CUSTOMER ADDRESS: EDGEN MURRAY CORPORATION Customer Order Number ASP Order Number
P.O. BOX 84160 LKD-251856 S113237
All tests are from the body of the pipe in the transverse direction unless otherwise noted.
Standard flat tensile gage length 1-1/2" x 2". Pipe body test location: Tensile T180; CVN T90.
_________________________________________________________________________________________________________
HEAT C MN P S CB SI TI CU NI MO CR V AL B N CA C.E. Pipe
Coil
Attachments PAGE 1
Continued
Attachments PAGE 2
Continued
____________________
STEEL SUPPLIER / MFG ________________
SUPPLIER ADDRESS
Nucor (Decatur) 4301 Iverson Blvd. / Trinity, AL 35673
Legend Analyses:
A-Z - Additional Testing R - Retest Hydrostatic Test: OK
H - Heat Analysis L - Longitudinal Flattening Test: OK
P - Product Analysis T - Transitional
M - Mechanical Properties W - Weld Line
Coils used for this order were melted and manufactured in the USA.
We hereby certify that the above figures are correct as contained in the records of this company, and that
the pipe were manufactured, tested, and inspected in compliance with the Latest edition of the applicable
specification at American Steel Pipe (ASP) located at 1501 31st Avenue North, Birmingham, AL 35207 (USA).
James B. Baird
Manager of Quality Assurance - Steel Pipe
PAGE 3
End of Report
Issue No.: 7 Form Date: 6/01/2013 QD-AW3F055