Professional Documents
Culture Documents
net/publication/275517831
CITATIONS READS
147 3,155
1 author:
Amund Bruland
Norwegian University of Science and Technology
75 PUBLICATIONS 1,585 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Amund Bruland on 27 April 2015.
Amund Bruland
Vol. 4 of 10
Costs
NTNU Trondheim
Norwegian University of
Science and Technology
Doctoral thesis
for the degree of doktor ingeniør
Faculty of Engineering Science
and Technology
Department of Civil and
Transport Engineering
PREFACE 1
0 GENERAL 3
1 NORMALISED COSTS 6
1.0 Introduction 6
1.3 Cutters 11
1.5 Labour 15
2 DETAILED COSTS 18
3.0 General 39
APPENDICES 43
A. Previous Editions 43
B. Research Partners 44
C. List of Parameters 45
D. Estimation Forms 48
PREFACE
The report is one of five reports about hard rock tunnel boring:
Combined with the other reports in the Project Report Series from the Department of
Building and Construction Engineering at NTNU, the reports present an updated and
systematised material on rock excavation and tunnelling to be used for:
•= Economic dimensioning
•= Choice of alternative
•= Time planning
•= Cost estimates, tender, budgeting and cost control
•= Choice of excavation method and equipment.
A list of available Project Reports may be requested from the Department of Building
and Construction Engineering at NTNU.
The advance rate, cutter wear and excavation cost models also exist as a WINDOWS
programme.
The report is prepared by Amund Bruland and is part of his dr.ing thesis about
hard rock tunnel boring.
The reports listed above describes a comprehensive model developed at NTNU The
model covers the complete tunnel boring process from the early planning stage
1
PREFACE
through preinvestigations, time and cost estimates, tunnel excavation and finally ac-
quisition and treatment of experience data. The models and data presented in the
reports are meant to be a practical tool for owners, consultants and contractors,
more than a theoretical analysis of the tunnel boring process.
The project has been granted financial support by our external research partners, see
list in Appendix.
Odd Johannessen
Professor
2
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
1C-98
The report provides methods and necessary data for estimation of excavation costs
and total construction costs for hard rock tunnel boring.
Project Report 1C-98 is a revised and updated version of parts of the project reports
1-76, 1-79, 1-83, 1-88 and 1-94, all published by the Department of Building and
Construction Engineering at NTNU.
Other Reports
The Project Report 1A-98 HARD ROCK TUNNEL BORING Design and Con-
struction describes general design parameters such as tunnel profile, tunnel inclina-
tion and curve radius. Some features of various tunnel types like water, sewage, road
and rail tunnels are treated. Transport, ventilation and other necessary service systems
are presented.
The Project Report 1B-98 HARD ROCK TUNNEL BORING Advance Rate and
Cutter Wear provides methods and necessary data for estimation of time
3
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
consumption and cutter wear for tunnel boring. Geological parameters and machine
factors of significance for the penetration rate and the cutter wear are presented
briefly.
The Project Report 1D-98 HARD ROCK TUNNEL BORING Geology and Pre-
investigations treats the rock mass parameters of the model in more detail. Preinves-
tigations and building of an engineering geological model adapted to the estimation
models for penetration rate and excavation costs are treated closely.
The Project Report 1E-98 HARD ROCK TUNNEL BORING Performance Data
and Back-mapping covers follow-up procedures and collecting of performance data
from tunnel boring projects. Engineering geological back-mapping is treated in detail.
Project Report 1F-98 HARD ROCK TUNNEL BORING The Boring Process
covers rock breaking and chipping, machine factors affecting performance, boring in
fractured rock mass, and various types of cutter wear.
The estimation models are aimed at being used through several stages in a project:
The estimation models for Hard Rock Tunnel Boring should be used with care. Com-
bined with other estimation models in the Project Report Series from the Department
of Building and Construction Engineering, the Hard Rock Tunnel Boring reports pro-
vide a reliable and practical tool to be used for:
4
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
Background
The estimation models are based on job site studies and statistics from tunnelling in
Norway and abroad, including more than 35 job sites and more than 250 km of tunnel.
