET IS 4.0 KN WHICH IS WEIGHT OF HQ. SHELL / CONE SB 575 HASTELLOY C-276
MESH OF BASKET SHALL BE PROPERLY SECURED WITH ROD & END PLATE. NOZZLE FLANGES SB 462 HASTELLOY C-276
ALL FILLED WELD SHALL BE MINIMUM 6MM. REFERENCE DRAWINGS¼jsQjsUl MkbZx½ NOZZLE NECK UPTO 100 NB SB 622 HASTELLOY C-276
32 ALL REQUIREMENTS OF PDS SHALL BE COMPLIED. NOZZLE ORIENTATIONS NOZZLE NECK ABOVE 100 NB SB 575 HASTELLOY C-276
NECESSARY FREE SPACE ON TOP OF THE VESSEL IS REQUIRED FOR LIFTING AND REMOVING OF THE LADDERS/PLATFORM CLEATS PIPE FITTINGS SB 366 HASTELLOY C-276
AGITATOR ASSEMBLY. PIPE SUPPORT CLEATS GASKET INTERNAL V#7010 OR EQUIVALENT
TRAY SUPPORT AND BOLTING BARS EXTERNAL STUDS/BOLTS/NUTS SB 574
DEMISTER DATA SHEET INTERNAL STUDS/BOLTS/NUTS SB 574
X PROCESS DATA SHEET PDPP-DS-V405 SUPPORT SA 516 GR.70 WITH SB 575 PAD
X AGITATOR DATA SHEET PDPP-DS-A405 INTERNAL PARTS SB 575 / SB 622 / SB 366
SEISMIC
36000 11000
SUPPORT HEIGHT X LADDER/PLATFORM CLEATS
ERECTION 12500 OPERATING 41000
LICENSOR'S STANDARD (DB) DETAILS OF INTERNALS TRAY SUPPORT/BOLTING BARS
ykbZlsUlj LVS.MlZ SEISMIC PIPE DAVIT
(MC) - - PACKING SUPPORT
HYDROTEST(SHOP) 43900 HYDROTEST ( FIELD ) 46000
JOB NO: UNIT NO: DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A842
;÷fuV l[;k PDE MkbZx uEcj REV
NEW DELHI CLIENT :
M/s BPCL, KOCHI CATALYST MIXING DRUM dSVyhLV fefDlax Mªe A842-PDE-80-43-DS-3405 0
DykbZV 0 12.04.2017 REVISED AS MARKED & ISSUED FOR PURCHASE. AKP SA PVS
bathfu;lZ bafM;k fyfeVsM PLANT : A 26.07.2016 ISSUED FOR BIDS/ENGG. SV SK/VIVEK IK
¼Hkkjr ljdkj dk midze½ IykaV PDPP
REVISION APPROVED
ITEM NO. PDE-V-405 vAbVe uEcj ihMhbZ&oh&405 SHEET 1 OF 3
REV DATE BY CHECKED
FORMAT NO.3-1646-0122 REV.2 (06.12.2011) A3-420 X 297
NOZZLES AND CONNECTIONS ¼uksty o duSD'ku½ GENERAL NOTES (tujy uksV~l½ SPECIFICATIONS ¼LisflfQds'lUl½ DESIGN DATA ¼fMtkbu MkVk½
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SECTION VIII DIV.-1 LATEST EDITION
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm g)
2
ATM
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR AUSTENTIC SS VESSELS 6-12-0006 DESIGN PRESSURE (mmWCg) INT. F.W. +150 EXT. NIL
N1 1 50 80S 150 SO RF
SEE
- LIQUID FROM LZ 441
3 NORTH DIRECTION WHEREVER SHOWN IS WITH RESPECT TO PLAN VIEW. X STD. SPEC. FOR BQCS PLATE 6-12-0011 WORKING TEMPERATURE (0C) 32
DWG. 4 (A) FOR NOZZLES ON SHELL PROJECTIONS ARE REFERRED FROM VESSEL CENTER LINE TO STD. SPEC. FOR STRUCTRAL QUALITY PLATES 6-12-0014 DESIGN TEMPERATURE (0C) 65
N2 1 50 80S 150 SO RF
SEE
- LIQUID FROM LZ 451
FLANGE CONTACT FACE.
X STD. SPEC. FOR SS PLATE 6-12-0020 MDMT ( 0C) 15
DWG. 4 (B) FOR NOZZLES ON HEAD PROJECTIONS ARE REFERRED FROM HEAD T.L TO FLANGE JOB SPEC. FOR SURFACE PREPARATION & PROTECTIVE CORROSION ALLLOWANCE (MM) 0 FOR SS
SEE CONTACT FACE. X COATING A842-000-79-41-PLS-01
TYPE OF HEAD FLAT
N3 1 50 80S 150 SO RF - LIQUID FROM LZ 451
DWG. 5 THE INDICATED THICKNESS IS THE MINIMUM ACCEPTABLE AFTER CONSTRUCTION. JOINT EFFICIENCY SHELL 0.85 HEAD 1
6 FLANGE GASKET FACE SHALL HAVE 125 AARH FINISH. RADIOGRAPHY SHELL SPOT HEAD FULL
N4 1 50 80S 150 SO RF 1510 - LIQUID FROM V-471
7 DIMENSIONS OF FLANGES FOR NOZZLES UPTO 600NB SHALL BE AS PER ASME B16.5
STANDARDS ¼LVS.MMZl½ POST WELD HEAT TREATMENT -
N12 1
50
80S 150 SO RF
SEE
- MIN. FLOW (FROM P-524A/B)
16 AFTER HYDROTEST ALL WELDS IN PRESSURE PARTS SHALL BE CHECKED BY DP X STANDARD BOLT HOLE ORIENTATION 7-12-0015
(HOLD) DWG. EXAMINATION. 7-12-0016 SHELL/BOOT SA 240 GR.304
ALLOY LINER DETAILS
17 ALL WELD LINES ON THE INNER SURFACE SHALL BE SMOOTHLY FINISHED BY A SIGHT GLASSES FOR PRESSURE VESSELS 7-12-0017 REINFORCEMENT PAD/INSERT PLATE SA 240 GR.304
N13 1 80 80S 150 SO RF 1560 45xT OVER FLOW GRINDER.
