Professional Documents
Culture Documents
net/publication/275540046
CITATIONS READS
9 1,241
1 author:
Amund Bruland
Norwegian University of Science and Technology
75 PUBLICATIONS 1,585 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Amund Bruland on 28 April 2015.
Amund Bruland
Vol. 6 of 10
NTNU Trondheim
Norwegian University of
Science and Technology
Doctoral thesis
for the degree of doktor ingeniør
Faculty of Engineering Science
and Technology
Department of Civil and
Transport Engineering
PREFACE 1
0 GENERAL 3
1 MACHINE PERFORMANCE 8
1.0 Introduction 8
1.3 Torque 14
2 CUTTER CONSUMPTION 23
2.0 Introduction 23
3 PENETRATION TESTS 40
4 CHIP ANALYSIS 51
5.0 Introduction 64
APPENDICES 79
A. Previous Editions 79
B. Research Partners 80
C. List of Parameters 81
The report is one of six reports about hard rock tunnel boring:
Combined with the other reports in the Project Report Series from the Department of
Building and Construction Engineering at NTNU, the reports present an updated and
systematised material on rock excavation and tunnelling to be used for:
• Economic dimensioning
• Choice of alternative
• Time planning
• Cost estimates, tender, budgeting and cost control
• Choice of excavation method and equipment.
A list of available Project Reports may be requested from the Department of Building
and Construction Engineering at NTNU.
The advance rate, cutter wear and excavation cost models also exist as a WINDOWS
programme.
The report is prepared by Amund Bruland and is part of his dr.ing thesis about
hard rock tunnel boring.
1
PREFACE
The reports listed above describes a comprehensive model developed at NTNU The
model covers the complete tunnel boring process from the early planning stage
through preinvestigations, time and cost estimates, tunnel excavation and finally ac-
quisition and treatment of experience data. The models and data presented in the
reports are meant to be a practical tool for owners, consultants and contractors,
more than a theoretical analysis of the tunnel boring process.
The project has been granted financial support by our external research partners, see
list in Appendix.
Odd Johannessen
Professor
2
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
1E-98
The report provides methods and data to be used during follow-up and analysis of
TBM performance and for back-mapping of engineering geological properties of
bored tunnels.
Project Report 1E-98 is partly based on the project reports 1-76, 1-79, 1-83, 1-88 and
1-94, all published by the Department of Building and Construction Engineering at
NTNU. The report presents updated and revised information from the previous re-
ports as well as experience from recent tunnelling projects.
Other Reports
The Project Report 1A-98 HARD ROCK TUNNEL BORING Design and Con-
struction describes general design parameters such as tunnel profile, tunnel inclina-
tion and curve radius. Some features of various tunnel types like water, sewage, road
3
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
and rail tunnels are treated. Transport, ventilation and other necessary service systems
are presented.
The Project Report 1B-98 HARD ROCK TUNNEL BORING Advance Rate and
Cutter Wear provides methods and necessary data for estimation of time consump-
tion and cutter wear for tunnel boring. Geological parameters and machine factors of
significance for the penetration rate and the cutter wear are presented briefly.
The Project Report 1C-98 HARD ROCK TUNNEL BORING Costs presents
models and data for estimation of tunnel excavation costs and total construction costs.
The Project Report 1D-98 HARD ROCK TUNNEL BORING Geology and Site
Investigations treats the rock mass parameters of the model in more detail. Site
investigations and building of an engineering geological model adapted to the estima-
tion models for penetration rate and excavation costs are treated closely.
Project Report 1F-98 HARD ROCK TUNNEL BORING The Boring Process
covers rock breaking and chipping, machine factors affecting performance, boring in
fractured rock mass, and various topics of cutter wear.
The estimation models are aimed at being used through several stages in a project:
The estimation models for Hard Rock Tunnel Boring should be used with care. Com-
bined with other estimation models in the Project Report Series from the Department
of Building and Construction Engineering, the Hard Rock Tunnel Boring reports pro-
vide a reliable and practical tool to be used for:
4
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
Background
The estimation models are based on job site studies and statistics from tunnelling in
Norway and abroad, including more than 35 job sites and more than 250 km of tunnel.
The data have been systematised and normalised. The results are regarded as being
representative for well organised tunnelling.
A more detailed treatment of the background and the basis for the Hard Rock Tunnel
Boring estimation models is found in HARD ROCK TUNNEL BORING Back-
ground and Discussion.
5
0. GENERAL 0.2 Field Performance Studies
The performance data of the machine are combined with the cutter wear data and data
from the engineering geological back-mapping to be able to evaluate the performance
of the tunnel excavation with regard to the geological conditions along the tunnel.
Field performance studies at a TBM tunnel aim to provide information and knowl-
edge to be used for several purposes:
The field performance studies should build a database that describes the geology and
the tunnelling performance by numbers. Each record of the database should represent
tunnel sections with approximately constant basic parameters, e.g. rock type, tunnel
direction, cutter thrust, cutterhead RPM. An example of sectioning of the database is
shown in Figure 0.1.
Z o n e 1 Z o n e 2 Z o n e 3
G e o lo g y
R a n g e 1 R a n g e 2 R a n g e 3 R a n g e 4 T B M
p a ra m e te rs
R a n g e 1 R a n g e 2 R a n g e 3 R a n g e 4 R a n g e 5 P e n e tr a tio n
ra te
R a n g e 1 R a n g e 2 C u tte r
c o n s u m p tio n
R e c o rd
1 2 3 4 5 6
D a ta b a s e
In this process, the geology and the machine performance are related to the chainage
along the tunnel. Hence, an accurate and close marking of the chainage is recom-
mended, e.g. with minor indicators at each metre and major indicators at each 10 me-
tres.
Furthermore, the performance data and the geological back-mapping are normalised
and included in the general database of hard rock tunnel boring to form the basis for
improving and extending the prediction models for time and cost estimates of TBM
tunnelling.
The data collection and the development of the prediction models is a more or less
continuous process since the models are purely empirical and new input in the form of
e.g. machine design, cutter material and geological conditions is constantly available.
The field performance studies and data collection described in this report are consis-
tent with the basic follow-up program performed by the Department of Building and
Construction Engineering at NTNU at various tunnel boring sites. At a given tunnel
project, it will often be of interest, or even necessary, to perform additional or more
detailed observations and analyses of selected processes, equipment, parameters or
similar.
When planning and performing the follow-up of a specific tunnelling project, one
should keep in mind that detailed studies will get an increased value if combined with
general follow-up as described in Sections 1.0, 2.0 and 5.0 of this report.
7
1. MACHINE PERFORMANCE 1.0 Introduction
1.0 INTRODUCTION
The machine performance is continuously recorded through the shift logs and/or log
files from the onboard computer.
Specific tests such as penetration tests give valuable and more detailed information
about the machine performance.
The logs should as a minimum provide data to be able to calculate the instantaneous
and average of:
8
1. MACHINE PERFORMANCE 1.1 Net Penetration Rate
The average net penetration rate is calculated based on systematic and continuous
recording of the chainage and the machine hours, recorded e.g. at the end of each
shift. For the accuracy of the records it is important that the machine hour meter
measures boring hours. Hence, it must only be activated by a combination of cutter-
head rotation and cutterhead thrust.
It is convenient to base the follow-up work on the average net penetration rate over
one shift, see Figure 1.1. When an onboard computer is used for data acquisition and
logging, shorter intervals like the stroke length may be used when the average net
penetration rate is calculated. The penetration rate calculated from the logging system
(shift log or computer) should be verified by penetration rate measurements, e.g. over
one stroke length.
m/h
0
2450 2460 2470 2480 2490 2500
Chainage, m
Figure 1.1 Net penetration rate at the Meraaker Project, calculated from shift logs.
dtbm = 3.5 m. Courtesy of NCC Eeg-Henriksen Anlegg AS and Veidekke
ASA.
The detailed net penetration records are compared to the engineering geological back-
mapping at a detailed level. Figure 1.1 may be explained as follows:
9
1. MACHINE PERFORMANCE 1.1 Net Penetration Rate
• The relative high net penetration rate from chainage 2450 to 2460 and from chain-
age 2490 to 2500 may have various reasons, of which the most likely are:
The average penetration rate must be calculated using the total machine hours used to
bore the actual tunnel length, and not as an arithmetical average of the penetration
rates of the subsections (e.g. shifts) constituting the actual tunnel length.
Im =
∑l j
=
∑l j
(m/h) [1.1]
∑T bj ∑ (l j / I nj )
It is convenient to average the net penetration rate over time periods of equal length
(e.g. weeks, see Figure 1.2) or over tunnel sections, each section with more or less
constant geological conditions.
10
1. MACHINE PERFORMANCE 1.1 Net Penetration Rate
9
m/h
8
Cumulated average
7
0
38 42 46 50 2 6 10 14 18 22 26 30 34
Week no. of 1991/1992
Figure 1.2 Average net penetration rate at the Meraaker Project, calculated from
shift logs. dtbm = 3.5 m, Lt = 10 km. Courtesy of NCC Eeg-Henriksen
Anlegg AS and Veidekke ASA.