The data have been systematised and normalised. The results are regarded as being
representative for well organised tunnelling.
A more detailed treatment of the background and the basis for the Hard Rock Tunnel
Boring estimation models is found in HARD ROCK TUNNEL BORING Back-
ground and Discussion.
5
1. NORMALISED COSTS 1.0 Introduction
1.0 INTRODUCTION
Depreciation of the main equipment for tunnelling is based on the concept of eco-
nomic useful life. The method of depreciation is further described in the Project Re-
port 15A-92 HEAVY CONSTRUCTION MACHINERY Costs, Performance and
Maintenance. Additional equipment is depreciated partly on time and partly on use.
The costs in this report are estimated in the same way as the costs in the Project Re-
port 2C-95 TUNNELLING Costs for Drill and Blast. The excavation costs of the
two tunnelling methods may be directly compared as long as corrections for price
level are performed.
All costs in this report are based on the price level of January 1999. The Depart-
ment of Building and Construction Engineering at NTNU calculates the necessary
correction factors for price level.
The normalised costs are an evened and normalised summary of the detailed cost
analyses given in Chapter 2, and represents averaged costs over the tunnel.
6
1. NORMALISED COSTS 1.0 Introduction
One should add costs for unforeseen conditions during the tunnel excavation. As a
rule of thumb, additional costs for unforeseen conditions amount to approximately
10 % of the estimated normalised costs.
The excavation costs must be adjusted for price increase according to the price level
of the cost model, which is January 1999.
The normalised costs are mainly used for estimation of various alternatives (routes,
cross sections and tunnelling methods). For a more detailed cost analysis, see the de-
tailed costs in Chapter 2.
The normalised costs include all necessary operations to excavate the tunnel. Costs
for rock support are not included. The total construction costs for the tunnel should
also include site preparation and operation, design and planning, construction man-
agement and interest during construction. See an example of application in Chapter 3.
The excavation costs are found by using the Figures 1.1 - 1.9 and Equations [1.1] -
[1.4] as shown in Appendix D.1.
The necessary input parameters like Im, Ntbm, Hhm and Ht may be estimated according
to the Project Report 1B-98 HARD ROCK TUNNEL BORING Advance Rate
and Cutter Wear.
7
1. NORMALISED COSTS 1.1 Assembly and Disassembly
Costs for freight of the TBM and backup equipment, concreting of starting blocks,
assembly and disassembly, and backing the machine out of the tunnel are shown in
Figure 1.1.
Crig
mill. NOK
4 5 6 7 8 9
TBM diameter, m
Figure 1.1 Costs for assembly and disassembly of the TBM and backup equipment.
8
1. NORMALISED COSTS 1.2 TBM and Backup Equipment
The Figures 1.2 and 1.3 show costs for TBM and backup equipment as a function of
TBM diameter and net penetration rate. Section 2.1 treats the cost items like deprecia-
tion, repair and maintenance, and energy consumption in more detail.
ctbm
NOK/m Im=1 m/h
12000
10000
1.5 m/h
8000
2 m/h
6000
3 m/h
4000
4 m/h
2000 6 m/h
4 5 6 7 8 9
TBM diameter, m
9
1. NORMALISED COSTS 1.2 TBM and Backup Equipment
Im=1 m/h
cback
NOK/m
2000
1.5 m/h
1500
2 m/h
1000
3 m/h
4 m/h
500
6 m/h
4 5 6 7 8 9
TBM diameter, m
10
1. NORMALISED COSTS 1.3 Cutters
1.3 CUTTERS
The cutter costs include rings, bearings, hubs and other cutter parts. Figure 1.4 shows
basic cutter costs c0b as a function of cutter ring life and cutter diameter. Average cut-
ter costs are calculated as follows:
N tbm
c b = c 0b ⋅ (NOK/m) [1.2]
Im
For definition and estimation of the input parameter Ht (cutter ring life), see Section
3.1 and Appendix D in the Project Report 1B-98 HARD ROCK TUNNEL
BORING Advance Rate and Cutter Wear.
