THUMB RULES FOR CIVIL WORKS LABOUR

PRODUCTIVITY

S.SUDHA VELAN B.E (CIVIL)


THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Bar bending Works (Reinforcement)

Slab & Beams -1 Fitter +1.5 Helper – 170 Kg/day

Footing - 1 Fitter +1.5 Helper – 200 Kg/day


THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Form Work (Shuttering) – Fixing & Removal

Slab & Beams -1 Carpenter +1.5 Helper – 5 Sqm /day

Footing - 1 Carpenter +1.5 Helper – 7 Sqm /day

Column Box Fixing -1 Carpenter + 2 Helpers- 20 Sqm/day

Column Starter Fixing – 1 carpenter + 2 Helpers – 6 Nos /day


THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Form Work Making

Beam sides -1 Carpenter +1 Helper – 6 Sqm /day

Column Boxes - 1 Carpenter +1 Helper – 3 Sqm /day

Starter -1 Carpenter + 1Helpers - 5 Nos /day


THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Concreting

Slab & Beams -1 Mason +1 Helper – 20 Cum /day


THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Block Works

Block Works -1 Mason +1.5 Helper – ( 6 – 8 ) Sqm/day


THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Plastering Works

Internal Plastering -1 Mason +1.5 Helper – 10 Sqm/day


External Plastering -1 Mason +1.5 Helper – 12 Sqm/day (Per Coat )
Ceiling Plastering -1 Mason +1.5 Helper – ( 10 – 12 ) Sqm/day
Corner beading Fixing -1 Mason +1 Helper – 7 Nos /day
Mesh Fixing & Packing -2 Mason +1 Helper – 60 Running Feet /day
THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Earth Work Excavation

Manual Excavation -2 Labours – 100 Cft /day


Machine Operated (Poclain)- 60 Cum/Hr
THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

MS Works

Window Grill Fixing - 1 Mason +1.5 Helper - 3 Nos /day (Size -1800 X 1400)
Balcony Handrail Fixing - 1 Mason +1.5 Helper - 5 Nos /day (2400 X 900 mm)
THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Water Proofing Works

Horizontal Membrane Application -1 Applicator + 1 Helper – 150 Sqm/day


Vertical Membrane Application -1 Applicator + 2 Helper – 50 Sqm/day
Brush On Application -1 Applicator + 1 Helper – 20 Sqm/day (1 Coat)
Bore Packing -1 Applicator +1 Helper – 3 Nos /day
THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Plumbing Works

Toilet Chasing -1 Chipper – 7 Rmt /day


Waterline Fixing - 1 Plumber + 1.5 Helper – 3 Toilets /day
Sanitary Line Fixing -1 Plumber + 2 Helper – 3 Toilets/day
Sanitary & CP Fittings -1.5 Plumber + 3 Helper – 3 Toilets & 1 kitchen /day
THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY

Electrical Works

Box Fixing (Marking + Chasing + Fixing + Leveling ) -1 Skilled Eletrician+2


Semi Skilled Electrician -1 Flat / 3 days

Note – 3 bedroom flat with around 50 Boxes


THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY
Tiling Works

Toilet Dado - 80 Sft/mason /day


Door Jambs - 30 Rft/mason /day
Toilet Skirting - 45 Rft/mason /day
Toilet Flooring - 90 Sft/mason /day
Balcony Skirting - 50 Rft/mason /day
Vitrified Flooring (Straight Joints)-100 Sft /mason/day
Vitrified Flooring (Diagonal Joints)- 90 Sft /mason/day
Vitrified Skirting - 70 Rft/mason /day
Joint Filling -100 Sft/mason/day
Roof Tiling -150 Sft/mason/day
THUMB RULES FOR CIVIL WORKS LABOUR PRODUCTIVITY
Granite & Marble Works

Hand Cutting - 150 Rft/mason /day


Machine Cutting - 450 Rft/mason /day
Groove Cutting - 200 Rft/mason /day

Indian & Italian Marble ,Granite Flooring - 60 Sft /mason /day


Staircase - 50 Sft/mason /day
Lift Cladding -50 Sft /mason/day
Joint Filling -100 Sft/mason/day
Floor Polishing -100 Sft/mason/day
Half & Full Nosing Making -60 Rft/mason/day
Nosing (Champhering) Making -200 Rft/mason/day
Half & Full Nosing Polishing – 35 Rft/mason/day