11
1. MACHINE PERFORMANCE 1.2 Gross Thrust
The prediction model in the Project Report 1B-98 HARD ROCK TUNNEL
BORING Advance Rate and Cutter Wear uses the gross average thrust per cutter
as a measure for the applied cutter force. Gross average thrust means:
• The total gross thrust is the gross thrust force from the thrust or propel cylinders,
including friction or drag of the cutterhead and the cutterhead support system and
other losses of thrust.
• The total gross thrust is divided by the number of cutters on the cutterhead to get
the gross average thrust per cutter.
The above system is meant to simplify and standardise the data acquisition and treat-
ment. Individual and net cutter forces are very difficult to measure and will introduce
additional uncertainty in the performance data analyses and in the prediction model.
The applied gross thrust is calculated from the applied hydraulic pressure in the pro-
pel cylinders, as shown in Section 3.2, Equation [3.5].
The applied thrust will oscillate somewhat. Since the prediction model for net pene-
tration rate is based on the applied gross average cutter thrust, it is important to use
the average reading of the pressure gauge and not the maximum deflection of the
pointer.
When the applied thrust is averaged over a given tunnel length, the instantaneous
thrust is weighted by time.
M Bm =
∑ (M ⋅ T
Bj bj )
(kN/cutter) [1.2]
∑T bj
12
1. MACHINE PERFORMANCE 1.2 Gross Thrust
lj
Tbj = (h) [1.3]
I nj
The gross thrust should be averaged over the same time periods and tunnel sections as
the net penetration rate.
13
1. MACHINE PERFORMANCE 1.3 Torque
1.3 TORQUE
The applied torque TB is calculated from the applied amperage of the cutterhead drive
motors. Equation [1.4] is applicable for 3-phase motors.
U B ⋅ I B ⋅ 3 ⋅ (cos φ ⋅ η ) ⋅ 60 ⋅ nm
TB = (kNm) [1.4]
2 ⋅ π ⋅ 1000 ⋅ RPM
The applied amperage will oscillate somewhat. Since the prediction model for neces-
sary torque is based on the average amperage, it is important to use the average read-
ing of the ampere meter and not the maximum deflection of the pointer.
When the applied amperage is averaged over a given tunnel length, the instantaneous
amperage is weighted by time.
I Bm =
∑ (I ⋅ T
Bj bj )
(A) [1.5]
∑T bj
The amperage should be averaged over the same time periods and tunnel sections as
the net penetration rate.
14
1. MACHINE PERFORMANCE 1.4 Machine Utilisation
The machine utilisation is defined as the boring time in percent of the total available
shift or working hours. The machine utilisation is calculated for given time periods
(e.g. week, month) or for given tunnel sections (e.g. geological zones, total tunnel
length).
The calculation of the machine utilisation is entirely based on data from the shift logs
recorded by the TBM operator. In some cases, it is difficult to state the appropriate
cause of stop in the boring. In the future, use of the onboard computer for semiauto-
matic data recording and treatment will improve the reliability and objectivity of the
shift log data. A digital shift log will also improve the possibilities and the results of
back-analyses of the machine performance.
An example of a well-suited shift log for hard rock tunnel boring is shown in Appen-
dix D. The grouping of the activities may vary, but the following is recommended to
be included in the main activities:
15
1. MACHINE PERFORMANCE 1.4 Machine Utilisation
The main activities may be subdivided into even more specific activities such as for
rock support in a continuously lined tunnel in weak and water-bearing rock mass.
♦ Rock support
• Probe drilling
• Pregrouting
• Segment erection
• Back-filling of the segmental lining
• Water inflow
• Other rock support.
One must however remember that the shift log is recorded by the TBM operator who
normally gives priority to the tunnel excavation operations. Hence, to ensure the qual-
ity of the recorded data, the shift log must not be too complex asking detailed infor-
mation of little relevance.
It is not convenient to record boring and regripping separately in the shift log. When
calculating the machine utilisation, one has to combine the recorded machine hours
(net boring time) and the recorded time consumption of boring, including regripping
as shown in [1.6] and [1.7]. The equations are based on a time period of one week.
Tb = t 2 − t1 (h /week ) [1.6]
16
1. MACHINE PERFORMANCE 1.4 Machine Utilisation
To be able to compare the achieved machine utilisation with the normalised model in
Project Report 1B-98 HARD ROCK TUNNEL BORING Advance Rate and
Cutter Wear, the time consumption for rock support work is excluded from the total
working hours to make up the available excavation time. The reason for this is that
the type and amount of rock support work is mainly dependent on the site geology
and much less by the tunnel boring system.
Tb I u ⋅ 100
ua = = (%) [1.9]
Tex I n ⋅ Tex
The utilisation must also be corrected for weekly working hours (shift hours) other
than 100 h/week.
Tsh
un = ua ⋅ (%) [1.10]
Teh
1
Figure 4.2 in Project Report 1B-98 HARD ROCK TUNNEL BORING Advance Rate and Cutter
Wear.
17
1. MACHINE PERFORMANCE 1.4 Machine Utilisation
An example of a plot of the weekly machine utilisation and cumulated machine utili-
sation is shown in Figure 1.3.
70
%
60
50 Cumulated average
40
30
20
10
0
38 42 46 50 2 6 10 14 18 22 26 30 34
Week no. of 1991/1992
Figure 1.3 Machine utilisation at the Meraaker Project. dtbm = 3.5 m, Lt = 10 km.
Courtesy of NCC Eeg-Henriksen Anlegg AS and Veidekke ASA.
The cumulated average machine utilisation for a given tunnel length or period of time
is calculated directly from the cumulated time consumption for the given period as in
[1.11]. If the weekly working hours varies from week to week, the cumulated utilisa-
tion may be calculated by [1.12], where the utilisation is weighted by working hours
per week. Non-productive stops like vacations are not included in the cumulated av-
erage.
um = ua =
∑T b
⋅ 100 (%) [1.11]
∑T ex
um =
∑ (u a ⋅ Tsh ) (%) [1.12]
∑ Tsh
18
1. MACHINE PERFORMANCE 1.4 Machine Utilisation
The total use of time distributed on the various tunnelling operations may be illus-
trated by pie charts as the example in Figure 1.4.
Other 4.6
Water etc. 10.0
Backup 4.1
TBM 5.4
Cutters 15.3
Regripping 10.7
Figure 1.4 Tunnelling time consumption in per cent distributed on various opera-
tions at the Meraaker Project. dtbm = 3.5 m, Lt = 10 km, Im = 6.4 m/h.
Courtesy of NCC Eeg-Henriksen Anlegg AS and Veidekke ASA.
19
1. MACHINE PERFORMANCE 1.5 Weekly Advance Rate
450
m/week
400
300
250
200
150
100
50
0
38 42 46 50 2 6 10 14 18 22 26 30 34
Week no. of 1991/1992
Figure 1.5 Weekly advance rate at the Meraaker Project. dtbm = 3.5 m, Lt = 10 km.
Courtesy of NCC Eeg-Henriksen Anlegg AS and Veidekke ASA.
The cumulated average weekly advance for a given tunnel length or period of time is
calculated directly from the bored tunnel length and the number of productive weeks
in the period. The cumulated average may also be calculated by the cumulated aver-
ages as in [1.14].
l 2 − l1
Iu = (%) [1.13]
nu
20
1. MACHINE PERFORMANCE 1.5 Weekly Advance Rate
To be able to compare the achieved weekly advance rate with the normalised model
in Project Report 1B-98 HARD ROCK TUNNEL BORING Advance Rate and
Cutter Wear, the advance rate must be related to 100 working hours available for
tunnel excavation per week, and also be corrected for weekly working hours (shift
hours) other than 100 h/week.
Tsh
I un = u m ⋅ 100 ⋅ I m ⋅ (m/week) [1.15]
Teh
21
1. MACHINE PERFORMANCE 1.6 Parameter Summary
It is convenient to aggregate the detailed information from the shift logs into a more
readable form. A visual presentation as shown in Figure 1.6 gives a quick and very
informative overview of the operation of the machine, as well as providing a basis for
analyses of the machine performance with regard to the engineering geological back-
mapping.
The aggregated performance data are also a good check for large errors in the back-
mapping. It is however not recommended to bring the summary into the tunnel while
performing the back-mapping. This may bias the classification of the rock mass de-
gree of fracturing or other parameters of the mapping.
5
N e t p e n e tr a tio n r a te , m /h
2 5 0
T h ru s t, k N /c u tte r
2 0 0
1 5 0
2 5 0
T o rq u e , A
2 0 0
1 5 0
2 4 5 0 2 4 6 0 2 4 7 0 2 4 8 0 2 4 9 0 2 5 0 0
C h a in a g e , m
22
2. CUTTER CONSUMPTION 2.0 Introduction
2.0 INTRODUCTION
The cutter consumption is recorded through the cutter change and inspection log in
the tunnel and the cutter repair log at the cutter shop. Specific tests such as the wear
progress of specific cutter rings and positions, steel quality measurements, etc., give
valuable and more detailed information about the cutter wear process.