X INTERNAL FLANGES 7-12-0018 BOTTOM PLATE/TOP PLATE SA 240 GR.304
SEE VORTEX BREAKERS 7-12-0019 SHELL FLANGES -
N14 1 50 80S 150 SO RF - FCS INLET
DWG. INLET DEFLECTOR BAFFLE 7-12-0020 NOZZLE FLANGES SA 182 F304
SEE SUPPORT RING AND BOLTING BAR 7-12-0021 NOZZLE NECK UPTO 150 NB SA 312 TP304
V1 1 80 80S 150 SO RF 45xT VENT
DWG. SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 NOZZLE NECK ABOVE 150 NB SA 240 GR.304
PIPE DAVIT 7-12-0023 PIPE FITTINGS SA 403 GR.304 (SEAMLESS)
D1 1 50 80S 150 SO RF 1510 - DRAIN
LIFTING LUG TOP HEAD TYPE 7-12-0024 GASKET EXTERNAL V#7010 OR EQUIVALENT
FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025 GASKET INTERNAL(NOTE-13) V#7010 OR RQUIVALENT
D2 1 50 80S 150 SO RF 1510 - DRAIN
X EARTHING LUG 7-12-0026 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7 / SA 194 GR.2H
HH1 1 150 150 SO RF 1560 85xT HANDHOLE + B.F. X ALLOWABLE NOZZLE LOADS 7-12-0038 DEMISTER/GRID -
PAD FOR EXTERNAL ATTACHMENT SA 240 GR.304
LIFTING LUG SA 516 GR.70
'T' DENOTES CORRESPONDING SHELL/DISH END/SKIRT NOMINAL THICKNESS.
CURB ANGLE SA 240 GR.304
JOB NO: UNIT NO: DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A842
;÷fuV l[;k PDE MkbZx uEcj REV
NEW DELHI CLIENT :
M/s BPCL, KOCHI WATER SURGE DRUM okVj ltZ Mªe A842-PDE-80-43-DS-3425 0
DykbZV 0 12.04.2017 REVISED AS MARKED & ISSUED FOR PURCHASE. AKP SA PVS
bathfu;lZ bafM;k fyfeVsM PLANT : A 28.06.2016 ISSUED FOR BIDS/ENGG. TAA DG/MKP -
¼Hkkjr ljdkj dk midze½ IykaV PDPP
REVISION APPROVED
ITEM NO. PDE-V-425 vkbVe uEcj ihMhbZ&oh&425 SHEET 1 OF 2
REV DATE BY CHECKED
FORMAT NO.3-1646-0122 REV.2 (06.12.2011) A3-420 X 297
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTION PAD
SERVICE
UNLESS STATED OTHER WISE
X DENOTES APPLICABLITY CODE ASME SEC VIII DIV. 1 EDITION 2015
ukfeuy 'kMwy o CLASS TYPE FACING NOTE-4 WxT
1 ALL DIMENSIONS ARE IN MM. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm 2g) ATM
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl SUPP. SPEC. FOR CS VESSELS 6-12-0002 DESIGN PRESSURE (mmWCg) INT FW+150 EXT -50
SEE 6 FLANGE GASKET FACE SHALL HAVE 125 AARH FINISH. WOODEN PILLOWS FOR SADDLE SUPPORT 7-12-0003 SP. GRAVITY 0.884
V1 1 80 80S 150 SO RF - VENT
DWG 7 SKIRT BASE DETAILS 7-12-0004 WIND SPECIFICATION IS 875
DIMENSIONS OF FLANGES FOR NOZZLES UPTO 600NB SHALL BE AS
SEE PER ASME B16.5 AND FOR NOZZLE ABOVE 600NB SHALL BE AS PER SKIRT OPENING DETAILS 7-12-0005 SEISMIC IS 1893 + SITE SPECTRA
D1 1 50 80S 150 SO RF - DRAIN ASME B16.47 SERIES `B' UNLESS SPECIFIED OTHERWISE.
DWG ANGLE LEG SUPPORT 7-12-0006 CAPACITY (M3) 0.9
LEVEL TRANSMITTER (DP 8 ID OF WELD NECK FLANGES SHALL MATCH WITH CORRESPONDING PIPE LEG SUPPORT 7-12-0007 PAINTING/CLEANING AS PER SPEC
L1/L2 2 80 80S 150 SO RF 460 40x4 ID OF NOZZLE PIPE.
DIASEAL) 0 X BRACKET SUPPORT FOR VERTICAL VESSEL 7-12-0008 INSULATION THICKNESS (mm) NIL HOT COLD
SIGHT GLASS CONNECTION 9 NOZZLES 50NB AND BELOW SHALL BE STIFFENED WITH 2NOS. 40 MANHOLE WITH HINGED COVER 7-12-0009 FIRE PROOFING (mm) (BY OTHERS) NIL YES NO
SG1-8 8 AS PER EIL STD 7-12-0017 X 6 THK. FLATS 90° APART.