11
1. NORMALISED COSTS 1.3 Cutters
c0b
NOK/hc
160
1 dc = 394mm
140 2 d = 432mm
c
3
dc = 483mm
120
100
80
60
40
1 2 3
20
12
1. NORMALISED COSTS 1.4 Work Behind the Face
The Figures 1.5 - 1.7 show total costs for work behind the face as a function of TBM
diameter and tunnel length. The costs include transport of muck, ventilation, electrical
installations and water supply.
dtbm=7.5m dtbm=7.5m
klbs Track-bound kibs Track-bound
transport transport
1.2 1.04
5.5m
5.5m
1.1 1
3.5m
3.5m
1.0
2 3 4 5
c0bs Net penetration rate, m/h
NOK/m 6 10
Tunnel length, km
4000
Lt=14km
3500 12km
10km
3000 8km
6km
4km
2500
2km
2000
Truck
transport
1500
1000 6 m/h
Track-bound transport
500
4 5 6 7 8 9
TBM diameter, m
Figure 1.5 Basic costs for work behind the face - track-bound and truck transport.
Correction factor kibs for net penetration rate Im ≠ 3 m/h and klbs for tun-
nel length Lt ≠ 6 km.
13
1. NORMALISED COSTS 1.4 Work Behind the Face
c0bs
NOK/m
1500
1400
1300
4 5 6 7 8 9
TBM diameter, m
Figure 1.6 Basic costs for work behind the face - transport with continuous con-
veyor. Correction factor klbs for tunnel length and net penetration rate is
shown in Figure 1.7.
1.6
klbs
1.4
Im=1 m/h
1.2
2 m/h
1.0 3 m/h
6 m/h
4 6 8 10 12 14
Tunnel length, km
Figure 1.7 Correction factor klbs for tunnel length and net penetration rate - trans-
port with continuous conveyor.
14
1. NORMALISED COSTS 1.5 Labour
1.5 LABOUR
Labour costs include work connected to the tunnel excavation, including work at the
adit and rig area. Hourly wages are estimated at 225 NOK/h + 50 % social security
costs for work in the tunnel and 160 NOK/h + 50 % social security costs for work
outside the tunnel.
Figure 1.8 shows labour costs as a function of net penetration rate, tunnel length and
cutter ring life.
Rock support work is not included. This means rock support that requires the boring
to be stopped, i.e. shotcreting, grouting, erection of segments, etc. However, rock
support work carried out while boring (e.g. scattered bolting), and without increasing
the crew, is included.
cl = c 0l ⋅ k il ⋅ k cl (NOK/m) [1.4]
15
1. NORMALISED COSTS 1.5 Labour
10 km
1.0 1
0.9
2 km
c0l
NOK/m 0.75
2 3 4 5 2 4 6 8
Net penetration rate, m/h Cutter life Hhm, h/c
2500
2000
1500
Continuous conveyor
Track-bound transport
1000
dtbm=7.5m
3.5m
500
Truck transport
1 2 3 4 5 6
Figure 1.8 Basic labour costs. Correction factor kil for net penetration rate Im and
correction factor kcl for cutter ring life Hhm ≠ 2.0 h/c.
16
1. NORMALISED COSTS 1.6 Declined Adit
Figure 1.9 shows additional costs for declined adit (length 300 m) as a function of net
penetration rate and tunnel length. The costs include pumping of water, extra ventila-
tion and other costs, which arises due to the declined adit.
cad
NOK/m
100
dtbm=9m
80
60
6m
40
3m
20
4 6 8 10 12 14
Tunnel length, km
17
2. DETAILED COSTS 2.1 TBM and Backup Equipment
The method and necessary equations to help estimate the machine costs of the TBM
or backup equipment are given in Section 2.2.
Cost calculation for TBMs and backup equipment follows the general machine cost
model described in detail in the Project Report 15A-92 HEAVY CONSTRUC-
TION MACHINERY Costs, Performance and Maintenance.