• Instantaneous and average cutter wear for the cutterhead (h/c, m/c and sm3/c)
• Cutter consumption for each cutter position (e.g. no. of rings)
• Reason for change (e.g. ring wear, oil leakage, blocked bearings)
• Type and extent of the wear of each ring
• Consumption of spare parts.
To be able to trace the individual cutter and record the necessary data for the above-
mentioned calculations, each cutter must have a unique identity, e.g. a number. The
cutter change log must be related to the tunnel chainage and the machine hours.
If swapping of partly used cutters between positions (e.g. from outer to inner gauge)
is done, this must be noted in the cutter change log and corrected for in the calcula-
tions of the cutter consumption.
To be able to calculate the instantaneous consumption towards the end of the tunnel,
one should record the wear state of all cutters when the boring is finished. The state is
recorded as wear height or as a rough estimate of remaining ring life in per cent. If the
boring of the tunnel starts with partly used cutter rings, the wear state of the cutters
should be recorded at the start of the boring in the same way.
23
2. CUTTER CONSUMPTION 2.1 Consumption per Position
• Evaluate the cutterhead design, e.g. with regard to placement of the individual
cutter.
• Calculate the cutterhead factor fD and the correction factor for TBM diameter with
regard to cutter consumption, see Figure 3.2 of Project Report 1B-98 HARD
ROCK TUNNEL BORING Advance Rate and Cutter Wear.
35
No. of rings used
Other
30 Chipped ring
Oil leakage
Blocked
25
Wear
20
15
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Cutter position no.
Figure 2.1 No. of rings used per cutter position at the Meraaker Project. dtbm = 3.5
m, Lt = 10 km, Ntbm = 25. Courtesy of NCC Eeg-Henriksen Anlegg AS
and Veidekke ASA.
Figure 2.1 shows two important features of the given cutterhead design:
• The positions 12 through 17 are exposed to the highest loads, indicated by the
number of cutters replaced for reasons other than wear. The load of the cutters
may be reduced by adding one cutter in this area (if possible).
24
2. CUTTER CONSUMPTION 2.1 Consumption per Position
• The centre cutter positions no. 2 and 4 should be examined to find a better design,
indicated by the number of cutters replaced for reasons other than wear. In the ac-
tual tunnel, the positions could be relieved by replacing the cutter in position 5
more often.
The cutterhead factor is calculated by normalising the cutter ring consumption per
position to a cutterhead with radius 1 and an average cutter consumption of 1 ring per
position as shown below.
Ni
rri = [2.1]
N tbm
H ri =
∑ H ni [2.2]
N tbm ⋅ H ni
fD =
∑H ri
[2.3]
N tbm
fD = cutterhead factor
fD
kD = [2.4]
f D0
kD = correction factor for TBM diameter with regard to cutter ring life
fD0 = 1.133, i.e. the cutterhead factor of the reference cutterhead
(dtbm = 3.5 m, dc = 394 mm, Ntbm = 27)
25
2. CUTTER CONSUMPTION 2.1 Consumption per Position
Table 2.1 Calculation of cutterhead factor and correction factor for TBM diameter
with regard to cutter consumption. Data from Figure 2.1.
26
2. CUTTER CONSUMPTION 2.1 Consumption per Position
Table 2.1 shows the calculation of the cutterhead factor fD and the correction factor kD
for the data in Figure 2.1.
Figure 2.2 shows observed and normalised cutter replacement curves (relative cutter
life) for various TBM diameters. The integral of the curves gives the cutterhead fac-
tor.
6 .0
R e la tiv e c u tte r life
5 .0
4 .0
3 .0
2 .0
d tb m = 6 .5 m
1 .0 4 .5 m
3 .5 m
0 .2 0 .4 0 .6 0 .8 1 .0
Figure 2.2 Normalised cutter replacement curves for varying TBM diameter.
27
2. CUTTER CONSUMPTION 2.2 Instantaneous Consumption
The instantaneous cutter consumption along the tunnel is calculated between cutter
changes as illustrated in Figure 2.3. The figure shows the calculation model for cutter
wear in cutter/m. The same model is used to calculate cutter/h, simply by substituting
the chainage (in metres) for each cutter change with the corresponding machine
hours.
C h a in a g e
m 1 2 0 2 0 0 2 9 0 3 4 0 4 1 0
C h a n g e
n o .
1 2 3 4 5
N c
w 1 ,3 = 3 )
w 2 ,3 = w 1 ,3 w 3 ,3 = w 1 ,3 w 4 ,3 = N /A
3
i
C u tte r p o s itio n , N
w 1 ,2 = 2 )
w 2 ,2 = w 1 ,2 w 3 ,2 = N /A w 4 ,2 = N /A
2
w 1 ,1 = 1 ) w 2 ,1 = 4 ) w 3 ,1 = 5 ) w 4 ,1 = w 3 ,1
3
T o ta l 3 3 w = å w 3
m 3 3 ,i
w e a r w m 1 = å w 1 ,i= 0 .0 2 2 9 w m 2 = å w 2 ,i= 0 .0 2 1 5 i= 1 w m 4 = å w 4 ,i= N /A
i= 1 i= 1 i= 1
[c /m ] = N /A
T o ta l 1 1
life H m 1 =
w
= 4 3 .6 7 H m 2 =
w
= 4 5 .5 1 H m 3 = N /A H m 4 = N /A
m 1 m 2
[m /c ]
1 0 0 2 0 0 3 0 0 4 0 0
C h a in a g e , m
S ta r t b o r in g
1 ) 1 3 ) 1 5 ) 1
w 1 ,1 = = 0 .0 1 2 5 c /m w 1 ,3 = = 0 .0 0 4 5 c /m w 3 ,1 = = 0 .0 0 8 3 c /m
2 0 0 -1 2 0 3 4 0 -1 2 0 4 1 0 -2 9 0
2 ) 1 4 ) 1
w 1 ,2 = = 0 .0 0 5 9 c /m w 2 ,1 = = 0 .0 1 1 1 c /m
2 9 0 -1 2 0 2 9 0 -2 0 0
= c u tte r p o s itio n r e p la c e d
28
2. CUTTER CONSUMPTION 2.2 Instantaneous Consumption
It must be noted that the terms cutter wear, cutter consumption, cutter/m and cutter/h
refer to the consumption of cutter rings only, and not of complete cutter assemblies.
The minimum requirements to the cutter change log are that it shows the following
for each cutter change:
Preferably, the cutter change log should include information on cutter identification,
reason for change, etc. See Appendix D.
Cutter replacement Defined as the replacement of a worn cutter with a new or re-
built cutter (new ring as a minimum) at a single position during
a cutter change.
The basic concept used to calculate the cutter consumption based on the cutter change
logs is shown in Figure 2.3. The detailed model will not be treated here, but is avail-
able as a PC program from the Department of Building and Construction Engineering
at NTNU.
Table 2.2 shows the minimum necessary input data of the PC program as recorded in
the data file. "1" means that the position has been replaced at the actual cutter change
and "0" means no cutter replacement.
The data in Table 2.2 are from a tunnel bored in extremely hard and strong rock with
medium abrasivity. This is reflected in the frequent cutter changes and very low cutter
life shown in Tables 2.2 and 2.3 and in Figure 2.4.
29
2. CUTTER CONSUMPTION 2.2 Instantaneous Consumption
Table 2.2 Data file for calculation of cutter consumption along the tunnel. TBM
with 25 cutters.
Table 2.3 and Figure 2.4 show results of the calculation of the instantaneous cutter
consumption based on the data in Table 2.2.
30
From To Interval
Hf Hh Hm wm Cutters % In Ic
Chainage Chainage 3 Length Ic /In
(m /c) (h/c) (m/c) (c/m) Changed Changed (m/h) (m/h)
Table 2.3
(m) (m) (m)
122.3 164.4 26.7 1.38 2.77 0.361 42.1 1 4 1.92 2.01 1.05
164.4 179.5 27.9 1.44 2.90 0.345 15.1 17 68 2.52 2.02 0.80
Table 2.2.