(REFER NOTE-15) X MANHOLE WITH DAVIT (FOR GUIDANCE) 7-12-0010 HYDROSTATIC TEST (kg/cm2g) HORIZONTAL VERTICAL (AT TOP)
SIGHT GLASS CONNECTION FOR 10 ALL NOZZLES FABRICATED FROM PLATE SHALL BE 100% LADDER RUNGS FOR MANHOLE/DEMISTER 7-12-0011 PRESSURE (NEW & COLD) FULL OF WATER
G1-8 8 50 80S 150 SO RF 460 - RADIOGRAPHED.
LIGHTING (REFER NOTE-15) RETAINING PLATE 7-12-0012 INSPECTION BY X EIL/TPIA CIB LLOYDS
11 AFTER COMPLETION OF FABRICATION & TESTING, ALL SS CLAD
SURFACES & SS INTERNALS(BOTH SIDES) SHALL BE PICKLED &
X NOZZLE REINFORCEMENT AND PROJECTION 7-12-0013 MATERIAL OF CONSTRUCTION ¼eSfVfj;y vk¡Q dUlVªD'ku)
PAD NOZZLES FOR VESSELS 7-12-0014 (AS PER ASME / IS OR EQUIVALENT)
PASSIVATED IN ACCORDANCE WITH ASTM A-380
12 ALL PLATES, WELDS AND HAZ SHALL BE IGC TESTED AS X STANDARD BOLT HOLE ORIENTATION 7-12-0015 SHELL SA 240 GR.304
PER ASTM A262 PRACTICE-E. ALLOY LINER DETAILS 7-12-0016 REINFORCEMENT PAD SA 240 GR.304
13 AFTER HYDROTEST ALL WELDS IN PRESSURE PARTS X SIGHT GLASSES FOR PRESSURE VESSELS 7-12-0017 HEADS SA 240 GR.304
SHALL BE CHECKED BY DP EXAMINATION. INTERNAL FLANGES 7-12-0018 SHELL FLANGES SA 240 GR.304
14 ALL WELDING LINES ON THE INNER SURFACE SHALL BE VORTEX BREAKERS 7-12-0019 NOZZLE FLANGES SA 182 F304
SMOOTHLY FINISHED BY A GRINDER INLET DEFLECTOR BAFFLE 7-12-0020 NOZZLE NECK UPTO 100 NB SA 312 TP 304
15 FOR SIGHT GLASS CONNECTION DETAILS, REFER SHT. 2 SUPPORT RING AND BOLTING BAR 7-12-0021 NOZZLE NECK ABOVE 100 NB -
OF 2 OF EIL STD. 7-12-0017 AND FOR SIGHT GLASS SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 PIPE FITTINGS SA 403 WP 304 (SEAMLESS)
CONNECTION FOR LIGHTING DETAILS, REFER SHT. 1 OF 2 PIPE DAVIT V#7010 OR EQ.
7-12-0023 GASKET EXTERNAL
OF EIL STD. 7-12-0017.
LIFTING LUG TOP HEAD TYPE 7-12-0024 GASKET INTERNAL SS 304
X FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7/ SA 194 GR.2H
NO PLATFORM/PIPE CLIP SHALL BE SUPPORTED FROM THIS X EARTHING LUG 7-12-0026 INTERNAL STUDS/BOLTS/NUTS SS 304
NAME PLATE 7-12-0027 SKIRT / SUPPORT IS 2062 GR. E250 QUALITY B
EQUIPMENT. MANUFACTURER NAME PLATE 7-12-0028 SKIRT / SUPPORT BASE IS 2062 GR. E250 QUALITY B
BRACKET FOR NAME PLATE 7-12-0029 INTERNAL PARTS (WELDED) SA 240 TP 304
TYPE
MAX MOMENT AT BASE (M) MAX. SHEAR FORCE AT BASE (H) X NOZZLE ORIENTATIONS SIZE OF NOZZLES PETROLEUM & EXPLOSIVES SAFETY ORGANISATION, (PESO)
(kgm) (kg) NOZZLE ELEVATIONS PIPE SUPPORT CLEATS
JOB NO: VESSEL DESIGN DATA oSly fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A842 PDE MkbZx uEcj REV
(A Govt. OF India Undertaking) CLIENT :
BPCL,KOCHI
0 12.04.2017REVISED AS MARKED & ISSUED FOR PURCHASE. AKP SA PVS SCUM SEPERATOR स्कम सेपेरटोर A842-PDE-80-43-DS-3433 0
DykbZV REVISED SHEET-2 SG/VIVEK
bathfu;lZ bafM;k fyfeVsM PLANT : PROPYLENE DERIVATIVES
B
A
03.10.2016
28.06.16 ISSUED FOR BIDS/ENGG.
TAA
TAA AS/SG
IK
VIVEK
¼Hkkjr ljdkj dk midze½ IykaV PETROCHEMICAL PROJECT (PDPP) REV DATE REVISION BY CHECKED APPROVED
ITEM NO. PDE-V-433 पीडीई&वी&433 SHEET 1 OF 3
FORMAT NO.3-1646-0113 REV.0 A3-420 X 297
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTION PAD
SERVICE X DENOTES APPLICABLITY CODE ASME SEC VIII DIV. 1 EDITION 2015
ukfeuy 'kMwy o CLASS TYPE FACING NOTE-4 WxT
1 ALL DIMENSIONS ARE IN MM. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm 2g) ATM
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl SUPP. SPEC. FOR CS VESSELS 6-12-0002 DESIGN PRESSURE (mmWCg) INT FW+150 EXT -50
V1 1 80 80S 150 SO RF
SEE
- VENT 5
THE INDICATED THICKNESS IS THE MINIMUM ACCEPTABLE AFTER X VESSEL TOLERANCES 7-12-0001 HEAT TREATMENT HEAD AS PER SPEC./CODE
DWG CONSTRUCTION. SUPPORT FOR HORIZONTAL VESSEL 7-12-0002 OPERATING MEDIUM PROCESS FLUID
SEE 6 FLANGE GASKET FACE SHALL HAVE 125 AARH FINISH. WOODEN PILLOWS FOR SADDLE SUPPORT 7-12-0003 SP. GRAVITY 0.884
D1 1 50 80S 150 SO RF - DRAIN
DWG 7 SKIRT BASE DETAILS 7-12-0004 WIND SPECIFICATION IS 875
DIMENSIONS OF FLANGES FOR NOZZLES UPTO 600NB SHALL BE AS
SIGHT GLASS CONNECTION PER ASME B16.5 AND FOR NOZZLE ABOVE 600NB SHALL BE AS PER SKIRT OPENING DETAILS 7-12-0005 SEISMIC IS 1893 + SITE SPECTRA
SG1-17 17 AS PER EIL STD 7-12-0017 ASME B16.47 SERIES `B' UNLESS SPECIFIED OTHERWISE.