Depreciation
One significant deviation from the general model is made: Only 50 % of the deprecia-
tion basis is assumed to contribute to the repair and maintenance costs. Therefore, 50
% of the depreciation basis is depreciated linearly and 50 % of the depreciation basis
is depreciated degressively.
IA
Rest value
Refurbishment
RR=0.22 IA
Costs are calculated as an average for the period until a rest value of 22 % is reached.
The costs are based on purchase prices for TBM and backup equipment as shown in
the Figures 2.2 and 2.3. The purchase price should be interpreted as the price of the
equipment delivered at the site. The depreciation basis must include investment tax or
similar. The costs in this report include an investment tax of 7 %.
When estimating costs for a specific tunnel project, it may be necessary to calculate
depreciation, interest and maintenance costs separately for that tunnel.
19
2. DETAILED COSTS 2.1 TBM and Backup Equipment
dc=483mm
Ip
mill. NOK
75
dc=432mm
50
4 5 6 7 8 9
TBM diameter, m
Figure 2.2 Purchase price for TBM, excluding investment tax, cutters and spare
parts.
IP Muck transport:
mill. NOK 1
1 Track-bound
15.0 2 Trucks or continuous
conveyor 2
12.5
10.0
4 5 6 7 8 9
TBM diameter, m
Figure 2.3 Purchase price for backup equipment, excluding investment tax.
20
2. DETAILED COSTS 2.1 TBM and Backup Equipment
Interest
It is supposed that the machine as an average bores ty = 1250 hours per year. Hence, it
will take about 7.5 years for a 3.5 m diameter TBM to reach 9333 hours.
When estimating costs for a specific tunnel job, one should assume a lower interest
rate, from 5 % to 7 %, depending on the duration of the job (applicable for Norway).
Repair and maintenance costs include spare parts and other materials, and workshop
costs for repairs carried out at a central workshop. The fixed part of the repair and
maintenance costs for TBM and backup equipment is shown in Figure 2.3. The vari-
able repair costs are estimated according to the Project Report 15A-92 HEAVY
CONSTRUCTION MACHINERY Costs, Performance and Maintenance.
Downtime
Indirect costs for standard downtime are incorporated through the machine utilisation.
The costs for major downtime include serious incidents like inspection or failure of
the main bearing, axles, etc., and are estimated as 20 % of the maintenance costs.
21
2. DETAILED COSTS 2.1 TBM and Backup Equipment
Service
The service costs include materials for routine service, e.g. oil change, lubrication and
change of filters. Figure 2.4 shows service costs for the TBM and backup equipment.
Electric Energy
The costs include the consumption of electric energy. Installations, cables, etc. are
included in Section 2.4 Other Costs.
Figure 2.5 shows energy consumption for the TBM and backup equipment. For high
penetration rate, it may be necessary to check the curve against the cutterhead power.
Cost of electric power is estimated at pe = 0.30 NOK per kWh.
kiA
c0A
1.5
NOK/h
800 1.0
TBM
2 3 4 5
Net penetration rate, m/h
600
400
Backup
200
4 5 6 7 8 9
TBM diameter, m
Figure 2.4 Basic fixed repair and maintenance costs for the TBM and backup
equipment. Correction factor for net penetration rate Im ≠ 3.0 m/h.
22
2. DETAILED COSTS 2.1 TBM and Backup Equipment
cs
NOK/h
TBM
250
200
150
100
Backup
50
4 5 6 7 8 9
TBM diameter, m
Figure 2.5 Service costs for the TBM and backup equipment.
kie
1.2
1.1
1.0
P0e
2 3 4 5
kWh/h
Net penetration rate, m/h
3000
2000
1000
4 5 6 7 8 9
TBM diameter, m
Figure 2.6 Energy consumption for the TBM (90 %) and backup equipment (10 %).
Correction factor for net penetration rate Im ≠ 3.0 m/h.