179.5 181.7 6.2 0.22 .65 1.544 2.2 2 8 3.67 2.91 0.79
181.7 195.6 14.8 .0.84 1.53 0.652 13.9 8 32 1.72 1.83 1.06
195.6 219.0 20.5 1.30 2.13 0.469 23.4 6 24 1.57 1.64 1.05
2. CUTTER CONSUMPTION
219.0 228.0 13.9 0.75 1.45 0.692 9.0 2 8 1.87 1.93 1.03
228.0 232.6 12.3 0.60 1.28 0.781 4.6 10 40 2.56 2.12 0.83
232.6 244.4 17.4 1.11 1.81 0.552 11.8 3 12 1.55 1.63 1.05
244.4 265.0 21.7 1.32 2.26 0.443 20.6 8 32 1.73 1.70 0.98
265.0 288.0 21.9 1.32 2.28 0.439 23.0 4 16 1.77 1.72 0.97
288.0 297.8 14.3 0.96 1.48 0.674 9.8 25 100 1.44 1.54 1.07
297.8 305.1 9.4 0.75 .98 1.022 7.3 5 20 1.12 1.31 1.17
305.1 311.1 13.7 0.81 1.43 0.700 6.0 2 8 2.31 1.76 0.76
311.1 316.5 14.9 0.84 1.55 0.646 5.4 3 12 1.42 1.85 1.30
316.5 325.0 14.9 0.76 1.55 0.646 8.5 7 28 2.30 2.04 0.89
31
2. CUTTER CONSUMPTION 2.2 Instantaneous Consumption
In Table 2.3, Hf, Hh, Hm and wm are calculated according to Figure 2.2. In is the
achieved penetration rate calculated from the chainage and the machine hours.
l c ,i +1 − l c ,i
I n ,i = (m/h) [2.5]
hc ,i +1 − hc ,i
Ic is the theoretical penetration rate calculated from the cutter life in metres and in
hours between the actual cutter changes.
H m ,i
I c ,i = (m/h) [2.6]
H h ,i
Hm,i = calculated cutter life between cutter changes no. i and i+1 (m/cutter)
Hh,i = calculated cutter life between cutter changes no. i and i+1 (h/cutter)
The ratio Ic /In is used to evaluate the quality of the calculated cutter life. When Ic /In is
close to 1.0, the cutter wear situation has been normal. When Ic /In is substantially less
or larger than 1.0, it is an indication of:
• Abnormal wear of the cutters, e.g. blocked cutter(s). The low cutter life and Ic /In
ratio between chainages 179.5 and 181.7 is caused by two blocked cutters being
replaced at chainage 181.7, see Table 2.2.
• Irregular replacement of cutters, e.g. replacement of one or more positions before
the cutter ring is worn to its limit. The low Ic /In ratio between chainages 228.0 and
232.6 is caused by one cutter position being replaced at chainage 232.6 as part of a
larger series of neighbouring positions being replaced, see Table 2.2.
The ratio Ic /In should be used when deciding suitable rock sampling sites to compare
the calculated cutter life to geological parameters.
32
2. CUTTER CONSUMPTION 2.2 Instantaneous Consumption
1.6
h/c
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
100 150 200 250 300 350
Chainage, m
Figure 2.4 Instantaneous cutter consumption along the tunnel, based on the data in
Table 2.2.
Figure 2.4 shows that the representative cutter life for the tunnel section until chain-
age 300 is at approximately 1.2 – 1.3 h/cutter.
33
2. CUTTER CONSUMPTION 2.3 Ring Wear
Data on the ring wear process is used as a basis to evaluate and improve:
Wear data are collected at the cutterhead during cutter inspections or cutter changes.
The extra few minutes used to collect the wear data from selected cutter positions will
give valuable information.
Wear Height
The wear rate of the individual cutter ring is measured as loss of ring height, see Fig-
ure 2.5. The ring height should be measured at the cutterhead a few times during the
ring life for selected cutter positions, and for each replaced ring at the cutter repair
shop.
h o h o
h i h i
h r h r
0 0
34
2. CUTTER CONSUMPTION 2.3 Ring Wear
hwi = h0 − hi
(mm) [2.7]
hwr = h0 − hr
Figure 2.6 shows a typical wear progress of a face cutter ring of the constant cross
section type in very hard rock. The wear was measured at each stop for cutter inspec-
tion. The wear progress is typical for hard and strong rock, with a high wear rate for
new cutter rings (from machine hours 2242.8 to machine hours 2244.6). At machine
hours 2244.6 and 2264.1, one neighbour cutter position was replaced, resulting in a
lower wear rate until the next cutter change. Of cutter ring properties, the wear rate is
mainly dependent on the ring steel quality (e.g. measured as Rockwell C hardness)
and the cutter edge width.
35
mm 2283.9
30
2277.1
25
2264.1
20
15
2252.2
10
2244.6
5
2242.8
0
2240 2250 2260 2270 2280 2290
Machine hours, h
Figure 2.6 Wear progress of a cutter ring in a face position. dc = 483 mm.
In general, the cutter wear rate increases towards the gauge. Thus, the gauge positions
are equipped with wider rings than the face positions. The ring edge width is impor-
tant to record when the ring wear rate is analysed.
35
2. CUTTER CONSUMPTION 2.3 Ring Wear
Figure 2.7 shows average wear height at cutter replacement, measured at the cutter
repair shop. The decreasing wear height towards the gauge is important to observe.
The main reason for less allowable wear in these positions is the need to maintain the
tunnel diameter for geometrical reasons. Furthermore, too large wear height in the
gauge will create poor conditions for the new gauge cutter rings when the boring is
resumed after the cutter change.
Position 20 in Figure 2.7 has very large wear height due to swapping of used cutters
from the outer gauge to this position. Hence, the cutters in this position have deliber-
ately been replaced very late.
45
mm
40
35
30
25
20
15
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Cutter Position
Figure 2.7 Average cutter ring wear height for the same TBM and tunnel as in Ta-
ble 2.2. Only cutters replaced due to wear are included.
1
Manufactured by PROCEQ SA, Switzerland.
36
2. CUTTER CONSUMPTION 2.3 Ring Wear
The ring steel hardness should be measured over a cross section of the ring as shown
in Figure 2.8. Results of such measurements are shown in Figure 2.9. To do so, the
new ring has to be cut, which means that the hardness measurements will be quite
expensive and should be limited to a few rings. An alternative method is to measure
the hardness at the surface of the ring as shown in Figure 2.8, supplied with measure-
ments over the cross section of the ring for selected ring types.
Selected rings are measured as new rings at the cutter shop before they are mounted
on the hub and as used rings when the worn ring has been cut and removed from the
hub. When the hardness is measured on selected rings on the cutterhead, it is impor-
tant that the measurements at consecutive cutter inspections or changes are taken at
the same positions along the ring. This may be ensured by defining a known point at
the hub as starting point and take the measurements at given intervals along the ring.
M e a s u r e m e n ts o v e r th e c r o s s s e c tio n
6
M e a s u re m e n ts
o n th e r in g s u r fa c e
37
2. CUTTER CONSUMPTION 2.3 Ring Wear
a 5 8 a 5 8
b 5 7 b 5 7
c 5 6 c 5 6
d 5 5 d 5 5
e 5 7 -3 7 e 5 4
f 3 5 f 5 3
5 0
5 0 4 9
4 9 4 8
5 2
4 8 5 1
4 7 4 6
4 6
4 5
4 4 4 5 4 4
Figure 2.9 Ring steel hardness (HRC) for two types of rings, measured over the
cross section according to Figure 2.8. The distance between measure-
ment points along the measurement lines was 7 mm.
M u s h ro o m w id th C h ip p e d a r e a
E d g e w id th
M u s h r o o m in g C h ip p in g
38
2. CUTTER CONSUMPTION 2.3 Ring Wear
The ring wear should be abrasive, and not destructive. Destructive wear occurs in two
main types for steel ring cutters:
Chipping along the cutter edge indicates that the steel hardness (or brittleness) is too
high with regard to the cutter thrust and/or the rock strength.
Mushrooming of the cutter edge indicates that the steel hardness (or brittleness) is too
low with regard to the cutter thrust and/or the rock strength.
The measurements should apply to each side of the ring edge, denoted as inner and
outer side in relation to the cutterhead centre.
39
3. PENETRATION TESTS 3.1 Test Procedure
• Measurement of the cutterhead penetration over a given time at various thrust lev-
els and constant RPM.
• Registration of the average cutterhead torque of each cutter load level.
• Registration of other relevant data such as cutter wear state, whether the test is at
the start, middle or end of the stroke, cutterhead vibration level, etc.
• Measurement or registration of the net penetration rate, cutter thrust level and cut-
terhead torque of the previous and following strokes.
• Collecting a complete chip sample for the penetration test and chip samples for the
previous and following strokes.
Thrust levels
A penetration test should include at least four thrust levels. When deciding the thrust
levels Mt to be used, the current thrust level used by the operator is selected as the 100
% level, denoted as MB100. This presupposes that the machine is operated at an opti-
mum thrust level concerning net penetration rate, cutter life, cutterhead vibrations,
etc. The thrust levels of the test are then selected as:
M t1 ≈ 0.7 ⋅ M B100
M t 2 ≈ 0.8 ⋅ M B100
(kN/cutter) [3.1]
M t 3 ≈ 0.9 ⋅ M B100
M t 4 ≈ 1.0 ⋅ M B100
If applicable with regard to the cutter life, available torque, etc., it is recommended to
include a fifth thrust level in the test:
40
3. PENETRATION TESTS 3.1 Test Procedure
The actual thrust levels are selected as rounded numbers to ease the operation of the
TBM during the test. If the machine in the given rock conditions is operated at a
thrust level corresponding to a cylinder pressure of pB100 = 217 bar, the actual thrust
levels are selected as follows:
p t1 = 160
p t 2 = 180
p t 3 = 200 (bar) [3.3]
p t 4 = 220
p t 5 = 230
To ensure the quality of the test, the operator must maintain a constant thrust level
during each step of the test. The applied thrust level must be recorded for each step of
the test, either as an observed average from the thrust cylinder pressure gauge or as a
printout from the onboard computer. The applied thrust must be averaged over time.