(REFER NOTE-15) ANGLE LEG SUPPORT 7-12-0006 CAPACITY (M3) 1.5
SIGHT GLASS CONNECTION FOR 8 ID OF WELD NECK FLANGES SHALL MATCH WITH CORRESPONDING PIPE LEG SUPPORT 7-12-0007 PAINTING/CLEANING AS PER SPEC.
G1-17 17 50 80S 150 SO RF 460 - ID OF NOZZLE PIPE.
LIGHTING (REFER NOTE-15)
X BRACKET SUPPORT FOR VERTICAL VESSEL 7-12-0008 INSULATION THICKNESS (mm) NIL HOT COLD
9 NOZZLES 50NB AND BELOW SHALL BE STIFFENED WITH 2NOS. 40 MANHOLE WITH HINGED COVER 7-12-0009 FIRE PROOFING (mm) (BY OTHERS) NIL YES NO
X 6 THK. FLATS 90° APART.
X MANHOLE WITH DAVIT (FOR GUIDANCE) 7-12-0010 HYDROSTATIC TEST (kg/cm2g) HORIZONTAL VERTICAL (AT TOP)
10 ALL NOZZLES FABRICATED FROM PLATE SHALL BE 100% LADDER RUNGS FOR MANHOLE/DEMISTER 7-12-0011 PRESSURE (NEW & COLD) FULL OF WATER
RADIOGRAPHED.
RETAINING PLATE 7-12-0012 INSPECTION BY X EIL/TPIA CIB LLOYDS
11 AFTER COMPLETION OF FABRICATION & TESTING, ALL SS CLAD
SURFACES & SS INTERNALS(BOTH SIDES) SHALL BE PICKLED &
X NOZZLE REINFORCEMENT AND PROJECTION 7-12-0013 MATERIAL OF CONSTRUCTION ¼eSfVfj;y vk¡Q dUlVªD'ku)
PAD NOZZLES FOR VESSELS 7-12-0014 (AS PER ASME / IS OR EQUIVALENT)
PASSIVATED IN ACCORDANCE WITH ASTM A-380
12 ALL PLATES, WELDS AND HAZ SHALL BE IGC TESTED AS X STANDARD BOLT HOLE ORIENTATION 7-12-0015 SHELL SA 240 GR.304
PER ASTM A262 PRACTICE-E. ALLOY LINER DETAILS 7-12-0016 REINFORCEMENT PAD SA 240 GR.304
13 AFTER HYDROTEST ALL WELDS IN PRESSURE PARTS X SIGHT GLASSES FOR PRESSURE VESSELS 7-12-0017 HEADS SA 240 GR.304
SHALL BE CHECKED BY DP EXAMINATION. INTERNAL FLANGES 7-12-0018 SHELL FLANGES SA 240 GR.304
14 ALL WELDING LINES ON THE INNER SURFACE SHALL BE VORTEX BREAKERS 7-12-0019 NOZZLE FLANGES SA 182 F 304
SMOOTHLY FINISHED BY A GRINDER INLET DEFLECTOR BAFFLE 7-12-0020 NOZZLE NECK UPTO 100 NB SA 312 TP 304
15 FOR SIGHT GLASS CONNECTION DETAILS, REFER SHT. 2 SUPPORT RING AND BOLTING BAR 7-12-0021 NOZZLE NECK ABOVE 100 NB -
OF 2 OF EIL STD. 7-12-0017 AND FOR SIGHT GLASS SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 PIPE FITTINGS SA 403 WP 304 (SEAMLESS)
CONNECTION FOR LIGHTING DETAILS, REFER SHT. 1 OF 2 PIPE DAVIT V#7010 OR EQ.
7-12-0023 GASKET EXTERNAL
OF EIL STD. 7-12-0017.