23
2. DETAILED COSTS 2.2 Example of Application - Machine Costs
Investment tax pt 7%
C d I A (100 − R R )
Depreciation until tR cd = = 4069 NOK/h Figure 2.1
tR t R ⋅ 100
R( x ) d ( x )
Rm = 0
⋅ 100 57 % PR 15A-92
tR
24
2. DETAILED COSTS 2.2 Example of Application - Machine Costs
Rm I A ⋅ p r
Interest until tR cr = ⋅ 1776 NOK/h PR 15A-92
100 ty
0.5 ⋅ I A
Variable repair costs until tR c B = ⋅ tR 1159 NOK/h PR 15A-92
(1 + k D ) ⋅ t B2
Figure 1.2 shows a TBM cost of 2400 NOK/m. The difference between the detailed
and normalised TBM cost is due to smoothing of the curves in Figure 1.2.
PR 1B-98 refers to the Project Report 1B-98 HARD ROCK TUNNEL BORING
Advance Rate and Cutter Wear, published by us.
Investment tax pt 7%
lt
Time of finished boring t 2 = t1 + 5232 h
Im
Rest value at t1
0.5 ⋅ (t B − t1 ) 2 0.5 ⋅ (t B − t1 )
R1 = ( + ) ⋅ 100 75 % PR 15A-92
t B2 tB
Rest value at t2
0.5 ⋅ (t B − t 2 ) 2 0.5 ⋅ (t B − t 2 )
R2 = ( + ) ⋅ 100 56 % PR 15A-92
t B2 tB
Depreciation from t1 to t2
Cd I ⋅ ( R2 − R1 )
cd = = A 4347 NOK/h Figure 2.1
t 2 − t1 100 ⋅ (t 2 − t1 )
R( x ) d ( x )
Rm = ⋅ 100
t1
65 % PR 15A-92
t 2 − t1
Rm I A ⋅ p r ⋅ t P
Interest from t1 to t2 cr = ⋅ 2082 NOK/h PR 15A-92
100 t 2 − t1
27
2. DETAILED COSTS 2.3 Muck Transport
Muck transport costs are estimated for track-bound transport, truck transport and use
of continuous conveyor. Transport by subcontractor is assumed for truck transport.
Required transport capacity is defined by fully utilising the penetration rate capacity
of the TBM and backup system.
Track Transport
•= Transport of muck
•= Rails
•= Switches
•= Dump costs.
Transport
Estimation of transport capacity is treated in the Project Report 1A-98 HARD
ROCK TUNNEL BORING Design and Construction. The transport costs are
based on the following assumptions:
•= Train speed 35 km/h, reduced to 10 km/h at and near the backup equipment,
California Switches, the adit, the dump station, etc.
•= Muck car size 6 lm3 for dtbm = 3.5 m increasing to 12 lm3 for dtbm = 9.5 m
•= Train size 10 muck cars, one locomotive
•= Double track backup equipment
•= Bottom-dump dump station
Figure 2.6 shows transport costs for track transport as a function of tunnel diameter,
tunnel length and net penetration rate. The costs are based on use of diesel locomo-
tives. The transport distance includes a 300 m adit and 300 m from the adit to the
muck disposal site.
28
2. DETAILED COSTS 2.3 Muck Transport
Tracks
The costs include rails, sleepers, switches, production of track sections as well as in-
stallation, maintenance and dismantling of the track. The rail size is presupposed to be
35 kg/m. Rails, sleepers and switches are depreciated partly on an annual and partly
on a reuse basis. Rail costs as a function of tunnel length and net penetration rate are
shown in Figure 2.7.