Test Duration
Before the measurement of the penetration starts, the operator must stabilise the thrust
at each level.
Penetration Measurement
The penetration it is measured in mm over the given time. It is recommended that the
penetration measurements are taken at one of the thrust cylinders since these are in
41
3. PENETRATION TESTS 3.1 Test Procedure
direct contact with the cutterhead. One may also use instruments at the operator con-
sole when the accuracy of such instruments has been verified.
Torque Measurement
The applied torque is recorded as the average amperage It for each step of the test,
either as an observed average of the ampere meters or as a printout from the onboard
computer. The applied amperage must be averaged over time.
The applied voltage of the cutterhead drive motors must be checked. The motors
should be operated at the rated voltage UN. Otherwise, the applied voltage of the test
Ut must be noted.
Table 3.1 Example of data recorded during a penetration test. For further treat-
ment of the test, see Section 3.2
It is recommended to measure the net penetration rate of the previous and following
strokes of the test stroke. This is done to ensure the quality and representativeness of
the test. The penetration rate should be measured over the complete strokes. For large
42
3. PENETRATION TESTS 3.1 Test Procedure
TBM diameters one may measure the net penetration rate only over parts of the stroke
length, e.g. for 20 - 30 minutes.
Personnel
At least two persons in addition to the TBM operator are needed to perform a penetra-
tion test with chip sampling: One for the penetration measurements and one for the
chip sampling.
43
3. PENETRATION TESTS 3.2 Penetration Curve
The penetration curve in [3.4] is found by treatment of the observed data as shown
below.
b
M
i 0 = t (mm/rev) [3.4]
M1
The data from Table 3.1 are modified to the data given in Table 3.2. The actual ma-
chine has Ntbm = 25 cutters and ntc = 2 thrust cylinders, each with an effective diame-
ter of dtc = 444.5 mm. The applied gross average thrust is calculated from the applied
cylinder pressure according to [3.5]. The basic penetration is found by [3.6].
π ⋅ d tc2 0.4536 ⋅ g
M t = p t ⋅ ntc ⋅ ⋅ ( p t in psi)
4 ⋅ 25.4 1000 ⋅ N tbm
2
(kN/cutter) [3.5]
p π ⋅ d tc2 1
M t = t ⋅ ntc ⋅ ⋅ ( p t in bar)
10 4 1000 ⋅ N tbm
it
i0 = (mm/rev) [3.6]
RPM ⋅ t t
44
3. PENETRATION TESTS 3.2 Penetration Curve
Table 3.2 Cutter thrust and basic penetration for a penetration test.
M1 and b in [3.4] are found by linear regression of the log10 values of the thrust and
the penetration. It is convenient to use a spreadsheet to perform the necessary calcula-
tions. An example of an EXCEL spreadsheet for this purpose is shown in appendix E.
The log10 values of Mt and i0 will usually fit very good to a straight line, see data of
Test 1 in Figure 3.1. The xy-plot of the log10 values should be analysed with regard to
which observations to include in the regression and the penetration curve. Test 2 is an
example of disturbed data, in this case a Marked Single Joint was found in the con-
secutive mapping of the actual tunnel section. Another cause of disturbance is too
large variation of the thrust during one or more steps of a test. When data of one or
two thrust levels are disturbed, the test may still be used for analyses, but with cau-
tion.
The linear regression of the log10 data results in the equation in [3.7]. The log10 ver-
sion of [3.4] is shown in [3.8]. The constants of the linear equation are transformed to
M1 and b according to [3.9] and [3.10].
BR
−
M 1 = 10 AR
(kN/cutter) [3.9]
BR
−
b ⋅ (log 10 ( M B ) − log 10 (10 AR
)) = AR ⋅ log 10 ( M B ) + B R [3.10]
⇒ b = AR
log10 i0
Test 1
0.8 Test 2
Linear regression of Test 1
Linear regression of Test 2
0.6
0.4
0.2
0
2.3 2.35 2.4 2.45 2.5
log10 M t
Figure 3.1 Plot of log10 values of Mt and i0 for two penetration tests, including lin-
ear regression curves.
46
3. PENETRATION TESTS 3.3 Cutter Coefficient
The calculation of the cutter coefficient kc and the cutter constant cc is based on the
registrations of the applied amperage during the penetration test, see Table 3.1. The
use of electric motors is presupposed.
To be able to calculate kc, one needs the rated amperage IN and the efficiency curve
(cosφ⋅η) of the motors. An example of this is shown in Table 3.3 and Figure 3.2.
Table 3.3 Efficiency of an electric cutterhead drive motor with a rated power of
PN = 336 kW and a rated amperage of IN = 351.8 A. The necessary data
are usually found in the Service and Operation Manual of the machine.
U t ⋅ I t ⋅ 3 ⋅ (cos φ ⋅ η ) ⋅ 60 ⋅ n m ⋅ 2
kc = [3.11]
2 ⋅ π ⋅ d tbm ⋅ rmc ⋅ M t ⋅ 1000 ⋅ N tbm ⋅ RPM
47
3. PENETRATION TESTS 3.3 Cutter Coefficient
1.0
cosφη
0.9
0.8
0.7
0.6
0.5
0.4
0.0 0.2 0.4 0.6 0.8 1.0 1.2
It/IN
N tbm
∑r
i =1
i
N tbm
rmc = [3.12]
0.5 ⋅ d tbm
The cutter constant is calculated according to [3.13]. The resulting cutter constant of a
penetration test is shown in Figure 3.3.
kc
cc = [3.13]
i0
48
3. PENETRATION TESTS 3.3 Cutter Coefficient
0.050
cc
0.045
0.040
0.035
0.030
200 220 240 260 280 300
Mt, kN/cutter
Figure 3.3 Cutter constant of the penetration test in the Tables 3.1 and 3.2.
Ut = 660 V, nm = 4, dtbm = 3.5 m, dc = 483 mm, rmc = 0.6334, Ntbm = 25.
Figure 3.3 shows an irregular progress of the cutter constant with regard to increased
thrust level. One reason may be incorrect reading of the Ampere meters, but most
likely it is because the two lowest thrust levels have a quite low basic penetration, see
Table 3.2, making [3.13] a somewhat incorrect approximation.
49
3. PENETRATION TESTS 3.4 Specific Energy
The gross specific energy used to break the rock may be estimated from the penetra-
tion test data or from shift log data. The specific energy estimated on that basis does
not include the cutterhead thrust system which usually has an installed power of 10 %
or less compared to the cutterhead torque system. Since the cutterhead torque is used
to estimate the specific energy for TBM boring, the muck removal through the cutter-
head is included. The contribution of the muck removal is negligible compared to the
contribution from the cutterhead rotation.
150
MJ/m3
140
130
120
110
100
200 220 240 260 280 300
Mt, kN/cutter
Figure 3.4 Specific energy consumption based on data from the penetration test in
Tables 3.1 and 3.2.
50
4. CHIP ANALYSES 4.1 Test Procedure
Analyses of the largest chips produced by a TBM may give information of the boring
process and the rock breaking mechanisms, as well as material properties of the TBM
muck and drillability parameters of the intact rock.
Chip sampling must be combined with registration of concurrent machine and per-
formance data. Chip sampling is of extra value when combined with a penetration
test. The following sampling procedure is related to penetration tests, but may be used
as a general procedure when sampling chips.
During a penetration test, the largest chips are sampled, measured and analysed as
described below.
Sample Site
Sample Time
When the operator has stabilised the thrust level of the machine, the penetration
measurement starts. After that, one should wait at least half a minute before the chip
sampling starts, to ensure that the chips sampled are inside the penetration measure-
ment. One should stop the sampling when the penetration measurement stops.
Sample Size
A chip sample should consist of 20 large chips at each thrust level. This is achieved
by picking a larger number of chips (25 - 30), sorting the chips according to size by
51
4. CHIP ANALYSES 4.1 Test Procedure
visual judgement, and then discarding the smallest, leaving the 20 largest chips for
measurements and possible laboratory testing. The number of chips is mainly decided
by the time available for sampling at each thrust level and by the necessary number of
chips to establish a stable mean value and standard deviation of the chip sizes. Figure
4.1 shows the fluctuation in the mean value and the standard deviation of the thick-
ness of the chip sample in Table 4.1.
30
mm
25
Mean value
20
15
10
5
Standard deviation
0
0 5 10 15 20 25
Number of chips measured
Figure 4.1 Mean value and standard deviation of the chip thickness as a function of
number of chips in the sample.
Normally, the largest chips will be produced by the face cutters. Chips from the gauge
will usually not be picked since they are thinner and less wide than chips from the
face cutters. Chips produced by the centre cutters will be recognised by the evident
ring shape. Chips that by visual judgement originate from the centre or gauge should
be discarded from the sample.