LIFTING LUG TOP HEAD TYPE 7-12-0024 GASKET INTERNAL SS 304
X FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7/ SA 194 GR.2H
NO PLATFORM/PIPE CLIP SHALL BE SUPPORTED FROM THIS X EARTHING LUG 7-12-0026 INTERNAL STUDS/BOLTS/NUTS SS 304
NAME PLATE 7-12-0027 SKIRT / SUPPORT IS 2062 GR. E250 QUALITY B
EQUIPMENT. MANUFACTURER NAME PLATE 7-12-0028 SKIRT / SUPPORT BASE IS 2062 GR. E250 QUALITY B
BRACKET FOR NAME PLATE 7-12-0029 INTERNAL PARTS (WELDED) SA 240 TP 304
X SUPPORTS FOR INTERNAL FEED PIPE 7-12-0032 CLIPS & ATTACHMENTS WELDED OVER PAD (EXTERNAL) IS 2062 GR. E250 QUALITY B
HOT INSULATION SUPPORT FOR HORIZONTAL VESSEL 7-12-0033 PAD FOR EXTERNAL ATTACHMENT SA 240 TP 304
PIPE DAVIT SUPPORT FOR COLD INS. VESSELS 7-12-0034 PIPE DAVIT SA 106 GR.B/SA 53
TYP. DETAILS OF WIRE MESH DEMISTER SUPPORTS 7-12-0036
S.R NOZZLE NECK (FOR GUIDANCE) 7-12-0037
TYPE
MAX MOMENT AT BASE (M) MAX. SHEAR FORCE AT BASE (H) X NOZZLE ORIENTATIONS SIZE OF NOZZLES PETROLEUM & EXPLOSIVES SAFETY ORGANISATION, (PESO)
(kgm) (kg) NOZZLE ELEVATIONS PIPE SUPPORT CLEATS
JOB NO: VESSEL DESIGN DATA oSly fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A842 PDE MkbZx uEcj REV
(A Govt. OF India Undertaking) CLIENT :
BPCL,KOCHI
0 12.04.2017REVISED AS MARKED & ISSUED FOR PURCHASE. AKP SA PVS OIL SEPERATOR ऑइल सेपेरटोर A842-PDE-80-43-DS-3432 0
DykbZV REVISED SHEET-2 SG/VIVEK
bathfu;lZ bafM;k fyfeVsM PLANT : PROPYLENE DERIVATIVES
B
A
03.10.2016
28.06.16 ISSUED FOR BIDS/ENGG.
TAA
TAA AS/SG
IK
VIVEK
¼Hkkjr ljdkj dk midze½ IykaV PETROCHEMICAL PROJECT (PDPP) REV DATE REVISION BY CHECKED APPROVED
ITEM NO. PDE-V-432 पीडीई&वी&432 SHEET 1 OF 3
FORMAT NO.3-1646-0113 REV.0 A3-420 X 297
NOZZLES AND CONNECTIONS ¼uksty o duSD'ku½ 0 GENERAL NOTES (tujy uksV~l½ SPECIFICATIONS ¼LisflfQds'lUl½ DESIGN DATA ¼fMtkbu MkVk½
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SECTION VIII DIV.-1 EDITION-LATEST
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm2g) ATM
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR AUSTENTIC SS VESSELS 6-12-0006 DESIGN PRESSURE (kg/cm2g) INT. 3.5 EXT. -
0
3 NORTH DIRECTION WHEREVER SHOWN IS WITH RESPECT TO PLAN VIEW. STD. SPEC. FOR BQCS PLATE 6-12-0011 WORKING TEMPERATURE ( C) 35
N1 1 80 80S 150 SO RF 1710 40 X T LIQUID FROM V-430
4 (A) FOR NOZZLES ON SHELL PROJECTIONS ARE REFERRED FROM HORIZONTAL X STD. SPEC. FOR STRUCTRAL QUALITY PLATES 6-12-0014 DESIGN TEMPERATURE 0
( C) 65
N5 1
100
40S 150 SO RF 2075 50 X T MIN. FLOW
7 DIMENSIONS OF FLANGES FOR NOZZLES UPTO 600NB SHALL BE AS PER ASME X VESSEL TOLERANCES 7-12-0001 HEAT TREATMENT HEAD AS PER SPEC./CODE
(HOLD) B16.5 AND FOR NOZZLE ABOVE 600NB SHALL BE AS PER ASME B16.47
UNLESS SPECIFIED OTHERWISE.
X SUPPORT FOR HORIZONTAL VESSEL 7-12-0002 OPERATING MEDIUM PROCESS FLUID
WOODEN PILLOWS FOR SADDLE SUPPORT 7-12-0003 SP. GRAVITY 0.884
N6 1 80 80S 150 SO RF 2000 40 X T EQUALIZATION
WIND SPECIFICATION IS 875
8 ID OF WELD NECK FLANGES SHALL MATCH WITH CORRESPONDING ID OF SKIRT BASE DETAILS 7-12-0004
SEE NOZZLE PIPE/SHELL. SKIRT OPENING DETAILS 7-12-0005 SEISMIC IS 1893 + SITE SPECTRA
N7 1 100 80S 150 SO RF 50 X T OVER FLOW
DRG. 9 NOZZLES 50NB AND BELOW SHALL BE STIFFENED WITH 2 NOS. 40 x 6 THK ANGLE LEG SUPPORT 7-12-0006 CAPACITY (M ) 3 49.7
FLATS 900 APART. PIPE LEG SUPPORT 7-12-0007 PAINTING/CLEANING AS PER PAINTING JOB SPEC.