Bypass Stations
Figure 2.8 shows costs for necessary California Switch(es) as a function of tunnel
length, TBM diameter and net penetration rate. The necessary number of switches is
calculated on the following basis:
29
2. DETAILED COSTS 2.3 Muck Transport
crt dtbm=7.5m
NOK/m
800
600 5.5m
400
3.5m
200
4 6 8 10 12 14
Tunnel length, km
crr
NOK/m
Im=2 m/h
225
200
3m
6 m/h
175
4 6 8 10 12 14
Tunnel length, km
30
2. DETAILED COSTS 2.3 Muck Transport
dtbm=7.5m
crs Im=6m/h
dtbm=5.5m
NOK/m
80
6m/h
60
40 2m/h
20
4 6 8 10 12 14
Tunnel length, km
1400
1200
dtbm=7.5m
1000
800
600 5.5m
400
3.5m
200
4 6 8 10 12 14
Tunnel length, km
Figure 2.10 Dump station and muck removal costs for track transport.
31
2. DETAILED COSTS 2.3 Muck Transport
Truck Transport
Transport
The transport costs are based on transport by subcontractor. Figure 2.11 shows trans-
port costs including dumping and muck disposal, as a function of tunnel length and
TBM diameter.
32
2. DETAILED COSTS 2.3 Muck Transport
ctt
NOK/m dtbm=12m
5000
4000 10m
3000
8m
2000
4 6 8 10 12 14
Tunnel length, km
Figure 2.11 Averaged transport costs for truck transport, including dumping and
muck disposal.
33
2. DETAILED COSTS 2.3 Muck Transport
ctr Roadway
NOK/m
200
150
100
Turning table
50
4 6 8 10 12 14
Tunnel length, km
Figure 2.12 Costs for roadway and turning table. Truck transport.
Transport
The transport costs are based on conveyor belt width and speed as shown in the
Project Report 1A-98 HARD ROCK TUNNEL BORING Design and Construc-
tion. Figure 2.13 shows transport costs including dumping and muck disposal, as a
function of TBM diameter.
34
2. DETAILED COSTS 2.3 Muck Transport
klct kict
Lt=14km
1.3 1.2
6km
1.2 1.1
2km
1.1 1.0
1.0
2 3 4 5
c0ct Net penetration rate, m/h
NOK/m 6 10
Tunnel length, km
900
800
700
4 5 6 7 8 9
TBM diameter, m
ccr
NOK/m
300
Track-bound transport
200
Truck transport
4 6 8 10 12 14
Tunnel length, km
35
2. DETAILED COSTS 2.4 Other Costs
Ventilation
The costs include ducts, duct couplings, materials for duct mounting and mainte-
nance, depreciation and repair of fans and ducts, electric power and dismantling of the
ventilation system.
Costs for dust filtration of air from the cutterhead are included in the backup equip-
ment costs.
Electrical Installations
The costs for electrical installations in the tunnel and at the dump station are shown in
Figure 2.16.
The costs include transformer(s), high voltage cables, materials for mounting and
maintenance of cables, and dismantling of cables and other electrical installations.
Costs for transformers at the backup equipment, flexicable, etc. are included in the
backup equipment costs.
Water Supply
The costs include pumps, water pipes, materials for installation, and dismantling of
the water supply system.
36
2. DETAILED COSTS 2.4 Other Costs
400
8m
300
200
100
4 6 8 10 12 14
Tunnel length, km
Figure 2.15 Ventilation costs. The costs are estimated for optimal supply of fresh air,
medium drillability and net penetration rate Im = 3 m/h.
37
2. DETAILED COSTS 2.4 Other Costs
kdes
c0es
1.2
NOK/m
120 1.1
100
5.5 7.5
TBM diameter, m
80
60
40
20
4 6 8 10 12 14
Tunnel length, km
Figure 2.16 Costs for electrical installations in the tunnel and at the dump station.
cw
NOK/m
Im=1m/h
50
40
3m/h
30
6m/h
20
4 6 8 10 12 14
Tunnel length, km
38
3. TOTAL CONSTRUCTION COSTS 3.0 General
3.0 GENERAL
In order to compare tunnel boring to drill and blast as excavation method for a spe-
cific tunnel, one has to estimate the construction time and the total construction costs.
The following example treats a 3.5 m diameter tunnel with a total length of 7300 m.