Chips that seem to be broken during removal from the rock face to the sampling site
are discarded. Blocks that are fall-outs from Marked Single Joints or similar are also
discarded.
52
4. CHIP ANALYSES 4.1 Test Procedure
Muck Sample
When collecting a muck sample for sieve testing, the sample volume should be at
least 20 l and may be collected at conveyor transfer points to get the best representa-
tive sample. Muck samples collected from e.g. a truck load or a muck pile may be
subject to separation of the fines from the coarser chips, and therefore not representa-
tive samples.
53
4. CHIP ANALYSES 4.2 Chip Size
The size of each chip is measured as largest length, width and thickness, regardless of
where along the chip the largest size occurs. It is of course important that the three
measurements are taken more or less perpendicularly to each other.
The chip size measurements are averaged for each thrust level as in the Tables 4.1 and
4.2, and plotted as a function of thrust as in Figure 4.2. The cubic chip size Vch is cal-
culated by [4.1] and plotted as in Figure 4.3. The chipping frequency fch is calculated
by [4.2] and plotted as in Figure 4.4.
Chip no. Height hch (mm) Width wch (mm) Length lch (mm)
1 24 65 267
2 43 65 209
⋅⋅⋅⋅⋅
19 16 67 193
20 26 66 204
Mean size (mm) 28.5 66.6 217.2
Standard Deviation, mm 7.9 5.8 37.2
Standard Deviation, % 27.7 8.7 15.4
Table 4.1 Chip size measurements for one thrust level of a penetration test.
dtbm = 8.5 m, dc = 432 mm. The rock type is mica gneiss.
Table 4.2 Chip size measurements and chipping frequency of a penetration test.
Data of the same test as in Table 4.1.
54
4. CHIP ANALYSES 4.2 Chip Size
300
mm Thickness
Width
250
Length
200
150
100
50
0
150 175 200 225 250
Mt, kN/cutter
Figure 4.2 Average size of the largest chips from the penetration test in Table 4.1.
500
1000 mm3
450
400
350
300
250
150 175 200 225 250
Mt, kN/cutter
Figure 4.3 Cubic chip size of the penetration test in Table 4.2.
55
4. CHIP ANALYSES 4.2 Chip Size
1
f ch = (rev −1 ) [4.2]
hch
i0
0.14
-1
rev
0.12
0.1
0.08
0.06
150 175 200 225 250
Mt, kN/cutter
56
4. CHIP ANALYSES 4.2 Chip Size
The shape factor is a relative measure of the shape of an individual chip or of the av-
erage dimensions of 20 large chips. The calculation of the shape factor is given in
[4.3]. A plot of the shape factor of the chips from the penetration test in Table 4.2 is
shown in Figure 4.5.
f hw = hch / wch
[4.3]
f wl = wch / l ch
1
fwl
0.9
FLAT CUBIC
0.8
0.7
0.6
0.5
ELONGATED
0.4
0.3
0.2
0.1
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
ftw
Figure 4.5 Chip shape of the average chip size of the penetration test in Table 4.2.
57
4. CHIP ANALYSES 4.3 Sieve Curve
The sieve curve is found by sieving the TBM muck at square sieves. The sieve sizes
to find a rough particle size distribution of the TBM muck are recommended as:
The sieve curve established by the above sieve range should only be used for evalua-
tion of the rock breaking and boring process. To perform a standard sieve test to char-
acterise the material for technical or building purposes, the finer fractions must be
decided by sieves down to 0.063 mm and by sedimentation for the even finer frac-
tions.
Using a sieve shaker will give a good result for the fractions below 2 mm. Experience
shows that from the 4 mm sieve and upwards, some chips that should have passed will
be left at the sieve due to the flat and elongated chip shape. Hence, the sieve test must
include a manual verification of the size of each chip as illustrated in Figure 4.6.
d s
d s
A chart for presentation of the sieve test results is shown in Appendix D. Normalised
sieve curves are found in the Project Report 1F-98 HARD ROCK TUNNEL
BORING The Boring Process.
58
4. CHIP ANALYSES 4.4 Kerf Depth Factor
The kerf depth factor is measured where the chip has its largest thickness. In the labo-
ratory, the chips are cut by diamond saw, which gives the best measurements. In the
field one has to rely more on judgement as the measurements are taken on uncut
chips.
Concerning the accuracy of the measurements, one should bear in mind that the kerf
depth factor is used to show a trend, not for precise calculations. Furthermore, when
the number of chips increases, the influence of the random measurement error is de-
creased.
The kerf depth is measured as shown in Figure 4.7. The kerf depth factor is:
ik
f kd = [4.4]
hch
C u tte r e d g e
ik in d e n ta tio n
h c h
59
4. CHIP ANALYSES 4.4 Kerf Depth Factor
It may be difficult or uncertain to identify the exact kerf depth or the cutter ring
indentation of each chip. The best indicator is the fine powder that may be found at
the side of the chip, combined with the form of the chip side towards the kerf, see
Figure 4.8. Deficient identification of the kerf depth should lead to discarding the chip
from the kerf depth measurements.
60
4. CHIP ANALYSES 4.5 Crack Growth
The best approach to study the crack growth and the chipping mechanisms for hard
rock tunnel boring is to examine cross sections of the large chips. When the chips are
cut by diamond saw, the cracks inside the chip are easy to identify. The chip forming
cracks are of course found as the surface of the chip.
Usually, the chip is cut where its thickness is largest. It is supposed that the final
forming of the chip occurred at that part of the chip. A three-dimensional model of the
crack pattern may be established by cutting the chip in equally spaced slices.
The orientation of the chip with regard to which side has been towards the cutterhead
is decided by the chip form and by the fine powder remaining in the kerfs made by the
cutter along the chip. Figure 4.8 shows a cross section of a chip with easily identifi-
able cutter tracks (kerfs) and radial cracks from cutter passes prior to the chip form-
ing.
C ra c k s fro m p r e v io u s p a s s e s
ik
ik
h c h h c h
61
4. CHIP ANALYSES 4.6 Rock Properties
The largest chips may be used for testing of drillability, strength and wear properties.
Actual tests to be performed on chips are DRI, Mini-DRI, CLI, CAI and Point Load
Strength. One must however observe that the chips have been subject to high stress
that may have influenced the rock properties somewhat.
DRI
The Brittleness Value S20 of the DRI test is believed to be influenced by the type of
test material. TBM chips will most likely contain some small cracks from the boring
process. Parallel tests of 50 mm diameter cores and TBM chips indicate that the
Brittleness Value (and therefore the DRI value) tested on chips is 2 - 4 units higher
than the Brittleness Value tested on 50 mm cores. The few available data covers the
Brittleness Value range of 35 - 50. Since the systematic error in the DRI value tested
on chips seems to be relatively small, it is advisable to use TBM chips as test material
in the DRI test.
The chips must be of a size and orientation so that one is able to perform the Sievers'
J-value (SJ) test parallel to the possible foliation of the rock. This is achieved in most
cases by cutting the chips in the desired orientation. The SJ test may be influenced by
microcracks resulting from the cutter forces.
Mini-DRI
The brittleness test of the Mini-DRI uses the crushed aggregate fraction of 2 - 4 mm.
The Mini-DRI value is believed to be little influenced by the type of test material as
long as it is chips, cores or blocks. Hence, the largest TBM chips are well suited to be
used in the Mini-DRI test. The SJ test requires the same size and orientation of the
chips as the standard DRI test.
CLI
The abrasion tests AV and AVS use the crushed fraction of grain size < 1 mm. The AV
and AVS value are not believed to be influenced by the type of test material as long as
it is crushed from larger pieces, and the largest TBM chips are well suited for these
tests. In order to calculate the CLI, the chips must be of a size and orientation so that
one is able to perform the SJ test parallel to the possible foliation of the rock.
62
4. CHIP ANALYSES 4.6 Rock Properties
CAI
The CAI test is a scratch test performed on a rough rock surface. The TBM chips are
well suited as test material to test the CAI value.
The Point Load test may be influenced by microcracks resulting from the rock cutting
process.
63
5. BACK-MAPPING 5.0 Introduction
5.0 INTRODUCTION
The engineering geological back-mapping of a bored tunnel should consist of the fol-
lowing:
It is convenient to map longer sections, e.g. 500 m, for each mapping round. Back-
mapping in tunnels lined with concrete elements or shotcrete at the cutterhead is very
difficult to perform with the purpose to establish a continuous geological model. In
such tunnels the back-mapping must be improvised and done at points whenever the
rock surface is available.
The mapping is a subjective task with regard to degree of fracturing, type of fractures,
rock type, etc. The quality of the mapping will improve substantially when a team of
two persons is doing the back-mapping.
The parameters used in the back-mapping are the same as those used in the site inves-
tigations, as described in the Project Report 1E-98 HARD ROCK TUNNEL
BORING Geology and Site Investigations.
64
5. BACK-MAPPING 5.1 Mapping Procedures
The mapping in the tunnel should be recorded on a sheet with standardised entries.