N8 1 80 80S 150 SO RF 2000 40 X T GAS FROM V-420
10 ALL NOZZLES FABRICATED FROM PLATE SHALL BE 100% RADIOGRAPHED. INSULATION THICKNESS (mm) NIL HOT
BRACKET SUPPORT FOR VERTICAL VESSEL 7-12-0008 COLD
11 SURFACE CLEANING/ PRIMER SHALL BE AS PER JOB SPECIFICATION. MANHOLE WITH HINGED COVER 7-12-0009 FIRE PROOFING YES X NO
V1 1 100 80S 150 SO RF 2000 50 X T VENT
12 MOC OF INTERNAL GASKET SHALL BE SUITABLE FOR THE DESIGN TEMPERATURE. X MANHOLE WITH DAVIT 7-12-0010 HYDROSTATIC TEST (kg/cm2g) HORIZONTAL (AT TOP)
SEISMIC
_ _
SUPPORT HEIGHT X LADDER/PLATFORM CLEATS
ERECTION 9500 OPERATING 50000
LICENSOR'S STANDARD (DB) DETAILS OF INTERNALS TRAY SUPPORT/BOLTING BARS
ykbZlsUlj LVS.MlZ SEISMIC PIPE DAVIT
(MC) _ _ PACKING SUPPORT
HYDROTEST(SHOP) 59200 HYDROTEST ( FIELD ) 62500
WIND _ _ NUMBER OF ITEMS : ONE
JOB NO: UNIT NO: DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A842
;÷fuV l[;k PDE MkbZx uEcj REV
NEW DELHI CLIENT : V-440 FEED DRUM वी&400 फीड ड्रम
DykbZV M/s BPCL, KOCHI
0 12.04.2017 REVISED AS MARKED & ISSUED FOR PURCHASE. AKP SA
A842-PDE-80-43-DS-3431 0
bathfu;lZ bafM;k fyfeVsM PLANT : A 06.07.2016 ISSUED FOR BIDS/ENGG. JSN SA/VIVEK
PVS
IK
PDPP ITEM NO. PDE-V-431 vkbVe uEcj & ihMhई&oh&431 SHEET 1 OF 2
¼Hkkjr ljdkj dk midze½ IykaV REV DATE REVISION BY CHECKED APPROVED
FORMAT NO.3-1646-0122 REV.2 (06.12.2011) A3-420 X 297
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SECTION VIII DIV.-1 LATEST EDITION,PRACTICE
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm2g) ATM
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR AUSTENTIC SS VESSELS 6-12-0006 DESIGN PRESSURE (NOTE-27) (mmWCg) INT. F.W. +100 EXT. (-) 50
V2 1 50 80S 150 SO RF
REFER
- VENT
14 AFTER COMPLETION OF FABRICATION & TESTING, ALL SS CLAD SURFACES & SS X LADDER RUNGS FOR MANHOLE/DEMISTER 7-12-0011 PRESSURE (NEW & COLD) FULL OF WATER
DRG. INTERNALS(BOTH SIDES) SHALL BE PICKLED & PASSIVATED IN ACCORDANCE WITH RETAINING PLATE 7-12-0012 INSPECTION BY X EIL/TPIA CIB LLOYDS
REFER
ASTM A-380.
X NOZZLE REINFORCEMENT AND PROJECTION 7-12-0013 MATERIAL OF CONSTRUCTION ¼eSfVfj;y vk¡Q dUlVªD'ku)
D1~2 2 50 80S 150 SO RF - DRAIN
DRG. 15 ALL PLATES, WELDS AND HAZ SHALL BE IGC TESTED AS PER ASTM A262 PRACTICE-E. PAD NOZZLES FOR VESSELS 7-12-0014 (AS PER ASME / IS OR EQUIVALENT)
X1 1
200
12 THK. 150 SO RF 400 -
AGITATOR MOUNT+ AGITATIOR 21 FULL AGITATOR ASSEMBLY INCLUDING MOTOR, GEARBOX, ALL SUPPORTS, DRIVES X FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025 GASKET INTERNAL(NOTE-13) V#7010 OR EQUIVALENT
(HOLD) ASSEMBLY + GASKET+BOLT INCLUDING ALL ACCESSORIES AND SPARES ETC. ARE TO BE DESIGNED AND SUPPLIED
BY VENDOR.
X EARTHING LUG 7-12-0026 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7 / SA 194 GR.4
SEISMIC
15000 4000
SUPPORT HEIGHT X LADDER/PLATFORM CLEATS
ERECTION 7500 OPERATING 15000
LICENSOR'S STANDARD (DB) DETAILS OF INTERNALS TRAY SUPPORT/BOLTING BARS
ykbZlsUlj LVS.MlZ SEISMIC PIPE DAVIT
(MC) - - PACKING SUPPORT
HYDROTEST(SHOP) 16500 HYDROTEST ( FIELD ) 18000
JOB NO: UNIT NO: DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A842
;÷fuV l[;k PDE MkbZx uEcj REV
NEW DELHI CLIENT :
M/s BPCL, KOCHI CATALYST MIXING DRUM dSVyhLV fefDlax Mªe A842-PDE-80-43-DS-3505 0
DykbZV 0 12.04.2017 REVISED AS MARKED & ISSUED FOR PURCHASE. AKP SA PVS
bathfu;lZ bafM;k fyfeVsM PLANT : A 26.07.2016 ISSUED FOR BIDS/ENGG. SV SK/VIVEK IK
¼Hkkjr ljdkj dk midze½ IykaV PDPP
REVISION APPROVED
ITEM NO. PDE-V-505 vAbVe uEcj ihMhbZ&oh&505 SHEET 1 OF 3
REV DATE BY CHECKED
FORMAT NO.3-1646-0122 REV.2 (06.12.2011) A3-420 X 297
NOZZLES AND CONNECTIONS ¼uksty o duSD'ku½ GENERAL NOTES (tujy uksV~l½ SPECIFICATIONS ¼LisflfQds'lUl½ DESIGN DATA ¼fMtkbu MkVk½
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTI
ON NOTE-
PAD W
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SECTION VIII DIV.-1 LATEST EDITION
ukfeuy 'kMwy o CLASS TYPE FACING 4
xT 1 ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (kg/cm g)
2
ATM
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izksts'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. X SUPP. SPEC. FOR AUSTENTIC SS VESSELS 6-12-0006 DESIGN PRESSURE (mmWCg) INT. F.W. +150 EXT. NIL
N1 1 50 80S 150 SO RF
SEE
- LIQUID FROM LZ-541
3 NORTH DIRECTION WHEREVER SHOWN IS WITH RESPECT TO PLAN VIEW. X STD. SPEC. FOR BQCS PLATE 6-12-0011 WORKING TEMPERATURE (0C) 37
DWG. 4 (A) FOR NOZZLES ON SHELL PROJECTIONS ARE REFERRED FROM VESSEL CENTER LINE TO STD. SPEC. FOR STRUCTRAL QUALITY PLATES 6-12-0014 DESIGN TEMPERATURE (0C) 65
N2 1 50 80S 150 SO RF
SEE
- LIQUID FROM LZ-541
FLANGE CONTACT FACE.