The net penetration rate, the machine utilisation, the weekly advance rate and the cut-
ter life have been estimated based on the Project Report 1B-98 HARD ROCK
TUNNEL BORING Advance Rate and Cutter Wear.
The excavation costs are estimated according to Chapter 1 Normalised Costs, and are
estimated at 3800 NOK/m, including 10 % unforeseen as recommended in Section
1.0.
As can be seen from the example on the following pages, the excavation costs makes
up only NOK 27.7 million of a total of NOK 62.0 million, or 45 % of the total costs.
The percentage will of course vary from project to project, but the example demon-
strates the importance of estimating the total construction time and costs as a basis to
decide the method of excavation from.
39
3. TOTAL CONSTRUCTION COSTS 3.1 Construction Time
40
3. TOTAL CONSTRUCTION COSTS 3.2 Construction Costs
Site Preparation
Site Operation
41
3. TOTAL CONSTRUCTION COSTS 3.2 Construction Costs
42
APPENDIX A. Previous Editions
A. PREVIOUS EDITIONS
Previous editions of the Hard Rock Tunnel Boring Report including project group
members:
43
APPENDIX B. Research Partners
B. RESEARCH PARTNERS
•= Statkraft anlegg as
•= Norwegian Public Roads Administration
•= Statsbygg
•= Scandinavian Rock Group AS
•= NCC Eeg-Henriksen Anlegg AS
•= Veidekke ASA
•= Andersen Mek. Verksted AS
•= DYNO Nobel
•= Atlas Copco Rock Drills AB
•= Tamrock OY
•= The Research Council of Norway
44
APPENDIX C. List of Parameters
C. List of Parameters
The parameters used in the report are listed in the following. The list is according to
when the parameter first is explained or treated.
45
APPENDIX C. List of Parameters
46
APPENDIX C. List of Parameters
lt Length of tunnel m 26
Lt Length of tunnel km 13
Ntbm Number of cutters on the cutterhead 11
pe Price of electric energy NOK/kWh 22
Pe Energy consumption of the TBM
and backup equipment kWh/h 23
P0e Basic energy consumption of the TBM
and backup equipment kWh/h 23
47
APPENDIX D. Estimation Forms
Tunnel length lt m
Basic costs for work behind the face c0bs NOK/m Figure 1.5/1.6
Costs for work behind the face cbs = c0bs ⋅ klbs ⋅ kibs NOK/m [1.3]
Investment tax pt %
C d I A (100 − R R )
Depreciation until tR cd = = NOK/h Figure 2.1
tR t R ⋅ 100
R( x ) d ( x )
Rm = 0
⋅ 100 % PR 15A-92
tR
Rm I A ⋅ p r
Interest until tR cr = ⋅ NOK/h PR 15A-92
100 ty
0.5 ⋅ I A
Variable repair costs until tR cB = ⋅ tR NOK/h PR 15A-92
(1 + k D ) ⋅ t B2
PR 1B-98 refers to the Project Report 1B-98 HARD ROCK TUNNEL BORING
Advance Rate and Cutter Wear, published by us.
Tunnel length lt m
Investment tax pt %
lt
Time of finished boring t 2 = t1 + h
Im
Rest value at t1
0.5 ⋅ (t B − t1 ) 2 0.5 ⋅ (t B − t1 )
R1 = ( + ) ⋅ 100 % PR 15A-92
t B2 tB
Rest value at t2
0.5 ⋅ (t B − t 2 ) 2 0.5 ⋅ (t B − t 2 )
R2 = ( + ) ⋅ 100 % PR 15A-92
t B2 tB
Depreciation from t1 to t2
Cd I ⋅ ( R2 − R1 )
cd = = A NOK/h Figure 2.1
t 2 − t1 100 ⋅ (t 2 − t1 )
R( x ) d ( x )
Rm = ⋅ 100
t1
% PR 15A-92
t 2 − t1
Rm I A ⋅ p r ⋅ t P
Interest from t1 to t2 cr = ⋅ NOK/h PR 15A-92
100 (t 2 − t1 )