An example of a completed sheet for a 50 m tunnel section is shown in Figure 5.1. A
blank form is found in Appendix D, and is also available in digital format1.
S ig n a tu r e :
T U N N E L : M E R K R A F T D a te : 3 / 2 - 9 2
A B / B S
C h a in -
a g e 4 5 5 0 6 0 7 0 8 0 9 0 4 6 0 0
1 3 5 °
L e ft w a ll
9 0 °
4 5 °
1
R o o f
0 °
1
-4 5 °
R ig h t w a ll
-9 0 °
-1 3 5 °
12 g / 3 9 °
R o c k ty p e
G r e e n s c h is t
(G r e e n s t o n e )
F r a c tu r in g
1 1
C o m m e n ts
D r ip p in g f o l: 2 1 1 g / 4 2 ° a @ 3 6 ° C la y f ille d 1 - 2 c m
tu n n e l ~ 2 8 0 g
1
Contact the author.
65
5. BACK-MAPPING 5.1 Mapping Procedures
+ + + + + +
chain- left roof right left roof right
age wall wall wall wall
0° 0°
135° -135°
180° 180°
-180° -180°
dtbm < 5 - 8m dtbm > 5 - 8m
Figure 5.2 Representation of the tunnel circumference in the mapping sheet. Right
and left wall applies when looking towards the tunnel face.
• Record the Marked Single Joints and measure strike and dip where convenient.
• Record other singular phenomena like intrusions, water, rock fall-outs, rock sup-
port, etc.
• Decide the rock type.
• Decide the number of fracturing systems (usually one or two).
• Decide the type of fracturing for each system (St or Sp).
• Decide the degree of fracturing for each system.
• Measure strike (αs) and dip (αf) of the fracturing system(s) at least once for each
50 m.
• Measure the strike of the tunnel (αt) at the same time as the strike and dip of the
fracturing is measured.
The registrations should be an average for the 10 m section. If necessary (e.g. change
of rock type), the 10 m section may be subdivided.
66
5. BACK-MAPPING 5.1 Mapping Procedures
In most cases, the degree of fracturing is recorded by visual interpretation with occa-
sional measurements of the distance between the planes of weakness. The distance is
measured perpendicular to the planes of weakness as shown in Figure 5.3.
= fis s u r e s
-4 5 °
R ig h t 2 4 4 0 2 4 3 5
tu n n e l
w a ll
S c a n lin e
0 6 7 5 0 0 0
fo r m a p p in g 1 3 5 1 2 5 9 0 0 1 0
-1 3 5 °
(1 3 5 0 + 6 7 5 + 1 2 5 0 + 9 0 0 + 1 0 0 0 )m m
a = = 1 0 3 5 m m » S t I-
f 5
Figure 5.3 Measurement of fracture spacing. The fissures have strike approximately
perpendicular to the tunnel axis.
Figure 5.4 shows two examples where it may be difficult to evaluate the degree of
fracturing. Case 1 has various possibilities, of which 3 are evaluated below.
• The rock mass is massive (homogeneous) outside the tunnel. Hence, there are only
3 fissures to consider, and the average distance between the fractures may be esti-
mated as:
(500 + 600) mm
af = = 550 mm
2
67
5. BACK-MAPPING 5.1 Mapping Procedures
• The "next" fissures are just outside the tunnel in the roof and the invert. Average
distance between the fractures will be:
• The "next" fissures are 800 mm outside the tunnel roof and 1600 mm outside the
tunnel invert. Average distance between the fractures will be:
The conclusion for Case 1 is that the degree of fracturing may be classified as St I-
or lower, with St 0-I as the recommended classification.
• The rock mass is massive (homogeneous) outside the tunnel. Hence, there are 6
fissures to consider, and the average distance between the fractures may be esti-
mated as:
500 mm
af = = 100 mm
5
68
5. BACK-MAPPING 5.1 Mapping Procedures
• If the "concentration" of fissures or joints has some extent along the tunnel (e.g.
more than 2 ⋅ dtbm), it may be regarded as a weakness zone and classified as a
prominent Marked Single Joint.
The conclusion for Case 2 is that the concentrated fissures or joints may be classi-
fied as a Marked Single Joint. It is however difficult to give general rules for simi-
lar cases for when to classify as Marked Single Joints and when to classify as sys-
tematic fractured rock mass.
e s
s u r
m m F is
8 0 0
m m m
0 m
5 0 0 2 2 0
m m
6 0 0
m m m
0 m 5 0 0
1 6 0
m m
8 0 0
re s
s s u
6 fi
C a s e 1 C a s e 2
The best way to adjust and fine tune the classification of the degree of fracturing as
seen in the tunnel wall, is to observe the tunnel face during a standstill of the TBM
and experience how the fracturing is utilised in the rock breaking process.
The notation and registrations of the back-mapping may be individual, but some basic
rules should be applied:
• The preferred sectioning of the tunnel circumference is as follows: The roof and
the walls of the mapping form cover a sector of 90° each, leaving a sector of 90°
in the invert. When necessary, the chainage field and the field below the right wall
field are utilised to record Marked Single Joints etc., see Figure 5.1.
69
5. BACK-MAPPING 5.1 Mapping Procedures
• For large diameter tunnels, the roof and wall sectors of the mapping form may be
increased to 120° to be able to cover the complete tunnel (see Figure 5.2 and Ap-
pendix D).
• Marked Single Joints are recorded as continuous lines, other rock mass fracturing
is recorded as dotted lines.
• The type and degree of fracturing must be noted for each 10 m section. Do not use
arrows or similar to indicate "continues from, or the same as, the previous sec-
tion".
• Strike and dip is measured in a 400g or 360° scale, with the dip direction always to
the same side of the strike direction2.
Quality Control
2
See Section 2.1 in the Project Report 1D-98 HARD ROCK TUNNEL BORING Geology and Site
Investigations.
70
5. BACK-MAPPING 5.2 Aggregation of Mapping Data
The data from the back-mapping must be aggregated to be used further. The geologi-
cal model of the tunnel is typically divided into sections, in which as many as possible
of the boring parameters are constant or showing little variation.
The most important parameters to consider when the tunnel is divided into sections,
are:
• Rock type and rock properties such as DRI, CLI, quartz content
• General level of rock mass degree of fracturing
• General angle between the tunnel axis and the planes of weakness
• Tunnel direction
• Machine parameters such as thrust level, cutterhead RPM, cutter type, etc.
Rock Properties
If test results for more than one rock sample is available for one geological tunnel
section, the arithmetic mean of the laboratory test results or indices are used.
In special cases, one may use a weighted average (parameters weighted by tunnel
length). When rock samples are assumed to represent a given length of a tunnel sec-
tion, it is recommended to subdivide the tunnel section rather than to use a weighted
average for the original section.
The systematic rock mass fracturing of the tunnel section is grouped according to the
degree of fracturing as shown in Figure 5.6.
The angle between the tunnel axis and the planes of weakness is estimated from pole
plots of the strike and dip measurements (see Project Report 1D-98 HARD ROCK
71
5. BACK-MAPPING 5.2 Aggregation of Mapping Data
The average ks factor of the section is calculated according to [5.1] and Table 5.1.
IV
4 .0
F is s u r e C la s s J o in t C la s s
k s
3 .0
III-IV
2 .0
III II
II-III I-II
1 .0
II I
I 0 -I
0 0
1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0
a , d e g re e s
Figure 5.5 Fracturing factor. From the Project Report 1B-98 HARD ROCK
TUNNEL BORING Advance Rate and Cutter Wear. The equations of
the ks factor are available from the author.
The ks factor of fracturing classes not shown as curves in Figure 5.5 is found by linear
interpolation between the given curves.
72
5. BACK-MAPPING 5.2 Aggregation of Mapping Data
90
m
80
70
60
50
40
30
20
10
0
st I+ st I-II st II- st II st II+ st II-III
Degree of fracturing
Figure 5.6 Example of distribution of rock mass fracturing of a 235 m long tunnel
section.
∑l i
k s − avg = n
i =1
[5.1]
li
∑
i =1 k s −i
The ks-avg relates to the basic net penetration rate I0 of the tunnel section, see below.
73
5. BACK-MAPPING 5.2 Aggregation of Mapping Data
li li
i Fracturing Class
Tunnel Length of Frac-
ks-i
k s −i
∑l i ∑k
turing Class i (m) s −i
∑l i
234
k s −avg = 6
i =1
= = 1.06 [5.1]
li 220.67
∑
i =1 k s − i
The total tunnel length of the section influenced by Marked Single Joints is found by
summing the length in the tunnel of each MSJ. Table 5.2 shows how the 8 Marked
Single Joints in Figure 5.1 are treated.
According to Figure 5.7, the Marked Single Joints should be grouped in two groups:
This may roughly be achieved by grouping the Marked Single Joints in two catego-
ries:
• MSJs each influencing a tunnel length less than the tunnel diameter, i.e. αesp > 45°
• MSJs each influencing a tunnel length greater than the tunnel diameter,
i.e. αesp ≤ 45°
The average angle αesp between the tunnel axis and each MSJ group is found by [5.2].