X STD. SPEC. FOR SS PLATE 6-12-0020 MDMT ( 0C) 15
DWG. 4 (B) FOR NOZZLES ON HEAD PROJECTIONS ARE REFERRED FROM HEAD T.L TO FLANGE JOB SPEC. FOR SURFACE PREPARATION & PROTECTIVE CORROSION ALLLOWANCE (MM) 0 FOR SS
SEE CONTACT FACE. X COATING A842-000-79-41-PLS-01
TYPE OF HEAD FLAT
N3 1 50 80S 150 SO RF - LIQUID FROM LZ -551
DWG. 5 THE INDICATED THICKNESS IS THE MINIMUM ACCEPTABLE AFTER CONSTRUCTION. JOINT EFFICIENCY SHELL 0.85 HEAD 1
6 FLANGE GASKET FACE SHALL HAVE 125 AARH FINISH. RADIOGRAPHY SHELL SPOT HEAD FULL
N4 1 50 80S 150 SO RF
SEE
DWG.
- LIQUID FROM LZ-551
7 DIMENSIONS OF FLANGES FOR NOZZLES UPTO 600NB SHALL BE AS PER ASME B16.5
STANDARDS ¼LVS.MMZl½ POST WELD HEAT TREATMENT -
N12 1
50
- 150 SO RF - - MIN. FLOW
16 AFTER HYDROTEST ALL WELDS IN PRESSURE PARTS SHALL BE CHECKED BY DP X STANDARD BOLT HOLE ORIENTATION 7-12-0015
(HOLD) EXAMINATION. 7-12-0016 SHELL/BOOT SA 240 GR.304
ALLOY LINER DETAILS
17 ALL WELD LINES ON THE INNER SURFACE SHALL BE SMOOTHLY FINISHED BY A SIGHT GLASSES FOR PRESSURE VESSELS 7-12-0017 REINFORCEMENT PAD/INSERT PLATE SA 240 GR.304
N13 1 50 80S 150 SO RF 1360 - OVER FLOW GRINDER.
X INTERNAL FLANGES 7-12-0018 BOTTOM PLATE/TOP PLATE SA 240 GR.304
SEE VORTEX BREAKERS 7-12-0019 SHELL FLANGES -
N14 1 50 80S 150 SO RF - FCS INLET
DWG. INLET DEFLECTOR BAFFLE 7-12-0020 NOZZLE FLANGES SA 182 F304
SEE SUPPORT RING AND BOLTING BAR 7-12-0021 NOZZLE NECK UPTO 150 NB SA 312 TP304
V1 1 80 80S 150 SO RF 45xT VENT
DWG. SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 NOZZLE NECK ABOVE 150 NB SA 240 GR.304
PIPE DAVIT 7-12-0023 PIPE FITTINGS SA 403 GR.304 (SEAMLESS)
D1 1 50 80S 150 SO RF 1360 - DRAIN
LIFTING LUG TOP HEAD TYPE 7-12-0024 GASKET EXTERNAL V#7010 OR EQUIVALENT
FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025 GASKET INTERNAL(NOTE-13) V#7010 OR RQUIVALENT
D2 1 50 80S 150 SO RF 1360 - DRAIN
X EARTHING LUG 7-12-0026 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7 / SA 194 GR.2H
MH1 1 600 150 SO RF 1460 300xT MAHOLE + DAVIT+ B.F. X ALLOWABLE NOZZLE LOADS 7-12-0038 DEMISTER/GRID -
PAD FOR EXTERNAL ATTACHMENT SA 240 GR.304
LIFTING LUG SA 516 GR.70
HH1 1 150 150 SO RF 1460 85xT HANDHOLE + B.F.
CURB ANGLE SA 240 GR.304
JOB NO: UNIT NO: DESIGN DATA fMtkbu MkVk DRAWING NUMBER
ENGINEERS INDIA LIMITED dk;Z l[;k A842
;÷fuV l[;k PDE MkbZx uEcj REV
NEW DELHI CLIENT :
M/s BPCL, KOCHI WATER SURGE DRUM okVj ltZ Mªe A842-PDE-80-43-DS-3525 0
DykbZV 0 12.04.2017REVISED AS MARKED AND ISSUED FOR PURCHASE TAA SA PVS
bathfu;lZ bafM;k fyfeVsM PLANT : A 28.06.2016 ISSUED FOR BIDS/ENGG. TAA DG/MKP -
¼Hkkjr ljdkj dk midze½ IykaV PDPP
REVISION APPROVED
ITEM NO. PDE-V-525 vkbVe uEcj ihMhbZ&oh&525 SHEET 1 OF 2
REV DATE BY CHECKED
FORMAT NO.3-1646-0122 REV.2 (06.12.2011) A3-420 X 297
LG
LG
MAHOLE + DAVIT+
B.F.
HANDHOLE + B.F.
RT NOMINAL THICKNESS.
MARK QTY
NOM. DIA SCH./THK. FLANGES PROJECTION
PAD WxT SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC VIII DIV. 1 LATEST EDITION
ukfeuy 'kMwy o CLASS TYPE FACING NOTE-4 1 ALL DIMENSIONS ARE IN MM, UNLESS OTHERWISE STATED. X GENERAL SPEC. FOR PRESSURE VESSELS 6-12-0001 WORKING PRESSURE (mm Hg) 200
ekdZ DokfUVVh Mka;k fFkduSl Dykl VkbZi Qsflx izkstsD'ku iSaM lfoZl 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRELINE. X SUPP. SPEC. FOR AUSTENTICS SS VESSELS 6-12-0006 DESIGN PRESSURE (kg/cm2a) INT 3.5 EXT F.V.