The basic net penetration rate I0 of the tunnel section is found by [5.3].
74
5. BACK-MAPPING 5.2 Aggregation of Mapping Data
nesp ⋅ d tbm
α esp = arctan (°) [5.2]
l esp
In l esp −i
I0 = (l j − ∑ l esp −i + ∑ ) (m/h) [5.3]
lj k esp −i
DRI=30 DRI=40
1.4
kesp DRI=50
1.3
DRI=60
1.2
1.1
10 20 30 40 50 60
a esp , degrees
Figure 5.7 Correction factor for Marked Single Joints. From the Project Report 1B-
98 HARD ROCK TUNNEL BORING Advance Rate and Cutter Wear.
75
5. BACK-MAPPING 5.2 Aggregation of Mapping Data
When the mapping form does not include the invert sector, it is a good possibility to
use the chainage field and the field below the right wall field to represent half of the
invert sector each, as indicated in Figure 5.2. This is utilised for Marked Single Joint
no. 2 in Figure 5.1.
Table 5.2 Calculation of lesp and αesp for a 3.5 m diameter tunnel. Data from Fig-
ure 5.1. Real Length in Tunnel is roughly estimated. DRI = 40.
76
5. BACK-MAPPING 5.3 Rock Sampling
The most important quality of a rock sample for laboratory testing, is that it is repre-
sentative of the rock type. The selection of sample sites must therefore be carefully
evaluated.
The following procedures may be utilised to find the best sample sites:
• Suitable sample sites with regard to representative and constant rock conditions as
well as sampling possibilities (block or core sample) are recorded during the back-
mapping.
• The number of samples is decided from the back-mapping and the machine per-
formance data. Each rock type should be represented by at least one sample. One
should at least test one rock sample for each 500 m of tunnel.
• The sample site should be located in a 20 - 30 m long subsection of stable degree
of fracturing and machine performance.
• The sample site should be located where the Ic/In ratio is close to 1.0, see Table
2.3.
• The sample site should not be close to larger discontinuities or intrusions, where
the rock properties may be influenced by alteration.
• Avoid sample sites with a high stress concentration along the tunnel circumfer-
ence.
The sampling method may vary, but block or core samples are recommended. Cores
should have a diameter of 50 mm or more. One sample may consist of several pieces
totalling 10 kg. Each piece should have a weight of at least 0.5 kg. Samples consisting
of the largest chips from the boring may be used for laboratory testing, with the re-
strictions given in Section 4.6.
It is a good practise to collect one or two large chips routinely (e.g. each day) to re-
cord the rock type, grain size, colour, etc. Typical chips from each 50 m tunnel sec-
tion, each week or similar lengths or time periods are stored until the tunnel is fin-
ished, building a rock database for the tunnel.
77
5. BACK-MAPPING 5.4 Achieved vs. Predicted Performance
When the DRI, CLI, quartz content, ks-avg, kesp and the applied machine parameters
have been found for a tunnel section, the achieved penetration rate, advance rate and
cutter consumption may be compared to the prediction model in the Project Report
1B-98 HARD ROCK TUNNEL BORING Advance Rate and Cutter Wear. Thus,
the actual tunnelling performance may be evaluated against a standardised model.
New data as a basis for improvement of the prediction models will also be provided in
such cases.
The model for penetration addition due to Marked Single Joints is based on less data
than the penetration rate model for systematic fractured rock mass. Hence, when
evaluating the machine performance as net penetration rate, one will get the best pic-
ture when using data from tunnel sections with few or no Marked Single Joints.
The data from the back-mapping should also be compared to the predicted geological
model established through the site investigations. Such verification will bring valu-
able information to improve:
78
APPENDIX A. Previous Editions
A. PREVIOUS EDITIONS
Previous editions of the Hard Rock Tunnel Boring Report including project group
members:
79
APPENDIX B. Research Partners
B. RESEARCH PARTNERS
• Statkraft anlegg as
• Norwegian Public Roads Administration
• Statsbygg
• Scandinavian Rock Group AS
• NCC Eeg-Henriksen Anlegg AS
• Veidekke ASA
• Andersen Mek. Verksted AS
• DYNO Nobel
• Atlas Copco Rock Drills AB
• Tamrock OY
• The Research Council of Norway
80
APPENDIX C. List of Parameters
C. List of Parameters
The parameters used in the report are listed in the following. The list is according to
when the parameter first is explained or treated.
81
APPENDIX C. List of Parameters
82
APPENDIX C. List of Parameters
83
APPENDIX C. List of Parameters
84
APPENDIX C. List of Parameters
85
APPENDIX D1. Mapping Sheet ±135°
-1 3 5 °
1 3 5 °
-4 5 °
-9 0 °
9 0 °
4 5 °
0 °
S ig n a tu r e :
D a te :
T U N N E L :
C h a in -
L e ft w a ll R o o f R ig h t w a ll R o c k ty p e F r a c tu r in g C o m m e n ts
a g e
86
APPENDIX D2. Mapping Sheet ±180°
-1 8 0 °
1 8 0 °
-6 0 °
-9 0 °
9 0 °
6 0 °
0 °
S ig n a tu r e :
D a te :
T U N N E L :
C h a in -
L e ft w a ll R o o f R ig h t w a ll R o c k ty p e F r a c tu r in g C o m m e n ts
a g e
87
S H IF T L O G T B M P R O J E C T :
L a s e r ta rg e ts : S ta r t o f s h ift E n d o f s h ift
D3. SHIFT LOG
APPENDIX
D a te : O p e ra to r: F ro n t B a c k F ro n t B a c k
6 6 6 6
4 4 4 4
M a c h in e h o u r s s to p : C h a in a g e s to p : 2 2 2 2
0 0 0 0
M a c h in e h o u r s s ta r t: C h a in a g e s ta r t: 2 2 2 2
4 4 4 4
B o r in g tim e : B o r e d le n g th : 6 6 6 6
6 4 2 0 2 4 6 8 6 4 2 0 2 4 6 8 6 4 2 0 2 4 6 8 6 4 2 0 2 4 6 8
D a y : 0 7 0 8 0 9 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9
N ig h t: 1 9 2 0 2 1 2 2 2 3 2 4 0 1 0 2 0 3 0 4 0 5 0 6 0 7
A m p e re
T h ru s t
88
D3. Shift Log
R E A S O N F O R C H A N G E : W = (A b r a s iv e ) w e a r
APPENDIX
C = R in g c h ip p in g
B = B lo c k e d b e a r in g s
L = O il le a k a g e
F = B ro k e n b o lts
2 4
2 2 O = O th e r ( w ith r e m a rk )
25 P o s . C u tte r n o . R e a s o n P o s . C u tte r n o . R e a s o n
2 4 2 2
n o . in o u t n o . in o u t
1 4
D4. CUTTER CHANGE LOG
1 4 1 1 2 5
1 1
1 2 1 -3 1 5
12
1 -3 1 6
1 9
1 9
7 5 1 7
1 6
6 .
1 6
6 . 6 1 8
9 .
7 1 9
2 3
8
3 1 2 4
1 8
9 .
8 2 0
8
2 3
1 8
9 2 1
1 3
5
1 3
1 0
1 1 2 3
1 7
5
1 7
1 0 1 2 2 4
1 5
1 3 2 5
2 0
2 1
1 5 1 4
2 1 2 0
C o m m e n ts :
C u tte r c h a n g e n o .
D a te
C h a in a g e
M a c h in e h o u r s
T o ta l n o . o f c u tte rs S H IF T : O P E R A T O R :
89
D4. Cutter Change Log
P a s s in g C L A Y S IL T S A N D G R A V E L
%
1 0 0
APPENDIX
9 0
8 0
D5. SIEVE CURVE SHEET
7 0
6 0
5 0
4 0
2 0
1 0
0
S ie v s iz e , m m 0 .0 6 3 0 .1 2 5 0 .2 5 0 .5 1 2 4 8 1 6 3 2 4 5 6 4
0 .0 0 0 6 0 .0 0 1 0 .0 0 2 0 .0 0 5 0 .0 1 0 .0 2 0 .0 6 0 .1 0 .2 0 .5 1 2 5 1 0 2 0 6 0
m m
1 0 0
90
D5. Sieve Curve Sheet
APPENDIX E. Penetration Test Spreadsheet
A B C D E
Normalised
1 Mt i0 log10(Mt) log10(i0) Penetration
Curve
2 205.5 1.74 2.312811826 0.240549248 1.742153183
3 231.2 2.41 2.36398783 0.382017043 2.418340339
4 256.9 3.28 2.409764104 0.515873844 3.242800145
5 282.6 4.2 2.451172158 0.62324929 4.228296974
6 #NUM! #NUM! 0
7 #NUM! #NUM! 0
8
9 ARX + BR 2.783161475 -6.195842434
10
11 6.37027E-07
12
13 M1= 168.3405072
12
15 b= 2.783161475
Cell Entries
91
ISBN 82-471-0281-1
ISSN 0802-3271