3 NORTH DIRECTION, WHEREVER SHOWN, IS WITH RESPECT TO PLAN SUPP. SPEC. FOR BQCS PLATE 6-12-0011 WORKING TEMPERATURE (0C) 31
N1 1 150 40S 150 SO RF 2020 70x12 LIQUID FROM E-412 VIEW.
X STD. SPEC. FOR STRUCTRAL QUALITY PLATES 6-12-0014 DESIGN TEMPERATURE 0
( C) 65
FOR NOZZLES ON HEAD, PROJECTIONS ARE REFERRED FROM HEAD T.L TYPE OF HEAD 2:1 ELLIPTICAL
N3 1 100 80S 150 SO RF 1810 50x12 LIQUID TO P-411A/B 4(B)
TO FLANGE CONTACT FACE. JOINT EFFICIENCY SHELL 0.85 HEAD 1
5 THE INDICATED THICKNESS ARE THE MINIMUM ACCEPTABLE AFTER RADIOGRAPHY SHELL SPOT HEAD FULL
N4 1 100 80S 150 SO RF 1810 50x12 LIQUID TO P-412A/B CONSTRUCTION. POST WELD HEAT TREATMENT AS PER CODE/SPEC.
100 6 FLANGE GASKET FACE SHALL HAVE 125 AARM FINISH. HEAT TREATMENT HEAD AS PER SPEC.
N5 1 80S 150 SO RF 2020 50x12 MIN. FLOW (FROM P-411A/B) DIMENSIONS OF FLANGES FOR NOZZLES UPTO 600NB SHALL BE AS PER
(HOLD) OPERATING MEDIUM PROCESS FLUID
100
7
ASME B16.5 AND FOR NOZZLE ABOVE 600NB SHALL BE AS PER ASME
B16.47 SERIES `B' UNLESS SPECIFIED OTHERWISE.
STANDARDS ¼LVS.MMZl½ SP. GRAVITY (LIQUID/GAS) 0.857/0.977
N6 1 80S 150 SO RF 2020 50x12 MIN. FLOW (FROM P-412A/B)
(HOLD) 8 ID OF WELD NECK FLANGES SHALL MATCH WITH CORRESPONDING ID OF X VESSEL TOLERANCES 7-12-0001 WIND SPECIFICATION IS 875
LEVEL TRANSMITTER (DP ALLOY LINER DETAILS 7-12-0016 NOZZLE FLANGES / LWN SA 182 F304
L2b 1 80 80S 150 SO RF 1450 40x12
DIASEAL) SIGHT GLASSES FOR PRESSURE VESSELS 7-12-0017 NOZZLE NECK UPTO 100 NB SA 312 TP.304
LEVEL GAUGE TRANSPARENT INLET DEFLECTOR BAFFLE 7-12-0020 GASKET EXTERNAL V#7010 OR EQ.
G1b 1 50 80S 150 SO RF 1300 -
(SS) SUPPORT RING AND BOLTING BAR 7-12-0021 GASKET INTERNAL V#7010 OR EQ.
SUPPORT RING SIZES FOR PACKED TOWERS 7-12-0022 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7/ SA 194 GR.2H
G2a,b 2 50 80S 150 SO RF 1300 - MAGNETIC LEVEL GAUGE
PIPE DAVIT 7-12-0023 INTERNAL STUDS/BOLTS/NUTS SS 304
LIFTING LUG TOP HEAD TYPE 7-12-0024 SUPPORT(SADDLE) IS 2062 GR.250 QUALITY B
P1 1 50 80S 150 SO RF 2020 - PT
FIRE PROOFING AND INSULATION SUPPORTS 7-12-0025 SUPPORT BASE IS 2062 GR.250 QUALITY B
P2 1 50 80S 150 SO RF 2020 - PG X EARTHING LUG 7-12-0026 INTERNAL PARTS (WELDED) SA 240 Gr.304/SA 312 TP.304
X NAME PLATE 7-12-0027 INTERNAL PARTS (BOLTED) SA 240 Gr.304/SA 312 TP.304
NAME PLATE FOR SMALL EQUIPMENT 7-12-0030 PAD FOR EXTERNAL ATTACHMENT SA 240 Gr.304
LADDERS/PLATFORM CLEATS -
PIPE SUPPORT CLEATS -
LICENSOR'S SPECIFICATION FOUNDATION LOADING DATA (OPERATING CONDITION) DEMISTER DATA SHEET -
STATUTORY REGULATIONS ¼LVSpqvjh jsxqys'kUl½
ykbZlsUlj LisflfQds'lUl QkaÅMs'ku yksfMxa MkVk ¼vksijsfVax dufM'ku) X PROCESS DATASHEET PDPP-DS-V411 INDIAN BOILER REGULATIONS (IBR)
PETROLEUM & EXPLOSIVES SAFETY ORGANISATION, (PESO)
TYPE MAX MOMENT AT BASE (M) (kgm)
MAX. SHEAR FORCE AT BASE (H)
(kg) HOLD UPS ¼gksYM vIl½
SEISMIC X NOZZLE ORIENTATIONS X SIZE OF NOZZLES-N5, N6
APPROXIMATE WEIGHT (kgs) (PER ITEM) ¼ ,ijkSfDlesaV otu½
- -
(DBE)
LICENSOR'S STANDARD X FIXED/SLIDING SUPPORT X PIPE SUPPORT CLEATS ERECTION 16000 OPERATING 73000
ykbZlsUlj LVS.MlZ SEISMIC X LADDER/PLATFORM CLEATS
- -
(MCE)
HYDROTEST ( SHOP ) 78000 HYDROTEST ( FIELD ) 80000
WIND - -
0 NUMBER OF ITEM : 01 (ONE)